UFGS 32 12 15.13 Asphalt Paving For Airfields
UFGS 32 12 15.13 Asphalt Paving For Airfields
UFGS 32 12 15.13 Asphalt Paving For Airfields
------------------------------------
Preparing Activity: USACE Superseding
UFGS-32 12 15.13 (November 2017)
SECTION 32 12 15.13
11/20
PART 1 GENERAL
PART 2 PRODUCTS
PART 3 EXECUTION
------------------------------------
Preparing Activity: USACE Superseding
UFGS-32 12 15.13 (November 2017)
SECTION 32 12 15.13
**************************************************************************
NOTE: This guide specification covers the
requirements for bituminous intermediate and wearing
courses (central-plant hot-mix and warm-mix) for
airfields using Marshall or Gyratory compaction
method.
PART 1 GENERAL
**************************************************************************
NOTE: Modifications must be made within bracketed
items to this guide specification during conversion
to a project specification in accordance with the
NOTES which are located throughout the document.
These NOTES are instructions to the designer, and
will not appear in the project specification.
**************************************************************************
NOTE: For unit-price contracts, include first
bracketed statements and delete the second set. For
lump sum contracts, delete the first bracketed
statements and include the second set.
[The amount paid for will be the number of metric tons of hot-mixwarm-mix
asphalt pavement mixture used in the accepted work. Hot-mixWarm-mix
asphalt pavement mixture shall be weighed after mixing. No separate
payment will be made for weight of asphalt binder material incorporated
herein.] [Utilize the quantity of hot-mixwarm-mix asphalt pavement, per
ton placed and accepted, for the purposes of assessing the pay factors
stipulated below.]
**************************************************************************
NOTE: For unit-price contracts, include first
bracketed statements and delete the second set. For
lump sum contracts, delete the first bracketed
statements and include the second set. Include
**************************************************************************
NOTE: The basis of pay testing includes material
tests to determine laboratory air voids, in-place
density, smoothness and plan grade which are needed
to determine percent payment.
**************************************************************************
The average in-place mat and joint densities are expressed as a percentage
of the average theoretical maximum density (TMD) for the lot. The average
TMD for each lot will be determined as the average TMD of the four random
samples per lot. The average in-place mat density and joint density for a
lot are determined and compared with Table 1 to calculate a single pay
factor per lot based on in-place density, as described below. All density
results for a lot will be completed and reported within 24 hours after the
construction of that lot. Use the following process to determine the
single pay factor for in-place density:
a. Step 1: Determine the pay factors for mat density and joint density
c. Step 3: Compute the weighted pay factor for the joint using the
formula in the example shown in paragraph PAY FACTOR BASED ON IN-PLACE
DENSITY.
e. Step 5: Compare weighted pay factor for joint density to pay factor
for mat density and select the lowest. This selected pay factor is
the pay factor based on density for the lot. When the TMD on both
sides of a longitudinal joint is different, the average of these two
TMD will be used as the TMD needed to calculate the percent joint
density.
When 0 percent payment is determined for mat density, remove and replace
the rejected lot at least 100 mm 4 inches into the cold lane adjacent to
the longitudinal joint. When 0 percent payment is determined for joint
density, remove and replace the rejected longitudinal joint with a 3 m 10
feet wide paving lane that is centered over the joint.
Table 1
Pay Factor Based on In-place Density
Average Mat Density (4 Pay Factor, percent Average Joint Density (4
cores) (Percent of TMD) cores)(Percent of TMD)
An example of the computation of a pay factor (in I-P units only) based on
in-place density, is as follows: Assume the following test results for
field density made on the lot: (1) Average mat density = 93.2 percent (of
lab TMD). (2) Average joint density = 91.5 percent (of lab TMD). (3)
Total area of lot = 30,000 square feet. (4) Length of completed
longitudinal construction joint = 2,000 feet.
wpf = joint pay factor + (100 - joint pay factor) (1 - ratio) wpf =
97.3 + (100-97.3) (1-0.6667) = 98.2 percent
d. Step 4: Compare weighted pay factor for joint density to pay factor
for mat density and select the smaller:
Pay factor for mat density: 98.3 percent. Weighted pay factor for
joint density: 98.2 percent
Select the smaller of the two values as pay factor based on density:
98.2 percent
**************************************************************************
NOTE: When Profilograph testing is not required,
delete the following paragraph for pay adjustment
for smoothness. This paragraph may be deleted for
projects where a profilograph cannot record 161
meters 0.10 of a mile in length. Profilograph
testing is required for runways and applicable
taxiway and landing zone pavements.
**************************************************************************
Test the entire lot in the longitudinal direction per ASTM E1274. Perform
the longitudinal testing at the centerline of each paving lot and 1/8th
point from each side of the lot. Record the location and data from all
profilograph measurements. Compute the profile index for each pass of the
profilograph (3 per lot) in each 0.1 km0.1 mile segment. The profile index
for each segment is the average of the profile indices for each pass in
each segment. When the average Profile Indices of a lot exceeds the
tolerance specified in paragraph SMOOTHNESS REQUIREMENTS determine pay
factor using Table 2. Correct any small individual area with surface
deviation which exceeds the tolerance specified in paragraph SMOOTHNESS
REQUIREMENTS by more than 79 mm per km 5.0 inches per mile or more, by
grinding to meet the specification requirements in Table 2 or remove and
replace at no additional cost to the Government.
Table 2
Pay Factor for Smoothness
Average of Profile Indices Exceeding Pay Factor, Percent
Tolerance (per lot)
less than or equal to 16 mm km1.0 inch 100.0
per mile
Mean Absolute Deviation = (|3.5 - 4.0| + |3.0 - 4.0| + |4.0 - 4.0| + |3.7
- 4.0|)/4
Table 3
Pay Factor Based on Laboratory Air Voids
Mean Absolute Deviation of Lab Air Voids from JMF Pay Factor, Percent
Mean Absolute Deviation of Lab Air Voids from JMF Pay Factor, Percent
0.61 - 0.80 98
0.81 - 1.00 95
1.01 - 1.20 90
Above 1.20 reject (0)
**************************************************************************
NOTE: The plan grade requirements specified below
are for the final wearing surface only. If there is
a requirement to test and control the grade and
smoothness for the intermediate courses, for
example, when the intermediate courses will be
exposed to traffic, slight modifications to this
specification will be required.
**************************************************************************
Table 4
Pay Factor for Plan Grade
1.3 REFERENCES
**************************************************************************
NOTE: This paragraph is used to list the
publications cited in the text of the guide
specification. The publications are referred to in
the text by basic designation only and listed in
this paragraph by organization, designation, date,
and title.
1.4 SUBMITTALS
**************************************************************************
NOTE: Review submittal description (SD) definitions
in Section 01 33 00 SUBMITTAL PROCEDURES and edit
the following list, and corresponding submittal
items in the text, to reflect only the submittals
required for the project. The Guide Specification
technical editors have classified those items that
require Government approval, due to their complexity
or criticality, with a "G." Generally, other
submittal items can be reviewed by the Contractor's
Quality Control System. Only add a “G” to an item,
if the submittal is sufficiently important or
complex in context of the project.
SD-04 Samples
Aggregates
Asphalt Binder
Warm-mix Additive
QC Monitoring
SD-07 Certificates
Testing Laboratory
Warm-mix Additive
**************************************************************************
NOTE: The airfield asphalt certification program is
intended to increase quality of construction for
work performed under this specification. The
certification program will provide knowledge to the
project team members as it relates to airfield
asphalt. Intended audience is the Contractor and
Government personnel. The below paragraph should be
modified or the general provisions of the contract
should be modified to require Title II inspectors or
third party laboratory firms attend the
certification program.
**************************************************************************
(1)
: Registration for the Airfield Asphalt Pavement Certification Program
can be found at www.airfieldasphaltcert.com.
1.6 ACCEPTANCE
**************************************************************************
NOTE: It is recommended that an independent
material testing firm be hired by the Contractor to
provide the acceptance testing for the project. It
is also recommended to keep the Government QA
acceptance testing separate and distinct from the
Contractor's QC testing for all airfield projects.
Provide all sampling and testing required for acceptance and payment
adjustment. Where appropriate, adjustments in payment for individual lots
of asphalt pavement will be made based on laboratory air voids, in-place
density, smoothness, and grade in accordance with the following
paragraphs. Surface smoothness and grade determinations will be made on
the lot as a whole. Exceptions or adjustments to this will be made in
situations where the mix within one lot is placed as part of both the
intermediate and surface courses, thus smoothness and grade measurements
for the entire lot cannot be made.
Obtain one random mixture sample from each sublot in accordance with
ASTM D979/D979M from a loaded truck or another approved location for
determining laboratory air voids, theoretical maximum density, Contractor
Quality Control, and for any additional testing as directed the
Government. Representative samples will be selected from random trucks,
using commonly recognized methods of assuring randomness conforming to
ASTM D3665 and employing tables of random numbers or computer programs.
Laboratory air voids will be determined from three laboratory compacted
specimens of each sublot sample in accordance with ASTM D3203/D3203M. The
specimens will be compacted within 2 hours of the time the mixture was
loaded into trucks at the asphalt plant. Samples will not be reheated
prior to compaction and insulated containers will be used as necessary to
maintain the temperature.
The Government reserves the right to direct additional samples and tests
for any area which appears to deviate from the specification
requirements. The cost of any additional testing will be paid for by the
Contractor. Testing in these areas will be treated as a separate lot.
Measure theoretical maximum density one time for each sublot in accordance
with ASTM D2041/D2041M for purposes of calculating laboratory air voids
and determining in-place density. The average TMD for each lot will be
determined as the average TMD of the random sublot samples. When the TMD
on both sides of a longitudinal joint is different, the average of these
two TMD values will be used as the TMD needed to calculate the percent
joint density.
**************************************************************************
NOTE: Select the appropriate tailoring option for
the Marshall or Superpave Methods.
**************************************************************************
Obtain one random 100 mm 4 inch or 150 mm 6 inch diameter core from the
mat and joint of each sublot in accordance with ASTM D5361/D5361M for
determining in-place density. Where different job mix formulas are
required as part of the same project, and are adjacent to one another,
follow the same joint density sampling and joint density testing
instructions of this specification. Cut samples neatly with a diamond core
drill bit. Obtain random cores that are the full thickness of the layer
being placed. Select core locations randomly using the procedures
contained in ASTM D3665. Locate cores for mat density no closer than 300
mm 12 inches from a transverse or longitudinal joint including the
pavement edge. Center all cores for joint density on the joint. Discard
samples that are clearly defective as a result of sampling and take an
additional random core. When the random core is less than 25 mm 1 inch
thick, it will not be included in the analysis. In this case, obtain
another random core sample. Clean and tack coat dry core holes before
filling with asphalt mixture. Fill all core holes with asphalt mixture
and compact using a manual (hand-held) Marshall hammer to the density
specified. Provide all tools, labor, and materials for cutting samples,
cleaning, and filling the cored pavement. Measure in-place density in
accordance with ASTM D2726/D2726M using each core obtained from the mat
and joint.
Table 5
Straightedge Surface Smoothness--Pavements
Pavement Category Direction of Testing Tolerance, mm inch
After the final rolling, but not later than 24 hours after placement, test
the surface of the pavement in each entire lot in a manner to reveal
surface irregularities exceeding the tolerances specified above. If any
pavement areas are diamond ground, retest these areas immediately after
Reduce any bumps ("must grind" areas) shown on the profilograph trace
which exceed 10 mm 0.4 inch in height by diamond grinding until they do
not exceed 7.5 mm 0.3 inch when retested. Taper diamond grinding in all
directions to provide smooth transitions to areas not requiring diamond
grinding. The following will not be permitted: (1) skin patching for
correcting low areas, (2) planing or milling for correcting high areas. [
At the Contractor's option, pavement areas, including diamond ground
areas, can be rechecked with the profilograph in order to record a lower
Profile Index.][ Perform additional profilograph testing in all areas
corrected by diamond grinding.]
1.6.10 Plan Grade
**************************************************************************
NOTE: For Army managed projects, keep the bracketed
text. For Air Force, and Navy, managed projects,
utilization of the USACE Materials Testing Center
(MTC) Validated Laboratory is optional.
**************************************************************************
Provide laboratories used to develop the Job Mix Formula (JMF), perform
acceptance testing, and Contractor Quality Control testing that meet the
requirements of ASTM D3666. Provide laboratories with a masonry saw having
a diamond blade for trimming pavement cores and samples. Perform all
required test methods by an accredited [and validated] laboratory.
Schedule and provide payment for laboratory inspections. Additional
payment or a time extension due to failure to acquire the required
laboratory accreditation is not allowed. The Government will inspect the
laboratory equipment and test procedures prior to the start of asphalt
pavement operations for conformance with ASTM D3666. [In addition, all
testing laboratories performing JMF, acceptance testing and Contractor
Quality Control requires USACE validation by the Material Testing Center
(MTC) for both parent laboratory and plant testing laboratory. Validation
on all laboratories is required to remain current throughout the duration
of the paving project. Contact the MTC manager listed at
https://mtc.erdc.dren.mil/ for costs and scheduling.] Submit a
certificate of compliance signed by the manager of the laboratory stating
that it meets these requirements to the Government prior to the start of
construction. At a minimum, include the following certifications:
**************************************************************************
NOTE: The temperature requirements in Table 6 are
included to avoid problems with the Contractor
achieving density because the mix cools too fast.
Waivers to these requirements, for isolated
incidences during production, are applicable if the
density requirements are still met.
**************************************************************************
Do not place asphalt pavement upon a wet surface or when the surface
temperature of the underlying course is less than specified in Table 6.
The temperature requirements may be waived by the Government, if
requested; provided all other requirements, including compaction, are met.
75 3 or greater 440
PART 2 PRODUCTS
Provide access to the Government at all times, to all areas of the plant
for checking adequacy of equipment; inspecting operation of the plant;
verifying weights, proportions, and material properties; checking the
temperatures maintained in the preparation of the mixtures and for taking
samples. Provide assistance as requested, for the Government to procure
any desired samples.
Provide trucks used for hauling asphalt mixture that have tight, clean,
and smooth metal beds. To prevent the mixture from adhering to them,
lightly coat the truck beds with a minimum amount of paraffin oil, lime
solution, or other approved material. Do not use petroleum based products
as a release agent. Provide each truck with a suitable cover to protect
the mixture from adverse weather. When necessary to ensure that the
mixture is delivered to the site at the specified temperature, provide
insulated or heated truck beds with covers (tarps) that are securely
fastened.
**************************************************************************
NOTE: A Material Transfer Vehicle (MTV) is required
for runway, taxiway, landing zone and apron
construction. The use of an MTV is optional for
shoulder construction.
**************************************************************************
**************************************************************************
NOTE: Delete information on automatic grade control
if not needed. Automatic grade control is needed
when the design requires elevations for the asphalt
pavement surface. Many maintenance and
rehabilitation projects require an overlay thickness
and do not specify actual grades.
**************************************************************************
d. Laser control.
2.1.5 Rollers
2.2 AGGREGATES
**************************************************************************
For Design-Bid-Build projects, select the first
bracketed text. For Design-Build projects, select
the second bracketed text..
**************************************************************************
**************************************************************************
NOTE: The requirement for sulfate soundness
(requirement b., below) may be deleted in climates
where freeze-thaw does not occur. However, in those
areas where freeze-thaw does not occur, requirement
b. must remain if experience has shown that this
test separates good performing aggregates from bad
performing aggregates. Retain this requirement for
all Navy projects.
a. The percentage of loss not greater than 40 [_____] percent after 500
revolutions when tested in accordance with ASTM C131/C131M.
f. Clay lumps and friable particles not exceeding 0.3 percent, by weight,
when tested in accordance with ASTM C142/C142M.
**************************************************************************
NOTE: Set the lower limit for uncompacted void
content (requirement c., below) at 45 for fine
aggregate angularity unless local experiences
indicate that a lower value can be used. There are
some aggregates which have a good performance record
and have an uncompacted void content less than 45.
In no case set the limit at less than 43.
**************************************************************************
d. Clay lumps and friable particles not exceeding 0.3 percent, by weight,
when tested in accordance with ASTM C142/C142M.
**************************************************************************
NOTE: Delete from Table 7, the gradations that will
not be used as a part of this project.
Table 7
Aggregate Gradations
**************************************************************************
NOTE: Specify Performance Graded (PG) asphalt
binders wherever available. Consider using the same
grade PG binder used by the state highway department
in the area as the base grade for the project (for
example, the grade typically specified in that
specific location for dense graded mixes on highways
Provide asphalt binder that conforms to ASTM D6373 for Performance Grade
(PG) [_____][Provide asphalt binder that conforms to ASTM D946/D946M
Penetration Grade [_____]][Provide asphalt binder that conforms to
ASTM D3381/D3381M Viscosity Grade [_____]]. Provide test data indicating
grade certification by the supplier at the time of delivery of each load
to the mix plant. [For modified binders, perform PG Plus test requirements
in ASTM D6084/D6084M Procedure B on RTFO aged binder, with a minimum
elastic recovery of [_____].] When warm-mix asphalt technology involves
additives, the asphalt binder shall be graded with the asphalt binder
additive included. Submit copies of these certifications to the
Government. The supplier is defined as the last source of any modification
to the binder. The Government may sample and test the binder at the mix
plant at any time before or during mix production. [Obtain samples for
this verification testing in accordance with ASTM D140/D140M and in the
presence of the Government. Provide these samples to the Government for
the verification testing, which will be performed at the Governments
expense. Submit 20 L 5 gallon sample of the asphalt binder specified for
mix design verification and approval not less than 14 days before start of
the test section.]
**************************************************************************
NOTE: Use 75 blow Marshall hand-held hammer
compaction or 75 gyration Superpave gyratory
compaction for all pavements designed for tire
pressures of 690 kPa 100 psi or higher.
Develop the mix design and provide results of the Job Mix formula (JMF)
and aggregates testing performed no earlier than 6 months prior to
contract award. Provide asphalt mixture composed of well-graded
aggregate, mineral filler if required, and asphalt material. Provide
aggregate fractions sized, handled in separate size groups, and combined
in such proportions that the resulting mixture meets the grading
requirements of Table 7. Do not produce asphalt pavement for payment
until a JMF has been approved. Design the asphalt mixture using hand-held
(manual) Marshall hammer procedures contained in AI MS-2 and the criteria
shown in Table 8. Mechanical hammers are not permitted during JMF
development. Design the asphalt mixture using the Superpave gyratory
compactor set at [50] [75] gyrations using the procedures contained in AI
MS-2 and the criteria shown in Table 8. Prepare samples at various asphalt
contents and compacted in accordance with ASTM D6925ASTM D6926. Use
laboratory compaction temperatures for Polymer Modified Asphalts as
recommended by the asphalt binder supplier. For tensile strength ratio
(TSR) testing, adjust the compactive effort, as required, to provide
specimens with an air void content of 7 plus or minus 1 percent. [Use
freeze/thaw conditioning in lieu of moisture conditioning per Note 6 of
ASTM D4867/D4867M. If freeze/thaw conditioning is used, include that fact
on the report.] If the Tensile Strength Ratio (TSR) of the composite
mixture, as determined by ASTM D4867/D4867M is less than 75, reject the
Submit the proposed JMF in writing, for approval, at least 14 days prior
to the start of the test section, including as a minimum:
u. Date the JMF was developed. Mix designs that are not dated or which
are from a prior construction season may not be accepted.
v. Warm-mix additive.
Table 8
Marshall Design Criteria
(2) The flow requirement is not applicable for Polymer Modified Asphalts
Table 8
Superpave Gyratory Compaction Criteria
Test Property Value
Table 9
Minimum Percent Voids in Mineral Aggregate (VMA)(1)
Gradation 1 13
Gradation 2 14
Gradation 3 15
(1) Calculate VMA in accordance with AI MS-2, based on ASTM C127 and ASTM C128
bulk specific gravity for the aggregate.
The JMF for each mixture is in effect until a new formula is approved in
writing by the Government. Should a change in sources of any materials be
made, perform a new mix design and a new JMF approved before the new
material is used. Make minor adjustments within the specification limits
to the JMF to optimize mix volumetric properties. Adjustments to the
original JMF are limited to plus or minus 4 percent on the 4.75 mm No. 4
and coarser sieves; plus or minus 3 percent on the 2.36 mm No. 8 to 0.30 mm
No. 50 sieves; and plus or minus 1 percent on the 0.15 mm No. 100 sieve.
Adjustments to the JMF are limited to plus or minus 1.0 percent on the
0.075 mm No. 200 sieve. Asphalt content adjustments are limited to plus
or minus 0.40 from the original JMF. If adjustments are needed that
exceed these limits, develop a new mix design.
**************************************************************************
NOTE: Do not use Reclaimed Asphalt Pavement (RAP)
for surface mixes, except on shoulders. It can be
used very effectively in lower layers, or for
shoulders. Limit the amount of RAP so the asphalt
binder from the RAP does not exceed 20 percent of
the total asphalt content. Remove these paragraphs
if RAP is not used.
Provide a blend of aggregates used in the reclaimed mix that meet the
requirements of paragraph AGGREGATES. Establish the percentage of asphalt
in the RAP for the mixture design according to ASTM D2172/D2172M using the
appropriate dust correction procedure.
Do not make adjustments to the virgin binder selection for 0-20 percent
recycled binder content.
]PART 3 EXECUTION
**************************************************************************
NOTE: The Contractor may be able to meet the
specified quality control requirements with in-house
capability or may have to use the independent
commercial laboratory to provide the required
quality control testing.
**************************************************************************
Submit the Quality Control Plan. The Quality Control Plan is specific to
this specification and supplements the overall Quality Control Plan
required by the project. Do not produce hot-mixwarm-mix asphalt pavement
for payment until the quality control plan has been approved. In the
quality control plan, address all elements which affect the quality of the
pavement including, but not limited to:
b. Aggregate Grading
c. Quality of Materials
g. Mixture Volumetrics
j. Joints
l. Surface Smoothness
3.1.3.3 Temperatures
Determine the moisture content of the mixture at least once per lot in
accordance with ASTM D1461.
3.1.3.6 Laboratory Air Voids, TMD, and VMA VMA, and Marshall Stability and
Flow
Obtain mixture samples at least four times per lot and compacted into
specimens, using [50] [75] blows per side with the Marshall hand-held
(manual) hammer as described in ASTM D6926. The mechanical Marshall hammer
can be used only after JMF development and after correlation from
hand-held (manual) Marshall hammer to mechanical Marshall hammer per
guidance in AI MS-2.using [50] [75] gyrations of the Superpave gyratory
compactor as described in ASTM D6925. After compaction, measure the bulk
density of laboratory compacted specimens in accordance with
ASTM D2726/D2726M. Determine the laboratory air voids from the set (three
laboratory compacted specimens) for each sample in accordance with
ASTM D3203/D3203M. Also calculate the VMA of each specimen in accordance
with AI MS-2 based on ASTM C127 and ASTM C128 bulk specific gravity for
the aggregate, as well as the Marshall stability and flow, as described in
ASTM D6927. Provide VMA within the limits of Table 9.
3.1.3.10 QC Monitoring
Submit all QC test results to the Government on a daily basis as the tests
are performed. The Government reserves the right to monitor any of the
Contractor's quality control testing and to perform duplicate testing as a
check to the Contractor's quality control testing.
3.1.4 Sampling
When directed by the Government, sample and test any material which
appears inconsistent with similar material being produced, unless such
material is voluntarily removed and replaced or deficiencies corrected.
Perform all sampling in accordance with standard procedures specified.
For process control, establish and maintain linear control charts on both
individual samples and the running average of last four samples for the
parameters listed in Table 10, as a minimum. Post the control charts as
directed by the Government and maintain current at all times. Identify the
following on the control charts, the project number, the test parameter
being plotted, the individual sample numbers, the Action and Suspension
Limits listed in Table 10 applicable to the test parameter being plotted,
and the test results. Also show target values (JMF) on the control charts
as indicators of central tendency for the cumulative percent passing,
asphalt content, and laboratory air voids parameters. When the test results
exceed either applicable Action Limit, take immediate steps to bring the
process back in control. When the test results exceed either applicable
Suspension Limit, halt production until the problem is solved. When the
Suspension Limit is exceeded for individual values or running average
values, the Government has the option to require removal and replacement of
the material represented by the samples or to leave in place and base
acceptance on mixture volumetric properties and in place density. Use the
control charts as part of the process control system for identifying trends
so that potential problems can be corrected before they occur. Make
decisions concerning mix modifications based on analysis of the results
provided in the control charts. In the Quality Control Plan, indicate the
appropriate action to be taken to bring the process into control when
certain parameters exceed their Action Limits.
Laboratory Air Voids, percent No specific action and suspension limits set since
deviation from JMF target value this parameter is used to determine percent payment
In-place Mat Density, percent No specific action and suspension limits set since
of TMD this parameter is used to determine percent payment
In-place Joint Density, No specific action and suspension limits set since
percent of TMD this parameter is used to determine percent payment
Table 10 cont'd
Action and Suspension Limits for the Parameters to be Plotted on Individual and Running
Avereage Control Charts
Stability, N pounds (minimum)
Heat the asphalt binder material while avoiding local overheating and
providing a continuous supply of the asphalt material to the mixer at a
uniform temperature. Maintain the temperature of unmodified asphalts to
no more than 160 degrees C 325 degrees F when added to the aggregates.
The temperature of modified asphalts is not to exceed 175 degrees C 350
degrees F.
Heat and dry the aggregate for the mixture prior to mixing. No damage to
the aggregates due to the maximum temperature and rate of heating used is
allowed. Maintain the temperature no lower than is required to obtain
complete coating and uniform distribution on the aggregate particles and
to provide a mixture of satisfactory workability.
Weigh or meter the aggregates and the asphalt binder and introduce into
the mixer in the amount specified by the JMF. Limit the temperature of
the asphalt mixture to 175 degrees C 350 degrees F 132 degrees C 270
degrees F when the asphalt binder is added. Mix the combined materials
until the aggregate obtains a thorough and uniform coating of asphalt
binder (testing in accordance with ASTM D2489/D2489M may be required by
the Contracting Officer) and is thoroughly distributed throughout the
mixture. The moisture content of all asphalt mixture upon discharge from
the plant is not to exceed 0.5 percent by total weight of mixture as
measured by ASTM D1461.
**************************************************************************
NOTE: If the underlying surface to be paved is an
unbound granular layer, apply a prime coat,
especially if this layer will be exposed to weather
for an extended period of time prior to covering
with an asphalt mixture. Benefits derived from a
prime coat include an additional weatherproofing of
the base, improving the bond between the base and
asphalt layer, and preventing the base from shifting
under construction equipment. If the prime coat
requirement is not a separate pay item and is waived
from this contract, make an adjustment to the
contract price. Environmental laws in certain
states may not allow prime coats to be applied.
Prior to full production, place a test section for each JMF used.
Construct a test section 75 to 150 m 250 to 500 feet long and two paver
passes wide with a longitudinal cold joint. Do not place the second lane
of test section until the temperature of pavement edge is less than 80
degrees C 175 degrees F. Construct the test section with the same depth
as the course which it represents. Ensure the underlying grade or
pavement structure upon which the test section is to be constructed is the
same or very similar to the underlying layer for the project. Use the
same equipment in construction of the test section as on the remainder of
the course represented by the test section. Construct the test section as
part of the project pavement as approved by the Government.
**************************************************************************
NOTE: Table 11 applies only to the test section.
The limits in Tables 1, 3, and 10, apply to a number
of tests run from a lot. This is why the limits
listed in Table 11 are different from those listed
in Tables 1, 3 and 10.
Obtain one representative sample from random trucks at the plant, compact
triplicate specimens, and test for stability, flow, and laboratory air
voids. Test a portion of the same sample for theoretical maximum density
(TMD), aggregate gradation and asphalt content. Test an additional
portion of the sample to determine the TSR. Adjust the compactive effort
as required to provide TSR specimens with an air void content of 7 plus or
minus 1 percent. Obtain four randomly selected cores from the finished
pavement mat, and four from the longitudinal joint, and test for density.
Perform random sampling in accordance with procedures contained in
ASTM D3665. Construction may continue provided the test results are
within the tolerances or exceed the minimum values shown in Table 11. If
all test results meet the specified requirements, the test section may
remain as part of the project pavement. If test results exceed the
tolerances shown, remove and replace the test section and construct
another test section at no additional cost to the Government.
Table 11 cont'd
Marshall Compaction
3.7.1 Transporting
Transport asphalt mixture from the mixing plant to the site in clean,
tight vehicles. Schedule deliveries so that placing and compacting of
mixture is uniform with minimum stopping and starting of the paver.
Provide adequate artificial lighting for night placements. Hauling over
freshly placed material is not permitted until the material has been
compacted as specified, and allowed to cool to 60 degrees C 140 degrees F.
3.8.1 General
3.8.2 Segregation
The Government can sample and test any material that looks deficient.
When the in-place material appears to be segregated, the Government has
the option to sample the material and have it tested and compared to the
3.9 JOINTS
Do not pass the roller over the unprotected end of the freshly laid
mixture, except when necessary to form a transverse joint. When necessary
to form a transverse joint, construct by means of placing a bulkhead or by
tapering the course. Utilize a dry saw cut on the transverse joint full
depth and width on a straight line to expose a vertical face prior to
placing the adjacent lane. Neither cutting equipment that uses water as a
cooling or cutting agent nor milling equipment is permitted. Remove the
cutback material and cutting debris from the project. Provide a tack coat
in accordance with Section 32 12 13 BITUMINOUS TACK AND PRIME COATS to all
contact surfaces before placing any fresh mixture against the joint.
Joints between asphalt pavement and Portland Cement Concrete (PCC) require
specific construction procedures for the asphalt pavement. The following
criteria are applicable to the first 3 m 10 feet or paver width of asphalt
pavement adjacent to the PCC.
b. Place the asphalt pavement side sufficiently high so that when fully
compacted the asphalt pavement is greater than 3 mm 1/8 inch but less
than 6 mm 1/4 inch higher than the PCC side of the joint.
c. Compact with steel wheel rollers and at least one rubber tire roller.
Compact with a rubber tire roller that weights at least 18 metric tons
20 tons with tires inflated to at least 620 kPa 90 psi. Avoid
spalling the PCC during placement and compaction of the asphalt
-- End of Section --