Wa-22m-338-10-2020 (Goj) Mme
Wa-22m-338-10-2020 (Goj) Mme
Wa-22m-338-10-2020 (Goj) Mme
BETWEEN
AND
JUDGMENT
1
[2] Due to the role reversal of parties from the previous suit
which may give rise to confusion, I shall refer to the Plaintiff
as “MME” and to the Defendant as “Bank Rakyat” for clarity
and disambiguity.
Background facts
2
“Cadangan membina dan menyiapkan Klinik
Kesihatan 3” (“the KK3 Project”) in Hulu
Terengganu under the Bai’ Al-Inah principle, a
Jaminan Bank-i (BG-i) convertible to Kemudahan
Berjangka-i Facility of RM2,847,441.68 under the Al-
Kafalah principle to guarantee the Bank Guarantee
(Advance Payment) Facility to be taken with a
Commercial Bank for the KK3 Project and a
Berjangka-i (TF-i) Facility for the amount of
RM934,483.34 under the Bai’ Al-Inah principle to
settle the amount due in the event that the Bank
Guarantee (Performance) to be taken with the
Commercial Bank is invoked.
3
c) Financing-i Facilities of RM5,255,000.00 (“the 3rd
Facility”), documented by a letter dated 9.11.2012,
comprising a Jaminan Bank-i (BG-i) (Performance
Guarantee) convertible to Berjangka-i (TF-i) Facility
of RM625,500.00, a Jaminan Bank-i (BG-i) (Advance
Payment) convertible to Berjangka-i (TF-i) Facility of
RM2,602,500.00 and a Kontrak-i (CF-i) Facility of
RM2 million to part finance payment for works in
relation to a project known as “Kerja-kerja
pembaikian Stadium Sultan Mizan Zainal Abidin, di
Kompleks Sukan Negeri Terenganu-Fasa 1” (“the
SKS Project”) with a contract value of
RM13,050,000.00.
4
SMKB Project”) with a contract value of
RM12,517,829.45.
5
Submissions as there appears to be an inconsistency from
MME’s pleadings, affidavits and Written Submissions as
MME only referred to and described 5 facilities which were
not in the correct chronological order when defining each
facility.
[9] MME failed to repay the sale prices for the Six Financing
Facilities. Bank Rakyat, by way of letters of demand dated
7.7.2014 and 3.9.2014 demanded payment of
RM16,017,143.21 and RM16,280,080.73 respectively to be
paid within 14 days. Subsequent demands were issued by
way of letters dated 4.3.2015 and 25.3.2015. These
payments were not forthcoming thus Bank Rakyat was
prompted to terminate the Six Financing Facilities through
Notices of Termination dated 26.3.2015 (“the Notices of
Termination”) issued through Bank Rakyat’s previous
solicitor Messrs. Shukor Baljit & Partners for each of these
facilities.
6
a) All Bai’ Al-Inah facilities (the 1st to 4th Facilities)
offered to MME were declared void but MME was
obliged to repay to Bank Rakyat the balance of its
indebtedness under the Bai’ Al-Inah facilities
pursuant to s. 66 of the Contracts Act 1950;
[11] Bank Rakyat was not satisfied with part of the High Court’s
decision and filed a Notice of Appeal to the Court of Appeal
on 9.5.2017 (“the Appeal”).
7
[12] The Appeal was heard and on 19.3.2018 the Court of
Appeal ordered that the Judgment in Suit 176 dated
10.4.2017 be set aside and further ordered that the
Judgment be entered against the Respondent (MME) for
the amount owed of RM21,560,323.45, the same amount
claimed by Bank Rakyat in Suit 176, as at 31.5.2015 and
late payment penalty at the rate of 1% on RM21,560,323.45
from 1.6.2015 until full settlement (“the Court of Appeal
Judgment”). MME did not file any appeal to the Federal
Court against the Court of Appeal Judgment.
8
c) For the duration of the Six Financing Facilities, Bank
Rakyat had breached the express and/or implied
terms of the Six Financing Facilities by delaying the
timely disbursement of the facilties to MME in the
completion of the Projects;
9
h) For the duration of the Six Financing Facilities, Bank
Rakyat refused to respond to communications and
letters sent by MME seeking extension of time and
renewal of the facilities when the facilities expired;
10
b) RM6,574,032.82 for the 2nd Facility;
i) Damages; and
11
The Application
12
b) MME’s claim herein involves the same or newly
pleaded issues between the same parties and for the
same facilities that have been raised by MME which
are barred by the doctrines of res judicata and
estoppel; and
13
“19. Striking out pleadings and endorsements (O. 18
r. 19)
14
(b) this summary procedure can only be adopted
when it can be clearly seen that a claim or answer is
on the face of it obviously unsustainable;
Res judicata
15
are scandalous, frivolous or vexatious or an abuse of court
process pursuant to O. 18 of r. 19(1) (b) and (d) of the
Rules of Court 2012.
[23] Counsel for Bank Rakyat referred the court to the case of
Asia Commercial Finance (M) Berhad v. Kawal Teliti Sdn
Bhd [1995] 3 CLJ 783 (Federal Court) for the proposition
that res judicata creates an estoppel per rem judicature, the
effect of which is that when a matter between two parties
has been adjudicated by a court of competent jurisdiction,
the parties and their privies are not permitted to litigate once
more the matter that has been adjucated upon.
[25] Bank Rakyat contends that the issues in Suit 176 have
already been decided and should not be determined again
by the court in the present action. The issues in Suit 176 are
reproduced in their original form as below:
16
“Sama ada MME Realty & Management Sdn Bhd
adalah terikat dengan perjanjian-perjanjian bagi
keenam-enam kemudahan tersebut?
Sama ada MME Realty & Management Sdn Bhd
telah mengingkari dan memecahkan terma-terma
perjanjian-perjanjian bagi keenam-enam kemudahan
tersebut?
[26] Counsel for Bank Rakyat submits that these issues in Suit
176 are premised on the cause of action, facts and the Six
Financing Facilities relating to the breach of contract which
are the same as MME’s claim in the present action.
18
final judgment in Suit 176 and the previous Court of
Appeal Judgment; and
[29] Bank Rakyat maintains that the issues raised by MME in the
present action should have been raised from the outset
when the Six Financing Facilities were disbursed. However,
MME continued to apply for financing and executed
agreements for the 1st Facility through to the 6th Facility. As
a consequence of MME’s breaches to repay the facilities as
agreed in the terms of the agreement and as stipulated by
Bank Rakyat and set out in the Assignment of Contract
Proceeds in each Facility Agreement, Bank Rakyat
commenced Suit 176.
19
beeen responsible in scrutinizing the company accounts of
MME when the matter went for trial in Suit 176.
[31] Further, counsel for Bank Rakyat submits that by filing this
new action, MME intends to cause the Court of Appeal
Judgment to lose its effect and be set aside. This is an
abuse of court process as according to procedure, the
Plaintiff was to file an appeal against the decision of the
Court of Appeal as explained in the Supreme Court case of
Adzmi Ali & Anor v. Mohd Isa Kasad [1987] CLJ (Rep) 37
where the Supreme Court ruled that when an aggrieved
party was dissatisfied with the decision of a judge to not set
aside a default judgment or an interlocutory judgment with
damages to be assessed, the proper procedure to be
followed was by way of an appeal to the Supreme Court.
20
been decided in the Court of Appeal earlier. The doctrine of
res judicata is applicable in these proceedings as MME is
raising issues relating to the Six Financing Facilities which
were adjudicated in the Court of Appeal. If these
proceedings are continued, it will result in the Court of
Appeal Judgment being ineffective.
[35] Counsel for Bank Rakyat submits that the doctrine of res
judicata is a factor for the court to take into account to
dismiss MME’s claim on the basis that the claim is
scandalous, frivolous or vexatious or an abuse of court
process as decided by the Court of Appeal in Sungai Dinar
Sdn Bhd v. Koperasi Pekebun Kecil Wilayah Johor Selatan
Bhd [2017] 1 CLJ 333 (Court of Appeal).
[36] Counsel for Bank Rakyat also submits that allowing MME’s
claim in the present action in respect of the Six Financing
Facilities, which is the subject matter of Suit 176, to proceed
will provide an opportunity to any customer who has been
previously sued by banks and found liable in a full trial to
relitigate the matter. Bank Rakyat referred the court to the
case of Chin Wai Leong & Ors v. PP & Other Applications
[2020] 7 CLJ 322 (Court of Appeal) which stated that
allowing a party to re-litigate a matter will open the floodgate
21
to endless re-litigation before the same court which causes
decisions of the court to become doubtful and uncertain.
[37] Counsel for Bank Rakyat submits that the decision of the
Court of Appeal is binding on the parties and filing a new
claim in respect of the same Six Financing Facilities is an
injustice which results in no end to the litigation process.
Allowing MME’s claim to proceed will open a floodgate of
cases especially in banking cases in Malaysia because
there is no finality of cases between the parties despite the
matter having been tried fairly and equitably in court.
[38] Counsel for MME submits that Bank Rakyat’s action in Suit
176 is not the same as MME’s action in the present action.
For this purpose MME referred the court to a table of
comparison which was put forward by Bank Rakyat in its
affidavit in support. Through this, MME sought to
demonstrate that the issues and contentions raised by MME
relating to Suit 176 are different from the issues in this
present action. MME maintains that res judicata does not
apply when the issues or questions in Suit 176 are not
present in the present action. These are summarised below.
22
Facility. However in the present action MME contends that
there were implied terms relating to the constant cash flow
requirements for MME and Bank Rakyat had breached
estimated these implied terms for the duration of all the
facilities granted, particularly for the 2nd Facility, 3rd Facility
and 5th Facility.
23
Facilities, resulting in MME not having constant cash flow to
complete the Projects.
24
assessment of suitability and affordability of financial
services offered to MME within s.42C of the Development
Financial Institutions Act 2002 (“DFIA”). In relation to this,
MME contends that the manner in which Bank Rakyat
utilized the funds in the contract proceeds paid into the
Designated Account solely managed by Bank Rakyat for the
facilities amounted to prohibited business conduct as set
out in the Second Schedule within s. 42D of DFIA. These
matters are pleaded in para.s 92 and 93 (a) to (o) of the
Statement of Claim.
25
additional bridging finance was made available. This
resulted in there being no meaningful balance left for
MME to pay its suppliers and contractor in the
housing development from the sales proceeds.
26
applying the contract proceeds of the DTIK Project to
pay for other projects since 19.9.2012 an impression
of default was created and Bank Rakyat could not
have offered MME the 3rd Facility and 4th Facility if
the existing facilities are in default and that there is
likelihood of further default.
27
[47] I have considered the submissions of counsel in respect of
the issue of whether res judicata will bar MME from raising
the issues in the present action. The first consideration of
the court is whether the issues that are raised in the present
action are the same issues that have previously been raised
in Suit 176. If the same issues are raised then it is clear that
MME is not allowed to re-litigate the matter as it would be
seeking to reopen the litigation in Suit 176 that has already
been concluded by the Court of Appeal decision on
19.3.2018.
[48] There is no dispute that the parties in the present action are
the same as the parties in Suit 176. In the present action,
Bank Rakyat, the defendant in Suit 176 has become the
plaintiff and MME, the defendant in Suit 176 has become
the plaintiff. The subject matter of the dispute is also the
same – the Six Financing Facilities. While in Suit 176 MME
raised a number of Bank Rakyat’s breaches as defences to
Bank Rakyat’s claim, in the present action, MME alleges a
number of breaches by Bank Rakyat in respect of the Six
Financing Facilities to establish its causes of action.
28
Whether MME has breached the terms of the
agreements for the Six Financing Facilities?
29
[51] Only with these issues being decided in the positive that
MME could be found liable for the full amount as claimed by
Bank Rakyat in Suit 176 and for the Court of Appeal
Judgment to be given against MME. This is the truth of the
matter. Despite the present action being dressed up in new
clothes in the form of the current issues raised by MME
relating to, inter alia, the breach of implied terms on the
need for constant cash flow for MME, timely disbursements
and not applying contract proceeds interchangeably, any
finding for MME in relation to these new issues would run
contrary to the finding of the Court of Appeal that MME is
bound by the agreements for the Six Financing Facilities,
that MME has breached the terms of the agreements for the
Six Financing Facilities and that MME is indebted to the
Plaintiff. This is because the termination of the Six
Financing Facilities would be unlawful if MME did not
breach the terms of the agreements for the Six Financing
Facilities.
30
seemingly unrelated to the earlier case cannot change that
truth.
(Emphasis added)
32
otherwise open the floodgate to endless re-litigation
before the same court. The value and usefulness of
a decision of this court becomes doubtful and
uncertain if the appeal can be reopened at any time
and the court is permitted to make a different order”.
(Emphasis added)
33
…. There is one school of thought that issue
estoppel applies only to issues actually decided by
the Court in the previous proceedings and not to
issues which might have been and which were not
brought forward, either deliberately or due to
negligence or inadvertence, while another school of
thought holds the contrary view that such issues
which might have been and which were not
brought forward as described, though not
actually decided by the Court, are still covered by
the doctrine of res judicata ie. doctrine of
estoppel per rem judicatum.
(Emphasis added)
34
[58] In Dato' Sivanathan a/l Shanmugam v. Artisan Fokus Sdn
Bhd [supra] the Court of Appeal stated:
35
should have done so via a counter claim or raised as
defences to Bank Rakyat’s claim in Suit 176.
36
[62] I am not persuaded that these are matters which MME has
discovered only recently as the facts MME relies on in the
present action which allegedly caused the failure of MME to
service the financings which led to Suit 176 had occurred
earlier during the time MME was breaching its obligation to
repay under the Six Financing Facilities. I agree with Bank
Rakyat’s submission that MME should have scrutinized the
company accounts when the matter went for trial in Suit
176.
(Emphasis added)
[66] I do find that if not for res judicata barring MME’s claim in
this action and if this was a genuinely fresh action, there is
force in MME’s arguments that the issues relating to the
deduction of contract proceeds, delays in the disbursements
and increase in the redemption amount of the 1st Facility
are matters which ought to go to trial and cannot be
determined by affidavit evidence alone. However, MME’s
claim must be struck out on the basis of res judicata alone
as discussed above.
38
Conclusion
13 September 2021
39
Counsel:
40