PDS No. 008 HEADLINING ASSY D26D
PDS No. 008 HEADLINING ASSY D26D
PDS No. 008 HEADLINING ASSY D26D
27-3 6-10 13-17 20-24 27-31 3-7 10-14 17-21 24-28 1-5 8-12 15-19 22-26 29-2 5-9 12-16 19-23 26-30 3-7 10-14 17-21 24-28 31-4 7-11 14-18 21-25 28-1 4-8 11-15 18-22 25-29 2-6 9-13 16-20 23-27 30-3 6-10 13-17 20-24 27-1 4-8 11-15 18-22 25-29 1-5 8-12 15-19 22-26 29-2 5-9 12-16 19-23 26-1 4-8 11-15 18-22 25-29 1-5 8-12 15-19 22-26 29-3 6-10 13-7 20-24 27-31 3-7 10-14 17-21 24-28
First Delivery KS
A TRAY EVENT PRE-PP EVENT PP EVENT
PROJECT MILESTONE SVP →
DESIGN T0.2
ORDER MATERIAL
LINE FILL
T0.1 13/06 T1.1 T1.2 T1.3 T2.1 T2.2 SVP →
DWA EVENT DESIGN FREEZE T2.3 T3.1 T3.2 T3.3 LVPT HVPT
Project Name : D26D Ornament Wheel Hub Duration Plan : 1006 Days Actual : 31 days
T Start
Enter Project
the name 27-Feb-23
of the Project Lead in cell B3. Enter: the Project Start date in cell E3. Pooject Start: label is in cell C3.
h Week
C : 1 2/27 3/6 3/13 3/20 3/27 4/3 4/10 4/17 4/24 5/1 5/8 5/15 5/22 5/29 6/5 6/12 6/19 6/26 7/3 7/10 7/17 7/24 7/31 8/7 8/14 8/21 8/28 9/4 9/11 9/18 9/25 10/2 10/9 #### #### 10/30 11/6 #### #### #### 12/4 #### #### 12/25 1/1 1/8 1/15 1/22 1/29 2/5 2/12 2/19 2/26 3/4 3/11 3/18 3/25 4/1 4/8 4/15 4/22 4/29 5/6 5/13 5/20 5/27 6/3 6/10 6/17 6/24
el # # # 30
T
hi M
T W T F S S M T W T F S S M T W T F S S M
T W
T F S S M T W T
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
27-3 6-10 13-17 20-24 27-31 3-7 10-14 17-21 24-28 1-5 8-12 15-19 22-26 29-2 5-9 12-16 19-23 26-30 3-7 10-14 17-21 24-28 31-4 7-11 14-18 21-25 28-1 4-8 11-15 18-22 25-29 2-6 9-13 16-20 23-27 30-3 6-10 13-17 20-24 27-1 4-8 11-15 18-22 25-29 1-5 8-12 15-19 22-26 29-2 5-9 12-16 19-23 26-1 4-8 11-15 18-22 25-29 1-5 8-12 15-19 22-26 29-3 6-10 13-7 20-24 27-31 3-7 10-14 17-21 24-28
First Delivery KS
A TRAY EVENT PRE-PP EVENT PP EVENT
PROJECT MILESTONE SVP →
DESIGN T0.2
ORDER MATERIAL
LINE FILL
T0.1 13/06 T1.1 T1.2 T1.3 T2.1 T2.2 SVP →
DWA EVENT DESIGN FREEZE T2.3 T3.1 T3.2 T3.3 LVPT HVPT
Project Name : D26D Ornament Wheel Hub Duration Plan : 1006 Days Actual : 31 days
T Start
Enter Project
the name 27-Feb-23
of the Project Lead in cell B3. Enter: the Project Start date in cell E3. Pooject Start: label is in cell C3.
h Week
C : 1 2/27 3/6 3/13 3/20 3/27 4/3 4/10 4/17 4/24 5/1 5/8 5/15 5/22 5/29 6/5 6/12 6/19 6/26 7/3 7/10 7/17 7/24 7/31 8/7 8/14 8/21 8/28 9/4 9/11 9/18 9/25 10/2 10/9 #### #### 10/30 11/6 #### #### #### 12/4 #### #### 12/25 1/1 1/8 1/15 1/22 1/29 2/5 2/12 2/19 2/26 3/4 3/11 3/18 3/25 4/1 4/8 4/15 4/22 4/29 5/6 5/13 5/20 5/27 6/3 6/10 6/17 6/24
el # # # 30
T
hi M
T W T F S S M T W T F S S M T W T F S S M
T W
T F S S M T W T
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
Remarks:
REVISION DUE DATE DESCRIPTION CHECKED BY PPL CHECKED BY PDD CHECKED BY PDE CHECKED BY MCE CHECKED BY NPR APPROVED BY DH
: Plan
: New Plan
: Actual
: Finish
: Start Fabrication of Packaging
Page 2 of 2