Unit 2
Unit 2
2 . INTRODUCTION
Uncofitrolled storm water and surface runoff can cause significant environmental
problems. Flooding is one obvious example of such a problem that is accompanied by
loss of property, and sometimes human and animal life too. Moreover, water pollution
problems c p be severe, such as : soil erosion and consequent sedimentat'ton in tanks, and
natuml drainages. It is well recognised that stom runoff is a major non-point source of
water pollutants : fertilizers, pesticides, oil, organics, and other substances.
Land development and urbanisation both increase the frequency and severity of these
problems. It is, therefore, necessary to provide storm drains for the removal of excess
water from streets, parking lots, parks and gardens. In fact, storm water is increasingly
being viewed as a natural resource for use in a manner beneficial to the community.
Therefore, its generation, estimation, and appropriate disposal constitute a complete
waste water management. Sometimes, in a combined sewerage system both storm water
and municipal out flow are carried by a single net work of the sewerage system.
Objectives
This unit aims at providing the following basic information to the student regarding :
estimation of storm runoff,
effects of land development,
basics of storm water detention, and
management of flood plains.
developed for different regions (i.e., they were region specific) that were based on actual -
observed storms and related floods.
-
In recent years, a method, known as rational method, was developed t o estimate peak
drainage discharge. However, the results given by this method in respect of areas greater
than 100 to 500 ha or so are generally erroneous. This method is suited for smaller area
(less than 50 ha or so) - for larger arqas empirical formulae seem to be suitable. Most
modern method for urban storm drainage comprises what is known as digital computer
simulation.
It may be reiterated that Q represents only the maximum discharge caused by a particular
- it can be visualised as the peak of the hydrograph generated by the storm
* - -
Storm Water Drainage
7 Maximum Q = C x ix A
s stormwater
c flow rate,
h Q
Time
1 2
I
I
I
0.85 - 0.90 1
3 Stone, brick, wood-brick pavement 0.75 - 0.85
with cemented joints
I f
4 1 Same as above with uncernented
5 1 Water bond macadam roads -
0.25 0.60
1 6 1 Gravel roads and walks 1 0.15 - 0.30 I
7 Unpaved streets and vacant lands 0.10 - 0.30
8 Parks, lawns, gardens, meadows, etc. 0.05 - 0.25
9 Wooden lands 0.01 - 0.20
where, the subscripts refer to respective sub-basin types, and A obviously is the
total basin area.
T i e of Concentration (T,)
Total time of concentration ean be visualised as composed of two parts : overland
flow time (also known as inlet time, or time of equilibrium), and channel flow time
(or gutter flow time), as shown in Figure (2.2).
4 I Discharge
where, Tiis in hours; L, the length of overland flow, in kilometers; and H, the total
fall of level from the britical point to the mouth of the drain, in metres. L and H can
be obtained fromthe wntour plan (survey plan) of the area. Moreover, several
charts 1 nomographs are available that correlate overland flow time with ground
slope and runoff coefficient (or land use). One such chart is presented in
Figure 2.3. Here, the chart is entered on the left with the known overland trav&
distance, along a horizontal: then a vertical path is traced to the known values of-
slope and runoff coefficient curves, respectively; and, finally, the overland travel
time is read from the vertical axis on the right side of the chart.
Storm Water Drainage
-0 10 20 30 40 50 60 70
. .
Duration in minutes -------c
l ~ I I * 3 ~ I I I l ~ ~ ~ ~ ~ ~ ..as ~I I I
~ I j
~ ~ ~
o 2 L 6 a 10 R . U 16 18 20 2 2 24 26 28 30 50 -I62 n
DURATION I N HOURSL
t = -
a
T+b . . . (2.5)
where, i is in cm 1 h, T (given duration of the storm) is in minutes, and a and b
are constants depending on T itself. Using T, in minutes for T, the value of i as
its critical value can be computed.
Besides this generalised equation, certain other empirical equations are .
available for the determination of rainfall intensity for various regions. It is to
be stressed that the use of these equations is best avoide&however, when there
is absolutely no rainfall record atailable they may be used for very ordinary
works.
- - - -
1 For the design of drains catering to large catchments (greater than 400 to 500 ha), some
empirical formulae are available for ready use. Some of them are based on local
conditions, and are used only when specific requirements are fulfilled. However, some
I
formulae, based on experimental studies over wide areas, are adopted for many localities.
Y (i) Burkli - Ziegler Formula
This is a very old empirical formula in use for the determination of peak rate of runoff.
It was developed by a Swiss engineer for particular local conditions; however, it was
soon followed in the entire USA. The formula is written as :
where, M = catchment area in km2(in Eq. 2.6, the value of A is expressed in ha), and
C = a constant depending upon all those factors that influence the amount of
runoff as discussed earlier.
- ~ i i u r 2.6
e :Values of C, in Dicken's Formula for Various Zones of India
..It is imperative that the value of C should be appropriately ascertained for a given
catchment. It depends on the characteristics of the catchment, asbell as the intensity
Wastewater Collection of T::;I::c~' - its nicrsge value is generally taken as 11.5, and has to be increased for
and Chatacteristics hilly terrains and decreased for plainer areas. For the same basin its value will be
@ higher for higher rainfall intensity. Figure 2.6 presents the values of C as applied to
different zones of India.
(iii) Ryve's Formula
This formula is similar to Dicken's model, except for the values of C and index M. It it, -
generally applicable to South Indian basins, and is written as follows :
--Location
- of Catchment Value
--of C1-
Areas nearly 24 km from the coaqr 6.8
Areas within 16-24 km from the coast 8.8
Limited areas near the hills 10.1
There are other empirical models also available for use, such as, due to Inglis, Nawab
Jung Bahadur, etc. I
2.2.3 Soil Conservation Service (SCS) Method
The Soil Conservation Service of the U.S. Department of Agriculture has developed
methods for estimating the volume and rate of storm runoff that are applicable to the
developing suburban areas of U.S. This method places emphasis on the correlation
between the type of soil cover in the basin and the runoff. Herein an outline of the SCS
Graphical Method, which is relevant to relatively small watersheds, is presented (using
American units for the concerned quantities) to bring out the basic approach adopted in
this procedure.
1
Four hydrologic soil groups are defined for use in this method, such as :
It is obvious that soil survey maps and measured infiltration rates are needed to identify
the appropriate soil group in a given area. It is to be understood that the volume and rate
of runoff also depend on the type of land-use in the watershed. Therefore, in the SCS
-
.'.
Example 2.2
In an aerial photographic survey of a 15.5-ha catchment following, area
classification was determined :
Description
(i) flat densely wooded = 6.6ha ; C = 0.01
(ii) lawn = 6.2ha ; C = 0.19
(ii) paved roadway and parking area = 2.7 ha ; C = 0.93
Complete the composite runoff coefficient (K) for the total area of the catchment.
Solution
1
3 K = - [ c ~ +AC2A2 ~ +c~A~]
A
Here, A = 6.6 + 6.2 + 2.7 = 15.50 ha (as also given as a data item)
Hence, K = ---
15.50
[0.01 x 6.6 + 0.19 x 6.2 + 0.93 x 2.71
Example 2.3
A 0.27-km2 basin has its composite runoff coefficient, C = 0.25. It has been
observed that the overland flow distance to the point of commencement of the
main stream, that drains the catchment, is 175 m, and its slope is 7.5%. This stream
is 650 m long, dropping 32 m in elevation by the time it leaves the watershed.
Estimate the peak rate of runoff for 5 year storm and also for 100-year storm,
given the typical rainfall intensity-duration-frequency curves (Figure 2.9) for the
region.
z -
s
E 5
250 (10)
225 (9)
f
& 200 (8)
175 (7)
c
2 150 (6)
E
2
z 125 (5)
lCQ(4)
C
- 75(3)
50 (2)
25(1) \ [ I I W L I I I I I I I I I I I , I I I I I [ l l
0 ~ l l ~ l T ~ l l ~ ~ l l ~ l ~ l l ~ l i l l ~ ~ ~
0 10 20 30 40 50 60 70 80 90 100110120
Ramfall duration, mln
Figure 2.9 :Typical Rainfall Intensity-Duration-Frequency Curves for the Given Region
Take the value of n of the stream as 0.035, and its hydraulic radius (when running
full) as 0.087 m for both the events for the sake of first approximation. (It may be
pointed out that nornographs are also available relating drop in a channel bed,
length of channel, and channel flow time - these can be used for a rough
approximation of channel flow time.)
Solution rd
1
?!
Peak runoff discharge before land
development
c
.-P
0
Time -
Figure 210 :Land Development Changes the Hydrograph Characteristics Adversely
Moreover, urban runoff generally carries lawn fertilizers, oil, organics, etc. into the main
drainage as well. Chances of occurring of severe floods, are in fact long-run effects,
while on a short-term basis soil erosion, and stream siltation result during land
development and construction period.
Modern land planning practices are designed to mitigate the long-term effects of
'
urbanisation, such as : temporary artificial storage of storm water, growing grass on open
lands to retard the flow velocity, etc.
Example 2.4
' The 0.27 lun2 catchment as described in Example 2.3 is proposed to bl developed
as residential and business locality. The resulting composite runoff coefficient C is
computed to be 0.60. Part of the flow is to be carried through a pipeline; and the
new channel flow time, after the above mentioned development, is projected to be
only 6.0 minutes.
For both the 5-year and the 100-year storms, estimate the expected peak flow rates
under the developed conditions, using the Rational Method. Compare the increases
in peak discharges with those occurring during the predevelopment conditions.
Solution
Entering Figure 2.3 with overland flow distance = 175 m, slope = 7596, and
C = 0.60, we read the corresponding overland travel time = 13.5 minutes.
.: . T, = 13.5 +6= 19.5 minutes for the developed basin.
Considering Figure 2.6, we read rainfall intensity values as under :
For 5-year storm, i = 86mrnIh
For 100-year storm. i = 1.8lmmlh
Applying the Rational Formula, we have :
5-year storm
Q = 0.6 x 0.086 (m / h) x 27000 m2
Thus the land development will increase the peak flow by a factor of
29322 / 9720 = 3.0, for 100-year storm.
Storm Water Drainage
2.4 STORM SEWER SYSTEMS
! Storm drainage system is put in place to convey surface runoff to the designated point of
storage, or disposal. It may be pointed out that sometimes storm sewer system is
1
combined with sewage sewer system - same sewer catering to the carriage of both these
types of waste water. In separate sewer system, obviously, sanitary and industrial waste
*
waters are excluded. There are some basic differences between storm and sanitary sewers
in so far as their designs are concerned.
Storm drainage system is allowed to periodically surcharge and overflow causing local
flooding, with a predictable recurrence interval. It is the result of having selected a storm
return period for estimating the magnitude of corresponding peak flow, and then basing
the size of the pipeline on this data. Obviously, this limits the capacity of the system, and
this has to be accepted with reference to economy; and. one has to understand that the
chance of sewers overflowing can never be completely eliminated. Sanitary sewers, on
the other hand, are designed to carry a peak flow for a given projected population; and,
thus, without overflowing. However, it may be mentioned that a sanitary sewer does
overflow usually due to excessive inflow of ground or surface water because of poor
construction or maintenance.
Storm sewers are usually having a much larger diameter than the separate sanitary sewers
for the same area that they serve - it is so because storm sewers have to be sized to carry
larger peak flows, though these carry no flow during dry weather season. Further, storm
sewers are placed at shallow depths to minimise excavation : whereas, sanitary sewers are
placed in relatively deeper trenches to accommodate service connection.
w , Str
Wastewater Collection appropriate location and spacing, inlets should be provided with sufficient capacity
aqd Chtacteristics to entrap and direct surface water as fast as possible with a view to avoid backups
on the ground surface after taking into account factors like, clogging, nuisance to
traffic, hydraulic capacity, and desired safety. It is within this context that flooding
across street intersections is avoided (Figure 2.11).
There are three basic types of inlets that are in ose, such as, kerb inlets, gutter (or 1
grate) inlets, and combined inlets (Figure 2.12). i
Vert~cal
Curb curb openlng Curb -
'f - I
I
d f fl
Figure 2.13 gives a cross-sectional view of an inlet basin to receive water from the inlet
and direct it to the storm drain. If the drain invert happens to be above the bottom of the
inlet basin (a position shown with the dashed lines), than this inlet basin is termed catch
basin. In fact, the catch basin is meant to trap the grit, sand, and leaves etc. that may be
washed into it. Sometimes catch basins are discouraged to be incorporated as a feature of
storm water collection design due to requirement for periodic cleaning, odour menace,
and mosquito problem - and, therefore, only inlet basins are adopted as the design feature
of the collection system at the inlet point. Approprigte design, and adopting self-cleansing
drain slopes m u l d in that case maintain the collection system free from blockage
problems. '
Cyrb Inlet
.Inlet basin
Stormdram
I I
I I
I I Debris .
II I I
I I
I :; ....:,,::..;.:. . . .. , .. , .. , . k ( C a t c h basin)
I '. I
-
Lined Drains
I Bumt-clay-tile lined
I 1.8
3. Cement concrete lined 2 to 2.5
Unlined Drains
/ 1. I Ordinary soils I 0.6 to 0;9
I
11 1( 3.
Very light, loose sand to an average
sandy soil
Black cotton soil, sandy loam, etc.
I1 0.3 to 0.6
0.6 to 0.9
I
1 1 Murram, hard soil, etc.
Rock and v e
Pipe'locations, diameters and slopes must be indicated on the plan of the area; and
the invert levels are determined in much the same fashion as for sanitary sewers.
An outfall structure by way of dissipating the excessive energy of flow at that
place (drain falling into another major drain, etc.) is also required. Moreover, a
regulator may sometimes have to be provided at the outfall point (say, a river) to
avoid back flow into the drain as could happen at high stages of flow of the
receiving water body.
Example 2.5
There is a proposed storm drainage system of an area whose total catchment has
been divided into several sub-catchments. Each sub-catchment has been suitably
provided with an inlet at its end point. The proposed drain connecting inlet 1 with
inlet 2 is designed as reach 1, and so on. Following data about first three reaches is
given :
(a) Sub-catchment I
Area, Al = 1.1 ha
Runoff coefficient, C1= 0.4 1
Inlet time = 4.9 minutes
(b) (i) Sub-catchment 2
Length = 178 m
Bed slope, s = 0.0019
C:o!lrction
iL.~:;!c~\ater
. >
! { o ; ~ : / t.j ( c ( ~ r ~ n : , ~ y l ~ ;:!;LC;
;:
,.
5 tc ; I L ! P ! 4,)
(L!)
itnil Chutacteristics .
Bed slope, s = 0.0016
Determine the diameters of pipe drains for the respective reaches ( ~ n n i n full),
g
using Rational Method for computing the design flows. Assume Manning's n as
0.013 for all the drains, and consider a 10-year storm for determining design
rainfalls.
Solution
Reach 1
-
*
Taking the inlet time (4.9 minutes), for area A,, as the time of concencation, we
read from Figure 2.9, i 153 mm / h for the 10-year storm. Using Rational
Formula, we have :
Q = 0.41 x 0.153 x 11OOO
= 690m3/h
= 0.i92rn3/s
Using Manning's equation, we write :
0.192 = ,.;,,
-. :d2 (!TI3
= 47.0 cm
Hence, velocity of flow in the pipe,
Reach 2
This reach connects inlet 2 and inlet 3. Before proceeding further, we first
compute the composite mnoff coefficient for areas A1 and A2 as follows :
and,
Reach 3
Total tributary area to inlet 3
= 1.1 + 1.4 + 2.2
178 - 175s
Now, the time of flow in reach 2 = -
1.02
= 2.9 minutes
Thus, the total flow time to inlet 3 (= inlet time for A1 + travel time for reach 1
+ travel time for reach 2)
= 9.6 minutes
This time is less than the individual inlet time for A3 (i.e., 11.0. minutes);
therefore the 11-minute inlet time becomes the governing factor. Thus, adopting
11.0 minutes as the time of concentration (i.e., storm duration) for the design of
reach 3, We enter Figure 2.9 with T, = 11.OO minutes, and read i = 136 mm / h
(i.e., 0.136 m / h) for the 10-year storm. From Rational Formula, we get :
Note :(1) The diameters computed for various reaches can respectively, be
rounded off to the nearest (higher) available standard sizes.
(2) The velocities computed for various reaches lie within the permissible
limits; hence, these values are acceptible.
Exat,jpil: 2.6
Design a trapezoidal-sectioned (unlined, with n = 0.025) storm water outfan
channel, for a basin whose area is 125 ha, within following parameters :
(i) Co-efficient of runoff = 0.53
(ii) Inlet time = 17.5 minutes
(iii) Flow time in the reaches upstream of the proposed channel = 27 minutes
(iv) Proposed water surface slope of the channel = 1 in 3500
(v) Maximum permissible flow velocity in the channel = 1.0 m I s
(vi) Design rainfall frequency = 5 years
(vii) Relevant data from depth duration curves that are available with reference to the
area under consideration are given as follows :
a = (hx o s i j x 7.03 x in
= 12.94cumec
Now, adopting a depth of flow Cy) as 1.5 m, we have from Eq. (2.2) :,
1.5 = 0.5
= (W +1.2~)~
=(9+1.2x1.5)1.5 .
= 16.25 m2
Wetted perimeter, P
= W + 2 m x 1 . 5
= 9 + 3 m T
= 13.68m
:. The hydraulic radius, R
Thus, we need an increased area fo flow; and, hence adopting a bed width of
9.5 m, we recalculate the necessary quantities as under :
Hence,
i
I = 12.94 cumec (which is satisfactory)
Check for Permissible Maximum Velocity
= 17.74 cumec
Hence, adopting only 9.00 m as the bottom width of the section, we have : . .
= 18.1 curnec
This value is about satisfactory, being very close to 17.74 m3 / s - :Lit: ;.xpc:~-,: Storm Wstcr Drui~:.qc
peak flow value.
Check for Maximum Velocity
17 74
Maximum average velocity generated = -- = 1.1 m 1 s
16.2
It is less than the permissible value (= 1.5 m / s) for a stone pitched section.
The final important parameters that are to be adopted are summarised as
follows :
Bed width = 9.0 m
Side slopes= 1 : 1.2
Bed slope = 1 in 2500
Adopt the appropriate value for the free board to amve at the working section
of the drain.
-
.
.-
a
,
-. -----.--.- . ~ .- . . -
2 5. STORM
----
WATER DETENTION
"
'I ,ht- concept of ionstructing smaller reservoid to detain, for sometime, water coming
: un streets, parking lots, etc., and then releasing under controlled conditions as required
(. saining growing acceptance. These devices are best suited to manage h e runoff from
~rrlativelyshort and intense local storms, that would otherwise cause frequent flooding
,Imid severe erosion, with the consequent effects. Some particular becefits ot storm water
rtorage through engineered detention can be listed as under :
(i) Peak runoff rates are reduced. -
(ii) Both the frequency and severity of flooding are attenuated.
Wastewater Collection (iii) Surface water quality is maintained to a satisfactory standard.
and Chatacteristics
(iv) Sedimentation in streams gets reduced due to the reduction of soil'erosion.
(v) While water stands detained, the chance's of recharge of acquifer increase;
however, much depends on the permeability of the soil.
However, the on-site storm water detention basins need to be looked after for appropriate
-maintenance. They are subject to sedimentation and deposition of debris being the first
stop that is applied on the surface flow; and their outlet structures, therefore, generally
get easily clogged. Another problem relates to weed control, and breeding of mosquitoes
in stagnant waters; moreover, the safety of children of the locality cannot be left
unattended. The beneficiaries must be motivated to share the responsibility of
maintenance; or any appropriate agency, like area municipality, can attend to this aspect.
Figure 2.15 depicts one of 'the types of a detention basin, where the outlet structure acts as
a bottleneck that is restraining the flow rate out of the pond.
A storage basin may retain water for all the time (i.e., with no outlets provided) forming a
permanent pond, and can also be harnessed to provide aesthetic and recreational
advantages to the community. Such a storage is known as retention basin. These is a third
type of storage structure, namely, recharge basin that allows the stored storm water to
percolate into the underlying aquifer, and thus recharging and replenishing the ground
water reserves in addition to the primary function of controlling the storm runoff. It is,
however, understood that the underlying soil must be permeable to an appropriate degree
for relatively rapid infiltration. It is helpful if the seasonal high water table is at least
0.5 m below the bottom of the tank.
On-site
storm sewer
/ ~unoff' Too of embankment
I ( b ~ a s i filling
n (AS positive)
Time --,
Figure 2.17 :Typical Inflow and Outflow Hydrographs for a Storm Water Dctentioq Basin
where, A t is an appropriately small interval of time (say, 5 or 10 minutes), I is the
average rate of inflow during A t, 0 is the average rate of outflow during At, and AS is
the change in stoi'age volume during At. We know that the solution of Eq. 2.22 (through
.
+ wivr Collection any flood routing procedure) give us the basin outflow hydrograph, whose time base is
..i Chetacteristics more, and peak flow rate is much less than that of the inflow hydrograph
(Figure 2.17) - the intended response, achieved by the basin and outlet structure. At first,
the rate of inflow exceeds the rate of outflow; and, thus, water keeps accumulating in the
basin (i.e., AS is positive). After the inflowing storm water subsides, the basin begins to
empty out gradually through the outlet (i.e., AS is now negative).
Usual flood routing procedures involve a lot of computation; therefore, for tackling the
present problsm, a simpler, but approximate, method is recommended which is quite
appropriate to give a preliminary estimate of the necessary storage volume or peak
outflow rate of the detention basin. However, a rigorous procedure is called for later on to
finalise the design of the whole structure. In the approximate method, referred to above,
following two factors have to be defined with respect to the effectiveness of detention
basin :
Basin storage volume
Storage factor (SF) = --
Total rainfall volume
Peak outflow rate
Flow factor (FF) = ----
Peak inflow rate
The relaiionship between S F and FF can be approximated by a straight line (Refer -
Pagan, A., "Flow Factor Line Used in Storage Calculations", ASCE, Journal of pl
Irrigation and Drainage, March, 1977) as shown in Figure 2.18 whose equation is given
below :
1 .o
0.2
0
0.2 0.4 0.6 0.8 1.0
Storage factor
-
would be equal to the inflow rate, and there being no flow attenuation, and
(ii) SF = 1, and so FF d, if the pond is big enough to store all the total surface
flow generated by the storm - i.e., there would be no outflow at all.
Further, computational simplificaions (and, therefore, approximations) can be introduced
by assuming, for all practical purposes, that the inflow hydrograph is triangular in shape
(Figure 2.19), with a view to estimating quickly the total rainfall volume. Its height
represents the peak inflow, (Q,& that can be calculated by Rational Method. The total
time for its rising limb (from start to the peak-flow point) is taken as the time of
concentration
Figure 2.19 :A Triangular Hydrograph as a Tool for a
Reasonable Estimation of Total Reinfall Volume
(T,) of the catchment area, while the time for the receding limb to meet the time base is .
conservatively taken as 2 T, . The area of the triangle
gives the total rainfall volume that has been received
Example 2.8 .
A given storm produces a peak runoff of 4.5 m3 I s over a drainage area whose
time of concentration (T,) is 31 minutes. If a detention basin with 9000 m3
capacity is made availab:e on site, what would be the peak outflow from the pond
for the given storm? Use triangular hydrograph method for finding the solution.
Solution
T, = 31 x 60 = 1860s -i
:. Total volume rainfall = 1.5 x 1860 x 5
9000
Now, SF = -= 0.65
13950
From Figure 2.18 or from Eq.2.23, we have :
FF = 1.0 - 0.65 = 0.35
.-. Peak outflow rate = 0.35 x 4.5
= 1.58m3 I s
Thus, it is expected that the 9000 - m3 storage pond will reduce the peak runoff
from 4.5 m3 / s to about 1.58 (or, say, 1.6) m3 I s.
Example 2.9
A catchment area (0.23 km2) is to be developed for residential purposes; and the
concerned planning board has laid down the provison that an on-site storm water
storage pond be constructed so that the peak runoff (based on 5-year storm) after
development (which otherwise is estimated to be 15000 m3/h) is not greater than
the peak flow that would build up prior to the development of the area (5000 m3/h).
Assume that the detention pond will have an average water depth of 2.2 m while
being filled to capacity.
Determine the fraction of the area of the total site that will have to be used for the
detention basin, taking the time of concentration after development to be
16 minutes.
Solution
As per requirement,we set the predevelopment discharge of 5000 m3/h equal to the
- basin (pond) outflow rate, and the post development discharge of 15000 m3/h equal
to theinflow rate. Thus, we have :
Wmkwater Collection
and Chatacteristics
7
91 > , t ; ~ r ncauses :i peak runoff of 8 m- i s in a drainage basin thathas a time of ,
coiici-nrration of 20 minutes. A detention basin with 12000 m3 of storage volume is
!:uilt on site. Estimatc the peak outflow rate from the basin for thrs storm, using the
. . ...
~ ~ r n p l ~storage
t ~ e d factor method.
I:$, iinate the ?torage volume necclctl in a detention basln to reduce a peak inflow
r 0 n 3 i s to 2 m3 / s, uhen ahc totdl r a ~ l ~ f avolume
ll is 15000 m 3 .
(i) floodway - it carries the major portion of the flood at high velocities,
-
(ii) flood fringe it is the area that is covered with shallower, and slowly flowing
water.
Floods cause damage to life and property situated in the floodway. And, also, floods
cause considerable pollution problems, particularly contamination of drinking water
supplies. Better land use procedures based on environmental planning, and proper flood
plain management practices go a long way in limiting flood damage to the minimum,
Urban development in a flood plain (entailing land filling as well for this purpose) causes
constriction in the flow width of the channel, and thus gives rise to increased elevations
of flood waters. The basic objective of forcing appropriate land use in flood plains is to
achieve reduction of the risk of flood damage in future. Therefore, it is in the interest of
the community to enforce regulations to avoid the following constructions in the
floodway :
(i) New buildings,
(ii) Sanitary landfills,
(iii) On-site sewage disposal structures.
To help monitor the flood plain management it is necessary to delineate the plain on a
topographic map, as a flood hazard area.
Of course, flood protection measures, like reservoirs, levees, and channelisation
(increasing the existing carrying capacity of the stream) are also adopted to afford
protection against floods caused by such storms as have equal or less than the design
recurrence interval - such structures induce additional'urban development in the flood
plain because of the mitigation of ~stentialthreat of flood damage.
2.7 SUMMARY
Study of the subject of storm water drainage begins with the consideration of methods to
estimate the peak surface runoff due to the storm of a given frequency that occurs over a
given catchment. The estimation is mostly done by Rational Method, use of empirical
formula'e (relevant for particular catchments only), or special procedures applicable to
specific areas (such as, Soil Conservation Service Method being used in USA) that may
be developed for ease in computations.
The need for estimation of runoff basically arises once an area is proposed to be
developed with a view to urbanisation, and the normal peak flow is expected to increase
due to increase in the coefficient of runoff of the area because of loss of natural seepage
through paved patches of land.
Storm sewer systems, for carrying the flow comprises suitable inlets in the streets, minor
and trunk sewer pipes. The design of the system involves fixing the inlet locations, slope
of sewer lines, and working out their diameters. Sewers and drains are designed with all
the considerations and formulae applicable for the design of open channels.
Use of storm water detention basins allows a temporary storage of water thaV41s,later on,
released; and it later on helps reduce the peak flow, and so lesser diameter of sewer lines
can be adopted to effect economy in the capital cost. Such basins can be designed to cater
to many storms falling in the desired range of frequency of occurrence. Hydraulic design
of these structures involves the use of flood routing procedures; and a simplified
procedure, namely, simplij?ed storage factor method comes handy in this context.