Zorlu Solar - Report
Zorlu Solar - Report
Zorlu Solar - Report
3-Final/18
INTERCONNECTION STUDY
For
Final Report
(January 2018)
1. Introduction
1.1. Background
1.2. Objectives
1.3. Planning Criteria
2. Assumptions of Data
2.1 Solar Power Plant Data
2.2 Network Data
3. Study Approach & Methodology
3.1 Understanding of the Problem
3.2 Approach to the Problem
4. Development of Scheme of Interconnection
4.1 The Proposed Network for Zorlu Solar-I Power Plant
4.2 The Scheme of Interconnection of Zorlu Solar-I Power Plant
4.3 Solar Plant Substation 132/33 kV
5 Detailed Load Flow Studies
5.1 Modeling of Solar Power Plant in the Load Flow
5.2 Reactive Power Requirements
5.3 Base Case Peak Summer 2019, Without Solar Power Plant
5.4 Load Flow with Zorlu Solar Power Plant-Case Summer 2019
5.5 Load Flow with Zorlu Solar Power Plant-Peak Load Case Summer 2021
5.6 Conclusion of Load Flow Analysis
6. Short Circuit Analysis
6.1 Methodology and Assumptions
6.2 Fault current calculations without Zorlu Solar-I Power Plant
6.3 Fault current calculations with Zorlu Solar-I Power Plant Interconnected
6.4 Conclusion of short circuit analysis
7. Transient Stability Analysis
7.1 Assumptions & Methodology
7.1.1 Stability Models
7.1.2 System Conditions
Appendices
Appendix –A: 1- Generation, Transmission Schedule and Load Forecast
2- Maps & Sketches
3- Manufacturer Data Sheets
Appendix –B: Plotted Results of Load Flow for Chapter 5
Appendix –C: Results of Short Circuit Calculations for Chapter 6
Appendix –D: Plotted Results of Stability Analysis for Chapter 7
Appendix –E: Dynamic Data for Stability Analysis
1.1 Background
Zorlu Solar Pakistan Limited (Zorlu-Solar) is developing a 100 MWp
Photovoltaic (PV) based Solar Power Project. The site of proposed project is
located in Punjab in the concession area of Multan Electric Power Company
(MEPCO). The net AC output power of the plant would be 78 MW. The project
will start commercial operation by the fourth quarter of 2018. The electricity
generated from this project would be supplied to the NTDC network through the
network developed for evacuation of power.
1.2 Objectives
The overall objective of the Study is to evolve an interconnection scheme between
Zorlu-Solar Power Project and NTDC network, for stable and reliable evacuation
of the electrical power generated from this plant, fulfilling N-1 reliability criteria.
The specific objectives are:
The Solar Power plant has been modeled according to the following block diagram
The way this works is that the irradiance profile from the sun is used as an input to the
panel module which then calculates the DC power at that value of the irradiance. This
value is then input to the electrical model of the solar power plant (inverter module)
which then goes on to calculate the AC power supplied by the solar power plant.
Two -5/+20 MVAR SVCs will be used to provide reactive compensation for Zorlu
Solar-I-PP
Dynamic Data:
The 132 kV networks available for interconnection to Zorlu Solar Pakistan Limited
Power Plant are as shown in Sketches attached in Appendix-A. The lengths of the
circuits are also mentioned in the sketches.
The input data of NTDC has been used in this study as per NTDC Letter No.
GMPP/CEMP/TRP-380/827-29 dated 14-02-2017. The latest load forecast and the
generation expansion plan of NTDC provided vide this letter has been used in the
study.
The 100 MW Solar Power Plant by Zorlu Solar Pakistan Limited is going to be a
photovoltaic (PV) based solar project in Punjab. It would run almost all the months of
the year though with some variation in its output due to variation in the strength of
light in winter and in rainy season.
The existing nearest grid station is Lal Sohanra 220/132 kV Substation. This is a
recently constructed grid station with 1 x 250 MVA transformation capacity. The
addition of this source of power generation shall provide relief to the 220 kV
Transmission lines from M.Garh-1 to BWP-New. The 132 kV network of MEPCO in
the electrical vicinity of Zorlu Solar-I has significant load demand; therefore a
considerable portion of the power from Zorlu Solar-I Power Plant will be utilized in
meeting this load demand.
The adequacy of NTDC network of 220 kV and MEPCO network of 132 kV in and
around the proposed site of Zorlu Solar-I Power Plant would be investigated in this
study for absorbing and transmitting this power fulfilling the reliability criteria.
A base case network model has been prepared for the peak load case of
Summer 2019, after the COD of 100 MW Solar PV Plant by Zorlu Solar
Pakistan Limited, comprising all 500 kV, 220 kV and 132 kV system,
envisaging the load forecast, the generation additions and transmission
expansions for that year particularly in MEPCO.
The expected COD of the project is by the fourth quarter of 2018. In view of
planned COD of Zorlu Solar-I Power Plant, the above proposed
interconnection scheme has been tested for steady state conditions through
detailed load flow studies for the peak load conditions of Summer 2019 to
assess the maximum impact on the Grid. In addition, an extended term
scenario of Summer 2021 has also been studied for load flow analysis.
Given the location of Zorlu Solar-I power plant, the most feasible interconnection
scheme would be a direct 132 kV double circuit from Zorlu Solar-I PP to Lal Sohanra
220/132 kV substation. The distance of the site of solar plant from the grid station, as
verified from site visit is approximately 2 km. The conductor used would be Rail with
a thermal capacity of 202 MVA. The final scheme of circuits is shown in Appendix –
A.
We see that the power flows on all circuits remain within their ratings. Thus we find
that there are no capacity constraints in terms of MW or MVA flow in the 132 kV
network available in the vicinity of Zorlu-Solar Power Plant for its connectivity under
normal conditions and the N-1 contingency conditions considered.
Mailsi to Karorpaca
Hasilpur to Chistian-New
Hasilpur to Ludden
Lodhran to P.Gaib-2
Lodhran to Bastimulk
Bahawalpur to Miranpur
The results of load flow with Zorlu Solar-I Power Plant interconnected as per
proposed scheme mentioned in chapter 4 are shown for each case. Zorlu Solar is
connected in a loop with Lal.Sohanra 220/132 kV substation. The power flows on the
circuits under normal conditions are seen well within the rated capacities and the
voltages on the bus bars are also within the permissible operating range of ± 5 % off
the nominal.
We find no capacity constraints on the 132 kV circuits under normal conditions i.e.
without any outages of circuits.
N-1 contingency analysis has been carried out and the plotted results are attached in
Appendix – B as follows:
In all the above contingency cases, we find that in the event of outage of any circuit,
the intact circuits remain within the rated capacity. Also the bus bar voltages in all
the contingency events are well within the rated limits. Thus there are no constraints
in this scheme in the contingency conditions mentioned above.
5.6 Load Flow with Zorlu Solar Power Plant-Peak Load Case
Summer 2021
Detailed load flow studies have also been carried out for an extended term spot year
of 2021. The objective is to have a comprehensive total view of Solar power potential
expected to be commissioned by 2021 and the adequacy of respective transmission
plans to evacuate overall power from the Solar Power Plants sources going to be
added in the area by that time. Similarly all other generation that are expected to be
commissioned till 2021 have also been modeled in the case as per the generation plan
obtained from NTDC.
Load flow studies have been carried out with all the additional power generation and
the associated additional transmission schemes. Complete scheme is shown in
Sketches of Appendix-A.
The following 132 kV line openings would be required for the case of Summer 2021
to avoid over-loadings under normal and N-1 contingency conditions.
Line Openings for Peak Load Case Summer 2021:
Jehanian to Dunyapur
Hasilpur to Ludden
Lodhran to P.Gaib-2
Lodhran to Bastimulk
Bahawalpur to Miranpur
Lal Sohanra to K.P.Tomi
Lal Sohanra to Hasilpur
The results of load flow with Zorlu Solar-I Power Plant interconnected as per
proposed scheme are shown for each case. The power flows on the circuits under
The results indicate that under all contingent conditions, the power flowing on the
intact circuits are within the rated limits and the bus voltages are also within the
allowable limits.
In order to assess the short circuit strength of the network without the Zorlu Solar-I
Power Plant for the grid of NTDC/MEPCO in the vicinity of the site of the Plant at
Zorlu Solar-I Park, fault currents have been calculated for balanced three-phase and
unbalanced single-phase short circuit conditions. These levels will not only give us
the idea of the fault levels without Zorlu Solar-I Power Plant and later on how much
the contribution of fault current from the Solar Power Plant may add to the existing
levels, but also we get a feel of the strength of the proposed node to connect this
Power Plant depending on its relative short circuit strength.
The results are attached in Appendix – C.
The short circuit levels have been represented graphically on the bus bars of 33 kV
,132 kV and 220 kV which are shown in the Exhibit 3.0 attached in Appendix-C.
interconnected
6.3.1 Maximum Short circuit Levels - Case 2019
Fault currents have been calculated for the electrical interconnection of Solar PP as
per proposed scheme. Three phase and single-phase fault currrents have been
evaluated at the 33 kV ,132 kV and 220 kV bus bars of Zorlu Solar-I Power and other
bus bars of the 132 kV substations in the electrical vicinity of Zorlu Solar-I. The
graphic results are indicated in Exhibit 3.1
The tabulated results of short circuit analysis showing all the fault current
contributions with short circuit impedances on 132 kV bars of the network in the
electrical vicinity of Zorlu Solar-I Power Plant are placed in Appendix-C. Brief
summary of fault currents at significant bus bars of 33 kV ,132 kV and 220 kV are
tabulated in Table 6.2.
We find that even after the interconnection of Zorlu Solar-I Power Plant these fault
levels are much below the rated short circuit values of the equipment installed on
these substations. The maximum short circuit level of 132 kV bus bar of Zorlu Solar-I
Power Plant is 8.59 kA and 7.43 kA for 3-phase and 1-phase faults respectively.
Therefore industry standard switchgear of the short circuit rating of 40 kA would be
fine to be installed at 132 kV switchyard of Zorlu-Solar-PP as per NTDC requirement
taking care of any future generation additions and system reinforcements in its
electrical vicinity. Similarly the maximum short circuit level of 33 kV bus bar of
Zorlu Solar-I Power Plant is 18.34 kA and 20.02 kA for 3-phase and 1-phase faults
respectively.