VDE AR N 4105d Z2 Security
VDE AR N 4105d Z2 Security
VDE AR N 4105d Z2 Security
REPORT
VDE-AR-N 4105:2018-11
Generators connected to the low-voltage distribution network –
Technical requirements for the connection to and parallel operation with
low-voltage distribution networks in junction with
DIN VDE V 0124-100 :2020-06
Manufacturer ....................................Same
: as Applicant
Model/Type reference ......................BW-HY3600,
: BW-HY4600
Nominal
mains 230Vac
voltage:
Max. output
current 18A 20A
Nominal
50Hz
frequency:
Power factor: 0.8 leading to 0.8 lagging
Max apparent
3790VA 4600VA
power:
Battery
Voltage 40-60Vdc
Range:
Max.
Charging 90A 120A
Current:
Max.
Discharging 90A 120A
Current:
Ingress
IP65
protection:
Protection
Class I
Class:
Operating
temperature -25℃ to +60℃,>45℃ Derating
range
FW-Version Ver2155
Remark:
Other than special notice, the model BW-HY4600 is
type tested and valid for model BW-HY3600
Note:
1. The above markings are the minimum requirements required by the safety standard. For the final
production samples, the additional markings which do not give rise to misunderstanding may be added.
2. Label is attached on the side surface of enclosure and visible after installation.
3. Other labels are identical to above, except the model name and ratings
General remarks:
The test results presented in this report relate only to the object tested.
This report shall not be reproduced, except in full, without the written approval of the Issuing testing
laboratory.
"(see Enclosure #)" refers to additional information appended to the report.
"(see appended table)" refers to a table appended to the report.
When determining for test conclusion, measurement uncertainty of tests has been considered.
This report is for the exclusive use of Intertek's Client and is provided pursuant to the agreement between
Intertek and its Client. Intertek's responsibility and liability are limited to the terms and conditions of the
agreement. Intertek assumes no liability to any party, other than to the Client in accordance with the
agreement, for any loss, expense or damage occasioned by the use of this report. Only the Client is
authorized to permit copying or distribution of this report and then only in its entirety. Any use of the Intertek
name or one of its marks for the sale or advertisement of the tested material, product or service must first be
approved in writing by Intertek. The observations and test results in this report are relevant only to the sample
tested. This report by itself does not imply that the material, product, or service is or has ever been under an
Intertek certification program.
The test report only allows to be revised only within the report defined retention period unless standard or
regulation was withdrawn or invalid.
This report is based on the original report No. 210125011GZU-001, dated 24 Feb 2021, and changed
the applicant, name plate, and model name to apply for a new certificate.
The tests had been performed on model BW-HY4600 are valid for model BW-HY3600 since it is identical in
hardware and just power derated by software.
VDE-AR-N 4105:2018-11
Clause Requirement - Test Result - Remark Verdict
5 Network connection P
5.1 Principles for determination of the network Shall consider in final PGS N/A
connection point
Power generation systems and storage units shall be
connected at a suitable point of the network, i. e. the
network connection point. Based on the documents
listed in 4.2, the network operator determines the
suitable
network connection point which will ensure safe
network operation while also taking into account the
power
generation system and the storage unit and at which
the requested power can be drawn and transmitted.
The essential aspect for a network connection
evaluation is always the behaviour of the power
generation system and the storage unit at the
network connection point or at the PCC. This is
intended to ensure that the power generation system
or storage unit is operated without adverse
interactions and impairment of the supply of other
customers. Annex D shows an example of the
connection evaluation of power generation systems..
5.2 Rating of the network equipment Shall consider in final PGS N/A
Due to their operating mode, power generation
systems and storage units may cause higher loading
of lines, transformers and other network equipment.
Therefore, the network operator verifies the
transmission capacity of the network equipment with
regard to the connected power generation systems
and storage units in accordance with the relevant
rating regulations.
For calculation purposes, the maximum apparent
power of the sum of all power generation systems
and
storage units ΣSAmax and usually the load factor m =
1 shall be used. This does not apply to buried cables
for the connection of photovoltaic systems where a
load factor m = 0,7 shall be used.
VDE-AR-N 4105:2018-11
Clause Requirement - Test Result - Remark Verdict
VDE-AR-N 4105:2018-11
Clause Requirement - Test Result - Remark Verdict
VDE-AR-N 4105:2018-11
Clause Requirement - Test Result - Remark Verdict
VDE-AR-N 4105:2018-11
Clause Requirement - Test Result - Remark Verdict
VDE-AR-N 4105:2018-11
Clause Requirement - Test Result - Remark Verdict
VDE-AR-N 4105:2018-11
Clause Requirement - Test Result - Remark Verdict
5.7.2.4 Methods for reactive power supply Method b and c are used for P
reactive power supply
The reactive power supply for steady-state voltage
PGU SEmax≤4.6 kVA
stability shall not impair the dynamic network stability.
characteristic curve provided
The reactive power to be provided by the power by the network operator within
generation system is limited to the range given in cosφ= 0.95under-excited to
Figure 5 or Figure 6, respectively. 0.95 over-excited.
In the context of network connection planning, the
network operator prescribes to the connection owner
one of the following methods for reactive power
supply at the generator terminals of the power
generation unit:
a) reactive power voltage characteristic curve Q(U);
or
b) displacement factor/active power characteristic
curve cos ϕ (P); or
c) fixed displacement factor cos ϕ.
The Q(U) rule applies only to three-phase power
generation units connected to the three-phase
current
system. Here, too, the reactive power requirements
are implemented at the generator terminals of the
power
generation units.
Re: a) reactive power voltage characteristic curve N/A
Q(U)
The objective of this method is the reactive power
exchange between power generation unit and
network
depending on the actual voltage at the generator
terminals of the power generation unit (Q= f (U)).
The reference voltage UQ0 is 400 V / 3.
The arithmetic mean of the r.m.s. values (optionally
of the positive sequence system) of the three
measured
line-to-neutral voltages at the generator terminals of
the power generation unit is the target value for the
reactive power to be fed in on all line conductors.
Voltage measurement shall not exceed a maximum
measurement error of 1 % in relation to the nominal
value.
Re: b) Displacement factor/active power (See appended table) P
characteristic curve cos ϕ (P)
The objective of this method is the reactive power
supply by the power generation unit depending on
the
actual active power output (Q = f (Pmom)).
VDE-AR-N 4105:2018-11
Clause Requirement - Test Result - Remark Verdict
VDE-AR-N 4105:2018-11
Clause Requirement - Test Result - Remark Verdict
VDE-AR-N 4105:2018-11
Clause Requirement - Test Result - Remark Verdict
VDE-AR-N 4105:2018-11
Clause Requirement - Test Result - Remark Verdict
VDE-AR-N 4105:2018-11
Clause Requirement - Test Result - Remark Verdict
5.7.4.2.1 Types of power generation systems and storage The active power can be P
units remote-controlled on the
communication interface
If not specified otherwise by legislation, the
requirements described below apply.
Photovoltaic systems
PV systems shall contribute to the avoidance of
network overload. For this purpose, PV system power
is divided into three power groups:
– For PV systems up to and including 30 kWp, the
system operator may chose between two options:
a) by means of a corresponding inverter design or a
certified technical control, the active power feed-in
of the PV system shall be permanently limited to a
maximum value of 70 % of the installed module
power at the network connection point with the power
gradients given in 5.7.4.1; or
b) the PV system shall be provided with a technical
means for remote-controlled reduction of the feedin
power by the network operator.
– PV systems > 30 kWp up to and including 100 kWp
shall be provided with a technical means enabling
the remote-controlled reduction of the feed-in power
by the network operator.
– PV systems > 100 kWp shall be provided with a
technical means enabling the remote-controlled
reduction of the feed-in power by the network
operator and for the provision of the actual feed-in
power.
If the installed total power increases to > 100 kWp
due to the installation of a further PV system on the
same
plot or building within a period of 12 months, legal
provisions require implementation of the feed-in
management for systems > 100 kWp while providing
the actual feed-in power for the total power..
Cogeneration of power and heat (CHP) systems, N/A
wind, biogas, hydroelectric power as well as
landfill and sewage gas systems
Those PV systems with PAmax > 100 kW shall be
provided with a technical means enabling the remote-
controlled reduction of the feed-in power by the
network operator and for the provision of the actual
feed-in power.
VDE-AR-N 4105:2018-11
Clause Requirement - Test Result - Remark Verdict
VDE-AR-N 4105:2018-11
Clause Requirement - Test Result - Remark Verdict
VDE-AR-N 4105:2018-11
Clause Requirement - Test Result - Remark Verdict
At frequencies below 49,8 Hz, all power generation DC coupled units, a gradient P
units shall increase the instantaneous generated of 40 % PEmax per Hertz (s =
active power Pmom with a gradient of 40 % PEmax per 5 %) applies
Hertz (s = 5 %) to its technically possible maximum
value. For storage units, a gradient of 100 % PEmax (See appended table)
per Hertz (s = 2 %) applies. The maximum value is
determined by the actual primary energy supply as
well as the actually usable storage power. Power
reductions for the protection of operating equipment
are permitted even at under-frequency. For CHP
systems, power reductions resulting from a heat-lead
operating mode or a power drop due to the rotational
speed are also permitted.
Storage units dedicated to other purposes (e. g. gas
storage units in biogas systems, DC buffer storage
elements for self-consumption etc.) should be
activated for this purpose. System-integrated storage
units with an energy level below Pn × 30 s (e. g.
smoothing chokes, indirect capacitors etc.) may be
neglected for this application.
Consequently, power generation units and storage
units will constantly move up and down along the
frequency characteristic also within the frequency
range of 49,8 Hz to 47,5 Hz or 47,8 Hz with regard to
their maximum possible active power feed-in
(“operation along the characteristic”).
At an under-frequency within the range of 49,8 Hz to
47,5 Hz, all storage units in charging mode shall
reduce their instantaneous charging power according
to the characteristic curve shown in Figure 15 to its
technically possible minimum value (“operation along
the characteristic”). In addition, storage units, as far
as their charging state permits, shall change into the
operating mode “energy supply” and increase their
power according to the characteristic curve shown in
Figure 15. In this case, system stability is of higher
priority than a potential restraint for feeding storage
energy into the network of the network operator
based on technical/financial requirements.
At network frequencies f < 47,5 Hz, power generation
units and storage units shall disconnect from the
network (see Figure 14 and Figure 15).
VDE-AR-N 4105:2018-11
Clause Requirement - Test Result - Remark Verdict
VDE-AR-N 4105:2018-11
Clause Requirement - Test Result - Remark Verdict
VDE-AR-N 4105:2018-11
Clause Requirement - Test Result - Remark Verdict
VDE-AR-N 4105:2018-11
Clause Requirement - Test Result - Remark Verdict
VDE-AR-N 4105:2018-11
Clause Requirement - Test Result - Remark Verdict
VDE-AR-N 4105:2018-11
Clause Requirement - Test Result - Remark Verdict
VDE-AR-N 4105:2018-11
Clause Requirement - Test Result - Remark Verdict
VDE-AR-N 4105:2018-11
Clause Requirement - Test Result - Remark Verdict
Operation type: Switching on at any power level (without default to primary energy source)
Note:
1) Sk,fic/Sn = 20
2) ki is the ratio of the highest current occurring during a switching operation to the normal
generator current, the current is to be considered as an r.m.s. value over a period
Switching actions Ki
Marking operation without default (to primary energy carrier) 0.034
Worst case at switch over of generator sections 0.034
Marking operation at reference conditions (of primary energy carrier) 0.036
Breaking operation at nominal power 0.223
Worst case value of all switching operations Ki max 0.223
L1 phase
65%PEmax and 75 % 5
2 0.57 0.17%
PEmax:
>90 % PEmax:
Noted: CH1 represents signal for activating logic interface, CH4: Current of EUT, CH2: Voltage of EUT
Response time
Response time
Response time
Response time
P-Q Diagram
fuse
test fuse
No. component No. fault test voltage (V) current result
time No.
(A)
1. PV: 500Vdc The PCE cannot work. After
Battery side: fault removed, it can be work
Mis-
DC input 48Vdc 5min -- -- normally. No damaged. No
wiring
AC output: hazard.
230Vac
2. PV: 500Vdc
Battery side:
Bararites side Mis- The PCE cannot work. Fuse
48Vdc 5min -- --
wiring damaged. No hazard.
AC output:
230Vac
3. PV: 500Vdc
Battery side:
Mis- The PCE work normally. No
AC side 48Vdc 5min -- --
wiring damage. No hazard.
AC output:
230Vac
4. PV: 500Vdc Shut down immediately. After
Battery side: fault removed, It can be work
AC side S/C 48Vdc 5min -- -- normally.No hazard No
AC output: damaged. No hazard.
230Vac
5. PV: 500Vdc Shut down immediately. After
Battery side: fault removed, It can be work
DSP (U18) S/C 48Vdc 5min -- -- normally.No hazard No
AC output: damaged. No hazard
230Vac
6. PV: 500Vdc PEC protected immediately.
failure Battery side: Disconnect from the grid.
DSP (U300)
of 48Vdc 5min -- -- After fault removed, it can be
power AC output: work normally. No damaged.
230Vac No hazard.
7. PV: 500Vdc
C214 S/C 5min -- -- Battery mode does not work,
Battery side:
PV mode is not affected. No
48Vdc
damaged. No hazard.
AC output:
230Vac
8. PV: 500Vdc PEC protected immediately.
Battery side: Disconnect from the grid.
C165 S/C 48Vdc 5min -- -- Q30, Q32, Q31, Q35 and
AC output: Fuse damaged. No hazard.
230Vac
OV
Stage 1 Limitation
Trip time [s] Test condition
[s]
No.
UV Set Measured
Stage 1 Limitation
value Test condition
[ms]
No. L1-N L2-N L3-N
0.8Un 184.00 -- -- +/-1%Un 1, applying ramp test, start
1 of >188.6 V, and ramp to
3s 3.050s -- -- 3-3.1s <179.4V, step voltage length is
<1.15 V, and step time is >3.2s
0.8Un 183.25 -- -- +/-1%Un
2 2, applying Jump test, start
3s 3.032s -- -- 3-3.1s of >200.1 V, and jump to
<179.4V, step voltage length
0.8Un 184.35 -- -- +/-1%Un is >9.2 V, and step time is >3.2s
3
3s 3.048s -- -- 3-3.1s
OV Stage 2:
OV Stage 1:
112% Un
Un to 1.08Un
1.06 Un to 1.14Un
UV Stage 2
UV Stage 1
OF:
UF:
Reactive
PEUT1)
load (% PAC2) QAC3) Run on
(% PEUT Actual
No. of (% of (% of time VDC Remarks4)
of EUT (KW) Qf
QL in nominal) nominal) (ms)
rating)
6.1.d)1)
Test bench in figure 1 shall be set up accordingly, and PAV,E monitoring device shall be installed on the
connection point of AC power source. Make test sample power Pinv=100% Pinst, and adjust AC load to make
Pload=30%Pinst, PAC =70%Pinst , open switch S2 and observe the power reduction on AC source side. The limit
curve in figure 2 shall not be exceeded. (Limit curve: PAV,E(t)= 0,67 x e-1,05 x (t-0,8)+1)
Power curve:
Case b, CH1: voltage of grid; CH2: current of grid; CH3: inject of 1,067PAVE; CH4: current of inverter
Case c, CH1: voltage of grid; CH2: current of grid; CH3: inject of 1,67PAVE; CH4: current of inverter
Case d, CH1: voltage of grid; CH2: current of grid; CH3: inject of 1,067PAVE; CH4: current of inverter
The effective network impedance from view of PGU must fulfill following criterion:
- short-circuited power at PGU before and after fault must be between 10xSn and 30xSn
- R/X 0.3-3 (for applied impedance in test equipment)
The test equipment and network simulator must be able to take the max. occurring PGU current, both in
generating and motoring area. The energy absorb shall be designed for sudden short circuited current Ip (per
IEC 60909). Ip is obvious different by the type of test sample, the correct value shall be:
2.3, 2.4, 3.3, 3.4 0.76, -161.1° 0.50, 90° 0.76, -19.1° D1
Diagram:
For each test the following diagrams shall be figured since t1-1s (one second before fault entry) till t2+6s (six
seconds after fault clear), zoomed if needed:
Method of calculations:
18 t1+100ms
During Line to
Voltage to t2- p.u. 0.15 0.5 0.5
dip t1 to neutral 20ms
t2 19 Phase 1 -- -- --
20 Line current Phase 2 t1+60ms p.u. -- -- --
21 Phase 3 0.015 0.020 0.020
22 Phase 1 -- -- --
23 Line current Phase 2 t1+100ms p.u. -- -- --
24 Phase 3 0.015 0.020 0.020
25 Total t1+100ms 0.000 0.000 0.000
Active to t2-
26 Positive p.u.
power 20ms -- -- --
sequence
27 Voltage Line to t2+3s to p.u.
t2+10s 1.00 1.00 1.00
neutral
28 Positive
Active t2+3s to -- -- --
sequence. p.u
power t2+10s
29 Total 1.001 0.966 0.967
39 Active Positive -- s
power rising sequence 0.334 0.353 0.331
time
After 31 Positive
Reactive t2+3s to -- -- --
dip sequence p.u.
power t2+10s
> t2 32 Total -0.038 0.314 -0.302
33 Reactive Positive -- s
power rising sequence 0.334 10.05 10.02
time
34 PGU does --
not
disconnect t2 to
t2+60s
Yes / No Yes
from grid till
60s after
fault
Empty load
Recovery time
Empty load
After dip(t2+3s)
Recovery time-P
Recovery time-Q
After dip(t2+3s)
Recovery time-P
Recovery time-Q
18 t1+100ms
During Line to
Voltage to t2- p.u. 0.85 1.25 1.20 1.15
dip t1 to neutral 20ms
t2
19 Line current Phase 1 t1+60ms p.u. -- -- -- --
20 Phase 2 -- -- -- --
21 Phase 3 0.470 0.041 0.050 0.054
22 Phase 1 -- -- -- --
23 Line current Phase 2 t1+100ms p.u. -- -- -- --
24 Phase 3 0.439 0.034 0.033 0.034
25 Total t1+100ms 0.387 0.028 0.006 -0.002
Active to t2-
26 Positive p.u.
power 20ms -- -- -- --
sequence
27 Voltage Line to t2+3s to p.u.
t2+10s 1.00 1.00 1.00 1.00
neutral
28 Positive
Active t2+3s to -- -- -- --
sequence. p.u
power t2+10s
29 Total 0.999 1.001 1.002 1.001
39 Active Positive -- s
power rising sequence 0.292 0.336 0.217 0.357
time
After 31 Positive
Reactive t2+3s to -- -- -- --
dip sequence p.u.
power t2+10s
> t2 32 Total 0.006 0.004 -0.027 0.004
33 Reactive Positive -- s
power rising sequence 0.292 0.336 0.217 0.357
time
34 PGU does --
not
disconnect t2 to
t2+60s
Yes / No Yes
from grid till
60s after
fault
After dip(t2+3s)
Recovery time
Empty Load
After dip(t2+3s)
Recovery time
Empty Load
After dip(t2+3s)
Recovery time
After dip(t2+3s)
Recovery time
18 t1+100ms
During Line to
Voltage to t2- p.u. 0.15 0.50 0.50
dip t1 to neutral 20ms
t2
19 Line current Phase 1 t1+60ms p.u. -- -- --
20 Phase 2 -- -- --
21 Phase 3 0.007 0.020 0.021
22 Phase 1 -- -- --
23 Line current Phase 2 t1+100ms p.u. -- -- --
24 Phase 3 0.006 0.021 0.021
25 Total t1+100ms 0.000 0.000 0.000
Active to t2-
26 Positive p.u.
power 20ms -- -- --
sequence
27 Voltage Line to t2+3s to p.u.
t2+10s 1.00 1.00 1.00
neutral
28 Positive
Active t2+3s to -- -- --
sequence. p.u
power t2+10s
29 Total 0.307 0.307 0.311
39 Active Positive -- s
power rising sequence 0.352 0.339 0.323
time
After 31 Positive
Reactive t2+3s to -- -- --
dip sequence p.u.
power t2+10s
> t2 32 Total -0.023 0.318 -0.320
33 Reactive Positive -- s
power rising sequence 0.352 10.00 10.00
time
34 PGU does --
not
disconnect t2 to
t2+60s
Yes / No Yes
from grid till
60s after
fault
After dip(t2+3s)
Recovery time
After dip(t2+3s)
Recovery time-P
Recovery time-Q
After dip(t2+3s)
Recovery time-P
Recovery time-Q
18 t1+100ms
During Line to
Voltage to t2- p.u. 0.85 1.25 1.20 1.15
dip t1 to neutral 20ms
t2
19 Line current Phase 1 t1+60ms p.u. -- -- -- --
20 Phase 2 -- -- -- --
21 Phase 3 0.117 0.044 0.042 0.037
22 Phase 1 -- -- -- --
23 Line current Phase 2 t1+100ms p.u. -- -- -- --
24 Phase 3 0.094 0.038 0.037 0.030
25 Total t1+100ms -0.004 0.042 -0.002 -0.003
Active to t2-
26 Positive p.u.
power 20ms -- -- -- --
sequence
27 Voltage Line to t2+3s to p.u.
t2+10s 1.00 1.00 1.00 1.00
neutral
28 Positive
Active t2+3s to -- -- -- --
sequence. p.u
power t2+10s
29 Total 0.309 0.312 0.308 0.306
39 Active Positive -- s
power rising sequence 0.390 0.253 0.246 0.299
time
After 31 Positive
Reactive t2+3s to -- -- -- --
dip sequence p.u.
power t2+10s
> t2 32 Total -0.024 0.006 -0.023 -0.024
33 Reactive Positive -- s
power rising sequence 0.390 0.253 0.246 0.299
time
34 PGU does --
not
disconnect t2 to
t2+60s
Yes / No Yes
from grid till
60s after
fault
After dip(t2+3s)
Recovery time
After dip(t2+3s)
Recovery time
After dip(t2+3s)
Recovery time
After dip(t2+3s)
Recovery time
18 Phase 1 t1+100ms -- -- -- --
During Voltage to t2- p.u.
dip t1 to Phase 2 -- -- -- --
After 31 Positive
Reactive t2+3s to -- -- -- --
dip sequence p.u.
power t2+10s
> t2 32 Total -0.026 0.283 0.279 -0.027
33 Reactive Positive -- s
power rising sequence 0.391 10.04 10.00 0.485
time
34 PGU does --
not
disconnect t2 to
t2+60s
Yes / No Yes
from grid till
60s after
fault
Empty load
Recovery time
Empty load
Recovery time-P
Recovery time-Q
Recovery time-P
Recovery time-Q
Recovery time
18 Phase 1 t1+100ms -- -- -- --
During Voltage to t2- p.u.
dip t1 to Phase 2 -- -- -- --
After 31 Positive
Reactive t2+3s to -- -- -- --
dip sequence p.u.
power t2+10s
> t2 32 Total -0.030 -0.022 -0.028 0.005
33 Reactive Positive -- s
power rising sequence 0.332 0.284 0.363 0.393
time
34 PGU does --
not
disconnect t2 to
t2+60s
Yes / No Yes
from grid till
60s after
fault
Empty load
Recovery time
Empty load
Recovery time
Empty load
Recovery time
Recovery time
18 Phase 1 t1+100ms -- -- -- --
During Voltage to t2- p.u.
dip t1 to Phase 2 -- -- -- --
After 31 Positive
Reactive t2+3s to -- -- -- --
dip sequence p.u.
power t2+10s
> t2 32 Total 0.307 0.320 -0.021 -0.021
33 Reactive Positive -- s
power rising sequence 10.01 10.00 0.394 0.319
time
34 PGU does --
not
disconnect t2 to
t2+60s
Yes / No Yes
from grid till
60s after
fault
Recovery time-P
Recovery time-Q
Recovery time-P
Recovery time-Q
Recovery time
Recovery time
18 Phase 1 t1+100ms -- -- -- --
During Voltage to t2- p.u.
dip t1 to Phase 2 -- -- 0.148 1.252
After 31 Positive
Reactive t2+3s to -- -- -- --
dip sequence p.u.
power t2+10s
> t2 32 Total -0.023 -0.024 -0.037 -0.022
33 Reactive Positive -- s
power rising sequence 0.316 0.337 0.328 0.300
time
34 PGU does --
not
disconnect t2 to
t2+60s
Yes / No Yes
from grid till
60s after
fault
Recovery time
Recovery time
Recovery time
Recovery time
* The tripping time includes the period from the limit value violation U/f until the tripping signal to the interface
switch.
When planning the power generation system, the response time of the interface switch shall be added to the
maximum time value obtained as indicated above.
The disconnection time (sum of tripping time of the NS protection plus response time of the interface switch)
shall not exceed 200 ms.
* Die Auslösezeit umfasst den Zeitraum von der Grenzwertverletzung U/f bis zum Auslösesignal an den
Kuppelschalter.
Bei der Planung der Erzeugungsanlage ist die Eigenzeit des Kuppelschalters zum höchsten oben ermittelten
Zeitwert zu addieren.
Die Abschaltzeit (Summe der Auslösezeit NA-Schutz zzgl. Eigenzeit des Kuppelschalters) darf 200 ms nicht
überschreiten.
For integrated NS protection (Bei integriertem NA-Schutz)
Assigned to power generation unit of type
BW-HY3600, BW-HY4600
zugeordnet zu Erzeugungseinheit Typ
Type integrated interface switch
Hongfa; HF161F-W/12- HT
Typ integrierter Kuppelschalter
Response time of interface switch for integrated NS
protection 10ms
Eigenzeit des Kuppelschalters bei integriertem NA-Schutz
Verification of the entire functional chain “integrated NS protection – interface switch” has resulted in successful
disconnection.
Die Überprüfung der Gesamtwirkungskette „integrierter NA-Schutz – Kuppelschalter“ führte zu einer
erfolgreichen Abschaltung.
Appended photos
Top view
Back view
Side view
Terminal view
Internal view
(End of Report)