CIPAA Syarikat Bina Darul Aman
CIPAA Syarikat Bina Darul Aman
CIPAA Syarikat Bina Darul Aman
And
And
And
And
BETWEEN
1
1. SYARIKAT BINA DARUL AMAN BERHAD
2. PEMBINAAN KERY SDN BHD … PLAINTIFFS
[Collectively referred to as BDB-Kerry (Joint Venture)]
AND
THE JUDGMENT OF
[1] The Plaintiff here is the Claimant in the Adjudication under the
Project
[2] The parties had entered into a contract in writing dated 23 January
2006, wherein the Defendant appointed the Plaintiff as the Contractor for
RM347,070,267.53.
2
[3] The Plaintiff subsequently awarded the construction of the whole
Works under the Contract to Bayu Melati Sdn Bhd (“Bayu Melati”) who in
Hup”). The Plaintiff stated that at all material times, the Defendant was
Claim.
[4] The form of contract between the parties is the PWD 203A
Contract”).
[5] Pursuant the Contract, the Plaintiff had proceeded to perform the
extensions of time for reasons beyond its control, extending the Contract
3
Problem
[6] Upon completion of the Works and vide a letter dated 26 January
2011, the Plaintiff submitted its claim pursuant to Clause 48(a) of the
[7] The Defendant and PJS Consultants Sdn Bhd (“PJS”), the
[8] There was a long waiting period after that and it was only by a
letter dated 5 January 2014 that the Defendant informed the Plaintiff that
they had made a Decision that only RM137,512.95 was due and owing
to the Plaintiff. The Plaintiff was unhappy with the amount claimed and
the paltry amount approved by the Defendant and so it asked vide its
2014 stating that they were unable to provide details regarding the
4
under a Final Claim. The Superintending Officer SO only certified by way
Adjudication.
was that the payments were not due under the terms of the Contract and
that the said claims were not in accordance with the terms of the
Contract and as such the Respondent stated that the Claimant was not
Prayers
[12] The Adjudicator dismissed the whole of the Claimant's claim. The
as:
5
b) The Plaintiff be entitled to re-commence Adjudication Proceedings
from the Notice of Adjudication dated 25th March 2016 with a new
d) Such further and other reliefs as this Honourable Court deems fit.
[13] Unlike most applications before this Court for setting aside of an
has to pay the sum stated in the Decision, here there is no such
application because the Respondent was not made to pay any sum to
here there is none because the whole of the Claimant's Payment Claim
was dismissed.
the meaning of section 15 CIPAA even though it was not required to pay
6
Proceedings in the Adjudication
TOTAL RM 347,070,267.53
2016 on the Claimant denying all the claims put forward by the Claimant
on grounds that the said claims were not in accordance with the terms of
7
the Contract and as such the Respondent stated that the Claimant was
Claim and the Respondent with the service of its Adjudication Response.
[18] The Claimant subsequently withdrew its claim for VOP for Diesel in
on 29 June 2016 while the Defendant did not file any written
submissions in reply.
Claim was invalid as it had not been based on what was certified by the
8
SO which in any event had been paid and that to entertain the
that was not prayed for, he does not have the jurisdiction to do so.
[21] He further stated that with respect to Claim No. 2 and No. 3, based
on the evidence adduced through the documents, the Claimant had not
proved its claim. As for Claim No. 4 the Adjudicator held that a claim for
"loss and expense" is outside the purview of CIPAA and that he has no
Principles
[22] Under section 15 CIPAA, only an aggrieved party may apply to the
is an aggrieved party?"
successful party. In such a case the aggrieved party who may apply to
9
[24] In the case where the Claimant is successful only in part or for far
less than what it claims, or as here, where the whole of its claim is
consistent with what the Court of Appeal held in Wu Shu Chen (SOLE
Anor v Raja Zainal Abidin bin Raja Hussin [1997] 2 MLJ 487 at
section 103E of the Legal Profession Act 1976, where the Federal Court
10
“The position in England has now changed. As Drost J observed
[27] In Punca Klasik Sdn Bhd v Abdul Aziz bin Abdul Hamid & Ors
Instrument held:
11
which has wrongfully deprived him of something, or wrongfully
something.’
[28] I agree with the Claimant that an “aggrieved party” within the
context of CIPAA must be given its plain and ordinary meaning, that is to
[29] Here the Claimant had his whole Payment Claim dismissed and so
have used that expression which was used in section 30(1) CIPAA with
adjudication decision in his favour" as the party who could enforce the
12
(1) If a party against whom an adjudication decision was
direct from the principal of the party against whom the adjudication
different words are used in the same statute; otherwise the same words
would be used for consistency of expression. One can surmise that "an
Adjudication Decision either because its whole Payment Claim has been
that it was given a sum less than what was claimed in its Payment
Claim.
have to set aside the whole of the Decision in its favour if it is minded to
apply to set aside the Decision unless it is a case where the heads of
claim without jurisdiction can be severed from those that are within
13
jurisdiction in which instance, only so much of the claim that is
[34] Presumably a Claimant who got much less than what was claimed
in the Payment Claim would have to set aside the whole of that Decision
bribery.
Payment Claim dismissed and costs awarded against it and it would not
awarded and for which payment had not been made by the Claimant.
14
[37] All said, a Claimant whose Payment Claim has been dismissed is
set aside the Decision, the Court may be minded to only set aside that
part of the Decision that was made when the Adjudicator erroneously
made in the Payment Claim as the Claimant had not prayed for the
Certificate to be revised
[38] The 3 Claims of the Claimant are set out in the Payment Claim and
the Respondent in its Payment Response had disputed and denied the
whole of the Payment Claim on ground that the Claims are not due
under the terms of the Contract and not in accordance with the terms of
the Contract.
[39] The matters raised in the Payment Claim and Payment Response
15
documents tendered. There was no oral hearings requested by the
parties and in any event, the Adjudicator had in his Decision stated that
review and revise the Certificate issued by the SO, then he has no
[42] In dealing with the issue on whether the Plaintiff was entitled to
following observations:
“In any event, the Plaintiff did not seek for any remedy in its
“It must be borne in mind that an Adjudicator does not step into
16
“If the Plaintiff is unhappy with the alleged under certification of its
[43] Learned counsel for the Claimant submitted that the Adjudicator
"Section 25 (m)
dispute.”
Adjudication in Malaysia by Lam Wai Loon and Ivan Loo at page 212
follows:
17
“Pursuant to section 25(m) of CIPA Act 2012, the Adjudicator has
[45] The Claimant further referred to the case of Vaultrise Ltd v Paul
final certificate should have been issued on or before the 30th July.
He went on to determine the amount and held that that sum was
18
should contain, should not be referred to adjudication.”
(emphasis added)
[46] By the same token, an Adjudicator may declare and decide how
is an under-certification or over-certification.
follow that the adjudicator can rule not only on that defence but
Before he can exercise any of the powers given to him under section 25,
he must first have the jurisdiction to hear the dispute under section 27.
19
nothing to state that he can only exercise his powers upon request of the
parties either in their Payment Claim as in this case when there was no
section 25(i) to inquisitorially take the initiative to ascertain the facts and
[49] So too if he should decide that there should be an oral hearing and
order that any evidence be given on oath under section 25(l). In as much
would say that he has the power to decide how much is due to the
Claimant even if a certificate has been issued which the Claimant felt is
[50] The fact that he has the power to review and revise any certificate
issued would mean that if in the process of finding a higher sum is due
and revise the Certificate. Such vast powers are granted to him when
parties have given him the jurisdiction to decide on the dispute; the
20
Claimant stating a certain sum is due and the reasons for it and the
[51] Here was a case where the Claimant had submitted the original
to decide whether the various sums claimed under the various heads of
not asked him to review and revise the certification of the SO would be
[53] Bearing in mind that a lot of Payment Claims are drafted by the
for under section 8(3) CIPAA, it behooves upon the Court not to take an
21
[54] In support of the Claimant's contention, the Claimant relied on the
Singapore High Court case of Chip Hup Hup Kee Construction Pte
237, where Judith Prakash J (now CA) made the following observations:
22
taken in the prior proceedings before the Adjudicator and the
in view of the fact that the contract between the parties had
23
was filed in support of SUM 3242. It asserted that the
the adjudication;
[55] Based on the above, Her Ladyship Judith Prakash J (now CA)
known to the respondent and its legal advisers if not at the time
24
that I had to consider was whether such facts could be relied on in
CA) had made reference to the Australian case of Parist Holdings Pty
Ltd v Wt Partnership Australia Pty Ltd [2003] NSWSC 365 where she
“In Parist, the defendant sought a declaration that the plaintiff must
contended, inter alia, that the adjudicator had acted ultra vires in
be paid. The plaintiff, however, had not put in issue the validity
25
adjudicator. It only raised this issue when it filed its summons
The court held that because the plaintiff had not raised the
[57] I find merit in the Claimant's submission that it is only now that the
with the position taken by the Adjudicator. If the Respondent had wanted
to raise the validity of the Payment Claim on ground that the Claims are
premature or that for some reasons the payment due dates are wrong, it
Claimant's Payment Claim for Claims No. 2 and 3. At para 126 of the
26
will deal with them in the order that the Claimant has done in its
Adjudication Reply...."
agree with the Respondent's contention that the Claim under this
134. It is also my finding that since the Claimant had signed the
infer that the Claimant had agreed with the calculation by the
find that the Claimant has waived its claim under Claim No. 3.
27
the poor workmanship of the Claimant. This is beyond the
(emphasis added)
[60] The Adjudicator having made a finding of mixed fact and law, it is
not for this Court to interfere on merits. This is not an appeal and the
Adjudicator having applied his mind to the clauses before him and the
persuade the Arbitrator that the Adjudicator had made a wrong finding of
mixed law and fact. It is not for this Court to enter into the realm of
not the ground relied on by the Claimant to set aside the Decision. There
arriving at his Decision to dismiss this head of Claim for he heard both
28
[61] So too with respect to Claim No.2 on Excess Guniting Works. The
Adjudicator had made a finding of mixed law and fact when he held as
follows:
"138. ...the Claimant has failed to prove the total slope area where
the gunite thickness was more than 100 mm thick. The Claimant
cannot claim for the total area where the gunite is more than 100
the total area where the guniting exceeded the 100 mm thickness.
In addition, the Claimant had signed the PHK No. 2 and PHK No.
[62] Again for the reasons given above, I would not disturb this finding
in breach of natural justice, this head of claim must remain intact until it
29
Whether the "Loss and Expense Claims" is a valid Payment Claim
under CIPAA
[63] This is the main plank of the Claimant's complaint on the Decision
of the Adjudicator. I note that the Adjudicator had stated that "Loss and
Decision:
case the claim has been evaluated by the S.O. and certified for
merit of the said claim since the Plaintiff may still want to refer the
30
[64] Having made such an observation and despite not making a
claim in toto. I also struck out the Plaintiff’s Claim No.1 as it had
[65] The Claimant submitted that based on the foregoing reasons, the
[66] I agree that the Adjudicator should have struck out the Claim under
this head of the Payment Claim. To dismiss this head of the Payment
Claim would mean that the merits had been considered and found
[67] However what is more important is not the nomenclature but the
nub of the issue which is whether a "Loss and Expense Claim" in this
[68] The Adjudicator's stand and stated position was that a "Loss and
is not "a payment for work done or services rendered under the express
31
terms of a construction contract" as "payment" is defined in section 4
CIPAA.
[69] My attention was drawn to the fact that the Adjudicator had, at
observation:
“No oral hearings were conducted nor was there any request from
2012.”
in this case, under Claim No.4 for "Loss and Expense Claim" was not
[71] As authority for this proposition, the Claimant referred this Court to
the case of Pilon Ltd v Breyer Group Plc [2010] EWHC 837 (TCC)
32
“An Adjudicator can make an inadvertent mistake when answering
the question put to him, and that mistake will not ordinarily affect
Jensen (UK) Ltd [2000] BLR 49. If, on the other hand, he considers
then his decision will not be enforced: see the discussion in Sindall
view of his own jurisdiction, with the result that he decides not
33
question then, whether right or wrong, his decision is
decide, then such a failure will not ordinarily render the Decision
22.4 It goes without saying that any such failure must also be
34
see Keir Regional Ltd v City and General (Holborn) Ltd [2006]
added)
35
“Furthermore, I do not think the nature and quantum of the claims
CIPAA. It would not be fair to the parties. I believe the Act does not
[74] I further agree with the Claimant that the Adjudicator must always
have in the forefront of his mind the intent and objective of CIPAA which
36
Act. If he cannot, he ought to resign. Thus, at the outset, the
fairly in the time period. Had he done so, I think it likely that for
this claim was not suitable for the summary adjudication process
[76] I appreciate that whilst a "Loss and Expense Claim" may in some
37
principal, there are cases where contractually such a claim is allowed to
Account and hence payable as part of the amount claimable for the
[77] The learned author Lim Chong Fong (now Justice Lim Chong
"As soon as is practicable but not later than ninety (90) days after
38
“44. Loss and Expense Caused by Delays
“If the regular progress of the Works or any part thereof has been
(i) hereof (and no other), and the Contractor has incurred direct
payment made under any other provision in this Contract, then the
[79] Finally Clause 48(a) of the PWD 203A Standard Form of Contract
provides as follows:
"So soon as is practicable but not later than three (3) months after
39
prepared by the S.O. provided always the Contractor had given the
said provisions."
[80] The learned authors Lam Wai Loon and Ivan Y F Loo of
Business, drew support for the proposition that a claim for losses
CA. It was held that so long as such an entitlement is provided for under
the written contract between the parties, such a claim can be mounted. I
construction contract; or
40
[81] In the New Zealand Court of Appeal case of George
55 of the judgement:
South Wales approach. The New South Wales Act is not identical
inevitably arise from carrying out the work. This might include
41
vindicated, the particular amount will not have to be paid, but that
will not prejudice the entitlement of the payee to be paid the other
which our CIPAA shares almost identical purpose and objectives, stated
(emphasis added)
[83] The same position was also propounded in the book Adjudication
by Chow Kok Fong, Lim Chong Fong and Oon Chee Kheng, wherein it is
stated that:
42
“[5.16] The items which are frequently tendered in a payment
heads:
of work.
43
temporary site buildings to house site personnel and
[5.30] It is clear from this quick survey of the authorities that the
44
clearly envisages such claims being made as part of the
preliminaries.
Contract are the express terms under which the Payment Claim was
made.
45
[85] I am further fortified in my view having regard to section 29(4)(c)
construction work if the adjudication decision has not been paid wholly
[86] Quite obviously the Payment Claim for this loss and expense is
made because the contract is still subsisting and there are further claims
due after the suspension of work because of further work done. It also
flows naturally from section 29(4)(b) CIPAA where the party who
exercises his right under section 29(3) CIPAA is entitled to a fair and
contract.
46
[87] As this is a case where the Adjudicator had erroneously held that
that goes towards jurisdiction. Not to hear a dispute submitted for his
[88] As this head of Claim in Claim No.4 is severable from Claims No. 3
and 4 which had been decided on merits and for which I would not
interfere, I may set aside that part of the Decision that is affected.
Pronouncement
[89] For the reasons given, I had set aside only the part of the
47
[91] In view of the peculiar circumstance of this case and the novelty of
costs.
- signed -
Y.A. LEE SWEE SENG
Judge
Construction Court
Kuala Lumpur
48