HVAC LQUP COMMISSIONING PLAN 1

TASK START END

HVAC TB COMMISSIONING 30-Oct-23 1-Dec-23


Pre-comm E&I - Energize System 30-Oct-23 19-Nov-23
Energize and pre-comm - SP-L07501 MCC-HVAC A 30-Oct-23 2-Nov-23
Energize and pre-comm - SP-L07502 MCC-HVAC B 2-Nov-23 5-Nov-23
Energize and pre-comm - AP-L07551 HVAC LCP 7-Nov-23 10-Nov-23
Hot loop check & functional test of motorized dampers (25 units ) - 5 units /day 11-Nov-23 16-Nov-23
Hot loop check of Instrument items (5 units) & functional test of duct heater (2 units)
17-Nov-23 19-Nov-23
hot loop check - 4 units/day
Pre-comm (HEI) 31-Oct-23 18-Nov-23
Flushing/purging of refrigerant pipe lines (2 circuits) 31-Oct-23 2-Nov-23
Pressure Test of Refrigeration Piping System Unit A & B - suction & liquid line (2
2-Nov-23 6-Nov-23
circuits) - 24 hours hold pressure each line
Vacuum Testing of Refrigeration System Unit A & B 6-Nov-23 11-Nov-23
Initial refrigerant gas charging Unit A & B 7-Nov-23 12-Nov-23
Alignment for AHU blower (2 units) 10-Nov-23 15-Nov-23
Energize compressor crankcase heaters (2 units) for at least 24 hours prior to starting
12-Nov-23 17-Nov-23
the compressor of ACCUs
Functional test for AHU blower (2 units), Fan ACCU (4 units) & exhaust fan (8 units) -
15-Nov-23 18-Nov-23
8 units/day
Perform HVAC SAT - Sequence of Start-up and Commissioning: 18-Nov-23 1-Dec-23
Starting of all Fans, Air handling Units & Condensing Units 18-Nov-23 19-Nov-23
Perform tuning for refrigerant (Hi Lo Pressure) - Unit A - Final Gas charging - 1 circuit 19-Nov-23 20-Nov-23
Perform tuning for refrigerant (Hi Lo Pressure) - Unit B - Final Gas charging - 1 circuit 20-Nov-23 21-Nov-23
Cause & Effect Checks (944 check) - 500 checks/day 19-Nov-23 22-Nov-23
Perform Static & Dynamic Balancing of Air Distribution System - (VCD - 21 units &
20-Nov-23 25-Nov-23
stream no - 75)
Commissioning checks & Perform 72 hours (each unit) HVAC Endurance Test 25-Nov-23 1-Dec-23
HVAC LQUP COMMISSIONING 30-Oct-23 5-Dec-23
Pre-comm E&I - Energize System 30-Oct-23 17-Nov-23
Energize and pre-comm - SP-L07501 MCC-HVAC A 30-Oct-23 2-Nov-23
Energize and pre-comm - SP-L07502 MCC-HVAC B 2-Nov-23 5-Nov-23
Energize and pre-comm - AP-L07551 HVAC LCP 7-Nov-23 10-Nov-23
Hot loop check & functional test of motorized dampers (25 units ) - 10 units /day 11-Nov-23 14-Nov-23
Hot loop check of Instrument items (5 units) & functional test of duct heater (2 units)
15-Nov-23 17-Nov-23
hot loop check - 8 units/day
Pre-comm (HEI) 31-Oct-23 22-Nov-23
Flushing/purging of refrigerant pipe lines (4 circuits) 31-Oct-23 4-Nov-23
Pressure Test of Refrigeration Piping System Unit A & B - suction & liquid line (4
2-Nov-23 10-Nov-23
circuits) - 24 hours hold pressure each line
Vacuum Testing of Refrigeration System Unit A & B 6-Nov-23 16-Nov-23
Refrigerant Oil and Gas Charging Unit A & B 11-Nov-23 15-Nov-23
Alignment for AHU blower (4 units) 14-Nov-23 16-Nov-23
Energize compressor crankcase heaters (2 units) for at least 24 hours prior to starting
16-Nov-23 21-Nov-23
the compressor of ACCUs
Functional test for AHU blower (2 units), Fan ACCU (4 units) & exhaust fan (8 units) -
19-Nov-23 22-Nov-23
8 units/day
Perform HVAC SAT - Sequence of Start-up and Commissioning: 22-Nov-23 5-Dec-23
Starting of all Fans, Air handling Units & Condensing Units 22-Nov-23 23-Nov-23
Perform tuning for refrigerant (Hi Lo Pressure) - Unit A - Final Gas charging - 1 circuit 23-Nov-23 24-Nov-23
Perform tuning for refrigerant (Hi Lo Pressure) - Unit B - Final Gas charging - 1 circuit 24-Nov-23 25-Nov-23
Cause & Effect Checks (944 check) - 500 checks/day 17-Nov-23 20-Nov-23
Perform Static & Dynamic Balancing of Air Distribution System - (VCD - 21 units &
24-Nov-23 29-Nov-23
stream no - 75)
Commissioning checks & Perform 72 hours (each unit) HVAC Endurance Test 29-Nov-23 5-Dec-23