SOP Biogas Clean 41188

Download as pdf or txt
Download as pdf or txt
You are on page 1of 20

BIOGASCLEAN A/S ASIA

Training
Why is desulphurization needed?
Gas Boiler Gas Engine Gas flare

H2S(g) Convert to SO2(g)

Tube Piston Stack

Low
Machine’s
Expensive
breakdown
> 200-250 PPM, No
more engine
warranty
Waste
life time Pollutions money
What is it in the BiogasCleaner?

Thiobacillus family
CH4+CO2+

CH4+CO2+
H2S
> 3500ppm
H2S < 100ppm
+etc.
+etc.

2 HS- + 4 O2 2 SO42- + 2 H+
Thiobacillus family
What does the bacteria in the process need?

H2S
(Biogas)
Moisture NPK
Temperature
35-55 C

closed acid-proof tank


Spray nozzle
Thiobacillus family

O2
Packing Media
(atmospheric air)
How is this provided?

Biogas flow
signal passing
BC tank LEL Cabinet

O2 signal
after Input Output
PLC
BC tank

Temp Sensor

HMI

Air flow meter Water flow meter


-10 mBar to +100 mBar

Tank

Fill up treated
digested effluent

PTU
Effluent
MUW tanks Storage
tank

High level

Low level

Effluent
Pump
Drain
Drain Gutter
Gas - 10 mBar to +100 mBar

inlet
Tank
O2

• Water circulating phase


• O2 adding phase
• Effluent water adding phase
• Chemical Pre-treatment(MUW) phase
• Drain at high level

PTU Gas
outlet Effluent
MUW tanks Storage
tank
O2
Air
High level
Circulating blower
Low level
pump
SO42- MgSO4, CaSO4 MgSO4, CaSO4
Effluent
Pump
Auto drain Gutter
Keep a good record of your operation!
• Daily check
• Weekly check
• 3 month service
• 1 year service
• 3 year service
• 5 year service
Daily check
Parameters (Read in display) Morning Noon Evening
GAS FLOW m3h
AIRFLOW m3h
GEN SET O2%
LIQUIDTEMP C
AIR INJECT m3h
AIR INJECT %
AMOUNT WATER m3
AMOUNT EFFLUENT m3
AMOUNT DRAIN m3
Active Alarms on PLC
Parameters Point Morning Noon Evening
pH on liquid in BC Tank

H2S before gas cleaner, make measurement


H2S after gas cleaner, make measurement
Air flow (l/h) meter at air blower (visual
inspection)

Liquid flow (m3/h) meter at


circulation/drain pump (visual inspection)

Has the BiogasCleaner been stopped in the


last 24 hours?
After handing over / commissioning
Weekly service
Activities Point Completed
Check/clean the filter for the circulation / drain pump
Check/clean the filter for the liquid supply
Check the water level
Check the adding of liquid function by using the force option
in the display
Water filter and Air filter cleaning

Air filter
Water filter
3 Month service
Activities Completed
Analyze the raw water/effluent as per the chapter "Maintenance" in
the manual
Check the pressure/relief valve
Stop the BiogasCleaner in order to inspect the packing media
Follow local regulations and the instructions in the manual regarding
safety
Open the lower manhole and make visual inspection of the packing
media
Take pictures of the packing media - See manual page 29
3 Month service

QSR cleaning

1-2 mm. of biofilm and minor sludge deposits. Heavily clogged packing
6 Month service
Activities Completed
Perform 3 month service and +
Perform QSR cleaning
Check the pumps and the blowers for wear
Calibrate the installed probes - follow instructions from the suppliers

9 Month service
Activities Completed
Perform 3 month service

1 year service
Activities Completed
Perform 6 month service and +
Perform QSR cleaning
3 year service
Activities Completed
Change the battery in the PLC

5 year service
Activities Completed
Perform QSR cleaning
Full tank inspection including removal of packing media from the tank
Why QSR?

The packing media is heavily The packing media is


coated. compressed
QSR at least 1 year a time
QSR tools

Water or Air Compressed Check valve Cooking oil 3-4Long ½”


Effluent compressor air header and hose pipes with
water Use as fitting.
6-8,000 l/ m antifoam
2-4 times of 6-8 Bar Length=
tank tank
volume, height+1m
depending
on sludge
forming.
QSR cleaning result

Before After
Thanks' for your attention !