Switchgear Operating Manual V2 by VESI
Switchgear Operating Manual V2 by VESI
Switchgear Operating Manual V2 by VESI
HV OUTDOOR
/UNDERGROUND REGULATORS BOXES INDICATORS
OPERATING
manual
SWITCHGEAR OPERATING MANUAL
DECEMBER 2015
This High Voltage Switchgear Operating manual is an operating guide for Authorised
persons working for the VESI Network Operator (AusNet Services, CitiPower, Jemena,
Powercor and United Energy).
As an operating guide, it does not include all of the technical considerations, system
protection requirements, and operational checks that may be required for the safe
operation of the networks. In the event that a user of this manual considers the provisions
do not cover, are uncertain, ambiguous or in need of interpretation, the user should seek
immediate clarification from the Network Operator responsible person or their Network
Control Centre.
The Manual shall be read and applied in conjunction with The Green Book (Electrical
Safety Rules for the VESI Distribution Networks) and the Network Operators HV
Operations procedure manuals.
MANDATORY REQUIREMENTS
3. Wear and use approved protective apparel, tools, ensuring operating equipment is in
good working order and within test date.
5. When access or switching is required on any VESI electrical network, for any
purpose, the relevant Network Control Centre must be advised prior to the
commencement and completion of any works/switching.
Feedback
For any improvements/changes/suggestions on the content of this manual, please advise
your Network Operator responsible person. The use of the “Contact Us – Network
Access” www.vesi.com.au/index.php/contact-us link on the VESI website can be utilised
for suggestions, enhancements and amendments.
HV INDOOR/UNDERGROUND
MERLIN GERIN RM6 – TALUS 200 REMOTE CONTROL WILSON – CALOR EMAG OPEN BUS SUBSTATION
MERLIN GERIN RM6 - TALUS DNP3 REMOTE CONTROL WILSON LOOP SUBSTATION
MI/STATOR VL
M.V. / A.G.E. 6.6KV CAST IRON CB
HV Indoor/Underground
Prior to any operation Functions: Opening Closing
Rating: 400 amps
• Confirm the switchgear is fit for service prior Insulant: Oil
to and after any operation. Voltage: 11kV
• This switchgear (left side of the main
picture) can be used as a single unit or as a
combination with other switchgear such as
the South Wales D4XD CB as shown on the
right side of the main picture.
• Confirm the switch location and labelling prior
to operating.
ON ON ON
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Indoor
HV Indoor/Underground
2
1 Confirm relevant the HV switch is open.
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV
HV Indoor
Indoor
HV Indoor/Underground
Prior to any operation Functions: Opening, Closing, Isolating
Rating: 400 amps
• Confirm the CB is fit for service prior to and
Insulant: Oil
after any operation.
Voltage: 11kV
• This circuit breaker can be used as a
single unit or as a combination with other
switchgear such as the South Wales IF4X
HV switch as shown in the main picture
insert.
• Remote operation of these CBs is always the
preferred method.
• Confirm the CB location and labelling prior to
operating.
ON OFF
CB Closed CB Open
Closing the CB
1 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
CONTENTS
HV
HV Indoor
Indoor
Opening the CB
HV Indoor/Underground
1 Open the ‘PUSH TO TRIP’ access flap.
2
Racking Out the CB
2 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
CONTENTS
HV
HV Indoor
Indoor
Racking in the CB
HV Indoor/Underground
1 Confirm the CB is open.
3
2 Confirm the ‘LOCATION SELECTOR’ Is In the ‘SERVICE’
position.
3 Push the CB into CB cubicle until the pointer aligns with the
‘SERVICE POSITION’ indicator. 2
Note: Ensure the shutter locks have been removed and the CB
is open prior to racking in.
2 Push the CB into CB cubicle until the pointer aligns with the
‘CIRCUIT EARTH’ indicator.
4 Close the CB as per the Closing the CB instruction to earth SOUTH WALES D4XD CB
the circuit.
3 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Indoor
STANGER SCD-2
Functions:
HV Indoor/Underground
Opening, Closing, Trans Switch/
Prior to any operation: CB, HV Fuses
Rating: 400 Amps
• Confirm the HV switch arc chutes are latched Insulant: Air
correctly prior to opening and after closing. Voltage: 11kV
• Note: There are two types of operating
mechanisms associated with this switch.
• Instructions on both are shown below.
• The HV operating stick lever can be located
on either side of the HV switch.
• These HV switches can be found in
combination with Powder Filled HV Fuses.
• Access Authority required for access to HV
fuses.
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Indoor
HV Indoor/Underground
1 Operation as for the ‘Closing and Opening of HV Cable
Switches - Type A’ as shown above.
STANGER SCD-2
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Indoor
HV Indoor/Underground
Functions: Opening, Closing, Trans Switch,
Prior to any operation: HV Fuses
Rating: 400 amps
• Ensure HV switch arc chutes are latched
Insulant: Air
correctly prior to opening and after closing. Voltage: 11kV
• Confirm switch location and labelling prior to
operation.
• Acces Authority required to access HV fuses.
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Indoor
HV Indoor/Underground
1 Operation as previous..
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Indoor
STATTER/MI EOD
HV Indoor/Underground
Prior to any operation Functions: Opening,Closing, Earthing
• Confirm the switchgear is fit for service prior Rating: 400 amps
Insulant: Oil
to and after any operation.
Voltage: 11kV, 6.6kV
• Confirm the HV switch oil level is correct prior
to any operating.
• Confirm the switch location and labelling prior
to operating.
Warning: On some radial feeders in the MCC area
the HV earth switch on the Statter switch units closes
on the incoming HV cable with the transformer HV
cable coming off the end box.
O O E
A
F R
N F
T
H
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Indoor
HV Indoor/Underground
1 Confirm relevant the HV switch is open.
3
2 Unlock the padlock and raise the earth switch interlock lever
to the stop position.
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Indoor
STATTER OD
HV Indoor/Underground
Prior to any operation Functions: Opening, Closing, Earthing
Rating: 400 amps
• Confirm the switchgear is fit for service prior Insulant: Oil
to and after any operation. Voltage: 11kV, 6.6kV
• Confirm the HV switch oil level is correct prior
to any operation.
• Confirm the switch location and labelling prior
to operating.
• Warning: On some radial feeders in the
MCC area the HV earth switch on the Statter
switch units closes on the incoming HV cable
with the transformer HV cable coming off the
end box.
• Caution: This switchgear is NOT spring
assisted. Operation must be a rapid, firm and
continuous motion.
E
A
HV Switch HV Switch R Earth Switch
Closed Open T Closed
H
2 1
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Indoor
STATTER OD (CONTINUED)
HV Indoor/Underground
3
1 Confirm relevant the HV switch is open.
3 Remove the padlock and push down the spring loaded earth
switch interlock whilst raising operating handle in a rapid,
firm and continuous motion to the ‘EARTH’ position.
E
A
2
HV Switch HV Switch R Earth Switch
4 Confirm the semaphore shows
Closed Open T
H
.
Closed
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Indoor
STATTER ODSA
HV Indoor/Underground
Prior to any operation Functions: Opening, Closing, Earthing
• Confirm the switchgear is fit for service prior Rating: 400 amps
to and after any operation. Insulant: Oil
Voltage: 11kV, 6.6kV
• Confirm the HV switch oil level is correct prior
to any operating.
• Confirm the switch location and labelling prior
to operating.
• Warning: On some radial feeders in the
MCC area the HV earth switch on the Statter
switch units closes on the incoming HV cable
with the transformer HV cable coming off the
end box.
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Indoor
HV Indoor/Underground
1 Confirm relevant the HV switch is open.
2 Unlock the padlock and raise the earth switch interlock lever. 4
2
3 Raise the HV switch interlock lever to the stop position.
Note: To open HV cable earth switch, lower the interlock lever to the
open position.
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Indoor
TSN
HV Indoor/Underground
Prior to any operation Functions: Opening, Closing, Earthing
Rating: 630 amps
• Confirm the switchgear is fit for service prior Insulant: Air
to and after any operation. Voltage: 11kV
• The substation doors must be closed when
operating this HV switch.
• Confirm the HV switch location and labelling
prior to operating.
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Indoor
TSN (CONTINUED)
HV Indoor/Underground
1 Confirm the HV switch is open.
TSN
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
CONTENTS
HV Indoor
HV
HV Indoor
Indoor
TSN (GMH)
HV Indoor/Underground
Prior to any operation Functions: Opening, Closing
Rating: 400 amps
• Confirm the switchgear is fit for service prior Insulant: Air
to and after any operation. Voltage: 6.6kV
• The substation doors must be closed when
operating this HV switch.
• Confirm the HV switch location and labelling
prior to operating.
1 of 1
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Indoor
HV Indoor/Underground
Prior to any operation: Functions: Opening, Closing, Earthing
Insulant: Air
• Note that when the transformer HV switch is Voltage: 22kV
open, the bottom contacts may still be ALIVE.
• Note the transformer HV fuses are hinged on
the transformer side.
• An Access Authority is required for the
removal of the transformer HV switch / earth
switch / HV fuse access cover.
• Check/confirm oil levels, labelling and
semaphores.
• Confirm the HV switch location and labelling.
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Indoor
WILSON – CALOR
WILSON – CALOREMAG OPENBUS
EMAG OPEN BUS SUBSTATION
SUBSTATION (CONTINUED)
(CONTINUED)
HV Indoor/Underground
1 Unlock, if required, and open the HV fuse access cover
retaining pad bolts.
Note: Confirm the remote end/s of the HV cable/s is/are isolated prior
to earthing. 2
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
CONTENTS
HV Indoor
HV
HV Indoor
Indoor
HV Indoor/Underground
Functions: Isolate, Earthing
Prior to any operation: Rating: 400 Amps
• For the HV cable elbow operation, refer to Insulant: Oil
the 200/400 or 600A Cable Elbows section in Voltage: 22KV
this manual.
• Confirm the loop substation location and
labelling prior to operation.
• NX type HV fuses can only be removed or
replaced with the substation de-energised.
HV fuses may be hot.
• Ensure earthing elbows are connected to the
substation earth grid prior to earthing.
For isolation and earthing of the HV Cables refer to the either the
200/400 Amp HV Cable Elbows or the 600 Amp HV Cable
Elbows template in this manual.
1 of 1
VESI Switchgear Manual Copyright © 2015
CONTENTS
CONTENTS
HV Indoor
HV
HV Indoor
Indoor
HV Indoor/Underground
Functions: Opening, Closing, Isolation, HV
Prior to any operation: Fuses
Rating: Various (HV Fuses)
• The HV powder filled fuses are hinged at the
Insulant: Air
top. Voltage: 22 kV
• HV fuses may be removed / replaced without
an Access Authority under the following
conditions:
– HV fuses must be isolated and confirmed
de-energised.
– HV operating sticks must be used.
2 Unlock and slide across the two (2) HV fuse access door pad
bolts.
2 2
1 of 1
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV
HV Indoor
Indoor
WILSON SUBSTATION
HV Indoor/Underground
Functions: Opening, Closing, HV Fuses
Prior to any operation: Rating: Various
Insulant: Oil
• Check oil level prior to switching and / or
Voltage: 22kV, 11kV
removal of HV bayonet fuses.
• Ensure the transformer tank pressure is
equalized via the bleed valve prior to removal
of the HV bayonet fuses.
• For the removal / earthing of the 200/400A
elbows refer to the ‘200/400A Cable
Connector Elbows’ template in this manual.
• Confirm switch location and labelling prior to
operation.
• Ensure HV fuses are kept clean at all times.
• HV bayonet fuses MUST NOT be used to de-
energise or energise transformers.
1 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
CONTENTS
HV
HV Indoor
Indoor
HV Indoor/Underground
1 Using a HV operating stick or HV operating gloves, pull the
pressure relief valve for a minimum of ten (10) seconds to 1
equalize the transformer tank pressure with the external air
pressure.
WILSON SUBSTATION
Replacing the HV Bayonet Fuse Element
2 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
CONTENTS
HV
HV Indoor
Indoor
HV Indoor/Underground
1 Insert the HV bayonet fuse by using the operating stick. 1
2 Push the HV bayonet fuse firmly home.
WILSON SUBSTATION
3 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Indoor
HV Indoor/Underground
Functions: Opening, Closing, Isolation,
Prior to any operation: Earthing, HV Fuses
Rating: 400 amps
• Prior to switching check HV switch oil level
Insulant: Oil
gauge. Voltage: 22kV
• NX type HV fuses can only be removed or
replaced with sub station de-energised.
For instruction on removal / replacement
refer to ‘NX HV Fuses’ section of this manual.
• For cable elbow operation refer to ‘200/400
or 600A Cable Elbows’ section of this
manual.
• Confirm switch location and labelling prior to
operation.
1 Place operating handle on HV switch open / close operating WILSON SWITCH LINK
mechanism.
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Indoor
Earthing of HV Cable
HV Indoor/Underground
1 Carry out Safe to Earth test.
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV
HV Indoor
Indoor
YORKSHIRE TYKE
HV Indoor/Underground
Functions: Opening, Closing, Trans Switch/
Prior to any operation: CD, Earthing, HV Fuses
Rating: 630 amps
• Confirm HV switchgear is fit for service prior
Insulant: Oil
to and after operation. Voltage: 11kV
• Confirm switch location and labelling prior to
operation.
• Access Authority required for access to HV
fuses.
1 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
CONTENTS
HV
HV Indoor
Indoor
Earthing of HV Cable
HV Indoor/Underground
1 Unlock and open the HV earth switch interlock flap.
flap. 3
Note: to open the transformer HV earth switch, push the operating lever.
2 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
CONTENTS
HV
HV Indoor
Indoor
Access to HV Fuses
HV Indoor/Underground
1 With transformer HV earth switch closed unscrew two (2) HV 1
1
fuse access cover plate bolts.
YORKSHIRE TYKE
3 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV
HV Indoor
Indoor
YORKSHIRE YSF6
HV Indoor/Underground
Functions: Opening, Closing, Racking, Trans
Prior to any operation: Switch/CB, Earthing
Rating: 630 amps
• If equipped with a gas indication gauge
Insulant: SF6
check for correct pressure prior to switching. Voltage: 22kV, 11kV
• Confirm HV CB location and labelling prior to
operation.
• Confirm HV CB location and labelling prior to
operation.
Closing CB
Opening CB
1 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
CONTENTS
HV
HV Indoor
Indoor
Racking Out CB
HV Indoor/Underground
1 Lift the interlock button and OPEN the racking mechanism
access shutter.
2
2 Push the selector lever ACW to the ‘Free’ position.
Locking Shutters
1
2
Racking In CB
2
the ‘Lock’ position.
2 of 3
2 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
CONTENTS
HV
HV Indoor
Indoor
HV Indoor/Underground
1 Check ratchet on spring charge handle is set to drive
clockwise.
2
2 Open CB cover panel then rotate open the spring charge
mechanism access flap and fit spring charge handle to
spring charging spigot.
YORKSHIRE YSF6
3 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV OUTDOOR
HV Outdoor
Functions: Opening, Closing
Prior to any operation: Rating: 630 amps
Insulant: Air
• Confirm HV switch is fit for service prior to
Voltage: 22kV
and after operation.
• Operating handles may differ in construction
however operating principles remain the C
same.
• Confirm switch location and labelling prior to
operation.
Closing HV Switch
1 of 1
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Functions: Opening, Closing, Trans Switch/
Prior to any operation CB, Earthing, HV Fuses
Rating: 400 Amps
• Confirm the HV switch is fit for service prior Insulant: Air
to and after any operation. Voltage: 22 kV
• The operating handles on this HV switch may
differ in construction however the operating
principles remain the same.
• Confirm the Duogap arc expulsion devices
have latched correctly prior to opening the
HV switch.
• Check/confirm labelling
• Confirm the HV switch location and labelling
prior to operation.
1
1
Duogap Latching
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Opening the HV Switch
22
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Functions: Opening, Closing
Prior to any operation: Rating: 630 amps
Insulant: SF6
• If ‘Gas Low’ semaphore appears in
Voltage: 22kV, 11kV, 6.6kV
semaphore window do not operate gas
switch.
• Confirm switch location and labelling prior to
operation.
Closing HV Switch
Opening HV Switch
1 of 1
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Functions: Opening, Closing, Earthing, HV
Prior to any operation Fuses
Rating: MVar
• AT ALL TIMES a period of at least five (5) Insulant: Oil / Vacuum
minutes must be allowed to elapse between Voltage: 22 kV
the capacitor modules being switched off
and the application of earths to the discharge
terminals.
• The hinged HV fuse MUST NOT be used to
make or break the capacitor current.
• Confirm the capacitor location and labelling
prior to operation.
• Check/confirm labelling and semaphores
• The close/open sequence can be cancelled
by momentarily moving the ‘AUTO /
MANUAL’ control switch to ‘AUTO’ and back
to ‘MANUAL’.
• Note: The preferred method of switching is
via the control box. Manual vacuum switch
operation is to be used only if AC supply is
unavailable to the control box.
• In some cases the 16 Kva transformer must
be de-energised for proximity reasons before
the capacitors can be earthed.
HV Outdoor
Closing the Capacitors Manually – Vacuum Switch
2 Place the operating stick pin under the yellow operating lever.
2 Place the operating stick pin over the yellow operating lever.
7 Test and apply earth and short circuits to the capacitor side
of the boric acid HV fuses.
4
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Functions: Opening, Closing, Earthing, HV
Prior to any operation Fuses
Rating: MVar
• At all times a period of at least five (5) Insulant: Oil / Vacuum
minutes must be allowed to elapse between Voltage: 22kV
the capacitor modules being switched off
and the application of earths to the discharge
terminals.
• The hinged HV fuse MUST NOT be used to
make or break the capacitor current.
• Confirm the capacitor location, labelling and
semaphores
• The close/open sequence can be cancelled
by momentarily moving the ‘AUTO /
MANUAL’ control switch to ‘AUTO’ and back
to ‘MANUAL’.
• After opening, the control box will not allow a
reclose for 5 minutes.
• Note the preferred method of switching is 3
phase via the control box. Manual vacuum
• switch operation is to be used only if AC
HV Outdoor
Closing the Capacitors Manually – Vacuum Switch
2
Opening the Capacitors Manually – Vacuum Switch
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Functions: Opening, Closing, HV Fuses
Prior to any operation Rating: 0 -15Amps
lnsulant: Air
• For instructions on opening and closing this
Voltage: 22 kV
unit refers to the EDO HV FUSES section in
this manual.
• Check/confirm labelling and semaphores
• Exercise caution when handling the
sectionaliser as it may be hot.
• Do not bend the spade terminals when
removing and re-attaching the connectors.
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Replacing the Sectionaliser Firing Pin
3 After closing the trundle ensure the firing pin latch has
engaged correctly.
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Functions: Opening, Closing
Prior to any operation Rating: 800 amps
• Confirm the suspension cable isolators are fit Insulant: Air
for service prior to and after any operation. Voltage: 22 kV
1 of 1
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Functions: Opening, Closing, HV Fuses
Prior to any operation: Rating: Various
Insulant: Air
• After removing HV fuses care should be
Voltage: 22kV, 11kV, 6.6kV
taken prior to handling as fuses may be hot.
• Boric Acid Fuses should not be left hanging
in the open position if moisture could enter
the exhaust end of the fuse thus affecting the
fuse performance.
• Ensure HV stick movement maintains
pressure on HV Fuse lower hinged fitting
during opening and closing.
• Warning: HV fuse may be hot.
Closing HV Fuse
Opening HV Fuse
Removing HV Fuse
1 of 1
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Functions: Opening, Closing and Fault
Prior to any operation: Interruption
Rating: Interrupting 600A, Continuous 42A
• Contact the Control Centre. Insulant: Oil with Magnetic interrupter
• Confirm HV CB/Switch location and labelling Voltage: 22kV and 12.7kV
prior to operation.
• Opening and closing only requires 2kg of
1
Opening the CB/Switch (With Semphore)
1 Place operating handle into the CB/switch mechanism and
turn slowly using very little force anti clockwise to stop point
1
to OPEN.
2 Ensure the semphore has operated via the red indicator and
switch is in the open position.
1 of 4
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Closing the CB/Switch (With Semphore)
2 of 42
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
1 Place operating handle into CB/switch mechanism and
turn slowly with very little force clockwise to stop point to
CLOSE. 1
2
Re-setting the CB/Switch after a Fault (With Semaphore)
When an overcurrent fault occurs, the CB handle will remain in the closed position. The semaphore
will be visible.
3 of 4
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
When an overcurrent fault occurs, the CB handle will remain in the closed position.
4 of 4
2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Functions: Opening, Closing, Earthing, HV
Prior to any operation Fuses
Rating: 400 KVA
• These line capacitors are star connected, Insulant: Oil
neutral point to ground, therefore before any Voltage: 22 kV
switching the following protection must be
suppressed:
• Earth leakage protection on any
upstream ACR
1 Place the operating stick pin into the yellow operating lever
eye hole.
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Discharging / Earthing the Capacitor
3 Lift and stow the capacitor line live line clamps if required. 3
4 Confirm a minimum of five (5) minutes has elapsed since the
capacitor HV oil switches were opened.
3
5 Perform a ‘Safe To Earth’ test and if in order attach earth and
shirt circuits to the earth flag bolts at the bottom of the EDO 5
5
units. 5
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Functions: Opening, Closing
Prior to any operation: Rating: 400 amps
Insulant: Air
• Confirm HV switch is fit for service prior to Voltage: 22kV, 11kV
operation.
• Operating handles may differ in construction
however operating principles remain the
same regardless of HV switch make or
voltage.
• If HV switch is vertically mounted operating
instructions may be reversed.
• Confirm switch location and labelling prior to
operation.
Closing HV Switch
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Opening HV Switch
2 of 2 2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Functions: Opening, Closing
Prior to any operation: Rating: 400 amps
Insulant: Air
• Confirm HV switch is fit for service prior to
Voltage: 22kV, 11kV
and after operation.
• Operating handles may differ in construction
however operating principles remain the
same regardless of HV switch make or
voltage.
• If HV switch is vertically mounted operating
instructions may be reversed.
• Confirm switch location and labelling prior to
operation.
Closing HV Switch
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Opening HV Switch
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
EDO HV FUSES
HV Outdoor
Functions: Opening, Closing, HV Fuses
Prior to any operation: Rating: Various
Insulant: Air
• After removing HV fuses care should be
Voltage: 22kV, 11kV, 6.6kV
taken prior to handling as fuses may be hot.
• Ensure HV stick movement maintains
pressure on HV Fuse lower hinged fitting
during closing and opening.
• Warning: HV fuse may be hot.
• EDO Fuses should not be left hanging in
the open position if moisture could enter the
exhaust end of the fuse thus affecting the
fuse performance.
Closing HV Fuse
2
Opening HV Fuse
Removing HV Fuse
EDO HV FUSES
1 of 1
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Functions: Opening, Closing
Prior to any operation Rating: 400 amps
Insulant: Air
• Confirm HV switch is fit for service prior to
Voltage: 22kV, 11kV, 6.6kV
and after operation.
• Operating handles may differ in construction
however operating principles remain the O C
same regardless of HV switch make or
voltage.
• If GAC is mounted vertically operating
instructions may be reversed.
• Confirm switch location and labelling prior to
operation.
Closing HV Switch
Opening HV Switch
1 of 1
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Functions: Opening, Closing
Prior to any operation Rating: 400 amps
Insulant: Air
• Confirm HV switch is fit for service prior to
Voltage: 22kV, 11kV
and after operation.
• Operating handles may differ in construction
however operating principles remain the O C
same regardless of HV switch make or
voltage.
• If GAC is mounted horizontally operating
instructions may be reversed.
• Confirm switch location and labelling prior to
operation.
Closing HV Switch
Opening HV Switch
1 of 1
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
GANG
GANGISOLATORS
ISOLATORS
HV Outdoor
Functions: Opening, Closing
Prior to any operation Rating: 400 amps
Break Rating: Energise/de-energise
• Confirm HV Gang Isolators are fit for service
unloaded trans/line only
prior to and after operation. Insulant: Air
• Confirm switch location and labelling prior to Voltage: 1kV, 6.6kV
operation.
O C
Closing HV Isolators
2
1
Opening HV Isolators
1 of 1
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Functions: Opening, Closing
Prior to any operation Rating: 400 amps
• Confirm the HV switch is fit for service prior Insulant: Air
to and after any operation. Voltage: 22kV, 11kV
O C
2 Pull down the locking pin and rotate to the left to the stop
position.
3 Place the HV operating stick pin in the ‘C’ hook on the raised
side of the operating mechanism crank. 2
2
4 Pull down the operating mechanism crank firmly to the stop
position to CLOSE the HV switch.
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Arc Expulsion Device Latching
2 Pull down the locking pin and rotate to the right to the stop
position.
3 Place the HV operating stick pin in the ‘C’ hook on the raised
side of the operating mechanism crank. 2
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Functions: Opening, Closing
Prior to any operation Rating: 400 amps
Break Rating: 20 amps
• Confirm HV switch is fit for service prior to
Insulant: Air
and after operation. Voltage: 22kV, 11kV, 6.6kV
• Operating handles may differ in construction
however operating principles remain the
same regardless of GFB make or voltage.
• Confirm switch location and labelling prior to
operation.
Closing HV Switch
1 of 1
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Functions: Opening, Closing
Prior to any operation Rating: 8 – 24, 40 -112
• For instructions on opening, closing and Insulant: Air
removal of the sectionaliser refer to the EDO Voltage: 2.7 kV
HV FUSE section in this manual.
• Note: Confirm the Sectionaliser is safe to
handle after removal - it may be hot.
Note: Ensure the latching pin is in the correct position before moving 1
the spring loaded flap.
3
4 Rotate the latching pin to the latch position as shown then
carefully release the spring loaded flap. The sectionaliser is
now ready for service.
Note: Avoid injury to fingers. Release the spring loaded flap carefully.
3
3
1 of 1
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Setting the Sectionaliser DIP Switches
3 Using a small bladed screw driver set the DIP switches to the
required setting.
4 Replace the top cap ensuring the allen key screws are 1
1
tightened firmly to seal against water ingress.
3
ON OFF OFF ON 8 2 40 2
ON OFF ON ON 8 3 40 3
OFF ON ON OFF 16 56 1
OFF ON OFF ON 16 2 56 2
OFF ON ON ON 16 3 56 3
OFF OFF ON ON 20 3 80 3
ON ON ON OFF 24 112 1
ON ON OFF ON 24 2 112 2
ON ON ON ON 24 3 112 3
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Functions: Opening, Closing
Prior to any operation Rating: 200 amps
Break Rating: Energise/de-energise
• Confirm HV switch is fit for service prior to
unloaded trans/line only
and after operation. Insulant: Air
• If HD switch is vertically mounted operating Voltage: 22kV, 11kV, 6.6kV
instructions may be reversed.
• Confirm switch location and labelling prior to
operation.
O C
Closing HV Switch
Opening HV Switch
1 of 1
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV ISOLATORS
HV Outdoor
Functions: Opening, Closing
Prior to any operation Rating: Various
Insulant: Air
• Confirm HV Isolators are fit for service prior Voltage: 66kV, 22kV, 11kV, 6.6kV
to and after operation.
• HV Isolators are NOT to be used to break
load.
• The HV Isolators pictured are a sample of
types used. In most cases the operating
principles, as described below, are the same
regardless of the make or operating voltage.
• Confirm Isolator location and labelling prior to
operation.
Closing HV Isolator
Opening HV Isolator
1 of 1
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Functions: Opening, Closing
Prior to any operation: Rating: 400 amps
Insulant: SF6
• Confirm the HV switch is fit for service prior
Voltage: 22kV, 11kV
to and after operation.
• Confirm correct HV switch gas pressure via
the gas pressure gauge prior to operating.
If the gauge indicates low gas pressure DO
NOT operate the HV switch.
• Confirm the HV switch location and labelling
prior to operation.
1 of 1
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Functions: Opening, Clsoing
Prior to any operation: Rating: Various
• Confirm the gang operated EDO fuses are fit Insulant: Air
for service prior to and after any operation. Voltage: 6.6kV
1 of 1
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Functions: Opening, Closing, Isolation, Auto
Prior to any operation Reclose, O/C Prot.
Rating: Various
• If power supply to ACR is via SWER
Insulant: Oil
transformer carry out Safe to Approach test Voltage: 22kV, 11kV
prior to operation.
• Confirm ACR location and labelling prior to
operation.
• Auto reclose must be suppressed if closing
after lockout operation.
2 Push up operating lever to stop position and hold for app. ten
(10) seconds to CLOSE ACR.
2
2
1 of 1
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Functions: Opening, Closing, Isolation, Auto
Prior to any operation: Reclose, HV Fuses
Rating: Various
• Confirm the ACR and associated apparatus Insulant: Oil
are fit for service prior to and after any Voltage: 2.7kV
operation.
• Ensure the bypass HV EDO fuse is closed
prior to opening the ACR.
• Ensure the correct identification of the
operating lever prior to
insertion of the operating stick.
• Do not leave the bypass HV EDO fuse in the
open position. Remove and stow out of the
weather until required for bypassing the ACR
• Confirm the ACR location and labelling prior
to operation.
• Some ACRs are constructed with only one
HV isolator on the line side and a live line
clamp on the load side. In this case the live
line clamp is lifted and stowed as the second
isolation.
1 Place the operating stick pin into the inner orange / grey
reclose suppression operating lever.
1
2 Pull down the orange / grey operating lever to suppress the
ACR auto reclose.
2
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Closing the ACR – Manually
1 Place the operating stick pin into the outer yellow open /
close operating lever.
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
LM RV ACR
HV Outdoor
Functions: Opening - HV Op Stick / Local
Prior to any operation: Electrical, Closing - HV Op Stick /
Local Electrical, E/F Protection,
• Confirm the ACR is fit for service prior to and Auto Reclose
after any operation. Rating: Various
Insulant: Oil
• The RV ACR is operated manually except for
Voltage: 22kV
those units constructed with the ex ‘SECV’
type control box. Instructions for both are
shown below.
• Confirm the ACR location and labelling prior
to operation.
• Check / confirm oil levels gas pressure
labelling semaphores
• The auto reclose must be suppressed if
closing after lockout operation.
1 Place the HV switch stick operating pin onto the INNER grey 1
operating lever as shown.
1
LM RV ACR
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
LM RV ACR (CONTINUED)
HV Outdoor
Closing the ACR – Manually
2
Opening the ACR - Manually
` 1
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Functions: Opening, Closing
Prior to any operation: Rating: 400 amps
• If required HV switch gas pressure can be Insulant: SF6
Voltage: 22kV
checked at test point adjacent to operating
handle. See insert in main picture.
• Confirm switch location and labelling prior to
operation.
Closing HV Switch
Opening HV Switch
1 of 1
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Functions: Opening, Closing
Prior to any operation: Rating: 400 amps
Insulant: SF6
• If low pressure gas indicator window is
Voltage: 22kV, 11kV
showing red indication do not operate HV
switch.
• For Electrical operation refer to the installed
Control Box in this manual.
• Electrical operation is always the preferred
method of operation.
• Confirm switch location and labelling prior to
operation.
1 of 1
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Functions: Opening, Closing
Prior to any operation: Rating: 400 amps
Insulant: SF6
• If low pressure gas indicator window is
Voltage: 22kV, 11kV
showing red indication, do NOT operate HV
switch.
• Confirm switch location and labelling prior to
operation.
Closing HV Switch
1 of 1
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Functions: Opening, Closing, Trans Switch/
Prior to any operation CB, Earthing, HV Fuses
Rating: 400 Amps
• Confirm the gas switch is fit for service prior Insulant: SF6
to and after any operation. Voltage: 22 kV
• Do not attempt to operate the gas switch if
the low gas pressure red indicator is visible.
• Local electrical operation of this gas switch is
always the preferred method.
• Confirm/check gas pressure and labelling.
• Confirm the gas switch location and labelling
prior to any operation.
and remove the local electrical control access cover. NGK MK1 GAS SWITCH
4 Confirm the ‘POWER’ switch is ‘ON’.
3
Ensure the electrical control access cover is replaced with the wing
nuts tightened and the security padlock in place at the completion of
any operation.
1 of 4
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Opening the Gas Switch – Local Electrically
access cover. 3
10 Replace the access cover and tighten the eight (8) wing
nuts. Lock the security padlock.
Note: Confirm the gas switch has opened via the mechanical
indicator.
Ensure the electrical control access cover is replaced with the wing
nuts tightened and the security padlock in place at the completion of
any operation.
2 Pull down the operating lever to the stop position to close the
gas switch. The indicator will point to ‘MANUAL ON’.
MANUAL REMOTE 2
3 Remove the HV operating stick.
22ofof42
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Opening the Gas Switch – Manually
1 Place the HV operating stick pin into the white (left side) of 4
the gas switch manual operating lever as shown.
ON OFF
2 Pull down the operating lever to the stop position to open the
gas switch. The indicator will point to ‘REMOTE’.
MANUAL REMOTE
3 Remove the HV operating stick. 2
When manually opening the gas switch the following may occur.
• If the electrical control station is disconnected / removed - the gas switch will remain open.
• If the electrical control station is in service and the ‘CONTROL SWITCH’ is in the ‘OFF’ position -
the gas switch will remain open.
• If the electrical control station is in service and the ‘CONTROL SWITCH’ is in the ‘ON’ position -
the gas switch will open then immediately close.
Note: If the gas switch is an isolation point for an Electrical Access
Permit the relevant ‘CONTROL SWITCH’ must be placed in the ‘OFF’
position.
6 Place the HV operating stick into the white (left side) of the ON OFF
gas switch manual operating lever as shown.
7 Pull down the operating lever to the sop position to open the MANUAL REMOTE
gas switch. The indicator will point to REMOTE.
7
8 Remove the HV operating stick.
NOVA ACR
HV Outdoor
Functions: Opening - HV Operating Stick,
Prior to any operation: Auto Reclose
Rating: Various
• Confirm the ACR location and labelling prior
Insulant: Vacuum
to operation. Voltage: 22kV
• Manual opening is only to be done if the ACR
cannot be operated from the control box.
• Confirm the ACR is fit for service prior to and
after any operation.
• Electrical operation of the Nova ACR is the
preferred method of operation. Refer to the
Kyle Form 5 Electronic Control Box template
in this manual for electrical operation details.
• The Nova ACR cannot be closed manually.
The yellow operating lever must be in the
fully raised position to enable electrical
closing of the ACR.
NOVA ACR
1 of 1
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
NULEC ACR
HV Outdoor
Functions: Opening
Prior to any operation:
Rating: Various
• Electrical operation of the Nulec ACR is Insulant: Vacuum
the preferred method of operation. Refer to Voltage: 22kV
the Nulec Electronic Control section of this
manual for electrical operation details.
• The Nulec ACR has a manual lock out lever
as shown in the ‘Opening. ACR - Manually’
instruction below.
• Confirm ACR location and labelling prior to
operation.
• Manual opening only to be used if ACR
cannot be operated from the control box.
NULEC ACR
1 of 1
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Functions: Opening, Closing
Prior to any operation Rating: Various
• Confirm the gas switch / sectionaliser is fit for Insulant: SF6
service prior to and after operation. Voltage: 22 kV
1 Place the HV operating stick pin onto the M/A operating lever 1
as shown.
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Opening the Gas Switch / Sectionaliser
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Functions: Opening – HV Operating Stick,
Prior to any operation: Closing – HV Operating Stick
• Remote operation is always the preferred Rating: 630 amps
method. Insulant: SF6
Voltage: 22kV
• Ensure the remote operation function is
disabled prior to any local manual operation.
Refer to the: Nulec CAPM5 Electronic
Recloser Control template in the Control
Boxes section of this manual for local
electrical operating instructions.
• This unit may be used as an LBS or
sectionaliser.
2 Place the HV operating stick pin onto the red (raised) end of
the manual operating lever.
3
3 Pull down the manual operating lever to the stop position to
CLOSE the switch.
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Opening the Switch - Local Manual
1 Place the HV operating stick pin onto the green (raised) end
of the manual operating lever. 1
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Functions: Opening, Closing, HV Fuses
Prior to any operation: Rating: Various
Insulant: Air
• After removing HV fuses care should be
Voltage: 22kV, 11kV, 6.6kV
taken prior to handling as fuses may be hot.
• Telescopic operating sticks shall NOT be
used to remove or replace Powder Filled
Fuses.
• Fuses may vary in colour as well as rating.
HV fuse mounting fittings may also vary in
design however operating principles remain
the same.
• Inset photo on right shows larger 3 inch (76
mm) diameter fuses.
• Ensure HV stick movement maintains
pressure on HV fuse
lower hinged fitting during opening/closing.
Closing HV Fuse
Opening HV Fuse
Removing HV Fuse
1 of 1
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Functions: Opening - HV Op Stick / Local
Prior to any operation: Electrical, Closing - HV Op Stick
/ Local Electrical, Isolation, E/F
• Confirm the ACR is fit for service prior to and Protection, Auto Reclose
after any operation. Rating: Various
Insulant: Oil
• If the power supply to the ACR is via a SWER
Voltage: 22kV
transformer perform a ‘Safe to Approach’ test
prior to operation.
• This ACR can be operated manually or
electrically. Electrical operation is the
preferred method of operation.
• Confirm the ACR location and labelling prior
to operation.
• Ensure the auto reclose is suppressed prior
to operation of the ACR.
1 Place the operating stick pin into the OUTER operating lever
eye hole as shown. 1
1 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Suppressing the ACR Earth Leakage Prot.
2 Place the operating stick pin into the INNER operating lever
eye hole as shown.
3 Push up the operating lever to the stop position and hold for 4
approximately five (5) seconds to CLOSE the ACR.
3
4 Confirm the semaphore agrees with the ACR status.
2 Place the operating stick pin into the INNER operating lever
eye hole as shown as shown.
2
3 Pull down the operating lever to the stop position to OPEN
the ACR.
3
Reyrolle oyt ACR
4 Confirm the semaphore agrees with the ACR status.
4
22of
of32
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Closing the ACR - Electrically
3 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
RV ACR
HV Outdoor
Functions: Opening, Closing, Auto Reclose,
Prior to any operation: Earth Fault prot., O/C Prot.
• Confirm the ACR is fit for service prior to and Rating: Various
after any operation. Insulant: Oil
Voltage: 22kV
• The RV ACR is operated manually except for
those units constructed with the ex ‘SECV’
type control box. Instructions for both are
shown below.
• Confirm the ACR location and labelling prior
to operation.
• Check / confirm oil levels gas pressure
labelling
• The auto reclose must be suppressed if
closing after lockout operation.
1 Place the HV switch stick operating pin onto the INNER grey
operating lever as shown.
2
RV ACR
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
RV ACR (CONTINUED)
HV Outdoor
Opening the ACR - Manually
1
RV ACR
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
RVE/VWVE ACR
HV Outdoor
Functions: Opening, Closing
Prior to any operation Rating: Various
• Electrical operation of the RVENWVE Insulant: Vacuum/Oil
ACR is the preferred method of operation. Voltage: 22kV, 11kV
Refer to the RVE/VWVE Electronic Control
Box template in this manual for electrical
operation details.
• The RVE/VWVE ACR does not have a
manual auto reclose suppression operating
lever.
• The RVE/VWVE ACR has a manual lock
out lever as shown in the ‘Opening ACR -
Manually’ instruction below.
• Confirm the ACR location and labelling prior
to operation.
• Manual opening only to be used if the ACR
cannot be operated from the control box.
Closing the ACR manually can only be done if the control box
fails and only after direction from control room.
closing.
1
1 Place the HV switch stick operating pin into the yellow
operating lever eye hole as shown.
1 of 1
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Functions: Opening, Closing, Trans Switch/
Prior to any operation: CB, Earthing, HV Fuses
• The Fault Tamer assembly should not be left Rating: Various
in the open position for extended periods of Insulant: Air
Voltage: 22kV, 11kV
time as water may enter and damage the
HV fuse.
• After removing the Fault Tamer assembly
care should be taken prior to handling as the
HV fuse unit may be hot.
• Ensure the HV stick movement maintains
pressure on the Fault Tamer lower hinged
fitting during opening and closing.
• Testing of the back-up limiter must
be performed after every Fault Tamer
operation.
2
1
Opening the Fault Tamer
2 ‘Crack / inch’ open the Fault Tamer and if in order fully lower
the Fault Tamer.
2
S & C FAULT TAMER
Note: The Fault Tamer assembly should not be left in the open
position for extended periods of time as water may enter and
damage the HV fuse tube.
1 of 2
1 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Changing the HV Fuse Element
1 Unscrew the collar nut and remove the fuse tube from the
back of the limiter assembly. 1
Note: Check the condition of the spring and cable assembly and
if damaged replace.
6 Push the upper ferrule down to the stop position (latched).
8 Rotate the red beaded pull tab so that it aligns with the fuse
cartridge assembly.
2 of 2
2 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
9 Insert the fuse cartridge/spring and cable assembly into the
fuse tube as shown and screq on the fuse tube cap and
tighten securely.
10 Using the red beaded pull tab carefully pull the fuse cartridge
through the fuse tube sgsindt the spring tension until the 10
contact fingers epand on the rig contact.
12
13
12 Carefully remove the red beaded pull tab as shown in the
photograph. 13
13 Align the keyways on the fuse tube with the notches in the
S & C FAULT TAMER
exhaust control device.
14 Insert the fuse tube into the exhaust control device and hand
tighten the collar nut.
14
33 of
of 32
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Functions: Opening, Closing
Prior to any operation Rating: 630 Amps
• Confirm the gas switch is fit for service prior Insulant: SF6
to and after any operation. Voltage: 22 kV
SF Gas SF Gas
Pressure NORMAL Pressure LOW
DO NOT OPERATE
1 Confirm the low SF6 gas pressure indicator does not show a 1
red semaphore.
1 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Closing the Gas Switch – Manually
3
1 Confirm the remote operation function is disabled.
3 Place the HV operating stick pin onto the red (raised) end of
4
the manual operating lever.
2 Place the HV operating stick pin onto the green (raised) end
of the manual operating lever.
3
3 Pull down the manual operating lever to the stop position to
OPEN the switch.
22ofof32
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Unlocking the Gas Switch
3 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Functions: Opening, Closing
Prior to any operation: Rating: 400 amps
Insulant: Air
• Confirm HV switch is fit for service prior to
Voltage: 22kV, 11kV
and after operation.
• Operating handles may differ in construction
however operating principles remain the
same regardless of GAC make or voltage.
• Confirm switch location and labelling prior to
operation.
Closing HV Switch
Opening HV Switch
1 of 1
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Functions: Saving of fuse operations on fused
Prior to any operation: spurs
Rating: 4KA
• These are a fuse saving device only.
Insulant: Vacuum Circuit Breaker
• Not to be used for A/R or Total Fire Ban Day Voltage: 24kV
A/R suppressions. Normal A/R suppression
operating procedures apply.
• Not to be used as an isolation point for
normal or emergancy shutdowns. Normal
operating isolation procedures apply.
• These units operate by detecting a fault on a
fused spur/line that they are installed on and
then open for approx 10 sec’s then close. If
the fault is still there they stay closed and the
fuses operate.
• If the fault has cleared the units stay closed.
• They are set set up to operate on SWER
or as single phase (2 unit intsallation) or 3
phase (3 unit installation). One unit will talk to
the others on the installation.
3 Red LED will flash for approx 3-4 sec’s then flash every 2
seconds until opened. (approx 40 sec’s)
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Overriding the Opening or Closing Sequence and Disable the Units
1 Place the operating stick into the external lever and gently
pull down on all units.
2 Once in the down position the units will not detect a fault
and open on all units.
Note: To enable the units again, gently push the external lever to the
up position on all units.
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Functions: Opening, Closing
Prior to any operation: Rating: 400 amps
Insulant: Air
• Confirm HV switch is fit for service prior to
Voltage: 22kV, 11kV, 6.6kV
and after operation.
• Confirm switch location and labelling prior to
operation.
Closing HV Switch
1
1 Prior to opening HV switch confirm arc chute latching elbow
is over-centre as shown.
Opening HV Switch
1 of 1
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Functions: Opening, Closing
Prior to any operation: Rating: 250 amps
Insulant: Air
• Confirm the isolators have been cut in and
Voltage: 22kV, 11kV, 6.6kV
the conductors tied back prior to operating.
• When opening and closing the isolators
ensure the HV operating stick movement
DOES NOT cause the conductors to swing.
• Confirm the isolators have latched correctly
prior to and after operation.
• Confirm HV switch is fit for service prior to
and after operation.
1 of 1
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Functions: Opening, Closing
Prior to any operation: Rating: 200 amps
Insulant: Vacuum
• Ensure all three (3) vacuum switches are
Voltage: 22kV, 11kV
opened / closed correctly. Electrical operation
is always the preferred method.
• For electrical operation of these vacuum
switches refer to the relevant templates in
this manual:
• Confirm the capacitor bank location and
labelling prior to operation. Electrical
operation is always the preferred method.
Ensure all three (3) vacuum switches are
opened correctly.
1 Place the HV operating stick pin in the yellow eye hole of the
vacuum switch operating lever.
1 Place the HV operating stick pin in the yellow eye hole of the
vacuum switch operating lever.
1 of 1
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Functions: Opening, Closing, Auto reclose,
Prior to any operation: Earth Fault Prot., LL Sequences
Rating: 630 amps
• Confirm ACR is fit for service prior to and Insulant: SF6, Vacuum
after operation. Voltage: 22kV
• Control relay has programmable default
settings. Condition of the protection settings
should be checked after each operation.
• Confirm ACR location and labelling prior to
operation.
• Manual opening only to be used if ACR
cannot be operated from the control box.
• Auto reclose must be suppressed prior to
closing ACR
1 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Opening ACR - Manually
22ofof32
VESI Switchgear Manual Copyright © 2015
CONTENTS
HV Outdoor
HV Outdoor
Suppression of ACR Remote Control
3 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
LINE REGULATORS
Line Regulators
Functions: Opening, Closing, Isolation, Tap
Prior to any operation: Changing - Electrical / Manual
• Ensure the regulator is on the neutral tap Rating: 5 kVA
prior to closing the HV by-pass switch. Insulant: Oil/Air
Voltage: 22 kV
• Adjusting the regulator tap by more than
three (3) positions in either direction may
adversely effect volts.
• The regulator neutral tap position number is
shown on the sign adjacent to the by-pass
switch operating handle.
1 of 3
2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Closing the Regulator HV By-pass Switch
2 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
5 Rotate the operating handle in the required direction to raise
or lower the regulator tap.
4
6 Confirm the correct tap position via the mechanical tap
position indicator.
9 Release the mechanism brake and turn the drum until the 6
clutch operating rod is fully returned – the mechanical access
flap is returned to the position as shown.
3 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Functions: Opening, Closing, Isolation, Tap
Prior to any operation: Changing - Electrical / Manual
Rating: Various
• Confirm the regulator and associated Insulant: Oil/Air
apparatus are fit for service prior to and after Voltage: 22kV
any operation.
• Ensure the regulator is on the neutral tap
prior to closing the HV by-pass switch.
• Adjusting the regulator tap by more than
three (3) positions in either direction may
adversely effect volts.
• Note the regulator neutral tap position
number is shown on the sign adjacent to the
by-pass switch operating handle.
2 Raise / lower the regulator tap via the voltage control ‘RAISE
/ LOWER’ push buttons until the tap indicator points to the
neutral tap position.
Note: Ensure the mechanical tap position indicator points to the neutral tap position.
1 of 3
2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Closing the Regulator HV By-pass Switch
Note: Ensure the regulator is on the neutral tap and LV supply is ‘OFF’
prior to closing the HV by-pass switch. 2
1 Confirm the regulator is on the neutral tap and the LV supply
is ‘OFF’.
2 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Changing the Regulator Tap - Manually
3 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Functions: Opening, Closing, Isolation, Tap
Prior to any operation: Changing - Electrical / Manual
• Confirm the regulator and associated Rating: Various
apparatus are fit for service prior to and after Insulant: Oil/Air
Voltage: 22kV
any operation.
• Ensure the regulator is on the neutral tap
prior to closing the HV by-pass switch.
• Adjusting the regulator tap by more than
three (3) positions in either direction may
adversely effect volts.
• The regulator neutral tap position number is
shown on the sign adjacent to the by-pass
switch operating handle.
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Closing the Regulator HV By-pass Switch
Note: Ensure the regulator is on the neutral tap and LV supply is ‘OFF’
prior to closing the HV by-pass switch.
2
1 Confirm the regulator is on the neutral tap and the LV supply
is ‘OFF’.
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Functions: Functions: Opening, Closing,
Prior to any operation: Isolation, HV Fuses,Tap
Changing - Electric / Manual
• Ensure the regulator is on the neutral tap Rating: 300 KVA
(0) prior to closing / opening the by-pass HV Insulant: Oil
fuse. Voltage: 22kV
• Adjusting the regulator tap by more than
three (3) tap positions may adversely effect
volts.
• This regulator maintains continuous voltage
regulation and as a consequence there are
no definite tap positions. The neutral indicator
light is provided to show when the input
and output voltages are equal. This is the
regulators neutral tap position (0).
3 Press and hold the ‘LOWER’ button until the tap position
motor stops running. 2
4 Confirm the regulator is in the neutral tap position by the
illumination of the ‘NEUTRAL POSITION’ indicating light. 5
5 Confirm the regulator neutral tap position by the mechanical
tap position indicator.
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Closing the Regulator By-pass HV EDO Fuse
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Functions: Opening, Closing, HV Fuses
Prior to any operation: Insulant: Oil/Air
• Ensure the regulators are on the neutral tap - Voltage: 22 KV
tap position ‘0’ – and the Auto/Remote toggle
switch is in the OFF position, prior to closing
the by-pass HV isolators.
• Adjusting the regulator tap in either direction
will change output voltage by 200 Volts per
tap. When changing taps care should be
taken to limit any adverse effect to the output
voltage.
• These single phase regulators can be
constructed in various combinations e.g.
Note: Confirm the mechanical tap position indicator points to the neutral
tap position ‘0’ on each regulator unit.
If the neutral tap position ‘0’ cannot be confirmed by the three methods
described - points 5,6 and 10 - then do not proceed any further.
1 of 5
2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
6 Press the ‘TAP POSITION’ keypad ‘4’ and confirm the LCD
screen displays Neutral Tap 0.
2 of 5
2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Placing the Regulators Into Service 1
Note: All three methods of neutral tap position ‘0’ verification must be
confirmed prior to placing the regulators into service.
5 Confirm the neutral tap position ‘0’ via the control panel.
Refer to the Confirming Neutral Tap Position Via Control
10
3 of 5
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Main Screen Menu Navigation
The diamond shaped keypad has three modes of user interface (listed below) with three
levels of nested menu structures:
• Numeric Keys
• Short-cut Keys
• Scroll Keys
The Escape key is used to step back or exit the sub menus. Repeated pressin gof the
Escape key will return the display to the Level 1 main
menu.
Short-cut Key
Keys
provide an instant display of
commonly request diagnostic
data as per the key label.
Keys
provide an instant access to
level 2 of the level 1 main
menu items as per the
key label.
4 of 52
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Scroll Keys
5 of 5
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Functions: Opening, Closing, Isolation, Tap
Prior to any operation: Changing - Electrical
• Confirm the regulators and associated Rating: Various
apparatus are fit for service prior to and after Insulant: Oil/Air
any operation. Voltage: 22kV
1 of 3
2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Confirming the Neutral Tap Position Via Control Box
Note: If the neutral tap position ‘0’ cannot be confirmed by the three
methods described - points 3,4 and 8 – then do not proceed
any further.
2 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Placing the Regulators Into Service
1
Note: All three methods of neutral tap position ‘0’ verification must be
confirmed prior to placing the regulators into service.
5 Confirm the regulators are on the neutral tap ‘0’ via the
indicating lights in the control boxes.
6 Confirm the neutral tap positions ‘0’ via the control panel.
Refer to the ‘Confirming Neutral Tap Position Via Control
Box’ instruction on the previous page.
3 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Functions: Opening, Closing, Isolation, Tap
Prior to any operation: Changing - Electrical
• Ensure the regulator is on the neutral tap Rating: 5 Kva
prior to closing the HV by-pass switch. Insulant: Oil/Air
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Closing the Regulator HV By-pass Switch
Note: By-pass switches may vary in make and type. Refer to appropriate
sections of this manual for operating instructions if required.
2 2
Changing the Regulator Tap - Manually
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Functions: Opening, Closing, Isolation, Tap
Changing - Electrical
Prior to any operation:
Insulant: Oil
• Ensure the regulator is on the neutral tap-tap Voltage: 22kV
position 1 – prior to closing the by-pass HV
EDO fuse.
• Adjusting the regulator tap by more than
three (3) positions in either direction may
adversely affect volts
Note: If the indicating light has not illuminated, check the condition
of the globe and replace if required. 2
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Closing the Regulator By-pass HV EDO Fuse
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
MODEL: GE-2011C VOLTAGE
Prior to any operation: REGULATOR CONTROL
Functions: Opening, Closing, Isolation, Tap
• Confirm the regulators and associated Changing - Electrical
apparatus are fit for service prior to entering Insulant: Oil/Air
and after exiting the regulator enclosure. Voltage: 22kV
• The neutral tap position for this regulator is ‘0’.
• Warning: Ensure the regulators are on
the neutral tap - tap position ‘0’ - prior to
operating the by-pass gas switch.
• Note adjusting the regulator tap by more
than six (6) positions in either direction may
adversely affect volts.
• Press the ‘Ent’ key to turn on the control
panel display - Press the ‘Exit’ key to exit the
display.
• Check and confirm oil levels, labeling and
semaphores
1 of 3
2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Confirming the Regulator Neutral Tap Position – continued
Note: If the neutral tap position ‘0’ cannot be confirmed by the three methods described - Neutral light,
mechanical indicator and display values - DO NOT PROCEED ANY FURTHER.
Note: All three methods of neutral tap position ‘0’ verification must be
confirmed prior to closing the bypass gas switch.
2 Confirm all the regulator units are on the neutral tap ‘0’.
Note: All three methods of neutral tap position ‘0’ verification must be
confirmed prior to isolating the regulators into service.
5 4
2 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
1 Confirm the regulator units bypass gas switch is closed.
2 Confirm all the regulator units are on the neutral tap ‘0’.
3 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Functions: Opening, Closing, Isolation, Tap
Prior to any operation: Changing - Electrical
Rating: Various
• Ensure regulator is on neutral tap ‘0’ prior to Insulant: Oil/Air
closing by-pass HV isolator. Voltage: 22kV
1
Isolating Regulator
3 11 of
of 12
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Functions: Opening, Closing, Isolation, Tap
Prior to any operation: Changing - Electrical
• The neutral tap position for this regulator Rating: 2000 Kva
is tap position ‘11’. This regulator can only Insulant: Oil/ Air/ SF6
boost the output voltage. Voltage: 22 KV
1 of 4
2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Closing the Regulator HV By-pass Switch
Note: HV isolating switches may vary in make and type. Refer to the 3
appropriate sections of this manual for operating instructions if required. 3
2 of 4
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Lowering the Regulator Tap – Manually
1 Rotate the over-travel stop plate 180 degrees ACW from the
lower position A to the upper position B as shown. 1
2 Insert the operating handle onto the over-travel stop plate so
the drive pin is on the CW side of the stop pin as shown.
3 of 4
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Re-engaging the Tap Change Drive Coupling
2 Rotate the operating handle slightly until the upper and lower
drive couplings align with the previously placed alignment
marks as shown. 2
4 of 4
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Functions: Opening, Closing, Isolation, Tap
Prior to any operation: Changing - Electric / Manual
Rating: 100KVA
• Confirm the regulator and associated Insulant: Oil
apparatus are fit for service prior to and after Voltage: 12.7kV
any operation.
• Ensure the regulator is on the neutral tap
prior to closing the HV by-pass switch.
• Adjusting the regulator tap by more than
three (3) positions in either direction may
adversely affect volt.
• The regulator by-pass HV fuse is not to be
left hanging open for extended periods of
time. This will prevent water ingress into the
fuse tube.
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Closing the Regulator By-pass HV EDO Fuse
1 Confirm the regulator is on the neutral tap (0%) and the by-
pass HV EDO fuse is closed.
1
2 OPEN the regulator line and load side fuses.
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Functions: Opening, Closing, Isolation, Tap
Prior to any operations: Changing - Electric / Manual
Rating: Various
• Confirm the regulator and associated Insulant: Oil/Air
apparatus are fit for service prior to and after Voltage: 22kV
any operation.
• Ensure the regulator is on the neutral tap
prior to closing the HV by-pass switch.
• Adjusting the regulator tap by more than
three (3) positions in either direction may
adversely affect volts.
• The regulator neutral tap position number is
shown on the sign adjacent to the by-pass
switch operating handle.
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Closing the Regulator HV By-pass Switch
2
1 Confirm the regulator is on the neutral tap and the LV supply
is ‘OFF’.
2
Changing the Regulator Tap – Manually
Note: Confirm the correct tap position via the mechanical tap position 1
indicator.
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Functions: Opening, Closing, Isolation, Tap
Prior to any operation: Changing - Electric / Manual
• Confirm the regulator and associated Rating: Various
Insulant: Oil/Air
apparatus are fit for service prior to and after
Voltage: 22kV
any operation.
• Ensure the regulator is on the neutral tap
prior to closing the HV by-pass switch.
• Adjusting the regulator tap by more than
three (3) positions in either direction may
adversely effect volts.
• This regulator has two (2) versions of the tap
changer control box. Both are shown below.
1 of 3
2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Adjusting the Regulator to Neutral Tap - Electrical (Control Box Type 2)
2 Raise / lower the regulator tap via the voltage control ‘RAISE
/ LOWER’ push buttons until the tap indicator points to the
neutral tap position.
Note: By-pass switches may vary in make and type. Refer to the
appropriate templates
2 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Changing the Regulator Tap - Manually
3 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Functions: Opening, Closing, Trans Switch/
Prior to any operation: CB, Earthing, HV Fuses
• Ensure the regulator is on the neutral tap Rating: Various
prior to closing the HV by-pass switch. Insulant: Oil/ Air
Voltage: 22 KV
• Adjusting the regulator tap by more than
three (3) positions in either direction may
adversely effect volts.
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Closing the Regulator HV By-pass Switch
Note: By-pass switches may vary in make and type. Refer to appropriate
sections of this manual for operating instructions if required.
Note: Isolating switches may vary in make and type. Refer to appropriate
sections of this manual for operating instructions if required.
2
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Prior to any operation: Functions: Opening, Closing, Tap Changing
Rating: 12.8 MVA
• The regulator supervisory control must be Insulant: Oil/ Air
placed in the ‘LOCAL’ position prior to any Voltage: 22 kV
local operation.
• Ensure the regulator is on the neutral tap
prior to closing the HV by-pass switch.
• Check/confirm oil levels, labeling and
semaphores.
Notes: Adjusting the regulator tap by more than three
(3) positions in either direction may adversely effect
volts.
11 of
of 52
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Control Panel Type B
Adjusting the Regulator to Neutral Tap – Electrical
3
1 Open the regulator control cabinet door.
2
2
22 of
of 52
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Opening the Regulator HV Isolating Switches
Note: Isolating switches may vary in make and type. Refer to appropriate
sections of this manual for operating instructions if required.
33ofof52
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
6 Insert the manual tap change handle into the manual tap
change mechanism as shown.
Note: Confirm the tap position via the mechanical indicator at the
completion of the manual tap change operation.
9
9
9 9
44ofof52
VESI Switchgear Manual Copyright © 2015
CONTENTS
Line Regulators
Line Regulators
Control Panel Type B
Changing the Regulator Tap - Manually 12
12
Changing the Regulator Rating – Manually
Confirm the regulator is on the new neutral tap ‘1’ before re-energising
the regulator.
5 of 5
2
VESI Switchgear Manual Copyright © 2015
CONTENTS
CONTROL BOXES
Control Boxes
Functions: Opening, Closing
Prior to any operation Rating: N/A
Insulant: N/A
• Confirm the capacitor units are fit for service
Voltage: N/A
prior to and after operation.
• Ensure all three capacitor vacuum switches
have operated correctly.
• The capacitor bank vacuum switches cannot
be closed for app. five (5) minutes after being
opened.
• Confirm the control box location and labelling
prior to operation.
1 Press the OPEN button. The OPEN PENDING LED will flash
for ten (10) seconds prior to the vacuum switches opening. 1 1
2 Confirm all three vacuum switches have opened correctly.
1 of 1
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Functions: Opening, Closing
Prior to any operation: Rating: N/A
• Confirm the capacitor units are fit for service Insulant: N/A
prior to and after operation. Voltage: N/A
1 of 1
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Functions: Opening, Closing
Prior to any operation Rating: N/A
Insulant: N/A
• Confirm the capacitor units are fit for service
Voltage: N/A
prior to and after operation.
• Ensure all three capacitor vacuum switches
have operated correctly.
• The capacitor bank vacuum switches cannot
be closed for app. five (5) minutes after being
opened.
• Confirm the control box location and labelling
prior to operation.
1 of 1
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Functions: Opening, Closing
Prior to any operation Rating: N/A
Insulant: N/A
• Confirm the capacitor units are fit for service
Voltage: N/A
prior to and after operation.
• Ensure all three capacitor vacuum switches
have operated correctly.
• Note the capacitor bank vacuum switches
cannot be closed for app. five (5) minutes
after being opened.
• Confirm the control box location and labelling
prior to operation.
1 of 1
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Functions: Open, Close, Electrical Local/
Prior to any operation: Remote, Fault Indicator
• This control box is only used with NGK Gas Insulant: N/A
Automatable HV Switches. Voltage: N/A
Note: If the gas switch is an isolation point for an Access Permit then
the selector switch must be placed in the ‘MANUAL’ position after
opening the gas switch. 1
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Resetting the Fault Indicators
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Operation Options:
Opening, Closing
Prior to any operation: Rating: N/A
Insulant: N/A
• Confirm the capacitor units are fit for service
Voltage: 22kV
prior to and after operation.
• Ensure all three capacitor vacuum switches
have operated correctly.
• Note: The capacitor bank vacuum switches
cannot be closed for app. five (5) minutes
after being opened.
• Confirm the control box location and labelling
prior to operation.
1
2
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Closing of Capacitor Bank
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Functions: Open, Close, Electrical Local/
Prior to any operation
Remote, Fault Indicator
• This control box may control various types of Rating: N/A
ACR. Confirm the ACR type on site prior to Insulant: N/A
operation. Voltage: N/A
Note: The auto reclose must be supressed before closing the ACR
after lockout.
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Opening the ACR – Locally Electrically
2 Rotate the ACR control lever ACW to the stop position and
3
release.
4 2
3 Rotate the ACR control lever CW to the stop position and
hold for approximately five (5) seconds then release to close
the ACR.
Note: Receive instruction from the Control Room before reclosing the
ACR.
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Functions: Open, Close, Electrical Local/
Prior to any operation Remote, Fault Indicator
Rating: N/A
• For Common Function Codes refer to the Insulant: N/A
table on page 4 of this section. Voltage: N/A
• Warning: Suppressing the ACR remote
control locally via the toggle switch will
remove any suppressions applied via a
supervisory signal from the control room. (ie.
Controller suppression of the ground trip or
reclose function.) Check the LCD indicators
on the local control panel for the actual status
of the ACR
• Confirm the ACR location and labelling prior
to any operation.
Note: If required log the data and report to the appropriate personnel.
1 of 4
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
LCD Indicators – Accessory Operation
Note: If required log the data and report to the appropriate personnel.
Note: If required log the data and report to the appropriate personnel.
22ofof42
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
LCD Indicators – Non Recloser Active
Note: If required log the data and report to the appropriate personnel.
Note: If required log the data and report to the appropriate personnel.
3 of 4
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
LCD Indicators – Recloser Closed
CODE FUNCTION
30 EXAMINE TARGETS
32 EXAMINE TARGET COUNTER GROUND
33 EXAMINE TARGET COUNTER 1-2 A PHASE
34 EXAMINE TARGET COUNTER 3-4 B PHASE
35 EXAMINE TARGET COUNTER 5-6 C PHASE
4 of 4
2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Functions: Open, Close, Electrical Local/
Prior to any operation Remote, Fault Indicator
Rating: N/A
• This control box is used with the NGK Gas
Insulant: N/A
Automatable HV switches and RVE/VWVE Voltage: N/A
auto circuit reclosers.
• For fault interrogation, refer to ‘Kyle Form C
Electronic Recloser Basic Functionality’ in
this section.
• WARNING. Suppressing the ACR remote
control locally via the toggle switch will
remove any suppressions applied via a
supervisory signal from the control room (ie
Controller suppression of the ground trip or
reclose function). Check the LCD indicators
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Suppressing the ACR Earth Leakage Prot.
Note: The auto reclose must be suppressed before closing the ACR
after lockout.
1
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Functions: Open, Close, Electrical Local/
Prior to any operation: Remote, Fault Indicator
Rating: N/A
• This control box can be used with the NGK Insulant: N/A
Gas Automatable HV switches. LM RVE / Voltage: N/A
VWVE ACRs and Nova ACRs.
• Note: There are two (2) versions of this
control box (both shown in the main
picture). The layout of the control buttons
differ, however the functionality remains
the same for both units. Ensure the
correct identification of buttons prior to any
operation.
• All instructions here refer to Version 1 of
the control box.
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Enabling of ACR Live Line Sequence
Note: ACR will not close whilst live line sequence is enabled..
1
Closing the ACR – Electrically
1
1 Press the ‘CHANGE’ button then press the ‘SUPERVISORY
BLOCKED’ button to disable remote operation.
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Functions: Open, Close, Electrical Local/
Prior to any operation: Remote, Fault Indicator
Rating: N/A
• This control box can be used with the NGK Insulant: N/A
Gas Automatable HV switches. LM RVE / Voltage: 22 KV
VWVE ACRs and Nova ACRs.
• Note: There are two (2) versions of this
control box (both shown in the main
picture). The layout of the control buttons
differ, however the functionality remains
the same for both units. Ensure the
correct identification of buttons prior to any
operation.
• All instructions here refer to Version 1 of
the control box.
• Confirm ACR/switch location2and labelling
prior to operation.
1 of 4
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Auto Reclose Suppression
3 2
Note: Placing the HOT LINE TAG switch “ON” places the ACR
protection to minimum trip operation and its fastest inverse time
curve.
1 Move the ‘HOT LINE TAG’ toggle switch to the “ON” position
(This will enable Live Line sequence).
2 of 4
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Closing the ACR
Note- This will not close the unit but will allow the unit to be closed at
the control panel
1
At the Controller
3
4
At the Controller
2
2 Press the ‘CHANGE’ button
3
4 Press the green ‘TRIP’ button to OPEN the ACR
3 of 4
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
KYLE
KYLEFORM
FORM66CONTROLLER
CONTROLLER(CONTINUED)
(CONTINUED)
Control Boxes
At the SWER ACR unit
Note: This is how you will find the unit if it has gone to lock out
4 of 4
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Functions: Opening, Closing
Prior to any operation: Rating: N/A
Insulant: SF6
• If equipped with a gas indication gauge
Voltage: 22kV
check for adequate pressure prior to
switching.
• Confirm the remote / local switch is in the
remote position Confirm HV switch location
and labelling prior to operation.
• For any local operation ensure the “Remote
/ Local” (R/L) switch is in the “Local” (L)
position
• Prior to local electrical operation confirm the
Note: The “Operator Safety Switch” inhibits any close control, both
local & remote for the HV switches
1 of 1
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Functions: Opening, Closing, Isolation
Prior to any operation: Rating: N/A
Insulant: N/A
• Remote operation is always the preferred
Voltage: N/A
method of operation. This control box is only
used on NGK gas switches.
• Confirm the gas switch is fit for service prior
to operating.
• Note: If the gas switch is an isolation point
for an Access Permit then the following must
be done:
• The ‘LOCAL / REM’ switch must be in
the ‘LOCAL’ position.
• The ‘DIS / ENA’ switch must be in the
‘DIS’ position.
• Confirm the gas switch location and labelling
5 Confirm the status of the gas switch via the indicating LEDs
and semaphore.
6 4
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Closing the Gas Switch – Local Electrical
2 3
5 Confirm the status of the gas switch via the indicating LEDs
Note: Confirm the ‘GAS OK’ and ‘HANDLE REMOTE’ LEDs are on.
6 4
If either is off, then the gas switch cannot be controlled locally or
remotely.
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Functions: Remote Electrical Open Close,
Prior to any operation Open Close Local Electric, Switch
Stick Open Close, Lock and Tag,
• Remote operation is always the preferred Spring Charge
method of operation. This control box Voltage: N/A
is only used on NGK gas switches. For
remote operation the gas switch MANUAL
ON/REMOTE semaphore must indicate
REMOTE on the switch (white handle down).
• Confirm the gas switch is fit for service prior
to operating.
• Note: If the gas switch is an isolation point
for an Access Permit then the following must
be done:
NGKSTANGERGCR100/300GASSWITCHCONTROL
• The ‘LOCAL / REM’ switch must be in
the ‘LOCAL’ position.
• The ‘DIS / ENA’ switch must be in the
‘DIS’ position.
• Confirm the gas switch location and labelling
prior to operation.
5 Confirm the status of the gas switch via the indicating LEDs
2 3
and semaphore.
Note: Confirm the ‘GAS OK’ and ‘HANDLE REMOTE’ LEDs are on.
If either is off, then the gas switch cannot be controlled locally or
remotely.
6
5
1 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Opening the Gas Switch – Local Electrical
5 Confirm the status of the gas switch via the indicating LEDs
and semaphore. 2 3
Note: Confirm the ‘GAS OK’ and ‘HANDLE REMOTE’ LEDs are on.
2 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Opening the Gas Switch - Manually
3 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Functions: Opening, Closing, Auto-reclose
Prior to any operation Suppression
• Confirm the ACR is fit for service prior to Rating: N/A
operating. Insulant: N/A
Voltage: 22 kV
• Confirm the ACR location and labelling prior
to operation.
1 of 4
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Electronic Operation of ACR
At the Controller
2 Press the OPEN button once (This will open the ACR unit) 2
At the Controller
At the Controller
2 of 4
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Selecting Alternative Active Group
At the Controller
Disable Protection
3 of 4
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Mechanical Operation of ACR
Functions:
• When the yellow ring is pulled down the ring
will mechanically open the ACR. The ACR
does not need to be in local control to open
via the yellow ring.
• When the ring is left down this prevents local
and remote control of the ACR.
• When pushed up, this will allow local and
remote operation of the ACR.
• The ACR can only be closed by using the
control panel or by remote control.
4 of 4
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Functions: Opening, Closing, Auto Reclose,
Prior to any operation: Earth Fault Prot.
Rating: N/A
• The ACR supervisory control must be Insulant: N/A
suppressed before any local control can be Voltage: N/A
achieved.
• Supervisory control must be suppressed for
Electrical Access Permit issue.
• Confirm ACR location and labelling prior to
operation.
• If the control panel display does not activate
after pressing the ON/OFF
PANEL
pad, press the
once.
1 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Closing ACR – Electrically
Notes: If closing onto a de-energised line the ‘Cold Load’ option must
1
be set. Refer to ‘Selecting Cold Load Pickup’ instruction.
Auto reclose must be suppressed before closing ACR after lockout.
1
3
Suppressing of ACR Auto Reclose
3 Press the ‘AUTO ON/OFF’ pad once - ‘Reclose On’ will flash 4
on the screen. Press the pad again to change screen to read
‘Reclose Off’.
1
4 Press the ‘ENTER’ pad to accept the changed state i.e.
Reclose Suppressed. 3
2 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Suppressing of ACR Earth Leakage & Sensitive E/L Prot.
3 Press the ‘EARTH PROT’ pad once - ‘Earth Fault On & SEF
On’ will flash on the screen. Press the pad again to change
screen to read ‘Earth Fault Off & SEF Off’.
2 Press the ‘EARTH PROT’ pad once - ‘Earth Fault Off & SEF
2
3 Press the ‘COLD LOAD’ pad once - ‘Cold Load Pickup’ will
flash on the screen. Press the pad again to change screen to
read ‘Cold Load Pickup On’.
3 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Functions: Open, Close, Electrical Local/
Prior to any operation Remote, Fault Indicaton
Insulant: N/A
• The ‘COLD LOAD PICK UP’ function on this
Voltage: N/A
control box is automatic.
• Only a local user can apply/remove the
‘WORK TAG’ when the Control Box is in the
‘LOCAL’ mode.
• Only a remote user can apply/remove the
‘WORK TAG’ when the Control Box is in the
‘REMOTE’ mode.
• The recloser cannot be closed by any means
when the ‘WORK TAG’ is applied.
• Confirm the ACR location and labelling prior
to operation.
1 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Suppressing the ACR Auto Reclose
2 Press the ‘AUTO ON/OFF’ pad once - ‘Auto Reclose ON’ will
display on the screen. Press the pad again to change screen
to read ‘Auto Reclose OFF -Single Shot Active’.
2 3
2 Press the ‘EARTH PROT’ pad once - ‘E/F ON / SEF ON’ will
1 Press the ‘EARTH PROT’ pad once - ‘E/F OFF / SEF OFF’
will display on the screen. Press the pad again and the Earth
Fault component will change to ‘E/F ON’. Press the pad
again and the SEF component will change to ‘SEF ON’.
2 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Opening the ACR – Local Electrically
1
3
Note: The Cold Load Pickup option is automatic on this control box.
Auto Reclose must be suppressed prior to closing the ACR 1
2 Press the ‘WORK TAG’ pad once - ‘WORK TAG OFF’ will be
displayed on the screen. Press the pad again to change the
screen to read ‘WORK TAG APPLIED.
Note: If the Work Tag is applied locally and the ACR control is left in
the LOCAL setting, the ACR cannot be closed remotely and the Work
Tag cannot be removed remotely.
3 2
Note: To switch off the Work Tag, reverse the above instruction.
3 of 3
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Functions: Remote Electrical Open Close,
Prior to any operation: Open Close Local Electric, Earth
Fault Protection, Overcurrent
• This electronic control box can be
Protection, Targets, Digital
programmed to operate the gas switch as a
Readout
sectionaliser. There are three (3) settings for
the sectionaliser mode. They are as follows:
• Sectionaliser on.
• Sectionaliser off.
• Sectionaliser one (1) shot to lockout.
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Opening the Gas Switch / Sectionaliser – Electrical
1
3
Resetting Targets
1
4
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Functions: Push button Open Close, Earth
Prior to any operation Fault Protection, Auto Reclose,
Digital Readout
• Loop Automation Scheme maybe feeder or Rating: N/A
tie ACRs. Voltage: 22 kV
• Note: Switching the Control Box to ‘LOCAL’
does not disable the Loop Automation. If the
Loop Automation feature is active ACRs may
operate at any time.
• Note: Special access precautions apply for
work on or adjacent to the Loop Automation
Scheme. Refer to the Distribution Operations
Procedures.
• If required, refer to the Nulec Control Box
Operation Flow Chart template in this
Caution: Suppression of the remote control does not disable the Loop
Automation Scheme.
1,2
Note: Supervisory control must be suppressed before any local
control can be achieved. Supervisory control must be suppressed for
electrical access permit issue.
3
1 of 5
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Disabling the Loop Automation Scheme – Local
Note: The Loop Automation Scheme can be enabled via SCADA from 4
the Control Room. This is the preferred method of disabling the Loop
Automation Scheme.
All ACRs in the Loop Automation Scheme should be enabled. Refer to
the Control Room for details if required.
5
22ofof52
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Closing the ACR Electrically - Local
Note: The Auto Reclose must be suppressed prior to closing the ACR. 2
The Cold Load Pickup option is automatic on this control box.
2
4
3 Press the ‘AUTO ON/OFF’ pad once - ‘Auto Reclose ON’ will
display on the screen. Press the pad again to change screen
to read ‘Auto Reclose OFF -Single Shot Active’.
Note: The Auto Reclose must be suppressed prior to closing the ACR
3 4
electrically - local.
3 of 5
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Suppressing the ACR Earth Leakage & Sensitive E/L Prot.
Note: Earth Fault (E/F) & Sensitive Earth Fault (SEF) protection must
be suppressed prior to operating the ACR by-pass switch.
3 Press the ‘EARTH PROT’ pad once - ‘E/F ON / SEF ON’ will
3
be displayed on the screen. Press the pad again to change
the screen to read ‘E/F OFF / SEF OFF’.
2 Press the ‘EARTH PROT’ pad once - ‘E/F OFF / SEF OFF’
will display on the screen. Press the pad again and the Earth
Fault component will change to ‘E/F ON’. Press the pad
again and the SEF component will change to ‘SEF ON’.
2 Press the ‘WORK TAG’ pad once - ‘WORK TAG OFF’ will be
displayed on the screen. Press the pad again to change the
screen to read ‘WORK TAG APPLIED.
Note: If the Work Tag is applied locally and the ACR control is left in
the LOCAL setting the ACR cannot be closed remotely and the Work 3 2
Tag cannot be removed remotely.
4 of 52
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Switching off the Work Tag Feature - Locally
Note: If the Work Tag is applied locally and the ACR control is left in
3 2
the LOCAL setting the ACR cannot be closed remotely and the Work
Tag cannot be removed remotely.
5 of 5
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Functions: Opening, Closing, Auto Reclose,
Prior to any operation: Earth Fault Prot.
• Confirm the capacitor units are fit for service Rating: N/A
Insulant: N/A
prior to and after operation.
Voltage: N/A
• Ensure all three capacitor vacuum switches
have operated correctly.
• The capacitor bank vacuum switches cannot
be closed for app. five (5) minutes after being
opened.
• Confirm the control box location and labelling
prior to operation.
• Ensure all three vacuum switches have
opened correctly.
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Closing the Capacitor Vacuum Switches
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Operation Options:
Local Electrical, Opening/
Prior to operation: Closing – Local Electrical
• This control box controls the ABB Pole Top Rating: N/A
Insulant: N/A
Capacitors.
Voltage: N/A
• Confirm the capacitor units are fit for service
prior to and after any operation.
• Ensure all three capacitor vacuum switches
have operated correctly.
• Note: The capacitor bank vacuum switches
cannot be closed for app. five (5) minutes
after being opened.
• Note: The ‘OPERATION MODE’ must be set
7 Confirm all three (3) capacitor module CBs have opened and
the ‘OPEN’ LED ceases blinking.
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
8 Press the ‘OPERATIONAL MODE’ ‘CHANGE’ button to to
switch the control to ‘AUTO’ and confirm the red ‘AUTO’ LED
illuminates.
8
9 Press the ‘SCADA CONTROL’ ‘CHANGE’ button to switch
the control to ‘REMOTE’ and confirm the red ‘REMOTE’ LED
illuminates.
7 Confirm all three (3) capacitor module CBs have closed and
the ‘CLOSE’ LED ceases blinking.
8 9
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Functions: Remote Electrical Open Close,
Prior to any operation Push Button Open Close, Earth
Fault Protection, Auto Reclose,
• Confirm the ACR is fit for service prior to and Digital Readout
after any operation. Insulant: N/A
• Note: Opening the access door activates the Voltage: 22 kV
control box panel.
• Note: When activated the control panel LCD
will firstly display the ACR name and location
followed by the TRIP FLAGS screen.
• The ‘LOOP AUTOMATION’ scheme (if fitted)
can only be disabled via SCADA from the
Control Room.
SchneiderNulecACR2ElectronicControlBox
• The recloser cannot be closed by any means
when the ‘WORK TAG’ is applied.
• Confirm the ACR location and labelling prior
to any operation.
1 of 5
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Restoring the ACR Remote Control
will be displayed.
2,3 4
1,2
3
22ofof52
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Suppressing the Earth Fault & Sensitive Earth Fault Prot.
2,3
4
Enabling the ACR Work Tag Function
3 of 5
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Disabling the ACR Work Tag Function
Note: The ACR can be tripped locally regardless of the status of the
remote control – ‘ON’ or ‘OFF’. The ACR cannot be closed locally
unless the remote control is suppressed – ‘OFF’.
4 4ofof5 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Isolating the ACR Trip Circuit
3 2
To restore the close circuit press the ‘CLOSE CIRCUIT
‘ENABLE’ switch and confirm the ‘DISABLED’ LED is off.
Note: Isolating the close circuit places a physical break in the circuit.
All operator settings remain unaffected.
5 of 5
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Prior to any operation Functions: Auto Reclose, Opening, Closing,
Rating 24kV
• There is no Earth Leakage on these units. Insulant: Vacuum Interupter
• Electrical operation is the preferred method Voltage: 12.7 kV
of operation on these SWER ACR’s
• Please refer to the Schneider Nulec ADVC
2 Electronic control box in the Control
Boxsection of this manual for electronic
operation.
Note: You CANNOT close the ACR via the manual operating handle.
Closing must be done via the electronic control box.
1 of 1
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Functions: Opening, Closing, Auto-reclose
Prior to any operation: Suppression
• The Fusesaver Control Panel is Insulant: N/A
fitted inside the RCU enclosure and Voltage: 22 kV
can be accessed by the operator
when the RCU door is open. ON/OFF button
indicator
• It is very important that the field
FuseSaver Control
operators be trained and familiar Source
FuseSaver
with the different indications, their status Control in Progress
meaning and functions before indicator
FuseSaver Trip/Close
operating the unit. All anomalies status & controls
must be reported to and rectified status
before operating.
FuseSaver Protection
• Do not operate the unit while FuseSaver
status & controls
Note: Ensure that the isolation switch behind the Radio tray
is switch on.
Control Boxes
Turning Remote Control Off & On
Panel ON
Remote – no indication
Panel ON
Remote - No indication
Local ON - RED
Panel ON – red
1
Local – ON – red
Remote – ON – red
22ofof52
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Local Operation
4 “Control in Progress” will flash Trip & Close LED’s will flash
4 4
33 of
of 52
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Closing the FuseSavers
4 Control in Progress & Prot ON & OFF will stop flashing once
operation is complete
4 of 52
VESI Switchgear Manual Copyright © 2015
CONTENTS
Control Boxes
Control Boxes
Instantaneous ON/OFF
Switching Instantaneous ON
55of
of52
VESI Switchgear Manual Copyright © 2015
CONTENTS
FAULT INDICATORS
Fault Indicators
Prior to any operation:
Functions: Fault Indication, Re-setting
• Note: The reset times for this fault indicator Rating: N/A
are as follows: Insulant: N/A
Voltage: N/A
• Xenon flash is four (4) hours if voltage is
not restored.
• Red/Amber LEDs – up to seven (7) days
depending on the configuration.
Note: If, under normal conditions, the fault indicator does not flash burst either one or two amber lights
every 30 seconds, then the unit may be faulty and require servicing.
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Fault Indicators
Fault Indicators
Resetting the Fault Indicator – Manually
Note: If, when resetting the unit, the self test cycle of one red flash,
one amber flash, one xenon strobe flash does not occur then the unit 2
may be faulty and require servicing.
Xenon Strobe
Permanent Fault (No volts on line after the 4 hour reset period)
Transient Fault (Volts on line before the 4 hour reset period)
Self Clearing Fault (Current spike with no protection operation)
No volts on line
Volts on line with zero or minimal current
Condition normal - volts and current on line
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Fault Indicators
Fault Indicators
Functions: Fault Indicator, Self Resetting,
Prior to any operation: Manual Resetting, Manual
Triggering
• This fault indicator WILL NOT detect a phase
Rating: N/A
to phase fault where the current flows in the
Insulant: N/A
outside conductors on the pole to which the Voltage: N/A
fault indicator is attached.
• This fault indicator has a provision for
SCADA input.
• The fault indicator will automatically reset
in either four (4) or (8) hours depending on
settings.
11ofof12
VESI Switchgear Manual Copyright © 2015
CONTENTS
Fault Indicators
Fault Indicators
Prior to any operation: Functions: Opening, Closing
Rating: N/A
• These fault indicators automatically reset in Insulant: N/A
approximately eight (8) hours. Voltage: N/A
11ofof12
VESI Switchgear Manual Copyright © 2015
CONTENTS
Fault Indicators
Fault Indicators
Functions: Fault Indicator, Self Resetting,
Prior to any operation: Manual Resetting, Manual
• These fault indicators automatically reset in Triggering
Rating: N/A
either two (2) or four (4) hours depending on
Insulant: N/A
the setting.
Voltage: N/A
11ofof12
VESI Switchgear Manual Copyright © 2015
CONTENTS
Fault Indicators
Fault Indicators
Functions: Fault Indicator
Prior to any operation: Rating: N/A
• These fault indicators DO NOT automatically Insulant: N/A
reset. Voltage: N/A
1 Spin the ‘Reset I Test’ knob ACW to reset the fault indicator.
11ofof12
VESI Switchgear Manual Copyright © 2015
CONTENTS
Fault Indicators
Fault Indicators
Functions: Fault Indicator, Self Resetting
Prior to any operation: Rating: N/A
Insulant: N/A
• These fault indicators cannot be reset
Voltage: N/A
manually. Automatic resetting takes
approximately four (4) hours.
11ofof12
VESI Switchgear Manual Copyright © 2015
CONTENTS
Fault Indicators
HORSTMANN
HORSTMANN ROTOR
ROTOR TYPE
TYPE FAULT
FAULT INDICATOR
INDICATOR
Fault Indicators
Functions: Fault Indicator, Manual Resetting
Prior to any operation: Rating: N/A
Insulant: N/A
• They do not reset automatically.
Voltage: N/A
• An HV operating stick must be used to reset
the fault indicator manually.
11ofof12
VESI Switchgear Manual Copyright © 2015
CONTENTS
Fault Indicators
Fault Indicators
Functions: Fault Indicator, Targets
Prior to any operation: Rating: Variable
• Check/confirm light indicators. Insulant: N/A
Voltage: 22 KVa
Fault Indication
Note: If the xenon flash is reset by the internal preset timer before the
line is re-energised the LED will continue to flash until the line is re-
energised. This prolonged indication lasts a maximum of twenty four
(24) hours to enable fault tracing after a fault occurence if the line is
still de-energised during this time.
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Fault Indicators
Fault Indicators
Resetting the Fault Indicator - Manually
3 Keep the tool in this position until the red LED stops flashing
(within 3 sec) then remove very slowly.
Note: After resetting the Lintroll remove the reset tool very slowly to
avoid reactivating the fault indicator.
Note: Before manually testing the Linetroll ensure the internal DIP
switch 8 is in the ‘OFF’ position and the line is energised.
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Fault Indicators
Fault Indicators
Functions: Fault Indicator, Targets, Digital
Prior to any operation: Readout
Rating: N/A
• The Easergy Flair fault indicator has a lithium Insulant: N/A
backup battery that will keep the display Voltage: N/A
active for up to 4 hours during a total power
interruption.
.
1,2
1,2
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Fault Indicators
Fault Indicators
Resetting the Fault Indicator
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Fault Indicators
Fault Indicators
Functions: Fault Indicator, Targets
Prior to any operation: Rating: N/A
• If the Easergy Flite 110 SA fault indicator is Insulant: N/A
flashing to indicate a transient fault and a Voltage: 22 kV
permanent fault occurs the flashing duration
will change to indicate a permanent fault.
• The flashing duration is different for each
fault indication - transient or permanent. The
LED intensity remains the same for both fault
indications.
• The Easergy Flite 110 SA fault indicator
resets automatically when power is restored.
1 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Fault Indicators
Fault Indicators
Resetting the Fault Indicator - Manually
2 of 2
VESI Switchgear Manual Copyright © 2015
CONTENTS
Fault Indicators
Fault Indicators
Functions: Fault Indicator, Targets
Prior to any operation: Rating: N/A
• These fault indicators automatically reset in Insulant: N/A
approximately eight (8) hours. Voltage: N/A
1 1
1
1
1
1
1
Resetting / Triggering the Fault Indicator Manually
11ofof12
VESI Switchgear Manual Copyright © 2015