GB Vapour Recovery
GB Vapour Recovery
GB Vapour Recovery
System Description
In some markets it is necessary to fit an automatic monitoring system to verify the functional capability of
vapour recovery systems installed in fuel dispensers. This requires a monitoring system that indicates a fault
if the vapour recovery volume varies by more than +/-15% from the correct value for ten filling operations in
succession. (To qualify as a filling to be counted it must last for longer than 20 seconds and have a flow
greater than 25 l/min.) In such a case the fuel flow will be cut off after 168 hours, so preventing further
operation of the dispenser.
For reliable functioning of the monitoring system the maximum fuel flow must not exceed 40 l/min.
We recommend a Qmax of 38l/min be set.
Existing fuel forecourts must be retrofitted with a monitoring system in the next few years.
Function: The vapour recovery monitoring system consists essentially of the flow meter GE1 and
Vapour Monitoring Controller (VMC). A flow meter is needed for each side of the dispenser.
During filling vapour and fuel flow data are collected. This is achieved by means of the flow meter
directly in the vapour recovery line and pulses which are taken from the dispenser computer.
Whenever a filling has been completed, a calculation is carried out, based on the data obtained and
the system status is signalled with two LEDs.
Operational States: The state of the vapour recovery and the monitoring equipment is indicated on
the one hand by the three colours (green, yellow, red) and on the other by various flashing of the
LEDs (A and B).
A
Green – rapid flash: Recording in progress
Only flow meter GE1 may be used for vapour measurement in dispensers. Assembly/dismantling
and commissioning may be carried out only by specialist personnel with appropriate training.
Before installation it must be ensured that the flame arresters are secure and properly screwed in.
Attention: If any problems arise the complete flow meter including the flame arrester must be
exchanged. The type ‘m’ cast metal encased pulser may be exchanged individually, type ‘d’ must
have the complete unit exchanged.
Interfaces
RS 422 (X7) V12 (R+ R- / T+ T-) Umax < 12V
Flat connector 10 pole
RS232 (X8) V24 Umax < 30V
SUB – D socket 9 pole
Service
Flow RS 422
Meter B To EC2000
Flow
Meter A
PC-Connection
Commissioning
Commissioning of dispensers on a forecourt may be carried out only by technicians who have
been trained on the Vapour Recovery System.
Tasks to be Implemented:
● Monitor the vapour recovery efficiency at all volatile fuel dispensing points.
(Adjustment of the simulated operation with the hand terminal at 40 l/min). If the
discrepancy is greater than 5% the suction flow must be readjusted. The values are to
be entered in the FEF Stage II Vapour Recovery Test Certificate (BUL 7407 Iss1).
● The fuel flow is now to be checked at fuel dispensing points. To ensure reliable
operation of the monitoring system the maximum fuel delivery of 40 litres per minute
may not be exceeded. We recommend it be set to a Qmax of 38 l/min.
● Is error recognition of the Vapour Monitoring System working? Simulate shut-off and
check whether all volatile fuel delivery points are inhibited.
Maintenance: The Vapour Monitor Controller (VMC) is maintenance free. If it is in storage for
longer than ten years, the equipment must be returned to the manufacturer for battery replacement.
The battery is not charged during normal operation. This time does not count as storage time.
Attention: Do not change the battery yourself.
Safety advice: The VMC has IP20 protection which therefore provides for installation in the final
equipment. If the VMC is operated in the EC2000-System, the power supply is via the RS422-
interface. The ribbon cable may by plugged in only when the power is off, as there is otherwise the
danger of damage to the equipment. In this case a 230V supply is unnecessary. In all other cases
power is supplied via the mains connection.
Installation of a vapour recovery monitoring system does not relieve the operator of
the responsibility to have the vapour recovery system checked every three years by
a specialist contractor!
Please select Dongle (1) and choose the side. This picture was not shown..
The VMC can be put into the alarm, stop or RSET condition through the functions displayed above.
If RESET is selected, the error counter on the appropriate side is simultaneously set back to zero.
That means that, irrespective of whether a simulated or real condition is the case, the reset is always
effective.
If ‘Sent OK’ appears in the last line of the terminal display, the action was successful.
For further assurance, the LED-indicator at the VMC should be monitored. If this shows the
desired flashing colour then the error simulation was successful. Up to the reset, all other status
changes are temporary. That means, after two minutes have elapsed, the original condition will be
reproduced. If, during the simulation the text 'FB1 serial number is invalid. FB1 update
necessary’ appears in the FB1 display, there is no valid serial number programmed and the VMC is
not responding even though 'Sent OK’ appears. In this case the terminal is to be returned to
Salzkotten for serial number allocation. The fitter’s details (name or company) are required
compulsorily before the terminal can be unlocked.
Please use the following scale to evaluate our performance / Bitte nutzen Sie die folgende Einstufung für Ihre Bewertung
1= Excellent / Sehr gut, 2 = Good / Gut, 3 = Acceptable / befriedigend, 4 = Not as good expected /
Nicht so wie erwartet, 5 = Unacceptable / Nicht annehmbar, N/A = not applicable / Nicht zutreffend
On time delivery Termintreue 1 2 3 4 5 N/A
Product manufactured exactly as ordered Übereinstimmung des Produktes mit 1 2 3 4 5 N/A
der Bestellung
Condition of panels, cladding, paintwork , Zustand der Bleche, Verkleidungen, 1 2 3 4 5 N/A
hoses, nozzles, locks, display windows Lackierung, Schläuche, Zapfventile,
(Please indicate any problems on the Schlösser und Anzeigen
diagram on the reverse page) (Bitte kennzeichnen Sie aufgetretene
Probleme in den Bildern auf der
Rückseite)
Installation/commissioning result Anlieferung und Installation 1 2 3 4 5 N/A
Equipment functionality & performance Funktion und Leistung der Produkte 1 2 3 4 5 N/A
Any other comments / zusätzliche Bemerkungen:
Betrag DM
Abgabe Liter
Pf
T ank an al g en
Verkauf aus diesem Gerät i mNamen und f ür Rechnungder Aral Aktiengese lschaf t * Kleinst eAbgabemenge 10 Lite r
Super Benzin
DM 0 0 0 0 0 Betrag 0 00 00 DM
0 00 0 T A N KA N LAG E N
Abgabe 0 00 0 0 Liter
Pf
Preis /l 00 0 0 Pf
TA N KA N LAG E N