Topic 1.2
Topic 1.2
Topic 1.2
Topic 1
Project Management
Paulo Faroleiro
Project Management
Part I
Project Information Project Management LifeCycle
Cost
Time
VARIABLES FOR
PROJECT SUCCESS
Predicting project success is one of the most difficult tasks
facing the project manager.
According to Kerzner - most project managers look only at
time, cost and performance. These parameters do not
necessary identify whether or not the project was
successfully managed although the deliverable was
achieved.
Internal project success is often measured by the “actions”of
three groups:
- the project manager and team
- the parent organization
- the client organization
DEFINITION OF
PROJECT SUCCESS
Before 90
Primary Factors
• Within Time
• Within Cost
• Within Quality
• Accepted by The Customer
After 90
Other Factors:
• Customer Reference • Environmental
• Follow-on Work Protection
• Financial Success • Corporate
• Technical Superiority Reputation
• Strategic Alignment • Employee Alignment
• Regulatory Agency • Ethical conduct
Relations
• Health and Safety
RISK PLANNING AND
MITIGATION STRATEGIES
Poor Risk Management
Performance
Technical
Inability
Time
Market Risk
Assessment Schedule Risk
and Forecasting Assessment
STARTUP (1)
1. There are four stages of team formation: 2. Project Start-up is a structured way to moving the
project team quickly and effectively through these four
• Forming
stages, so as to:
• Storming
• Define the project’s context and objectives
• Norming
• Develop the project model
• Performing
• Define the management approach
3. The methods of project start-up include 4. A stage launch workshop may be held with the
objectives:
• Stage launch workshops
• To gain commitment and build the team spirit
• Start-up reports
• To ratify the project definition as produced in the previous
• Ad-hoc assistance
stage
STARTUP (2)
5. A project definition report may be prepared with the 6. The contents of the report may include
objectives:
• Background
• To commit resources to design
• Purpose, scope, and objectives
• To provide a basis for design
• Project success and mission
• To set the project’s priority
• Work breakdown structure
• To inform all those effected by the project
• Project organization
• To gain commitment
• Stakeholder register
• Quality plan
• Cost estimates
7. The systems design produced during the design and • Schedule
appraisal stage may be summarized in a project
• Risk register
manual, which may have as its contents:
• Initial activity plans
• Project description and objectives
• Project appraisal
• Master project plan
• Project management system
• Management plan
• Performance specification
• Technical specification
• Project constraints
CONTROL (1)
1. The process of resourcing a project includes the 2. The five steps of activity planning are
following steps:
• Define the activities to achieve a milestone or work package.
• Identify what is to be achieved.
• Ratify the people involved.
• Identify the skills and skill types required.
• Define their roles and responsibilities.
• Identify the people available.
• Estimate work content and durations.
• Assess their competence.
• Schedule activities within a work package.
• Identify any training required.
3. After creation of the activity schedule, it is entered 4. Activity schedules may be represented by:
into the master plan, and at appropriate intervals work
• Responsibility charts
allocated to people. Both steps must be authorized by
the project manager. • Estimating sheets
• Nested networks
CONTROL (2)
5. Work is allocated to people via work-to lists, by: 6. The four steps in the control cycle are:
• Time period • Plan future performance.
7. For control to be effective, each step in this cycle 8. Requirements for effective reporting include:
must be effective. Requirements for effective planning
• Reports against the plan
will be described.
• Defined criteria for control
• Creative discussions
EXECUTION AND
Startup Control Closure
CONTROL (3)
9. This can be achieved by gathering data using 10. Time is controlled by recording progress on the
turnaround documents, which can be used to gather critical or near critical paths, or by comparing the cost
data to control the five objectives: of work actually completed to that planned to have
been completed. In order to do this, the following
• Time
progress data is collected:
• Cost
• Actual and Revised start/finish
• Quality
• Effort to Date and Effort Remaining
• Organization
• Costs to date and Cost Remaining
• Scope
11. Cost is controlled by comparing costs incurred to 12. When the divergence of achievement from the plan
the planned cost of work actually completed. In order to becomes too great, the project must be recovered.
do this, the same data is required.
The ten-step problem-solving cycle can be applied to
Costs are said to be incurred when the expenditure is find the solution to plan recovery.
committed, not when the invoices are paid, because at
that time the plan can still be recovered. Possible courses of action include
• Rearranging the plan
• Compromising time
• Compromising cost
• Compromising scope
• Transferring the product to the users • Planning and controlling at lower levels of work breakdown
3. Effective product transfer to the users is facilitated 4. The facility must be commissioned to obtain the
by: required benefit, and this can be controlled by:
• Planning the transition • Defining the desired benefit and desired performance
improvement and by drawing a benefits map
• Ensuring user acceptance
• Monitoring performance improvement and tracking progress
• Training the users against the benefits map
• Obtaining definite cutover • Identifying shortfalls
• Recording the as-built design • Taking action to overcome the shortfalls
• Ensuring maintenance of the facility
Startup Control Closure
• Rewarding achievement
• Counselling staff
Part I
Project Information