The Earned Schedule
The Earned Schedule
Abstract
The Earned Value Management (EVM) and the Critical Path Method (CPM) are widely accepted
methods and are often used simultaneously to evaluate project performance. The common
practice is to use EVM to evaluate the status of project cost and forecast the project's cost at
completion while using CPM to evaluate the status of project schedule and forecast the project's
completion time. However, EVM and CPM are based on different assumptions about the future
and using them simultaneously can lead to the wrong decisions about the project.
The Earned Schedule (ES) allows EVM metrics to be transformed to time or duration metrics to
enhance the evaluation of project schedule performance and to forecast the duration needed to
complete the project. ES extends the use of EVM data to the assessment of the project's schedule
status and the forecast of its completion time. These additional insights regarding the schedule
are gained without the need for additional data collection and related cost. ES and EVM use the
same underlying assumptions, leading to consistent forecasts about project outcomes. When
combined with schedule analysis using CPM, ES enhances the project manager's understanding
of project schedule status and forecasts and provides further support for making better, evidence-
based decisions about the project's schedule and other parameters.
EVM, ES, and CPM are powerful methods that give executives, project managers, and other
stakeholders the ability to visualize project cost and schedule status throughout the project life
cycle and consequently manage projects, programs, and portfolios more effectively.
Keywords: Earned Schedule (ES); Earned Value Management (EVM); Critical Path Method
(CPM); forecasting project outcomes; underlying assumptions.
Introduction
The Earned Value Management (EVM) method helps managers in making evidence-based
decisions about project scope, resources, and cost; as a result, it supports effective project cost
control and oversight. EVM gives the executive, program manager, project manager, and other
stakeholders the ability to visualize project cost status throughout the project life cycle and
consequently manage projects, programs, and portfolios more effectively. In its original form, EVM
was used to evaluate project performance and forecast the cost of the project at completion.
Usually, project control is established at the work package or cost account level. EVM data were
generally not used to estimate the time needed to complete an activity, work package, or project,
or to forecast their completion date. Project schedule network analysis techniques, such as the
Critical Path Method (CPM) method, has been used widely to evaluate project schedule
performance and forecasts of completion time. However, EVM and CPM are based on different
assumptions about the future and using them simultaneously can lead the project manager to
make the wrong decisions about the project. Extensions to EVM have been developed to use
EVM data for schedule performance assessment and forecasts. The Earned Schedule (ES)
concept allows EVM metrics to be transformed to time or duration metrics to enhance the
evaluation of project schedule performance and to forecast the duration needed to complete the
project. When combined with appropriate schedule analysis, this approach can enhance the
project manager's understanding of the time estimate at completion of the project, and provide
further insights for making better decisions about the project schedule and other related
parameters. This paper highlights the main elements of EVM; presents the ES concept; compares
ES with CPM; and integrates EVM, ES, and CPM.
The use of EVM in private industry and support by popular project management software
packages have been rapidly growing in recent years. Details of the method were provided
in Practice Standard for Earned Value Management—Second Edition (Project Management
Institute, 2011) and in other sources (Anbari, 2003; Association for Project Management, 2006;
Humphreys, 2002; Kerzner, 2009; Project Management Institute, 2008; Turner, 2009; Turner,
Huemann, Anbari, & Bredillet, 2010). There has been a high degree of acceptance among users
of EVM, who tend to agree that EVM can improve the cost, schedule, and technical performance
of their projects. Non-believers in EVM claim that the method is hard to use, that it applies primarily
to very large projects, and that they do not need it (Fleming & Koppelman, 2010; Kim, Wells, &
Duffey, 2003). Anbari, (2003), Kwak and Anbari (2010), Turner (2009), and Turner et al. (2010)
show how the method can be simplified and implemented effectively while retaining its essential
features. The interest in EVM and its use in differing types of projects are growing globally,
particularly in the public sector, with notable progress in Australia, Japan, Sweden, the United
Kingdom, and the United States.
ES is a valuable extension to EVM, requires no additional data collection, and provides valuable
insights into the project schedule and forecast of its outcome. The use of ES is still very limited in
practice.
EVM integrates three critical elements of project management: scope management, cost
management, and time management. It requires the periodic monitoring of actual expenditures
and the amount of work done (expressed in cost units). To determine cost performance, EVM
compares how much we have spent with what we planned to have spent to do the work we have
done. To determine time performance, it compares the amount of work done with the amount of
work scheduled to be done. To make these comparisons, EVM calculates cost and schedule
variances, along with performance indices for project performance management. Based on these
results, it forecasts the cost and date of the project at completion and highlights the possible need
for corrective action. EVM uses the following project parameters to evaluate project performance
(Exhibit 1):
Planned Value (PV): This is the cumulative planned cost for the work planned to be done on the
project up to a given point in time. It is the approved budget for completing the work planned so
far, and as such it is the cost baseline for the project. It was previously called the budgeted cost
of work scheduled (BCWS).
Exhibit 1: Components of earned value management.
(Adapted from Anbari, 2003; Kwak & Anbari, 2010; Turner et al., 2010)
Budget at Completion (BAC): This is the total amount of money expected to be spent on the
project, and as such, it is the value that PV is planned to reach at completion.
Actual cost (AC): This is the cumulative actual cost spent on the project so far, including all
accrued cost on the work done. AC was previously called the actual cost of work performed
(ACWP).
Earned value (EV): This represents the cumulative amount of work done up to a point in time,
expressed in cost units. It is expressed as the amount that was planned to have been spent on
the work that has been completed up to this point. EV was previously called the budgeted cost of
work performed (BCWP). To calculate the EV for a given element of work, the planned cost is
multiplied by the percentage complete. The EV for the project is the sum of the EV for all the work
elements.
BAC, PV, AC, and EV are expressed in cost units. These may be in units of actual money, in any
currency, or expressed in hours or days of work. PV, AC, and EV can be calculated for any
element of work to determine progress and status of that element of work.
Cost performance on the project is determined by comparing EV with AC. AC represents what
has actually been spent and accrued to do the work so far, and EV represents what was planned
to be spent to do the work so far. The difference shows whether the project is over-spent or under-
spent. Schedule performance is determined by comparing the EV with the PV. PV shows the
amount of work that was planned to have been done and EV represents the amount that has
been done. By comparing the two we can determine whether more or less work has been
performed than should have been done, and whether the project is ahead or behind schedule.
We do these comparisons by calculating the variances and the performance indices.
Variances
• CV = EV − AC
The schedule variance (SV) is a measure schedule performance:
• SV = EV − PV
Variance Percentages
• CV% = CV ÷ EV
Schedule variance percent (SV%):
• SV% = SV ÷ PV
In the above formulas, 0 indicates that performance is on target. A positive value indicates good
performance; a negative value indicates poor performance.
Performance Indices
• CPI = EV ÷ AC
The schedule performance index (SPI) is another measure of schedule performance:
• SPI = EV ÷ PV
In the above formulas, 1 indicates that performance is on target; more than 1indicates good
performance; and less than 1 indicates poor performance.
Project management is primarily concerned with decisions affecting the future. Therefore,
forecasting is an extremely important aspect of project management. EVM is particularly useful in
forecasting the cost and time of the project at completion, based on actual performance to date
using the following calculations.
• The remaining work will be performed according to the original plan, therefore (Turner, 2009):
o ETC = BAC − EV
o EAC = AC + BAC − EV = BAC + CV
• The remaining work will be performed while continuing to over-spend or under-spend at the same
rate (Anbari, 2003; Project Management Institute, 2011; Turner, 2009):
o ETC = (BAC − EV) ÷ CPI
o EAC = AC + (BAC − EV) ÷ CPI = BAC ÷ CPI
The cost Variance at Completion (VAC) provides an indication of the estimated cost under-run or
over-run at the completion of the project:
Earned Schedule
In its basic form, EVM has not been used to estimate the time to completion or to forecast the end
date. However, extensions to EVM have been developed to use EVM data for that purpose
(Anbari, 2003; Lipke, 2009; Lipke, Zwikael, Henderson & Anbari, 2009; Turner et al., 2010).
The terminology in this area is not as fully agreed on as in EVM, so the following terminology will
be used:
Schedule at Completion (SAC): This is the original planned completion duration (date) of the
project.
Earned Schedule (ES): This duration from the beginning of the project to the date on which the
PV should have been equal to the current value of EV. On the EVM chart (Exhibit 2), it is the date
on which the horizontal line through the current value of EV intersects the PV curve.
Actual Time (AT): This is the duration from the beginning of the project to status date.
The average PV per time period can be calculated by dividing the BAC by SAC, and can be called
the PV Rate or the Planned Accomplishment Rate (PAR):
• TV = SV ÷ PAR
ES can be calculated by dividing EV by PAR:
• ES = EV ÷ PAR
Alternately, TV can be calculated by subtracting AT from ES:
• TV = ES − AT
If TV value is negative, the project is behind schedule and if it is positive, it is ahead of schedule.
This is sometimes called the schedule variance (time), SV(t), but this name can lead to possible
confusion with the schedule variance.
• TV% = TV ÷ AT
The result of the above formula is consistent with the result obtained by using the SV% formula
provided earlier. However, a more realistic measure of schedule performance may be obtained
by calculating TV% by dividing TV by ES.
The time performance index (TPI) can be defined as the ratio of ES to AT and calculated as:
• TPI = ES ÷ AT
This is sometimes called schedule performance index (time), SPI(t), but again there is a possible
risk of confusion with SPI. As with SPI, if TPI is greater than 1, then the project is ahead of
schedule and if it is less than 1, then the project is behind schedule.
Forecasting of Completion Time
The forecasting of time at completion can be called the time estimate at completion (TEAC). The
fact that the estimated cost at completion is generally called the estimate at completion (EAC)
and not the cost estimate at completion (CEAC), whereas the estimated time at completion has
to be called the time estimate at completion (TEAC), underlines EVM's primary focus on cost
control. The forecast of time to complete the remaining work can be called the time estimate to
complete (TETC).
Several assumptions can be made about project schedule performance in the future (Anbari,
2003). Two major assumptions are:
• The remaining work will be performed according to the original plan and there will be no further delay
to (or speeding of) the project, therefore (Anbari, 2003; Turner et al., 2010):
o TEAC = SAC + TV
• The remaining work will be performed while maintaining the same rate of doing work for the rest of
the project (Anbari, 2003; Lipke, 2009; Lipke et al., 2009; Turner et al., 2010):
o TEAC = SAC ÷ TPI
TEAC can also be calculated using the SPI, but the calculations are more complicated. They depend
on whether the project has reached the planned completion date and whether it is ahead or behind
schedule. If the date is earlier than SAC and the project has not yet finished:
o TEAC = SAC ÷ SPI
After the SAC is reached, SV tends toward 0 and concludes at 0 and SPI tends toward 1.0 and
concludes at 1when the project is completed. Hence, using SPI for schedule forecasting after the
SAC is reached would lead to erroneous results. Therefore, we define the Expected Accomplishment
Rate (EAR) as the expected average accomplishment rate per time period from the status date to
the completion of the project or the work package. Then:
o TEAC = AT + (BAC − EV) ÷ EAR
When past schedule performance is a good predictor of future schedule performance, EAR would
be equal to the average Actual Accomplishment Rate (AAR) per time period to date, which can be
obtained by dividing EV over AT:
o EAR = AAR = EV ÷ AT
Then:
o TEAC = AT + (BAC − EV) ÷ AAR
Time Variance at Completion
The Time Variance at Completion (TVAC) gives an indication of the estimated amount of time
that the project will be completed ahead or behind schedule:
Statistical Forecasting
EVM and ES have been integrated with statistical confidence limits to derive the range of probable
outcomes for the project final cost and duration. Results of this work demonstrate that the
proposed approach is sufficiently reliable for general application of the forecasting method for
both cost and duration, and that the ES approach can be applied effectively, regardless of the
type of work or the magnitude of cost and duration of the project (Lipke et al., 2009).
Example
The following example (adapted from Anbari, 2003 and Kwak & Anbari, 2010) illustrates the
concepts discussed in this paper. Consider a project that has a baseline Budget at Completion of
US$100 (followed by an appropriate number of 0's) and a baseline schedule of 40 weeks. The
baseline indicates that by the end of week 20, the project is planned to be 50% complete. At the
end of week 20, it is reported that 40% of the project work has been completed at a cost of US$60.
The main components of this example are shown in Exhibit 3.
• AT = 20 weeks
• ES = 40 ÷ 2.5 = 16 weeks
• TV = AT − ES = 20 − 16 = -4 weeks
• TPI = ES ÷ AT = 16 ÷ 20 = 0.80
• TEAC = SAC ÷ TPI = 40 ÷ 0.80 = 50 weeks
• TVAC = SAC − TEAC = 40 − 50 = -10 weeks
From the above, we can conclude that this project is in serious trouble regarding both cost and
schedule performance. Corrective actions should have already been taken. It is critical to conduct
an immediate review of this project, evaluate the underlying causes of the problems facing it, and
make evidence-based, appropriate decisions promptly.
Comparison and Integration of ES and CPM
Many professionals like to use network analysis techniques, such as CPM, for schedule
forecasting and EVM for cost forecasting. However, it is important to note that these methods
have different underlying assumptions. CPM is primarily a planning tool, whereas EVM is primarily
a monitoring and control tool. CPM generally assumes that future performance will parallel the
original plan, unless changes are made to the original plan scope, time, logic, resources, or cost.
CPM assumes initially that problems or opportunities that affected performance in the past will
not recur in the future and that the original plan is better than past performance on the project as
a predictor of future performance on the same project. By contrast, the assumption generally
associated with EVM is that past performance on the project is a good predictor of future
performance on the same project, that performance to date will continue into the future, and that
efficiencies or inefficiencies observed to date will prevail through the completion of the project,
unless changes are made. Which of these assumptions and related forecasts will materialize
depends greatly on decisions and actions taken by the project manager, the project team, senior
executives, and others in the organization (Anbari, 2003; Turner et al., 2010).
Considering the above example, the project is 4 weeks behind schedule as of week 20. Using
CPM analysis and assuming the worst case scenario that the 4 weeks are entirely on the critical
path of 40 weeks, the project would be forecasted to be completed in 44 weeks, with a delay of 4
weeks. This analysis is demonstrated in Exhibit 4, where the critical path consists of activities C,
D, and G, resulting in the planned project duration of 40 weeks:
Conclusions
ES is a powerful method that helps the executive, program manager, project manager, and other
stakeholders in managing projects, programs, and portfolios more effectively. ES allows EVM
metrics to be transformed to time or duration metrics to enhance the evaluation of project schedule
performance, forecast the duration needed to complete the project, augment the project
manager's understanding of the time estimate at completion of the project, and provide further
insights for making better, evidence-based decisions about the project schedule and other
parameters.
Anbari, F.T. (2003). Earned value project management method and extensions. Project
Management Journal, 34(4), 12–23.
Association for Project Management (2006). APM body of knowledge (5th ed.). Buckinghamshire,
UK: APM Publishing.
Fleming, Q.W., & Koppelman, J.M. (2010). Earned value project management (4th ed.). Newtown
Square, PA: Project Management Institute.
Humphreys, G.C. (2002). Project management using earned value. Orange, CA: Humphreys &
Associates.
Kerzner, H. (2009). Project management: A systems approach to planning, scheduling, and
controlling (10th ed.). Hoboken, NJ: Wiley.
Kim, E.H., Wells Jr., W.G., & Duffey, M.R. (2003). A model for effective implementation of earned
value management methodology. International Journal of Project Management, 21(5), 375–382.
Kwak, Y.H., & Anbari, F. T. (2010). Project management in government: An introduction to earned
value management (EVM). Washington, DC: IBM Center for The Business of Government.
Lipke, W.H. (2009). Earned schedule. Raleigh, NC: Lulu Publishing.
Project Management Institute (2008). A guide to the project management body of knowledge
(PMBOK® guide)—Fourth Edition. Newtown Square, PA: Author.
Project Management Institute (2011). Practice standard for earned value management—Second
Edition. Newtown Square, PA: Author.
Turner, J.R. (2009). The handbook of project based management, (3rd ed.). New York, NY:
McGraw-Hill.
Turner, J.R., Huemann, M., Anbari, F.T., & Bredillet, C.N. (2010). Perspectives on
projects. London, and New York: Routledge.