Nominated Sub Contractor & Supplier PDF
Nominated Sub Contractor & Supplier PDF
Nominated Sub Contractor & Supplier PDF
NOMINATED SUPPLIER
PROVISION IN THE CONTRACT
Relevant contractual provisions regarding
Nominated sub-contractors/suppliers in P.W.D.
203A (Rev. 1/2010) Standard form of contract:
a) Clause 47 – Sub-contract or assignment
b) Clause 60 – Nominated Sub-Contractors
(NSC) or Nominated Suppliers (NS)
c) Clause 60 – Payment to NSC and NS
d) Clause 34 – Prime Cost/Provisional Sum
PROVISION IN THE CONTRACT
Clause 47 – Sub-contract or Assignment
Sub-Contract Assignment
• Transfer the right and responsibilities to
• The contractor passes over part only of
another party - where the contractor
the works and rewards for so doing to
wishes to dispose his obligations under
another person
the contract to a new contractor
• The contractor remains involved in the
• Written consent of the employer is
management of the contract.
required
• Contractual liability over performance
• In construction contract, contractor
remains with the contractor. Sub let does
cannot assign his obligation to complete
not release the contractor for all his
the works to another. He may assign the
contractual obligation
right of receiving payments due under
• Written consent of the C.A. (Contract
the contract in order to obtain credit
Administrator) is required
from supplier or funding institution
TYPES OF SUB CONTRACTOR
a) Domestic Sub-Contractor
• Appointed by the contractor himself to execute the
works or services which form part of the main
contract.
• Contractor must not sublet any part of the work to his
sub-contractor without prior consent of the S.O.
• S.O.’s consent must not unreasonably withheld to the
prejudice of the contractor.
TYPES OF SUB CONTRACTOR
b) Nominated Sub-Contractor
• Person who nominated by the employer/S.O. to execute
the work or services which form part of the main contract.
• The affected work are covered under P.C. sums in the BQ.
May also cover under Provisional Sum if so instructed by
the S.O.
• The S.O. cannot instruct measured works priced by the
contractor to be done by N.S.C.
• N.S.C. is similar like N.S. but N.S. merely supply material or
goods for the contractor to fix.
NOMINATION OF NOMINATED SUB
CONTRACTOR & NOMINATED SUPPLIER
Clause 60.1
• N.S.C. is normally procured through a quotation or
tendering process.
• S.O. must not delay the nomination of N.S.C., since it may
affect the overall progress of the work and cause financial
loss to main contractor.
• The delay in nomination by the S.O. is a ground for the
main contractor to claim for:
a) Extension of time
b) Loss and expense
OBJECTION TO NOMINATION
Clause 60.2
• The objection by the main contractor to the proposed N.S.C. must be
made in writing within 21 days from the receipt of S.O.’s instruction
but the objection is nonetheless still subject to the S.O.’s concurrence
• If the objection is not accepted by the S.O. – main contractor has to
enter into sub-contract with N.S.C. or he can bring the matter to
arbitration (clause 65.1)
Tender for sun- Objection by main
contractor/supplier Nomination by S.O. contractor
<21 days
OBJECTION TO NOMINATION
Clause 60.2
Possible ground for main contractor’s reasonable
objection:
• N.S.C.’s financial instability
• Technical incompetence of the N.S.C.
• Introduction of special conditions by N.S.C.
• N.S.C. declines to provide main contractor appropriate indemnity
• N.S.C. fails to undertake certain specified obligation
• N.S.C.’s work programme is incompatible with main contractor’s
programme
PROCESS OF N.S.C. / N.S. NOMINATION
Clause 60.3 Tender for sub-
contractor/supplier
This cycle is repeated until
contractor accepts
nomination by S.O.
Nomination by S.O.
Vary the work to overcome
problems
Yes
Omit the work and give it Contractor’s
to others objection