C&R Panel Testing Procedure
C&R Panel Testing Procedure
CONTROL
&
RELAY PANEL
CAUTION: - Hard copy of this document is for information purposes only. The content of the procedures may
be changed with out notification. The controlled procedures are those only on the SCI server. P1 of 4
Document No. Solution Centre India
SE-SCI-CON-S-52 Design & Engineering Procedure
Revision No. 00
Department – Design & Engineering
Date: 01/01/2013
1.0 Introduction
The following test procedure has been prepared for the testing and commissioning of the equipment
at ……………………………………. project India.
All Testing and Commissioning documentation must be produced in accordance with all relevant
codes of practice of India and international standard.
The following test instrumentation & tools will be required to undertake the tests detailed within this
procedure:
500 Volt Megger
Relay Test Kit,
Multimeter, Tong Tester,
Switch Board, Tool Box Kit,
Test Lead with wires and Cables
Any other Test Equipment the Manufacturer deems necessary
"R" Ph
Instantaneous Unit
CAUTION: - Hard copy of this document is for information purposes only. The content of the procedures may
be changed with out notification. The controlled procedures are those only on the SCI server. P3 of 4
Document No. Solution Centre India
SE-SCI-CON-S-52 Design & Engineering Procedure
Revision No. 00
Department – Design & Engineering
Date: 01/01/2013
Functional Check:-
The all functional check to be checked the operation and Annunciation window
1. Protection System / Circuit Checked : OK
2. Alarm System / Circuit Checked : OK
3. Trip System / Circuit Checked : OK
4. Indication lamps / Circuit Checked : OK
5. Annunciation Circuit Checked if available : OK
6. Operation of Bell / Hooter Checked : OK
7. Heater, Lamp, Plug Point / Circuit Checked : OK
8. Ear thing Continuity Checked : OK
6.0 RECORDS
Control & Relay Panel Test Report
Pre Commissioning Check List
Loto Check Sheet
Energizing Protocol
CAUTION: - Hard copy of this document is for information purposes only. The content of the procedures may
be changed with out notification. The controlled procedures are those only on the SCI server. P4 of 4