Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Civil Work Productivity Norms

Download as pdf or txt
Download as pdf or txt
You are on page 1of 54

Civil Work Productivity Norms

Source:
https://www.cmu.edu/cee/projects/PMbook/04_Labor,_Material,_And_Equipment_Utilization.html

4. Labor, Material and Equipment Utilization


4.1 Historical Perspective
Good project management in construction must vigorously pursue the efficient utilization of
labor, material and equipment. Improvement of labor productivity should be a major and
continual concern of those who are responsible for cost control of constructed facilities. Material
handling, which includes procurement, inventory, shop fabrication and field servicing, requires
special attention for cost reduction. The use of new equipment and innovative methods has made
possible wholesale changes in construction technologies in recent decades. Organizations which
do not recognize the impact of various innovations and have not adapted to changing
environments have justifiably been forced out of the mainstream of construction activities.

Observing the trends in construction technology presents a very mixed and ambiguous picture.
On the one hand, many of the techniques and materials used for construction are essentially
unchanged since the introduction of mechanization in the early part of the twentieth century. For
example, a history of the Panama Canal construction from 1904 to 1914 argues that:

[T]he work could not have done any faster or more efficiently in our day, despite all
technological and mechanical advances in the time since, the reason being that no present system
could possibly carry the spoil away any faster or more efficiently than the system employed. No
motor trucks were used in the digging of the canal; everything ran on rails. And because of the
mud and rain, no other method would have worked half so well. [1]

In contrast to this view of one large project, one may also point to the continual change and
improvements occurring in traditional materials and techniques. Bricklaying provides a good
example of such changes:

Bricklaying...is said not to have changed in thousands of years; perhaps in the literal placing of
brick on brick it has not. But masonry technology has changed a great deal. Motorized
wheelbarrows and mortar mixers, sophisticated scaffolding systems, and forklift trucks now
assist the bricklayer. New epoxy mortars give stronger adhesion between bricks. Mortar
additives and cold-weather protection eliminate winter shutdowns. [2]

Add to this list of existing innovations the possibility of robotic bricklaying; automated
prototypes for masonry construction already exist. Technical change is certainly occurring in
construction, although it may occur at a slower rate than in other sectors of the economy.
The United States construction industry often points to factors which cannot be controlled by the
industry as a major explanatory factor in cost increases and lack of technical innovation. These
include the imposition of restrictions for protection of the environment and historical districts,
requirements for community participation in major construction projects, labor laws which allow
union strikes to become a source of disruption, regulatory policies including building codes and
zoning ordinances, and tax laws which inhibit construction abroad. However, the construction
industry should bear a large share of blame for not realizing earlier that the technological edge
held by the large U.S. construction firms has eroded in face of stiff foreign competition. Many
past practices, which were tolerated when U.S. contractors had a technological lead, must now be
changed in the face of stiff competition. Otherwise, the U.S. construction industry will continue
to find itself in trouble.

With a strong technological base, there is no reason why the construction industry cannot catch
up and reassert itself to meet competition wherever it may be. Individual design and/or
construction firms must explore new ways to improve productivity for the future. Of course,
operational planning for construction projects is still important, but such tactical planning has
limitations and may soon reach the point of diminishing return because much that can be wrung
out of the existing practices have already been tried. What is needed the most is strategic
planning to usher in a revolution which can improve productivity by an order of magnitude or
more. Strategic planning should look at opportunities and ask whether there are potential options
along which new goals may be sought on the basis of existing resources. No one can be certain
about the success of various development options for the design professions and the construction
industry. However, with the availability of today's high technology, some options have good
potential of success because of the social and economic necessity which will eventually push
barriers aside. Ultimately, decisions for action, not plans, will dictate future outcomes.

Back to top

4.2 Labor Productivity


Productivity in construction is often broadly defined as output per labor hour. Since labor
constitutes a large part of the construction cost and the quantity of labor hours in performing a
task in construction is more susceptible to the influence of management than are materials or
capital, this productivity measure is often referred to as labor productivity. However, it is
important to note that labor productivity is a measure of the overall effectiveness of an operating
system in utilizing labor, equipment and capital to convert labor efforts into useful output, and is
not a measure of the capabilities of labor alone. For example, by investing in a piece of new
equipment to perform certain tasks in construction, output may be increased for the same number
of labor hours, thus resulting in higher labor productivity.

Construction output may be expressed in terms of functional units or constant dollars. In the
former case, labor productivity is associated with units of product per labor hour, such as cubic
yards of concrete placed per hour or miles of highway paved per hour. In the latter case, labor
productivity is identified with value of construction (in constant dollars) per labor hour. The
value of construction in this regard is not measured by the benefit of constructed facilities, but by
construction cost. Labor productivity measured in this way requires considerable care in
interpretation. For example, wage rates in construction have been declining in the US during the
period 1970 to 1990, and since wages are an important component in construction costs, the
value of construction put in place per hour of work will decline as a result, suggesting lower
productivity.

Productivity at the Job Site

Contractors and owners are often concerned with the labor activity at job sites. For this purpose,
it is convenient to express labor productivity as functional units per labor hour for each type of
construction task. However, even for such specific purposes, different levels of measure may be
used. For example, cubic yards of concrete placed per hour is a lower level of measure than
miles of highway paved per hour. Lower-level measures are more useful for monitoring
individual activities, while higher-level measures may be more convenient for developing
industry-wide standards of performance.

While each contractor or owner is free to use its own system to measure labor productivity at a
site, it is a good practice to set up a system which can be used to track productivity trends over
time and in varied locations. Considerable efforts are required to collect information regionally
or nationally over a number of years to produce such results. The productivity indices compiled
from statistical data should include parameters such as the performance of major crafts, effects of
project size, type and location, and other major project influences.

In order to develop industry-wide standards of performance, there must be a general agreement


on the measures to be useful for compiling data. Then, the job site productivity data collected by
various contractors and owners can be correlated and analyzed to develop certain measures for
each of the major segment of the construction industry. Thus, a contractor or owner can compare
its performance with that of the industry average.

Productivity in the Construction Industry

Because of the diversity of the construction industry, a single index for the entire industry is
neither meaningful nor reliable. Productivity indices may be developed for major segments of the
construction industry nationwide if reliable statistical data can be obtained for separate industrial
segments. For this general type of productivity measure, it is more convenient to express labor
productivity as constant dollars per labor hours since dollar values are more easily aggregated
from a large amount of data collected from different sources. The use of constant dollars allows
meaningful approximations of the changes in construction output from one year to another when
price deflators are applied to current dollars to obtain the corresponding values in constant
dollars. However, since most construction price deflators are obtained from a combination of
price indices for material and labor inputs, they reflect only the change of price levels and do not
capture any savings arising from improved labor productivity. Such deflators tend to overstate
increases in construction costs over a long period of time, and consequently understate the
physical volume or value of construction work in years subsequent to the base year for the
indices.

Back to top
4.3 Factors Affecting Job-Site Productivity
Job-site productivity is influenced by many factors which can be characterized either as labor
characteristics, project work conditions or as non-productive activities. The labor characteristics
include:

 age, skill and experience of workforce


 leadership and motivation of workforce

The project work conditions include among other factors:

 Job size and complexity.


 Job site accessibility.
 Labor availability.
 Equipment utilization.
 Contractual agreements.
 Local climate.
 Local cultural characteristics, particularly in foreign operations.

The non-productive activities associated with a project may or may not be paid by the owner, but
they nevertheless take up potential labor resources which can otherwise be directed to the
project. The non-productive activities include among other factors:

 Indirect labor required to maintain the progress of the project


 Rework for correcting unsatisfactory work
 Temporary work stoppage due to inclement weather or material shortage
 Time off for union activities
 Absentee time, including late start and early quits
 Non-working holidays
 Strikes

Each category of factors affects the productive labor available to a project as well as the on-site
labor efficiency.

Labor Characteristics

Performance analysis is a common tool for assessing worker quality and contribution. Factors
that might be evaluated include:

 Quality of Work - caliber of work produced or accomplished.


 Quantity of Work - volume of acceptable work
 Job Knowledge - demonstrated knowledge of requirements, methods, techniques and
skills involved in doing the job and in applying these to increase productivity.
 Related Work Knowledge - knowledge of effects of work upon other areas and
knowledge of related areas which have influence on assigned work.
 Judgment - soundness of conclusions, decisions and actions.
 Initiative - ability to take effective action without being told.
 Resource Utilization - ability to delineate project needs and locate, plan and effectively
use all resources available.
 Dependability - reliability in assuming and carrying out commitments and obligations.
 Analytical Ability - effectiveness in thinking through a problem and reaching sound
conclusions.
 Communicative Ability - effectiveness in using orgal and written communications and in
keeping subordinates, associates, superiors and others adequately informed.
 Interpersonal Skills - effectiveness in relating in an appropriate and productive manner to
others.
 Ability to Work Under Pressure - ability to meet tight deadlines and adapt to changes.
 Security Sensitivity - ability to handle confidential information appropriately and to
exercise care in safeguarding sensitive information.
 Safety Consciousness - has knowledge of good safety practices and demonstrates
awareness of own personal safety and the safety of others.
 Profit and Cost Sensitivity - ability to seek out, generate and implement profit-making
ideas.
 Planning Effectiveness - ability to anticipate needs, forecast conditions, set goals and
standards, plan and schedule work and measure results.
 Leadership - ability to develop in others the willingenss and desire to work towards
common objectives.
 Delegating - effectiveness in delegating work appropriately.
 Development People - ability to select, train and appraise personnel, set standards of
performance, and provide motivation to grow in their capacity. < li>Diversity (Equal
Employment Opportunity) - ability to be senstive to the needs of minorities, females and
other protected groups and to demonstrate affirmative action in responding to these
needs.

These different factors could each be assessed on a three point scale: (1) recognized strength, (2)
meets expectations, (3) area needing improvement. Examples of work performance in these areas
might also be provided.

Project Work Conditions

Job-site labor productivity can be estimated either for each craft (carpenter, bricklayer, etc.) or
each type of construction (residential housing, processing plant, etc.) under a specific set of work
conditions. A base labor productivity may be defined for a set of work conditions specified by
the owner or contractor who wishes to observe and measure the labor performance over a period
of time under such conditions. A labor productivity index may then be defined as the ratio of the
job-site labor productivity under a different set of work conditions to the base labor productivity,
and is a measure of the relative labor efficiency of a project under this new set of work
conditions.

The effects of various factors related to work conditions on a new project can be estimated in
advance, some more accurately than others. For example, for very large construction projects,
the labor productivity index tends to decrease as the project size and/or complexity increase
because of logistic problems and the "learning" that the work force must undergo before
adjusting to the new environment. Job-site accessibility often may reduce the labor productivity
index if the workers must perform their jobs in round about ways, such as avoiding traffic in
repaving the highway surface or maintaining the operation of a plant during renovation. Labor
availability in the local market is another factor. Shortage of local labor will force the contractor
to bring in non-local labor or schedule overtime work or both. In either case, the labor efficiency
will be reduced in addition to incurring additional expenses. The degree of equipment utilization
and mechanization of a construction project clearly will have direct bearing on job-site labor
productivity. The contractual agreements play an important role in the utilization of union or
non-union labor, the use of subcontractors and the degree of field supervision, all of which will
impact job-site labor productivity. Since on-site construction essentially involves outdoor
activities, the local climate will influence the efficiency of workers directly. In foreign
operations, the cultural characteristics of the host country should be observed in assessing the
labor efficiency.

Non-Productive Activities

The non-productive activities associated with a project should also be examined in order to
examine the productive labor yield, which is defined as the ratio of direct labor hours devoted to
the completion of a project to the potential labor hours. The direct labor hours are estimated on
the basis of the best possible conditions at a job site by excluding all factors which may reduce
the productive labor yield. For example, in the repaving of highway surface, the flagmen
required to divert traffic represent indirect labor which does not contribute to the labor efficiency
of the paving crew if the highway is closed to the traffic. Similarly, for large projects in remote
areas, indirect labor may be used to provide housing and infrastructure for the workers hired to
supply the direct labor for a project. The labor hours spent on rework to correct unsatisfactory
original work represent extra time taken away from potential labor hours. The labor hours related
to such activities must be deducted from the potential labor hours in order to obtain the actual
productive labor yield.

Example 4-1: Effects of job size on productivity

A contractor has established that under a set of "standard" work conditions for building
construction, a job requiring 500,000 labor hours is considered standard in determining the base
labor productivity. All other factors being the same, the labor productivity index will increase to
1.1 or 110% for a job requiring only 400,000 labor-hours. Assuming that a linear relation exists
for the range between jobs requiring 300,000 to 700,000 labor hours as shown in Figure 4-1,
determine the labor productivity index for a new job requiring 650,000 labor hours under
otherwise the same set of work conditions.
Figure 4-1: Illustrative Relationship between Productivity Index and Job Size

The labor productivity index I for the new job can be obtained by linear interpolation of the
available data as follows:

This implies that labor is 15% less productive on the large job than on the standard project.

Example 4-2: Productive labor yield [3]

In the construction of an off-shore oil drilling platform, the potential labor hours were found to
be L = 7.5 million hours. Of this total, the non-productive activities expressed in thousand labor
hours were as follows:

 A = 417 for holidays and strikes


 B = 1,415 for absentees (i.e. vacation, sick time, etc.)
 C = 1,141 for temporary stoppage (i.e. weather, waiting, union activities, etc.)
 D = 1,431 for indirect labor (i.e. building temporary facilities, cleaning up the site,
rework to correct errors, etc.)

Determine the productive labor yield after the above factors are taken into consideration.
The percentages of time allocated to various non-productive activities, A, B, C and D are:

The total percentage of time X for all non-productive activities is:

The productive labor yield, Y, when the given factors for A, B, C and D are considered, is as
follows:

As a result, only 41% of the budgeted labor time was devoted directly to work on the facility.

Example 4-3: Utilization of on-site worker's time

An example illustrating the effects of indirect labor requirements which limit productive labor by
a typical craftsman on the job site was given by R. Tucker with the following percentages of time
allocation: [4]

Productive time 40%


Unproductive time
Administrative delays 20%
Inefficient work methods 20%
Labor jurisdictions and other work restrictions 15%
Personal time 5%

In this estimate, as much time is spent on productive work as on delays due to management and
inefficiencies due to antiquated work methods.

Back to top

4.4 Labor Relations in Construction


The market demand in construction fluctuates greatly, often within short periods and with
uneven distributions among geographical regions. Even when the volume of construction is
relatively steady, some types of work may decline in importance while other types gain. Under
an unstable economic environment, employers in the construction industry place great value on
flexibility in hiring and laying off workers as their volumes of work wax and wane. On the other
hand, construction workers sense their insecurity under such circumstances and attempt to limit
the impacts of changing economic conditions through labor organizations.

There are many crafts in the construction labor forces, but most contractors hire from only a few
of these crafts to satisfy their specialized needs. Because of the peculiar characteristics of
employment conditions, employers and workers are placed in a more intimate relationship than
in many other industries. Labor and management arrangements in the construction industry
include both unionized and non-unionized operations which compete for future dominance.
Dramatic shifts in unionization can occur. For example, the fraction of trade union members in
the construction industry declined from 42% in 1992 to 26% in 2000 in Australia, a 40% decline
in 8 years.

Unionized Construction

The craft unions work with construction contractors using unionized labor through various
market institutions such as jurisdiction rules, apprenticeship programs, and the referral system.
Craft unions with specific jurisdiction rules for different trades set uniform hourly wage rates for
journeymen and offer formal apprenticeship training to provide common and equivalent skill for
each trade. Contractors, through the contractors' associations, enter into legally binding
collective bargaining agreements with one or more of the craft unions in the construction trades.
The system which bind both parties to a collective bargaining agreement is referred to as the
"union shop". These agreements obligate a contractor to observe the work jurisdictions of
various unions and to hire employees through a union operated referral system commonly known
as the hiring hall.

The referral systems operated by union organizations are required to observe several conditions:

1. All qualified workers reported to the referral system must be made available to the
contractor without discrimination on the basis of union membership or other relationship
to the union. The "closed shop" which limits referral to union members only is now
illegal.
2. The contractor reserves the right to hire or refuse to hire any worker referred by the union
on the basis of his or her qualifications.
3. The referral plan must be posted in public, including any priorities of referrals or required
qualifications.

While these principles must prevail, referral systems operated by labor organizations differ
widely in the construction industry.

Contractors and craft unions must negotiate not only wage rates and working conditions, but also
hiring and apprentice training practices. The purpose of trade jurisdiction is to encourage
considerable investment in apprentice training on the part of the union so that the contractor will
be protected by having only qualified workers perform the job even though such workers are not
permanently attached to the contractor and thus may have no sense of security or loyalty. The
referral system is often a rapid and dependable source of workers, particularly for a contractor
who moves into a new geographical location or starts a new project which has high fluctuations
in demand for labor. By and large, the referral system has functioned smoothly in providing
qualified workers to contractors, even though some other aspects of union operations are not as
well accepted by contractors.

Non-Unionized Construction

In recent years, non-union contractors have entered and prospered in an industry which has a
long tradition of unionization. Non-union operations in construction are referred to as "open
shops." However, in the absence of collective bargaining agreements, many contractors operate
under policies adopted by non-union contractors' associations. This practice is referred to as
"merit shop", which follows substantially the same policies and procedures as collective
bargaining although under the control of a non-union contractors' association without union
participation. Other contractors may choose to be totally "unorganized" by not following either
union shop or merit shop practices.

The operations of the merit shop are national in scope, except for the local or state apprenticeship
and training plans. The comprehensive plans of the contractors' association apply to all
employees and crafts of a contractor regardless of their trades. Under such operations, workers
have full rights to move through the nation among member contractors of the association. Thus,
the non-union segment of the industry is organized by contractors' associations into an integral
part of the construction industry. However, since merit shop workers are employed directly by
the construction firms, they have a greater loyalty to the firm, and recognize that their own
interest will be affected by the financial health of the firm.

Playing a significant role in the early growth and continued expansion of merit shop construction
is the Associated Builders and Contractors association. By 1987, it had a membership of nearly
20,000 contractors and a network of 75 chapters through the nation. Among the merit shop
contractors are large construction firms such as Fluor Daniel, Blount International, and Brown &
Root Construction. The advantages of merit shops as claimed by its advocates are:

 the ability to manage their own work force


 flexibility in making timely management decisions
 the emphasis on making maximum usage of local labor force
 the emphasis on encouraging individual work advancement through continued
development of skills
 the shared interest that management and workers have in seeing an individual firm
prosper.

By shouldering the training responsibility for producing skill workers, the merit shop contractors
have deflected the most serious complaints of users and labor that used to be raised against the
open shop. On the other hand, the use of mixed crews of skilled workers at a job site by merit
shop contractors enables them to remove a major source of inefficiencies caused by the exclusive
jurisdiction practiced in the union shop, namely the idea that only members of a particular union
should be permitted to perform any given task in construction. As a result, merit shop contractors
are able to exert a beneficial influence on productivity and cost-effectiveness of construction
projects.

The unorganized form of open shop is found primarily in housing construction where a large
percentage of workers are characterized as unskilled helpers. The skilled workers in various
crafts are developed gradually through informal apprenticeships while serving as helpers. This
form of open shop is not expected to expand beyond the type of construction projects in which
highly specialized skills are not required.

Back to top

4.5 Problems in Collective Bargaining


In the organized building trades in North American construction, the primary unit is the
international union, which is an association of local unions in the United States and Canada.
Although only the international unions have the power to issue or remove charters and to
organize or combine local unions, each local union has considerable degrees of autonomy in the
conduct of its affairs, including the negotiation of collective bargaining agreements. The business
agent of a local union is an elected official who is the most important person in handling the day
to day operations on behalf of the union. The contractors' associations representing the
employers vary widely in composition and structure, particularly in different geographical
regions. In general, local contractors' associations are considerably less well organized than the
union with which they deal, but they try to strengthen themselves through affiliation with state
and national organizations. Typically, collective bargaining agreements in construction are
negotiated between a local union in a single craft and the employers of that craft as represented
by a contractors' association, but there are many exceptions to this pattern. For example, a
contractor may remain outside the association and negotiate independently of the union, but it
usually cannot obtain a better agreement than the association.

Because of the great variety of bargaining structures in which the union and contractors'
organization may choose to stage negotiations, there are many problems arising from
jurisdictional disputes and other causes. Given the traditional rivalries among various crafts and
the ineffective organization of some of contractors' associations, coupled with the lack of
adequate mechanisms for settling disputes, some possible solutions to these problems deserve
serious attention: [5]

Regional Bargaining

Currently, the geographical area in a collective bargaining agreement does not necessarily
coincide with the territory of the union and contractors' associations in the negotiations. There
are overlapping of jurisdictions as well as territories, which may create successions of contract
termination dates for different crafts. Most collective bargaining agreements are negotiated
locally, but regional agreements with more comprehensive coverage embracing a number of
states have been established. The role of national union negotiators and contractors'
representatives in local collective bargaining is limited. The national agreement between
international unions and a national contractor normally binds the contractors' association and its
bargaining unit. Consequently, the most promising reform lies in the broadening of the
geographic region of an agreement in a single trade without overlapping territories or
jurisdictions.

Multicraft Bargaining

The treatment of interrelationships among various craft trades in construction presents one of the
most complex issues in the collective bargaining process. Past experience on project agreements
has dealt with such issues successfully in that collective bargaining agreements are signed by a
group of craft trade unions and a contractor for the duration of a project. Project agreements may
reference other agreements on particular points, such as wage rates and fringe benefits, but may
set their own working conditions and procedures for settling disputes including a commitment of
no-strike and no-lockout. This type of agreement may serve as a starting point for multicraft
bargaining on a regional, non-project basis.

Improvement of Bargaining Performance

Although both sides of the bargaining table are to some degree responsible for the success or
failure of negotiation, contractors have often been responsible for the poor performance of
collective bargaining in construction in recent years because local contractors' associations are
generally less well organized and less professionally staffed than the unions with which they
deal. Legislation providing for contractors' association accreditation as an exclusive bargaining
agent has now been provided in several provinces in Canada. It provides a government board that
could hold hearings and establish an appropriate bargaining unit by geographic region or sector
of the industry, on a single-trade or multi-trade basis.

Back to top

4.6 Materials Management


Materials management is an important element in project planning and control. Materials
represent a major expense in construction, so minimizing procurement or purchase costs
presents important opportunities for reducing costs. Poor materials management can also result
in large and avoidable costs during construction. First, if materials are purchased early, capital
may be tied up and interest charges incurred on the excess inventory of materials. Even worse,
materials may deteriorate during storage or be stolen unless special care is taken. For example,
electrical equipment often must be stored in waterproof locations. Second, delays and extra
expenses may be incurred if materials required for particular activities are not available.
Accordingly, insuring a timely flow of material is an important concern of project managers.

Materials management is not just a concern during the monitoring stage in which construction is
taking place. Decisions about material procurement may also be required during the initial
planning and scheduling stages. For example, activities can be inserted in the project schedule to
represent purchasing of major items such as elevators for buildings. The availability of materials
may greatly influence the schedule in projects with a fast track or very tight time schedule:
sufficient time for obtaining the necessary materials must be allowed. In some case, more
expensive suppliers or shippers may be employed to save time.

Materials management is also a problem at the organization level if central purchasing and
inventory control is used for standard items. In this case, the various projects undertaken by the
organization would present requests to the central purchasing group. In turn, this group would
maintain inventories of standard items to reduce the delay in providing material or to obtain
lower costs due to bulk purchasing. This organizational materials management problem is
analogous to inventory control in any organization facing continuing demand for particular
items.

Materials ordering problems lend themselves particularly well to computer based systems to
insure the consistency and completeness of the purchasing process. In the manufacturing realm,
the use of automated materials requirements planning systems is common. In these systems, the
master production schedule, inventory records and product component lists are merged to
determine what items must be ordered, when they should be ordered, and how much of each item
should be ordered in each time period. The heart of these calculations is simple arithmetic: the
projected demand for each material item in each period is subtracted from the available
inventory. When the inventory becomes too low, a new order is recommended. For items that are
non-standard or not kept in inventory, the calculation is even simpler since no inventory must be
considered. With a materials requirement system, much of the detailed record keeping is
automated and project managers are alerted to purchasing requirements.

Example 4-4: Examples of benefits for materials management systems.[6]

From a study of twenty heavy construction sites, the following benefits from the introduction of
materials management systems were noted:

 In one project, a 6% reduction in craft labor costs occurred due to the improved
availability of materials as needed on site. On other projects, an 8% savings due to
reduced delay for materials was estimated.
 A comparison of two projects with and without a materials management system
revealed a change in productivity from 1.92 man-hours per unit without a system
to 1.14 man-hours per unit with a new system. Again, much of this difference can
be attributed to the timely availability of materials.
 Warehouse costs were found to decrease 50% on one project with the introduction
of improved inventory management, representing a savings of $ 92,000. Interest
charges for inventory also declined, with one project reporting a cash flow
savings of $ 85,000 from improved materials management.

Against these various benefits, the costs of acquiring and maintaining a materials management
system has to be compared. However, management studies suggest that investment in such
systems can be quite beneficial.
Back to top

4.7 Material Procurement and Delivery


The main sources of information for feedback and control of material procurement are
requisitions, bids and quotations, purchase orders and subcontracts, shipping and receiving
documents, and invoices. For projects involving the large scale use of critical resources, the
owner may initiate the procurement procedure even before the selection of a constructor in order
to avoid shortages and delays. Under ordinary circumstances, the constructor will handle the
procurement to shop for materials with the best price/performance characteristics specified by
the designer. Some overlapping and rehandling in the procurement process is unavoidable, but it
should be minimized to insure timely delivery of the materials in good condition.

The materials for delivery to and from a construction site may be broadly classified as : (1) bulk
materials, (2) standard off-the-shelf materials, and (3) fabricated members or units. The process
of delivery, including transportation, field storage and installation will be different for these
classes of materials. The equipment needed to handle and haul these classes of materials will also
be different.

Bulk materials refer to materials in their natural or semi-processed state, such as earthwork to be
excavated, wet concrete mix, etc. which are usually encountered in large quantities in
construction. Some bulk materials such as earthwork or gravels may be measured in bank (solid
in situ) volume. Obviously, the quantities of materials for delivery may be substantially different
when expressed in different measures of volume, depending on the characteristics of such
materials.

Standard piping and valves are typical examples of standard off-the-shelf materials which are
used extensively in the chemical processing industry. Since standard off-the-shelf materials can
easily be stockpiled, the delivery process is relatively simple.

Fabricated members such as steel beams and columns for buildings are pre-processed in a shop
to simplify the field erection procedures. Welded or bolted connections are attached partially to
the members which are cut to precise dimensions for adequate fit. Similarly, steel tanks and
pressure vessels are often partly or fully fabricated before shipping to the field. In general, if the
work can be done in the shop where working conditions can better be controlled, it is advisable
to do so, provided that the fabricated members or units can be shipped to the construction site in
a satisfactory manner at a reasonable cost.

As a further step to simplify field assembly, an entire wall panel including plumbing and wiring
or even an entire room may be prefabricated and shipped to the site. While the field labor is
greatly reduced in such cases, "materials" for delivery are in fact manufactured products with
value added by another type of labor. With modern means of transporting construction materials
and fabricated units, the percentages of costs on direct labor and materials for a project may
change if more prefabricated units are introduced in the construction process.
In the construction industry, materials used by a specific craft are generally handled by
craftsmen, not by general labor. Thus, electricians handle electrical materials, pipefitters handle
pipe materials, etc. This multiple handling diverts scarce skilled craftsmen and contractor
supervision into activities which do not directly contribute to construction. Since contractors are
not normally in the freight business, they do not perform the tasks of freight delivery efficiently.
All these factors tend to exacerbate the problems of freight delivery for very large projects.

Example 4-5: Freight delivery for the Alaska Pipeline Project [7]

The freight delivery system for the Alaska pipeline project was set up to handle 600,000 tons of
materials and supplies. This tonnage did not include the pipes which comprised another 500,000
tons and were shipped through a different routing system.

The complexity of this delivery system is illustrated in Figure 4-2. The rectangular boxes denote
geographical locations. The points of origin represent plants and factories throughout the US and
elsewhere. Some of the materials went to a primary staging point in Seattle and some went
directly to Alaska. There were five ports of entry: Valdez, Anchorage, Whittier, Seward and
Prudhoe Bay. There was a secondary staging area in Fairbanks and the pipeline itself was
divided into six sections. Beyond the Yukon River, there was nothing available but a dirt road for
hauling. The amounts of freight in thousands of tons shipped to and from various locations are
indicated by the numbers near the network branches (with arrows showing the directions of
material flows) and the modes of transportation are noted above the branches. In each of the
locations, the contractor had supervision and construction labor to identify materials, unload
from transport, determine where the material was going, repackage if required to split shipments,
and then re-load material on outgoing transport.
Figure 4-2: Freight Delivery for the Alaska Pipeline Project

Example 4-6: Process plant equipment procurement [8]

The procurement and delivery of bulk materials items such as piping electrical and structural
elements involves a series of activities if such items are not standard and/or in stock. The times
required for various activities in the procurement of such items might be estimated to be as
follows:
Duration Cumulative
Activities
(days) Duration
Requisition ready by designer 0 0
Owner approval 5 5
Inquiry issued to vendors 3 8
Vendor quotations received 15 23
Complete bid evaluation by designer 7 30
Owner approval 5 35
Place purchase order 5 40
Receive preliminary shop drawings 10 50
Receive final design drawings 10 60
Fabrication and delivery 60-200 120-260

As a result, this type of equipment procurement will typically require four to nine months.
Slippage or contraction in this standard schedule is also possible, based on such factors as the
extent to which a fabricator is busy.

Back to top

4.8 Inventory Control


Once goods are purchased, they represent an inventory used during the construction process. The
general objective of inventory control is to minimize the total cost of keeping the inventory while
making tradeoffs among the major categories of costs: (1) purchase costs, (2) order cost, (3)
holding costs, and (4) unavailable cost. These cost categories are interrelated since reducing cost
in one category may increase cost in others. The costs in all categories generally are subject to
considerable uncertainty.

Purchase Costs

The purchase cost of an item is the unit purchase price from an external source including
transportation and freight costs. For construction materials, it is common to receive discounts for
bulk purchases, so the unit purchase cost declines as quantity increases. These reductions may
reflect manufacturers' marketing policies, economies of scale in the material production, or scale
economies in transportation. There are also advantages in having homogeneous materials. For
example, a bulk order to insure the same color or size of items such as bricks may be desirable.
Accordingly, it is usually desirable to make a limited number of large purchases for materials. In
some cases, organizations may consolidate small orders from a number of different projects to
capture such bulk discounts; this is a basic saving to be derived from a central purchasing office.

The cost of materials is based on prices obtained through effective bargaining. Unit prices of
materials depend on bargaining leverage, quantities and delivery time. Organizations with
potential for long-term purchase volume can command better bargaining leverage. While orders
in large quantities may result in lower unit prices, they may also increase holding costs and thus
cause problems in cash flow. Requirements of short delivery time can also adversely affect unit
prices. Furthermore, design characteristics which include items of odd sizes or shapes should be
avoided. Since such items normally are not available in the standard stockpile, purchasing them
causes higher prices.

The transportation costs are affected by shipment sizes and other factors. Shipment by the full
load of a carrier often reduces prices and assures quicker delivery, as the carrier can travel from
the origin to the destination of the full load without having to stop for delivering part of the cargo
at other stations. Avoiding transshipment is another consideration in reducing shipping cost.
While the reduction in shipping costs is a major objective, the requirements of delicate handling
of some items may favor a more expensive mode of transportation to avoid breakage and
replacement costs.

Order Cost

The order cost reflects the administrative expense of issuing a purchase order to an outside
supplier. Order costs include expenses of making requisitions, analyzing alternative vendors,
writing purchase orders, receiving materials, inspecting materials, checking on orders, and
maintaining records of the entire process. Order costs are usually only a small portion of total
costs for material management in construction projects, although ordering may require
substantial time.

Holding Costs

The holding costs or carrying costs are primarily the result of capital costs, handling, storage,
obsolescence, shrinkage and deterioration. Capital cost results from the opportunity cost or
financial expense of capital tied up in inventory. Once payment for goods is made, borrowing
costs are incurred or capital must be diverted from other productive uses. Consequently, a capital
carrying cost is incurred equal to the value of the inventory during a period multiplied by the
interest rate obtainable or paid during that period. Note that capital costs only accumulate when
payment for materials actually occurs; many organizations attempt to delay payments as long as
possible to minimize such costs. Handling and storage represent the movement and protection
charges incurred for materials. Storage costs also include the disruption caused to other project
activities by large inventories of materials that get in the way. Obsolescence is the risk that an
item will lose value because of changes in specifications. Shrinkage is the decrease in inventory
over time due to theft or loss. Deterioration reflects a change in material quality due to age or
environmental degradation. Many of these holding cost components are difficult to predict in
advance; a project manager knows only that there is some chance that specific categories of cost
will occur. In addition to these major categories of cost, there may be ancillary costs of
additional insurance, taxes (many states treat inventories as taxable property), or additional fire
hazards. As a general rule, holding costs will typically represent 20 to 40% of the average
inventory value over the course of a year; thus if the average material inventory on a project is $
1 million over a year, the holding cost might be expected to be $200,000 to $400,000.

Unavailability Cost
The unavailability cost is incurred when a desired material is not available at the desired time. In
manufacturing industries, this cost is often called the stockout or depletion cost. Shortages may
delay work, thereby wasting labor resources or delaying the completion of the entire project.
Again, it may be difficult to forecast in advance exactly when an item may be required or when
an shipment will be received. While the project schedule gives one estimate, deviations from the
schedule may occur during construction. Moreover, the cost associated with a shortage may also
be difficult to assess; if the material used for one activity is not available, it may be possible to
assign workers to other activities and, depending upon which activities are critical, the project
may not be delayed.

Back to top

4.9 Tradeoffs of Costs in Materials Management.


To illustrate the type of trade-offs encountered in materials management, suppose that a
particular item is to be ordered for a project. The amount of time required for processing the
order and shipping the item is uncertain. Consequently, the project manager must decide how
much lead time to provide in ordering the item. Ordering early and thereby providing a long lead
time will increase the chance that the item is available when needed, but it increases the costs of
inventory and the chance of spoilage on site.

Let T be the time for the delivery of a particular item, R be the time required for process the
order, and S be the shipping time. Then, the minimum amount of time for the delivery of the
item is T = R + S. In general, both R and S are random variables; hence T is also a random
variable. For the sake of simplicity, we shall consider only the case of instant processing for an
order, i.e. R = 0. Then, the delivery time T equals the shipping time S.

Since T is a random variable, the chance that an item will be delivered on day t is represented by
the probability p(t). Then, the probability that the item will be delivered on or before t day is
given by:

4.1

If a and b are the lower and upper bounds of possible delivery dates, the expected delivery time
is then given by:

4.2

The lead time L for ordering an item is the time period ahead of the delivery time, and will
depend on the tradeoff between holding costs and unavailability costs. A project manager may
want to avoid the unavailable cost by requiring delivery on the scheduled date of use, or may be
to lower the holding cost by adopting a more flexible lead time based on the expected delivery
time. For example, the manager may make the tradeoff by specifying the lead time to be D days
more than the expected delivery time, i.e.,

4.3

where D may vary from 0 to the number of additional days required to produce certain delivery
on the desired date.

In a more realistic situation, the project manager would also contend with the uncertainty of
exactly when the item might be required. Even if the item is scheduled for use on a particular
date, the work progress might vary so that the desired date would differ. In many cases, greater
than expected work progress may result in no savings because materials for future activities are
unavailable.

Example 4-7: : Lead time for ordering with no processing time.

Table 4-1 summarizes the probability of different delivery times for an item. In this table, the
first column lists the possible shipping times (ranging from 10 to 16 days), the second column
lists the probability or chance that this shipping time will occur and the third column summarizes
the chance that the item arrives on or before a particular date. This table can be used to indicate
the chance that the item will arrive on a desired date for different lead times. For example, if the
order is placed 12 days in advance of the desired date (so the lead time is 12 days), then there is a
15% chance that the item will arrive exactly on the desired day and a 35% chance that the item
will arrive on or before the desired date. Note that this implies that there is a 1 - 0.35 = 0.65 or
65% chance that the item will not arrive by the desired date with a lead time of 12 days. Given
the information in Table 4-1, when should the item order be placed?

Table 4-1 Delivery Date on Orders and Probability of


Delivery for an Example

Delivery Probability of Cummulative probability


Date delivery on date t of delivery by day t
t p(t) Pr{T t}

10 0.10 0.10
11 0.10 0.20
12 0.15 0.35
13 0.20 0.55
14 0.30 0.85
15 0.10 0.95
16 0.05 1.00
Suppose that the scheduled date of use for the item is in 16 days. To be completely certain to
have delivery by the desired day, the order should be placed 16 days in advance. However, the
expected delivery date with a 16 day lead time would be:

= (10)(0.1) + (11)(0.1) + (12)(0.15) + (13)(0.20) + (14)(0.30) + (15)(0.10) + (16)(0.05) = 13.0

Thus, the actual delivery date may be 16-13 = 3 days early, and this early delivery might involve
significant holding costs. A project manager might then decide to provide a lead time so that the
expected delivery date was equal to the desired assembly date as long as the availability of the
item was not critical. Alternatively, the project manager might negotiate a more certain delivery
date from the supplier.

Back to top

4.10 Construction Equipment


The selection of the appropriate type and size of construction equipment often affects the
required amount of time and effort and thus the job-site productivity of a project. It is therefore
important for site managers and construction planners to be familiar with the characteristics of
the major types of equipment most commonly used in construction. [9]

Excavation and Loading

One family of construction machines used for excavation is broadly classified as a crane-shovel
as indicated by the variety of machines in Figure 4-3. The crane-shovel consists of three major
components:

 a carrier or mounting which provides mobility and stability for the machine.
 a revolving deck or turntable which contains the power and control units.
 a front end attachment which serves the special functions in an operation.

The type of mounting for all machines in Figure 4-3 is referred to as crawler mounting, which is
particularly suitable for crawling over relatively rugged surfaces at a job site. Other types of
mounting include truck mounting and wheel mounting which provide greater mobility between
job sites, but require better surfaces for their operation. The revolving deck includes a cab to
house the person operating the mounting and/or the revolving deck. The types of front end
attachments in Figure 4-3 might include a crane with hook, claim shell, dragline, backhoe, shovel
and piledriver.
Figure 4-3 Typical Machines in the Crane-Shovel Family

A tractor consists of a crawler mounting and a non-revolving cab. When an earth moving blade
is attached to the front end of a tractor, the assembly is called a bulldozer. When a bucket is
attached to its front end, the assembly is known as a loader or bucket loader. There are different
types of loaders designed to handle most efficiently materials of different weights and moisture
contents.

Scrapers are multiple-units of tractor-truck and blade-bucket assemblies with various


combinations to facilitate the loading and hauling of earthwork. Major types of scrapers include
single engine two-axle or three axle scrapers, twin-engine all-wheel-drive scrapers, elevating
scrapers, and push-pull scrapers. Each type has different characteristics of rolling resistance,
maneuverability stability, and speed in operation.
Compaction and Grading

The function of compaction equipment is to produce higher density in soil mechanically. The
basic forces used in compaction are static weight, kneading, impact and vibration. The degree of
compaction that may be achieved depends on the properties of soil, its moisture content, the
thickness of the soil layer for compaction and the method of compaction. Some major types of
compaction equipment are shown in Figure 4-4, which includes rollers with different operating
characteristics.

The function of grading equipment is to bring the earthwork to the desired shape and elevation.
Major types of grading equipment include motor graders and grade trimmers. The former is an
all-purpose machine for grading and surface finishing, while the latter is used for heavy
construction because of its higher operating speed.
Figure 4-4 Some Major Types of Compaction Equipment

Drilling and Blasting

Rock excavation is an audacious task requiring special equipment and methods. The degree of
difficulty depends on physical characteristics of the rock type to be excavated, such as grain size,
planes of weakness, weathering, brittleness and hardness. The task of rock excavation includes
loosening, loading, hauling and compacting. The loosening operation is specialized for rock
excavation and is performed by drilling, blasting or ripping.

Major types of drilling equipment are percussion drills, rotary drills, and rotary-percussion drills.
A percussion drill penetrates and cuts rock by impact while it rotates without cutting on the
upstroke. Common types of percussion drills include a jackhammer which is hand-held and
others which are mounted on a fixed frame or on a wagon or crawl for mobility. A rotary drill
cuts by turning a bit against the rock surface. A rotary-percussion drill combines the two cutting
movements to provide a faster penetration in rock.

Blasting requires the use of explosives, the most common of which is dynamite. Generally,
electric blasting caps are connected in a circuit with insulated wires. Power sources may be
power lines or blasting machines designed for firing electric cap circuits. Also available are non-
electrical blasting systems which combine the precise timing and flexibility of electric blasting
and the safety of non-electrical detonation.

Tractor-mounted rippers are capable of penetrating and prying loose most rock types. The blade
or ripper is connected to an adjustable shank which controls the angle at the tip of the blade as it
is raised or lowered. Automated ripper control may be installed to control ripping depth and tip
angle.

In rock tunneling, special tunnel machines equipped with multiple cutter heads and capable of
excavating full diameter of the tunnel are now available. Their use has increasingly replaced the
traditional methods of drilling and blasting.

Lifting and Erecting

Derricks are commonly used to lift equipment of materials in industrial or building construction.
A derrick consists of a vertical mast and an inclined boom sprouting from the foot of the mast.
The mast is held in position by guys or stifflegs connected to a base while a topping lift links the
top of the mast and the top of the inclined boom. A hook in the road line hanging from the top of
the inclined boom is used to lift loads. Guy derricks may easily be moved from one floor to the
next in a building under construction while stiffleg derricks may be mounted on tracks for
movement within a work area.
Tower cranes are used to lift loads to great heights and to facilitate the erection of steel building
frames. Horizon boom type tower cranes are most common in highrise building construction.
Inclined boom type tower cranes are also used for erecting steel structures.

Mixing and Paving

Basic types of equipment for paving include machines for dispensing concrete and bituminous
materials for pavement surfaces. Concrete mixers may also be used to mix portland cement,
sand, gravel and water in batches for other types of construction other than paving.

A truck mixer refers to a concrete mixer mounted on a truck which is capable of transporting
ready mixed concrete from a central batch plant to construction sites. A paving mixer is a self
propelled concrete mixer equipped with a boom and a bucket to place concrete at any desired
point within a roadway. It can be used as a stationary mixer or used to supply slipform pavers
that are capable of spreading, consolidating and finishing a concrete slab without the use of
forms.

A bituminous distributor is a truck-mounted plant for generating liquid bituminous materials and
applying them to road surfaces through a spray bar connected to the end of the truck. Bituminous
materials include both asphalt and tar which have similar properties except that tar is not soluble
in petroleum products. While asphalt is most frequently used for road surfacing, tar is used when
the pavement is likely to be heavily exposed to petroleum spills.

Construction Tools and Other Equipment

Air compressors and pumps are widely used as the power sources for construction tools and
equipment. Common pneumatic construction tools include drills, hammers, grinders, saws,
wrenches, staple guns, sandblasting guns, and concrete vibrators. Pumps are used to supply water
or to dewater at construction sites and to provide water jets for some types of construction.

Automation of Equipment

The introduction of new mechanized equipment in construction has had a profound effect on the
cost and productivity of construction as well as the methods used for construction itself. An
exciting example of innovation in this regard is the introduction of computer microprocessors on
tools and equipment. As a result, the performance and activity of equipment can be continually
monitored and adjusted for improvement. In many cases, automation of at least part of the
construction process is possible and desirable. For example, wrenches that automatically monitor
the elongation of bolts and the applied torque can be programmed to achieve the best bolt
tightness. On grading projects, laser controlled scrapers can produce desired cuts faster and more
precisely than wholly manual methods. [10] Possibilities for automation and robotics in
construction are explored more fully in Chapter 16.

Example 4-8: Tunneling Equipment [11]


In the mid-1980's, some Japanese firms were successful in obtaining construction contracts for
tunneling in the United States by using new equipment and methods. For example, the Japanese
firm of Ohbayashi won the sewer contract in San Francisco because of its advanced tunneling
technology. When a tunnel is dug through soft earth, as in San Francisco, it must be maintained
at a few atmospheres of pressure to keep it from caving in. Workers must spend several hours in
a pressure chamber before entering the tunnel and several more in decompression afterwards.
They can stay inside for only three or four hours, always at considerable risk from cave-ins and
asphyxiation. Ohbayashi used the new Japanese "earth-pressure-balance" method, which
eliminates these problems. Whirling blades advance slowly, cutting the tunnel. The loose earth
temporarily remains behind to balance the pressure of the compact earth on all sides. Meanwhile,
prefabricated concrete segments are inserted and joined with waterproof seals to line the tunnel.
Then the loose earth is conveyed away. This new tunneling method enabled Ohbayashi to bid $5
million below the engineer's estimate for a San Francisco sewer. The firm completed the tunnel
three months ahead of schedule. In effect, an innovation involving new technology and method
led to considerable cost and time savings.

Back to top

4.11 Choice of Equipment and Standard Production Rates


Typically, construction equipment is used to perform essentially repetitive operations, and can be
broadly classified according to two basic functions: (1) operators such as cranes, graders, etc.
which stay within the confines of the construction site, and (2) haulers such as dump trucks,
ready mixed concrete truck, etc. which transport materials to and from the site. In both cases, the
cycle of a piece of equipment is a sequence of tasks which is repeated to produce a unit of
output. For example, the sequence of tasks for a crane might be to fit and install a wall panel (or
a package of eight wall panels) on the side of a building; similarly, the sequence of tasks of a
ready mixed concrete truck might be to load, haul and unload two cubic yards (or one truck load)
of fresh concrete.

In order to increase job-site productivity, it is beneficial to select equipment with proper


characteristics and a size most suitable for the work conditions at a construction site. In
excavation for building construction, for examples, factors that could affect the selection of
excavators include:

1. Size of the job: Larger volumes of excavation will require larger excavators, or smaller
excavators in greater number.
2. Activity time constraints: Shortage of time for excavation may force contractors to
increase the size or numbers of equipment for activities related to excavation.
3. Availability of equipment: Productivity of excavation activities will diminish if the
equipment used to perform them is available but not the most adequate.
4. Cost of transportation of equipment: This cost depends on the size of the job, the
distance of transportation, and the means of transportation.
5. Type of excavation: Principal types of excavation in building projects are cut and/or fill,
excavation massive, and excavation for the elements of foundation. The most adequate
equipment to perform one of these activities is not the most adequate to perform the
others.
6. Soil characteristics: The type and condition of the soil is important when choosing the
most adequate equipment since each piece of equipment has different outputs for
different soils. Moreover, one excavation pit could have different soils at different
stratums.
7. Geometric characteristics of elements to be excavated: Functional characteristics of
different types of equipment makes such considerations necessary.
8. Space constraints: The performance of equipment is influenced by the spatial limitations
for the movement of excavators.
9. Characteristics of haul units: The size of an excavator will depend on the haul units if
there is a constraint on the size and/or number of these units.
10. Location of dumping areas: The distance between the construction site and dumping
areas could be relevant not only for selecting the type and number of haulers, but also the
type of excavators.
11. Weather and temperature: Rain, snow and severe temperature conditions affect the
job-site productivity of labor and equipment.

By comparing various types of machines for excavation, for example, power shovels are
generally found to be the most suitable for excavating from a level surface and for attacking an
existing digging surface or one created by the power shovel; furthermore, they have the
capability of placing the excavated material directly onto the haulers. Another alternative is to
use bulldozers for excavation.

The choice of the type and size of haulers is based on the consideration that the number of
haulers selected must be capable of disposing of the excavated materials expeditiously. Factors
which affect this selection include:

1. Output of excavators: The size and characteristics of the excavators selected will
determine the output volume excavated per day.
2. Distance to dump site: Sometimes part of the excavated materials may be piled up in a
corner at the job-site for use as backfill.
3. Probable average speed: The average speed of the haulers to and from the dumping site
will determine the cycle time for each hauling trip.
4. Volume of excavated materials: The volume of excavated materials including the part
to be piled up should be hauled away as soon as possible.
5. Spatial and weight constraints: The size and weight of the haulers must be feasible at
the job site and over the route from the construction site to the dumping area.

Dump trucks are usually used as haulers for excavated materials as they can move freely with
relatively high speeds on city streets as well as on highways.

The cycle capacity C of a piece of equipment is defined as the number of output units per cycle
of operation under standard work conditions. The capacity is a function of the output units used
in the measurement as well as the size of the equipment and the material to be processed. The
cycle time T refers to units of time per cycle of operation. The standard production rate R of a
piece of construction equipment is defined as the number of output units per unit time. Hence:

4.4

or

4.5

The daily standard production rate Pe of an excavator can be obtained by multiplying its standard
production rate Re by the number of operating hours He per day. Thus:

4.6

where Ce and Te are cycle capacity (in units of volume) and cycle time (in hours) of the
excavator respectively.

In determining the daily standard production rate of a hauler, it is necessary to determine first the
cycle time from the distance D to a dump site and the average speed S of the hauler. Let Tt be the
travel time for the round trip to the dump site, To be the loading time and Td be the dumping
time. Then the travel time for the round trip is given by:

4.7

The loading time is related to the cycle time of the excavator Te and the relative capacities Ch
and Ce of the hauler and the excavator respectively. In the optimum or standard case:

4.8

For a given dumping time Td, the cycle time Th of the hauler is given by:

4.9

The daily standard production rate Ph of a hauler can be obtained by multiplying its standard
production rate Rh by the number of operating hours Hh per day. Hence:
4.10

This expression assumes that haulers begin loading as soon as they return from the dump site.

The number of haulers required is also of interest. Let w denote the swell factor of the soil such
that wPe denotes the daily volume of loose excavated materials resulting from the excavation
volume Pe. Then the approximate number of haulers required to dispose of the excavated
materials is given by:

4.11

While the standard production rate of a piece of equipment is based on "standard" or ideal
conditions, equipment productivities at job sites are influenced by actual work conditions and a
variety of inefficiencies and work stoppages. As one example, various factor adjustments can be
used to account in a approximate fashion for actual site conditions. If the conditions that lower
the standard production rate are denoted by n factors F1, F2, ..., Fn, each of which is smaller than
1, then the actual equipment productivity R' at the job site can be related to the standard
production rate R as follows:

4.12

On the other hand, the cycle time T' at the job site will be increased by these factors, reflecting
actual work conditions. If only these factors are involved, T' is related to the standard cycle time
T as:

4.13

Each of these various adjustment factors must be determined from experience or observation of
job sites. For example, a bulk composition factor is derived for bulk excavation in building
construction because the standard production rate for general bulk excavation is reduced when an
excavator is used to create a ramp to reach the bottom of the bulk and to open up a space in the
bulk to accommodate the hauler.

In addition to the problem of estimating the various factors, F1, F2, ..., Fn, it may also be
important to account for interactions among the factors and the exact influence of particular site
characteristics.

Example 4-9: Daily standard production rate of a power shovel [12]


A power shovel with a dipper of one cubic yard capacity has a standard operating cycle time of
30 seconds. Find the daily standard production rate of the shovel.

For Ce = 1 cu. yd., Te = 30 sec. and He = 8 hours, the daily standard production rate is found from
Eq. (4.6) as follows:

In practice, of course, this standard rate would be modified to reflect various production
inefficiencies, as described in Example 4-11.

Example 4-10: Daily standard production rate of a dump truck

A dump truck with a capacity of 6 cubic yards is used to dispose of excavated materials at a
dump site 4 miles away. The average speed of the dump truck is 30 mph and the dumping time is
30 seconds. Find the daily standard production rate of the truck. If a fleet of dump trucks of this
capacity is used to dispose of the excavated materials in Example 4-9 for 8 hours per day,
determine the number of trucks needed daily, assuming a swell factor of 1.1 for the soil.

The daily standard production rate of a dump truck can be obtained by using Equations (4.7)
through (4.10):

Hence, the daily hauler productivity is:


Finally, from Equation (4.12), the number of trucks required is:

implying that 8 trucks should be used.

Example 4-11: Job site productivity of a power shovel

A power shovel with a dipper of one cubic yard capacity (in Example 4-9) has a standard
production rate of 960 cubic yards for an 8-hour day. Determine the job site productivity and the
actual cycle time of this shovel under the work conditions at the site that affects its productivity
as shown below:

Work Conditions at the Site Factors


Bulk composition 0.954
Soil properties and water content 0.983
Equipment idle time for worker breaks 0.8
Management efficiency 0.7

Using Equation (4.11), the job site productivity of the power shovel per day is given by:

The actual cycle time can be determined as follows:

Noting Equation (4.6), the actual cycle time can also be obtained from the relation T'e =
(CeHe)/P'e. Thus:

Example 4-12: Job site productivity of a dump truck


A dump truck with a capacity of 6 cubic yards (in Example 4-10) is used to dispose of excavated
materials. The distance from the dump site is 4 miles and the average speed of the dump truck is
30 mph. The job site productivity of the power shovel per day (in Example 4-11) is 504 cubic
yards, which will be modified by a swell factor of 1.1. The only factors affecting the job site
productivity of the dump truck in addition to those affecting the power shovel are 0.80 for
equipment idle time and 0.70 for management efficiency. Determine the job site productivity of
the dump truck. If a fleet of such trucks is used to haul the excavated material, find the number
of trucks needed daily.

The actual cycle time T'h of the dump truck can be obtained by summing the actual times for
traveling, loading and dumping:

Hence, the actual cycle time is:

The jobsite productivity P'h of the dump truck per day is:

The number of trucks needed daily is:


so 8 trucks are required.

Back to top

4.12 Construction Processes


The previous sections described the primary inputs of labor, material and equipment to the
construction process. At varying levels of detail, a project manager must insure that these inputs
are effectively coordinated to achieve an efficient construction process. This coordination
involves both strategic decisions and tactical management in the field. For example, strategic
decisions about appropriate technologies or site layout are often made during the process of
construction planning. During the course of construction, foremen and site managers will make
decisions about work to be undertaken at particular times of the day based upon the availability
of the necessary resources of labor, materials and equipment. Without coordination among these
necessary inputs, the construction process will be inefficient or stop altogether.

Example 4-13: Steel erection

Erection of structural steel for buildings, bridges or other facilities is an example of a


construction process requiring considerable coordination. Fabricated steel pieces must arrive on
site in the correct order and quantity for the planned effort during a day. Crews of steelworkers
must be available to fit pieces together, bolt joints, and perform any necessary welding. Cranes
and crane operators may be required to lift fabricated components into place; other activities on a
job site may also be competing for use of particular cranes. Welding equipment, wrenches and
other hand tools must be readily available. Finally, ancillary materials such as bolts of the correct
size must be provided.

In coordinating a process such as steel erection, it is common to assign different tasks to specific
crews. For example, one crew may place members in place and insert a few bolts in joints in a
specific area. A following crew would be assigned to finish bolting, and a third crew might
perform necessary welds or attachment of brackets for items such as curtain walls.

With the required coordination among these resources, it is easy to see how poor management or
other problems can result in considerable inefficiency. For example, if a shipment of fabricated
steel is improperly prepared, the crews and equipment on site may have to wait for new
deliveries.

Example 4-14: Construction process simulation models

Computer based simulation of construction operations can be a useful although laborious tool in
analyzing the efficiency of particular processes or technologies. These tools tend to be either
oriented toward modeling resource processes or towards representation of spatial constraints and
resource movements. Later chapters will describe simulation in more detail, but a small example
of a construction operation model can be described here. [13] The process involved placing
concrete within existing formwork for the columns of a new structure. A crane-and-bucket
combination with one cubic yard capacity and a flexible "elephant trunk" was assumed for
placement. Concrete was delivered in trucks with a capacity of eight cubic yards. Because of site
constraints, only one truck could be moved into the delivery position at a time. Construction
workers and electric immersion-type concrete vibrators were also assumed for the process.

The simulation model of this process is illustrated in Figure 4-5. Node 2 signals the availability
of a concrete truck arriving from the batch plant. As with other circular nodes in Figure 4-5, the
availability of a truck may result in a resource waiting or queueing for use. If a truck (node 2)
and the crane (node 3) are both available, then the crane can load and hoist a bucket of concrete
(node 4). As with other rectangular nodes in the model, this operation will require an appreciable
period of time. On the completion of the load and hoist operations, the bucket (node 5) is
available for concrete placement. Placement is accomplished by having a worker guide the
bucket's elephant trunk between the concrete forms and having a second worker operate the
bucket release lever. A third laborer operates a vibrator in the concrete while the bucket (node 8)
moves back to receive a new load. Once the concrete placement is complete, the crew becomes
available to place a new bucket load (node 7). After two buckets are placed, then the column is
complete (node 9) and the equipment and crew can move to the next column (node 10). After the
movement to the new column is complete, placement in the new column can begin (node 11).
Finally, after a truck is emptied (nodes 12 and 13), the truck departs and a new truck can enter
the delivery stall (node 14) if one is waiting.
Figure 4-5: Illustration of a Concrete-Placing Simulation Model
Application of the simulation model consists of tracing through the time required for these
various operations. Events are also simulated such as the arrival times of concrete trucks. If
random elements are introduced, numerous simulations are required to estimate the actual
productivity and resource requirements of the process. For example, one simulation of this
process using four concrete trucks found that a truck was waiting 83% of the time with an
average wait at the site of 14 minutes. This type of simulation can be used to estimate the various
productivity adjustment factors described in the previous section.

Back to top

4.13 Queues and Resource Bottlenecks


A project manager needs to insure that resources required for and/or shared by numerous
activities are adequate. Problems in this area can be indicated in part by the existence of queues
of resource demands during construction operations. A queue can be a waiting line for service.
One can imagine a queue as an orderly line of customers waiting for a stationary server such as a
ticket seller. However, the demands for service might not be so neatly arranged. For example, we
can speak of the queue of welds on a building site waiting for inspection. In this case, demands
do not come to the server, but a roving inspector travels among the waiting service points.
Waiting for resources such as a particular piece of equipment or a particular individual is an
endemic problem on construction sites. If workers spend appreciable portions of time waiting for
particular tools, materials or an inspector, costs increase and productivity declines. Insuring
adequate resources to serve expected demands is an important problem during construction
planning and field management.

In general, there is a trade-off between waiting times and utilization of resources. Utilization is
the proportion of time a particular resource is in productive use. Higher amounts of resource
utilization will be beneficial as long as it does not impose undue costs on the entire operation.
For example, a welding inspector might have one hundred percent utilization, but workers
throughout the jobsite might be wasting inordinate time waiting for inspections. Providing
additional inspectors may be cost effective, even if they are not utilized at all times.

A few conceptual models of queueing systems may be helpful to construction planners in


considering the level of adequate resources to provide. First, we shall consider the case of time-
varying demands and a server with a constant service rate. This might be the situation for an
elevator in which large demands for transportation occur during the morning or at a shift change.
Second, we shall consider the situation of randomly arriving demands for service and constant
service rates. Finally, we shall consider briefly the problems involving multiple serving stations.

Single-Server with Deterministic Arrivals and Services

Suppose that the cumulative number of demands for service or "customers" at any time t is
known and equal to the value of the function A(t). These "customers" might be crane loads, weld
inspections, or any other defined group of items to be serviced. Suppose further that a single
server is available to handle these demands, such as a single crane or a single inspector. For this
model of queueing, we assume that the server can handle customers at some constant, maximum
rate denoted as x "customers" per unit of time. This is a maximum rate since the server may be
idle for periods of time if no customers are waiting. This system is deterministic in the sense that
both the arrival function and the service process are assumed to have no random or unknown
component.

Figure 4-6: Cumulative Arrivals and Departures in a Deterministic Queue

A cumulative arrival function of customers, A(t), is shown in Figure 4-6 in which the vertical
axis represents the cumulative number of customers, while the horizontal axis represents the
passage of time. The arrival of individual customers to the queue would actually represent a unit
step in the arrival function A(t), but these small steps are approximated by a continuous curve in
the figure. The rate of arrivals for a unit time interval t from t-1 to t is given by:

4.14

While an hour or a minute is a natural choice as a unit time interval, other time periods may also
be used as long as the passage of time is expressed as multiples of such time periods. For
instance, if half an hour is used as unit time interval for a process involving ten hours, then the
arrivals should be represented by 20 steps of half hour each. Hence, the unit time interval
between t-1 and t is t = t - (t-1) = 1, and the slope of the cumulative arrival function in the
interval is given by:
4.15

The cumulative number of customers served over time is represented by the cumulative
departure function D(t). While the maximum service rate is x per unit time, the actual service
rate for a unit time interval t from t-1 to t is:

4.16

The slope of the cumulative departure function is:

4.17

Any time that the rate of arrivals to the queue exceeds the maximum service rate, then a queue
begins to form and the cumulative departures will occur at the maximum service rate. The
cumulative departures from the queue will proceed at the maximum service rate of x "customers"
per unit of time, so that the slope of D(t) is x during this period. The cumulative departure
function D(t) can be readily constructed graphically by running a ruler with a slope of x along
the cumulative arrival function A(t). As soon as the function A(t) climbs above the ruler, a queue
begins to form. The maximum service rate will continue until the queue disappears, which is
represented by the convergence of the cumulative arrival and departure functions A(t) and D(t).

With the cumulative arrivals and cumulative departure functions represented graphically, a
variety of service indicators can be readily obtained as shown in Figure 4-6. Let A'(t) and D'(t)
denote the derivatives of A(t) and D(t) with respect to t, respectively. For 0 t ti in which
A'(t) x, there is no queue. At t = ti, when A'(t) > D'(t), a queue is formed. Then D'(t) = x in the
interval ti t tk. As A'(t) continues to increase with increasing t, the queue becomes longer
since the service rate D'(t) = x cannot catch up with the arrivals. However, when again A'(t)
D'(t) as t increases, the queue becomes shorter until it reaches 0 at t = tk. At any given time t, the
queue length is

4.18

For example, suppose a queue begins to form at time ti and is dispersed by time tk. The
maximum number of customers waiting or queue length is represented by the maximum
difference between the cumulative arrival and cumulative departure functions between ti and tk,
i.e. the maximum value of Q(t). The total waiting time for service is indicated by the total area
between the cumulative arrival and cumulative departure functions.
Generally, the arrival rates At = 1, 2, . . ., n periods of a process as well as the maximum
service rate x are known. Then the cumulative arrival function and the cumulative departure
function can be constructed systematically together with other pertinent quantities as follows:

1. Starting with the initial conditions D(t-1)=0 and Q(t-1)=0 at t=1, find the actual service rate at
t=1:

4.19

2. Starting with A(t-1)=0 at t=1, find the cumulative arrival function for t=2,3,. . .,n accordingly:

4.20

3. Compute the queue length for t=1,2, . . .,n.

4.21

4. Compute Dt for t=2,3,. . .,n after Q(t-1) is found first for each t:

4.22

5. If A'(t) > x, find the cumulative departure function in the time period between ti where a queue
is formed and tk where the queue dissipates:

4.23

6. Compute the waiting time w for the arrivals which are waiting for service in interval t:

4.24

7. Compute the total waiting time W over the time period between ti and tk.

4.25

8. Compute the average waiting time w for arrivals which are waiting for service in the process.
4.26

This simple, deterministic model has a number of implications for operations planning. First, an
increase in the maximum service rate will result in reductions in waiting time and the maximum
queue length. Such increases might be obtained by speeding up the service rate such as
introducing shorter inspection procedures or installing faster cranes on a site. Second, altering
the pattern of cumulative arrivals can result in changes in total waiting time and in the maximum
queue length. In particular, if the maximum arrival rate never exceeds the maximum service rate,
no queue will form, or if the arrival rate always exceeds the maximum service rate, the
bottleneck cannot be dispersed. Both cases are shown in Figure 4-7.

Figure 4-7: Cases of No Queue and Permanent Bottleneck

A practical means to alter the arrival function and obtain these benefits is to inaugurate a
reservation system for customers. Even without drawing a graph such as Figure 4-6, good
operations planners should consider the effects of different operation or service rates on the flow
of work. Clearly, service rates less than the expected arrival rate of work will result in resource
bottlenecks on a job.

Single-Server with Random Arrivals and Constant Service Rate

Suppose that arrivals of "customers" to a queue are not deterministic or known as in Figure 4-6.
In particular, suppose that "customers" such as joints are completed or crane loads arrive at
random intervals. What are the implications for the smooth flow of work? Unfortunately,
bottlenecks and queues may arise in this situation even if the maximum service rate is larger than
the average or expected arrival rate of customers. This occurs because random arrivals will often
bunch together, thereby temporarily exceeding the capacity of the system. While the average
arrival rate may not change over time, temporary resource shortages can occur in this
circumstance.

Let w be the average waiting time, a be the average arrival rate of customers, and x be the
deterministic constant service rate (in customers per unit of time). Then, the expected average
time for a customer in this situation is given by: [14]

4.27

If the average utilization rate of the service is defined as the ratio of the average arrival rate and
the constant service rate, i.e.,

4.28

Then, Eq. (4.27) becomes:

4.29

In this equation, the ratio u of arrival rate to service rate is very important: if the average arrival
rate approaches the service rate, the waiting time can be very long. If a x, then the queue
expands indefinitely. Resource bottlenecks will occur with random arrivals unless a measure of
extra service capacity is available to accommodate sudden bunches in the arrival stream. Figure
4-8 illustrates the waiting time resulting from different combinations of arrival rates and service
times.
Figure 4-8: Illustrative Waiting Times for Different Average Arrival Rates and Service Times

Multiple Servers

Both of the simple models of service performance described above are limited to single servers.
In operations planning, it is commonly the case that numerous operators are available and
numerous stages of operations exist. In these circumstances, a planner typically attempts to
match the service rates occurring at different stages in the process. For example, construction of
a high rise building involves a series of operations on each floor, including erection of structural
elements, pouring or assembling a floor, construction of walls, installation of HVAC (Heating,
ventilating and air conditioning) equipment, installation of plumbing and electric wiring, etc. A
smooth construction process would have each of these various activities occurring at different
floors at the same time without large time gaps between activities on any particular floor. Thus,
floors would be installed soon after erection of structural elements, walls would follow
subsequently, and so on. From the standpoint of a queueing system, the planning problem is to
insure that the productivity or service rate per floor of these different activities are approximately
equal, so that one crew is not continually waiting on the completion of a preceding activity or
interfering with a following activity. In the realm of manufacturing systems, creating this balance
among operations is called assembly line balancing.
Figure 4-9: Arrivals and Services of Crane Loads with a Crane Breakdown

Example 4-15: Effect of a crane breakdown

Suppose that loads for a crane are arriving at a steady rate of one every ten minutes. The crane
has the capacity to handle one load every five minutes. Suppose further that the crane breaks
down for ninety minutes. How many loads are delayed, what is the total delay, and how long will
be required before the crane can catch up with the backlog of loads?

The cumulative arrival and service functions are graphed in Figure 4-9. Starting with the
breakdown at time zero, nine loads arrive during the ninety minute repair time. From Figure 4-9,
an additional nine loads arrive before the entire queue is served. Algebraically, the required time
for service, t, can be calculated by noted that the number of arrivals must equal the number of
loads served. Thus:
A queue is formed at t = 0 because of the breakdown, but it dissipates at A(t) = D2(t). Let

from which we obtain t = 180 min. Hence

The total waiting time W can be calculated as the area between the cumulative arrival and
service functions in Figure 4-9. Algebraically, this is conveniently calculated as the difference in
the areas of two triangles:

so the average delay per load is w = 810/18 = 45 minutes.

Example 4-16: Waiting time with random arrivals

Suppose that material loads to be inspected arrive randomly but with an average of 5 arrivals per
hour. Each load requires ten minutes for an inspection, so an inspector can handle six loads per
hour. Inspections must be completed before the material can be unloaded from a truck. The cost
per hour of holding a material load in waiting is $30, representing the cost of a driver and a
truck. In this example, the arrival rate, a, equals 5 arrivals per hour and the service rate, x, equals
6 material loads per hour. Then, the average waiting time of any material load for u = 5/6 is:
At a resource cost of $30.00 per hour, this waiting would represent a cost of (30)(0.4)(5) =
$60.00 per hour on the project.

In contrast, if the possible service rate is x = 10 material loads per hour, then the expected
waiting time of any material load for u = 5/10 = 0.5 is:

which has only a cost of (30)(0.05)(5) = $7.50 per hour.

Example 4-17: Delay of lift loads on a building site

Suppose that a single crane is available on a building site and that each lift requires three minutes
including the time for attaching loads. Suppose further that the cumulative arrivals of lift loads at
different time periods are as follows:

8 per
6:00-7:00 A.M. 4 per hour 12:00-4:00 P.M.
hour
15 per 4 per
7:00-8:00 A.M. 4:00-6:00 P.M.
hour hour
25 per 6:00P.M.-6:00 0 per
8:00-11:00 A.M.
hour A.M. hour
11:00-12:00
5 per hour
A.M.

Using the above information of arrival and service rates

1. Find the cumulative arrivals and cumulative number of loads served as a function
of time, beginning with 6:00 AM.
2. Estimate the maximum queue length of loads waiting for service. What time does
the maximum queue occur?
3. Estimate the total waiting time for loads.
4. Graph the cumulative arrival and departure functions.

The maximum service rate x = 60 min/3 min per lift = 20 lifts per minute. The detailed
computation can be carried out in the Table 4-2, and the graph of A(t) and D(t) is given in Figure
4-10.
Table 4-2 Computation of queue length and waiting time

Cumulative Cumulative
Arrival arrivals Departure departures Waiting
Period rate A(T) Queue rate D(T) time

6-7:00 4 4 0 4 4 0
7-8:00 15 19 0 15 19 0
8-9:00 25 44 5 20 39 5
9-10:00 25 69 10 20 59 10
10-11:00 25 94 15 20 79 15
11-12:00 5 99 0 20 99 0
12-1:00 8 107 0 8 107 0
1-2:00 8 115 0 8 115 0
2-3:00 8 123 0 8 123 0
3-4:00 8 131 0 8 131 0
4-5:00 4 135 0 4 135 0
5-6:00 4 139 0 4 139 0
6-7:00 0 139 0 0 139 0
7-8:00 0 139 0 0 139 0
Total waiting time = 30
Maximum queue = 15
Figure 4-10: Delay of Lift Loads on a Building Site

Back to top

4.14 References
1. Bourdon, C.C., and R.W. Levitt, Union and Open Shop Construction, Lexington Books,
D.C. Heath and Co., Lexington, MA, 1980.
2. Caterpillar Performance Handbook, 18@+(th) Edition, Caterpillar, Inc., Peoria, IL,
1987.
3. Cordell, R.H., "Construction Productivity Management," Cost Engineering, Vol. 28, No.
2, February 1986, pp. 14-23.
4. Lange, J.E., and D.Q. Mills, The Construction Industry, Lexington Books, D.C. Heath
and Co., Lexington, MA, 1979.
5. Nunnally, S.W., Construction Methods and Management, Prentice-Hall, Englewoood
Cliffs, NJ, 2nd Ed., 1987.
6. Peurifoy, R.L., Construction Planning, Equipment and Methods, 2nd Edition, McGraw-
Hill, New York, 1970.
7. Tersine, R.J., Principles of Inventory and Materials Management, North Holland, New
York, 1982.

Back to top

4.15 Problems
1. Using the relationship between the productivity index and job size in Example 4-1,
determine the labor productivity for a new job requiring 350,000 labor hours under
otherwise the same set of work conditions.

2. The potential labor hours available for a large energy complex were found to be 5.4
million hours. The non-productive activities expressed in thousands of labor hours were:
1. 360 for holidays and strikes
2. 1,152 for absentees
3. 785 for temporary stoppage
4. 1,084 for indirect labor

Determine the productive labor yield after the above factors are taken into consideration.

3. Labor productivity at job site is known to decrease with overtime work. Let x be the
percentage of overtime over normal work week. If x is expressed in decimals, the
productivity index I as a function of the percentage of overtime is found to be:
4. Find the value of the index I for x = 0, 0.1, 0.2, 0.3, 0.4 and 0.5 and plot the relationship
in a graph.

5. Labor productivity for a complex project is known to increase gradually in the first
500,000 labor hours because of the learning effects. Let x be the number of 100,000 labor
hours. The labor productivity index I is found to be a function of x as follows:

6. Find the value of the index I for x = 0, 1, 2, 3, 4 and 5 and plot the relationship in a graph.

7. The probabilities for different delivery times of an item are given in the table below. Find
the expected delivery date of the item. Also find the lead time required to provide an
expected delivery date one day less than the desired delivery date.

t p(t) Pr{T t}

12 0.05 0.05
13 0.10 0.15
14 0.25 0.40
15 0.35 0.75
16 0.15 0.90
17 0.10 1.00

8. A power shovel with a dipper of two cubic yard capacity has a standard operating cycle
time of 80 seconds. The excavated material which has a swell factor of 1.05 will be
disposed by a dump truck with an 8 cubic yard capacity at a dump site 6 miles away. The
average speed of the dump truck is 30 mph and the dumping time is 40 seconds. Find the
daily standard production rates of the power shovel and the dump truck if both are
operated 8 hours per day. Determine also the number of trucks needed daily to dispose of
the excavated material.

9. The power shovel in Problem P6 has a daily standard production rate of 720 cubic yards.
Determine the job site productivity and the actual cycle time of this shovel under the
work conditions at the site that affect the productivity as shown below:
Work conditions at site Factors

Bulk composition 0.972


Soil properties and water content 0.960
Equipment idle time for breaks 0.750
Management inefficiency 0.750

10. Based on the information given for Problems P4-6 and P4-7, find the job site productivity
of a dump truck, assuming that the only factors affecting work conditions are 0.85 for
equipment idle time and 0.80 for management efficiency. Also find the number of dump
trucks required.

11. A Power shovel with a dipper of 1.5 cubic yard capacity has a standard operating cycle
time of 60 seconds. The excavated material which has a swell factor of 1.08 will be
disposed by a dump truck with a 7.5 cubic yard capacity at a dumpsite 5 miles away. The
average speed of a dump truck is 25 mph and the dumping time is 75 seconds. Both the
power shovel and the dump truck are operated 8 hours per day.
1. Find the daily standard production rate of the power shovel.
2. Find the daily standard production rate of the dump truck and number of trucks
required.
3. If the work conditions at the site that affect the productivity of the shovel can be
represented by four factors F1 = 0.940, F2 = 0.952, F3 = 0.850 and F4 = 0.750,
determine the job-site productivity and the actual cycle time.
4. If the work conditions at the site affect the productivity of the dump truck can be
represented by three factors F1 = 0.952, F2 = 0.700 and F3 = 0.750, determine the
job site productivity of the dump truck, and the number of dump trucks required.

12. Suppose that a single piece of equipment is available on a site for testing joints. Further,
suppose that each joint has to be tested and certified before work can proceed. Joints are
completed and ready for testing at random intervals during a shift. Each test requires an
average of ten minutes. What is the average utilization of the testing equipment and the
average wait of a completed joint for testing if the number of joints completed is (a) five
per hour or (b) three per hour.

13. Suppose that the steel plates to be inspected are arriving steadily at a rate of one every
twelve minutes. Each inspection requires sixteen minutes, but two inspectors are
available so the inspection service rate is one every eight minutes. Suppose one inspector
takes a break for sixty minutes. What is the resulting delay in the arriving pieces? What is
the average delay among the pieces that have to wait?

14. Suppose that three machines are available in a fabrication ship for testing welded joints of
structural members so that the testing service rate of the three machines is one in every 20
minutes. However, one of the three machines is shut down for 90 minutes when the
welded joints to be tested arrive at a rate of one in every 25 minutes. What is the total
delay for the testing service of the arriving joints? What is the average delay? Sketch the
cumulative arrivals and services versus time.

15. Solve Example 4-17 if each lift requires 5 minutes instead of 3 minutes.

16. Solve Example 4-17 if each lift requires 6 minutes instead of 3 minutes

17. Suppose that up to 12 customers can be served per hour in an automated inspection
process. What is the total waiting time and maximum queue with arrival rates for both
cases (a) and (b) below:

(a) (b)

6-7:00 am 0 0
7-8:00 25 10
8-9:00 25 10
9-10:00 am 25 15
10-11:00 am 25 15
11-12:00 am 10 10
12-1:00 pm 8 15
1-2:00 pm 0 15
2-3:00 pm 0 10
3-4:00 pm 0 10
4-5:00 pm 0 10
After 5 pm 0 0
Total number of arrivals 118 120

18. For the list of labor characteristic qualities in Section 4.3 (beginning with Quality of
Work and ending with Diversity), rate your own job performance on the three point scale
given.

Back to top

4.16 Footnotes
1. McCullough, David, The Path Between the Seas, Simon and Schuster, 1977, pg. 531. (Back)

2. Rosefielde, Steven and Daniel Quinn Mills, "Is Construction Technologically Stagnant?", in
Lange, Julian E. and Daniel Quinn Mills, The Construction Industry, Lexington Books, 1979, pg.
83. (Back)
3. This example was adapted with permission from an unpublished paper "Managing Mega
Projects" presented by G.R. Desnoyers at the Project Management Symposium sponsored by the
Exxon Research and Engineering Company, Florham Park, NJ, November 12, 1980. (Back)

4. See R.L. Tucker, "Perfection of the Buggy Whip," The Construction Advancement Address,
ASCE, Boston, MA, Oct. 29, 1986. (Back)

5. For more detailed discussion, see D.G. Mills: "Labor Relations and Collective Bargaining"
(Chapter 4) in The Construction Industry (by J.E. Lang and D.Q. Mills), Lexington Books, D.C.
Heath and Co., Lexington, MA, 1979. (Back)

6. This example was adapted from Stukhart, G. and Bell, L.C. "Costs and Benefits of Materials
Management Systems,", ASCE Journal of Construction Engineering and Management, Vol. 113,
No. 2, June 1987, pp. 222-234. (Back)

7. The information for this example was provided by Exxon Pipeline Company, Houston, Texas,
with permission from the Alyeska Pipeline Service Co., Anchorage, Alaska. (Back)

8. This example was adapted from A.E. Kerridge, "How to Develop a Project Schedule," in A.E.
Kerridge and C. H. Vervalin (eds.), Engineering and Construction Project Management, Gulf
Publishing Company, Houston, 1986. (Back)

9. For further details on equipment characteristics, see, for example, S.W. Nunnally,
Construction Methods and Management, Second Edition, Prentice-Hall, 1986 (Back)

10. See Paulson, C., "Automation and Robotics for Construction," ASCE Journal of Construction
Engineering and Management, Vol. 111, No. CO-3, 1985, pp. 190-207. (Back)

11. This example is adapted from Fred Moavenzadeh, "Construction's High-Technology


Revolution," Technology Review, October, 1985, pg. 32. (Back)

12. This and the following examples in this section have been adapted from E. Baracco-Miller
and C.T. Hendrickson, Planning for Construction, Technical Report No. R-87-162, Department
of Civil Engineering, Carnegie Mellon University, Pittsburgh, PA 1987. (Back)

13. This model used the INSIGHT simulation language and was described in B.C. Paulson, W.T.
Chan, and C.C. Koo, "Construction Operations Simulation by Microcomputer," ASCE Journal of
Construction Engineering and Management, Vol. 113, No. CO-2, June 1987, pp. 302-314.
(Back)

14. In the literature of queueing theory, this formula represents an M/D/1 queue, meaning that
the arrival process is Markovian or random, the service time is fixed, only one server exists, and
the system is in "steady state," implying that the service time and average arrival rate are
constant. Altering these assumptions would require changes in the waiting time formula; for
example, if service times were also random, the waiting time formula would not have the 2
shown in the denominator of Eq. (4.27). For more details on queueing systems, see Newell, G.F.
Applications of Queueing Theory, Chapman and Hall, London, 1982. (Back)

Previous Chapter | Table of Contents | Next Chapter

You might also like