2 .Laporan Reschedule Cv. Barona Usaha
2 .Laporan Reschedule Cv. Barona Usaha
2 .Laporan Reschedule Cv. Barona Usaha
DURASI
RE - SCHEDULE
NO. URAIAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT MINGGU KET
SEPTEMBER 2020 OKTOBER 2020 NOPEMBER 2020 DESEMBER 2020 JANUARI 2021 FEBRUARI 2021 MARET 2021 APRIL 2021 MEI 2021
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
I. PEKERJAAN PERSIAPAN
100
1 Mobilisasi dan Demobilisasi (Direksi Keet/sewa, 1.00 Ls 7,500,000.00 7,500,000.00 0.28 35.00 0.03 0.03 0.03 0.03 0.03 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3 Administrasi (Dok. Kontrak, Shop Drawing dan As-built 1.00 Ls 5,000,000.00 5,000,000.00 0.19 35.00 0.02 0.02 0.02 0.02 0.02 0.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
- Pipa HDPE SDR 17 (PN 10) ND. 90 mm 3,100.00 M' 75,000.00 232,500,000.00 8.83 6.00 1.71 - 3.13 0.85 - - - - - - - - - -
2 Pengadaan Accessories
- Tee Steel dia. 250mm x 100mm 2.00 Bh 1,750,000.00 3,500,000.00 0.13 1.00 - - - - - - - - - - - - -
90
- Gate Valve Cl dia. 250mm 1.00 Bh 5,300,000.00 5,300,000.00 0.20 1.00 - - - - - - - - - - - - -
- Butt Fusion Reduser Tee ND 110mm x 90mm 16.00 Bh 500,000.00 8,000,000.00 0.30 1.00 - - - - - - - - - - - - -
- Butt Fusion Cup dia 110 mm 2.00 Bh 300,000.00 600,000.00 0.02 1.00 - - - - - - - - - - - - -
- Baut Lengkap Ring dan Mur Untuk Flange 200.00 Bh 10,000.00 2,000,000.00 0.08 2.00 - - - - - - - - - - - - - 80
- Paking/Gasket untuk Flange 2.00 M2 325,000.00 650,000.00 0.02 2.00 - - - - - - - - - - - - -
III. PEKERJAAN PEMASANGAN PIPA, ACESSORIES TERMASUK FITTING VALVE DAN PENGETESAN
1 Pekerjaan Tanah
- Galian Tanah Keras 3,874.93 M3 102,520.00 397,257,823.60 15.08 15.00 5.25 4.67 1.17 0.58 0.41 0.43 0.43 0.43 0.43 - - - - - -
- Mengurug Kembali Galian 3,754.00 M3 33,916.00 127,320,664.00 4.83 15.00 1.68 1.50 0.37 0.19 0.13 0.14 0.14 0.14 0.14 - - - - - -
- Urugan Tanah Bekas Galian Termasuk Perataan dan 120.93 M3 56,650.00 6,850,684.50 0.26 15.00 0.09 0.08 0.02 0.01 0.01 0.01 0.01 0.01 0.01 - - - - - -
Pemadatan
JADWAL
2 Pemasangan Pipa Termasuk Fitting, accessories dan Valve
PELAKSANAAN
KONTRAK AWAL
- Pipa HDPE SDR 17 (PN 10) ND. 110 mm 10,656.00 M' 6,490.00 69,157,440.00 2.63 9.00 1.11 0.99 0.25 0.17 0.09 - - - - - - - - - -
- Pipa HDPE SDR 17 (PN 10) ND. 90 mm 3,100.00 M' 6,030.00 18,693,000.00 0.71 6.00 - - - 0.11 0.11 0.11 0.11 - - - - - -
Pemasangan Accessories
- Accessories dia. 250 mm 4.00 Bh 52,937.00 211,748.00 0.01 2.00 - - - - - - - - - - - - -
70
- Penyambungan Pipa HDPE SDR 17 (PN 10) ND. 90 mm 31.00 Titik 37,876.00 1,174,156.00 0.04 6.00 - - - 0.01 0.01 0.01 0.01 - - - - - -
60
- Penyambungan AcessoriesPipa HDPE SDR 17 (PN 10) ND. 110 mm 44.00 Titik 50,001.00 2,200,044.00 0.08 9.00 - 0.01 0.01 - - - - - - - - - -
- Penyambungan Acessories Pipa HDPE SDR 17 (PN 10) ND. 90 mm 64.00 Titik 37,876.00 2,424,064.00 0.09 6.00 - - - 0.01 0.00 0.01 0.00 - - - - - -
60
DURASI
RE - SCHEDULE
NO. URAIAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT MINGGU KET
SEPTEMBER 2020 OKTOBER 2020 NOPEMBER 2020 DESEMBER 2020 JANUARI 2021 FEBRUARI 2021 MARET 2021 APRIL 2021 MEI 2021
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
4 Pengetesan Pipa
- Pipa HDPE SDR 17 (PN 10) ND. 110 mm 10,656.00 M' 2,125.00 22,644,000.00 0.86 1.00 REALISASI - - - - - - - - - - - - -
100
- Pipa HDPE SDR 17 (PN 10) ND. 90 mm 3,100.00 M' 1,905.00 5,905,500.00 0.22 1.00 PELAKSANAAN - - - - - - - - - - - - -
DILAPANGAN
5 Interkoneksi dengan Pipa Lama/Eksisting dan Boring Pipa
- Galian tanah untuk koneksi 39.55 M3 102,520.00 4,054,666.00 0.15 2.00 - - - - - - - - - - - - -
- Interkoneksi dengan Pipa Lama dia. 150 mm 15.00 Titik 423,720.00 6,355,800.00 0.24 2.00 - - - - - - - - - - - - -
dan Accessories L = 1m - 5m
- Loose Flange dia. 300 mm 16.00 Bh 600,000.00 9,600,000.00 0.36 8.00 0.36 - - - - - - - - - - - - -
- Pemasangan Pipa Steel dia. 300 mm 48.00 M 185,168.00 8,888,064.00 0.34 8.00 - - - - - 0.34 - - - - - - - 80
- Pengelasan Flange dia. 300 mm 16.00 Bh 792,950.00 12,687,200.00 0.48 8.00 - - - - 0.48 - - - - - - - -
- Pemasangan Asseccories dia. 300 mm 1.00 Bh 70,785.00 70,785.00 0.00 8.00 - - - - - 0.00 - - - - - - -
- Bongkar batu kali (tebal >50 cm) 12.00 M3 66,661.00 799,932.00 0.03 8.00 - - - - - 0.03 - - - - - - -
3 Penyambungan Daya PLN 66 KVA BP material dan pemasangan 1.00 Pkt 73,210,000.00 73,210,000.00 2.78 4.00 2.50 - - - 0.14 - - - - - - - - -
30
4 Rekondisi Pipa Bocor
- Giboul Join dia. 250 mm 10.00 Bh 2,000,000.00 20,000,000.00 0.76 6.00 - - - - - - - - - - - - -
- Pipa HDPE SDR 17 (PN 10) ND. 250 mm 12.00 M 700,000.00 8,400,000.00 0.32 6.00 - - - - - - - - - - - - -
- Pipa HDPE SDR 17 (PN 10) ND. 200 mm 24.00 M 450,000.00 10,800,000.00 0.41 6.00 - - - - - - - - - - - - -
- Pemasangan Pipa HDPE SDR 17 (PN 10) ND. 250 mm 12.00 M 21,598.00 259,176.00 0.01 6.00 - - - - - - - - - - - - -
- Pemasangan Pipa HDPE SDR 17 (PN 10) ND. 200 mm 24.00 M 16,527.00 396,648.00 0.02 6.00 - - - - - - - - - - - - -
6 Pembuatan Wash Out dia. 75 mm pada Jaringan Pipa dia. 100 mm (1 Unit)
Pengadaan Pipa dan Accessories
- Gate Valve dia. 100 mm 1.00 Bh 2,700,000.00 2,700,000.00 0.10 1.00 - - - - - - - - - - - - -
60
- Gate Valve dia. 75 mm 1.00 Bh 1,750,000.00 1,750,000.00 0.07 1.00 - - - - - - - - - - - - -
- Butt Fusion Elbouw ND. 90 mm x 90º 1.00 Bh 750,000.00 750,000.00 0.03 1.00 - - - - - - - - - - - - -
- Pipa HDPE SDR 17 (PN 10) ND. 90 mm 6.00 M 80,000.00 480,000.00 0.02 1.00 - - - - - - - - - - - - -
- Pipa PVC dia. 150 mm Untuk Selubung Street Box 2.00 Bh 150,000.00 300,000.00 0.01 1.00 - - - - - - - - - - - - -
50
10
DURASI
RE - SCHEDULE
NO. URAIAN VOLUME HARGA SATUAN JUMLAH HARGA BOBOT MINGGU KET
SEPTEMBER 2020 OKTOBER 2020 NOPEMBER 2020 DESEMBER 2020 JANUARI 2021 FEBRUARI 2021 MARET 2021 APRIL 2021 MEI 2021
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
7 Pekerjaan Pemasangan Pipa dan Accessories
- Galian tanah 2.31 M3 102,520.00 236,821.20 0.01 1.00 - - - - - - - - - - - - -
100
- Mengurug kembali 2.19 M3 33,916.00 74,276.04 0.00 1.00 - - - - - - - - - - - - -
- Pemasangan Pipa HDPE SDR 17 (PN 10) ND. 90 mm 6.00 M 5,571.00 33,426.00 0.00 1.00 - - - - - - - - - - - - -
-
PHO
RENCANA KEMAJUAN PEKERJAAN KOMULATIF KONTRAK AWAL - 0.09 0.18 2.30 4.42 7.38 10.34 13.31 16.27 22.20 28.12 34.05 39.97 46.63 53.29 56.80 60.30 63.81 67.31 71.18 75.05 78.91 82.78 86.47 90.16 93.54 94.60 95.65 96.06 97.59 98.12 98.57 100.0
90
RENCANA KEMAJUAN PEKERJAAN MINGGUAN 0.01 0.01 0.99 0.40 0.18 0.18 7.96 6.95 6.05 6.12 6.12 6.12 6.12 6.12 2.01 0.03 4.24 8.31 2.70 1.97 3.73 2.87 3.50 3.34 3.47 2.08 1.64 1.71 1.97 1.10 1.26 0.72
RENCANA KEMAJUAN PEKERJAAN MINGGUAN KOMULATIF - 0.01 0.03 1.02 1.42 1.60 1.78 9.74 16.69 22.74 28.86 34.98 41.10 47.21 53.33 55.34 55.37 59.61 67.93 70.63 72.60 76.34 79.21 82.71 86.05 89.52 91.60 93.24 94.95 96.92 98.02 99.28 100.0
KEMAJUAN REALISASI PEKERJAAN MINGGUAN 0.02 1.01 0.77 0.05 0.05 0.05 0.05 8.74 27.11 15.67 0.16 0.16 1.98 3.65 0.27 0.01 2.51 0.01 0.01 10.46 4.14 1.66 0.91 1.32 1.32 0.98 0.01
KEMAJUAN REALISASI PEKERJAAN MINGGUAN KOMULATIF - 0.02 1.02 1.79 1.84 1.89 1.94 1.98 10.73 37.84 53.51 53.67 53.83 55.81 59.45 59.73 59.74 62.25 62.25 62.26 72.72 76.86 78.52 79.43 80.75 82.07 83.05 100.0
DEVIASI 0.01 1.00 0.78 0.43 0.29 0.16 (7.75) (5.97) 15.10 24.65 18.69 12.73 8.60 6.12 4.38 4.37 2.63 (5.67) (8.37) 0.11 0.52 (0.69) (3.28) (5.30) (7.45) (8.55) -
RENALDI PURBA, ST
Manager Proyek
80
70
60
50
BENTUK RENCANA KESELAMATAN KONSTRUKSI (RKK)
#REF!
DAFTAR ISI
A. Kepemimpinan dan Partisipasi Pekerja dalam Keselamatan Konstruksi
A.1 Kepedulian pimpinan terhadap Isu eksternal dan internal
A.2 Komitmen Keselamatan Konstruksi
B. Perencanaan keselamatan konstruksi
B.1 Identifikasi bahaya, Penilaian risiko, Pengendalian dan Peluang.
B.2 Rencana tindakan (sasaran & program)
B.3 Rencana tindakan (sasaran & program)
C. Dukungan Keselamatan Konstruksi
C.1 Sumber daya
C.2 Kompetesni
C.3 Kepedulian
C.4 Komunikasi
C.5 Informasi Terdokumentasi
D. Operasi Keselamatan Konstruksi
D.1 Perencanaan Operasi
E. Evaluasi Kinerja Keselamatan Konstruksi
E.1 Pemantauan dan evaluasi
E.2 Tinjauan manajemen
E.3 Peningkatan kinerja keselamatan konstruksi
Dalam rangka pengadaan Pekerjaan Optimalisasi IKK Kluet Timur Kab. Aceh Selatan berkomitmen melaksanakan konstruksi berkeselamatan demi terciptanya Zero Accident, dengan memastikan bahwa seluruh pelaksanaan konstruksi.
#REF!
#REF!
#REF!
#REF!
B.1. Identifikasi bahaya, Penilaian risiko, Pengendalian dan Peluang.
PENILAIAN RISIKO
PENETAPAN PENGENDALIAN
NO JENIS/TIPE PEKERJAAN IDENTIFIKASI BAHAYA DAMPAK SKALA PRIORITAS
TINGKAT RISIKO K3
KEKERAPAN KEPARAHAN
RESIKO
(1) (2) (3) (4) (5) (6) (7) (8) (9)
1 Setting - out Terjatuh, Luka Ringan, Berat 3 3 9 Sedang
a. Pengendalian Kehati-hatian dalam
dan Meninggal
Tertabrak Truck, pengendalian alat
Tertusuk Benda Tajam dan Material Lainnya
b. Pengendalian arahan pada pekerja
lapangan
c. Memeriksa kelengkapan alat yang
dibawa beserta sefty lainya
2 Mobilisasi Pipa Tertimpa Material Luka Ringan, dan 3 2 6 Sedang
a. Pengendalian Kehati-hatian dalam
Sedang
pengendalian alat
b. Pengendalian arahan pada pekerja
lapangan
c. Memeriksa kelengkapan alat yang
dibawa beserta sefty lainya
3 Mobilisasi dan Demolisasi Pekerja Tertabrak Truck Luka Ringan, Berat 3 3 9 Sedang
a. Pengendalian Kehati-hatian dalam
dan Meninggal
pengendalian alat
13 Pemasangan Pipa Steel Terjepit, Terluka Oleh Alat kerja, Tertimpa Luka Ringan, dan 3 2 6 Sedang a) Menggunakan Sarung tangan
Sedang b) Gunakanlah alat dengan tepat
c) Menggunakan Sepatu Kerja
d) Menggunakan masker penutup
mulut
14 Pemasangan Pipa HDPE Terjepit, Terluka Oleh Alat kerja, Tertimpa Luka Ringan, dan 3 2 6 Sedang a) Menggunakan Sarung tangan
Sedang b) Gunakanlah alat dengan tepat
c) Menggunakan Sepatu Kerja
d) memberikan turap-turap penahan
tanah
e) Menggunakan masker penutup
mulut
15 Pekerjaan Pembesian Tertimpa Material Luka Ringan, dan 3 2 6 Sedang a) Menggunakan Sarung tangan
Sedang b) Gunakanlah alat dengan tepat
c) Menggunakan Sepatu kerja
d) Menggunakan masker penutup
mulut
Terluka, Terkena Material, Cat Terkena Mata
16 Pengecatan Engsel, Dan Gembok Luka Ringan, dan 3 2 6 Sedang a) Menggunakan masker penutup
Sedang mulut
b) Pengecatan tidak berlawanan arah
angin
Terjepit, Terluka Oleh Alat kerja, Tertimpa
17 Pemasangan Pompa Luka Ringan, dan 3 3 9 Sedang a) Menggunakan Sarung tangan
Berat b) Gunakanlah alat dengan tepat
c) Menggunakan Sepatu Kerja
d) Berhati-hati dalam pemasangan
pompa
18 Rekondisi Panel Dan Kabel Terjepit, Terluka Oleh Alat kerja, Tersetrum Luka Ringan, dan 3 3 9 Sedang
a. Pengendalian Menjaga jarak antara
Berat
alat dengan tenaga pengarah
20 Pemotongan Pipa Steel Terluka Oleh Alat Kerja Luka Ringan, dan 3 2 6 Sedang a) Menggunakan Sarung tangan
Sedang b) Gunakanlah alat dengan tepat
c) Menggunakan Sepatu kerja
d) Menggunakan masker penutup
mulut
21 Pengelasan Pipa Steel Terkena Percikan Material Las Luka Ringan, dan 3 2 6 Sedang a) Menggunakan Sarung tangan
Sedang b) Gunakanlah alat dengan tepat
c) Menggunakan Sepatu kerja
d) Menggunakan kaca mata las
d) Menggunakan masker penutup
mulut
22 Pengelasan Accessories Pipa Steel Terkena Percikan Material Las Luka Ringan, dan 3 2 6 Sedang a) Menggunakan Sarung tangan
Sedang b) Gunakanlah alat dengan tepat
c) Menggunakan Sepatu kerja
d) Menggunakan kaca mata las
d) Menggunakan masker penutup
mulut
23 Pengelasan Flange Terkena Percikan Material Las Luka Ringan, dan 3 2 6 Sedang a) Menggunakan Sarung tangan
Sedang b) Gunakanlah alat dengan tepat
c) Menggunakan Sepatu kerja
d) Menggunakan kaca mata las
e) Menggunakan masker penutup
mulut
24 Penyambungan dan Pemasangan Accessories PIPA Terluka Oleh Alat Kerja, Luka Ringan, dan 3 2 6 Sedang a) Menggunakan Sarung tangan
Sedang b) Gunakanlah alat dengan tepat
c) Menggunakan Sepatu Kerja
d) Menggunakan masker penutup
mulut
25 Pemasangan Gate Valve Terluka Oleh Alat Kerja Luka Ringan, dan 3 2 6 Sedang a) Menggunakan Sarung tangan
Sedang b) Gunakanlah alat dengan tepat
c) Menggunakan Sepatu Kerja
d) Menggunakan masker penutup
mulut
26 Penyambunggan Pipa HDPE Terluka Oleh Alat Kerja, Tertimpa Material Luka Ringan, dan 3 2 6 Sedang a) Menggunakan Sarung tangan
Sedang b) Gunakanlah alat dengan tepat
c) Menggunakan Sepatu Kerja
d) Menggunakan masker penutup
mulut
27 Pengecatan Pipa dan Baja Profil Siku Terluka, Terkena Material, Cat Terkena Mata Luka Ringan, dan 3 2 6 Sedang a) Menggunakan masker penutup
Sedang mulut
b) Pengecatan tidak berlawanan arah
angin
28 Pekerjaan Galian Tanah Untuk Koneksi Terluka Oleh Alat Kerja Luka Ringan, dan 3 1 3 Kecil
a. Pengendalian Menjaga jarak antara
Sedang
alat dengan tenaga pengarah
b. Pengendalian memberikan
gambangan pada titik-titik tanah labil
c) Pengendalian jarak antara pekerja
dengan pekerja
29 Pekerjaan Interkoneksi Pipa Lama Terluka Oleh Alat Kerja Luka Ringan, dan 3 2 6 Sedang
a. Pengendalian Menjaga jarak antara
Sedang
alat dengan tenaga pengarah
b. Pengendalian memberikan
gambangan pada titik-titik tanah labil
c) Pengendalian jarak antara pekerja
dengan pekerja
30 Pengerjaan Beton K -175 Untuk Umpak Tertimpa Material dan Terluka Karena Material Luka Ringan, dan 3 2 6 Sedang
a. Pengendalian Menjaga jarak antara
Sedang
alat dengan tenaga pengarah
b. Pengendalian memberikan
gambangan pada titik-titik tanah labil
c) Pengendalian jarak antara pekerja
dengan pekerja
31 Pekerjaan Bongkaran Aspal Hotmix dan Beton Terluka Oleh Alat Kerja Luka Ringan, dan 3 3 9 Sedang a) Menggunakan Sarung tangan
Berat b) memberikan polis lane pada titik
bahaya disekitar Bongkaran Aspal
Hotmix dan Beton
c) Pengendalian jarak antara pekerja
dengan pekerja
32 Pembersian Lokasi IPA Terluka Oleh Alat Kerja Luka Ringan, dan 3 2 6 Sedang
a. Pengendalian Kehati-hatian dalam
Sedang
pengendalian alatarahan
b. Pengendalian kerja pada pekerja
lapangan
c. Memeriksa kelengkapan alat yang
Terluka Oleh Alat Kerja, Tertimpa Material dibawa beserta sefty lainya
33 Pemasangan Pipa Sadap Untuk Intek Luka Ringan, dan 3 3 9 Sedang a) Menggunakan Sarung tangan
Berat b) Gunakanlah alat dengan tepat
Terluka Oleh Alat Kerja, Tertimpa Material, c) Menggunakan Sepatu Kerja
Tersetrum d) Menggunakan masker penutup
mulut
34 Pekerjaan Bongkar Batu Kali Luka Ringan, dan 3 2 6 Sedang a) Menggunakan Sarung tangan
Sedang
b) memberikan polis lane pada titik
bahaya disekitar Bongkaran batu kali
#REF!
#REF!
#REF!
#REF!
B.2. Rencana tindakan (sasaran & program)
2 Mobilisasi Pipa a)Pengendalian Kehati-hatian dalam pengendalian Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
alat b) Pengendalian arahan pada Op. trado c) Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
Memeriksa kelengkapan alat yang dibawa beserta Kebugaran, Kondisi sesuai dengan rambu, modul metode
sefty lainya mental, Bekerja spesifikasi kerja
sendirian.
3 Mobilisasi dan Demolisasi Pekerja a)Pengendalian Kehati-hatian dalam pengendalian Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
alat b) Pengendalian arahan pada Op. trado c) Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
Memeriksa kelengkapan alat yang dibawa beserta Kebugaran, Kondisi sesuai dengan rambu, modul metode
sefty lainya mental, Bekerja spesifikasi kerja
sendirian.
4 Mobilisasi Accessories, Pompa, Panel, Dan Kabel a)Pengendalian Kehati-hatian dalam pengendalian Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
alat b) Pengendalian arahan pada Op. trado c) Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
Memeriksa kelengkapan alat yang dibawa beserta Kebugaran, Kondisi sesuai dengan rambu, modul metode
sefty lainya mental, Bekerja spesifikasi kerja
sendirian.
5 Pekerjaan Galian Tanah Cadas / Tanah Keras a) Menggunakan peralatan kerja dan APD yang Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
benar, Menggunakan metode / cara kerja yang Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
benar dan peralatan kerja yang baik, menyusun Kebugaran, Kondisi sesuai dengan rambu, modul metode
intruksi kerja b) Pengendalian Menjaga jarak mental, Bekerja spesifikasi kerja
antara alat dengan tenaga pengarah c) sendirian.
Mengunakan Pelindung Pernapasan dan Mulut
(Masker)
6 Timbun Kembali Galian Tanah Cadas / Tanah Keras a) Menggunakan peralatan kerja dan APD yang Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
benar, Menggunakan metode / cara kerja yang Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
benar dan peralatan kerja yang baik, menyusun Kebugaran, Kondisi sesuai dengan rambu, modul metode
intruksi kerja b) Memakai sarung tangan. mental, Bekerja spesifikasi kerja
sendirian.
7 Rekondisi Lampu Penerangan a. Pengendalian Menjaga jarak antara alat dengan Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
tenaga pengarah b) memberikan polis lane pada Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
titik bahaya disekitar rekondisa lampu penerangan Kebugaran, Kondisi sesuai dengan rambu, modul metode
c) Pengendalian jarak antara pekerja dengan mental, Bekerja spesifikasi kerja
pekerja sendirian.
8 Pekerjaan Perataan dan Pemadatan Tanah Urugan a) Menggunakan peralatan kerja dan APD yang Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
benar, Menggunakan metode / cara kerja yang Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
benar dan peralatan kerja yang baik, menyusun Kebugaran, Kondisi sesuai dengan rambu, modul metode
intruksi kerja b) Memakai sarung tangan. mental, Bekerja spesifikasi kerja
sendirian.
9 Rekondisi Pompa Transmisi Dan Distribusi a. Pengendalian Menjaga jarak antara alat dengan Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
tenaga pengarah b) memberikan polis lane pada Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
titik bahaya disekitar rekondisa lampu penerangan Kebugaran, Kondisi sesuai dengan rambu, modul metode
c) Pengendalian jarak antara pekerja dengan mental, Bekerja spesifikasi kerja
pekerja sendirian.
10 Urugan Tanah a) Menggunakan peralatan kerja dan APD yang Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
benar, Menggunakan metode / cara kerja yang Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
benar dan peralatan kerja yang baik, menyusun Kebugaran, Kondisi sesuai dengan rambu, modul metode
intruksi kerja b) Memakai sarung tangan. mental, Bekerja spesifikasi kerja
sendirian.
11 Bekisting Dinding a) Menggunakan peralatan kerja dan APD yang Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
benar, Menggunakan metode / cara kerja yang Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
benar dan peralatan kerja yang, menyusun intruksi Kebugaran, Kondisi sesuai dengan rambu, modul metode
kerja b) Pengendalian Menjaga jarak antara alat mental, Bekerja spesifikasi kerja
dengan tenaga pengarah sendirian.
c) Pengendalian memberikan
gambangan pada titik-titik tanah labil
12 Bekisting Tutup a) Menggunakan peralatan kerja dan APD yang Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
benar, Menggunakan metode / cara kerja yang Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
benar dan peralatan kerja yang, menyusun intruksi Kebugaran, Kondisi sesuai dengan rambu, modul metode
kerja b) Pengendalian Menjaga jarak antara alat mental, Bekerja spesifikasi kerja
dengan tenaga pengarah sendirian.
c) Pengendalian memberikan
gambangan pada titik-titik tanah labil
13 Pemasangan Pipa Steel a) Menggunakan peralatan kerja dan APD yang Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
benar, Menggunakan metode / cara kerja yang Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
benar dan peralatan kerja yang, menyusun intruksi Kebugaran, Kondisi sesuai dengan rambu, modul metode
kerja b) Menggunakan Sarung tangan c) mental, Bekerja spesifikasi kerja
Gunakanlah alat dengan tepat d) Menggunakan sendirian.
Sepatu Kerja e) Menggunakan masker penutup
mulut
14 Pemasangan Pipa HDPE a) Menggunakan peralatan kerja dan APD yang Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
benar, Menggunakan metode / cara kerja yang Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
benar dan peralatan kerja yang, menyusun intruksi Kebugaran, Kondisi sesuai dengan rambu, modul metode
kerja b) Menggunakan Sarung tangan c) mental, Bekerja spesifikasi kerja
Gunakanlah alat dengan tepat d) Menggunakan sendirian.
Sepatu Kerja e) Menggunakan masker penutup
mulut
15 Pekerjaan Pembesian a) Menggunakan peralatan kerja dan APD yang Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
benar, Menggunakan metode / cara kerja yang Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
benar dan peralatan kerja yang, menyusun intruksi Kebugaran, Kondisi sesuai dengan rambu, modul metode
kerja b) Menggunakan Sarung tangan c) mental, Bekerja spesifikasi kerja
Gunakanlah alat dengan tepat d) Menggunakan sendirian.
Sepatu Kerja e) Menggunakan masker penutup
mulut
16 Pengecatan Engsel, Dan Gembok a) Menggunakan peralatan kerja dan APD yang Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
benar, Menggunakan metode / cara kerja yang Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
benar dan peralatan kerja yang, menyusun intruksi Kebugaran, Kondisi sesuai dengan rambu, modul metode
kerja b) Menggunakan masker penutup mulut c) mental, Bekerja spesifikasi kerja
Pengecatan tidak berlawanan arah angin sendirian.
17 Pemasangan Pompa a) Menggunakan peralatan kerja dan APD yang Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
benar, Menggunakan metode / cara kerja yang Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
benar dan peralatan kerja yang, menyusun intruksi Kebugaran, Kondisi sesuai dengan rambu, modul metode
kerja b) Menggunakan Sarung tangan c) mental, Bekerja spesifikasi kerja
Gunakanlah alat dengan tepat d) Menggunakan sendirian.
Sepatu Kerja e) Berhati-hati dalam pemasangan
pompa
18 Rekondisi Panel Dan Kabel a. Pengendalian Menjaga jarak antara alat dengan Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
tenaga pengarah b) memberikan polis lane pada Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
titik bahaya disekitar rekondisa panel dan kabel c) Kebugaran, Kondisi sesuai dengan rambu, modul metode
Pengendalian jarak antara pekerja dengan pekerja mental, Bekerja spesifikasi kerja
sendirian.
19 Bekisting a) Menggunakan peralatan kerja dan APD yang Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
benar, Menggunakan metode / cara kerja yang Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
benar dan peralatan kerja yang, menyusun intruksi Kebugaran, Kondisi sesuai dengan rambu, modul metode
kerja b) Pengendalian Menjaga jarak antara alat mental, Bekerja spesifikasi kerja
dengan tenaga pengarah sendirian.
c) Pengendalian memberikan
gambangan pada titik-titik tanah labil
20 Pemotongan Pipa Steel a) Menggunakan peralatan kerja dan APD yang Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
benar, Menggunakan metode / cara kerja yang Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
benar dan peralatan kerja yang, menyusun intruksi Kebugaran, Kondisi sesuai dengan rambu, modul metode
kerja b) Menggunakan Sarung tangan c) mental, Bekerja spesifikasi kerja
Gunakanlah alat dengan tepat d) Menggunakan sendirian.
Sepatu Kerja e) Menggunakan masker penutup
mulut
21 Pengelasan Pipa Steel a) Menggunakan peralatan kerja dan APD yang Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
benar, Menggunakan metode / cara kerja yang Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
benar dan peralatan kerja yang, menyusun intruksi Kebugaran, Kondisi sesuai dengan rambu, modul metode
kerja b) Menggunakan Sarung tangan c) mental, Bekerja spesifikasi kerja
Gunakanlah alat dengan tepat d) Menggunakan sendirian.
Sepatu Kerja e) Menggunakan masker penutup
mulut
22 Pengelasan Accessories Pipa Steel a) Menggunakan peralatan kerja dan APD yang Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
benar, Menggunakan metode / cara kerja yang Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
benar dan peralatan kerja yang, menyusun intruksi Kebugaran, Kondisi sesuai dengan rambu, modul metode
kerja b) Menggunakan Sarung tangan c) mental, Bekerja spesifikasi kerja
Gunakanlah alat dengan tepat d) Menggunakan sendirian.
Sepatu Kerja e) Menggunakan masker penutup
mulut
23 Pengelasan Flange a) Menggunakan peralatan kerja dan APD yang Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
benar, Menggunakan metode / cara kerja yang Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
benar dan peralatan kerja yang, menyusun intruksi Kebugaran, Kondisi sesuai dengan rambu, modul metode
kerja b) Menggunakan Sarung tangan c) mental, Bekerja spesifikasi kerja
Gunakanlah alat dengan tepat d) Menggunakan sendirian.
Sepatu Kerja e) Menggunakan masker penutup
mulut
24 Penyambungan dan Pemasangan Accessories PIPA a) Menggunakan peralatan kerja dan APD yang Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
benar, Menggunakan metode / cara kerja yang Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
benar dan peralatan kerja yang, menyusun intruksi Kebugaran, Kondisi sesuai dengan rambu, modul metode
kerja b) Menggunakan Sarung tangan c) mental, Bekerja spesifikasi kerja
Gunakanlah alat dengan tepat d) Menggunakan sendirian.
Sepatu Kerja e) Menggunakan masker penutup
mulut
25 Pemasangan Gate Valve a) Menggunakan peralatan kerja dan APD yang Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
benar, Menggunakan metode / cara kerja yang Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
benar dan peralatan kerja yang, menyusun intruksi Kebugaran, Kondisi sesuai dengan rambu, modul metode
kerja b) Menggunakan Sarung tangan c) mental, Bekerja spesifikasi kerja
Gunakanlah alat dengan tepat d) Menggunakan sendirian.
Sepatu Kerja e) Menggunakan masker penutup
mulut
26 Penyambunggan Pipa HDPE a) Menggunakan peralatan kerja dan APD yang Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
benar, Menggunakan metode / cara kerja yang Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
benar dan peralatan kerja yang, menyusun intruksi Kebugaran, Kondisi sesuai dengan rambu, modul metode
kerja b) Menggunakan Sarung tangan c) mental, Bekerja spesifikasi kerja
Gunakanlah alat dengan tepat d) Menggunakan sendirian.
Sepatu Kerja e) Menggunakan masker penutup
mulut
27 Pengecatan Pipa dan Baja Profil Siku a) Menggunakan peralatan kerja dan APD yang Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
benar, Menggunakan metode / cara kerja yang Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
benar dan peralatan kerja yang, menyusun intruksi Kebugaran, Kondisi sesuai dengan rambu, modul metode
kerja b) Menggunakan masker penutup mulut c) mental, Bekerja spesifikasi kerja
Pengecatan tidak berlawanan arah angin sendirian.
28 Pekerjaan Galian Tanah Untuk Koneksi a) Menggunakan peralatan kerja dan APD yang Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
benar, Menggunakan metode / cara kerja yang Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
benar dan peralatan kerja yang baik, menyusun Kebugaran, Kondisi sesuai dengan rambu, modul metode
intruksi kerja b) Pengendalian Menjaga jarak mental, Bekerja spesifikasi kerja
antara alat dengan tenaga pengarah c) sendirian.
Mengunakan Pelindung Pernapasan dan Mulut
(Masker)
29 Pekerjaan Interkoneksi Pipa Lama a) Menggunakan peralatan kerja dan APD yang Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
benar, Menggunakan metode / cara kerja yang Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
benar dan peralatan kerja yang baik, menyusun Kebugaran, Kondisi sesuai dengan rambu, modul metode
intruksi kerja b) Pengendalian Menjaga jarak mental, Bekerja spesifikasi kerja
antara alat dengan tenaga pengarah c) sendirian.
Mengunakan Pelindung Pernapasan dan Mulut
(Masker)
30 Pengerjaan Beton K -175 Untuk Umpak a) Menggunakan peralatan kerja dan APD yang Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
benar, Menggunakan metode / cara kerja yang Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
benar dan peralatan kerja yang baik, menyusun Kebugaran, Kondisi sesuai dengan rambu, modul metode
intruksi kerja b) Pengendalian Menjaga jarak mental, Bekerja spesifikasi kerja
antara alat dengan tenaga pengarah c) sendirian.
Mengunakan Pelindung Pernapasan dan Mulut
(Masker)
31 Pekerjaan Bongkaran Aspal Hotmix dan Beton a) Menggunakan peralatan kerja dan APD yang Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
benar, Menggunakan metode / cara kerja yang Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
benar dan peralatan kerja yang baik, menyusun Kebugaran, Kondisi sesuai dengan rambu, modul metode
intruksi kerja b) Pengendalian Menjaga jarak mental, Bekerja spesifikasi kerja
antara alat dengan tenaga pengarah c) sendirian.
Mengunakan Pelindung Pernapasan dan Mulut
(Masker)
32 Pembersian Lokasi IPA a) Menggunakan peralatan kerja dan APD yang Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
benar, Menggunakan metode / cara kerja yang Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
benar dan peralatan kerja yang baik, menyusun Kebugaran, Kondisi sesuai dengan rambu, modul metode
intruksi kerja b). Pengendalian arahan pada mental, Bekerja spesifikasi kerja
pekerja lapangan c). Memeriksa kelengkapan alat sendirian.
yang dibawa beserta sefty lainya
33 Pemasangan Pipa Sadap Untuk Intek a) Menggunakan peralatan kerja dan APD yang Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
benar, Menggunakan metode / cara kerja yang Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
benar dan peralatan kerja yang, menyusun intruksi Kebugaran, Kondisi sesuai dengan rambu, modul metode
kerja b) Menggunakan Sarung tangan c) mental, Bekerja spesifikasi kerja
Gunakanlah alat dengan tepat d) Menggunakan sendirian.
Sepatu Kerja e) Menggunakan masker penutup
mulut
34 Pekerjaan Bongkar Batu Kali a. Pengendalian Menjaga jarak antara alat dengan Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
tenaga pengarah b) memberikan polis lane pada Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
titik bahaya disekitar bongkaran batu kali c) Kebugaran, Kondisi sesuai dengan rambu, modul metode
Pengendalian jarak antara pekerja dengan pekerja mental, Bekerja spesifikasi kerja
sendirian.
35 Penyambungan Daya PLN 66 KVA BP Material dan Pemasaa) Menggunakan peralatan kerja dan APD yang Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
benar, Menggunakan metode / cara kerja yang Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
benar dan peralatan kerja yang, menyusun intruksi Kebugaran, Kondisi sesuai dengan rambu, modul metode
kerja b) Menggunakan Sarung tangan c) mental, Bekerja spesifikasi kerja
Gunakanlah alat dengan tepat d) Menggunakan sendirian.
Sepatu Kerja e) Berhati-hati dalam penyambungan
kabel
36 Pekerjaan Rekondisi Pipa Bocor a. Pengendalian Menjaga jarak antara alat dengan Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
tenaga pengarah b) memberikan polis lane pada Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
titik bahaya disekitar rekondisi pipa bocor c) Kebugaran, Kondisi sesuai dengan rambu, modul metode
Pengendalian jarak antara pekerja dengan pekerja mental, Bekerja spesifikasi kerja
sendirian.
37 Pengetesan Pipa a) Menggunakan peralatan kerja dan APD yang Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
benar, Menggunakan metode / cara kerja yang Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
benar dan peralatan kerja yang, menyusun intruksi Kebugaran, Kondisi sesuai dengan rambu, modul metode
kerja b) Menggunakan Sarung tangan c) mental, Bekerja spesifikasi kerja
Gunakanlah alat dengan tepat d) Menggunakan sendirian.
Sepatu Kerja e) Menggunakan masker penutup
mulut
38 Pekerjaan Rekondisi Genset a. Pengendalian Menjaga jarak antara alat dengan Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
tenaga pengarah b) memberikan polis lane pada Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
titik bahaya disekitar rekondisi genset c) Kebugaran, Kondisi sesuai dengan rambu, modul metode
Pengendalian jarak antara pekerja dengan pekerja mental, Bekerja spesifikasi kerja
sendirian.
39 Plesteran 1 : 2 a) Menggunakan peralatan kerja dan APD yang Kompetensi, Mengoptimalka Alat Pelindung Sesuai Jadwal Tertib melaksanakan Cheklist Ahli K3
benar, Menggunakan metode / cara kerja yang Kesehatan & n pekerjaan Diri, Rambu- Pelaksanaan Pekerjaan sesuai
benar dan peralatan kerja yang, menyusun intruksi Kebugaran, Kondisi sesuai dengan rambu, modul metode
kerja b) Pengendalian Menempatkan perancah yg mental, Bekerja spesifikasi kerja
baik dan benar pada posisi yang diizinkan c) sendirian.
Pengendalian bahan yang dipergunkan untuk
bahan perancah, menempatkan tanaga yang ahli.
d) Pengendalian sefty ditempatkan sesuai dengan
arahan pengawas
#REF!
#REF!
#REF!
#REF!
PELAKSANAAN TA 2020
PEKERJAAN : OPTIMALISASI IKK KLUET TIMUR KAB. ACEH SELATAN
I. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi (Direksi Keet/sewa, 0.72 Ls 7,500,000.00 5,375,000.00
0 Tenaga kerja, Alat, Bahan)
2 Setting-Out 13,756.00 M' 1,870.00 25,723,720.00
3 Administrasi (Dok. Kontrak, Shop Drawing dan As-built 0.72 Ls 5,000,000.00 3,583,333.33
Drawing, Site management, Dok. Proyek, Fasilitas Sementara)
4 SMK3 Konstruksi 1.00 Ls 20,270,000.00 20,270,000.00
2 Pengadaan Accessories
- Tee Steel dia. 250mm x 100mm - Bh 1,750,000.00 -
- Gate Valve Cl dia. 250mm - Bh 5,300,000.00 -
- Gate Valve Cl dia. 100mm - Bh 2,700,000.00 -
- Gate Valve Cl dia. 75mm
- Loose Flange dia. 250mm - Bh 400,000.00 -
- Loose Flange dia. 100mm - Bh 175,000.00 -
- Flange Socket dia. 250mm - Bh 1,500,000.00 -
- Stube Flang dia. 110mm - Bh 500,000.00 -
- Stube Flange dia. 90mm
- Butt Fusion Reduser Tee ND 110mm x 90mm - Bh 500,000.00 -
- Butt Fusion Cup dia 110 mm - Bh 300,000.00 -
- Butt Fusion Cup dia 90 mm
- Street Box - Bh 500,000.00 -
- Pipa Selubung Street Box - Bh 100,000.00 -
- Baut Lengkap Ring dan Mur Untuk Flange - Bh 10,000.00 -
- Paking/Gasket untuk Flange - M2 325,000.00 -
4 Pengetesan Pipa
- Pipa HDPE SDR 17 (PN 10) ND. 110 mm
- Pipa HDPE SDR 17 (PN 10) ND. 90 mm
6 Pembuatan Wash Out dia. 75 mm pada Jaringan Pipa dia. 100 mm (1 Unit)
Pengadaan Pipa dan Accessories
- Gate Valve dia. 100 mm
- Gate Valve dia. 75 mm
- Tee Steel dia. 100 x 75 mm
- Stub Flange HDPE ND. 90 mm
- Loose Flange dia. 100 mm
- Loose Flange dia. 75 mm
- Butt Fusion Elbouw ND. 90 mm x 90º
- Pipa HDPE SDR 17 (PN 10) ND. 90 mm
- Pipa PVC dia. 150 mm Untuk Selubung Street Box
- Street Box
- Baut Lengkap Ring dan Mur Untuk Flange
- Paking / Gasket Untuk Flange
DIBULATKAN : 1,590,228,000.00
TABEL 1. IDENTIFIKASI BAHAYA, PENILAIAN RISIKO, PENGENDALIAN RISIKO K3,
PROGRAM K3, DAN BIAYA
#REF! : #REF!
#REF! : #REF!
#REF! : #REF!
1 Mobilisasi dan Demobilisasi a) Terjadi Kecelakaan lalu lintas/Tabrakan ˃ Rusak alat dan korban jiwa mencegah Ketrampilan dan berhati- Peralatan : 1 Unit Trado 560,000.00
b). Terjepit/tertabrak dengan alat berat dan pengangkutnya ˃ luka berat terjadinya hati dalam menjalankan Bahan : -
kecelakaan trado
c.) Lepasnya alat berat dari mobil angkutan / jatuh ˃ Rusak ringan SDM : 1 Sopir Trado
d.) Terkena alat berat ˃ luka berat 1 Kenek Trado
e) Kesetrum arus listrik dari Kabel listrik dijalan raya ˃ luka berat/Meninggal
3 Direksi keet + Gudang a). Terjepit anggota tubuh oleh kayu ˃ luka berat/luka ringan a) Gunakanlah alat dengan
b). Terkena paku/luka ringan, luka sedang ˃ luka ringan, luka sedang mencegah tepat Peralatan : alat bantu 140,000.00
terjadinya Bahan : kayu
kecelakaan b) berhati-hati dalam
mengangkat kayu SDM : 10 org pekerja
1 org pengawas
4 Galian Tanah Biasa a). Terkena peralatan kerja ˃ luka ringan/berat a) memberikan turap-turap
b). Pekerja/Orang jatuh ke dalam galian ˃ luka ringan/berat mencegah penahan tanah 9,670,350.00
˃ luka ringan/berat terjadinya b) memberikan polis lane Peralatan : alat bantu
kecelakaan pada titik bahaya disekitar Bahan : -
galian saat pengalian
SDM : 5 org pekerja
1 org pengawas
c) Pengendalian jarak
dengan patok-patok yang
akan digali
5 Urugan Kembali a). Terkena peralatan kerja, cangkul ˃ Luka berat/Luka ringan a) memberikan turap-turap
mencegah penahan tanah Peralatan : alat bantu 2,424,800.00
terjadinya b) memberikan polis lane Bahan : -
kecelakaan pada titik bahaya disekitar SDM : 5 org pekerja
timbunan saat penimbunan
kembali 1 org pengawas
c) Pengendalian jarak
antara pekerja dengan
pekerja
6 Beton Cor K. 175 a). Mengalami luka tangan saat memasukkan material ke dalam ˃ Luka berat/Luka sedang a) Pengendalian
Molen mencegah Menempatkan tenaga 158,800.00
terjadinya bekesting/mal yang
˃ Luka berat/Luka sedang propesional, serta melihat Peralatan : molen
kecelakaan
b). Mengalami gangguan pernafasan akibat penggunaan bahan semen sambungan kayu yg Bahan : Semen Portland
˃ Luka berat/Luka sedang terpasang dengan kuat. Pasir Pasang
c). Terjadi iritasi pada kulit dan mata akibat percikan semen atau
adukan semen Kerikil
d). Terkena percikan beton saat kerja beton ˃ Luka berat/Luka sedang SDM : 6 org pekerja
b) Pengendalian alat kerja 1 org pengawas
ditempatkan sesuai dengan
arahan pengawas
c) Pengendalianya
membuat jalan menuju
tempat pengecoran yang
kuat dan bisa dilalui tenaga
untuk pengecoran
7 Pemotongan PIPA GIP/CI a). Tetimpa Pipa GIP/CI ˃ Luka ringan/Luka sedang a) Menggunakan Sarung
b). Terjepit Pipa GIP/CI ˃ Luka ringan/Luka sedang mencegah tangan Peralatan : Pemotong GIP/CI 213,800.00
terjadinya
c). Terkena Peralatan kerja ˃ Luka ringan/Luka sedang
kecelakaan b) Gunakanlah alat dengan Bahan : -
tepat SDM : 4 org pekerja
c) Menggunakan Sepatu 1 org pengawas
Sefte
8 Pemotongan PIPA PVC a). Tetimpa Pipa PVC ˃ Luka ringan/Luka sedang a) Menggunakan Sarung
b). Terjepit Pipa PVC ˃ Luka ringan/Luka sedang mencegah tangan Peralatan : Pemotong PVC 320,000.00
terjadinya
c). Terkena Peralatan kerja ˃ Luka ringan/Luka sedang
kecelakaan b) Gunakanlah alat dengan Bahan : -
tepat SDM : 4 org pekerja
c) Menggunakan Sepatu 1 org pengawas
kerja
9 Pemotongan PIPA HDPE a). Tetimpa Pipa PVC ˃ Luka ringan/Luka sedang a) Menggunakan Sarung
b). Terjepit Pipa PVC ˃ Luka ringan/Luka sedang mencegah tangan Peralatan : Pemotong HDPE 800,000.00
terjadinya
c). Terkena Peralatan kerja ˃ Luka ringan/Luka sedang
kecelakaan b) Gunakanlah alat dengan Bahan : -
tepat SDM : 4 org pekerja
c) Menggunakan Sepatu 1 org pengawas
kerja
10 Penyambungan PIPA GIP/CI a). Tetimpa Pipa GIP/CI ˃ Luka ringan/Luka sedang a) Menggunakan Sarung
b). Terjepit Pipa GIP/CI ˃ Luka ringan/Luka sedang mencegah tangan Peralatan : Katrol, Mesin Las
terjadinya
c). Terkena Peralatan kerja (Katrol, Mesin Las, Alat Bantu, Dll) ˃ Luka ringan/Luka sedang
kecelakaan b) Gunakanlah alat dengan Bahan : Kawat Las 356,450.00
d). Terperosok kedalam kedalam lubang ˃ Luka ringan/Luka sedang tepat SDM : 4 org pekerja
c) Menggunakan Sepatu 1 org pengawas
Kerja
d) memberikan turap-turap
penahan tanah
e) Menggunakan masker
penutup mulut
11 Penyambungan PIPA PVC a). Tetimpa Pipa PVC ˃ Luka ringan/Luka sedang a) Menggunakan Sarung
b). Terjepit Pipa PVC ˃ Luka ringan/Luka sedang mencegah tangan Peralatan : Katrol, A. Bantu 235,650.00
terjadinya
c). Terkena Peralatan kerja (Katrol, Alat Bantu, Dll) ˃ Luka ringan/Luka sedang
kecelakaan b) Gunakanlah alat dengan Bahan : Lem Pipa
d). Terperosok kedalam kedalam lubang ˃ Luka ringan/Luka sedang tepat SDM : 6 org pekerja
c) Menggunakan Sepatu 1 org pengawas
Kerja
d) memberikan turap-turap
penahan tanah
e) Menggunakan masker
penutup mulut
12 Penyambungan PIPA HDPE a). Tetimpa Pipa PVC ˃ Luka ringan/Luka sedang a) Menggunakan Sarung
b). Terjepit Pipa PVC ˃ Luka ringan/Luka sedang mencegah tangan Peralatan : Mesin penyambung HDPE 1,000,000.00
terjadinya
c). Terkena Peralatan kerja (Katrol, Alat Bantu, Dll) ˃ Luka ringan/Luka sedang
kecelakaan b) Gunakanlah alat dengan Bahan : Solar
d). Terperosok kedalam kedalam lubang ˃ Luka ringan/Luka sedang tepat Minyak pelumas
c) Menggunakan Sepatu SDM : 6 org pekerja
Kerja 1 org pengawas
d) memberikan turap-turap
penahan tanah
e) Menggunakan masker
penutup mulut
13 Interkoneksi a). Tetimpa Pipa PVC ˃ Luka ringan/Luka sedang a) Menggunakan Sarung
dengan Pipa Eksisting b). Terjepit Pipa PVC ˃ Luka ringan/Luka sedang mencegah tangan Peralatan : Katrol, A. Bantu 650,250.00
terjadinya
c). Terkena Peralatan kerja (Katrol, Alat Bantu, Dll) ˃ Luka ringan/Luka sedang
kecelakaan b) Gunakanlah alat dengan Bahan : -
d). Terperosok kedalam kedalam lubang ˃ Luka ringan/Luka sedang tepat SDM : 8 org pekerja
c) Menggunakan Sepatu 1 org pengawas
Kerja
d) memberikan turap-turap
penahan tanah
14 Pemotongan Jalan dan a). Tetimpa Peralatan kerja ˃ Luka ringan/Luka sedang a) memberikan turap-turap
perbaikan kembali b). Terjepit Alat Kerja ˃ Luka ringan/Luka sedang mencegah penahan tanah Peralatan : Alat Bantu 800,000.00
c). Terjatuh dalam galian ˃ Luka ringan/Luka sedang terjadinya Bahan : -
kecelakaan
˃ Luka ringan/Luka sedang SDM : 8 org pekerja
b) memberikan polis lane
pada titik bahaya disekitar 1 org pengawas
galian saat pengalian
c) Pengendalian jarak
dengan patok-patok yang
akan digali
SAIFULLAH, SE
Direktur
REKAPITULASI ANALISA HARGA SATUAN PEKERJAAN
1 2 3 4
PEKERJAAN PERSIAPAN
1 Uitset Pengukuran Jarak M' AHSP PU - T.04 -
2 Pengukuran M' AHSP PU - T.04.1 2,046.00
PEKERJAAN TANAH
1 Galian Tanah Biasa Sedalam 1 Meter M3 AHSP PU A.2.3.1.1 77,275.00
2 Galian Tanah Keras Sedalam 1 Meter M3 AHSP PU A.2.3.1.4 102,872.00
3 Galian tanah cadas sedalam 1 meter M3 AHSP PU A.2.3.1.5 -
4 Galian Tanah Tanah Lumpur Sedalam 1 Meter M3 AHSP PU A.2.3.1.6 -
5 Mengurug Kembali Galian M3 AHSP PU A.2.3.1.9 34,829.30
6 Urugan Tanah Bekas Galian Termasuk Perataan dan Pemadatan (stamper) M3 AHSP PU - T.14 b 59,950.00
7 Urugan Pasir M3 AHSP PU A.2.3.1.11 149,710.00
PEKERJAAN PASANGAN
1 Pondasi Batu Belah/Kali Campuran 1:4 M3 AHSP PU A.3.2.1.2 -
2 Pekerjaan Batu Kosong (Aantamping) M3 AHSP PU A.3.2.1.9 -
PEKERJAAN BETON
1 Lantai Kerja Beton Mutu F'c = 7,4 Mpa (K 100), Slump (3-6) cm, W/c = 0,87 M3 AHSP PU A.4.1.1.4 -
2 Beton Mutu F'c = 14,5 Mpa (K 175), Slump (12 ± 2) cm, W/c = 0,66 M3 AHSP PU A.4.1.1.5 876,007.17
3 Beton Mutu F'c = 21,7 Mpa (K 250), Slump (12 ± 2) cm, W/c = 0,56 M3 AHSP PU A.4.1.1.8 959,285.61
4 Pembesian 1 Kg Dengan Besi Polos Atau Besi Ulir KG AHSP PU A.4.1.1.17 17,301.90
5 Memasang Bekisting Untuk Pondasi M2 AHSP PU A.4.1.1.20 87,208.00
PEKERJAAN PENGELASAN
1 Pengelasan dengan Listrik M' AHSP PU A.4.2.1.5 -
2 Pemasangan Baja Profil Kg AHSP PU A.4.2.1.1 13,695.00
3 1 M' Pengelasan Pipa HDPE M Anl. HDPE. A -
PEKERJAAN PEMASANGAN PIPA PVC
1 Pemasangan 1 m pipa HDPE Ø 75 mm M' AHSP PU A.8.4.1.14 -
2 Pemasangan 1 m pipa HDPE Ø 90 mm M' AHSP PU A.8.4.1.17 #REF!
3 Pemasangan 1 m pipa HDPE Ø 110 mm M' AHSP PU A.8.4.1.18 #REF!
4 Memasang 1 M' pipa PVC dia. 150 mm M' AHSP PU A.8.4.1.4 19,624.00
5 Memasang 1 M' pipa PVC dia. 200 mm M' AHSP PU A.8.4.1.5 31,460.00
PEKERJAAN PEMASANGAN PIPA STEEL
1 Memasang 1 M' pipa Steel dia. 75 mm M' AHSP PU A.8.4.1.64 66,451.00
2 Memasang 1 M' pipa Steel dia. 75 mm M' AHSP PU A.8.4.1.64.a 71,775.00
3 Memasang 1 M' pipa Steel dia. 100 mm M' AHSP PU A.8.4.1.65 77,099.00
4 Memasang 1 M' pipa Steel dia. 150 mm M' AHSP PU A.8.4.1.67 94,303.00
5 Memasang 1 M' pipa Steel dia. 200 mm M' AHSP PU A.8.4.1.68 148,148.00
PEKERJAAN PEMASANGAN PIPA HDPE
1 Memasang 1 M' pipa HDPE dia. 50 mm M' AHSP PU A.8.1.17 5,698.00
2 Memasang 1 M' pipa HDPE dia. 75 mm M' AHSP PU A.8.1.17.a 6,171.00
3 Memasang 1 M' pipa HDPE dia. 100 mm M' AHSP PU A.8.1.18 6,644.00
4 Memasang 1 M' pipa HDPE dia. 150 mm M' AHSP PU A.8.1.20 10,274.00
5 Memasang 1 M' pipa HDPE dia. 200 mm M' AHSP PU A.8.1.21 16,918.00
6 Memasang 1 M' pipa HDPE dia. 250 mm M' AHSP PU A.8.1.22 20,900.00
7 Memasang 1 M' pipa HDPE dia. 300 mm M' AHSP PU A.8.1.23 28,237.00
8 Memasang 1 M' pipa HDPE dia. 350 mm M' AHSP PU A.8.1.23.a 38,203.00
9 Memasang 1 M' pipa HDPE dia. 400 mm M' AHSP PU A.8.1.24 48,169.00
PEKERJAAN PENGELASAN PIPA STEEL
1 Pengelasan Pipa Steel dia. 75 mm Titik Anl. L.1 114,910.88
2 Pengelasan Pipa Steel dia. 75 mm Titik Anl. L.2 114,910.88
3 Pengelasan Pipa Steel dia. 100 mm Titik Anl. L.3 152,007.01
4 Pengelasan Pipa Steel dia. 150 mm Titik Anl. L.4 221,116.02
5 Pengelasan Pipa Steel dia. 200 mm Titik Anl. L.5 290,696.04
PEKERJAAN PENGELASAN FLANGE
1 Pengelasan Flange dia. 250 mm Bh Anl. L. F. 6 539,972.35
2 Pengelasan Flange dia. 200 mm Bh Anl. L. F. 5 436,210.38
3 Pengelasan Flange dia. 150 mm Bh Anl. L. F. 4 331,650.01
4 Pengelasan Flange dia. 100 mm Bh Anl. L. F. 3 227,889.21
NO URAIAN SATUAN ANALISA HARGA SATUAN
1 2 3 4
5 Pengelasan Flange dia. 75 mm Bh Anl. L. F. 2 172,689.54
6 Pengelasan Flange dia. 50 mm Bh Anl. L. F. 1 -
NO URAIAN SATUAN ANALISA HARGA SATUAN
1 2 3 4
PEKERJAAN PEMOTONGAN PIPA STEEL
1 Pemotongan Pipa Steel dia. 200 mm Bh AHSP PU A.8.4.2.68 66,682.00
2 Pemotongan Pipa Steel dia. 150 mm Bh AHSP PU A.8.4.2.67 26,939.00
3 Pemotongan Pipa Steel dia. 100 mm Bh AHSP PU A.8.4.2.65 13,453.00
4 Pemotongan Pipa Steel dia. 75 mm Bh AHSP PU A.8.4.2.64.a 9,724.00
5 Pemotongan Pipa Steel dia. 50 mm Bh AHSP PU A.8.4.2.64 5,830.00
PEKERJAAN PENYAMBUNGAN PIPA HDPE
1 Penyambungan Pipa HDPE dia. 75 mm Titik Anl. HDPE. A1 28,646.48
2 Penyambungan Pipa HDPE dia. 75 mm Titik Anl. HDPE. A2 28,646.48
3 Penyambungan Pipa HDPE dia. 100 mm Titik Anl. HDPE. A3 38,021.91
4 Penyambungan Pipa HDPE dia. 150 mm Titik Anl. HDPE. A4 55,265.93
5 Penyambungan Pipa HDPE dia. 200 mm Titik Anl. HDPE. A5 72,662.63
6 Penyambungan Pipa HDPE dia. 250 mm Titik Anl. HDPE. A6 89,907.68
7 Penyambungan Pipa HDPE dia. 300 mm Titik Anl. HDPE. A7 108,296.86
8 Penyambungan Pipa HDPE dia. 350 mm Titik Anl. HDPE. A8 125,651.90
PENGETESAN PIPA
1 Pengetesan Pipa dia. 75 mm M' AHSP PU A.8.4.5.1 -
2 Pengetesan Pipa dia. 75 mm M' AHSP PU A.8.4.5.2 2,065.80
3 Pengetesan Pipa dia. 100 mm M' AHSP PU A.8.4.5.3 2,439.80
3 Pengetesan Pipa dia. 150 mm M' AHSP PU A.8.4.5.4 3,374.80
4 Pengetesan Pipa dia. 200 mm M' AHSP PU A.8.4.5.5 4,590.30
PEKERJAAN PEMASANGAN AKSESORIS PIPA
1 Pemasangan Valve dia. 50 - 150 mm BH AHSP PU A.8.4.3.1 237,424.00
2 Pemasangan Valve dia. 200 mm BH AHSP PU A.8.4.3.2 284,647.00
3 Pemasangan Accessories dia. 50 - 150 mm BH AHSP PU A.8.4.3.15 17,655.00
4 Pemasangan Accessories dia. 200 mm BH AHSP PU A.8.4.3.16 35,926.00
5 Pemasangan Accessories dia. 250 mm BH AHSP PU A.8.4.3.17 54,197.00
6 Pemasangan Accessories dia. 300 mm BH AHSP PU A.8.4.3.18 72,468.00
PEKERJAAN PENYAMBUNGAN PIPA BARU KE PIPA LAMA
1 Penyambungan Pipa Baru Ke Pipa Lama dia. 80 mm Titik AHSP PU A.8.4.4.1 274,901.00
2 Penyambungan Pipa Baru Ke Pipa Lama dia. 100 mm Titik AHSP PU A.8.4.4.2 309,199.00
3 Penyambungan Pipa Baru Ke Pipa Lama dia. 150 mm Titik AHSP PU A.8.4.4.3 389,994.00
4 Penyambungan Pipa Baru Ke Pipa Lama dia. 200 mm Titik AHSP PU A.8.4.4.4 470,789.00
5 Penyambungan Pipa Baru Ke Pipa Lama dia. 250 mm Titik AHSP PU A.8.4.4.5 551,584.00
PEKERJAAN PENGECATAN
1 Pengecatan Pipa M2 AHSP PU A.4.7.1.20 150,535.00
PEKERJAAN ACCESSORIS LAINNYA
1 Pemasangan Baja Profil Kg AHSP PU A.4.2.1.1 45,320.00
2 Lps. Pond. Ag. Kls. A (LPA) M2 Analisa EI-421.1 317,664.60
3 Lps. Pond. Ag. Kls. B (LPB) M3 Analisa EI-422.1 310,824.80
4 Lapis Resap Perekat (Prime Coat) M3 Analisa EI-427.A 31,420.40
5 Bongkaran Aspal Hotmix dan Beton M2 Analisa EI-428.A 90,200.00
6 Pembongkaran Beton M3 Analisa EI-7152 110,891.00
7 Laston Lapis Aus (AC-WC) M3 Analisa EI 635a 1,899,561.13
8 Borring Pipa Horizontal dia. 50 - 200 mm M' Analisa B.1 676,934.50
II PEKERJAAN GALIAN
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Galian Tanah Biasa Sedalam 1 Meter
Satuan / Unit : M3
Analisa : AHSP PU A.2.3.1.1
Jumlah Bahan
C PERALATAN
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 70,250.00
E Overhead & Profit 10.00 % x D 7,025.00
F Harga Satuan Pekerjaan (D+E) 77,275.00
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Galian Tanah Keras Sedalam 1 Meter
Satuan / Unit : M3
Analisa : AHSP PU A.2.3.1.4
A TENAGA
1 Pekerja Galian Tanah OH 1.0000 90,000.00 90,000.00
2 Mandor OH 0.0320 110,000.00 3,520.00
Jumlah Tenaga Kerja 93,520.00
B BAHAN
Jumlah Bahan
C PERALATAN
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 93,520.00
E Overhead & Profit 10.00 % x D 9,352.00
F Harga Satuan Pekerjaan (D+E) 102,872.00
Jumlah Bahan
C PERALATAN
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 31,663.00
E Overhead & Profit 10.00 % x D 3,166.30
F Harga Satuan Pekerjaan (D+E) 34,829.30
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Urugan Pasir
Satuan / Unit : M3
Analisa : AHSP PU A.2.3.1.11
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 136,100.00
E Overhead & Profit 10.00 % x D 13,610.00
F Harga Satuan Pekerjaan (D+E) 149,710.00
Jumlah Bahan -
C PERALATAN
1 Pemadat Timbunan (Stamper) Sewa-Hari 0.0500 80,000.00 4,000.00
Jumlah Peralatan 4,000.00
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 54,500.00
E Overhead & Profit 10.00 % x D 5,450.00
F Harga Satuan Pekerjaan (D+E) 59,950.00
Jumlah Peralatan
` D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 79,280.00
E Overhead & Profit 10.00 % x D 7,928.00
F Harga Satuan Pekerjaan (D+E) 87,208.00
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Beton Mutu F'c = 21,7 Mpa (K 250), Slump (12 ± 2) cm, W/c = 0,56
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.8
A TENAGA
1 Pekerja OH 0.0080 90,000.00 720.00
4 Mandor OH 0.0008 110,000.00 88.00
Jumlah Tenaga Kerja 808.00
B BAHAN
1 Air Bersih Untuk Pengetesan M3 0.0040 85,000.00 340.00
2 Bahan Bakar Solar Liter 0.0600 12,000.00 720.00
3 Oli Liter 0.0020 5,000.00 10.00
Jumlah Bahan 1,070.00
C PERALATAN
-
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 1,878.00
E Overhead & Profit 10.00 % x D 187.80
F Harga Satuan Pekerjaan (D+E) 2,065.80
A TENAGA
1 Pekerja OH 0.0080 90,000.00 720.00
4 Mandor OH 0.0008 110,000.00 88.00
Jumlah Tenaga Kerja 808.00
B BAHAN
1 Air Bersih Untuk Pengetesan M3 0.0080 85,000.00 680.00
2 Bahan Bakar Solar Liter 0.0600 12,000.00 720.00
3 Oli Liter 0.0020 5,000.00 10.00
Jumlah Bahan 1,410.00
C PERALATAN
-
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 2,218.00
E Overhead & Profit 10.00 % x D 221.80
F Harga Satuan Pekerjaan (D+E) 2,439.80
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pengetesan Pipa dia. 150 mm
Satuan / Unit : M1
Analisa : AHSP PU A.8.4.5.4
A TENAGA
1 Pekerja OH 0.0080 90,000.00 720.00
4 Mandor OH 0.0008 110,000.00 88.00
Jumlah Tenaga Kerja 808.00
B BAHAN
1 Air Bersih Untuk Pengetesan M3 0.0180 85,000.00 1,530.00
2 Bahan Bakar Solar Liter 0.0600 12,000.00 720.00
3 Oli Liter 0.0020 5,000.00 10.00
Jumlah Bahan 2,260.00
C PERALATAN
-
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 3,068.00
E Overhead & Profit 10.00 % x D 306.80
F Harga Satuan Pekerjaan (D+E) 3,374.80
A TENAGA
1 Pekerja OH 1.0000 90,000.00 90,000.00
2 Operator OH 3.0000 150,000.00 450,000.00
3 Mandor OH 0.1000 110,000.00 11,000.00
Jumlah Tenaga Kerja 551,000.00
B BAHAN
1 Solar Liter 2.4500 12,000.00 29,400.00
A TENAGA
1 Pekerja OH 0.0300 90,000.00 2,700.00
2 Mandor OH 0.0060 110,000.00 660.00
Jumlah Tenaga Kerja 3,360.00
B BAHAN
1 Aspal Kg 0.6340 25,000.00 15,850.00
2 Korosen Ltr 0.4840 8,500.00 4,114.00
Jumlah Bahan 19,964.00
C PERALATAN
1 Dump Truck Jam 0.0030 80,000.00 240.00
2 Alat Bantu Jam 1.0000 5,000.00 5,000.00
Jumlah Peralatan 5,240.00
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 28,564.00
E Overhead & Profit 10.00 % x D 2,856.40
F Harga Satuan Pekerjaan (D+E) 31,420.40
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Bongkaran Aspal Hotmix dan Beton
Satuan / Unit : M2
Analisa : Analisa El-428.A
A TENAGA
1 Pekerja OH 0.2000 90,000.00 18,000.00
2 Mandor OH 0.2000 110,000.00 22,000.00
Jumlah Tenaga Kerja 40,000.00
B BAHAN
1 Solar Liter 1.0000 12,000.00 12,000.00
Jumlah Bahan 12,000.00
C PERALATAN
1 Sewa Jack Hammer dan Mesin Cutter Jam 0.2500 120,000.00 30,000.00
Jumlah Peralatan 30,000.00
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 82,000.00
E Overhead & Profit 10.00 % x D 8,200.00
F Harga Satuan Pekerjaan (D+E) 90,200.00
Jumlah Bahan -
C PERALATAN
1 - -
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 215,840.00
E Overhead & Profit 10.00 % x D 21,584.00
F Harga Satuan Pekerjaan (D+E) 237,424.00
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pemasangan Accessories dia. 200 mm
Accessories Mekanik (Gate Valve, Water Meter, Chek Valve, Butterfly Valve)
Satuan / Unit : 1 Buah
Analisa : AHSP PU A.8.4.3.2
A TENAGA
1 Pekerja OH 1.7140 90,000.00 154,260.00
2 Tukang OH 0.8570 100,000.00 85,700.00
3 Mandor OH 0.1710 110,000.00 18,810.00
Jumlah Tenaga Kerja 258,770.00
B BAHAN
Jumlah Bahan -
C PERALATAN
1
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 258,770.00
E Overhead & Profit 10.00 % x D 25,877.00
F Harga Satuan Pekerjaan (D+E) 284,647.00
Jumlah Bahan -
C PERALATAN
1 - -
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 16,050.00
E Overhead & Profit 10.00 % x D 1,605.00
F Harga Satuan Pekerjaan (D+E) 17,655.00
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pemasangan Accesories dia. 200 mm
Accessories Statis (Bend, Tee, Reducer, Flange Socket, Flange Spigot, Valve Socket
Repair Socket, Gibolt Joint, Clamp Sadle)
Satuan / Unit : 1 Buah
Analisa : AHSP PU A.8.4.3.16
A TENAGA
1 Pekerja OH 0.2160 90,000.00 19,440.00
2 Tukang OH 0.1080 100,000.00 10,800.00
3 Mandor OH 0.0220 110,000.00 2,420.00
Jumlah Tenaga Kerja 32,660.00
B BAHAN
Jumlah Bahan -
C PERALATAN
1 -
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 32,660.00
E Overhead & Profit 10.00 % x D 3,266.00
F Harga Satuan Pekerjaan (D+E) 35,926.00
A TENAGA
1 Pekerja OH 0.3260 90,000.00 29,340.00
2 Tukang OH 0.1630 100,000.00 16,300.00
3 Mandor OH 0.0330 110,000.00 3,630.00
Jumlah Tenaga Kerja 49,270.00
B BAHAN
Jumlah Bahan -
C PERALATAN
1 -
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 49,270.00
E Overhead & Profit 10.00 % x D 4,927.00
F Harga Satuan Pekerjaan (D+E) 54,197.00
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pemasangan Accesories dia. 300 mm
Accessories Statis (Bend, Tee, Reducer, Flange Socket, Flange Spigot, Valve Socket
Repair Socket, Gibolt Joint, Clamp Sadle)
Satuan / Unit : 1 Buah
Analisa : AHSP PU A.8.4.3.18
A TENAGA
1 Pekerja OH 0.4360 90,000.00 39,240.00
2 Tukang OH 0.2180 100,000.00 21,800.00
3 Mandor OH 0.0440 110,000.00 4,840.00
Jumlah Tenaga Kerja 65,880.00
B BAHAN
Jumlah Bahan -
C PERALATAN
1 -
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 65,880.00
E Overhead & Profit 10.00 % x D 6,588.00
F Harga Satuan Pekerjaan (D+E) 72,468.00
Jumlah Bahan -
C PERALATAN
Peralatan Potong Pipa T2/Mekanik/Cli Hari 0.6500 50,000.00 32,500.00
Jumlah Peralatan 32,500.00
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 281,090.00
E Overhead & Profit 10.00 % x D 28,109.00
F Harga Satuan Pekerjaan (D+E) 309,199.00
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pengelasan Pipa Steel dia. 100 mm
Satuan / Unit : Titik
Analisa : Anl. L.3
A TENAGA
1 Pekerja OH 0.2760 90,000.00 24,840.00
2 Tukang OH 0.1380 100,000.00 13,800.00
3 Kepala Tukang OH 0.0140 120,000.00 1,680.00
4 Mandor OH 0.0140 110,000.00 1,540.00
Jumlah Tenaga Kerja 41,860.00
B BAHAN
1 Kawat Las Listrik Kg 2.7560 25,000.00 68,900.00
2 Solar Liter 2.0670 12,000.00 24,804.00
3 Minyak Pelumas Liter 0.2760 5,000.00 1,380.00
Jumlah Bahan 95,084.00
C PERALATAN
1 Sewa Mesin Las Jam 0.1171 10,625.00 1,244.19
Jumlah Peralatan 1,244.19
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 138,188.19
E Overhead & Profit 10.00 % x D 13,818.82
F Harga Satuan Pekerjaan (D+E) 152,007.01
A TENAGA
1 Pekerja OH 0.4010 90,000.00 36,090.00
2 Tukang OH 0.2010 100,000.00 20,100.00
3 Kepala Tukang OH 0.0200 120,000.00 2,400.00
4 Mandor OH 0.0200 110,000.00 2,200.00
Jumlah Tenaga Kerja 60,790.00
B BAHAN
1 Kawat Las Listrik Kg 4.0120 25,000.00 100,300.00
2 Solar Liter 3.0090 12,000.00 36,108.00
3 Minyak Pelumas Liter 0.4010 5,000.00 2,005.00
Jumlah Bahan 138,413.00
C PERALATAN
1 Sewa Mesin Las Jam 0.1705 10,625.00 1,811.56
Jumlah Peralatan 1,811.56
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 201,014.56
E Overhead & Profit 10.00 % x D 20,101.46
F Harga Satuan Pekerjaan (D+E) 221,116.02
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pengelasan Pipa Steel dia. 200 mm
Satuan / Unit : Titik
Analisa : Anl. L.5
A TENAGA
1 Pekerja OH 0.5280 90,000.00 47,520.00
2 Tukang OH 0.2640 100,000.00 26,400.00
3 Kepala Tukang OH 0.0260 120,000.00 3,120.00
4 Mandor OH 0.0260 110,000.00 2,860.00
Jumlah Tenaga Kerja 79,900.00
B BAHAN
1 Kawat Las Listrik Kg 5.2750 25,000.00 131,875.00
2 Solar Liter 3.9560 12,000.00 47,472.00
3 Minyak Pelumas Liter 0.5280 5,000.00 2,640.00
Jumlah Bahan 181,987.00
C PERALATAN
1 Sewa Mesin Las Jam 0.2242 10,625.00 2,382.13
Jumlah Peralatan 2,382.13
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 264,269.13
E Overhead & Profit 10.00 % x D 26,426.91
F Harga Satuan Pekerjaan (D+E) 290,696.04
A TENAGA
1 Pekerja OH 0.2090 90,000.00 18,810.00
2 Tukang OH 0.1040 100,000.00 10,400.00
3 Kepala Tukang OH 0.0100 120,000.00 1,200.00
4 Mandor OH 0.0100 110,000.00 1,100.00
Jumlah Tenaga Kerja 31,510.00
B BAHAN
1 Kawat Las Listrik Kg 2.0870 25,000.00 52,175.00
2 Solar Liter 1.5660 12,000.00 18,792.00
3 Minyak Pelumas Liter 0.2090 5,000.00 1,045.00
Jumlah Bahan 72,012.00
C PERALATAN
1 Sewa Mesin Las Jam 0.0887 10,625.00 942.44
Jumlah Peralatan 942.44
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 104,464.44
E Overhead & Profit 10.00 % x D 10,446.44
F Harga Satuan Pekerjaan (D+E) 114,910.88
A TENAGA
1 Pekerja OH 1.4460 90,000.00 130,140.00
2 Tukang OH 0.7330 100,000.00 73,300.00
3 Mandor OH 0.1470 110,000.00 16,170.00
Jumlah Tenaga Kerja 219,610.00
B BAHAN
Jumlah Bahan -
C PERALATAN
Peralatan Potong Pipa T2/Mekanik/Cli Hari 0.6060 50,000.00 30,300.00
Jumlah Peralatan 30,300.00
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 249,910.00
E Overhead & Profit 10.00 % x D 24,991.00
F Harga Satuan Pekerjaan (D+E) 274,901.00
A TENAGA
1 Pekerja OH 2.0960 90,000.00 188,640.00
2 Tukang OH 1.0480 100,000.00 104,800.00
3 Mandor OH 0.2100 110,000.00 23,100.00
Jumlah Tenaga Kerja 316,540.00
B BAHAN
Jumlah Bahan -
C PERALATAN
Peralatan Potong Pipa T2/Mekanik/Cli Hari 0.7600 50,000.00 38,000.00
Jumlah Peralatan 38,000.00
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 354,540.00
E Overhead & Profit 10.00 % x D 35,454.00
F Harga Satuan Pekerjaan (D+E) 389,994.00
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Penyambungan Pipa Baru ke Pipa Lama dia. 200 mm
Satuan / Unit : 1 Buah
Analisa : AHSP PU A.8.4.4.4
A TENAGA
1 Pekerja OH 2.5460 90,000.00 229,140.00
2 Tukang OH 1.2730 100,000.00 127,300.00
3 Mandor OH 0.2550 110,000.00 28,050.00
Jumlah Tenaga Kerja 384,490.00
B BAHAN
Jumlah Bahan -
C PERALATAN
Peralatan Potong Pipa T2/Mekanik/Cli Hari 0.8700 50,000.00 43,500.00
Jumlah Peralatan 43,500.00
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 427,990.00
E Overhead & Profit 10.00 % x D 42,799.00
F Harga Satuan Pekerjaan (D+E) 470,789.00
A TENAGA
1 Pekerja OH 2.9960 90,000.00 269,640.00
2 Tukang OH 1.4980 100,000.00 149,800.00
3 Mandor OH 0.3000 110,000.00 33,000.00
Jumlah Tenaga Kerja 452,440.00
B BAHAN
Jumlah Bahan -
C PERALATAN
Peralatan Potong Pipa T2/Mekanik/Cli Hari 0.9800 50,000.00 49,000.00
Jumlah Peralatan 49,000.00
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 501,440.00
E Overhead & Profit 10.00 % x D 50,144.00
F Harga Satuan Pekerjaan (D+E) 551,584.00
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pemasangan Baja Profil
Satuan / Unit : Kg
Analisa : AHSP PU A.4.2.1.1
Jumlah Bahan -
C PERALATAN
-
Jumlah Peralatan -
` Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 12,450.00
E Overhead & Profit 10.00 % x D 1,245.00
F Harga Satuan Pekerjaan (D+E) 13,695.00
A TENAGA
1 Pekerja OH 1.1130 90,000.00 100,170.00
2 Tukang OH 0.2230 100,000.00 22,300.00
3 Mandor OH 0.1110 110,000.00 12,210.00
Jumlah Tenaga Kerja 134,680.00
B BAHAN
Jumlah Bahan -
C PERALATAN
-
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 134,680.00
E Overhead & Profit 10.00 % x D 13,468.00
F Harga Satuan Pekerjaan (D+E) 148,148.00
A TENAGA
1 Pekerja OH 0.7080 90,000.00 63,720.00
2 Tukang OH 0.1420 100,000.00 14,200.00
3 Mandor OH 0.0710 110,000.00 7,810.00
Jumlah Tenaga Kerja 85,730.00
B BAHAN
Jumlah Bahan -
C PERALATAN
-
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 85,730.00
E Overhead & Profit 10.00 % x D 8,573.00
F Harga Satuan Pekerjaan (D+E) 94,303.00
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pemotongan Pipa Steel dia. 200 mm
Satuan / Unit : Bh
Analisa : AHSP PU A.8.4.2.68
A TENAGA
1 Pekerja OH 0.5790 90,000.00 52,110.00
2 Tukang OH 0.1160 100,000.00 11,600.00
3 Mandor OH 0.0580 110,000.00 6,380.00
Jumlah Tenaga Kerja 70,090.00
B BAHAN
Jumlah Bahan -
C PERALATAN
-
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 70,090.00
E Overhead & Profit 10.00 % x D 7,009.00
F Harga Satuan Pekerjaan (D+E) 77,099.00
A TENAGA
1 Pekerja OH 0.4990 90,000.00 44,910.00
2 Tukang OH 0.1000 100,000.00 10,000.00
3 Mandor OH 0.0500 110,000.00 5,500.00
Jumlah Tenaga Kerja 60,410.00
B BAHAN
Jumlah Bahan -
C PERALATAN
-
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 60,410.00
E Overhead & Profit 10.00 % x D 6,041.00
F Harga Satuan Pekerjaan (D+E) 66,451.00
A TENAGA
1 Pekerja OH 0.5390 90,000.00 48,510.00
2 Tukang OH 0.1080 100,000.00 10,800.00
3 Mandor OH 0.0540 110,000.00 5,940.00
Jumlah Tenaga Kerja 65,250.00
B BAHAN
Jumlah Bahan -
C PERALATAN
-
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 65,250.00
E Overhead & Profit 10.00 % x D 6,525.00
F Harga Satuan Pekerjaan (D+E) 71,775.00
A TENAGA
1 Pekerja OH 0.1540 90,000.00 13,860.00
2 Mandor OH 0.0220 110,000.00 2,420.00
Jumlah Tenaga Kerja 16,280.00
B BAHAN
1 Aggregat Kasar M3 0.6600 200,000.00 132,000.00
2 Agregat Halus M3 0.5400 230,000.00 124,200.00
Jumlah Bahan 256,200.00
C PERALATAN
1 Wheel Loader Jam 0.0178 180,000.00 3,204.00
2 Dump Truck Jam 0.0820 80,000.00 6,560.00
3 Stamper Jam 0.1542 10,000.00 1,542.00
4 Alat Bantu Hari 1.0000 5,000.00 5,000.00
Jumlah Peralatan 16,306.00
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 288,786.00
E Overhead & Profit 10.00 % x D 28,878.60
F Harga Satuan Pekerjaan (D+E) 317,664.60
A TENAGA
1 Pekerja OH 0.1450 90,000.00 13,050.00
2 Mandor OH 0.0210 110,000.00 2,310.00
Jumlah Tenaga Kerja 15,360.00
B BAHAN
1 Aggregat Kasar M3 0.4200 200,000.00 84,000.00
2 Agregat Halus M3 0.2400 230,000.00 55,200.00
3 Pasir Batu (Sirtu) Material Jalan M3 0.5400 200,000.00 108,000.00
Jumlah Bahan 247,200.00
C PERALATAN
1 Wheel Loader Jam 0.0178 180,000.00 3,204.00
2 Dump Truck Jam 0.0820 80,000.00 6,560.00
3 Stamper Jam 0.1446 10,000.00 1,446.00
4 Water Tanker Jam 0.0211 180,000.00 3,798.00
5 Alat Bantu Hari 1.0000 5,000.00 5,000.00
Jumlah Peralatan 20,008.00
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 282,568.00
E Overhead & Profit 10.00 % x D 28,256.80
F Harga Satuan Pekerjaan (D+E) 310,824.80
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Laston Lapis Aus (AC-WC)
Satuan / Unit : M3
Analisa : Analisa EI 635a
A TENAGA
1 Pekerja OH 0.2410 90,000.00 21,690.00
2 Mandor OH 0.0241 110,000.00 2,651.00
Jumlah Tenaga Kerja 24,341.00
B BAHAN
1 Lolos screen2 ukuran ( 9.5 - 19,0) M3 0.2978 200,000.00 59,560.00
2 Lolos screen2 ukuran ( 0 - 5) M3 0.3513 230,000.00 80,799.00
3 Semen Kg 12.4900 1,375.00 17,173.75
4 Aspal Kg 61.8000 25,000.00 1,545,000.00
Jumlah Bahan 1,702,532.75
C PERALATAN
1 -
2 -
3 -
4 -
5 -
6 -
Jumlah Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 1,726,873.75
E Overhead & Profit 10.00 % x D 172,687.38
F Harga Satuan Pekerjaan (D+E) 1,899,561.13
SAIFULLAH, SE
Direktur
Memasang 1 M'ANALISA
pipa HDPEHARGA SATUAN PEKERJAAN
dia. 50 mm
Jenis Pekerjaan :
Satuan / Unit : M'
Analisa : AHSP PU A.8.1.17
Memasang 1 M'ANALISA
pipa HDPEHARGA SATUAN PEKERJAAN
dia. 75 mm
Jenis Pekerjaan :
Satuan / Unit : M'
Analisa : AHSP PU A.8.1.17.a
Jumlah Bahan
C PERALATAN
1 Alat Bantu Ls 1.0000
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
II PEKERJAAN GALIAN
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Galian Tanah Biasa Sedalam 1 Meter
Satuan / Unit : M3
Analisa : AHSP PU A.2.3.1.1
Jumlah Bahan
C PERALATAN
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Galian Tanah Keras Sedalam 1 Meter
Satuan / Unit : M3
Analisa : AHSP PU A.2.3.1.4
A TENAGA
1 Pekerja Galian Tanah OH 1.0000
2 Mandor OH 0.0320
Jumlah Tenaga Kerja
B BAHAN
Jumlah Bahan
C PERALATAN
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
Jumlah Bahan
C PERALATAN
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Urugan Pasir
Satuan / Unit : M3
Analisa : AHSP PU A.2.3.1.11
Jumlah Bahan
C PERALATAN
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
Jumlah Bahan
C PERALATAN
1 Pemadat Timbunan (Stamper) Sewa-Hari 0.0500
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
Jumlah Peralatan
` D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Beton Mutu F'c = 21,7 Mpa (K 250), Slump (12 ± 2) cm, W/c = 0,56
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.8
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Beton Mutu F¹C = 14,5 Mpa (K-175) Slump (12±2) cm, W/c = 0,66
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.5
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
Jumlah Bahan
C PERALATAN
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
Per Kg Pembesian = D / 10
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pemasangan 1 m pipa HDPE Ø 90 mm
Satuan / Unit : M1
Analisa : AHSP PU A.8.4.1.17
Jumlah Bahan
C PERALATAN
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pengetesan Pipa dia. 75 mm
Satuan / Unit : M1
Analisa : AHSP PU A.8.4.5.2
A TENAGA
1 Pekerja OH 0.0080
4 Mandor OH 0.0008
Jumlah Tenaga Kerja
B BAHAN
1 Air Bersih Untuk Pengetesan M3 0.0040
2 Bahan Bakar Solar Liter 0.0600
3 Oli Liter 0.0020
Jumlah Bahan
C PERALATAN
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
A TENAGA
1 Pekerja OH 0.0080
4 Mandor OH 0.0008
Jumlah Tenaga Kerja
B BAHAN
1 Air Bersih Untuk Pengetesan M3 0.0080
2 Bahan Bakar Solar Liter 0.0600
3 Oli Liter 0.0020
Jumlah Bahan
C PERALATAN
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pengetesan Pipa dia. 150 mm
Satuan / Unit : M1
Analisa : AHSP PU A.8.4.5.4
A TENAGA
1 Pekerja OH 0.0080
4 Mandor OH 0.0008
Jumlah Tenaga Kerja
B BAHAN
1 Air Bersih Untuk Pengetesan M3 0.0180
2 Bahan Bakar Solar Liter 0.0600
3 Oli Liter 0.0020
Jumlah Bahan
C PERALATAN
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Borring Pipa Horizontal dia. 50 - 200 mm
Satuan / Unit : M'
Analisa : Analisa B.1
A TENAGA
1 Pekerja OH 1.0000
2 Operator OH 3.0000
3 Mandor OH 0.1000
Jumlah Tenaga Kerja
B BAHAN
1 Solar Liter 2.4500
Jumlah Bahan
C PERALATAN
1 Water Pump 4" Jam 2.3330
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
A TENAGA
1 Pekerja OH 0.0300
2 Mandor OH 0.0060
Jumlah Tenaga Kerja
B BAHAN
1 Aspal Kg 0.6340
2 Korosen Ltr 0.4840
Jumlah Bahan
C PERALATAN
1 Dump Truck Jam 0.0030
2 Alat Bantu Jam 1.0000
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Bongkaran Aspal Hotmix dan Beton
Satuan / Unit : M2
Analisa : Analisa El-428.A
A TENAGA
1 Pekerja OH 0.2000
2 Mandor OH 0.2000
Jumlah Tenaga Kerja
B BAHAN
1 Solar Liter 1.0000
Jumlah Bahan
C PERALATAN
1 Sewa Jack Hammer dan Mesin Cutter Jam 0.2500
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
Jumlah Bahan
C PERALATAN
1
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pemasangan Accessories dia. 200 mm
Accessories Mekanik (Gate Valve, Water Meter, Chek Valve, Butterfly Valve)
Satuan / Unit : 1 Buah
Analisa : AHSP PU A.8.4.3.2
A TENAGA
1 Pekerja OH 1.7140
2 Tukang OH 0.8570
3 Mandor OH 0.1710
Jumlah Tenaga Kerja
B BAHAN
Jumlah Bahan
C PERALATAN
1
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
Jumlah Bahan
C PERALATAN
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pemasangan Accesories dia. 200 mm
Accessories Statis (Bend, Tee, Reducer, Flange Socket, Flange Spigot, Valve Socket
Repair Socket, Gibolt Joint, Clamp Sadle)
Satuan / Unit : 1 Buah
Analisa : AHSP PU A.8.4.3.16
A TENAGA
1 Pekerja OH 0.2160
2 Tukang OH 0.1080
3 Mandor OH 0.0220
Jumlah Tenaga Kerja
B BAHAN
Jumlah Bahan
C PERALATAN
1
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
A TENAGA
1 Pekerja OH 0.3260
2 Tukang OH 0.1630
3 Mandor OH 0.0330
Jumlah Tenaga Kerja
B BAHAN
Jumlah Bahan
C PERALATAN
1
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pemasangan Accesories dia. 300 mm
Accessories Statis (Bend, Tee, Reducer, Flange Socket, Flange Spigot, Valve Socket
Repair Socket, Gibolt Joint, Clamp Sadle)
Satuan / Unit : 1 Buah
Analisa : AHSP PU A.8.4.3.18
A TENAGA
1 Pekerja OH 0.4360
2 Tukang OH 0.2180
3 Mandor OH 0.0440
Jumlah Tenaga Kerja
B BAHAN
Jumlah Bahan
C PERALATAN
1
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
Jumlah Bahan
C PERALATAN
Peralatan Potong Pipa T2/Mekanik/Clinder Saw Hari 0.6500
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pengelasan Pipa Steel dia. 100 mm
Satuan / Unit : Titik
Analisa : Anl. L.3
A TENAGA
1 Pekerja OH 0.2760
2 Tukang OH 0.1380
3 Kepala Tukang OH 0.0140
4 Mandor OH 0.0140
Jumlah Tenaga Kerja
B BAHAN
1 Kawat Las Listrik Kg 2.7560
2 Solar Liter 2.0670
3 Minyak Pelumas Liter 0.2760
Jumlah Bahan
C PERALATAN
1 Sewa Mesin Las Jam 0.1171
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
A TENAGA
1 Pekerja OH 0.4010
2 Tukang OH 0.2010
3 Kepala Tukang OH 0.0200
4 Mandor OH 0.0200
Jumlah Tenaga Kerja
B BAHAN
1 Kawat Las Listrik Kg 4.0120
2 Solar Liter 3.0090
3 Minyak Pelumas Liter 0.4010
Jumlah Bahan
C PERALATAN
1 Sewa Mesin Las Jam 0.1705
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pengelasan Pipa Steel dia. 200 mm
Satuan / Unit : Titik
Analisa : Anl. L.5
A TENAGA
1 Pekerja OH 0.5280
2 Tukang OH 0.2640
3 Kepala Tukang OH 0.0260
4 Mandor OH 0.0260
Jumlah Tenaga Kerja
B BAHAN
1 Kawat Las Listrik Kg 5.2750
2 Solar Liter 3.9560
3 Minyak Pelumas Liter 0.5280
Jumlah Bahan
C PERALATAN
1 Sewa Mesin Las Jam 0.2242
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
A TENAGA
1 Pekerja OH 0.2090
2 Tukang OH 0.1040
3 Kepala Tukang OH 0.0100
4 Mandor OH 0.0100
Jumlah Tenaga Kerja
B BAHAN
1 Kawat Las Listrik Kg 2.0870
2 Solar Liter 1.5660
3 Minyak Pelumas Liter 0.2090
Jumlah Bahan
C PERALATAN
1 Sewa Mesin Las Jam 0.0887
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
A TENAGA
1 Pekerja OH 1.4460
2 Tukang OH 0.7330
3 Mandor OH 0.1470
Jumlah Tenaga Kerja
B BAHAN
Jumlah Bahan
C PERALATAN
Peralatan Potong Pipa T2/Mekanik/Clinder Saw Hari 0.6060
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
A TENAGA
1 Pekerja OH 2.0960
2 Tukang OH 1.0480
3 Mandor OH 0.2100
Jumlah Tenaga Kerja
B BAHAN
Jumlah Bahan
C PERALATAN
Peralatan Potong Pipa T2/Mekanik/Clinder Saw Hari 0.7600
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Penyambungan Pipa Baru ke Pipa Lama dia. 200 mm
Satuan / Unit : 1 Buah
Analisa : AHSP PU A.8.4.4.4
A TENAGA
1 Pekerja OH 2.5460
2 Tukang OH 1.2730
3 Mandor OH 0.2550
Jumlah Tenaga Kerja
B BAHAN
Jumlah Bahan
C PERALATAN
Peralatan Potong Pipa T2/Mekanik/Clinder Saw Hari 0.8700
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
A TENAGA
1 Pekerja OH 2.9960
2 Tukang OH 1.4980
3 Mandor OH 0.3000
Jumlah Tenaga Kerja
B BAHAN
Jumlah Bahan
C PERALATAN
Peralatan Potong Pipa T2/Mekanik/Clinder Saw Hari 0.9800
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pemasangan Baja Profil
Satuan / Unit : Kg
Analisa : AHSP PU A.4.2.1.1
Jumlah Bahan
C PERALATAN
Jumlah Peralatan
` Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Memasang 1 M' Pipa Steel dia. 200 mm
Satuan / Unit : M'
Analisa : AHSP PU A.8.4.1.68
A TENAGA
1 Pekerja OH 1.1130
2 Tukang OH 0.2230
3 Mandor OH 0.1110
Jumlah Tenaga Kerja
B BAHAN
Jumlah Bahan
C PERALATAN
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
A TENAGA
1 Pekerja OH 0.7080
2 Tukang OH 0.1420
3 Mandor OH 0.0710
Jumlah Tenaga Kerja
B BAHAN
Jumlah Bahan
C PERALATAN
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pemotongan Pipa Steel dia. 200 mm
Satuan / Unit : Bh
Analisa : AHSP PU A.8.4.2.68
A TENAGA
1 Pekerja OH 0.5790
2 Tukang OH 0.1160
3 Mandor OH 0.0580
Jumlah Tenaga Kerja
B BAHAN
Jumlah Bahan
C PERALATAN
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
A TENAGA
1 Pekerja OH 0.5390
2 Tukang OH 0.1080
3 Mandor OH 0.0540
Jumlah Tenaga Kerja
B BAHAN
Jumlah Bahan
C PERALATAN
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
A TENAGA
1 Pekerja OH 0.1540
2 Mandor OH 0.0220
Jumlah Tenaga Kerja
B BAHAN
1 Aggregat Kasar M3 0.6600
2 Agregat Halus M3 0.5400
Jumlah Bahan
C PERALATAN
1 Wheel Loader Jam 0.0178
2 Dump Truck Jam 0.0820
3 Stamper Jam 0.1542
4 Alat Bantu Hari 1.0000
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
A TENAGA
1 Pekerja OH 0.1450
2 Mandor OH 0.0210
Jumlah Tenaga Kerja
B BAHAN
1 Aggregat Kasar M3 0.4200
2 Agregat Halus M3 0.2400
3 Pasir Batu (Sirtu) Material Jalan M3 0.5400
Jumlah Bahan
C PERALATAN
1 Wheel Loader Jam 0.0178
2 Dump Truck Jam 0.0820
3 Stamper Jam 0.1446
4 Water Tanker Jam 0.0211
5 Alat Bantu Hari 1.0000
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Laston Lapis Aus (AC-WC)
Satuan / Unit : M3
Analisa : Analisa EI 635a
A TENAGA
1 Pekerja OH 0.2410
2 Mandor OH 0.0241
Jumlah Tenaga Kerja
B BAHAN
1 Lolos screen2 ukuran ( 9.5 - 19,0) M3 0.2978
2 Lolos screen2 ukuran ( 0 - 5) M3 0.3513
3 Semen Kg 12.4900
4 Aspal Kg 61.8000
Jumlah Bahan
C PERALATAN
1
2
3
4
5
6
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
SAIFULLAH, SE
Direktur
MemasangANALISA HARGA
1 M' pipa HDPE SATUAN
dia. 50 mm PEKERJAAN
Jenis Pekerjaan :
Satuan / Unit : M'
Analisa : AHSP PU A.8.1.17
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
MemasangANALISA HARGA
1 M' pipa HDPE SATUAN
dia. 75 mm PEKERJAAN
Jenis Pekerjaan :
Satuan / Unit : M'
Analisa : AHSP PU A.8.1.17.a
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
MemasangANALISA HARGA
1 M' pipa HDPE SATUAN
dia. 100 mm PEKERJAAN
Jenis Pekerjaan :
Satuan / Unit : M'
Analisa : AHSP PU A.8.1.18
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Memasang 1 M' pipa HDPE dia. 200 mm
Satuan / Unit : M'
Analisa : AHSP PU A.8.1.21
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Memasang 1 M' pipa HDPE dia. 300 mm
Satuan / Unit : M'
Analisa : AHSP PU A.8.1.23
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Memasang 1 M' pipa HDPE dia. 400 mm
Satuan / Unit : M'
Analisa : AHSP PU A.8.1.24
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
Jumlah Bahan
C PERALATAN
Sewa Jack Hammer Jam 0.2500
Sewa compressor Jam -
Sewa mesin cutter Jam 0.2500
Jumlah Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C)
E Overhead & Profit 10.00 % x D
F Harga Satuan Pekerjaan (D+E)
HARGA SATUAN
NO U R A I A N SATUAN ( Rp. )
I. UPAH
1 Pekerja Galian Tanah OH 90,000.00
2 Pekerja OH 90,000.00
3 Tukang OH 100,000.00
4 Kepala Tukang OH 120,000.00
5 Mandor OH 110,000.00
6 Penjaga Malam OH 120,000.00
7 Supir OH 100,000.00
8 Operator OH 150,000.00
9 Pembantu Operator OH 120,000.00
10 Pembantu Juru Ukur OH 80,000.00
11 Juru Ukur OH 120,000.00
II. MATERIAL/BAHAN
1 Air M3 85,000.00
2 Air Liter 100.00
3 Agregat Kasar M3 200,000.00
4 Agregat Halus M3 230,000.00
5 Asphalt kg 25,000.00
6 Alat Bantu Ls 5,000.00
7 Baja Profil Kg 25,000.00
8 Bak Cuci Piring Logam bh 1,500,000.00
9 Batu Bata bh 550.00
10 Batu Kali/Batu Belah (Sungai/Gunung) M3 180,000.00
11 Bensin (Industri) Liter 12,000.00
12 Besi Beton Polos kg 13,000.00
13 Besi Beton Ulir kg 20,000.00
14 Beton Rooster/Kerawang bh 5,000.00
15 Bubungan Seng M' 15,000.00
16 Cat Kayu Dasar kg 35,000.00
17 Cat Kayu Mengkilat/Penutup kg 35,000.00
18 Cat Dasar Kg 45,000.00
19 Cat Penutup kg 45,000.00
20 Cat Tembok kg 40,000.00
21 Kayu kelas I M3 5,500,000.00
22 Kayu kelas I M3 4,800,000.00
23 Kayu kelas III M3 4,000,000.00
24 kawat Las Listrik Kg 25,000.00
25 kawat Beton Kg 15,000.00
26 Kerikil M3 110,000.00
27 Minyak Tanah/Kerosen Liter 8,500.00
28 Minyak Pelumas/Bekisting Liter 5,000.00
29 Flier Kg 3,600.00
30 Plastik Hitam M2 3,000.00
31 Pasir M3 100,000.00
32 Pasir Beton Kerikil M3 100,000.00
33 Pasir Pasang M3 100,000.00
34 Pasir Urug M3 90,000.00
35 Paku 5 cm - 10 cm Kg 15,000.00
36 Pengencer Liter 12,000.00
37 Pelumas/Olie Liter 5,000.00
38 Kuas Bh 38,000.00
39 Sirtu M3 200,000.00
40 Semen Andalas @ 40 Kg Zak 55,000.00
41 Semen Andalas @ 50 Kg Zak 80,000.00
42 Solar Non Subsidi Liter 12,000.00
HARGA SATUAN
NO U R A I A N SATUAN ( Rp. )
III. PERALATAN
1 Cylinder Saw/Mesin Potong Pipa Hari 50,000.00
2 Sewa Tripot/Tacket & hendle crane Hari 250,000.00
3 Mesin Las Hari 85,000.00
4 Mesin Penyambung HDPE/Butt Fusion Hari 75,000.00
5 Stamper Hari 80,000.00
6 Water Pass Hari 80,000.00
7 Theodolit Hari 80,000.00
8 Sewa Jack Hammer dan Mesin Cutter Jam 120,000.00
9 Sewa Aspalt Spayer Jam 150,000.00
10 Air kompresor Jam 60,000.00
11 Wheel Loader Jam 180,000.00
12 AMP Jam 250,000.00
13 Motor Greder Jam 250,000.00
14 Water Tanker Jam 180,000.00
15 Genset Jam 15,000.00
16 Dump Truck jam 80,000.00
17 Asphal Finisher jam 170,000.00
18 Tandem Roller jam 200,000.00
19 Penetrasi Roller Jam 230,000.00
20 P. Tyre Roller jam 200,000.00
21 Molen Beton 0,3 - 0,6 M3 jam 50,000.00
22 Water Pump Jam 15,000.00
SAIFULLAH, SE
Direktur
REKAPITULASI
PERKIRAAN HARGA PEKERJAAN
### : #REF!
### :
#REF!
### : #REF!
### : #REF!
Total Harga
No. URAIAN
(Rp)
I ### #REF!
II ### #REF!
III ### #REF!
IV ### #REF!
V ### #REF!
VI ### #REF!
Terbilang : #NAME?
SAIFULLAH, SE
Direktur
Galian Dan Urugan untuk Jaringan Pipa
Jaringan
Galian Tanah Panjang
Dia. Pipa
Penampan Ukuran Volume (M3) Pipa
g Pipa
Dalam Luar Urugan
Tinggi Lebar Galian M'
dia. 400 415 0.135 1.800 0.850 1.530 1.395
dia. 350 365 0.105 1.600 0.750 1.200 1.095
dia. 300 315 0.078 1.500 0.500 0.750 0.672
dia. 250 265 0.055 1.400 0.450 0.630 0.575
dia. 200 210 0.035 1.350 0.400 0.540 0.505
dia. 150 160 0.020 1.100 0.350 0.385 0.365
dia. 100 110 0.009 1.000 0.300 0.300 0.29 1,500
dia. 100 110 0.009 1.000 0.300 0.300 0.29 1,000
dia. 100 110 0.009 1.000 0.300 0.300 0.291 156
dia. 75 90 0.006 0.875 0.250 0.219 0.212 500
dia. 75 90 0.006 0.875 0.250 0.219 0.212 600
dia. 50 63 0.003 0.750 0.200 0.150 0.147
dia. 40 50 0.002 0.650 0.200 0.130 0.128
JUMLAH 3,756
Pipa Sadap
Galian Tanah Panjang
Dia. Pipa
Penampan Ukuran Volume (M3) Pipa
g Pipa
Dalam Luar Urugan
Tinggi Lebar Galian M'
dia. 400 415 0.135 1.800 0.850 1.530 1.395
dia. 350 365 0.105 1.600 0.750 1.200 1.095
dia. 300 315 0.078 1.500 0.500 0.750 0.672 48
dia. 250 265 0.055 1.400 0.450 0.630 0.575
dia. 200 210 0.035 1.350 0.400 0.540 0.505
dia. 150 160 0.020 1.100 0.350 0.385 0.365
dia. 100 110 0.009 1.000 0.300 0.300 0.291
dia. 75 90 0.006 0.875 0.250 0.219 0.212
dia. 50 63 0.003 0.750 0.200 0.150 0.147
dia. 40 50 0.002 0.650 0.200 0.130 0.128
JUMLAH 48
Urugan Sisi
Urugan T P
Galian Dipadatkan Miring
- - - 2.30 2.30 6.51
- - - 2.10 2.10 5.94
- - - 2.00 2.00 5.66
- - - 1.90 1.90 5.37
- - - 1.85 1.85 5.23
- - - 1.60 1.60 4.53
450.00 435.8 14.25 1.50 1.50 4.24
300.00 290.5 9.50 1.50 1.50 4.24
46.80 45.3 1.48 1.50 1.50 4.24
109.38 106.2 3.18 1.38 1.38 3.89
131.25 127.4 3.82 1.38 1.38 3.89
- - - 1.25 1.25 3.54
- - - 1.15 1.15 3.25
1,037.43 1,005.20 32.22
Urugan Sisi
Urugan T P
Galian Dipadatkan Miring
- - - 2.30 2.30 6.51
- - - 2.10 2.10 5.94
36.00 32.3 3.74 2.00 2.00 5.66
- - - 1.90 1.90 5.37
- - - 1.85 1.85 5.23
- - - 1.60 1.60 4.53
- - - 1.50 1.50 4.24
- - - 1.38 1.38 3.89
- - - 1.25 1.25 3.54
- - - 1.15 1.15 3.25
36.00 32.26 3.74
ut
Asumsi 50 cm diatas tanah
Volume Galian (M3) Panjang Pipa Perlintasan
Urugan Sisi
Urugan T P
Galian Dipadatkan Miring
- - - 2.30 2.30 6.51
- - - 2.10 2.10 5.94
- - - 2.00 2.00 5.66
- - - 1.90 1.90 5.37
- - - 1.85 1.85 5.23
2.31 2.2 0.12 1.60 1.60 4.53
- - - 1.50 1.50 4.24
- - - 1.38 1.38 3.89
- - - 1.25 1.25 3.54
- - - 1.15 1.15 3.25
2.31 2.19 0.12
cor
Volume Galian (M3)
Urugan
Urugan
Galian Dipadatkan
- - -
- - -
- - - Panjang
11.20 10.9 0.28 2
21.60 21.3 0.35 2
- - -
- - -
- - -
- - -
- - -
32.80 32.18 0.62
ipa
Volume Galian (M3)
Urugan
Urugan
Galian Dipadatkan
- - -
- - -
- - -
- - -
- - - 8
- - -
6.75 6.7 0.01 2
- - -
- - -
- - -
6.75 6.72 0.01
Umpak