Final Survey Report - PT Stargate Pasific Resources

Download as pdf or txt
Download as pdf or txt
You are on page 1of 26

FINAL SURVEY REPORT

PT STARGATE PASIFIC RESOURCE


A
PROJECT LAMERURU, KECAMATAN LANGGIKIMA, KABUPATEN KONAWE UTARA, SULAWESI TENGGARA
GENERAL INFORMATION
ARRIVAL INFORMATION
(a) (b)

The location of the project is in the Sub-District of Langgikima, North Konawe Regency, Southeast Sulawesi Province,
Indonesia. Kendari can be reached through air transportation from Makassar to Kendari is within 55 minutes.
a) The land transportation from Haluoleo Airport to PT Stargate Pasific Resources about 184 km (4 hours 54 minutes)
b) The land transportation from Kendari City to PT Stargate Pasific Resources about 188 km (4 hours 49 minutes)
ARRIVAL INFORMATION
(a) (b) (c)

a) The land transportation from PT IMIP to PT Stargate Pasific Resources about 112 km (3 hours 4 minutes)
b) The land transportation from Maleo Airport to PT Stargate Pasific Resources about 219 km (6 hours 5 minutes)
c) The land transportation from Morowali City to PT Stargate Pasific Resources about 148 km (4 hours 22 minutes)
PROJECT AREA
OVERVIEW PIT & STOCKPILE AREA
OVERVIEW JETTY AREA
CONTRACTOR AND VENDOR RELATION

Name Focus

PT Kalimantan Prima Persada Mining, Hauling, and Barging

PT Fathan Surya Segara Agen Shipping

PT Carsurin Tbk Surveyor

Pertamina Patra Niaga Fuel

PT Sutra Alam Perkasa Waste Management


SITE INFORMATION / CUSTOMER INFORMATION
Item Detail
Company Name Stargate Pasific Resources

Project Name Lameruru Project

Business Commodity Nickel

Desa Molore, Desa Lameruru, Kecamatan Langgikima, Kabupaten Konawe


Site Address
Utara, Provinsi Sulawesi Tenggara

IUP Number IUP No. 668 Tahun 2017


Total Widht IUP Area 1,213.20 Ha
Kode WIUP 3474092122014112
Date Of Deed 03-08-2017
Date of Expire 21-12-2029
Status Clean and Clear CNC-15 No. 668 Tahun 2017

Referensi Head of Operations PT Stargate Pasific Resources


DATA REFERENCE
Item Detail

Yearly Target Production Next RKAB 2,500,000 ton

Yearly Current Target Production 1,800,000 ton

Yearly Actual Production 260,000, tons until August 2023

Monthly Target Production 100,000 tons

Monthly Actual Production 50,000 - 100,000 tons

Daily Actual Production 5,000 - 8,000 tons

Speed Max 30 km / hour

Pit to stockpile maximal 20 ton


Unit Load Capacity
Stockpile to jetty maximal 20 ton
PIT, STOCKPILE AND JETTY
DETAILS CONDITION
DETAILS CONDITION PIT LAMERURU

The Lameruru’s pit has total width is 17,5 Ha. Divided to 3 layers, which is Overburden, Limonite, and Sapprolite. The elevation of
Overburden layer is 80 -100 masl, Limonite layer 20 – 80 masl, and Sapprolite layer 0 – 20 masl. The distance from pit to efo is ±
500 m.
DETAILS CONDITION STOCKPILE LAMERURU

The Lameruru’s stockpile has 6 areas from area 1 to 6 with total width is 52,16 Ha and maximal capacity is around 60,000 tons. The ongoing
activity at Lameruru’s stockpile is loading of ore from the pit to the stockpile. Stockpile’s Cargo divided to Sapprolite and Limonite.
Sapprolite’s Cargo has a capacity of 10,000 tons, and Limonite’s Cargo has a capacity of 50,000 tons.
AREA JETTY AND HAULING ROAD DETAILS LAMERURU

The picture above describes the lameruru jetty area with total The picture above shows the hauling road from the direction
width is 2.4 ha. For barge slots at the Wolo jetty there are 3 slots. of stockpile to jetty. With hauling road width is 10 m and
Adequate lighting, using PLN power lines and there is a generator average hauling road grade is 8 %.
as a spare when there is a power outage.
HAULING ROAD DETAILS STOCKPILE TO JETTY LAMERURU

Distance : 1.5 Km
Cycle Time : 15 minutes
Grade : 8 – 10 %
Bundwall : 1 meter
Bridge Details : No Bridge
Crossroad :1
Crossfall :2%
Compacted : Yes
Width : ± 10 meter
Road Capacity : ± 40 ton The picture above describe hauling road condition from stockpile
to jetty Lameruru. From the picture, can be concluded that the
Road Material : Quarry condition hauling road is safe. The road material is quite dense
and does not require long time for maintenance after rain.
Downhill : 1 downhill before arriving at jetty
Maintenance Company : Handle by each company with their
areas
RAINY DAYS AND RAINFALL 2023
Items Jan-23 Feb-23 Mar-23 Apr-23 May-23 Jun-23 Jul-23 Aug-23
Total Rainfall (mm) 74 263 273 396 792 396 503 255
Total Duration (hours) 28.0 46.5 47.0 79.5 79.5 0.0 102.0 73.5
Rainy Days 13 20 15 18 23 18 26 18

Rainy Days and Rainfall 2023


900 30

800
25
700

600 20

500
15
400

300 10

200
5
100

0 0
Jan-23 Feb-23 Mar-23 Apr-23 May-23 Jun-23 Jul-23 Aug-23

Total Rainfall (mm) Total Duration (hours) Rainy Days


INFRASTRUCTURE
PT STARGATE PASIFIC RESOURCES
SITE FACILITY LAYOUT
OFFICE AREA
(a) (b)

a) PT Stargate Pasific Resources office area which located in Molore Site


b) PT Kalimantan Prima Persada office area which located in Lameruru Site
MESS AREA

(a) (b)

a) PT Stargate Pasific Resources mess area which located in


Molore Site
b) PT Kalimantan Prima Persada mess area which located in
Lameruru Site
SAMPLE PREPARATION & ANALYSIS AREA
(a) (b)

a) Sample preparation area which located in Lameruru Site


b) Sample analysis area which located in Molore Site
MOSQUE AND CANTEEN AREA

(a) (b)

a) Mosque which located in Molore Site


b) Canteen provide meals 3 times a day which located
in Molore Site
WORKSHOP AREA

Workshop area which is located in Molore area


MINI PORT
(a) (b)

Mini port usage is to connect the both of Molore site and Lameruru site
a) Mini port which located in Molore Site
b) Mini port which located in Lameruru Site
CUSTOMER DEMAND
PT Stargate Pasific Resources needs additional units to increase their production to achieve monthly target and yearly
targets. In addition to that, PT Pasific also needs a supports to fullfill ore demand quota from PT IMIP of around 2.500.000
tons / year.

OPPORTUNITY
There are 2 opportunities for PT Tempopress International Delivery to join as a contractor at PT Stargate Pasific Resources:
1. Hauling from Pit to EFO
2. Barging from EFO to Barge

OPERATIONAL ISSUE
The operational issues at PT Stargate Pasific Resources:
1. Pit Molore currently not active, estimated active at 2024
2. Currently there is no radio rig at each unit, No Radio Tower
MANPOWER
1. For the recruitment is handle by each contractors.
2. Contractor salary standards need balanced with other contractors to reduced more issue
3. For all contractors there a weekly meeting for discuss about production
4. For meals, there is canteen that provide day, afternoon, and night meals.
5. For employees PT Stargate Pasific Resources and all contractor employees get Facility following Mess, Meals,
Laundry
6. If we join to PT Stargate Pasific Resources, we plan bring skilled employee like drivers (just in early operation). But,
local employee must be prior.

LOCAL ISSUE
1. Will be priority when recruitment
2. Needed explain to local about professional work