Advances in Earned Schedule and Earned Value Management
Advances in Earned Schedule and Earned Value Management
Abstract
Introduction
Planned Value (PV): This is the cumulative planned cost for the work
planned to be done on the project up to a given point in time. It is the
approved budget for completing the work planned so far, and as such
it is the cost baseline for the project. It was previously called the
budgeted cost of work scheduled (BCWS).
Actual cost (AC): This is the cumulative actual cost spent on the
project so far, including all accrued costs on the work done. AC was
previously called the actual cost of work performed (ACWP).
ВАС, PV, AC, and EV are expressed in cost units. That may be in units
of actual money, in any currency. Or it can be expressed in hours or
days of work done. PV, AC, and EV can be calculated for any element
of work to determine progress on that element of work.
Variances:
CV = EV – AC
SV = EV – PV
Variance Percentages
CV% = CV ÷ EV
SV% = SV ÷ PV
In the above formulas,
Performance Indices
CPI = EV ÷ AC
SPI = EV ÷ PV
In this equation,
Earned Schedule
In its basic form, EVM has not been used to estimate the time to
completion or forecast end date. However, extensions to EVM have
been developed to use EVM data for that purpose (Anbari, 2003b;
Lipke, 2009; Lipke, Zwikael, Henderson & Anbari, 2009; Turner et al.,
2010).
Earned Schedule (ES): This duration from the beginning of the project
to the date on which the PV should have been equal to the current
value of EV. On the EVM chart (Exhibit 2), it is the date on which the
horizontal line through the current value of EV intersects the PV curve.
Actual Time (AT): This is the duration from the beginning of the
project to the status date.
TV = ES – AT
TV% = TV ÷ ES
TPI = ES ÷ AT
TEAC can also be calculated using the SPI, but the calculations are
more complicated. They depend on whether the project has
reached the planned completion date and whether it is ahead or
behind schedule. If the date is earlier than SAC and the project has
not yet finished:
After the SAC is reached, SV tends toward and concludes at 0.0 and
SPI tends towards and concludes at 1.0 when the project is
completed. Hence, using SPI for schedule forecasting after the SAC
is reached would lead to erroneous results. Therefore, we define
the expected accomplishment rate (EAR) as the expected average
accomplishment rate per period from the status date to the
completion of the project or work package. Then:
Statistical Forecasting
Example
The following example (adapted from Anbari, 2003; Kwak & Anbari,
2010) illustrates the concepts discussed in this paper. Consider a
project that has a baseline Budget at Completion of $100 (followed by
an appropriate number of 0’s) and a baseline schedule of 40 weeks.
The baseline indicates that by the end of week 20, the project is
planned to be 50% complete. At the end of week 20, it is reported that
40% of the project work has been completed at $60. The main
components of this example are shown in Exhibit 3.
Exhibit 3 – Main Components of the Example Project
(Adapted from Anbari, 2003; Kwak & Anbari, 2010)
BAC = $iGG
AT = 2G weeks
AC = $6G
Therefore:
Earned Schedule:
AT = 20 weeks
ES = 16 weeks
TV = AT – ES = 20 – 16 = -4 weeks
TPI = ES ÷ AT = 16 ÷ 20 = 0.80
Conclusions