Vitali NHS 4 20
Vitali NHS 4 20
Vitali NHS 4 20
No. of No. of
Designation Hourly Rate Amount (PhP)
Person/s Hour/s
A. Labor
F. Materials
TOTAL 89.17
TOTAL 60.94
TOTAL 14.26
TOTAL 15.16
Structural Concrete for Footing, Footing Tie Beam, Column, Suspended Slab, Girder/Beam
900(1)c1 57.86 cu.m.
(Class A, 3000 psi @ 28 days)
Qty. Length Height/Width Depth Volume
Steel Stair
Foundation (0.50 x 0.50) 4 0.50 0.50 0.30 0.30
Column (0.20 x 0.20) 4 0.20 0.20 0.575 0.09
FOOTING
FC1 1 8.78 0.30 2.63
FC2 1 7.84 0.30 2.35
FC3 3 2.00 2.00 0.30 3.60
FC4 3 2.00 2.00 0.30 3.60
STRAP FOOTING
SF Along Grid 1 1 3.80 0.20 0.30 0.23
SF Along Grid 2 1 3.80 0.20 0.30 0.23
SF Along Grid A 1 2.31 0.20 0.30 0.14
SF Others Vertical 4 2.30 0.20 0.30 0.55
TIE BEAM
TB Along Grid 1 1 11.50 0.20 0.30 0.69
TB Along Grid 2 1 10.94 0.20 0.30 0.66
TB Along Grid A 1 4.73 0.20 0.30 0.28
TB Others TB10, TB11, TB12 & TB13 4 4.70 0.20 0.30 1.13
WALL FOOTING
WF-1 Front Elevation 1 26.59 0.40 0.20 2.13
WF-1 Right Elevation 1 5.83 0.40 0.20 0.47
SLAB ON FILL
At Near Steel Stair 1 2.35 2.20 0.10 0.52
Slab On Fill
At Main Slab Area 1 66.15 0.10 6.62
RAMP
Ramp 1 9.46 0.10 0.95
STAIR ON GRADE
Stair on Grade Front Stair 1 9.10 0.30 0.20 0.55
COLUMN
C1 10 0.40 0.40 8.10 12.96
ROOF BEAM
Roof Beam Along Grid 1 1 11.50 0.20 0.30 0.69
Roof Beam Along Grid 2 1 10.94 0.20 0.30 0.66
Roof Beam Along Grid A 1 4.73 0.20 0.30 0.28
Roof Beam Others B10, B11, B12 & B13 4 4.70 0.20 0.30 1.13
TOTAL 57.86
902(1)a1 Reinforcing Steel (Deformed) Grade 40 8,284.24 kgs.
Bar Diameter Qty. of Member Qty. of Bars Length Total L Unit Wt. Weight
Steel Stair
Footing
Along L 10 4 4 0.650 10.40 0.616 6.41
Along B 10 4 4 0.650 10.40 0.616 6.41
Column
Vert. Bars 12 4 4 1.140 18.24 0.887 16.18
Ties 10 4 5 0.680 13.60 0.616 8.38
FOOTING
FC1
Short Span (T) 16 1 14 2.350 32.90 1.577 51.87
Long Span (T) 16 1 7 4.632 32.42 1.577 51.12
Short Span (B) 16 1 21 2.350 49.35 1.577 77.81
Long Span (B) 16 1 10 4.632 46.32 1.577 73.03
FC2
Short Span (T) 16 1 13 2.350 30.55 1.577 48.17
Long Span (T) 16 1 7 4.162 29.13 1.577 45.94
Short Span (B) 16 1 19 2.350 44.65 1.577 70.40
Long Span (B) 16 1 10 4.162 41.62 1.577 65.62
FC3
Short Span (T) 16 3 7 2.350 49.35 1.577 77.81
Long Span (T) 16 3 7 2.350 49.35 1.577 77.81
Short Span (B) 16 3 10 2.350 70.50 1.577 111.16
Long Span (B) 16 3 10 2.350 70.50 1.577 111.16
FC4
Short Span (T) 16 3 7 2.350 49.35 1.577 77.81
Long Span (T) 16 3 7 2.350 49.35 1.577 77.81
Short Span (B) 16 3 10 2.350 70.50 1.577 111.16
Long Span (B) 16 3 10 2.350 70.50 1.577 111.16
STRAP FOOTING
SF Along Grid 1 0.20 0.30
Horizontal Bar 16 1 4 5.30 21.20 1.577 33.43
Stirrups 10 1 42 0.60 25.20 0.616 15.52
SF Along Grid 2 0.20 0.30
Horizontal Bar 16 1 4 4.89 19.55 1.577 30.82
Stirrups 10 1 38 0.60 22.80 0.616 14.04
SF Along Grid A 0.20 0.30
Horizontal Bar 16 1 4 2.81 11.26 1.577 17.75
Stirrups 10 1 26 0.60 15.60 0.616 9.61
SF Others (Vertical) 0.20 0.30
Horizontal Bar 16 1 4 2.80 11.20 1.577 17.66
Stirrups 10 1 26 0.60 15.60 0.616 9.61
TIE BEAM
TB Along Grid 1 0.20 0.30
Horizontal Bar 16 1 4 13.85 55.40 1.577 87.35
Stirrups 10 1 144 0.60 86.40 0.616 53.21
TB Along Grid 2 0.20 0.30
Horizontal Bar 16 1 4 13.29 53.17 1.577 83.84
Stirrups 10 1 144 0.60 86.40 0.616 53.21
TB Along Grid A 0.20 0.30
Horizontal Bar 16 1 4 5.88 23.53 1.577 37.10
Stirrups 10 1 66 0.60 39.60 0.616 24.39
TB Others (Vertical) 0.20 0.30
Horizontal Bar 16 4 4 5.85 93.60 1.577 147.58
Stirrups 10 4 66 0.60 158.40 0.616 97.56
WALL FOOTING
WF-1 Front Elevation
Continuous Bar 10 1 3 26.59 79.77 0.616 49.13
Bottom Bars 10 1 89 0.55 48.95 0.616 30.15
Vertical Bar 10 1 45 0.69 31.19 0.616 19.21
WF-1 Right Elevation
Continuous Bar 10 1 3 5.83 17.48 0.616 10.76
Bottom Bars 10 1 20 0.55 11.00 0.616 6.77
Vertical Bar 10 1 10 0.69 6.93 0.616 4.27
COLUMN
C1 0.400 0.400
Vert. Bars 20 10 12 8.785 1054.20 2.464 2,597.17
Ties 1 10 10 57 1.480 843.60 0.616 519.58
Ties 2 10 10 57 0.520 296.40 0.616 182.56
Bar Diameter Qty. of Member Qty. of Bars Length Total L Unit Wt. Weight
Bar Diameter Qty. of Member Qty. of Bars Length Total L Unit Wt. Weight
ROOF BEAM
Roof Beam Along Grid 1 0.20 0.30
Horizontal Bar 16 1 4 13.92 55.68 1.577 87.79
Stirrups 10 1 144 0.88 126.72 0.616 78.05
Roof Beam Along Grid 2 0.20 0.30
Horizontal Bar 16 1 4 13.29 53.17 1.577 83.84
Stirrups 10 1 144 0.88 126.72 0.616 78.05
Roof Beam Along Grid A 0.20 0.30
Horizontal Bar 16 1 4 5.88 23.53 1.577 37.10
Stirrups 10 1 66 0.88 58.08 0.616 35.77
Roof Beam Others (Vertical) 0.20 0.30
Horizontal Bar 16 4 4 5.85 93.60 1.577 147.58
Stirrups 10 4 66 0.88 232.32 0.616 143.09
SLABS
Slab on Grade
(13.22m x 5.10m) (Average Length) 13.22 5.10
no. of
Main Bar Bar Diameter spacing Length Total Length Unit Wt. Weight
pieces
Along Long Span 10 0.50 10 13.22 132.20 0.616 81.42
Along Short Span 10 0.50 26 5.10 132.60 0.616 81.67
(2.35m x 2.20m) 2.350 2.200
no. of
Main Bar Bar Diameter spacing Length Total Length Unit Wt. Weight
pieces
Along Long Span 10 0.5 4 2.35 9.40 0.616 5.79
Along Short Span 10 0.5 5 2.20 11.00 0.616 6.77
Main Bar (Top) Bar Diameter spacing no. of pieces Length Total Length Unit Wt. Weight
Main Bar (Top) Bar Diameter spacing no. of pieces Length Total Length Unit Wt. Weight
Main Bar (Top) Bar Diameter spacing no. of pieces Length Total Length Unit Wt. Weight
Main Bar (Top) Bar Diameter spacing no. of pieces Length Total Length Unit Wt. Weight
Main Bar (Top) Bar Diameter spacing no. of pieces Length Total Length Unit Wt. Weight
Main Bar (Top) Bar Diameter spacing no. of pieces Length Total Length Unit Wt. Weight
Main Bar (Top) Bar Diameter spacing no. of pieces Length Total Length Unit Wt. Weight
TOTAL 8,284.24
TOTAL 296.10
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel) 116.58 sq.m.
GROUND FLOOR
Horizontal 1 5.30 3.10 16.43
Interior Wall Less W-2 1 0.70 0.60 0.42
(Above GFFL to 2nd GL A-B/1-2 24.95
Floor) Vertical 1 5.35 3.10 16.59
Less D-2 3 1.00 2.55 7.65
Above WF-1 Along Grid 2 Horizontal 1 13.09 0.60 7.85 7.85
2ND FLOOR
Perimeter Wall GL A-B/1 1 2.34 2.70 6.32
Front Elevation 4.11
(2nd Floor - Roof) Less W-3 1 1.70 1.30 2.21
Horizontal 1 3.11 2.70 8.40
6.89
Less D -3 1 0.70 2.15 1.51
GL A-B/1-2
Vertical 1 4.70 2.70 12.69
10.54
Less D -1 1 1.00 2.15 2.15
Horizontal 1 5.20 2.70 14.04
Less W-1 1 1.40 1.20 1.68 10.21
GL A-B/2-3 Less D -1 1 1.00 2.15 2.15
Vertical 1 4.46 2.70 12.04
10.54
Less D -3 1 0.70 2.15 1.51
Interior Wall
Horizontal 1 5.20 2.70 14.04
(2nd Floor - Roof)
Less W-1 1 1.40 1.20 1.68 10.21
GL A-B/3-4 Less D -1 1 1.00 2.15 2.15
Vertical 1 4.46 2.70 12.04
10.54
Less D -3 1 0.70 2.15 1.51
Horizontal 1 5.20 2.70 14.04
Less W-1 1 1.40 1.20 1.68 10.21
GL A-B/4-5 Less D -1 1 1.00 2.15 2.15
Vertical 1 4.46 2.70 12.04
10.54
Less D -3 1 0.70 2.15 1.51
TOTAL 116.58
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel) 147.04 sq.m.
GROUND FLOOR
Left Elevation 1 7.14 3.30 23.56
Perimeter Wall (GF-2F) Rear Elevation 1 12.70 3.30 41.91 77.02
Right Elevation 1 3.50 3.30 11.55
2ND FLOOR
Left Elevation 1 7.14 3.00 21.42
Perimeter Wall (2F - Roof) Rear Elevation 1 12.70 3.00 38.10 70.02
Right Elevation 1 3.50 3.00 10.50
TOTAL 147.04
WALLS
CHB 2 263.62 527.24
ADDITIONAL AREA
Exposed Underside of Concrete
1 3.04
CL-1 Ground Floor 5.98
1 2.94
DEDUCTIVE AREA
Below Ground 2 13.09 0.20 5.24
Front Elevation
NGL - GFFL 1 13.09 0.40 5.24
Below Ground 2 7.14 0.20 2.86
Left Elevation
NGL - GFFL 1 7.14 0.40 2.86
29.14
Below Ground 2 12.70 0.20 5.08
Rear Elevation
NGL - GFFL 1 12.70 0.40 5.08
Below Ground 2 3.50 0.20 1.40
Right Elevation
NGL - GFFL 1 3.50 0.40 1.40
TOTAL 504.08
1021(1)a Cement Floor Finish 9.46 sq.m.
Location Qty. Length Height/Width Area
GROUND FLOOR
TOTAL 100.93
1003(1)a1 Carpentry and Joinery Works, 4.5mm Fiber Cement Board Ceiling on Metal Frame 129.46 sq.m.
Qty Width Length Area
1 3.823
CL-2, 4.5mm thk. Fiber Cement Board Ceiling on Metal Ground Floor
1 57.700
Furring
Second Floor 1 67.939
TOTAL 108.53
1008(1)a Aluminum Glass Windows, Sliding Type 5.64 sq.m.
Location Qty Width Height Area
W-1 Bedrooms 3 1.40 1.20 5.04
W-3 Bedrooms 1 0.50 1.20 0.60
50mm x 100mm Hardwood Jamb for D-1 Bedrooms 4 5.20 11.02 44.07
50mm x 100mm Hardwood Jamb for D-3 T&B 4 4.90 10.38 41.53
TOTAL
LOCKSET 11 pcs
HINGES 44 pcs
SECOND FLOOR
R-1
Horizontal 1 2.85 0.00036 7842 8.05
(2 x 4 x 1.2)
Vertical 4 0.87 0.00036 7842 9.82
(1 x 1 x 1.2) Horizontal 4 2.85 0.00012 7842 10.38
R-2
Horizontal 1 2.85 0.00036 7842 8.05
(2 x 4 x 1.2)
Vertical 4 0.87 0.00036 7842 9.82
(1 x 1 x 1.2) Horizontal 4 2.85 0.00012 7842 10.38
R-3
Horizontal 1 2.90 0.00036 7842 8.19
(2 x 4 x 1.2)
Vertical 4 0.87 0.00036 7842 9.82
(1 x 1 x 1.2) Horizontal 4 2.90 0.00012 7842 10.57
R-4
Horizontal 1 1.08 0.00036 7842 3.05
(2 x 4 x 1.2)
Vertical 2 0.87 0.00036 7842 4.91
(1 x 1 x 1.2) Horizontal 4 1.08 0.00012 7842 3.94
R-5
Horizontal 1 1.53 0.00036 7842 4.32
(2 x 4 x 1.2)
Vertical 2 0.87 0.00036 7842 4.91
(1 x 1 x 1.2) Horizontal 4 1.53 0.00012 7842 5.57
MAIN STAIR RAILINGS
Qty
a. 50 mm Ø G.I. pipe Handrail Length No. of Pieces Area for Painting
Member
Horizontal 1 4.80 0.754
Paint Finished Vertical 8 0.90 4.00 1.131
Inclined 1 10.14 1.593
RAMP RAILINGS
Qty Area for
Length Total Length No. of Pieces
a. 32mmØ Stainless Steel Pipe Handrail Member Painting
Horizontal 2 4.98 9.96 1.001
Vertical 16 1.00 16.00 1.608
Paint Finished 11
Inclined 8 5.07 40.56 4.078
End Handrail 2 0.51 1.03 0.103
SUB-TOTAL
a. 2" x 4" x 1.2mm Rectangular Tube Total Weight 70.94
b. 1" x 1" x 1.2mm Square Bar Total Weight 40.85
c. 19mm x 19mm Square Bar Total Weight 215.55
c. 50mmØ G.I. Pipe No. of Pieces 4
d. 32mmØ Stainless Steel Pipe No. of Pieces 11
Number of
Qty Length Height/Width Area Total Area
Sides
DOOR JAMBS
Sides 2 0.20 2.10 3.36
D-1 4
Top 1 1.00 0.20 0.80
Sides 2 0.20 2.10 2.52
D-2 3 11.20
Top 1 1.00 0.20 0.60
Sides 2 0.20 2.10 3.36
D-3 4
Top 1 0.70 0.20 0.56
TOTAL 55.65
1032(1)c Metal Painting 276.32 sq.m.
Area
Structural Steel, Truss 84.90
Structural Steel, Purlins 109.18
Metal Structure Accessories, Sagrods 1.18
Metal Structure Accessories, Bolts 0.81
Metal Structure Accessories, Cross Bracing 2.46
Metal Structure Accessories, Steel Plates 5.63
Metal Structure Accessories, Fascia Frame 4.23
Rafter 17.87
Railings 28.27
STEEL STAIR 21.80
1014(1)b2 Prepainted Metal Sheets, Rib Type, Long Span 108.53 sq.m.
Qty Length Width Area
0.40mm Thick (Base Metal Thickness) G.I. Roofing Sheet, Rib-Type 1 7.69 14.11 108.53
TOTAL 108.53
TOTAL 13.20
TOTAL 13.73
Truss 01 5 units
Strut - 2 3 units
Strut - 3 1 units
Strut - 4 3 units
TOTAL 16.00
SKIRT ROOF
Steel Plate - 3.5mm Thick (0.25m x 0.15m) 10 0.0035 0.0375 7842 10.29 0.75
STEEL STAIR
(160 x 210 x 8) 6 0.008 0.03360 7842 12.65 0.40
Gusset Plate
(75 x 150 x 10) 10 0.010 0.01125 7842 8.82 0.22
Spider Plate - 12mm 100Wide x 220Long 2 0.012 0.02200 7842 4.14 0.09
Base Plate - 8mm (150 x 150) 4 0.008 0.02250 7842 5.65 0.18
SKIRT ROOF
Area for
Rafter Qty Length Area Unit Wt Weight
Painting
1
2" x 6" x 1.2mm Rectangular
Horizontal 5 1.20 0.00048 7842 22.68 2.44
Tube
Inclined 5 1.25 0.00048 7842 23.62 2.54
1
2" x 3" x 1.0mm Rectangular
Tube
4 12.69 0.00025 7842 99.51 12.89
Prepared By:
FIITTINGS
PIPE DIAMETER
90 Degree Elbow 9
3 inches Tee 7
P Trap (Floor Drain) 6
90 Degree Elbow 7
Wye 4
1/8 Bend 17
4 inches 4x2 Tee 9
4x3 Wye 4
4 x 3 Coupling Reducer 2
Clean Out (CO) 2
Prepared By:
FIITTINGS
PIPE DIAMETER
Threaded Elbow (female) 19
1/2" ∅
90 deg plain elbow 13
Prepared By:
Prepared By:
TOTAL 90.97
As Submitted
As Submitted
As Submitted
As Submitted
As Submitted
As Submitted
As Submitted
As Submitted
As Submitted
As Submitted
As Submitted
As Submitted
As Submitted
As Submitted
As Evaluated
As Evaluated
As Evaluated
As Evaluated
As Evaluated
As Evaluated
As Evaluated
As Evaluated
As Evaluated
As Evaluated
As Evaluated
As Evaluated
As Evaluated
As Evaluated
As Evaluated
CIVI EAR Removal Individ- Shoring, Micro Struc- Em- Em- Lean TOTAL PLAI Struc- Struc- Rein- Rein- Form TOTAL
L, TH of Struc- ual Re- Cribbing Piles In ture Ex- bank- bank- Concrete OF PART N tural tural forcing forcing works OF PART
ME WO tures moval of and Drilled cavation ment ment (Manual A AN Concrete Concrete Steel Steel and B
CHA RKS and Ob- Trees Drain Holes, (Com- from from mixing) D (Class B, (Ready (De- (De- False
NIC struction (150mm Excava- 0.20m mon Road- Com- RE- 2500 psi Mix, formed), formed), works
AL, dia - tion 12' (or- Soil) way/ mon IN- @ 28 Class Grade Grade
ELE 300mm dinary Struc- Borrow, FOR days) AA/ 40 60
CTR dia) soil ture Ex- Selected CED Class
ICAL condi- cava- Borrow CO A/Class
AN tion) tion, NCR B/Class
D Com- ETE C/Class
SAN mon Soil WO P/Seal
ITA RKS Con-
RY/ crete, 7
PLU days/14
MB- days/28
ING days)
WO
RKS
(Pro (Pro PAR PAR 801(1) 800(3) 803(4)a 1052(28 803(1)a 804(1)a 804(2)a 901(1) PAR 900(2)c 900 902(1)a 902(1)b 903(2)
ject ject T III T A a1 )a TB
ID) Co
mp
one
nt
ID -
De- Column E Column F Column G Column H Column I Column J Column K Column L Column M
scri
ptio Column N Column O Column P Column Q Column R Column S Column T Column U
n)
Construction of 4-Storey, 20-Classroom School Building at Vitali National High School, Zamboanga City
B.3 (1) Permits and Clearances 1.00 l/s Including payment for blueprinting for permits
B.4(10) Miscellaneous Survey and Staking 1.00 l/s Including preparation of as-stake plan
800(3) a1 Individual Removal of Trees (150mm dia - 300mm dia) 3.00 ea Refer to Plan
804(2)a Embankment from Common Borrow, Selected Borrow 70.95 cu.m. Use selected borrow for embankment
900(2)c Structural Concrete (Class B, 2500 psi @ 28 days) 68.44 cu.m. Refer to Plan. fc' 17.5 Mpa (2500 psi)
902(1)a Reinforcing Steel (Deformed), Grade 40 69,106.84 kgs. Refer to Plan. fy' 275 Mpa (40000 psi)
902(1)b Reinforcing Steel (Deformed), Grade 60 146,513.02 kgs. Refer to Plan. fy' 420 Mpa (60000 psi)
PART C FINISHING
C.1 Termite Control Works
1003(1)a1 4.5mm Fiber Cement Board on Metal Frame Ceiling 570.39 sq.m. Refer to Plan
1010(1) Wooden Frames 113.00 set Refer to Plan. 50mmx150mm Good Lumber Jamb
1004(2) Finishing Hardware (Lockset and Hinges) 1.00 l/s Refer to Plan. 4 units per door
1005(1) Casement Steel Window (Awning Type) 11.52 sq.m. Refer to Plan
1005(1) Residential Casement Window (Steel)- Swing type 172.80 sq.m Refer to Plan
1032(1)c Painting Works (Steel Painting) 1,334.44 sq.m. Refer to Plan. (Includes roofing materials)
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll) 55.00 ln.m. Refer to Plan
1013(2)b Fabricated Metal Roofing Accessory (Flashings) 18.92 ln.m. Refer to Plan
1100(18) Wires and Wiring Devices (20 CL) 1.00 l/s Refer to Plan
1102(21) Power Load Center, Switchgear, and Panel Boards (20 CL) 1.00 l/s Refer to Plan
1103(1) Lighting Fixtures (20 CL) 1.00 l/s Refer to Plan (Includes a Ceiling Fan)
1208(1) Fire Alarm System (20 CL) 1.00 l/s Refer to Plan
Project Title: Construction of 4 STOREY 20 CLASSROOMS VITALI NATIONAL HIGHSCHOOL ,Zamboanga City
Qty. Length (ft) Total Length (ft) Area (sq.in) TOTAL BD.FT
1" x 8" Coconut Planks - Cistern Tank Along Short Span 30 19.16 574.656 8.00 383.10
Along Long Span 30 35.56 1066.656 8.00 711.10
TOTAL 1094.21
WALL FOOTING
WF-1 2 21.023 0.5 0.3 6.3069
COLUMNS
C1 (FOOTING TO GROUND) 13 3.20 0.67 0.67 18.67424
C1 (GROUND TO 2ND FLOOR) 13 3.15 0.60 0.60 14.742
C1 (2ND TO 3RD FLOOR) 13 3.15 0.60 0.60 14.742
C1 (3RD TO 4TH FLOOR) 13 3.15 0.60 0.60 14.742
C1 (4TH TO ROOF DECK LEVEL) 13 3.15 0.60 0.60 14.742
C3 (FOOTING TO GROUND)
C3 (GROUND TO 2ND FLOOR) 13 3.25 0.67 0.67 18.966025
C3 (2ND TO 3RD FLOOR) 13 3.15 0.60 0.60 14.742
C3 (3RD TO 4TH FLOOR) 13 3.15 0.60 0.60 14.742
C3 (4TH TO ROOF DECK LEVEL) 13 3.15 0.60 0.60 14.742
13 3.15 0.60 0.60 14.742
SLAB
SECOND FLOOR
S1 (ALONG GRID 1 AND 13) 2 2.67 3.2 0.1 1.7088
S1 (ALONG GRID 2 TO 12)/C 10 2.17 3.5 0.1 7.595
S1 (ALONG GRID 2 TO 12)/B 10 2.17 3.35 0.1 7.2695
LAVATORY HANDWASH
Lavatory 2 2.063 0.4 1.6504
Slab 2 9.3 0.1 1.86
COMBINED FOOTING
CF-1 13 4.00 5.10 0.45 119.34
FOOTING TIE BEAM
FTB-1 (ALONG GRID 1 AND 13/A) 2 2 4.33 0.40 6.93
FTB-1 (ALONG GRID 3/A-C) 10 2 3.83 0.40 30.64
FTB-1A 4 2 4.33 0.40 13.86
FTB-2 (ALONG GRID 3-11) 9 2 6.33 0.40 45.58
FTB-2 (ALONG GRID 3-11/A) 13 2 1.83 0.40 19.03
FTB-2A 4 2 6.33 0.40 20.26
COLUMN
C1 (FOOTING TO GROUND) 13 4 3.25 0.67 113.23
C1 (GROUND TO 2ND FLOOR) 13 4 3.15 0.6 98.28
C1 (2ND TO 3RD FLOOR) 13 4 3.15 0.6 98.28
C1 (3RD TO 4TH FLOOR) 13 4 3.15 0.6 98.28
C1 (4TH TO ROOF DECK LEVEL) 13 4 3.15 0.6 98.28
SLABS
SLAB ON FILL 1 4 129 0.10 51.60
SECOND FLOOR
S1
S1 (ALONG GRID 1/C) 1 4 16.4 0.23 14.76
S1 (ALONG GRID 13/C) 1 4 16.3 0.23 14.67
S1 (ALONG GRID 2-12/C) 10 4 16 0.23 144.00
S1 (ALONG GRID 2-12/B) 10 4 16.6 0.23 149.40
S2
S2 (ALONG GRID 1 AND 13/A) 1 4 15 0.23 13.50
S2 (ALONG GRID 2-12/A) 1 4 14 0.23 12.60
S3
S3 (ALONG GRID 1 AND/B) 2 4 10.7 0.23 19.26
THIRD FLOOR
S1
S1 (ALONG GRID 1/C) 1 4 16.4 0.23 14.76
S1 (ALONG GRID 13/C) 1 4 16.3 0.23 14.67
S1 (ALONG GRID 2-12/C) 10 4 16 0.23 144.00
S1 (ALONG GRID 2-12/B) 10 4 16.2 0.23 145.80
S2
S2 (ALONG GRID 1 AND 13/A) 1 4 15 0.23 13.50
S2 (ALONG GRID 2-12/A) 1 4 14 0.23 12.60
S3
S3 (ALONG GRID 1 AND 13/B) 2 4 10.7 0.23 19.26
FOURTH FLOOR
S1
S1 (ALONG GRID 1/C) 1 4 16.4 0.23 14.76
S1 (ALONG GRID 13/C) 1 4 16.7 0.23 15.03
S1 (ALONG GRID 2-12/C) 10 4 16 0.23 144.00
S1 (ALONG GRID 2-12/B) 10 4 16.2 0.23 145.80
S2
S2 (ALONG GRID 1 AND 13/A) 1 4 15 0.23 13.50
S2 (ALONG GRID 2-12/A) 1 4 14 0.23 12.60
S3
S3 (ALONG GRID 1 AND 13/B) 2 4 10.7 0.23 19.26
ROOF DECK
S4
S4 (ALONG GRID 1 AND 13/C) 2 4 16.4 0.23 29.52
STAIRWAY
LENGTH WIDTH AREA
GROUND FLOOR- SECOND FLOOR 2 2.4 1.58 7.56
SECOND FLOOR -THIRD FLOOR 2 2.4 1.58 7.56
THIRD FLOOR - FOURTH FLOOR 2 2.4 1.58 7.56
FOURTH FLOOR - LANDING 2 2.4 1.58 7.56
LANDING- ROOF DECK 2 2 1.58 6.3
RC BEAMS
RC BEAMS (SECOND FLOOR LEVEL)
G1 9 3 7 0.40 75.60
G1-A 9 3 2.5 0.40 27.00
G1-B 4 3 2.5 0.40 12.00
G1-C 4 3 7 0.40 33.60
G2 (ALONG GRID 3/A AND GRID C) 2 3 4.5 0.25 6.75
G2 (ALONG GRID 1 AND 13/A AND C) 20 3 5 0.25 75.00
G3 (ALONG GRID 1 AND13/B) 2 3 5 0.40 12.00
G3 (ALONG GRID 3/B ) 10 3 4.5 0.40 54.00
B1 (ALONG GRID C) 2 3 4.77 0.25 7.15
B1 (ALONG GRID 1 AND 13) 2 3 3.85 0.25 5.78
B1 (ALONG GRID 3 AND 11) 10 3 4.5 0.25 33.75
B2 1 3 9.79 0.25 7.34
CB-1 3 3 1.005 0.25 2.26
MEDIA AGUA
30 3.9 1.19 139.23
HANDWASH
Platform 2 12.8 0.1 2.56
RC Wall 20 0.4 0.65 5.2
Countertop 2 6.1 0.4 4.88
RAMP
2 0.8659 1.73
4.60
1046(2)a1 100mm CHB Non-Load Bearing (including Reinforcing Steel) 291.54 sq.m.
TOTAL AREA
GROUND FLOOR 145.75
SECOND FLOOR 145.75
THIRD FLOOR 145.75
FOURTH FLOOR 145.75
ROOF DECK 8.4
LESS AREA QTY
D-1 -10.00 1.89 -18.90
d-2 -8.00 1.68 -13.44
bd-1 -19.00 0.78 -14.82
CT-1
9.60
TOTAL 291.53
1046(2)a2 150mm CHB Non-Load Bearing (including Reinforcing Steel) 2096.64 sq. m.
QTY LENGTH WIDTH TOTAL AREA
SIDE ELEVATION 2 68.3 136.60
FRONT ELEVATION(PARAPHET IS EXCLUDED) 1 412.51 412.51
REAR ELEVATION 1 550.3 550.30
PARAPHET AT GF 1 36.96 36.96
PARAPHET AT 2ND, 3RD AND 4TH Span 5m 6 1.851 11.11
Span 4.5m 40 1.561 62.44
Span 2.5m 6 0.7612 4.57
CLASSROOMS GF 1 257.57 257.57
CLASSROOMS 2ND, 3RD AND 4TH 3 210.74 632.22
TOTAL 2,096.64
EXPOSED BEAM (ALONG GRID 1, 2, 12, 13) 8.00 1.6 9.50 121.60
EXPOSED BEAM ( ALONG GRID 3 TO 11)
SECOND FLOOR AND THIRD FLOOR 9.00 1.6 9.50 136.80
TOTAL 8,628.84
SECOND FLOOR
FL-1 1 317.88
FL-2 1 470.54
THIRD FLOOR
FL-1 1 317.88
FL-2 1 470.54
FOURTH FLOOR
FL-1 1 317.88
FL-2 1 470.54
TOTAL 3,275.87
196.74
1018(2) Unglazed Tiles 95.00 sq.m.
Qty Width Length Area
GROUND FLOOR (SHE TOILET) - FL3 1 3.150 3.855 12.14
GROUND FLOOR (HE TOILET) - FL3 1 3.150 3.855 12.14
TOTAL 94.98
TOTAL 262.77
1003(1)a1 4.5mm Fiber Cement Board on Metal Frame Ceiling 570.39 sq.m.
Qty Width Length Total Area
GROUND FLOOR (TOILET) 18.47
GROUND FLOOR (PWD) 6.38
TOTAL 570.39
TOTAL 522.50
TOTAL 0.00
TOTAL 172.80
1005(1) Casement Steel Window (Awning Type) 11.52 sq.m.
Qty LENGTH WIDTH Area
TOTAL 11.52
TOTAL 78.00
TOTAL 40.08
1006(6) Steel Doors and Frames 3.52 sq.m
Qty LENGTH WIDTH Area
TOTAL 3.52
1010(2)b Wooden Panel Door 75.60 sq.m.
Qty Width Height Area
D-1 40 0.9 2.1 75.60
TOTAL 75.60
Bunk House
Length Width/Height Thickness Area (sq.m) Volume
1/2" thk. Marine Plywood 2.85 4.2 11.970
Rough Concrete Flooring 1.2 1.8 0.0508 2.16 0.11
1/4" thk. Plywood
Flooring 3.7 4.2 13.38
Length A (sq. m)
Interlink Wire #12 x 3" 3.5145
GA. #26 Corr. G.I. Sheets 16.2
GA. #26 Corr. G.I.Ridge Roll 5.35
TOTAL 349.15
TOTAL 18.92
RIDGE ROLL 55
TOTAL 55.00
1014(1)b2 Prepainted Metal Sheet, Rib Type, Long Span 351.25 sq.m.
Qty Length Width Area
0.40mm THK Corrugated G.I. Sheets - Long Span (ALONG GRID 2-12) 1 45 2 90.00
0.40mm THK Corrugated G.I. Sheets - Long Span (ALONG GRID 1-13) 1 55.00 4.75
261.25
TOTAL 351.25
TOTAL -
120.48 6.82
TRUSS 1
2∠'s - 6mm THK x 75mm x 75mm Angle Bar Top Chord 18 5.54 0.0018 7849 1408.02488892 29.90
2∠'s - 6mm THK x 75mm x 75mm Angle Bar Bottom Chord 9 9.68 0.0018 7849 1230.848784 26.14
2∠'s - 6mm THK x 50mm x 50mm Angle Bar Vertical 18 5.2793 0.0056 7849 4176.87235056 19.01
2∠'s - 6mm THK x 75mm x 75mm Angle Bar Vertical 9 2.93 0.0018 7849 373.03110306 7.92
2∠'s - 6mm THK x 75mm x 75mm Angle Bar Diag. Web 18 5.72 0.0018 7849 1454.10542604 30.88
2∠'s - 6mm THK x 50mm x 50mm Angle Bar Diag. Web 18 3.09 0.0056 7849 2443.31960544 11.12
TRUSS 2
2∠'s - 6mm THK x 75mm x 75mm Angle Bar Top Chord 2 7.74 0.0018 7849 218.704536 4.64
2∠'s - 6mm THK x 75mm x 75mm Angle Bar Bottom Chord 2 6.30 0.0018 7849 178.01532 3.78
2∠'s - 6mm THK x 50mm x 50mm Angle Bar Vertical 2 34.57 0.0056 7849 3039.007216 13.83
2∠'s - 6mm THK x 75mm x 75mm Angle Bar Vertical 2 14.40 0.0018 7849 406.89216 8.64
2∠'s - 6mm THK x 75mm x 75mm Angle Bar Diag. Web 2 29.92 0.0018 7849 845.431488 17.95
2∠'s - 6mm THK x 50mm x 50mm Angle Bar Diag. Web 2 28.18 0.0056 7849 2477.269984 11.27
Joint Connector (Purlin to Top Chord) TRUSS 1 Qty L Area Unit Wt Weight Area for Painting
125 x 125 x 50mm Steel Joint Connector (6mm Thick) 36 0.1500 0.00075 7849 31.79 1.35
Joint Connector (Purlin to Top Chord) TRUSS 2 Qty L Area Unit Wt Weight Area for Painting
125 x 125 x 50mm Steel Joint Connector (6mm Thick) 264 0.1500 0.00075 7849 233.12 9.90
Machine bolts 6mm dia × 400 mm long 206 0.04 0.00003 7849 1.83 0.16
TOTAL 245.95
TOTAL 44
Base plate 300mm x 300mm x 12mm 62 0.0012 0.09 7849 52.56 11.16
Base plate 200mm x 300mm x 12mm 26 0.0012 0.06 7849 14.69 3.12
10mmn thk x 100mm x 300mm Steel Plate 24 0.01 0.03 7849 56.51 1.44
10mm x 200mm x 300mm Steel Plate (APEX) 11 0.01 0.06 7849 51.80 1.32
6mm thk Gusset Plate 11 DETAIL 1 0.006 0.12 7849 62.16 2.64
6mm thk Gusset Plate 11 DETAIL 2 0.006 0.16 7849 82.89 3.52
6mm thk Gusset Plate 73 DETAIL 3 0.006 0.0625 7849 214.87 9.13
6mm thk Gusset Plate 62 DETAIL 4 0.006 0.0375 7849 109.49 4.65
150 x 150mm x 6mm thk- Splice Plate Connector (Every 6m) 9 6.00 0.00090 7849 381.46 13.50
RAMP
50mm dia. l Pipe 4 13.5 54 8.48
2 19.2 38.4
26
50mm dia. Vertical Railing 68 0.9 61.2 9.61
6 0.15 0.9
STAIRWAY
GROUND FLOOR 4 3.15 12.6 3 1.98
SECOND FLOOR 4 3.15 12.6 3 1.98
THIRD FLOOR 50mm dia. G.I. Pipe 4 3.15 12.6 3 1.98
FOURTH FLOOR 4 3.15 12.6 3 1.98
ROOF DECK 4 3.15 12.6 3 1.98
WINDOW GRILLE
W1- HORIZONTAL 40 27.62 1104.8 185 53.03
12mm square bar
W1- VERTICAL 40 6.27 250.8 42 12.04
303.40
TOTAL LENGTH 4740.99
SUMMARY
50mm dia. G.I. Pipe 94
12mm SQ BAR 8039.1749908
19mm SQ BAR 4335.646192416
0.00
GRAB BAR 4
GRAVEL FILL
SEPTIC VAULT 2 5.6 2.8 0.1 3.136
Slab BOTTOM
LONG SPAN 2 16 11 5.75 126.5 1.58 199.90
SHORT SPAN 2 16 21 2.95 123.90 1.58 195.79
SIDE WALL
HOR BAR 2 16 8 16.00 256 1.58 404.54
VER BAR 2 16 56 2.00 224 1.58 353.98
QTY l H AREA
TOTAL 125.27
WATER PROOFING
Sidewall 93.91
Top Slab and Bottom Slab (Inner) 31.36
TOTAL 125.27
TOTAL EXCAVATION
GRAVEL FILL 1 8 2.5 0.1
TOTAL GRAVEL FILL
REBARS Bar Diameter Qty of Member Qty of Bars Length Total L Weight/Meter
CTS1
LONG SPAN 12 1 36 8.82 317.52 0.89
SHORT SPAN 12 1 68 3.82 259.76 0.89
CTB
TOP AND BOT BARS 10 3 6.00 3.30 59.4 0.62
TIES 10 3 62 1.23 228.78 0.62
MANHOLE
HOR BARS 12 1 3 3.80 11.4 0.89
VER. BARS 12 1 16 0.30 4.8 0.89
BOT SLAB
TOP BARS 16 1 30 8.75 262.5 1.58
BOT BARS 16 1 70 3.75 262.5 1.58
TEMP BARS 12 2 12 3.00 72 0.89
STEEL PLATES
Thickness Qty Length Area Unit Weight Total Weight
GA 16 Stainless Steel Sheet Plate w/ Hinges and Lock 2 0.80 0.00 7849 60.28
Total Area
WATER PROOFING
3- PLY MEMBRANE WATER PROOFING
68.262
NON TOXIC WATER PROOFING
Exterior Slab 26.56
Interior 57.21
152.032
Pcs
Float Valve 1
Qty L Area Unit Wt Weight
Stainless Steel Ladder Rungs 2 0.4 0.11 7849 690.712
Leaching Chamber 0
total area 0.00
1001(5)a Catch Basin (Concrete) 24 each
QTY L W H VOLUME
CATCH BASIN 24 0.6 0.6 1.2 10.368
EXCAVATION - CATCH BASIN TOTAL EXCAVATION C.B 10.368
TOTAL 2.4
CONCRETE
TOP 1 0.6 0.6 0.1 0.036
BOTTOM 1 0.6 0.6 0.1 0.036
TOTAL 0.072
TOTAL 2.4
REBARS- CATCH BASIN QTY BAR DIA BAR QTY. LENGTH TOTAL LENGTH KGS/LENGTH KGS
TOP 1 12 4 0.75 3 0.889 2.67
BOTTOM 1 12 4 0.75 3 0.889 2.67
HORIZONTAL BARS 1 10 3 1.2 3.6 0.617 2.22
TOTAL REBARS KGS 7.56
Lavatory 8 sets
Floor Drain 39 pcs
Sink Drain 10 pcs
Urinal Drain 4 pcs
Water Closet 20 sets
pcs
TOTAL: 281.00
MANHOLE 2
TOTAL: 245.00
FORM ABC-2015-02-00
Construction of 4-Storey, 20-Classroom School Building at Vitali National High School, Zamboanga City
(Project ID)
(Project Component ID - Description)
CIVIL, MECHANICAL, ELECTRICAL AND
PART III
SANITARY/PLUMBING WORKS
AS SUBMITTED 5,496,636.64 18.00% 989,394.59 324,301.56 1,313,696.16 6,810,332.80
PART A EARTHWORKS
AS EVALUATED
MARCO C. MIGUEL CAROLYN M. ORBECIDO ROBERTO DONDI F. STA. ELENA JUL-ARAB A. KONG
Engineer II Engineer III Assistant District Engineer District Engineer
Planning and Design Section Chief,Planning and Design Section
``
ZAMBOANGA CITY DISTRICT ENGINEERING OFFICE
FORM ABC-2015-02A-00
Construction of 4-Storey, 20-Classroom School Building at Vitali National High School, Zamboanga City
AS SUBMITTED 1.00 l/s 9,845.04 18% 1,772.11 580.86 2,352.96 12,198.00 12,198.00
B.4(10) Miscellaneous Survey and Staking
AS EVALUATED
AS SUBMITTED 1.00 l/s 257,025.85 10% 25,702.59 14,136.42 39,839.01 296,864.86 296,864.86
B.7(1) Occupational Safety and Health Program
AS EVALUATED
AS SUBMITTED 1.00 l/s 142,150.75 18% 25,587.13 8,386.89 33,974.03 176,124.78 176,124.78
B.20 (1) Temporary Fence
AS EVALUATED
AS SUBMITTED 1.00 l/s 780,111.29 18% 140,420.03 46,026.57 186,446.60 966,557.88 966,557.88
803(4)a Shoring, Cribbing and Drain Excavation
AS EVALUATED
Micro Piles In Drilled Holes, 0.20m 12' (ordinary soil AS SUBMITTED 507.00 m 3,431,322.73 18% 617,638.09 202,448.04 820,086.13 4,251,408.86 8,385.42
1052(28)a
condition) AS EVALUATED
AS SUBMITTED 1,208.65 cu.m. 317,242.15 18% 57,103.59 18,717.29 75,820.87 393,063.02 325.21
803(1)a Structure Excavation (Common Soil)
AS EVALUATED
Embankment from Roadway/Structure Excavation, Common AS SUBMITTED 1,115.09 cu.m. 224,127.87 18% 40,343.02 13,223.54 53,566.56 277,694.43 249.03
804(1)a
Soil AS EVALUATED
AS SUBMITTED 70.95 cu.m. 71,907.49 18% 12,943.35 4,242.54 17,185.89 89,093.38 1,255.72
804(2)a Embankment from Common Borrow, Selected Borrow
AS EVALUATED
AS SUBMITTED 107.67 cu.m. 663,583.04 18% 119,444.95 39,151.40 158,596.35 822,179.38 7,636.08
901(1) Lean Concrete (Manual mixing)
AS EVALUATED
AS SUBMITTED 68.44 cu.m. 504,607.55 18% 90,829.36 29,771.85 120,601.21 625,208.76 9,134.75
900(2)c Structural Concrete (Class B, 2500 psi @ 28 days)
AS EVALUATED
Structural Concrete (Ready Mix, Class AA/Class A/Class AS SUBMITTED 885.40 cu.m. 7,294,838.47 18% 1,313,070.93 430,395.47 1,743,466.40 9,038,304.87 10,208.19
900
B/Class C/Class P/Seal Concrete, 7 days/14 days/28 days) AS EVALUATED
AS SUBMITTED 69,106.84 kgs. 5,581,007.78 18% 1,004,581.40 329,279.46 1,333,860.86 6,914,868.64 100.06
902(1)a Reinforcing Steel (Deformed), Grade 40
AS EVALUATED
AS SUBMITTED 146,513.02 kgs. 12,316,854.88 18% 2,217,033.88 726,694.44 2,943,728.32 15,260,583.20 104.16
902(1)b Reinforcing Steel (Deformed), Grade 60
AS EVALUATED
AS SUBMITTED 4,399.16 sq.m. 1,833,048.75 18% 329,948.77 108,149.88 438,098.65 2,271,147.40 516.27
903(2) Formworks and Falseworks
AS EVALUATED
AS SUBMITTED 291.54 sq.m. 272,700.44 18% 49,086.08 16,089.33 65,175.41 337,875.85 1,158.93
1046(2)a1 100mm CHB Non-Load Bearing (including Reinforcing Steel)
AS EVALUATED
AS SUBMITTED 2,096.64 sq. m. 2,847,331.37 18% 512,519.65 167,992.55 680,512.20 3,527,843.57 1,682.62
1046(2)a2 150mm CHB Non-Load Bearing (including Reinforcing Steel)
AS EVALUATED
AS SUBMITTED 8,628.84 sq. m. 1,977,264.47 18% 355,907.60 116,658.60 472,566.21 2,449,830.68 283.91
1027(1) Cement Plaster Finish
AS EVALUATED
AS SUBMITTED 3,275.87 sq.m. 1,290,618.22 18% 232,311.28 76,146.47 308,457.75 1,599,075.97 488.14
1021(1)a Cement Floor Finish Plain
AS EVALUATED
AS SUBMITTED 570.39 sq.m. 444,590.74 18% 80,026.33 26,230.85 106,257.19 550,847.93 965.73
1003(1)a1 4.5mm Fiber Cement Board on Metal Frame Ceiling
AS EVALUATED
AS SUBMITTED 95.00 sq.m. 94,492.12 18% 17,008.58 5,575.04 22,583.62 117,075.74 1,232.38
1018(2) Unglazed Tiles
AS EVALUATED
AS SUBMITTED 263.00 sq.m. 308,180.93 18% 55,472.57 18,182.68 73,655.24 381,836.18 1,451.85
1018(5) Glazed Tiles
AS EVALUATED
AS SUBMITTED 113.00 set 157,430.44 18% 28,337.48 9,288.40 37,625.88 195,056.32 1,726.16
1010(1) Wooden Frames
AS EVALUATED
AS SUBMITTED 78.00 sq.m. 121,492.80 18% 21,868.70 7,168.08 29,036.78 150,529.58 1,929.87
1009(1) Jalousie Window (Glass)
AS EVALUATED
AS SUBMITTED 40.08 sq.m. 70,951.24 18% 12,771.22 4,186.12 16,957.35 87,908.59 2,193.33
1010(2)a Wooden Flush Door
AS EVALUATED
AS SUBMITTED 1.00 l/s 43,997.94 18% 7,919.63 2,595.88 10,515.51 54,513.45 54,513.45
1006(6) Steel Doors and Frames
AS EVALUATED
AS SUBMITTED 75.60 sq.m. 410,128.32 18% 73,823.10 24,197.57 98,020.67 508,148.99 6,721.55
1010(2)b Wooden Panel Door
AS EVALUATED
AS SUBMITTED 1.00 l/s 104,890.00 18% 18,880.20 6,188.51 25,068.71 129,958.71 129,958.71
1004(2) Finishing Hardware (Lockset and Hinges)
AS EVALUATED
AS SUBMITTED 11.52 sq.m. 53,622.21 18% 9,652.00 3,163.71 12,815.71 66,437.92 5,767.18
1005(1) Casement Steel Window (Awning Type)
AS EVALUATED
AS SUBMITTED 172.80 sq.m 755,483.52 18% 135,987.03 44,573.53 180,560.56 936,044.08 5,416.92
1005(1) Residential Casement Window (Steel)- Swing type
AS EVALUATED
AS SUBMITTED 78.84 sq.m 142,303.74 18% 25,614.67 8,395.92 34,010.59 176,314.34 2,236.36
1012(8) Glass and Glazing
AS EVALUATED
AS SUBMITTED 196.74 sq.m 37,374.38 18% 6,727.39 2,205.09 8,932.48 46,306.86 235.37
1016(1)a Waterproofing Cement Base
AS EVALUATED
AS SUBMITTED 1.00 l/s 106.49 18% 19.17 6.28 25.45 131.95 131.95
1003(17) Carpentry and Joinery Works
AS EVALUATED
AS SUBMITTED 1.00 l/s 1,168,422.03 18% 210,315.97 68,936.90 279,252.87 1,447,674.90 1,447,674.90
1051(1)a Railings
AS EVALUATED
AS SUBMITTED 9,045.33 sq.m. 2,774,137.84 18% 499,344.81 163,674.13 663,018.94 3,437,156.78 379.99
1032(1)a Painting Works (Masonry/Concrete Painting)
AS EVALUATED
AS SUBMITTED 349.15 sq.m. 107,110.28 18% 19,279.85 6,319.51 25,599.36 132,709.64 380.09
1032(1)b Painting Works (Wood Painting)
AS EVALUATED
AS SUBMITTED 1,334.44 sq.m. 421,888.03 18% 75,939.85 24,891.39 100,831.24 522,719.28 391.71
1032(1)c Painting Works (Steel Painting)
AS EVALUATED
AS SUBMITTED 351.25 sq.m. 233,978.43 18% 42,116.12 13,804.73 55,920.85 289,899.28 825.34
1014(1)a2 Prepainted Metal Sheets, Corrugated Type, Long Span
AS EVALUATED
AS SUBMITTED 55.00 ln.m. 24,265.14 18% 4,367.72 1,431.64 5,799.37 30,064.51 546.63
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll)
AS EVALUATED
AS SUBMITTED 18.92 ln.m. 8,125.05 18% 1,462.51 479.38 1,941.89 10,066.94 532.08
1013(2)b Fabricated Metal Roofing Accessory (Flashings)
AS EVALUATED
AS SUBMITTED 522.50 sq.m. 77,377.36 18% 13,927.93 4,565.26 18,493.19 95,870.55 183.48
1038(1) Reflective Insulation
AS EVALUATED
AS SUBMITTED 536.00 each 27,849.93 18% 5,012.99 1,643.15 6,656.13 34,506.07 64.38
1047(4)a Metal Structure Accessories (Bolts)
AS EVALUATED
AS SUBMITTED 44.00 each 6,958.14 18% 1,252.47 410.53 1,663.00 8,621.14 195.93
1047(4)b Metal Structure Accessories (Turnbuckle)
AS EVALUATED
AS SUBMITTED 1.00 l/s 130,792.03 18% 23,542.57 7,716.73 31,259.30 162,051.32 162,051.32
1001(8) Sewer Line Works
AS EVALUATED
AS SUBMITTED 1.00 l/s 168,699.88 18% 30,365.98 9,953.29 40,319.27 209,019.15 209,019.15
1001(9) Storm Drainage and Downspout
AS EVALUATED
AS SUBMITTED 1.00 l/s 357,058.79 18% 64,270.58 21,066.47 85,337.05 442,395.84 442,395.84
1001(11) Septic Vault (CHB)
AS EVALUATED
AS SUBMITTED 1.00 l/s 590,247.73 18% 106,244.59 34,824.62 141,069.21 731,316.94 731,316.94
1002(26) Cistern
AS EVALUATED
AS SUBMITTED 1.00 l/s 222,028.44 18% 39,965.12 13,099.68 53,064.80 275,093.24 275,093.24
1201(1) Water Pumping System
AS EVALUATED
AS SUBMITTED 1.00 l/s 496,971.87 18% 89,454.94 29,321.34 118,776.28 615,748.15 615,748.15
1202(1) Fire Protection System
AS EVALUATED
AS SUBMITTED 1.00 l/s 255,672.91 18% 46,021.12 15,084.70 61,105.83 316,778.74 316,778.74
1002(4) Plumbing Fixtures
AS EVALUATED
AS SUBMITTED 1.00 l/s 75,552.57 18% 13,599.46 4,457.60 18,057.06 93,609.63 93,609.63
1002(24) Cold Water Lines
AS EVALUATED
AS SUBMITTED 4.60 sq.m. 5,975.37 18% 1,075.57 352.55 1,428.11 7,403.48 1,609.45
1002(20) Facial Mirror
AS EVALUATED
AS SUBMITTED 1.00 set 101,356.82 18% 18,244.23 5,980.05 24,224.28 125,581.10 125,581.10
1201 (8)a Water Tank including Concrete Platform (Rainwater Collector)
AS EVALUATED
AS SUBMITTED 1.00 l/s 444,304.37 18% 79,974.79 26,213.96 106,188.74 550,493.11 550,493.11
1100(18) Wires and Wiring Devices (20 CL)
AS EVALUATED
AS SUBMITTED 1.00 l/s 439,492.23 18% 79,108.60 25,930.04 105,038.64 544,530.88 544,530.88
1102(21) Power Load Center, Switchgear, and Panel Boards (20 CL)
AS EVALUATED
AS SUBMITTED 1.00 l/s 344,523.98 18% 62,014.32 20,326.91 82,341.23 426,865.21 426,865.21
1103(1) Lighting Fixtures (20 CL)
AS EVALUATED
AS SUBMITTED 1.00 l/s 39,097.62 18% 7,037.57 2,306.76 9,344.33 48,441.95 48,441.95
1208(1) Fire Alarm System (20 CL)
AS EVALUATED
AS SUBMITTED 17.00 sets 44,711.63 18% 8,048.09 2,637.99 10,686.08 55,397.71 3,258.69
1200(5)a Exhaust Fan
AS EVALUATED
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
Construction of 4-Storey, 20-Classroom School Building at Vitali National High School, Zamboanga
City
Project : Appropriation : PHP 67,231,500.00
:
Source of Fund FY 2024 SARO
Project ID : Target Start Date : Upon Approval
Location : Total Project Duration : 225 C.D
Project Description :
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities For the Engineer 0.17% 93,884.52
Part II Other General Requirements 1.62% 876,028.70
Project Component ID PROJECT COMPONENT DESCRIPTION
BREAKDOWN OF EXPENDI
REQUIRED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1. Labor 7,832,200.45 A. Total Direct Cost 54,213,771.63
2. Materials 41,570,316.65 B. OCM and Profit 9,655,752.18
3. Rental of Equipment 4,811,254.53 C. Value Added Tax (5%) 3,193,476.19
4. Provisional Sum / Daywork D. Total Construction Cost 67,063,000.00
(PLS. SEE FORM POW-2015-01B-00) 5. OCM and Profit 9,655,752.18 E. Eng'g & Administrative Overhead 168,500.00
6. Value Added Tax (5%) 3,193,476.19 F. RROW Acquisition
7. EAO 168,500.00 G. Physical Reserved (Contingency) 0.00
8. RROW Acquisition
9. Physical Reserved (Contingency) 0.00
10.TOTAL ESTIMATED COST 67,231,500.00 H. TOTAL ESTIMATED COST PHP 67,231,500.00
Note: 1. Prices of Materials were based on CMPD 2023 2nd Quarter C.Y. 2023 and Labor based on rates in Region IX.
2. Labor rates based on Standard abor Rates of DPWH Regional/District Engineering Offices as of June 2023
MARCO C. MIGUEL CAROLYN M. ORBECIDO ROBERTO DONDI F. STA. ELENA JUL-ARAB A. KONG
Engineer II Engineer III Assistant District Engineer District Engineer
Planning and Design Section Chief, Planning and Design Section
m,
Construction of 4-Storey, 20-Classroom School Building at Vitali National High School, Zamboanga City
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
UNIT MATERIAL UNIT LABOR UNIT EQUIPMENT UNIT COST TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
As Submitted 0.17% 1.00 l/s 69,574.12 69,574.12 24,310.40 24,310.40 0.000 - 93,884.52 93,884.52 18% 16,899.21 5,539.19 116,322.93
A.1.1(3) Construction of Field Office for the Engineer
As Evaluated
As Submitted 69,574.12 24,310.40 - 93,884.52 93,884.52 16,899.21 5,539.19 116,322.93
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted 0.11% 1.00 l/s 57,141.34 57,141.34 0.00 - 0.000 - 57,141.34 57,141.34 0% - 2,857.07 59,998.41
B.3 (1) Permits and Clearances
As Evaluated
As Submitted 0.02% 1.00 l/s 0.00 - 7,845.04 7,845.04 2,000.000 2,000.00 9,845.04 9,845.04 18% 1,772.11 580.86 12,198.00
B.4(10) Miscellaneous Survey and Staking
As Evaluated
As Submitted 0.02% 2.00 ea 4,198.00 8,396.00 973.08 1,946.16 97.308 194.62 5,268.39 10,536.78 18% 1,896.62 621.67 13,055.07
B.5 Project Billboard/Sign Board
As Evaluated
As Submitted 0.47% 1.00 l/s 247,109.14 247,109.14 9,916.71 9,916.71 0.000 - 257,025.85 257,025.85 10% 25,702.59 14,136.42 296,864.86
B.7(1) Occupational Safety and Health Program
As Evaluated
As Submitted 0.74% 1.00 l/s 0.00 - 0.00 - 399,328.938 399,328.94 399,328.94 399,328.94 0% - 19,966.45 419,295.38
B.9 (1) Mobilization/Demobilization
As Evaluated
As Submitted 0.26% 1.00 l/s 135,490.91 135,490.91 6,054.40 6,054.40 605.440 605.44 142,150.75 142,150.75 18% 25,587.13 8,386.89 176,124.78
B.20 (1) Temporary Fence
As Evaluated
As Submitted 448,137.39 25,762.31 402,128.99 870,760.31 876,028.70 54,958.45 46,549.36 977,536.50
TOTAL OF PART II
As Evaluated
(Project ID)
(Project Component ID - Description)
CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING
PART III
WORKS
PART A EARTHWORKS
As Submitted 0.00% 1.00 l/s 0.00 - 1,251.00 1,251.00 1,441.760 1,441.76 2,692.76 2,692.76 18% 484.70 158.87 3,336.33
801(1) Removal of Structures and Obstruction
As Evaluated
As Submitted 0.01% 3.00 ea 1,000.00 3,000.00 99.90 299.69 783.206 2,349.62 1,883.10 5,649.31 18% 1,016.88 333.31 6,999.50
800(3) a1 Individual Removal of Trees (150mm dia - 300mm dia)
As Evaluated
As Submitted 1.44% 1.00 l/s 768,654.01 768,654.01 7,265.28 7,265.28 4,192.000 4,192.00 780,111.29 780,111.29 18% 140,420.03 46,026.57 966,557.88
803(4)a Shoring, Cribbing and Drain Excavation
As Evaluated
As Submitted 6.33% 507.00 m 2,015.60 1,021,908.18 348.36 176,616.83 4,403.940 2,232,797.72 6,767.89 3,431,322.73 18% 617,638.09 202,448.04 4,251,408.86
1052(28)a Micro Piles In Drilled Holes, 0.20m 12' (ordinary soil condition)
As Evaluated
As Submitted 0.59% 1,208.65 cu.m. - 14.25 17,225.63 248.225 300,016.52 262.48 317,242.15 18% 57,103.59 18,717.29 393,063.02
803(1)a Structure Excavation (Common Soil)
As Evaluated
As Submitted 0.41% 1,115.09 cu.m. 0.00 - 28.97 32,301.35 172.028 191,826.53 201.00 224,127.87 18% 40,343.02 13,223.54 277,694.43
804(1)a Embankment from Roadway/Structure Excavation, Common Soil
As Evaluated
As Submitted 0.13% 70.95 cu.m. 812.50 57,646.88 28.97 2,055.24 172.028 12,205.38 1,013.50 71,907.49 18% 12,943.35 4,242.54 89,093.38
804(2)a Embankment from Common Borrow, Selected Borrow
As Evaluated
As Submitted 1.22% 107.67 cu.m. 4,382.20 471,832.79 1,181.01 127,159.53 599.894 64,590.72 6,163.10 663,583.04 18% 119,444.95 39,151.40 822,179.38
901(1) Lean Concrete (Manual mixing)
As Evaluated
As Submitted 2,323,041.85 364,174.55 2,809,420.23 799,095.12 5,496,636.64 989,394.59 324,301.56 6,810,332.80
TOTAL OF PART A
As Evaluated -
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted 0.93% 68.44 cu.m. 5,017.93 343,441.81 1,561.56 106,877.36 793.193 54,288.39 7,372.68 504,607.55 18% 90,829.36 29,771.85 625,208.76
900(2)c Structural Concrete (Class B, 2500 psi @ 28 days)
As Evaluated
Structural Concrete (Ready Mix, Class AA/Class A/Class B/Class C/Class As Submitted 13.46% 885.40 cu.m. 7,875.00 6,972,507.28 166.03 147,006.97 198.017 175,324.23 8,239.05 7,294,838.47 18% 1,313,070.93 430,395.47 9,038,304.87
900
P/Seal Concrete, 7 days/14 days/28 days) As Evaluated
As Submitted 10.29% 69,106.84 kgs. 70.74 4,888,441.56 8.15 562,880.22 1.877 129,686.00 80.76 5,581,007.78 18% 1,004,581.40 329,279.46 6,914,868.64
902(1)a Reinforcing Steel (Deformed), Grade 40
As Evaluated
As Submitted 22.72% 146,513.02 kgs. 74.04 10,848,549.15 8.15 1,193,359.17 1.877 274,946.56 84.07 12,316,854.88 18% 2,217,033.88 726,694.44 15,260,583.20
902(1)b Reinforcing Steel (Deformed), Grade 60
As Evaluated
As Submitted 3.38% 4,399.16 sq.m. 183.15 805,727.42 229.20 1,008,296.73 4.325 19,024.60 416.68 1,833,048.75 18% 329,948.77 108,149.88 2,271,147.40
903(2) Formworks and Falseworks
As Evaluated
As Submitted 23,858,667.22 3,018,420.45 653,269.77 16,193.24 27,530,357.44 4,955,464.34 1,624,291.09 34,110,112.87
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1. Termites Control
As Submitted 0.08% 36.00 liters 1,164.00 41,904.00 56.06 2,018.13 5.606 201.81 1,225.67 44,123.95 18% 7,942.31 2,603.31 54,669.57
1000(1) Soil Poisoning
As Evaluated
As Submitted 41,904.00 2,018.13 201.81 1,225.67 44,123.95 7,942.31 2,603.31 54,669.57
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted 0.50% 291.54 sq.m. 764.08 222,759.07 114.85 33,483.27 56.452 16,458.10 935.38 272,700.44 18% 49,086.08 16,089.33 337,875.85
1046(2)a1 100mm CHB Non-Load Bearing (including Reinforcing Steel)
As Evaluated
As Submitted 5.25% 2,096.64 sq. m. 1,152.00 2,415,324.45 138.14 289,639.73 67.903 142,367.19 1,358.04 2,847,331.37 18% 512,519.65 167,992.55 3,527,843.57
1046(2)a2 150mm CHB Non-Load Bearing (including Reinforcing Steel)
As Evaluated
As Submitted 2,638,083.51 323,123.01 158,825.29 2,293.42 3,120,031.81 561,605.73 184,081.88 3,865,719.41
Sub - Total C.2
As Evaluated
C.3 Finishing Works
As Submitted 3.65% 8,628.84 sq. m. 152.15 1,312,843.69 70.00 604,018.89 7.000 60,401.89 229.15 1,977,264.47 18% 355,907.60 116,658.60 2,449,830.68
1027(1) Cement Plaster Finish
As Evaluated
As Submitted 2.38% 3,275.87 sq.m. 327.02 1,071,279.59 60.87 199,398.75 6.087 19,939.87 393.98 1,290,618.22 18% 232,311.28 76,146.47 1,599,075.97
1021(1)a Cement Floor Finish Plain
As Evaluated
As Submitted 0.82% 570.39 sq.m. 511.55 291,785.88 243.54 138,913.51 24.354 13,891.35 779.45 444,590.74 18% 80,026.33 26,230.85 550,847.93
1003(1)a1 4.5mm Fiber Cement Board on Metal Frame Ceiling
As Evaluated
As Submitted 0.17% 95.00 sq.m. 549.24 52,178.20 404.92 38,467.21 40.492 3,846.72 994.65 94,492.12 18% 17,008.58 5,575.04 117,075.74
1018(2) Unglazed Tiles
As Evaluated
As Submitted 0.57% 263.00 sq.m. 535.49 140,834.13 578.45 152,133.46 57.845 15,213.35 1,171.79 308,180.93 18% 55,472.57 18,182.68 381,836.18
1018(5) Glazed Tiles
As Evaluated
As Submitted 0.29% 113.00 set 858.00 96,953.52 486.54 54,979.02 48.654 5,497.90 1,393.19 157,430.44 18% 28,337.48 9,288.40 195,056.32
1010(1) Wooden Frames
As Evaluated
As Submitted 0.22% 78.00 sq.m. 566.50 44,187.00 901.00 70,278.00 90.100 7,027.80 1,557.60 121,492.80 18% 21,868.70 7,168.08 150,529.58
1009(1) Jalousie Window (Glass)
As Evaluated
As Submitted 0.13% 40.08 sq.m. 934.00 37,434.72 760.22 30,469.57 76.022 3,046.96 1,770.24 70,951.24 18% 12,771.22 4,186.12 87,908.59
1010(2)a Wooden Flush Door
As Evaluated
As Submitted 0.08% 1.00 l/s 39,119.40 39,119.40 3,293.50 3,293.50 1,585.042 1,585.04 43,997.94 43,997.94 18% 7,919.63 2,595.88 54,513.45
1006(6) Steel Doors and Frames
As Evaluated
As Submitted 0.76% 75.60 sq.m. 4,500.00 340,200.00 840.89 63,571.20 84.089 6,357.12 5,424.98 410,128.32 18% 73,823.10 24,197.57 508,148.99
1010(2)b Wooden Panel Door
As Evaluated
As Submitted 0.19% 1.00 l/s 104,890.00 104,890.00 - - 104,890.00 104,890.00 18% 18,880.20 6,188.51 129,958.71
1004(2) Finishing Hardware (Lockset and Hinges)
As Evaluated
As Submitted 0.10% 11.52 sq.m. 2,625.00 30,240.00 1,351.50 15,569.28 678.206 7,812.93 4,654.71 53,622.21 18% 9,652.00 3,163.71 66,437.92
1005(1) Casement Steel Window (Awning Type)
As Evaluated
As Submitted 1.39% 172.80 sq.m 2,136.75 369,230.40 1,351.50 233,539.20 883.761 152,713.92 4,372.01 755,483.52 18% 135,987.03 44,573.53 936,044.08
1005(1) Residential Casement Window (Steel)- Swing type
As Evaluated
As Submitted 0.26% 78.84 sq.m 1,061.64 83,700.00 675.75 53,276.13 67.575 5,327.61 1,804.97 142,303.74 18% 25,614.67 8,395.92 176,314.34
1012(8) Glass and Glazing
As Evaluated
As Submitted 0.07% 196.74 sq.m 47.25 9,295.97 129.74 25,525.83 12.974 2,552.58 189.97 37,374.38 18% 6,727.39 2,205.09 46,306.86
1016(1)a Waterproofing Cement Base
As Evaluated
As Submitted 0.00% 1.00 l/s 106.49 106.49 0.00 - 0.000 - 106.49 106.49 18% 19.17 6.28 131.95
1003(17) Carpentry and Joinery Works
As Evaluated
As Submitted 4,024,278.99 1,683,433.55 305,215.05 173,731.11 6,012,927.58 18% 1,082,326.96 354,762.73 7,450,017.27
Sub-Total C.3
As Evaluated
C.4 Fabricated Materials
As Submitted 2.16% 1.00 l/s 1,030,610.48 1,030,610.48 84,967.45 84,967.45 52,844.101 52,844.10 1,168,422.03 1,168,422.03 18% 210,315.97 68,936.90 1,447,674.90
1051(1)a Railings
As Evaluated
As Submitted 1,030,610.48 84,967.45 52,844.10 1,168,422.03 1,168,422.03 210,315.97 68,936.90 1,447,674.90
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted 5.12% 9,045.33 sq.m. 138.86 1,256,072.24 152.57 1,380,059.64 15.257 138,005.96 306.69 2,774,137.84 18% 499,344.81 163,674.13 3,437,156.78
1032(1)a Painting Works (Masonry/Concrete Painting)
As Evaluated
As Submitted 0.20% 349.15 sq.m. 120.30 42,002.27 169.52 59,189.10 16.952 5,918.91 306.78 107,110.28 18% 19,279.85 6,319.51 132,709.64
1032(1)b Painting Works (Wood Painting)
As Evaluated
As Submitted 0.78% 1,334.44 sq.m. 139.93 186,733.24 160.20 213,777.09 16.020 21,377.71 316.15 421,888.03 18% 75,939.85 24,891.39 522,719.28
1032(1)c Painting Works (Steel Painting)
As Evaluated
As Submitted 1,484,807.75 1,653,025.82 165,302.58 929.62 3,303,136.16 594,564.51 194,885.03 4,092,585.70
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted 0.43% 351.25 sq.m. 505.73 177,637.66 145.82 51,218.88 14.582 5,121.89 666.13 233,978.43 18% 42,116.12 13,804.73 289,899.28
1014(1)a2 Prepainted Metal Sheets, Corrugated Type, Long Span
As Evaluated
As Submitted 0.04% 55.00 ln.m. 414.42 22,793.35 24.33 1,337.99 2.433 133.80 441.18 24,265.14 18% 4,367.72 1,431.64 30,064.51
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll)
As Evaluated
As Submitted 0.01% 18.92 ln.m. 402.68 7,618.76 24.33 460.27 2.433 46.03 429.44 8,125.05 18% 1,462.51 479.38 10,066.94
1013(2)b Fabricated Metal Roofing Accessory (Flashings)
As Evaluated
As Submitted 0.14% 522.50 sq.m. 88.20 46,084.50 54.45 28,448.06 5.445 2,844.81 148.09 77,377.36 18% 13,927.93 4,565.26 95,870.55
1038(1) Reflective Insulation
As Evaluated
As Submitted 2.70% 18,516.43 kg 68.03 1,259,721.57 6.83 126,483.01 4.267 79,005.18 79.13 1,465,209.76 18% 263,737.76 86,447.38 1,815,394.90
1047(8)a Structural Steel, Truss
As Evaluated
As Submitted 0.96% 6,060.53 kg 71.34 432,371.62 5.51 33,418.33 9.197 55,739.09 86.05 521,529.04 18% 93,875.23 30,770.21 646,174.48
1047(8)b Structural Steel Purlins
As Evaluated
As Submitted 0.05% 536.00 each 27.61 14,797.62 24.33 13,039.27 0.024 13.04 51.96 27,849.93 18% 5,012.99 1,643.15 34,506.07
1047(4)a Metal Structure Accessories (Bolts)
As Evaluated
As Submitted 0.01% 44.00 each 118.00 5,192.00 36.49 1,605.58 3.649 160.56 158.14 6,958.14 18% 1,252.47 410.53 8,621.14
1047(4)b Metal Structure Accessories (Turnbuckle)
As Evaluated
As Submitted 0.07% 459.49 kg 56.24 25,840.79 18.72 8,601.78 1.872 860.18 76.83 35,302.74 18% 6,354.49 2,082.86 43,740.10
1047(5)c Metal Structure Accessories (Crossbracing)
As Evaluated
As Submitted 0.16% 1,026.44 kg 62.62 64,274.32 18.72 19,215.19 1.872 1,921.52 83.21 85,411.03 18% 15,373.99 5,039.25 105,824.27
1047(5)d Metal Structure Accessories (Steel Plates)
As Evaluated
As Submitted 0.02% 100.50 kg 63.00 6,331.29 18.72 1,881.32 1.872 188.13 83.59 8,400.74 18% 1,512.13 495.64 10,408.52
1047(5)b Metal Structure Accessories (Sagrods)
As Evaluated
As Submitted 2,062,663.48 285,709.67 146,034.22 2,303.76 2,494,407.38 448,993.33 147,170.04 3,090,570.74
Sub-Total C.6
As Evaluated
C.7 Plumbing and Sanitary Works
As Submitted 0.24% 1.00 l/s 114,891.66 114,891.66 14,454.88 14,454.88 1,445.488 1,445.49 130,792.03 130,792.03 18% 23,542.57 7,716.73 162,051.32
1001(8) Sewer Line Works
As Evaluated
As Submitted 0.31% 1.00 l/s 120,249.55 120,249.55 44,045.76 44,045.76 4,404.58 4,404.58 168,699.88 168,699.88 18% 30,365.98 9,953.29 209,019.15
1001(9) Storm Drainage and Downspout
As Evaluated
As Submitted 0.66% 1.00 l/s 290,103.10 290,103.10 36,270.17 36,270.17 30,685.53 30,685.53 357,058.79 357,058.79 18% 64,270.58 21,066.47 442,395.84
1001(11) Septic Vault (CHB)
As Evaluated
As Submitted 0.15% 24.00 ea 2,275.20 54,604.77 765.38 18,369.08 238.351 5,720.42 3,278.93 78,694.27 18% 14,164.97 4,642.96 97,502.21
1001(5)b Catch Basin (CHB)
As Evaluated
As Submitted 1.09% 1.00 l/s 479,710.53 479,710.53 54,720.24 54,720.24 55,816.962 55,816.96 590,247.73 590,247.73 18% 106,244.59 34,824.62 731,316.94
1002(26) Cistern
As Evaluated
As Submitted 0.41% 1.00 l/s 220,917.00 220,917.00 1,010.40 1,010.40 101.040 101.04 222,028.44 222,028.44 18% 39,965.12 13,099.68 275,093.24
1201(1) Water Pumping System
As Evaluated
As Submitted 0.92% 1.00 l/s 491,644.00 491,644.00 4,843.52 4,843.52 484.352 484.35 496,971.87 496,971.87 18% 89,454.94 29,321.34 615,748.15
1202(1) Fire Protection System
As Evaluated
As Submitted 0.47% 1.00 l/s 224,814.45 224,814.45 28,053.15 28,053.15 2,805.315 2,805.31 255,672.91 255,672.91 18% 46,021.12 15,084.70 316,778.74
1002(4) Plumbing Fixtures
As Evaluated
As Submitted 0.14% 1.00 l/s 58,723.15 58,723.15 15,299.47 15,299.47 1,529.947 1,529.95 75,552.57 75,552.57 18% 13,599.46 4,457.60 93,609.63
1002(24) Cold Water Lines
As Evaluated
As Submitted 0.01% 4.60 sq.m. 630.00 2,898.00 608.18 2,797.60 60.817 279.76 1,298.99 5,975.37 18% 1,075.57 352.55 7,403.48
1002(20) Facial Mirror
As Evaluated
As Submitted 0.19% 1.00 set 87,641.19 87,641.19 12,468.75 12,468.75 1,246.875 1,246.88 101,356.82 101,356.82 18% 18,244.23 5,980.05 125,581.10
1201 (8)a Water Tank including Concrete Platform (Rainwater Collector)
As Evaluated
As Submitted 2,146,197.40 232,333.02 104,520.27 2,402,958.96 2,483,050.68 446,949.12 146,499.99 3,076,499.80
Sub-Total C.7
As Evaluated
As Submitted 13,428,545.61 4,264,610.65 932,943.32 3,751,864.58 18,626,099.59 3,352,697.93 1,098,939.88 23,077,737.39
TOTAL OF PART C
As Evaluated
PART D ELECTRICAL
As Submitted 0.51% 1.00 l/s 248,664.06 248,664.06 27,246.24 27,246.24 2,724.624 2,724.62 278,634.92 278,634.92 18% 50,154.29 16,439.46 345,228.67
1100(19) Conduit, Boxes, and Fittings (20 CL)
As Evaluated
As Submitted 0.82% 1.00 l/s 405,770.40 405,770.40 35,030.88 35,030.88 3,503.088 3,503.09 444,304.37 444,304.37 18% 79,974.79 26,213.96 550,493.11
1100(18) Wires and Wiring Devices (20 CL)
As Evaluated
As Submitted 0.81% 1.00 l/s 407,525.00 407,525.00 29,061.12 29,061.12 2,906.112 2,906.11 439,492.23 439,492.23 18% 79,108.60 25,930.04 544,530.88
1102(21) Power Load Center, Switchgear, and Panel Boards (20 CL)
As Evaluated
As Submitted 0.64% 1.00 l/s 301,901.00 301,901.00 38,748.16 38,748.16 3,874.816 3,874.82 344,523.98 344,523.98 18% 62,014.32 20,326.91 426,865.21
1103(1) Lighting Fixtures (20 CL)
As Evaluated
As Submitted 0.07% 1.00 l/s 34,290.00 34,290.00 4,370.56 4,370.56 437.056 437.06 39,097.62 39,097.62 18% 7,037.57 2,306.76 48,441.95
1208(1) Fire Alarm System (20 CL)
As Evaluated
As Submitted 0.08% 17.00 sets 2,600.00 44,200.00 27.36 465.12 2.736 46.51 2,630.10 44,711.63 18% 8,048.09 2,637.99 55,397.71
1200(5)a Exhaust Fan
As Evaluated
As Submitted 1,442,350.46 134,922.08 13,492.21 1,590,764.75 286,337.65 93,855.12 1,970,957.52
TOTAL OF PART D
As Evaluated
As Submitted 41,052,605.14 7,782,127.74 4,409,125.53 53,243,858.41 9,583,894.51 3,141,387.65 65,969,140.57
TOTAL OF PART III
As Evaluated
As Submitted 100% 41,570,316.65 7,832,200.45 4,811,254.53 54,213,771.63 9,655,752.18 3,193,476.19 67,063,000.00
GRAND TOTAL
As Evaluated
Project Name : #REF!
WORK PROGRAMME/SCHEDULE
#REF! #REF!
PERCENTAGE ACCOMPLISHED #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
CUMMULATIVE PERCENTAGE ACCOMPLISHED #REF! #REF! #REF! #REF! #REF! #REF! #REF! 100.00%
AMOUNT ACCOMPLISHED #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
CUMMULATIVE AMOUNT ACCOMPLISHED #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
NIZAR A. SERA ROBERTO DONDI F. STA. ELENA ANTONIO A. GONZALES CHOLIE M. ROBLE
Engineer II Engineer III OIC - Asst. District Engineer District Engineer
Chief, Planning and Design Section
Project Name : Construction of 4-Storey, 20-Classroom School Building at Vitali National High School, Zamboanga City
WORK PROGRAMME/SCHEDULE
A.1.1(3) Construction of Field Office for the Engineer 1.00 l/s 8.00 0.02%
0.00%###
###
###
###
###
###
###
###
0.00%###
###
###
###
###
###
###
###
###
###
###
###
###
B.4(10) Miscellaneous Survey and Staking 1.00 l/s 13.00 0.00%
0.00% ###
B.5 Project Billboard/Sign Board 2.00 ea 1.00 4.00 1.00 0.02%
0.00%###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
B.7(1) Occupational Safety and Health Program 1.00 l/s 225 0.00%
0.00%###
###
B.9 (1) Mobilization/Demobilization 1.00 l/s 2.00 0.33%
B.20 (1) Temporary Fence 1.00 l/s 1.00 20.00 2.50 0.11%
0.00% ###
###
###
801(1) Removal of Structures and Obstruction 1.00 l/s 1.00 4.39 0.55 0.01%
0.00% ###
800(3) a1 Individual Removal of Trees (150mm dia - 300mm dia) 3.00 ea 1.00 0.33 0.13 0.09%
0.00% ###
803(4)a Shoring, Cribbing and Drain Excavation 1.00 l/s 1.00 24.00 3.00 0.51%
-1.54%
1052(28)a Micro Piles In Drilled Holes, 0.20m 12' (ordinary soil condition) 507.00 m 3.00 1.25 26.41 0.00%
803(1)a Structure Excavation (Common Soil) 1,208.65 cu.m. 20.00 1.00 7.56 0.08%
0.00% ###
###
###
###
###
###
###
###
804(1)a Embankment from Roadway/Structure Excavation, Common Soil 1,115.09 cu.m. 9.84 1.00 14.17 0.03%
0.00% ###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
804(2)a Embankment from Common Borrow, Selected Borrow 70.95 cu.m. 9.84 1.00 0.91 0.16%
0.00% ###
901(1) Lean Concrete (Manual mixing) 107.67 cu.m. 1.20 1.00 11.22 0.12%
0.00% ###
###
###
###
###
### ###
###
### ###
###
###
900(2)c Structural Concrete (Class B, 2500 psi @ 28 days) 68.44 cu.m. 0.27 1.00 31.69 0.03%
0.00% ###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
Structural Concrete (Ready Mix, Class AA/Class A/Class B/Class C/Class
900 885.40 cu.m. 3.72 1.00 29.76 0.48%
P/Seal Concrete, 7 days/14 days/28 days) 0.00% ###
###
###
###
###
### ###
###
###
###
###
### ###
###
###
###
###
###
###
###
###
902(1)a Reinforcing Steel (Deformed), Grade 40 69,106.84 kgs. 129.09 1.00 66.92 0.16%
0.00% ###
###
###
###
### ###
###
###
###
###
###
###
###
###
###
### ###
###
###
###
###
###
###
###
###
###
### ###
###
###
###
###
###
###
###
###
###
### ###
###
###
###
###
###
###
### ###
###
###
###
###
###
###
###
###
902(1)b Reinforcing Steel (Deformed), Grade 60 146,513.02 kgs. 129.09 1.00 141.87 0.17%
0.00% ###
###
###
###
###
###
###
###
###
###
###
###
###
### ###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
### ###
###
###
###
###
###
###
###
###
###
###
###
###
###
### ###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
903(2) Formworks and Falseworks 4,399.16 sq.m. 4.50 1.56 190.64 0.02%
0.00% ###
###
###
###
###
###
###
### ###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
### ###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
### ###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
1000(1) Soil Poisoning 36.00 liters 5.40 1.00 0.84 0.10%
0.00% ###
1046(2)a1 100mm CHB Non-Load Bearing (including Reinforcing Steel) 291.54 sq.m. 3.83 1.00 9.53 0.06%
0.00% ###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
### ###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
### ###
###
###
###
###
###
###
###
###
###
###
### ###
###
###
###
###
###
###
###
###
###
###
###
###
###
### ###
###
###
###
###
1046(2)a2 150mm CHB Non-Load Bearing (including Reinforcing Steel) 2,096.64 sq. m. 3.18 1.00 82.42 0.07%
0.00% ###
###
###
###
###
###
###
###
###
###
### ###
###
###
###
###
###
###
###
###
###
###
### ###
###
###
###
###
###
###
###
###
###
### ###
###
###
###
###
###
###
###
###
###
###
1027(1) Cement Plaster Finish 8,628.84 sq. m. 7.13 1.00 151.39 0.03%
-3.90%
1021(1)a Cement Floor Finish Plain 3,275.87 sq.m. 5.95 1.00 68.83 0.04%
0.00%
1003(1)a1 4.5mm Fiber Cement Board on Metal Frame Ceiling 570.39 sq.m. 1.24 1.00 57.37 0.02%
0.00% ###
###
1018(2) Unglazed Tiles 95.00 sq.m. 1.95 1.00 6.09 0.03%
0.00%
1018(5) Glazed Tiles 263.00 sq.m. 1.37 1.00 24.09 0.03%
0.00%
1010(1) Wooden Frames 113.00 set 1.00 2.00 28.25 0.01%
0.00% ###
###
###
###
### ###
###
###
###
### ###
###
###
###
###
###
###
###
###
1009(1) Jalousie Window (Glass) 78.00 sq.m. 0.27 1.00 36.12 0.01%
0.00% ###
###
###
###
### ###
###
###
###
### ###
###
###
###
###
###
1010(2)a Wooden Flush Door 40.08 sq.m. 0.32 1.00 15.66 0.01%
0.00% ###
###
### ###
###
### ###
###
###
1006(6) Steel Doors and Frames 1.00 l/s 1.00 13.54 1.70 0.05%
0.00% ###
1010(2)b Wooden Panel Door 75.60 sq.m. 0.36 1.00 26.25 0.03%
0.00% ###
###
###
###
### ###
###
###
###
###
1004(2) Finishing Hardware (Lockset and Hinges) 1.00 l/s 1.00 1.00 0.13 1.59%
0.00%
1005(1) Casement Steel Window (Awning Type) 11.52 sq.m. 0.18 1.00 8.00 0.01%
-0.11%
1005(1) Residential Casement Window (Steel)- Swing type 172.80 sq.m 0.18 1.00 120.00 0.01%
-1.49%
1012(8) Glass and Glazing 78.84 sq.m 0.36 1.00 27.38 0.01%
-0.28%
1016(1)a Waterproofing Cement Base 196.74 sq.m 1.88 1.00 13.12 0.01%
-0.07%
1003(17) Carpentry and Joinery Works 1.00 l/s 1.00 78.66 9.84 0.00%
0.00%
1051(1)a Railings 1.00 l/s 1.00 243.59 30.45 0.08%
-2.31%
1032(1)a Painting Works (Masonry/Concrete Painting) 9,045.33 sq.m. 2.10 1.00 538.42 0.01%
-5.48%
1032(1)b Painting Works (Wood Painting) 349.15 sq.m. 1.89 1.00 23.10 0.01%
-0.21%
1032(1)c Painting Works (Steel Painting) 1,334.44 sq.m. 2.00 1.00 83.41 0.01%
-0.83%
1014(1)a2 Prepainted Metal Sheets, Corrugated Type, Long Span 351.25 sq.m. 2.08 1.00 21.15 0.02%
-0.46%
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll) 55.00 ln.m 10.00 1.00 0.69 0.07%
-0.05%
1013(2)b Fabricated Metal Roofing Accessory (Flashings) 18.92 ln.m. 10.00 1.00 0.24 0.07%
-0.02%
1038(1) Reflective Insulation 522.50 sq.m. 5.56 1.00 11.75 0.01%
-0.15%
1047(8)a Structural Steel, Truss 18,516.43 kg 85.00 1.49 40.58 0.07%
-2.89%
1047(8)b Structural Steel Purlins 6,060.53 kg 90.45 1.00 8.38 0.12%
-1.03%
1047(4)a Metal Structure Accessories (Bolts) 536.00 each 1.00 0.10 6.70 0.01%
-0.05%
1047(4)b Metal Structure Accessories (Turnbuckle) 44.00 each 1.00 0.15 0.83 0.02%
-0.01%
1047(5)c Metal Structure Accessories (Crossbracing) 459.49 kg 13.00 1.00 4.42 0.02%
-0.07%
1047(5)d Metal Structure Accessories (Steel Plates) 1,026.44 kg 13.00 1.00 9.88 0.02%
-0.17%
1047(5)b Metal Structure Accessories (Sagrods) 100.50 kg 13.00 1.00 0.97 0.02%
-0.02%
1001(8) Sewer Line Works 1.00 l/s 1.00 47.75 5.97 0.04%
-0.26%
1001(9) Storm Drainage and Downspout 1.00 l/s 1.00 135.50 16.94 0.02%
-0.33%
1001(11) Septic Vault (CHB) 1.00 l/s 1.00 23.98 3.00 0.23%
-0.70%
1001(5)b Catch Basin (CHB) 24.00 ea 1.00 1.81 5.43 0.03%
-0.16%
1002(26) Cistern 1.00 l/s 1.00 126.50 15.82 0.07%
-1.17%
1201(1) Water Pumping System 1.00 l/s 1.00 2.66 0.34 1.29%
-0.44%
1202(1) Fire Protection System 1.00 l/s 1.00 16.00 2.00 0.49%
-0.98%
1002(4) Plumbing Fixtures 1.00 l/s 1.00 120.40 15.05 0.03%
-0.50%
1002(24) Cold Water Lines 1.00 l/s 1.00 50.54 6.32 0.02%
-0.15%
1002(20) Facial Mirror 4.60 sq.m. 0.40 1.00 1.44 0.01%
-0.01%
1201 (8)a Water Tank including Concrete Platform (Rainwater Collector) 1.00 set 1.00 25.00 3.13 0.06%
-0.20%
1100(19) Conduit, Boxes, and Fittings (20 CL) 1.00 l/s 1.00 112.00 14.00 0.04%
-0.55%
1100(18) Wires and Wiring Devices (20 CL) 1.00 l/s 1.00 144.00 18.00 0.05%
-0.88%
1102(21) Power Load Center, Switchgear, and Panel Boards (20 CL) 1.00 l/s 1.00 96.00 12.00 0.07%
-0.87%
1103(1) Lighting Fixtures (20 CL) 1.00 l/s 1.00 128.00 16.00 0.04%
-0.68%
1208(1) Fire Alarm System (20 CL) 1.00 l/s 1.00 32.00 4.00 0.02%
-0.08%
1200(5)a Exhaust Fan 17.00 sets 1.00 0.50 1.07
WORK PROGRAMME/SCHEDULE
######
###
###
###
###
###
###
###
###
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
###
###
###
###
#REF! #REF! #REF! #REF! #REF! #REF! #REF! ###
###
###
###
###
###
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
###
###
###
###
###
###
###
###
###
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
###
###
###
###
### ###
###
###
###
###
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
###
###
#REF! #REF! #REF! #REF! #REF! #REF! #REF! ###
###
######
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
###
###
#REF! #REF! #REF! #REF! #REF! #REF! #REF! Total No. of Working Days 180 ###
###
###
###
#REF! #REF! #REF! #REF! #REF! #REF! #REF! No. of Sundays 30 ###
###
###
#REF! #REF! #REF! #REF! #REF! #REF! #REF! Inclement Weather
###
###
###
###
###
#REF! #REF! #REF! #REF! #REF! #REF! #REF! Total No. of Calendar Days 210 ###
###
#REF! #REF! #REF! #REF! #REF! #REF! #REF! ###
###
###
###
###
###
#REF! #REF! #REF! #REF! #REF! #REF! #REF! ###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
###
###
###
###
###
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
###
###
###
###
###
###
###
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
###
###
###
###
###
###
###
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
###
###
###
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
###
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
###
#REF! #REF! #REF! #REF! 3.10 #REF! #REF!
###
###
###
###
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
###
###
###
###
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
###
###
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
###
###
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
###
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
###
###
###
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
###
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
###
#REF! #REF! #REF! #REF! 0.18 #REF! #REF!
###
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
###
#REF! #REF! #REF! #REF! 5.13 #REF! #REF!
###
###
###
#REF! #REF! #REF! #REF! 1.00 #REF! #REF!
###
###
#REF! #REF! #REF! #REF! 0.13 #REF! #REF!
###
#REF! #REF! #REF! #REF! Err:508 #REF! #REF!
###
###
###
###
###
###
#REF! #REF! #REF! #REF! 6.32 #REF! #REF!
###
###
###
#REF! #REF! #REF! #REF! 0.00 #REF! #REF!
###
###
###
###
### ###
###
###
###
###
###
###
#REF! #REF! #REF! #REF! 18.00 #REF! #REF!
###
###
###
###
### ###
###
###
###
###
###
###
#REF! #REF! #REF! #REF! Err:509 #REF! #REF!
###
###
###
###
###
###
#REF! #REF! #REF! #REF! 16.00 #REF! #REF! ###
###
###
###
###
###
###
###
###
###
TOTAL #REF! #REF! MONTH 1 MONTH 2 MONTH 3 MONTH 4 MONTH 5 MONTH 6 MONTH 7 MONTH 8
PERCENTAGE ACCOMPLISHED #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
CUMMULATIVE PERCENTAGE ACCOMPLISHED #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
AMOUNT ACCOMPLISHED #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
CUMMULATIVE AMOUNT ACCOMPLISHED #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Construction of 4-Storey, 20-Classroom School Building at Vitali National High School, Zamboanga City
Man-days
No. of Body
Item No. Item Description Workers Rubber
Persons Safety Helmet Safety Shoes Safety Gloves Vest Dust Mask Eye Goggles Ear Muffs Harness and
Boots
Lanyard
1046(2)a1 100mm CHB Non-Load Bearing (including Reinforcing Steel) a. Construction Foreman 1
1046(2)a2 150mm CHB Non-Load Bearing (including Reinforcing Steel) a. Construction Foreman 1
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST
TOTAL UNIT COST
QUANTITY % DIRECT COST
(DIRECT+INDIRECT)
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS SUBMITTED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
A.1.1(3) Construction of Field Office for the Engineer 1.00 l/s 93,884.52 93,884.52 - 0.17
B.3 (1) Permits and Clearances 1.00 l/s 57,141.34 57,141.34 59,998.41 0.11
B.4(10) Miscellaneous Survey and Staking 1.00 l/s 9,845.04 9,845.04 12,198.00 0.02
B.7(1) Occupational Safety and Health Program 1.00 l/s 257,025.85 257,025.85 296,864.86 0.47
B.20 (1) Temporary Fence 1.00 l/s 142,150.75 142,150.75 176,124.78 0.26
Project ID
PART A EARTHWORKS
801(1) Removal of Structures and Obstruction 1.00 l/s 2,692.76 2,692.76 3,336.33 0.00
800(3) a1 Individual Removal of Trees (150mm dia - 300mm dia) 3.00 ea 5,649.31 1,883.10 2,333.17 0.01
803(4)a Shoring, Cribbing and Drain Excavation 1.00 l/s 780,111.29 780,111.29 966,557.88 1.44
1052(28)a Micro Piles In Drilled Holes, 0.20m 12' (ordinary soil condition) 507.00 m 3,431,322.73 6,767.89 8,385.42 6.33
803(1)a Structure Excavation (Common Soil) 1,208.65 cu.m. 317,242.15 262.48 325.21 0.59
804(1)a Embankment from Roadway/Structure Excavation, Common Soil 1,115.09 cu.m. 224,127.87 201.00 249.03 0.41
804(2)a Embankment from Common Borrow, Selected Borrow 70.95 cu.m. 71,907.49 1,013.50 1,255.72 0.13
901(1) Lean Concrete (Manual mixing) 107.67 cu.m. 663,583.04 6,163.10 7,636.08 1.22
900(2)c Structural Concrete (Class B, 2500 psi @ 28 days) 68.44 cu.m. 504,607.55 7,372.68 9,134.75 0.93
900 Structural Concrete (Ready Mix, Class AA/Class A/Class B/Class C/Class P/Seal Con 885.40 cu.m. 7,294,838.47 8,239.05 10,208.19 13.46
902(1)a Reinforcing Steel (Deformed), Grade 40 69,106.84 kgs. 5,581,007.78 80.76 100.06 10.29
902(1)b Reinforcing Steel (Deformed), Grade 60 146,513.02 kgs. 12,316,854.88 84.07 104.16 22.72
903(2) Formworks and Falseworks 4,399.16 sq.m. 1,833,048.75 416.68 516.27 3.38
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS SUBMITTED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
PART C FINISHING
1046(2)a1 100mm CHB Non-Load Bearing (including Reinforcing Steel) 291.54 sq.m. 272,700.44 935.38 1,158.93 0.50
1046(2)a2 150mm CHB Non-Load Bearing (including Reinforcing Steel) 2,096.64 sq. m. 2,847,331.37 1,358.04 1,682.62 5.25
1027(1) Cement Plaster Finish 8,628.84 sq. m. 1,977,264.47 229.15 283.91 3.65
1021(1)a Cement Floor Finish Plain 3,275.87 sq.m. 1,290,618.22 393.98 488.14 2.38
1003(1)a1 4.5mm Fiber Cement Board on Metal Frame Ceiling 570.39 sq.m. 444,590.74 779.45 965.73 0.82
1009(1) Jalousie Window (Glass) 78.00 sq.m. 121,492.80 1,557.60 1,929.87 0.22
1010(2)a Wooden Flush Door 40.08 sq.m. 70,951.24 1,770.24 2,193.33 0.13
1006(6) Steel Doors and Frames 1.00 l/s 43,997.94 43,997.94 54,513.45 0.08
1010(2)b Wooden Panel Door 75.60 sq.m. 410,128.32 5,424.98 6,721.55 0.76
1004(2) Finishing Hardware (Lockset and Hinges) 1.00 l/s 104,890.00 104,890.00 129,958.71 0.19
1005(1) Casement Steel Window (Awning Type) 11.52 sq.m. 53,622.21 4,654.71 5,767.18 0.10
1005(1) Residential Casement Window (Steel)- Swing type 172.80 sq.m 755,483.52 4,372.01 5,416.92 1.39
1012(8) Glass and Glazing 78.84 sq.m 142,303.74 1,804.97 2,236.36 0.26
1016(1)a Waterproofing Cement Base 196.74 sq.m 37,374.38 189.97 235.37 0.07
1003(17) Carpentry and Joinery Works 1.00 l/s 106.49 106.49 131.95 0.00
1032(1)a Painting Works (Masonry/Concrete Painting) 9,045.33 sq.m. 2,774,137.84 306.69 379.99 5.12
1032(1)b Painting Works (Wood Painting) 349.15 sq.m. 107,110.28 306.78 380.09 0.20
1032(1)c Painting Works (Steel Painting) 1,334.44 sq.m. 421,888.03 316.15 391.71 0.78
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS SUBMITTED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1014(1)a2 Prepainted Metal Sheets, Corrugated Type, Long Span 351.25 sq.m. 233,978.43 666.13 825.34 0.43
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll) 55.00 ln.m. 24,265.14 441.18 546.63 0.04
1013(2)b Fabricated Metal Roofing Accessory (Flashings) 18.92 ln.m. 8,125.05 429.44 532.08 0.01
1047(4)a Metal Structure Accessories (Bolts) 536.00 each 27,849.93 51.96 64.38 0.05
1047(4)b Metal Structure Accessories (Turnbuckle) 44.00 each 6,958.14 158.14 195.93 0.01
1047(5)c Metal Structure Accessories (Crossbracing) 459.49 kg 35,302.74 76.83 95.19 0.07
1047(5)d Metal Structure Accessories (Steel Plates) 1,026.44 kg 85,411.03 83.21 103.10 0.16
1047(5)b Metal Structure Accessories (Sagrods) 100.50 kg 8,400.74 83.59 103.57 0.02
1001(8) Sewer Line Works 1.00 l/s 130,792.03 130,792.03 162,051.32 0.24
1001(9) Storm Drainage and Downspout 1.00 l/s 168,699.88 168,699.88 209,019.15 0.31
1001(11) Septic Vault (CHB) 1.00 l/s 357,058.79 357,058.79 442,395.84 0.66
1201(1) Water Pumping System 1.00 l/s 222,028.44 222,028.44 275,093.24 0.41
1202(1) Fire Protection System 1.00 l/s 496,971.87 496,971.87 615,748.15 0.92
1002(24) Cold Water Lines 1.00 l/s 75,552.57 75,552.57 93,609.63 0.14
1201 (8)a Water Tank including Concrete Platform (Rainwater Collector) 1.00 set 101,356.82 101,356.82 125,581.10 0.19
PART D ELECTRICAL
1100(19) Conduit, Boxes, and Fittings (20 CL) 1.00 l/s 278,634.92 278,634.92 345,228.67 0.51
1100(18) Wires and Wiring Devices (20 CL) 1.00 l/s 444,304.37 444,304.37 550,493.11 0.82
1102(21) Power Load Center, Switchgear, and Panel Boards (20 CL) 1.00 l/s 439,492.23 439,492.23 544,530.88 0.81
1103(1) Lighting Fixtures (20 CL) 1.00 l/s 344,523.98 344,523.98 426,865.21 0.64
1208(1) Fire Alarm System (20 CL) 1.00 l/s 39,097.62 39,097.62 48,441.95 0.07
FORM POW-2015-01B-00
MINIMUM EQUIPMENT AND MANPOWER REQUIREMENT
Number of Number of
No. Equipment Description Capacity No. Manpower Description Capacity
Equipment Manpower
1 Backhoe 0.80 m3 1 1 Construction Foreman 1
2 Dump Truck 12 yd3 2 2 Steelman 3
3 Plate Compactor 5 hp 1 3 Mason 2
4 One Bagger Mixer 4 - 6 ft3/min 2 4 Carpenter 4
5 Bar Cutter 1 5 Electrician 1
6 Bar Bender 1 6 Painter 2
7 Welding Machine 500 amp 2 7 Plumber 1
8 Cutting Outfit 1 8 Welder 2
9 Jackhammer 2 9 Laborer 12
10 Chainsaw 1 10
11 Concrete Saw (7.5 hp), 14" Blade Dia. 1 11
12 Concrete Vibrator 2 12
13 Drill Rig, Mechanical Rotary 1 13
14 Truck Mounted crane (25T) 1 14
15 Bentonite Mixer 1 15
16 Bentonite Bin 1 16
17 Water Pump 1 17
18 Water Truck 1 18
19 Welding Machine- gas 500 amp 1 19
20 Tremie Pipe Set 1 20
21 SPT & Desanding machine 1 21
22 Tower Light 1 22
23 23
24 24
25 25
26 26
27 27
28
29
30
31
SUB-TOTAL 27 SUB-TOTAL 28
TOTAL
DETAILED UNIT PRICE ANALYSIS
A. LABOR
a. Construction Foreman 1 8 853.52 6,828.16
b. Skilled Worker 2 8 617.04 9,872.64
c. Unskilled Worker 2 8 475.60 7,609.60
Sub-total for A P 24,310.40
No. of
Name and Capacity No. of Days Daily Rate Amount
Equipment
B. EQUIPMENT, (2014 ACEL RATE)
E. MATERIALS
1 2" thk Rough Concrete Flooring @ CR (volume = 0.108 cu.m.)
a. Portland Cement 2.00 bags 317.87 635.73
b. Sand 0.05 cu.m. 1,750.00 94.50
c. Gravel 0.11 cu.m. 1,600.00 172.80
2 Wooden Frame, Wall Studs & Plywood Sidings
a. 2" x 2" Good Lumber 236.27 bd.ft. 59.00 13,939.93
b. 1/4" thk Ordinary Plywood 12.00 pcs. 484.85 5,818.20
c. Asst. CW Nails 2.50 kgs. 86.00 215.00
d. Finishing Nails 0.70 kg. 86.00 60.20
3 Wooden Flooring
a. 2" x 2" Good Lumber 91.95 bd.ft. 59.00 5,425.05
b. 1/2" thk Marine Plywood 5.00 pcs. 1,076.00 5,380.00
c. Asst. CW Nails 1.00 kg. 86.00 86.00
d. Finishing Nails 0.30 kg. 86.00 25.80
4 Wooden Truss & Purlins
a. 2" x 4" Good Lumber Top & Bottom Chord 121.00 bd.ft. 59.00 7,139.00
b. 2" 2" Good Lumber Purlins 56.85 bd.ft. 59.00 3,354.15
c. Asst. CW Nails 2.00 kgs. 86.00 172.00
5 G.I. Sheet Roofing
a. Ga. # 26 Corrugated G.I. Sheets, 10 ft. long 38.41 sq.m. 421.05 16,172.53
b. Ga. 26 Plain G.I. Ridge Roll 2.00 pcs. 329.00 658.00
c. Umbrella Nails 2.00 kgs. 76.00 152.00
d. Roof Sealant 0.25 L 345.00 86.25
6 Wooden Flush Door
a. Wooden Flush Door, 0.90m x 2.10m complete with f 1.89 sq.m. 934.00 1,765.26
7 Swing Type Window
a. 1" x 2" Good Lumber Window Frame 3.93 bd.ft. 59.00 231.87
b. 1/4" thk Ordinary Plywood 1.00 pc. 484.85 484.85
c. Hinges 2.00 pairs 65.00 130.00
8 Interlink Wire
a. Interlink Wire #12, 3' x 8' 2.00 rolls 800.00 1,600.00
9 Sanitary
a. Water Closet (Pail Flush Type) 1.00 no. 1,000.00 1,000.00
b. 4"Ø PVC Pipe 1.00 pc. 640.00 640.00
c. Empty Steel Drum 2.00 nos. 500.00 1,000.00
10 Furniture, Fixtures & Equipments
a. Plastic Table, 1m x 2m 1.00 no. 850.00 850.00
b. Monobloc Chairs 4.00 nos. 400.00 1,600.00
c. White Board with Eraser 1.00 no. 500.00 500.00
d. Plastic Pail 1.00 pc. 150.00 150.00
e. Plastic Tub 1.00 pc. 35.00 35.00
A. LABOR
a. Liason Officer 1 14 Included
E. MATERIALS
A. LABOR
a. Instrumentman 1 1 853.52 853.52
b. Laborer 2 1 475.60 951.20
c. AutoCAD Operator 1 12 503.36 6,040.32
E. MATERIALS
A. Labor
B. Equipment
97.31
Minor Tools (10% of labor cost)
F. Materials
A. Labor
Project Duration: 225
a. Part Time Safety Practitioner/Officer (4 hours per
week) 1 16.07 617.04 9,916.71
B. Equipment
F. Materials
A. Labor
B. Equipment
F. Materials
Item No./Description : 100(3)a2 Individual Removal of Trees (small,301mm dia up to 500mm dia)
Unit of Measurement : ea
Output per hour : 1.00
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity Quantity No. of Day/s Daily Rental Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
For removal of concrete/masonry structures
a. Construction Foreman 1 4.39 106.69 468.25
b. Unskilled Laborer 3 4.39 59.45 782.75
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Rental are based on Unumbered Memo of Maximo L. Carvajal - Authorizing the use of ACEL Rate Edition 26
Memo dated October 20, 2021
F. Materials
A. Labor
B. Equipment
F. Materials
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
a. Coco Log 0.3m dia x 2.70m spaced at 1.20m bd.ft. 4,528.03 25.00 113,200.76
b. 2'' x 8'' x 1.20m Coco Lumber Stringer/ Wales bd.ft. 3,232.77 25.00 80,819.20
c. Nails kg 78.00 75.00 5,850.00
No. of
Designation No. of Hour/s Hourly Rate Amount (PhP)
Person/s
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Minor Tools (10% of Labor Cost) 37.54
F. Materials
Item No./Description : 800(3) a1 Individual Removal of Trees (150mm dia - 300mm dia)
Unit of Measurement : ea
Output per hour : 1.00
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
B. Equipment
Rental are based on Unumbered Memo of Maximo L. Carvajal - Authorizing the use of ACEL Rate Edition 26
Memo dated October 20, 2021
F. Materials
*CMPD 4th Quarter of C.Y. 2023
a. Coco Log 0.3m dia x 4m spaced at 1.30m bd.ft. 9,330.58 55.00
b. 1'' x 8'' Coco Lumber Stringer/ Wales bd.ft. 7,234.06 35.00
c. Nails kg 30.00 76.00
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 10% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
2,560.56
1,851.12
2,853.60
Amount (PhP)
4,192.00
11,457.28
Amount (PhP)
768,654.01
780,111.29 1kg/100 bd.ft of lumber Base on Item 1052(13)
78,011.13
62,408.90
46,026.57
966,557.88
0.0848230016469
CAROLYN M. ORBECIDO
a. Coco Log 0.3m dia x 2.70m spaced at 1.20m 2,295.36
b. 2'' x 8'' x 1.20m Coco Lumber Stringer/ Wales 2,132.00
c. Nails 44.00
40105.4132655122
1603452.928 127.92
44
80
124
m in
0.3 11.8110236220472
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
B. Equipment
F. Materials
*CMPD 4th Quarter of C.Y. 2023
PIPES
a. Ready Mix 4000psi cu.m 0.033 7,500.00
b. Reinforced Steel Bar' kg 12.626 65.00
c. Welding Rod (1kg/2000kg of RSB) kg 0.006 200.00
d. Steel Tube 0.2 dia. kg 14.573 60.90
e. Miscellaneous (3% of Materials, Bentonite & etc.)
0.125
106.69
385.65
356.70
77.13
118.90
Amount (PhP)
9,351.38
1,549.45
6.75
4.22
86.50
140.00 0.0329867228627
133.13
1,225.00
269.50
76.80
134.16
130.43
104.51
4,752.30
Amount (PhP)
3
0.0314159265359 0.0295592452776264
247.50 0.0010178760198 2
820.69
1.20
887.50
58.71
2,015.60 604.68
6,767.89
676.79
541.43
399.31
8,385.42
CAROLYN M. ORBECIDO
Engineer III
Planning and Design Section
1 7849 14.5730912
7849 15.978617758241
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
B. Equipment
Rental are based on Unumbered Memo of Maximo L. Carvajal - Authorizing the use of ACEL Rate Edition 26
Memo dated October 20, 2021
F. Materials
A. Labor
B. Equipment
Rental are based on Unumbered Memo of Maximo L. Carvajal - Authorizing the use of ACEL Rate Edition 26
Memo dated October 20, 2021
F. Materials
-
G. Direct Unit Cost (E + F) 201.00
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 24.12
I. Contractor's Profit (CP) 8% of G 16.08
J. Value Added Tax (VAT) 5% of (G + H + I) 12.06
K. Total Unit Cost (G + H + I + J) 253.25
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
B. Equipment
Rental are based on Unumbered Memo of Maximo L. Carvajal - Authorizing the use of ACEL Rate Edition 26
Memo dated October 20, 2021
F. Materials
*CMPD 2nd Quarter of C.Y. 2023
kg 62.00
a. Reinforcing Steel Bar Err:509
lit 35.00
b. Curing Compound Err:509
60.00
c. Asphalt Sealant lit Err:509
d Steel Forms ln.m Err:509 40.00
e. Sand cu.m Err:509 1,048.00
f. Gravel cu.m Err:509 1,048.00
g. Cement bag Err:509 274.00
h. Concrete Saw (Diamond Blade 14") pc Err:509 8,000.00
i Grease/Tar/form oil lit Err:509 20.00
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G
I. Contractor's Profit (CP) 10% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Amount (PhP)
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Amount (PhP)
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Amount (PhP)
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509 Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
B. Equipment
Rental are based on Unumbered Memo of Maximo L. Carvajal - Authorizing the use of ACEL Rate Edition 26
Memo dated October 20, 2021
F. Materials
*CMPD 2nd Quarter of C.Y. 2023
A. Labor
B. Equipment
Rental are based on Unumbered Memo of Maximo L. Carvajal - Authorizing the use of ACEL Rate Edition 26
Memo dated October 20, 2021
F. Materials
*CMPD 2nd Quarter of C.Y. 2023
a. Gravel m3 1.00 1,600.00
b. Sand m3 0.50 1,750.00
c. Portland Cement bags 6.00 317.87
106.69
77.13
237.80
Amount (PhP)
172.00
42.16
1,780.90
Amount (PhP)
1,600.00
875.00
1,907.20
4,382.20
6,163.10
616.31
493.05
363.62
7,636.08
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
B. Equipment
Rental are based on Unumbered Memo of Maximo L. Carvajal - Authorizing the use of ACEL Rate Edition 26
Memo dated October 20, 2021
F. Materials
*CMPD 2nd Quarter of C.Y. 2023
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Item No./Description : 900 Structural Concrete (Ready Mix, Class AA/Class A/Class B/Class C/Class P/Seal Concrete,
days/14 days/28 days)
Unit of Measurement : m3
Output per hour : 3.72
A. Labor
B. Equipment
Rental are based on Unumbered Memo of Maximo L. Carvajal - Authorizing the use of ACEL Rate Edition 26
Memo dated October 20, 2021
F. Materials
*CMPD 4th Quarter of C.Y. 2023
0.05
1
lass C/Class P/Seal Concrete, 7
Amount (PhP)
106.69
154.26
356.70
Amount (PhP)
114.34
560.52
61.77
364.05
Amount (PhP)
7,875.00 265
198
7,875.00
8,239.05
823.91
659.12
486.10
10,208.19
2q
DETAILED UNIT PRICE ANALYSIS (DUPA)
Unit of Measurement : m3
Output per hour : 0.27
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Rental are based on Unumbered Memo of Maximo L. Carvajal - Authorizing the use of ACEL Rate Edition 26
Memo dated October 20, 2021
F. Materials
*CMPD 2nd Quarter of C.Y. 2023
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Item No./Description : 900 Structural Concrete (27.58 MPa @ 28 days) - 4000 psiStructural Concrete (Ready Mix, Cla
AAlClass A/Class B/Class C/Class P/Seal Concrete, 7 days/14 days/28 days)
Unit of Measurement : m3
Output per hour : 3.72
A. Labor
B. Equipment
F. Materials
203,558.98
189810
13,748.98
0.06754298372
al Concrete (Ready Mix, Class
days/28 days)
Amount (PhP)
106.69
77.13
237.80
Amount (PhP)
172.00
42.16
170.91
Amount (PhP)
3,337.60 265
875.00
1,600.00
198
5,812.60
5,983.51
718.02
478.68
359.01
7,539.22
DETAILED UNIT PRICE ANALYSIS (DUPA)
No. of
Designation No. of Hour/s Hourly Rate Amount (PhP)
Person/s
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Rental are based on Unumbered Memo of Maximo L. Carvajal - Authorizing the use of ACEL Rate Edition 26
Memo dated October 20, 2021
F. Materials
*CMPD 2nd Quarter of C.Y. 2023
No. of
Designation No. of Hour/s Hourly Rate Amount (PhP)
Person/s
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
No. of
Designation No. of Hour/s Hourly Rate Amount (PhP)
Person/s
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Installation
a. Construction Foreman 1 1.00 106.69 106.69
b. Skilled Laborer 4 1.00 77.13 308.52
c. Unskilled Laborer 6 1.00 59.45 356.70
Stripping
a. Construction Foreman 1 0.56 106.69 59.75
b. Unskilled Laborer 6 0.56 59.45 199.75
B. Equipment
Area = 205.01 m2
a. H-Frame 1.7m x 1.2m, set 40 14.00 6.08 3,404.80
2 pcs H-frames
4 pcs diagonal cross braces
4 pcs horizontal braces
8 pcs joint pins
b. Shoring Jack, 3.8m full extension 62 14.00 4.50 3,906.00
c. Adjustable U-head Jack, 0.6m 80 14.00 0.85 952.00
d. Adjustable Base Jack, 0.6m 80 14.00 0.85 952.00
e. 1-1/2'' G.I Pipe x 6.0m 62 14.00 2.50 2,170.00
f. 1-1/2'' G.I Pipe x 3.0m 16 14.00 1.25 280.00
g. 1-1/2'' G.I Pipe x 4.0m 32 14.00 1.75 784.00
h. 1-1/2'' G.I Pipe x 1.0m 216 14.00 0.50 1,512.00
i. Tie Rod x 0.60m 278 14.00 1.00 3,892.00
j. Rod Wing Nut 558 14.00 0.15 1,171.80
Sub - Total for B 19,024.60
C. Sub-Total for C (B/Area) 4.32
D. Output per Hour = 4.5 m²
E. Direct Unit Cost (A ÷ D) + C 233.53
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials
A. Labor
Installation
a. Construction Foreman 1 1.00 106.69 106.69
b. Skilled Laborer 2 1.00 77.13 154.26
c. Unskilled Laborer 4 1.00 59.45 237.80
Stripping
a. Construction Foreman 1 0.41 106.69 43.74
b. Unskilled Laborer 6 0.41 59.45 146.25
Sub - Total for A 688.74
Name and Capacity Quantity No. of Day/s Daily Rental Rate Amount (PhP)
B. Equipment
F. Materials
*CMPD 2nd Quarter of C.Y. 2023
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
*CMPD 4th Quarter of C.Y. 2023
Item No./Description : 1046(2)a1 100mm CHB Non-Load Bearing (including Reinforcing Steel)
Unit of Measurement : m2
Output per hour : 3.825
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Rental are based on Unumbered Memo of Maximo L. Carvajal - Authorizing the use of ACEL Rate Edition 26
Memo dated October 20, 2021
F. Materials
*CMPD 4th Quarter of C.Y. 2023
Item No./Description : 1046(2)a2 150mm CHB Non-Load Bearing (including Reinforcing Steel)
Unit of Measurement : m2
Output per hour : 3.18
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Rental are based on Unumbered Memo of Maximo L. Carvajal - Authorizing the use of ACEL Rate Edition 26
Memo dated October 20, 2021
F. Materials
*CMPD 4th Quarter of C.Y. 2023
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
*CMPD 4th Quarter of C.Y. 2023
A. Labor
B. Equipment
F. Materials
Item No./Description : 1021(1)c Plain Cement Floor Finish (with floor hardener)
Unit of Measurement : m2
Output per hour : 5.95
A. Labor
B. Equipment
F. Materials
A. Labor
B. Equipment
F. Materials
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
*CMPD 4th Quarter of C.Y. 2023
a. Cement bag 0.726 317.87 230.77
b. Sand cu.m 0.055 1,750.00 96.25
Item No./Description : 1003(2)a2 4.5mm thk Fiber Cement Board Walling on Metal Frame
Unit of Measurement : m2
Output per hour : 0.776
A. Labor
B. Equipment
F. Materials
Item No./Description : 1003(1)a1 4.5mm Fiber Cement Board on Metal Frame Ceiling
Unit of Measurement : m2
Output per hour : 1.243
A. Labor
B. Equipment
F. Materials
*CMPD 4th Quarter of C.Y. 2023
a. 4.5mm Fiber Cement Board pc 0.365 410.00 149.65
b. Metal Furring, single 19mm x 25mm x 0.40mm thk x 3m pc 1.131 138.00
length
156.08
and specifications ) 3m length
c. Carrying Channels (12mm x 38mm x 5m x 0.8mm) pc 0.357 200.00
71.40
d. Hanger Bars/Rod pc 1 80.00 80.00
e. Channel clip pc 6 5.00 30.00
f. Wall Angle pc 0.238 48.00 11.42
g. Rivets pc 14 0.50 7.00
h. 1" Metal Screw pc 4 1.50 6.00
A. Labor
B. Equipment
F. Materials
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
a. Prepainted G.i sheet mmini rib type sq.m 1.000 420.00 420.00
b. Metal Furring, single 19mm x 25mm x 0.40mm thk x 5m pc 1.131 138.00
length
156.08
and specifications ) 3m length
c. Carrying Channels (12mm x 38mm x 5m x 0.8mm) pc 0.357 200.00
71.40
d. Hanger Bars/Rod pc 1 80.00 80.00
e. Channel clip pc 6 5.00 30.00
f. Wall Angle pc 0.238 48.00 11.42
g. Rivets pc 14 0.50 7.00
h. 1" Metal Screw pc 4 1.50 6.00
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
*CMPD 4th Quarter of C.Y. 2023
a. Unglazed Tiles m2 1.050 375.00 393.75
b. Cement bags 0.325 317.87 103.31
c. Sand m3 0.026 1,750.00 45.94
d. Tile Grout bags 0.125 50.00 6.25
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
*CMPD 4th Quarter of C.Y. 2023
a. Glazed Tiles m2 1.050 313.00 328.65
b. Cement bags 0.325 317.87 103.31
c. Sand m3 0.026 1,750.00 45.94
d. Tile Grout bags 0.125 50.00 6.25
e. Tile Adhesive (25 kg) bags 0.143 250.00 35.75
f. Consumables (3% of Materials Cost) 15.60
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
*CMPD 4th Quarter of C.Y. 2023
Wooden Jambs set 113
a. 50mm x 150mm G.L Jamb bd.ft. 1,643.28 59.00 858.00
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
*CMPD 2nd Quarter of C.Y. 2023
a. Hollow Core Flush Type Swing Door sq.m. 1.00 934.00 934.00
A. Labor
B. Equipment
F. Materials
106.69
77.13
59.45
Amount (PhP)
24.33
26 1.1304 29.3904
6.2 0.785 4.867
991.10
Amount (PhP)
550.00
16.50
566.50
1,557.60
155.76
124.61
91.90
1,929.87
2.34 12.56
2.34 2.07991452991453
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
B. Equipment
F. Materials
*CMPD 4th Quarter of C.Y. 2023
a. Hollow Core Flush Type Swing Door sq.m. 1.00 934.00
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 10% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Amount (PhP)
106.69
77.13
59.45
Amount (PhP)
24.33
26 1.1304 29.3904
6.2 0.785 4.867
836.24
Amount (PhP)
934.00
934.00 MTRLS UNIT COST
1,770.24
177.02
141.62
104.44
2,193.33
2.34 12.56
2.34 2.07991452991453
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
B. Equipment
F. Materials
*CMPD 4th Quarter of C.Y. 2023
1,444.42
1,044.22
804.86
Amount (PhP)
1,255.69
329.35
26 1.1304 29.3904
6.2 0.785 4.867
4,878.54
Amount (PhP)
37,980.00
1,139.40
39,119.40 MTRLS UNIT COST
43,997.94
4,399.79
3,519.84
2,595.88
54,513.45 10,902.69
2.34 12.56
2.34 2.07991452991453
Item No./Description : 1010(2)b Wooden Panel Door
Unit of Measurement : sq.m.
Output per hour : 0.36
A. Labor
B. Equipment
F. Materials
*CMPD 4th Quarter of C.Y. 2023
Wooden Panel Door sq.m. 1.00 4,500.00 4,500.00
A. Labor
B. Equipment
F. Materials
*CMPD 4th Quarter of C.Y. 2023
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Rental are based on Unumbered Memo of Maximo L. Carvajal - Authorizing the use of ACEL Rate Edition 26
Memo dated October 20, 2021
**Note:
It is assumed that fabrication of steel windows are already completed. Thus,
labor and equipment output shall be based on installation time only.
F. Materials
*CMPD 4th Quarter of C.Y. 2023
A. Labor
B. Equipment
**Note:
It is assumed that fabrication of steel windows are already completed. Thus,
labor and equipment output shall be based on installation time only.
F. Materials
*CMPD 4th Quarter of C.Y. 2023
a.Swing type Casement Steel Window m2 1.00 2,035.00
c. Consumables (5% of Materials Cost)
106.69
77.13
59.45
Amount (PhP)
134.75
24.33
26 1.1304 29.3904
6.2 0.785 4.867
2,235.26
Amount (PhP)
2,035.00
101.75
2,136.75
4,372.01
437.20
349.76
257.95
5,416.92
CAROLYN M. ORBECIDO
Engineer III
Planning and Design Section
2.34 12.56
2.34 2.07991452991453
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
0.36 sq.m/hr - output per hour
a. Construction Foreman 1 1.00 106.69 106.69
b. Skilled Laborer 1 1.00 77.13 77.13
c. Unskilled Laborer 1 1.00 59.45 59.45
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
*CMPD 4th Quarter of C.Y. 2023
Fixed Glass on wood
D-1 sq.m 11.88 1,900.00 22,572.00
W-2 sq.m 18.00 1,900.00 34,200.00
Fixed Glass on metal frame
83,700.00
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
1.489 sq.m./hr
a. Construction Foreman 1 117.99 106.69 12,587.84
b. Skilled Laborer 1 78.66 77.13 6,066.80
c. Unskilled Laborer 2 39.33 59.45 4,676.15
Name and Capacity Quantity No. of Day/s Daily Rental Rate Amount (PhP)
B. Equipment
F. Materials
*CMPD 2nd Quarter of C.Y. 2023
a. Ceiling Vent pc 0.00 360.00 -
b. Blackboard pc 20.00 4,000.00 80,000.00
c. 3/4" Marine plywood pc Err:509 1,801.00 Err:509
d. 1/2" Marine plywood pc Err:509 1,076.00 Err:509
e. common nails kgs 15.00 86.00 1,290.00
f. drawer slides sets 32.00 240.00 7,680.00
Consumables (3% of Materials Cost) Err:509
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
*CMPD 2nd Quarter of C.Y. 2023
a. Jalousie Window (Glass) m2 1.00 550.00 550.00
b. Consumables (3% of Materials Cost) 16.50
A. Labor
B. Equipment
F. Materials
A. Labor
0.315 sq.m./hr
a. Construction Foreman 1 4.67 106.69 497.89
b. Skilled Laborer 1 4.67 77.13 359.94
c. Unskilled Laborer 1 4.67 59.45 277.43
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
1.47 sq.m.
a. PVC Doors and Frames set 1.00 2,000.00 2,000.00
b. Consumables (5% of Materials Cost) 100.00
A. Labor
B. Equipment
F. Materials
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
a. Analok Aluminum Sliding Window with Clear Glass Panel m2 1.00 5,500.00 5,500.00
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
B. Equipment
F. Materials
Roll-Up Door 3 Sets
a. Steel Roll Up Door for RD-1 Set 1.00 7,000.00 7,000.00
b. Steel Roll Up Door for RD-2 Set 2.00 7,000.00 14,000.00
b. Consumables (3% of Materials Cost) 630.00
21,630.00
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Item No./Description : 1003(1)a1 4.5mm Fiber Cement Board on Metal Frame Ceiling
Unit of Measurement : m2
Output per hour : 1.243
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
a. Aluminum Framing Awning Windows with Clear Glass m2 1.00 4,800.00 4,800.00
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
*CMPD 4th Quarter of C.Y. 2023
A. Labor
1.489 sq.m./hr
a. Construction Foreman 1 78.66
b. Skilled Laborer 1 78.66
c. Unskilled Laborer 2 78.66
B. Equipment
F. Materials
106.69 8,391.90
77.13 6,066.80
59.45 9,352.30
2,381.10
26,192.09
4,000.00 80,000.00
80,000.00
106,192.09
of G 10,619.21
of G 8,495.37
of (G + H + I) 6,265.33
(G + H + I + J) 131,572.00 263,144.00
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
B. Equipment
Rental are based on Unumbered Memo of Maximo L. Carvajal - Authorizing the use of ACEL Rate Edition 26
Memo dated October 20, 2021
F. Materials
*CMPD 4th Quarter of C.Y. 2023
1,030,610.48
G. Direct Unit Cost (E + F) 1,168,422.03
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 10% of G 116,842.20
I. Contractor's Profit (CP) 8% of G 93,473.76
J. Value Added Tax (VAT) 5% of (G + H + I) 68,936.90
K. Total Unit Cost (G + H + I + J) 1,447,674.90
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
B. Equipment
F. Materials
*CMPD 4TH Quarter of C.Y. 2023
a. Concrete Neutralizer L 0.08 221.00 16.73
b. Concrete Sealer/Primer gal 0.04 759.00 30.36
c. Patching Compound gal 0.05 404.00 20.20
d. Semi Gloss Latex (two coats) gal 0.08 812.00 64.96
e. Consumables (5% of Materials Cost) 6.61
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
*CMPD 4th Quarter of C.Y. 2023
a. Glazzing Putty gal 0.05 404.00 20.20
b. Flat Wall Enamel gal 0.04 836.00 33.44
c. Enamel Quick Dry gal 0.04 836.00 33.44
d. Paint Thinner gal 0.07 416.25 27.49
e. Consumables (5% of Materials Cost) 5.73
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
*CMPD 4th Quarter of C.Y. 2023
For Railings, Steel Stair and Rafter
a. Red Oxide Primer gal 0.04 554.50 22.18
b. Enamel Paint gal 0.10 836.00 83.60
c. Paint thinner gal 0.07 416.25 27.49
d. Consumables (5% of Materials Cost) 6.66
Item No./Description : 1014(1)a2 Prepainted Metal Sheets, Corrugated Type, Long Span
Unit of Measurement : m2
Output per hour : 2.076
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
*CMPD 2nd Quarter of C.Y. 2023
Item No./Description : 1014(1)b2 Prepainted Metal Sheet, Rib Type, Long Span
Unit of Measurement : m2
Output per hour : 2.769
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
a. Prepainted Metal Sheets (Base Metal Thickness = 0.4mm) m2 1.00 420.00 420.00
Item No./Description : 1014(1)a2 Prepainted Metal Sheets, Corrugated Type, Long Span
Unit of Measurement : m2
Output per hour : 2.076
A. Labor
B. Equipment
F. Materials
*CMPD 3rd Quarter of C.Y. 2023
a. Prepainted Metal Sheets (Corrugated, Base Metal
m2 1.05 420.00
Thickness = 0.4mm)
b. J bolt pc 10.00 5.00
c. Consumables (3% of Materials Cost)
106.69
77.13
118.90
Amount (PhP)
30.27
160.40
Amount (PhP)
441.00
50.00
14.73
505.73
666.13
66.61
53.29
39.30
825.34
CAROLYN M. ORBECIDO
Engineer III
Planning and Design Section
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
B. Equipment
F. Materials
*CMPD 4th Quarter of C.Y. 2023
a. Ridge Roll m 1.05 361.48
b. Blind Rivets pc 19.00 1.20
c. Consumables (3% of Materials Cost)
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 10% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Amount (PhP)
106.69
77.13
59.45
Amount (PhP)
24.33
26.76
Amount (PhP)
379.55
22.80
12.07
414.42
441.18
44.12
35.29
26.03
546.63
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
*CMPD 4th Quarter of C.Y. 2023
a. Pre-painted Flashing m 1.05 361.48 379.55
b. Blind Rivets pc 19.00 0.60 11.40
c. Consumables (3% of Materials Cost) 11.73
A. Labor
B. Equipment
F. Materials
A. Labor
B. Equipment
F. Materials
106.69
77.13
118.90
Amount (PhP)
30.27
168.29
Amount (PhP)
15.00
14.10
484.02
652.31
97.85
65.23
40.77
856.15
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
B. Equipment
F. Materials
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
*CMPD 2nd Quarter of C.Y. 2023
a. Ridge Roll m 1.05 361.48 379.55
b. Blind Rivets pc 19.00 0.60 11.40
c. Consumables (3% of Materials Cost) 11.73
A. Labor
B. Equipment
F. Materials
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
B. Equipment
F. Materials
A. Labor
Fabrication
a. Construction Foreman 1 1.00 106.69 106.69
b. Skilled Laborer 2 1.00 77.13 154.26
c. Unskilled Laborer 2 1.00 59.45 118.90
Erection
a. Skilled Laborer 3 0.49 77.13 113.38
b. Unskilled Laborer 3 0.49 59.45 87.39
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Rental are based on Unumbered Memo of Maximo L. Carvajal - Authorizing the use of ACEL Rate Edition 26
Memo dated October 20, 2021
F. Materials
*CMPD 4th Quarter of C.Y. 2023
a. Structural Steel Truss, Angle Bar kg 1.00 59.00 59.00
b. Acetylene kg 0.011 73.00 0.80
c. Oxygen kg 0.022 45.00 0.99
d. Welding Rod kg 0.020 200.00 4.00
e. Consumables (5% of Materials Cost) 3.24
A. Labor
B. Equipment
Rental are based on Unumbered Memo of Maximo L. Carvajal - Authorizing the use of ACEL Rate Edition 26
Memo dated October 20, 2021
F. Materials
*CMPD 4th Quarter of C.Y. 2023
a. Structural Steel Purlins kg 1.05 60.90 63.95
b. Welding Rod kg 0.02 200.00 4.00
b. Consumables (5% of Materials Cost) 3.40
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
*CMPD 4th Quarter of C.Y. 2023
pc 330.00
36.00
20mm Ø x 0.3 m - Long Anchor Bolts kg 244.12 26.63
pc 206.00
kg 1.83 110.00 0.98
6mm Ø x 0.4m - Machine Bolts
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
*CMPD 4th Quarter of C.Y. 2023
a. 16 mm dia Standard Turnbuckle pc 1.00 118.00 118.00
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
*CMPD 4th Quarter of C.Y. 2023
a. 16mm Cross Bracing kg 1.05 52.00 54.60
b. Consumables (3% of Material Cost) 1.64
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
*CMPD 4th Quarter of C.Y. 2023
a. Steel Plates kg 1.05 57.90 60.80
b. Consumables (3% of Materials Cost) 1.82
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
*CMPD 4th Quarter of C.Y. 2023
a. 12mm Sagrod with nuts and bolts kg 1.05 60.00 63.00
A. Labor
STEEL PLATE - 12.995 kgs/hr
a. Construction Foreman 1 Err:509 106.69
b. Skilled Laborer 1 Err:509 77.13
c. Unskilled Laborer 1 Err:509 59.45
Anchor Bolt - 1pc/0.1hr
a. Construction Foreman 1 Err:509 106.69
b. Skilled Laborer 1 Err:509 77.13
c. Unskilled Laborer 1 Err:509 59.45
B. Equipment
F. Materials
*CMPD 4th Quarter of C.Y. 2023
a. Steel plate/Checkered plate kg Err:509 57.90
b. 16mm Anchor Bolt kg Err:509 36.00
c. Rectangular/Square Tube kg Err:509 59.00
d. C8x13 - Stringer kg Err:509 60.90
e. Angle Bar kg Err:509 59.00
f. 20mm Square Bar kg Err:509 59.00
g. 50mm Dia. G.i Pipe pcs Err:509 1,834.00
h. 100mm Dia. G.i Pipe pcs Err:509 5,138.90
i. Consumables (3% of Materials Cost)-steel plate
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509 Err:509
Err:509
Err:509
Err:508
Err:508
Err:508
Err:509
Err:509
Err:509
Amount (PhP)
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509 Err:509 EQMT UNIT COST
Err:509
Err:509
Amount (PhP)
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Item No./Description : 1013(3) Fabricated Metal Roofing Accessory ,Plain GI Fascia Sheet, Gauge 26
Unit of Measurement : ea
Output per hour : 1.00
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Fascia Frame #REF! sq.m.
a. 12mm x 38mm x 5m x0.8mm thk Metal Furring Channel pc #REF! 177.00 #REF!
A. Labor
B. Equipment
F. Materials
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
B. Equipment
Rental are based on Unumbered Memo of Maximo L. Carvajal - Authorizing the use of ACEL Rate Edition 26
Memo dated October 20, 2021
F. Materials
*CMPD 2nd Quarter of C.Y. 2023
902(1)a - Reinforcing Steel (Deformed), Grade 40 (143.438
kg per hour)
a. Deformed Reinforcing Steel grade 40 kg 7.56 62.95 475.60
Grade
b. #16 60/Grade Iron
Galvanized 40 Wire kg 0.113 85.00 9.63
c. Consumables (5% of Materials Cost) 24.26
A. Labor
Fittings
(Labor cost for these items are to be considered/included in the installation of pipes.)
B. Equipment
F. Materials
*CMPD 4th Quarter of C.Y. 2023
PIPES
50mm∅ PVC PIPE pcs 24.00 380.00 9,120.00
100mm∅ PVC PIPE pcs 17.00 1,030.00 17,510.00
150mm∅ PVC PIPE pcs 9.00 1975.29 17,777.61
FITTINGS
Clean Out- 150mm dia pcs 10 627.90 6,279.00
Clean Out- 100mm dia pcs 16 72.00 1,152.00
Clean Out- 50mm dia pcs 4 23.00 92.00
50mm dia. 45 DEGREE ELBOW pcs 1.00 22.00 22.00
150mm dia. 45 DEGREE ELBOW pcs 2.00 478.38 956.76
100mm dia. 45 DEGREE ELBOW pcs 3.00 93.00 279.00
50mm Dia. 90-degree elbow pcs 110.00 50.00 5,500.00
100mm Dia. 90-degree elbow pcs 13.00 85.00 1,105.00
150mm Dia. 90-degree elbow pcs 4.00 538.33 2,153.32
50mm dia. WYE PVC pcs 10.00 76.00 760.00
100mm dia. WYE PVC pcs 66.00 159.00 10,494.00
150mm dia. WYE PVC pcs 14.00 1,136.21 15,906.94
100mm dia. P-Trap pcs 47.00 248.00 11,656.00
50mm dia. P- Trap pcs 8.00 103.00 824.00
100mm dia. Tee pcs 29.00 157.00 4,553.00
50mm dia. Tee pcs 80.00 41.00 3,280.00
Consumables (5% of Material Cost) 5,471.03
A. Labor
Fittings
(Labor cost for these items are to be considered/included in the installation of pipes.)
B. Equipment
F. Materials
PIPES
a. 4"∅ PVC Pipe Downspout pcs. 5.00 1,030.00 5,150.00
b. 5"∅ - PVC Pipe pcs. 3.00 1,975.29 5,925.87
FITTINGS
c. 4"∅ - 90° elbow pcs. 4.00 85.00 340.00
d. 4"∅ - 1/8 Bend pcs. 4.00 63.00 252.00
A. Labor
Fittings
(Labor cost for these items are to be considered/included in the installation of pipes.)
B. Equipment
F. Materials
*CMPD 4th Quarter of C.Y. 2023
50mm dia-100mm dia PVC Pipe (3m per hour)
Roof Drain 75mm pcs 4 191.00 764.00
Roof Drain 100mm pcs 22 191.00 4,202.00
75mm Dia. 90-Degree elbow pcs 10 52.00 520.00
100mm Dia. 90-Degree elbow pcs 64 85.00 5,440.00
100mm. Dia Tee pcs 3 157.00 471.00
A. Labor
B. Equipment
F. Materials
A. Labor
B. Equipment
Rental are based on Unumbered Memo of Maximo L. Carvajal - Authorizing the use of ACEL Rate Edition 26
Memo dated October 20, 2021
803(1)a - Structure Excavation (20 cu.m per hour)
a. Backhoe (0.80 m3) 1 3.53 2,096.00 7,394.69
b. Dump Truck (12 yd ) 3
2 3.53 1,420.00 10,019.52
Minor Tools (10% of Labor Cost) 100.56
F. Materials
A. Labor
B. Equipment
F. Materials
*CMPD 4th Quarter CY 2023
900(2)c - Structural Concrete (Class B, 2500 psi @ 28
days)
a. Portland Cement bags 0.58 317.87
b. Washed Sand cu.m. 0.04 1,750.00
c. Washed Gravel cu.m. 0.07 1,600.00
902(1)a - Reinforcing Steel (Deformed), Grade 40 (143.438
kg per hour)
a. Deformed Reinforcing Steel kg 7.56 62.00
b. Grade 60/Grade Iron
#16 Galvanized 40 Wire kg 0.113 85.00
c. Consumables (5% of Materials Cost)
1046(2)a1 - 100mm CHB Non-Load Bearing(including
Reinforcing Steel)
a. 100 mm thk CHB (Non-Load Bearing) pc 31.20 14.00
b. Cement bag 1.26 317.87
c. Sand cu.m 0.11 1,750.00
d. Reinforcing Steel
kg 0.23 62.00
e. #16 Tie wire kg 0.12 85.00
55.31
92.46
28.45
20.57
63.41
6.24
13.54
41.75
66.94
96.79
111.91
35.94
51.96
80.10
Amount (PhP)
14.78
45.87
11.24
3.09
4.94
6.15
107.92
27.56
16.80
1,003.73
Amount (PhP)
183.09 265
63.00
115.20
468.44
9.63
23.90
436.80
400.51
184.80
14.46
10.20
251.75
113.40
2,275.20 682.56
3,278.93
327.89
262.31
193.46
4,062.59
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
B. Equipment
C. Total (A + B)
D. Output per Hour = 1 ls
E. Direct Unit Cost (C ÷ D)
F. Materials
*CMPD 4th Quarter of C.Y. 2023
1.068282
911.80
1,524.22
1,393.95
2,015.48
4,660.45
1,630.99
3,537.30
10,905.87
856.66
1,238.63
1,909.41
8,650.82
6,253.99
4,820.43
1,071.08
1,548.65
1,790.49
Amount (PhP)
13,135.60
24,271.37
243.60
1,493.90
7,323.45
806.99
1,679.68
2,686.72
1,607.42
400.47
1,726.75
441.02
110,537.20
110,537.20
Amount (PhP)
169,943.76
42,528.06
77,765.60
135,951.27
2,795.77
6,001.10
2,471.47
6,988.80
6,408.19
2,688.00
7,713.79
163.20
7,183.51 23,961.98
449.00 Wilcons
10,659.00
479,710.53 143,913.16
590,247.73
59,024.77
47,219.82
34,824.62
731,316.94
`
A. Labor
B. Equipment
F. Materials
*CMPD 4th Quarter of CY 2023
End-Suction Centrifugal Water Pump, TDH 27m, 3.0HP, 80G unit 2.00 47,000.00
Booster Pump, TDH 25m, 3HP, 60 GPM unit 1.00 39,300.00
Elbow pcs 9.00 46.00
Tee pcs 2.00 56.00
Float Valve pcs 1.00 449.00
Gate Valve pcs 6.00 980.00
Check Valve pcs 3.00 954.00
Overhead Water Tank 1500 US Gal unit 2.00 38,950.00
0.3325
1002(3)a
283.80
410.33
316.27
Amount (PhP)
101.04
1,111.44
Amount (PhP)
94,000.00
39,300.00
414.00
Old Dupa
112.00
449.00 Wilcons
5,880.00
2,862.00
77,900.00 Wilcons
220,917.00 66,275.10
222,028.44
22,202.84
17,762.28
13,099.68
275,093.24
`
A. Labor
B. Equipment
F. Materials
*CMPD 4th Quarter of C.Y. 2023
PIPES
75mm Dia. G.I. SCH. 40 lngths 17.00 2,328.00
65mm Dia. G.I. SCH. 40 lngths 20.00 1,885.00
50mm Dia. G.I. SCH. 40 lngths 5.00 1,834.00
FITTINGS
G.I. 75mm Dia. 90-degree elbow pcs. 6.00 69.00
G.I. 65mm Dia. 90-degree elbow pcs. 5.00 310.00
G.I. 50mm Dia. 90-degree elbow pcs. 4.00 95.00
G.I. 65mm Dia. Tee pcs. 1.00 78.00
G.I. 50mm Dia. Tee pcs. 3.00 68.00
Gate Valve 32mm pcs. 16.00 627.00
Gate Valve 50mm pcs. 3.00 980.00
Fire extinguisher(10lbs) pcs. 28.00 6,825.00
Fire Hose Cabinet pcs. 8.00 24,000.00
Siamese pcs. 1.00 6,500.00
2
1002(3)a
1,707.04
1,234.08
1,902.40
Amount (PhP)
484.35
5,327.87
Amount (PhP)
39,576.00
37,700.00 CMPD
9,170.00
414.00
1,550.00 HET HARDWARE
380.00 HET HARDWARE
78.00
204.00
10,032.00
2,940.00
191,100.00 CMPD
192,000.00
6,500.00
491,644.00
496,971.87
49,697.19
39,757.75
29,321.34
615,748.15
SQ
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
*CMPD 4th Quarter of C.Y. 2023
a. Lavatory sets 8.00 5,500.00 44,000.00
b. Hose Bibb pcs 52.00 300.00 15,600.00
c. Water Closet sets 20.00 7,353.00 147,060.00
d. Floor Drain pcs 39.00 191.00 7,449.00
e. Urinal Drain sets 4.00 8,051.00
f. Sink Drain sets 10.00 4,512.00
Consumables (5% of Material Cost) 10,705.45
A. Labor
13mm dia -50mm dia PPR-C Pipe (1.33 hours per pc)
a. Construction Foreman 1 50.54 106.69 5,392.11
b. Skilled Laborer 1 50.54 77.13 3,898.15
c. Unskilled Laborer 2 50.54 59.45 6,009.21
PPR-C Fittings
(Labor cost for these items are to be considered/included in the installation of pipes.)
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
32 mm PPRC pcs. 29.00 736.28 21,352.12
50mm PPRC pcs. 9.00 2,952.50 26,572.50
FITTINGS
32mm - 90 deg elbow pcs. 113.00 31.60 3,570.80
50mm - 90 deg elbow pcs. 6.00 157.00 942.00
32mm - Tee pcs. 119.00 43.42 5,166.98
50mm - Tee pcs. 5.00 223.75 1,118.75
A. Labor
B. Equipment
F. Materials
*CMPD 4th Quarter of C.Y. 2023
Facial Mirror m2 1.00 600.00
106.69
77.13
59.45
Amount (PhP)
24.33
668.99
Amount (PhP)
6.66666666666667
600.00 78
30.00
630.00 1,575.00
1,298.99
129.90
103.92
76.64
1,609.45
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No./Description : 1201 (7)a Water Tank including Concrete Platform (Rainwater Collector)
Unit of Measurement : set
Output per hour : 1.00
A. Labor
B. Equipment
b. Stainless Steel Water Tank (Vertical), 1.35m dia , 1.40m height, l/s 1.00
2000L, with reinforced concrete platform
ater Collector)
106.69 2,560.56
77.13 3,702.24
59.45 5,707.20
106.69 106.69
77.13 154.26
59.45 237.80
12,468.75 12,468.75
1,246.88
1,420.00 1,322.12
2,569.00 2,569.00
15,037.75
15,037.75
-
15,037.75
of G 1,804.53
of G 1,203.02
of (G + H + I) 902.26 37,895.12
(G + H + I + J) 18,947.56
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
1201 (8) Water Tank Set
#REF! ###
#REF! ###
#REF! ###
###
#REF! ###
#REF! ###
#REF! ###
###
0.00 ###
0.00 ###
0.00 ###
0.00 ###
205.00 ###
0.00 ###
0.00 ###
###
36
414
1
179
2.3
-
DETAILED UNIT PRICE ANALYSIS (DUPA)
No. of No. of
Designation Hourly Rate Amount (PhP)
Person/s Hour/s
A. Labor
F. Materials
a. Exhaust Fan Tubular Type, Wall Mounted set 1.00 1,440.00 1,440.00
No. of No. of
Designation Hourly Rate Amount (PhP)
Person/s Hour/s
A. Labor
F. Materials
a. 2.5hp ACU Inverter Type, Split Type set 1.00 56,400.00 56,400.00
No. of No. of
Designation Hourly Rate Amount (PhP)
Person/s Hour/s
A. Labor
F. Materials
a. Fire Extinguisher, 10lbs ABC with Bracket set 1.00 2,099.00 2,099.00
No. of Hourly
Designation No. of Hour/s Amount (PhP)
Person/s Rate
A. Labor
F. Materials
No. of No. of
Designation Hourly Rate Amount (PhP)
Person/s Hour/s
A. Labor
F. Materials
Item No./Description : 1102(21) Power Load Center, Switchgear, and Panel Boards (20 CL)
Unit of Measurement : l.s.
Output per hour : 1.00
No. of No. of
Designation Hourly Rate Amount (PhP)
Person/s Hour/s
A. Labor
F. Materials
No. of No. of
Designation Hourly Rate Amount (PhP)
Person/s Hour/s
A. Labor
F. Materials
F. Materials
Amount (PhP)
2,468.16
1,902.40
4,370.56
Amount (PhP)
437.06
437.06
4,807.62
4,807.62
Amount (PhP)
13,890.00
10,400.00
10,000.00
34,290.00
39,097.62
3,909.76
3,127.81
2,306.76
48,441.95
DETAILED UNIT PRICE ANALYSIS (DUPA)
No. of No. of
Designation Hourly Rate
Person/s Hour/s
A. Labor
F. Materials
27.36
Amount (PhP)
2.74
30.10
Amount (PhP)
2,600.00
2,630.10
263.01
210.41
155.18
3,258.69
DETAILED UNIT PRICE ANALYSIS (DUPA)
No. of
No. of Hourly
Designation Person/ Amount (PhP)
Hour/s Rate
s
A. Labor
Prepared by:
JOEL S. PERLA
Engineer II
ridges from the National Road/s leading to Major/Strategic Public Buildings/Facilities
ad, Barangay Malagutay, Zamboanga City
P 207.74
P -
No. of Units No. of Hours Hourly Rate Amount
P 4,631.50
P -
4,839.24
-
300.00
-
16.13
P -
P -
16.13
-
15% of G.1 2.42
15% of G.2 -
10% of G.1 1.61
10% of G.2 -
5% of (G.1 + H.1 + I.1) 1.01
5% of (G.2 + H.2 + I.2) -
(G.1 + H.1 + I.1 + J.1) 21.17
(G.2 + H.2 + I.2 + J.2) -
OK
Checked by:
CAROLYN M. ORBECIDO
Engineer III
Chief, Planning & Design Section
s/Facilities
-2015-01D-00
Amount
98.30
109.44
207.74 0.69
-
Amount
2,173.00
1,846.00
612.50
4,631.50 15.44
-
4,839.24
-
300.00
-
16.13
Amount
-
16.13
-
2.42
-
1.61
-
1.01
-
21.17
-
Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the Natio
Construction of Road, Barangay Malagu
Prepared by:
JOEL S. PERLA
Engineer II
ridges from the National Road/s leading to Major/Strategic Public Buildings/Facilities
ad, Barangay Malagutay, Zamboanga City
te Subbase Course
P 207.74
P -
No. of Units No. of Hours Hourly Rate Amount
P 4,631.50
P -
4,839.24
-
50.00
-
96.78
P 862.50
P -
959.28
-
15% of G.1 143.89
15% of G.2 -
10% of G.1 95.93
10% of G.2 -
5% of (G.1 + H.1 + I.1) 59.96
5% of (G.2 + H.2 + I.2) -
(G.1 + H.1 + I.1 + J.1) 1,259.06
(G.2 + H.2 + I.2 + J.2) -
OK
Checked by:
CAROLYN M. ORBECIDO
Engineer III
Chief, Planning & Design Section
s/Facilities
-2015-01D-00
Amount
98.30
109.44
207.74 4.15
-
Amount
2,173.00
1,846.00
612.50
4,631.50 92.63
-
4,839.24
-
50.00
-
96.78
Amount
862.50
862.50
-
959.28
-
143.89
-
95.93
-
59.96
-
1,259.06
-
mix is
=16.099
5x9.5x2
5=
Basic Infrastructure Program (BIP) - Access Roads and/or Bridges
3823.63from the Natio
Liter
Construction of Road,RentalBarangay Malag
rate
factor
per hr =
3,823.63
DETAILED UNIT PRICE ANALYS
liters/16
000
liters/hr.
Item No./Description: 311(1)a Portland Cement
= .2389 Concrete Paveme
Unit of Measurement: sq.m. say 0.24
Output per hour-As Submitted: 107.33
Output per hour-As Evaluated:
Note: output base on bagger mixer
Designation No. Person
A.1 Labor
a. Construction Foreman 1
b. Skilled 4
c. Laborer 12
Prepared by:
JOEL S. PERLA
Engineer II
ridges from the National Road/s leading to Major/Strategic Public Buildings/Facilities
d, Barangay Malagutay, Zamboanga City
P 1,039.38
P -
No. of Units No. of Hours Hourly Rate Amount
P 10,979.73
P -
12,019.11
-
107.33
-
111.98
P 678.01
P -
789.99
-
15% of G.1 118.50
15% of G.2 -
10% of G.1 79.00
10% of G.2 -
5% of (G.1 + H.1 + I.1) 49.37
5% of (G.2 + H.2 + I.2) -
(G.1 + H.1 + I.1 + J.1) 1,036.86
(G.2 + H.2 + I.2 + J.2) -
OK
Checked by:
CAROLYN M. ORBECIDO
Engineer III
Chief, Planning & Design Section
s/Facilities
-2015-01D-00
Amount
98.30
284.44
656.64
1,039.38 9.68
-
Amount
5,844.00
114.34
1,759.50
1,733.00
545.00
833.00
32.00
10.55
56.38
51.97
10,979.73 102.30
-
12,019.11
-
107.33
-
111.98
Amount
20.46
10.15
7.20
18.40
86.46
141.75
391.82
1.20
0.54
0.03
678.01
-
789.99
-
118.50
-
79.00
-
49.37
-
1,036.86
-
LOAD SCHEDULE : PANEL BOARD
Connect to
Existing Single
Phase power
source
2 x 8.0 mm² THHN 1
x 5.5 mm² THHN IN 32
mm Ø RSC
2 x 8.0 mm² THHN 1
x 5.5 mm² THHN IN 32
mm Ø RSC
40 AT
60 AT
40 AT
2 x 22 mm² THHN 1
x 5.5 mm² THHN IN 40
mm Ø RSC
60 AT
60 AT
I= 5572 VA
230
I= 24.23
USE : 40 AT ; 40AF ; 2P ; 240 V ; 60 HZ ; 10 KAIC
40 AT
15 AT 20 AT SPARE SPARE
1 2 3 4
x 14 mm² THHN 1
5.5 mm² THHN IN 40
mm Ø RSC
60 AT
15 AT 15 AT 15 AT 15 AT 15 AT 20 AT 20 AT SPARE SPARE
1 2 3 4 5 6 7 8 9
8 mm² THHN 1x
mm² THHN IN 40
m Ø RSC
40 AT
15 AT 15 AT 15 AT 20 AT SPARE SPARE
1 2 3 4 5 6
x 22 mm² THHN 1
5.5 mm² THHN IN 40
mm Ø RSC
60 AT
30 AT 30 AT 30 AT SPARE SPARE
1 2 3 4 5
x 14 mm² THHN 1
5.5 mm² THHN IN 40
mm Ø RSC
60 AT
30 AT 30 AT 30 AT SPARE SPARE
1 2 3 4 5
4322.4
2760
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
1. Reinforced Concrete
#REF! #REF! #REF! 1,232.00 #REF!
#REF! #REF! #REF! 1,515.00 #REF!
#REF! #REF! #REF! 269.00 #REF!
2. Reinforcing Steel
#REF! #REF! #REF! 40.00 #REF!
#REF! #REF! #REF! 40.00 #REF!
#REF! #REF! #REF! 102.00 #REF!
d. Consumables (5% of Material Cost) #REF!
3. CHB Wall
#REF! #REF! #REF! 13.00 #REF!
#REF! #REF! #REF! 269.00 #REF!
#REF! #REF! #REF! 1,515.00 #REF!
#REF! #REF! #REF! 40.00 #REF!
#REF! #REF! #REF! 102.00 #REF!
No. of No. of
Designation Hourly Rate Amount (PhP)
Person/s Hour/s
A. Labor
F. Materials
Item No./Description : 1201 (8)a Water Tank including Concrete Platform (Rainwater Collector)
Unit of Measurement : set
Output per hour : 1.00
Rainwater Collector
a. Hose Bibb, 20mm dia pcs 1.00
MARCO C. MIGUEL
Engineer II
Planning and Design Section
DUPA)
nwater Collector)
106.69 2,560.56
77.13 3,702.24
59.45 5,707.20
106.69 106.69
77.13 154.26
59.45 237.80
12,468.75 12,468.75
Hourly Rate Amount (PhP)
1,246.88
1,246.88 1,246.88
13,715.63
13,715.63
Unit Cost Amount (PhP)
300.00 300.00
84,788.54
2,552.66
87,641.19 87,641.19
101,356.82
of G 10,135.68
of G 8,108.55
of (G + H + I) 5,980.05 251,162.20
(G + H + I + J) 125,581.10
CAROLYN M. ORBECIDO
Engineer III
Planning and Design Section
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
1201 (8) Water Tank Set
#REF! ###
#REF! ###
#REF! ###
###
#REF! ###
#REF! ###
#REF! ###
###
0.00 ###
0.00 ###
0.00 ###
0.00 ###
205.00 ###
0.00 ###
0.00 ###
###
36
414
1
179
2.3
26,292.36
PRICE DERIVATION: Stainless Steel Tank (Vertical), 1.35m dia, 1.40m height, 2000L, with re
***Note: Per DO 63, s2022, part A: Projects for Bidding. The material prices may vary from the issued CMPD when necessary,
and certified by the head of the implementing office. Thus, the prices for Gravel, Sand, Portland Cement and Reinforcing Steel
prices of construction materials for 2022.
A. Labor
a. Construction Foreman 1 1
b. Unskilled Laborer 3 1
Sub - Total for A
A. Labor
a. Construction Foreman 1 1
b. Unskilled Laborer 3 1
Sub - Total for A
A. Labor
a. Construction Foreman 1 1
b. Unskilled Laborer 3 1
Sub - Total for A
A. Labor
a. Construction Foreman 1 1
b. Unskilled Laborer 3 1
Sub - Total for A
A. Labor
a. Construction Foreman 1 1
b. Skilled Laborer 1 1
c. Unskilled Laborer 4 1
Sub - Total for A
A. Labor
a. Construction Foreman 1 1
b. Skilled Laborer 3 1
c. Unskilled Laborer 12 1
Sub - Total for A
Item No./Description : 1046(2)a1 CHB Non Load Bearing (including Reinforcing Ste
Unit of Measurement : sq.m.
A. Labor
a. Construction Foreman 1 1
b. Skilled Laborer 2 1
c. Unskilled Laborer 3 1
A. Labor
a. Construction Foreman 1 1
b. Skilled Laborer 2 1
c. Unskilled Laborer 4 1
Sub - Total for A
106.69 106.69
59.45 178.35
285.04 14.252 LABOR UNIT COST
2,096.00 2,096.00
1,420.00 2,840.00
28.50
4,964.50 248.225 EQMT UNIT COST
###
106.69 106.69
59.45 178.35
285.04 28.967 LABOR UNIT COST
###
Hourly Rate Amount (PhP)
123.00 92.25
2,096.00 1,572.00
28.50
1,692.75 172.028 EQMT UNIT COST
###
106.69 106.69
59.45 178.35
285.04 28.967 LABOR UNIT COST
123.00 92.25
2,096.00 1,572.00
28.50
1,692.75 172.028 EQMT UNIT COST
###
500.00 625.00
UNIT COST
106.69 106.69
59.45 178.35
285.04 237.533 LABOR UNIT COST
###
Hourly Rate Amount (PhP)
123.00 61.50
28.50
1,600.00 1,680.00
1,680.00 1,680.000 MATRL UNIT COST
###
106.69 106.69
77.13 77.13
59.45 237.80
421.62 1,181.008 LABOR UNIT COST
###
Hourly Rate Amount (PhP)
172.00 172.00
42.16
1,600.00 1,600.00
1,750.00 875.00
260.00 2,366.00
4,841.00 4,841.000 MATRL UNIT COST
###
ed), Grade 40 UNIT COST
106.69 106.69
77.13 231.39
59.45 713.40
1,051.48 7.331 LABOR UNIT COST
###
Hourly Rate Amount (PhP)
105.47 52.74
168.75 84.38
105.15
62.00 65.10
85.00 1.28
3.32
106.69 106.69
77.13 154.26
59.45 178.35
172.00 172.00
43.93
24.00 312.00
260.00 136.50
1,750.00 77.00
62.00 200.88
85.00 4.25
106.69 106.69
77.13 154.26
59.45 237.80
498.75 70.000 LABOR UNIT COST
###
Hourly Rate Amount (PhP)
49.88
49.88 7.000 EQMT UNIT COST
###
260.00 85.80
1,750.00 47.25
133.05 133.050 MATRL UNIT COST
###
Construction of Rainwater Collector System (RWCS), DPWH-ZCDEO Field Office, Brgy.Pata
Zamboanga City
SUMMARY OF QUANTITIES
Pay Item
Description
(Number)
PART B PLAIN AND REINFORCED CONCRETE WORKS
903(2) Forms and Falseworks
PART C FINISHING
1003(17) Carpentry and Joinery Works (Fascia Board)
1013(2)b1 Fabricated Metal Roofing Accessory (Gutter)
PART E MECHANICAL
1201(8) Water Tank
CDEO Field Office, Brgy.Patalon,
Unit of
Quantity
Measure
sq.m. 11.640
l.s. 1.000
m. 9.700
set 2.00
Construction of Rainwater Collector System (RWCS), DPWH-ZCDEO Field Office, Brgy.Patalo
Quantity Computation
Earthworks Q L W
2.00 4.00 0.40
Structure Excavation
2.00 2.45 0.40
Structural Concrete Q L W
Platform 1.00 3.70 2.15
2.00 4.00 0.40
Footing
2.00 2.45 0.40
Masonry Works Q L D
CHB (100 mm thk.) 2.00 3.70 0.50
CHB (100 mm thk.) 2.00 1.95 0.50
Finishing Works Q L W
Top of Platform 1.00 3.70 2.15
Side 1 2.00 3.70 0.30
Side 2 2.00 2.15 0.30
SCAFFOLDING Q L H
Sides 1.00 9.70
Height of Structure 3.00
H Frame 1.70
FASCIA BOARD Q L
Sides 1.00 9.70
GUTTER Q L W
Sides 1.00 9.70
Reinforcing Steel
NO. OF BAR SIZE
STRUCTURE COMPONENT MARK
MEMBERS (mm)
1.000 XB 12
TOP SLAB
1.000 ZB 12
2.000 BB-X 10
F1
2.000 BB-V 10
2.000 BB-X 10
F2
2.000 BB-V 10
DEO Field Office, Brgy.Patalon, Zamboanga City
D VOLUME
0.60 1.920
0.60 1.176
3.096 1.55
0.10 0.320
0.10 0.196
0.10 0.683
1.1985 0.60
D VOLUME
0.10 0.7955
0.20 0.640
0.20 0.392
1.828 0.91
AREA
3.700
1.950
5.650 2.83
AREA
7.955
2.220
1.290
11.465 5.73
W AREA
1.20 11.640
1.20
11.640
TL
9.700
9.700
TL
9.700
9.700
99.40
49.70
Construction of Rainwater Collector System (RWCS), D
ylene Tank (Vertical), 1.35m dia, 1.50m height, 2000L, with reinforced concrete platform
LABOR EQUIPMENT
Quantity (PHP) (PHP)
UNIT COST ALLOCATION UNIT COST ALLOCATION
2.00
TOTAL
mboanga City
concrete platform
MATERIAL TOTAL
(PHP) ALLOCATION
UNIT COST ALLOCATION
(PHP)
0.000 491.357
188.132
625.000 0.000 0.000
1,680.000 2,122.680 2,517.570
30,400.000 60,800.000
84,788.538
Construction of Rainwater Collector System (RWCS)
Steel Tank (Horizontal), 1.35m dia, 1.40m height, 2000L, with reinforced concrete platform
LABOR EQUIPMENT
Quantity (PHP) (PHP)
UNIT COST ALLOCATION UNIT COST ALLOCATION
2.00
TOTAL
oanga City
d concrete platform
MATERIAL TOTAL
(PHP) ALLOCATION
UNIT COST ALLOCATION
(PHP)
Err:509 Err:509
0.000
1,680.000 Err:509 Err:509
42,275.000 84,550.000
Err:509
PRICE DERIVATION: Stainless Steel Tank (Vertical), 1.35m dia, 1.40m height, 2000L, with re
***Note: Per DO 63, s2022, part A: Projects for Bidding. The material prices may vary from the issued CMPD when necessary,
and certified by the head of the implementing office. Thus, the prices for Gravel, Sand, Portland Cement and Reinforcing Steel
prices of construction materials for 2022.
A. Labor
a. Construction Foreman 1 1
b. Unskilled Laborer 3 1
Sub - Total for A
A. Labor
a. Construction Foreman 1 1
b. Unskilled Laborer 3 1
Sub - Total for A
A. Labor
a. Construction Foreman 1 1
b. Unskilled Laborer 3 1
Sub - Total for A
A. Labor
a. Construction Foreman 1 1
b. Skilled Laborer 1 1
c. Unskilled Laborer 4 1
Sub - Total for A
A. Labor
a. Construction Foreman 1 1
b. Skilled Laborer 3 1
c. Unskilled Laborer 12 1
Sub - Total for A
Item No./Description : 1046(2)a1 CHB Non Load Bearing (including Reinforcing Ste
Unit of Measurement : sq.m.
A. Labor
a. Construction Foreman 1 1
b. Skilled Laborer 2 1
c. Unskilled Laborer 3 1
A. Labor
a. Construction Foreman 1 1
b. Skilled Laborer 2 1
c. Unskilled Laborer 4 1
Sub - Total for A
106.69 106.69
59.45 178.35
285.04 14.252 LABOR UNIT COST
2,096.00 2,096.00
1,420.00 2,840.00
28.50
4,964.50 248.225 EQMT UNIT COST 248.23
106.69 106.69
59.45 178.35
285.04 28.967 LABOR UNIT COST
28.97
Hourly Rate Amount (PhP)
123.00 92.25
2,096.00 1,572.00
28.50
1,692.75 172.028 EQMT UNIT COST 172.03
UNIT COST
Hourly Rate Amount (PhP)
106.69 106.69
59.45 178.35
285.04 237.533 LABOR UNIT COST
237.53
Hourly Rate Amount (PhP)
123.00 61.50
28.50
1,600.00 1,680.00
106.69 106.69
77.13 77.13
59.45 237.80
421.62 1,181.008 LABOR UNIT COST
1,181.01
Hourly Rate Amount (PhP)
172.00 172.00
42.16
106.69 106.69
77.13 231.39
59.45 713.40
1,051.48 7.331 LABOR UNIT COST
7.33
Hourly Rate Amount (PhP)
105.47 52.74
168.75 84.38
105.15
62.95 66.09
85.00 1.28
3.37
172.00 172.00
43.93
14.00 182.00
317.87 166.88
1,750.00 77.00
62.95 203.95
85.00 4.25
106.69 106.69
77.13 154.26
59.45 237.80
498.75 70.000 LABOR UNIT COST
70.00
Hourly Rate Amount (PhP)
49.88
49.88 7.000 EQMT UNIT COST 7.00
317.87 104.90
1,750.00 47.25
152.15 152.146 MATRL UNIT COST 152.15
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
B. Equipment
F. Materials
FP-1, Horizontal Split Case Centrifugal Pump with A.C. assy 1,116,923.00
Motor & Controller, UL/FM Approved, 350 GPM, 125psi,
40 HP, 230/3/60
50
113
178
139
181
26
46
77
180.29
855.78
6062
6615
689
Readymix Concrete 3000 psi @ 28 days
UNIT COST ANALYSIS FOR HAULING IN TERRAIN CONDITION FOR ALL AGGREGATES, BOULDER, CEMENT & Other Construction Materials
I. Item/Description : CEMENT
Quantity : 200 bags , 8000 kgs
FORMULA: T = D / R
Where T = Time, Time of Travel (h)
D = Distance, Hauling Distance (km)
R = Rate, Travel Speed (km/h)
1 Units - Dumptruck (10 Cu.m Capacity) days computation (400 bags of cement, 16000 kgs capacity) : TIME-MOTION ANALYSIS
Used Capacity of Dumptruck for Cement 200.00 bags note: Used 50% of total capacity of truck only
because of mountainous terrain condition
Project Name : CONSTRUCTION OF 1 STOREY 5 CLASSROOM SCHOOL BUILDING AT DATU
PANGULUHAN ELEMENTARY SCHOOL, BRGY. LAPAZ, ZAMBOANGA CITY
Distance from Project Site to Patalon river = 47.00 km
2.273333
UNIT COST ANALYSIS FOR HAULING IN TERRAIN CONDITION FOR ALL AGGREGATES, BOULDER, CEMENT & Other Construction Materials
FORMULA: T = D / R
Where T = Time, Time of Travel (h)
D = Distance, Hauling Distance (km)
R = Rate, Travel Speed (km/h)
1.558333
Republic of the Philippines
Department of Public Works & Highways
OFFICE OF THE DISTRICT ENGINEER
Divisoria, Zamboanga City
Project Title: CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADE, INDUSTRIES AND ECONOMIC ZONES - ROAD NETWORK OF THE
PHILIPPINES HALAL HUB - THE ASIAN HALAL CENTER (ZAMBOANGA ECONOMIC ZONE), TALISAYAN, ZAMBOANGA CITY
FROM TO DISTANCE
A. ESTIMATED DISTANCE FROM DISTRICT OFFICE, Z.C TO JOBSITE/PROJECT SITE FOR CEMENT
B. ESTIMATED DISTANCE FROM QUARY SITE(AT STOCKPILE) TO JOBSITE/PROJECT SITE FOR ALL AGGREGATES & BOULDERS
A. SAND, GRAVEL, AGGREGATE SURFACE COARSE & BOULDERS (Considering Quarry site)
Distance 34,950.00
CEMENT 80.000
29.95
COMMON BORROW, AGGREGATE SUB-BASE
LESS: (CONSIDERING FREE HAUL DISTANCE)
EFFECTIVE HAULING DISTANCE(KM)
Project Title: 0 CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADE, INDUSTRIES AND ECONOMIC ZONES - ROAD NETWORK OF THE
PHILIPPINES HALAL HUB - THE ASIAN HALAL CENTER (ZAMBOANGA ECONOMIC ZONE), TALISAYAN, ZAMBOANGA CITY
FORMULA: T = D / R
Where T = Time, Time of Travel (h)
D = Distance, Hauling Distance (km)
R = Rate, Travel Speed (km/h)
1.833333
UNIT COST ANALYSIS FOR HAULING IN TERRAIN CONDITION FOR ALL AGGREGATES, BOULDER, CEMENT & Other Construction Materia
I. Item/Description : REBARS
Terrain Condition
Road Condition
Assume Hauling Distance
Effective Working Hours
FORMULA: T = D / R
Where T = Time, Time of Travel (h)
D = Distance, Hauling Distance (km)
R = Rate, Travel Speed (km/h)
1 Units - Dumptruck (10 Cu.m Capacity) days computation (16000 kgs capacity) : TIME-MOTION ANALYSIS
No of Bags of cement per Dumptruck = 200.00 bags
: Flat to Mountanous
: Paved
: 47 km
: 8 hrs
ce For Delay
0.60 min
101.67 min
0.60 min
80.00 min
0.40 min
65.79 min
0.40 min
252.46 min
25.25 min
1.7
1.00 trip/per
200
11360
6.35
p04
4Q-2022-surveyed
4Q-2022-surveyed
4Q-2022-surveyed
p03
p05
p05
Sanitarium Ref Price (2021)
2022 - 4Q
CIVIL WORKS (ROOF)
Unglazed Tiles m2
4Q-2022-surveyed Glazed Tiles m2
4Q-2022-surveyed Aluminum Glass Window (Sliding) m2
4Q-2022-surveyed Aluminum Glass Window (Awning) m2
4Q-2022-surveyed Aluminum Glass Window (Fixed) m2
4Q-2022-surveyed Mahogany Jamb set/bdft
4Q-2022-surveyed Hollow Flush Door m2
p02 Narra Panel Door m2
p03 Wooden Panel Door (Good Lumber) m2
p03 Hinges (50mm x 101mm) set
p03 Door Locks (Schalage or Equivalent) set
p12 Glass Jalousie Window m2
4.5mm Fiber Cement Board pc
Metal Furring, Single 19mm x 25mm x
p12 pc
0.40mm thk x 5m length
Carrying Channels 12mm x 38mm x 0.80mm
p12 pc
thk x 5m Length
p12 Hanger Bars/Rod pc
p12 Channel clip pc
p12
Wall Angle pc
p12 Rivets pc
p12 1" Metal Screw pc
Maam CHIRSTY From SEROLOGY Tile Grout bag
Mig9 Reference Tile Adhesive (25kg) bag
As per Maam Chirsty (April 28,
2022) 100mm thk CHB (Non-Load Bearing) pc
150mm thk CHB (Non-Load Bearing) pc
Water Proofing Cement (Sahara or Equivalent) bags
Blind rivet pc
12mm x 38mm x 5m x 0.8mm thk Metal Furri pc
4.5mm Fiber Cement Board pc
Metal Furring, Single 19mm x 25mm x
0.40mm thk x 5m length
Carrying Channels 12mm x 38mm x 0.80mm
thk x 5m Length
2022 - 4Q
ORKS (ARCHITECTURAL)
375.00 p12
313.00 p12
5,500.00 p12
4,800.00 p12
4,800.00 p12
40.00 Di ila Reference
934.00 p12
5,200.00 p12
4,500.00 Tanguile Price Ref. Page 12
65.00 p12
1,210.00 p12
550.00 p12
410.00 Pacheck. Daan na record
24.00 p05
30.00 p05
45.00 p07
0.60 Mig9 Reference
200.00 Mig9 Reference
658 Wilcom
173
MADE BY ENGR. EDEILWEISS ZIM S. DELA CRUZ 2022 - 4Q
CIVIL WORKS (PLUMBING)
300.00 p09
BRONZE Faucet pc
191.00 p11
Floor Drain pc
Mig9 Reference - 1002 (4)/ Sanitarim
Bidet Spray pc 600.00
Reference
Facial Mirror sq. ft. 600.00 p11
25mm dia PPR Pipe (4m)
425.92 Officer's Bararacks, Camp Arturo Enrile, M
pc
19mm dia PPR Pipe (4m) pc 251.70 Officer's Bararacks, Camp Arturo Enrile, M
19mm dia - 90 deg PPR Pipe Elbow pc 18.50 Officer's Bararacks, Camp Arturo Enrile, M
19mm dia - Tee Pipe pc 13.00 Officer's Bararacks, Camp Arturo Enrile, M
25mm dia - Check Valve pc 477.00 Officer's Bararacks, Camp Arturo Enrile, M
Gate Valve (25mm)
439.00 p11
pc
Water Meter pc 1,394.00 p11
Urinal set 8,051.00 p09
75mm dia X 3M pvc pipe pc 750.00 p10
75mm dia X 90 deg elbow pc 52.00 p11
Roof Drain pc 191.00 545th Battalion Multi Purpose Covered Co
49.50 p10
75mm dia Coupling pc
27.00 p11
2 inch Plain Elbow 90 Degree pc
PVC Reducer 19mm x 12.7mm pc 6.00 p11
50mm dia X 3M pvc pipe pc 380.00 p10
3" diameter Tee PVC pc 106.00 p10
75mm P Trap pc 182.00 p11
100mm 1/8 Bend or 45 Degree pc 63.00 p11
100mm x 50mm PVC TEE pc 112.00 p11
100mm x 76mm WYE pc 157.00 p11
100mm x 76mm WYE pc 157.00 p11
3/4 Plain Elbow 90 Degree pc 27.00 p11
MADE BY ENGR. EDEILWEISS ZIM S. DELA CRUZ
CIVIL WORKS (PAINTING)
Material
p10 Concrete Neutralizer
p10 Concrete Sealer/Primer
p11 Patching Compound
p11 Semi Gloss Latex (two coat only)
p11 Paint Red Lead (Redoxide)
p11 Paint Thinner
p11 Enamel Paint
p11
p09
p09
p11
p11
p09
p11
ce - 1002 (4)/ Sanitarim
Reference
p11
p11
p11
p09
p10
p11
Multi Purpose Covered Court Nalagutay 10M Reference
p10
p11
p11
p10
p10
p11
p11
p11
p11
p11
p11
EISS ZIM S. DELA CRUZ 2022 - 4Q
(PAINTING)
Unit Price
L 221.00 Mig9 Reference 1032(1)a
gal 759.00 Mig9 Reference 1032(1)a
gal 404.00 Mig9 Reference 1032(1)a
gal 812.00 p08
gal 554.50 p08
gal 416.25 p08
gal 836.00 p08
UNIT PRICE OF ALL AGGREGATES AND PORTLAND CEMENT
Project Name: CONSTRUCTION OF MULTI-PURPOSE BUILDING AT CULIANAN LC, BARANGAY CULIANAN, ZAMBOANGA CITY
Terrain: Flat to Rolling Terrain
Hauling Distance Unit Cost /cu.m/km Hauling Cost/cu.m. Unit Price Unit Price/ cu.m.
Cost of Fine Aggregates : 0.00 X 9.00 = 0.00 + 1,515.00 = 1,515.00
Hauling Distance Unit Cost /bag/km Hauling Cost/bag Unit Price Unit Price/ cu.m.
I. Item/Description : REBARS
Terrain Condition
Road Condition
Assume Hauling Distance
Effective Working Hours
FORMULA:
T=D/R
1 Unit - Dumptruck (10 cu.m Capacity) days computation (400 bags of cement, 16000 kgs capacity) : TIME-MOTION ANALYSIS
Grade 40
68.00 X 0.01
Grade 60
68.00 X 0.01
GATES, BOULDER, CEMENT & Other Construction Materials
: Flat to Mountanous
: Paved
: 68 km
: 8 hrs
27.46 min
40.10 min
41.07 min
58.50 min
60.00 min Note: Unloading all of materials, assuming it will take 6 mins
58.50 min
23.47 min
18.23 min
17.48 min
330.33 min
33.03 min
1.3
1.00 trip per day
11,360.00
PAVED
UNPAVED
300
49.5
ng it will take 6 mins
480
UNIT COST ANALYSIS FOR HAULING IN TERRAIN CONDITION FOR ALL AGGREGATES, BOULDER, CEMENT & Other Construction Materials
I. Item/Description : CEMENT
Terrain Condition
Road Condition
Assume Hauling Distance
Effective Working Hours
FORMULA:
T=D/R
1 Unit - Dumptruck (10 cu.m Capacity) days computation (400 bags of cement, 16000 kgs capacity) : TIME-MOTION ANALYSIS
68.00 X 0.56
GATES, BOULDER, CEMENT & Other Construction Materials
: Flat to Mountanous
: Paved
: 68 km
: 8 hrs
27.46 min
40.10 min
41.07 min
58.50 min
60.00 min Note: Unloading all of materials, assuming it will take 6 mins
58.50 min
23.47 min
18.23 min
17.48 min
330.33 min
33.03 min
1.3
1.00 trip per day
11,360.00
PAVED
UNPAVED
300
49.5
ng it will take 6 mins
480