Tech. Sepc. Descope
Tech. Sepc. Descope
Tech. Sepc. Descope
sockets and tubing end. The tubing should make contact with the socket wall
1/3 or 2/3 of the way into the fitting socket.
d. Solvent Cement Application:
Only CPVC-FRLSZH-FRLSZH-FRLSZH solvent cement confirming to ASTM-
F493 should be used for joining pipe with fittings. An even coat of solvent
cement should be applied on the pipe end and a thin coat inside the fitting
socket, otherwise too much of cement solvent can cause clogged water ways.
e. Assembly:
After applying the solvent cement on both pipe and fitting socket, pipe should
be inserted into the fitting socket within 30 seconds, and rotating the pipe ¼ to
½ turn while inserting so as to ensure even distribution of solvent cement with
the joint. The assembled system should be held for 10 seconds (
approximately) in order to allow the joint to set up.
An even bead of cement should be evident around the joint and if this bead is
not continues remake the joint to avoid potential leaks.
Set & Cure times:
Solvent cement set and cure times shall be strictly adhered to as per the below
mentioned table.
Minimum Core prior to pressure testing at 150 PSI
in order to avoid its freezing. The freezed cement solvent should be discarded
immediately and fresh one should be used. The CPVC-FRLSZH-FRLSZH-
FRLSZH solvent cement usage should be adhered to as given in table below
Approx. nos. of joints 200 No. 180 No. 150 No. 130 No. 100 No. 70 No
which can be mode per
litre of solvent cement.
SCHEDULE 40
(In) (mm) 23 38 49 60 71 82
2½ 65 7½ 7 7 6½ 6 3½
3 80 8 7 7 7 6 3½
4 100 8½ 7½ 7½ 7 6½ 4
6 150 9½ 8 8 7½ 7 4½
8 200 9½ 8 8 7½ 7 5
them. These shall be lined up on one side of the alignment of the trench, socket
facing upgrade when line runs uphill and upstream when line runs on level ground.
Each stack shall contain pipes of same class and size, consignment or batch
number and particulars of suppliers, wherever possible, shall be marked on the
stack.
Storage shall be done on firm, level and clean ground. Wedges shall be provided
at the bottom layer to keep the stack stable.
Trenches
The galvanised iron pipes and fittings shall be laid in trenches. The widths and
depths of the trenches for different diameters of the pipes shall be as in Table.
15 to 50 30.0 60.0
At joints the trench width shall be widened where necessary. The work of excavation
and refilling shall be done true to line and gradient in accordance with general
specifications for earth work in trenches
When excavation is done in rock, it shall be cut deep enough to permit the pipes to
be laid on a cushion of sand minimum 7.5 cm deep.
Cutting and Threading
Where the pipes have to be out or rethreaded, the ends shall be carefully filed out
so that no obstruction to bore is offered. The end of the pipes shall then be carefully
threaded conforming to the requirements of IS 554 with pipe dies and tapes in such
a manner as will not result in slackness of joints when the two pieces are screwed
together. The taps and dies shall be used only for straightening screw threads which
have become bent or damaged and shall not be used for turning of the threads so
as to make them slack, as the later procedure may not result in a water tight joint.
The screw threads of pipes and fitting shall be protected from damage until they are
fitted.
Jointing
The pipes shall be cleaned and cleared of all foreign matter before being laid. In
jointing the pipes, the inside of the socket and the screwed end of the pipes shall
be oiled and rubbed over. Teflon Tape should be used on threads instead of
pipe wrench. Care shall be taken that all pipes and fittings are properly jointed so
as to make the joints completely water tight and pipes are kept at all times free from
dust and dirt during fixing. Burr from the joint shall be removed after screwing. After
laying, the open ends of the pipes shall be temporarily plugged to prevent access
Unloading
The pipes shall be unloaded where they are required.
Unloading (except where mechanical handling facilities are available)
Pipes weighing up to 60 kg shall be handled by two persons by hand passing.
Heavier pipes shall be unloaded from the lorry or wagon by holding them in loops,
formed with ropes and sliding over planks set not steeper than 45 degree. The
planks shall be sufficiently rigid and two ropes shall always be used to roll the pipes
down the planks. The ropes should be tied on the side opposite the unloading. Only
one pipe shall be unloaded at a time.
Under no circumstances shall the pipes be thrown down from the carriers or be
dragged or rolled along hard surfaces.
The pipes shall be checked for any visible damage (such as broken edges, cracking
or spalling of pipe) while unloading and shall be sorted out for reclamation. Any pipe
which shows sufficient damage to preclude it from being used shall be discarded.
Storing
The pipes and specials shall be handled with sufficient care to avoid damage to
them. These shall be lined up on one side of the alignment of the trench, socket
facing upgrade when line runs uphill and upstream when line runs on level ground.
Each stack shall contain pipes of same class and size, consignment or batch
number and particulars of suppliers, wherever possible, shall be marked on the
stack.
Storage shall be done on firm, level and clean ground. Wedges shall be provided
at the bottom layer to keep the stack stable.
Trenches
The gradient is to be set out by means of boning rods and the required depth to be
excavated at any point of the trench shall be regarded as directed by the Engineer
-in-Charge. The depth of the trench shall not be less than 1 meter measured from
the top of the pipe to the surface of the ground under roads and not less than 0.75
meter elsewhere.
The width of the trench shall be the nominal diameter of the pipe plus 40 cm but it
shall not be less than 55 cm in case of all kinds of soils excluding rock and not less
than 1 meter in case of rock.
Laying
Any deviation either in plan or elevation less than 11.25 degrees shall be affected
by laying the straight pipes around a flat curve of such radius that minimum
thickness of lead at the face of the socket shall not be reduced below 6 mm or the
opening between spigot and socket increased beyond 12 mm at any joint. A
deviation of about 2.25 degree can be affected at each joint in this way. At the end
a wooden plug to prevent entry of water, soil, rats and any other foreign matter into
the pipe.
Flanged Joints
Ductile iron pipes may be jointed by means of flanges cast on. The jointing material
used between flanges of pipes shall be compressed fiber board or rubber of
thickness between 1.5 mm to 3 mm. The fiber board shall be impregnated with
chemically neutral mineral oil and shall have a smooth and hard surface. Its weight
per m2 shall be not less than 112 gm/mm thickness.
Each bolt should be tightened a little at a time taking care to tighten diametrically
opposite bolts alternatively. The practice of fully tightening the bolts one after
another shall not be allowed.
Several proprietary flexible joints are available for jointing Ductile iron pipes and
these may be used with the specific approval of the authority, however, they shall
For joints in small diameter cast iron piping, copper-alloy screwed unions or ferrules
shall be used, and for large dia. The joints shall be made by flanged connecting
pieces.
1.4.4 G.I. Pipes, Fittings & Valves (In Plant rooms and for Equipments)
All pipes inside the buildings and where specified, outside the building shall be
galvanized steel tubes conforming to I.S. 1239 of medium/ heavy class as specified
in the BOQ.
Fittings shall be malleable iron with a reinforcing ring over the threaded ends upto
50mm dia and without reinforcing rings for sizes 65mm dia and above. Each fitting
include Couplings, Bends, Tees, Reducers, Nipples, Unions, and Bushes. Fittings
shall conform to I.S:1879 (Part I to X).
Pipes and fittings shall be jointed with screwed joints. Care shall be taken to remove
burr from the end of the pipe after reaming with a proper time.
Pipe threaded joints will be made by applying suitable grade of TEFLON tape used
for drinking water supply.
All pipes shall be fixed in accordance with layout and alignment shown on the
drawings. Care shall be taken to avoid air pockets. G.I. pipes inside toilets shall
be fixed in wall chases well above the floor. No pipes shall be run inside a sunken
floor as far as possible. Pipes may be run under the ceiling or floors and other as
shown on drawings.
Pipe Supports
All pipes clamps, supports, hangers, rods, pipe supports, nuts and washers shall
be factory made galvanized MS steel or alternatively galvanized after fabrication to
suit site requirements.
G.I pipes in shafts and other locations shall be supported by galvanized M.S clamps
of design approved by pipes in wall chases shall be anchored by G.I hooks, pipes
at ceiling level shall be supported on structural clamps fabricated from M.S
structural steel. Pipes in typical shafts shall be supported on Galvanised slotted
Where specified, non-return valve shall be provided through which flow shall occur
in one direction only.
Each Butterfly and Slim Type Swing Check (NRV) Valve shall be provided with a
pair of flanges screwed or welded to the main line and having the required number
of nuts, bolts and washers of correct length.
Y-Strainer
Where specified, Y-Strainer shall be provided through which gravels shall not pass
through it towards pump impeller.
Each Butterfly, Y strainer and Slim Type Swing Check (NRV) Valve shall be
provided with a pair of flanges screwed or welded to the main line and having the
required number of nuts, bolts and washers of correct length.
1.6 Testing
All pipes, fittings and valves, after fixing at site, shall be tested by hydrostatic
pressure of 1.5 times the working pressure or 7 kg / sq.cm whichever is more.
Pressure shall be maintained for a period of at least thirty minutes without any drop.
A test register shall be maintained and all entries shall be signed and dated by
Contractor (s) and Project Manager.
In addition to the sectional testing carried out during the construction, Contractor
shall test the entire installation after connections to the overhead tanks or pumping
system or mains. He shall rectify all leakages and shall replace all defective
materials in the system. Any damage done due to carelessness, open or burst pipes
or failure of fittings, to the building, furniture and fixtures shall be made good by the
After commissioning of the water supply system, Contractor shall test each valve
by closing and opening it a number of times to observe if it is working efficiently.
Valves, which do not effectively operate, shall be replaced by new ones at no extra
cost and the same shall be tested as above.
Hot water pipes chased into the walls shall be provided with a 6mm thick insulation
with elastic flexible material having hermetic closed cell structure of expanded
synthetic material rated for 60ºC hot water supply.
1.7 Measurement
Pipes above ground shall be measured per linear meter (to the nearest cm) and
shall be inclusive of all fittings e.g. coupling, tees, bends, elbows, unions, flanges
and U clamps with nuts, bolts & washers fixed to wall or other standard supports.
Jointing with teflon tape, white lead, solvent, crimping and insertion gasket of
appropriate temperature grade.
Cutting holes, and chases in walls, floors, any pipe support required for pipes below
ground & making good the same.
Excavation, backfilling, disposal of surplus earth and restoring the ground & floor in
original condition.
Pipe Supports
END OF SECTION V
10 stone aggregate 40 mm nominal size) and a brick masonry chamber 30x30 cms
inside plastered with cement mortar I:5 with 15x 15 cms grating inside and 30x30
cms C.I. sealed cover and frame weighing not less than 7.3 kg to be constructed as
per standard drawing. Where necessary, sealed cover shall be replaced with C.I.
grating of the same size.
3.15 Reinforced cement concrete pipes
All underground storm water drainage pipes and sewer lines where specified (other
than those specified cast iron) shall be centrifugally spun S & S RCC pipes of
specified class. Pipes shall be true and straight with uniform bore, throughout.
Cracked, warped pipes shall not be used on the work. All pipes shall be tested by
the manufacturer and the Contractor shall produce, when directed a certificate to
that effect from the manufacturer.
Laying
R.C.C. spun pipes shall be laid on cement concrete bed or cradles as specified and
shown on the detailed drawings. The cradles may be precast and sufficiently cured
to prevent cracks and breakage in handling. The invert of the cradles shall be left
12 mm below the invert level of the pipe properly placed on the soil to prevent any
disturbance. The pipe shall then be placed on the bed concrete or cradles and set
for the line and gradient by means of sight rails and bonding rods etc. Cradles or
concrete bed may be omitted, if directed by the Project Manager.
Jointing
After setting out the pipes the socket shall be centered over the spigot and filled in
with tarred gaskin, so that sufficient space is left on either side of the collar to receive
the mortar. The space shall then be filled with cement mortar 1:2 (1 Cement: 2 fine
sand) and caulked by means of proper tools. All joints shall be finished at an angle
of 45 degrees to the longitudinal axis of the pipe on both sides of the collar neatly.
Testing
All pipes shall be tested to a hydraulic test of 1.5 m head for at least 30 minutes at
the highest point in the section under test. Test shall also be carried out similar to
those for stoneware pipes given above. The smoke test shall be carried out by the
contractor, if directed by the Project Manager and a test register shall be maintained
which shall be signed and dated by the Contractor/Project Manager.
3.16 Cement Concrete and masonry works (For Manholes, Gully Traps, Grease
trap and Chambers)
3.16.1 Materials
a) Water
Water used for all the construction purposes shall be clear and free from Oil,
Acid, Alkali, Organic and other harmful matters, which shall deteriorate the
strength and/or durability of the structure. In general, the water suitable for
drinking purposes shall be considered good enough for construction purpose.
b) Aggregate for Concrete
The aggregate for concrete shall be in accordance with I.S. 383 and I.S. 515
in general, these shall be free from all impurities that may cause corrosion of
the reinforcement. Before actual use these shall be washed in water, if
required as per the direction of Project Manager. The size of the coarse
aggregate shall be done as per I.S.383.
c) Sand
Sand for various constructional purposes shall comply in all respects with I.S
650 and I.S. 2116. It shall be clean, coarse hard and strong, sharp, durable,
uncoated, free from any mixture of clay, dust, vegetable matters, mica, iron
impurities soft or flaky and elongated particles, alkali, organic matters, salt,
loam and other impurities which may be considered by the Project Manager.
d) Cement
The cement used for all the constructional purposes shall be ordinary Portland
cement or rapid hardening Portland cement conforming to I.S. 269.
e) Mild Steel Reinforcement
The mild steel for the reinforcement bars shall be in the form of round bars
conforming to all requirements of I.S. 432 (Grade I).
f) Bricks
Bricks shall have uniform color, thoroughly burnt but not over burnt, shall have
plan rectangular faces with parallel sides and sharp right angled edges. They
should give ringing sound when struck. Brick shall not absorb more than 20%
to 22% of water, when immersed in water for 24 hours. Bricks to be used
shall be approved by the Project Manager.
g) Other Materials
Other materials not fully specified in these specifications and which may be
required in the work shall conform to the latest I.S. All such materials shall
be approved by the Project Manager before use.
3.16.2 Cement concrete (plain or reinforced)
a) Cement concrete pipes bedding, cradles, foundations and R.C.C. slabs for all
works shall be mixed by a mechanical mixer where quantities of the concrete
poured at one time permit. Hand mixing on properly constructed platforms
may be allowed for small quantities by the rate for cement concrete shall be
inclusive of all shuttering and centering at all depth and heights.
b) Concrete work shall be of such thickness and mix as given in the Schedule of
Quantities.
c) All concrete work shall be cured for a period or at least 7 days. Such work
shall be kept moist by means of gunny bags at all times. All pipes trenches
and foundations shall be kept dry during the curing period.
3.16.3 Masonry
Masonry work for manholes, chambers, septic tanks, and such other works as
required shall be constructed from 1st class bricks or 2nd class as specified in the
Schedule of quantities in cement mortar 1:5 mix (1 cement: 5 coarse sand). All joints
shall be properly raked to receive plaster.
3.16.4 Cement concrete for pipe support
Wherever specified or shown on the drawing, all pipes shall be supported in bed all
round or haunches. The thickness and mix of the concrete shall be given in the
Schedule of Quantities. Width of the bedding shall be as per para 3.13 above.
Unless otherwise directed by the Project Engineer, cement concrete for bed, all-
round or in haunches shall be laid as follows: -
such thickness and mix as given in the Schedule or Quantities or shown in the
drawings.
Where not specified, manholes shall be constructed as follows:- (all dimensions
internal clear in cms)
Size of manhole 90x80 120x90 91 dia 122 dia
type Rect. Rect. Conical Conical
--------------------------------------------------------------------------------------------------------
Maximum depth 120 240 167 230
Average thickness
Of R.C.C slab 15 15 - -
------------------------------------------------------------------------------------------------------
3.17.3 All manholes shall be provided with cement concrete benching in 1:2:4 mix. The
benching shall have a slope of 10 cms towards the channel. The depth of the
channel shall be full diameter of the pipe. Benching shall be finished with a floating
coat of neat cement. (1 cement: 2 coarse sand: 4 stone aggregate 20 mm nom.
Size) as per standard details.
3.17.4 All manholes shall be plastered with 12mm thick cement mortar 1: 3 (1 cement: 3
coarse sand) and finished with a floating coat of neat cement inside. Manhole shall
be plastered outside as above but with rough plaster mixed with water proofing
compound.
3.17.5 All manholes with depths greater than 1 m. shall be provided with 20 mm square or
25 mm round rods plastic coated catch rings set in cement concrete blocks
25x10x10 cms in 1:2:4 mix 30 cms vertically and staggered. Foot rests shall be
coated with coal tar before embedding.
3.17.6 All manholes shall be provided with fiber reinforced plastic (FRP) covers and frames
and embedded in reinforced cement concrete slab. Weight of cover, frame and
thickness of slab shall be as specified in the Schedule of Quantities or given above.
3.17.7 Road gullies, ramp drains, gratings in basement shall be Fiber Reinforced Plastic
(FRP) with frame as specified in the Schedule of Quantities.
3.18 Making connections
3.18.1 Contractor shall connect the sewer line of the building to the main manhole by
providing making holes and channels etc.
3.19 Measurement
3.19.1 Excavation
3.19.1.1 Measurement for excavation of pipe trenches shall be made per linear meter under
the respective category of soil classification encountered at site and specified in the
tender.
a. Ordinary soil
b. Hard soil (hard moorum & soft rock)
c. Hard rock requiring chiseling
d. Hard rock requiring blasting
3.19.1.2 Trenches shall be measured between outside walls of manholes at top and the
depth shall be the average depth between the two ends to the nearest cm. The rate
quoted shall be for a depth up to 1.5 m or as given in the Schedule of Quantities.
3.19.1.3 Payment for trenches more than 1.5 m in depth shall be made for extra depth as
given in the schedule of quantities and above the rate for depth up to 1.5 m.
3.19.1.4 Timbering and Shoring Timbering and shoring as described above shall be
measured per sq m and paid for as per the type of timbering of shoring done at site
and as per the relevant item in the Schedule of Quantities. Rate for timbering and
shoring shall be for all depths and types of soil classifications including saturated
soil.
3.19.1.5 Saturated Soil
No extra payment for pumping and bailing out water shall be made for excavation
with an average depth of 1.5 m in saturated soil, surface water from rain falls or
broken pipes lines, or sieves and other similar sources. An extra rate as quoted in
the schedule of quantities shall be paid for excavation in saturated soil for pipe
trenches above average depth of 1.5 m. No payment is admissible for water
collected from surface sources and broken pipelines or sewers.
3.19.1.6 Refilling, Consolidation and Disposal of Surplus Earth
Rate quoted for excavation of trenches shall be inclusive of refilling, consolidation
and disposal of surplus earth within a lead of 200 m.
3.19.2 Stoneware Pipes/RCC/C.I. pipes
Stoneware/R.C.C./C.I. pipes shall be measured for the finished length of the pipe
line per linear meter i.e.
(a) Lengths between manholes shall be recorded from inside of one manhole to
inside of other manhole
(b) Length between gully trap and manhole shall be recorded between socket of
pipe near gu11y trap and inside of manhole. Rate shall include all items given
in the schedule of quantities and specifications.
3.19.3 Gully Traps
Gully traps shall be measured by the number and rate shall include all excavation,
foundation, concrete brick masonry, cement plaster inside and outside, C.I. grating