Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

EPC Contracts in The Solar Industry

Download as pdf or txt
Download as pdf or txt
You are on page 1of 55

Table of contents

Introduction 3

Contractual structure and bankability of solar projects 4

Basic features of an EPC Contract 8

Key solar-specific clauses in solar EPC Contracts 12

Key performance clauses in power EPC Contracts 18

Key general clauses in EPC Contracts – Delay and extensions of time 23

Exclusive remedies and fail safe clauses 28

Operation and maintenance 35

Appendix 1: Example clause: Performance testing and guarantee regime 37

Appendix 2: Example clause: Extension of time regime 43

Appendix 3: Example clause: Grid access regime 48

Appendix 4: Example clause: Free issue 50

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 2


Introduction
Engineering, procurement and construction (EPC) Contracts are the most common form of contract used
to undertake construction works on utility-scale solar projects by the private sector.1 Under an EPC
Contract, a Contractor is obliged to deliver a complete facility to the Project Company. The Project
Company needs only to turn a key to start operating the facility, hence EPC Contracts are sometimes
called ‘turnkey’ construction contracts. The Contractor must deliver the complete facility for a guaranteed
price by a guaranteed date and the facility must perform to the specified level. Failure to comply with any
requirements will usually result in the Contractor incurring monetary liabilities.

EPC Contracts and their use on solar projects has recently attracted negative publicity, particularly in
contracting circles. Some Contractors have suffered heavy losses due to a range of factors including grid
connection delays and constraints, unidentified site risks, and supply chain delays arising from
international and domestic responses to COVID-19.2 Contractors are increasingly hesitant to enter into
EPC Contracts in Australia. This problem has been exacerbated by a substantial tightening in the
insurance market. Construction insurance has become more expensive due to significant losses suffered
on many projects and the impact of COVID-19 on the insurance market.

However, given their flexibility and the value and certainty that Owners and Lenders derive from them,
EPC Contracts will continue to be the most commonly used form of construction contract for utility-scale
solar projects in most jurisdictions.3

While our focus here is on the use of EPC Contracts in the solar sector, many of the issues are applicable
to EPC Contracts in all sectors. EPC Contracts do not eliminate or mitigate against all risks; however,
when drafted correctly they can ensure performance, timely delivery and rectification within agreed
parameters or up to agreed caps. For this reason, we recommend advice on a project-by-project,
contract-by-contract basis.

Before examining EPC Contracts in detail, it is useful to explore the basic features of a solar project.

1
For our purposes here, we use ARENA’s definition of utility-scale solar as a solar farm which can generate anywhere from hundreds of kilowatts to
thousands of megawatts of solar power. Other terms used for utility-scale solar projects include solar power plants and large-scale solar. See
https://arena.gov.au/renewable-energy/large-scale-solar/
2
The administrators acting on behalf of RCR Tomlinson cited unprofitable solar contracts within its renewables operations as central to the cash-flow
issues leading to its demise. See ‘RCR Tomlinson administrators reveal debts of up to $630m from collapsed engineering firm’, ABC News, 3
December 2018, https://www.abc.net.au/news/2018-12-03/rcr-tomlinson-administrators-reveal-debts-of-up-to-$630/10576754
3
Some jurisdictions, such as the USA, use alternative structures which separate the work into various components.

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 3


Contractual structure and
bankability of solar projects
The detailed contractual structure will vary from project to project. Most solar projects using an EPC
Contract will have a similar basic structure, as shown below. The detailed contractual structure will vary
among projects.

The Project Company4 will usually enter into agreements which cover the following elements:

● A power purchase agreement (PPA) between the Project Company and power purchaser (or
‘offtaker’): In most, but not all, project-financed utility-scale solar projects (as opposed to merchant
projects), the power purchaser undertakes to pay for a set amount of electricity every year of the PPA,
subject to availability, regardless of whether it actually takes that amount of electricity (referred to as a
‘take or pay’ obligation). Sometimes a tolling agreement is used instead of a PPA, under which the
power purchaser directs how the facility is to be operated and despatched.In the absence of a PPA,
Lenders and Project Companies developing a merchant project do not have the same certainty of
cash flow. Therefore, merchant projects are generally considered higher risk than non-merchant
projects.5 This risk can be mitigated by entering into hedge agreements.Project Companies developing
merchant projects often enter into synthetic PPAs or hedge agreements to provide some certainty of
revenue. These agreements are financial hedges rather than physical sales contracts.

4
Given our focus on project-financed infrastructure projects, we refer to the employer as the Project Company. Whilst Project Companies are usually
limited liability companies incorporated in the jurisdiction in which the project is being developed, the actual structure of the Project Company will
vary from project to project and jurisdiction to jurisdiction.
5
However, because merchant power projects are generally undertaken in more sophisticated and mature markets, there is usually a lower level of
country or political risk, yet this may no longer be the case as electricity markets in various countries move towards privatisation.

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 4


● A construction contract: An EPC Contract is one contractual approach that can be taken to
construct a solar facility. Another option is a disaggregated approach with, for example, a supply
contract, a design agreement and a construction contract with or without a project management
agreement. The choice of contracting approach will depend on factors such as the time available,
Lenders’ requirements and the identity of the Contractor(s). The major advantage of the EPC Contract
is that it provides a single point of responsibility. In our experience, most utility-scale solar projects use
an EPC Contract.

● An operation and maintenance agreement: This is usually a medium- to long-term Operating and
Maintenance agreement (O&M Agreement) with an Operator. The term of the O&M Agreement will
vary from project to project. The Operator will usually be an equity sponsor of the Owner, especially if
one of the sponsors is an independent power producer (IPP) or utility company. The term of the O&M
Agreement will likely match the term of the PPA. In limited circumstances, Lenders will require the
Project Company to operate the facility itself and the O&M Agreement will be replaced with a technical
services agreement under which the Project Company is supplied with the know-how necessary for its
own employees to operate the facility.

● Financing and security agreements with Lenders to finance the development of the project:
Most utility-scale solar projects will require debt funding. Before committing to financing terms,
Lenders will need to be satisfied with the risk allocation in the aforementioned construction and
operation and maintenance arrangements as well as other key project agreements. To avoid onerous
lending terms, contingent equity requirements and increased security arrangements in the Financing
Agreement(s), the Owner will need to demonstrate to Lenders that the project is viable and therefore
bankable for the duration of the loan period and beyond.

Accordingly, the construction contract is only one of a suite of documents on a solar project. Importantly,
the Project Company operates the project and earns revenues under contracts other than the
construction contract. Therefore, the construction contract must, where practical, be tailored to be
consistent with the requirements of the other project documents, and it is vital to properly manage the
interfaces between the various types of agreements.

Bankability

A bankable EPC Contract is a contract with a risk allocation between the Contractor and the Project
Company to the satisfaction of Lenders and their credit committees. Lenders focus on the ability (or more
particularly, the lack thereof) of the Contractor to claim additional costs or extensions of time as well as
the security provided by the Contractor for the performance of its obligations. The less comfortable
Lenders are with these provisions, the more equity support (direct or contingent) the Owner’s equity
sponsors will need to provide. In addition, Lenders will have to be satisfied on the technical risks in any
project. Price is also a consideration but is usually considered separately from the bankability of the
contract because the contract price (or more accurately the capital cost of the solar facility) relates to the
bankability of the project as a whole.

Before examining the requirements for bankability, it is worth considering the appropriate financing
structures and lending institutions. The most common form of financing for infrastructure projects is
project financing. Project financing refers to financing secured only by the assets of the project itself.
Therefore, the revenue generated by the project must be sufficient to support the financing. Project
financing is often referred to as either non-recourse financing or limited recourse financing, and these
terms are often used interchangeably. However, the terms mean different things: non-recourse means
there is no recourse to the Owner’s equity sponsors at all; whereas limited recourse means that some
recourse to the Owner’s equity sponsors is possible. The recourse is limited in terms of when it can occur
and the extent of additional equity support. In practice, true non-recourse financing is rare. In most
projects, the Owner’s equity sponsors will be obliged to contribute additional equity support in certain
situations.

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 5


Project financing was traditionally provided by commercial Lenders. Whilst commercial Lenders still
provide finance, governments now also provide financing either through export credit agencies (ECAs) or
multilateral organisations such as the World Bank, the Asian Development Bank, European Bank for
Reconstruction, etc. Many countries offer export credit financing for large energy and infrastructure
projects via the establishment of government-mandated export ECAs. As reported in the June 2020
Report to the US Congress on Global Export Credit Competition, there are 115 known official ECAs
worldwide, varying significantly in export credit volumes. In 2019, the top five largest ECAs by medium to
long-term export credit volumes were the ECAs for China, France, Germany, Italy and Korea. Each ECA
is given a mandate by its government outlining what support it can provide. The mandates of the ECAs
can differ markedly and can change from time to time; though, given the current global focus on climate
change and carbon emission control, financing for renewable energy projects is likely to be prominent in
the coming years. The products offered by most ECAs include:

● direct finance (tied and untied)

● guarantees and bonds

● insurance products, including credit insurance and political risk insurance (the latter of which is either
unobtainable or prohibitively expensive in the commercial marketplace).

Most ECAs work within a regulated environment where they are obliged to comply with a set of OECD
guidelines called the Arrangement on Officially Supported Export Credits (OECD Arrangement). The
OECD Arrangement aims to avoid unfair competition as a result of certain ECAs offering particularly
generous financing conditions. It typically sets out:

● minimum interest rates for fixed-rate loans defined as the commercial interest reference rate (CIRR).
The CIRR depends on the currency of the transaction, and is adjusted by the OECD on a monthly
basis

● the maximum repayment tenor for both standard exports, as well as for specified industries through
special sector understandings

● an allowance for the financing of a percentage of local costs associated with the exported items

● compliance obligations associated with the social and environmental standards of the Equator
Principles.

The OECD Arrangement has been updated to include sector-specific annexes called ‘Sector
Understandings’. This includes the Renewable Energy, Climate Change Mitigation and Adaptation and
Water Projects Sector Understanding (Annex IV of the OECD Arrangement) (Annex IV), which aims to
promote good practice in terms of scaling up and better targeting public and private finance that supports
climate-friendly investment. Annex IV provides more flexible conditions for the provision of export credits
relating to renewable energy projects or climate change mitigation projects. This contrasts with the
Coal-Fired Electricity Generation Sector Understanding (Annex VI of the OECD Arrangement), which
provides stricter conditions for the provision of export credits relating to coal-fired electricity generation
projects.

Owner’s equity sponsors are also using other sophisticated products to provide a portion of the necessary
finance, such as credit-wrapped bonds, securitisation of future cash flows, and political risk insurance.

Assessing bankability
In assessing bankability, Lenders look at a range of factors and assess a contract as a whole. Therefore,
in isolation it is difficult to state whether one approach is or is not bankable. However, generally speaking,
Lenders will require:

● a fixed completion date

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 6


● a fixed completion price

● no or limited technology risk

● output guarantees

● liquidated damages for both delay and performance

● security from the Contractor and/or its parent

● large caps on liability (ideally, there would be no caps on liability, however, there are almost always
caps on liability given the nature of EPC Contracting and the risks to the Contractors involved)

● restrictions on the ability of the Contractor to claim extensions of time and additional costs.

An EPC Contract delivers these requirements in a single integrated package, which is one of the major
reasons why EPC Contracts are the most common form of construction contract used in project-financed
utility-scale solar projects.

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 7


Basic features of an EPC Contract
The key clauses in any construction contract are those that impact on time, cost and quality.

The same is true of EPC Contracts. However, EPC Contracts tend to deal with issues with greater
sophistication than other types of construction contracts in order to satisfy Lenders’ requirements for
bankability.

EPC Contracts provide for:

● A single point of responsibility: The Contractor is responsible for all design, engineering,
procurement, construction, commissioning and testing activities. If any problems occur, the Project
Company need only look to one party – the Contractor – to fix the problem and provide compensation.
If the Contractor is a consortium comprising several entities, the EPC Contract must provide that those
entities are jointly and severally liable to the Project Company.

● A fixed contract price: The risk of cost overruns and the benefit of any cost savings are to the
Contractor’s account. The Contractor’s ability to claim additional money is usually limited to
circumstances in which the Project Company has delayed the Contractor or has ordered variations to
the works.

● A fixed completion date: EPC Contracts include a guaranteed completion date that is either a fixed
date or a fixed period after the commencement of the EPC Contract. If this date is not met, the
Contractor is liable for delay liquidated damages (DLDs). DLDs are designed to compensate the
Project Company for loss and damage suffered as a result of late completion of the solar facility. To be
enforceable in common law jurisdictions, DLDs must be a genuine pre-estimate of the loss or damage
that the Project Company will suffer if the solar facility is not completed by the target completion date.
The genuine pre-estimate is determined by reference to the time the contract was executed.

DLDs are usually expressed as a rate per day which represents the estimated extra costs incurred (such
as extra insurance, supervision fees and financing charges) and losses suffered (revenue forgone) for
each day of delay.

In addition, the EPC Contract must provide for the Contractor to be granted an extension of time when it
is delayed by the acts or omissions of the Project Company.

● Performance guarantees: The Project Company’s revenue will be earned through the operation of
the solar facility. Therefore, it is vital that the solar facility performs as required in terms of output,
efficiency and reliability. To protect the Project Company, EPC Contracts contain performance
guarantees backed by performance liquidated damages (PLDs) payable by the Contractor if it fails to
meet the performance guarantees.

PLDs must be a genuine pre-estimate of the loss and damage that the Project Company will suffer over
the life of the project if the solar facility does not meet the performance guarantees. As with DLDs, the
genuine pre-estimate is determined by reference to the time the contract was signed.

PLDs are usually a net present value (NPV) (less expenses) calculation of the revenue forgone over the
life of the project. For example, if the output of the facility is 5 MWs less than the specification, the PLDs
are designed to compensate the Project Company for the revenue forgone over the life of the project by
being unable to sell the output for the 5 MWs.

● Caps on liability: Most Contractors will not, as a matter of company policy, enter into contracts with
unlimited liability. Therefore, EPC Contracts for utility-scale solar projects cap the Contractor’s liability
at a percentage of the contract price. This varies from project to project; however, an overall liability
cap of 100% of the contract price is common. In addition, there are normally sub-caps on the

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 8


Contractor’s liquidated damages liability. For example, DLDs and PLDs might each be capped at
10–15% of the contract price with an overall cap on both types of liquidated damages of 20–25% of
the contract price. We expect to see Contractors increase their press for the lower end of each scale
given recent high-profile cost overruns arising as a result of DLDs6. Similarly, we also anticipate
Lenders will be especially focussed on the duration of time during which DLDs can sustain the project
and keep the Project Company whole during potentially lengthy periods of delay. The method of
calculation and applicable caps on DLDs will therefore be an even bigger commercial consideration in
the months and years ahead.

There will also likely be a prohibition on the claiming of consequential damages. Consequential damages
are damages that do not flow directly from a breach of contract but which were in the reasonable
contemplation of the parties at the time the contract was signed. This used to mean heads of damage like
loss of profit. However, loss of profit is now usually recognised as a direct loss on project-financed
projects and, therefore, would be recoverable under a contract containing a standard exclusion of
consequential loss clause. Nonetheless, care should be taken to state explicitly that liquidated damages
can include elements of consequential damages. Given that the rate of liquidated damages is pre-agreed,
most Contractors will not object to this exception.

In relation to caps on liability and exclusion of liability, it is common for exceptions which apply to either or
both the cap on liability and the prohibition on claiming consequential losses. The exceptions themselves
are often project-specific. However, some common examples include cases of fraud or wilful misconduct,
death or personal injury, situations where the minimum performance guarantees have not been met and
the cap on delay liquidated damages has been reached, and breaches of the intellectual property
warranties. The cap on liability typically does not apply to the extent that amounts would be recoverable
under insurance policies required under the contract, but for a breach, failure, act or omission by the party
responsible for the procurement of such policies. As per above, given recent project examples we expect
to see attempts for further carve-outs from such caps by Contractors.

● Security: It is standard for the Contractor to provide performance security to protect the Project
Company if the Contractor does not comply with its obligations under the EPC Contract. The security
takes a number of forms including:

- A bank guarantee for a percentage, normally in the range of 10–20%, of the contract price. The
actual percentage will depend on a number of factors including the other security available to the
Project Company, the payment schedule (because the greater the percentage of the contract price
unpaid by the Project Company at the time it is most likely to draw on security, i.e. to satisfy DLD
and PLD obligations, the smaller the bank guarantee can be), the identity of the Contractor and the
risk of it not properly performing its obligations, the price of the bank guarantee and the extent of
the technology risk.

- Retention, i.e. withholding a percentage (usually 5–10%) of each payment. Provision is often made
to replace retention monies with a bank guarantee (sometimes referred to as a retention guarantee
(bond)). However, it is now uncommon for both a bank guarantee and cash retention in the above
ranges to be in the same security package; it is one or the other.

- Advance payment guarantee, if an advance payment is made.

- A parent company guarantee from the ultimate parent (or other suitably related entity) of the
Contractor which provides that it will perform the Contractor’s obligations if, for whatever reason,
the Contractor does not perform. This is typical in circumstances in which the Contractor is a
jurisdiction-specific corporate entity controlled by an international construction firm.

● Variations: The Project Company has the right to order variations and agree to variations suggested
by the Contractor. If the Project Company wants the right to omit works either in their entirety or to be
able to engage a different Contractor, this must be stated specifically. In addition, a properly drafted
variations clause should make provision for how the price of a variation is to be determined. In the

6
https://reneweconomy.com.au/biggest-solar-contractor-in-australia-hit-by-damages-claims-soaring-module-costs/

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 9


event the parties do not reach agreement on the price of a variation, the Project Company or its
representative should be able to determine the price. This determination is subject to the dispute
resolution provisions. In addition, the variations clause should detail how the impact, if any, on the
performance guarantees is to be treated. For some larger variations, the Project Company may also
wish to receive additional security. If so, this must also be dealt with in the variations clause.

● Defects liability: The Contractor is usually obliged to repair defects that occur in the 12 to 24 month
period following completion of the performance testing and acceptance of the facility. Defects liability
clauses can be tiered, i.e. the clause can provide for one period for the entire solar facility and a
second, extended period for more critical items. In the case of key component parts, the concept of
‘serial defects’ means substantially the same defect having the same root cause that has been
identified in the same part, for example in 5% or more of the total number of panels in the solar facility.
In such instances, the Contractor is also obliged to rectify the defect on all items of that particular
piece of equipment even if the defect itself has not yet materialised in all items of that equipment.

● Intellectual property: The Contractor warrants that it has rights to all the intellectual property used in
the execution of the works and indemnifies the Project Company if any third-party intellectual property
rights are infringed. Upon creation, all project-specific intellectual property vests in, and is the sole and
exclusive property of, the Project Company.

● Force majeure: The parties are excused from performing their obligations if a force majeure event
occurs.

● Suspension: The Project Company usually has the right to suspend the works. During the period of
suspension, the Contractor must not remove any equipment from the project site.

● Termination: This sets out the contractual termination rights of both parties. The Contractor usually
has very limited contractual termination rights. These rights are limited to the right to terminate for
non-payment, Project Company insolvency or for prolonged suspension or prolonged force majeure
and will be further limited by the tripartite or direct agreement between the Project Company, Lenders
and the Contractor. The Project Company will have more extensive contractual termination rights.
They will usually include the ability to terminate immediately for certain major breaches or if the
Contractor becomes insolvent and the right to terminate after a cure period for other breaches. In
addition, the Project Company may have a right to terminate for convenience, though Contractors will
typically expect a termination fee in the event of a termination for convenience and it is likely that the
Project Company’s ability to exercise its termination rights will also be limited by the terms of the
financing agreements.

● Performance specification: Unlike a traditional construction contract, an EPC Contract usually


contains a performance specification. The performance specification details the performance criteria
that the Contractor must meet. However, it does not dictate how they must be met. This is left to the
Contractor to determine. A delicate balance must be maintained. The specification must be detailed
enough to ensure the Project Company knows what it is contracting to receive but not so detailed that
if problems arise the Contractor can argue they are not its responsibility. In particular, there must be
agreement and certainty in respect of key concepts including what constitutes completion, particularly
on novel or complex matters.

Whilst there are, as described above, numerous advantages to using an EPC Contract, there are some
disadvantages. These include the fact that it can result in a higher contract price than alternative
contractual structures. This higher price is a result of a number of factors not least of which is the
allocation of almost all the construction risk to the Contractor. This has a number of consequences, one of
which is that the Contractor will have to factor into its price the cost of absorbing those risks, which will
result in the Contractor building contingencies into the contract price for events that are unforeseeable
and/or unlikely to occur. If those contingencies were not included, the contract price would be lower.
However, the Project Company would bear more of the risk of those unlikely or unforeseeable events.
The Owner will have to determine, in the context of its particular project, whether the increased price is
worth paying.

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 10


As a result, the Owner and its advisers must critically examine the risk allocation on every project. Risk
allocation should not be an automatic process. Instead, the Project Company should allocate risk in a
sophisticated way that delivers the most efficient result. For example, if a project is being undertaken in
an area with unknown geology and without the time to undertake a proper geotechnical survey, the
Project Company may be best served by bearing the site condition risk itself as it will mean the Contractor
does not have to price a contingency it has no way of quantifying. This approach can lower the risk
premium paid by the Project Company. Alternatively, the opposite may be true. The Project Company
may wish to pay for the contingency in return for passing off the risk, which quantifies and caps its
exposure. This type of analysis must be undertaken on all major risks prior to going out to tender.

Another consequence of the risk allocation is that there are relatively few construction companies willing
to enter into EPC Contracts, particularly in the solar sector which has unquestionably narrowed in
Australia within the past 2–3 years. The scarcity of Contractors can also result in relatively high contract
prices and longer project delivery timeframes.

Another major disadvantage of an EPC Contract becomes evident when problems occur during
construction. In return for a guaranteed price and a guaranteed completion date, the Project Company
cedes most of the day-to-day control over the construction. Therefore, Project Companies have limited
ability to intervene when problems occur during construction. As a general rule, the more the Project
Company interferes, the greater the likelihood of the Contractor claiming additional time and costs. In
addition, interference by the Project Company will make it substantially easier for Contractors to defeat
claims for liquidated damages and defective works.

Ensuring the project is completed satisfactorily is usually more important than protecting the integrity of
the contractual structure. However, if the Project Company interferes with the execution of the works, it
will, in most circumstances, have the worst of both worlds. It will have a contract that exposes it to liability
for time and costs incurred as a result of interference without any corresponding ability to hold the
Contractor liable for delays in completion or defective performance. The same problems occur even when
the EPC Contract is drafted to give the Project Company the ability to intervene. In many circumstances,
regardless of the actual drafting, if the Project Company becomes involved in determining how the
Contractor executes the works, then the Contractor will be able to argue that it is not liable for either
delayed or defective performance.

As a result, it is vitally important that great care is taken in selecting the Contractor and in ensuring the
Contractor has sufficient knowledge and expertise and available resources to execute the works. Given
the significant monetary value of EPC Contracts, and the potential adverse consequences if problems
occur during construction, the lowest price should not be the only factor used when selecting a
Contractor.

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 11


Key solar-specific clauses in solar
EPC Contracts
General interface issues
As noted earlier, an EPC Contract is one of a suite of agreements necessary to develop a solar project.
Therefore, it is vital that the EPC Contract properly interfaces with those other agreements. In particular,
care should be taken to ensure the following aspects interface properly:

● commencement and completion dates

● liquidated damages amounts and trigger points

● caps on liability

● indemnities

● entitlements to extensions of time

● insurance

● force majeure

● intellectual property.

Not all of these aspects will be relevant for all agreements. In addition to these general interface issues
that apply to most types of projects, there are also solar-specific issues that must be considered, mainly
concerned with the nature of the site and the technology.

Major solar-specific interface issues are:

● access for the Contractor to the transmission grid to allow timely completion of construction,
commissioning and testing (grid access), including generator performance standards and compliance
with AEMO requirements

● consistency of commissioning and testing regimes

● warranty and design life requirements for key component parts

● interface issues between the relevant government agencies, landowners, local communities, the
Project Company and the Contractor. In particular, whilst the Project Company must maintain a
long-term or comfortable relationship with government agencies, the Contractor does not necessarily
need to do so.

Grid access
EPC Contracts will not provide for the handover of the solar facility to the Project Company, and the PPA
will not become effective until all commissioning and reliability trialling has been successfully completed.
This raises the important issue of the Contractor’s grid access and the need for the EPC Contract to
clearly define the obligations of the Project Company in providing grid access.

Lenders want to avoid the situation where the Project Company’s obligation to ensure grid access is
uncertain. This will result in protracted disputes with the Contractor concerning its ability to place load

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 12


onto the grid system and to obtain extensions of time in situations where delay has been caused as a
result of the failure or otherwise of the Project Company to provide grid access.

Grid access issues arise at two levels:

● the obligation to ensure that the infrastructure is in place

● the obligation to ensure that the Contractor is permitted to export power.

With respect to the obligation to ensure that the infrastructure is in place, the responsibility will be
project-specific and covered in the relevant Connection Agreement. In the case of existing grid
infrastructure already in situ, the grid operator will retain control of existing grid infrastructure and carry
out any necessary upgrades. The cost will form part of the connection fee payable by the Project
Company in accordance with the Connection Agreement. For new infrastructure (e.g. substations, or
material upgrades to existing underground or overhead infrastructure), the Project Company will typically
bear this risk vis à vis the Contractor, with the relevant requirements and works passed directly from the
Connection Agreement to the Contractor via the EPC Contract. Issues that must be considered include:

● What are the facilities to be constructed and how will these facilities interface with the Contractor’s
works? Is the construction of these facilities covered by the Connection Agreement or any other
construction agreement? If so, are the rights and obligations of the Project Company dealt with in a
consistent manner?

● Will the infrastructure be project-specific? Or will it be made available by the grid operator to other
applications and projects (including, potentially, projects of a similar nature)?

● What is the timing for completion of the infrastructure? Will it fit in with the timing under the EPC
Contract?

With respect to the Contractor’s ability to export power, the EPC Contract must adequately deal with this
risk and satisfactorily answer the following questions to ensure smooth testing, commissioning and
commercial operation:

● What is the extent of the grid access obligation? Is it merely an obligation to ensure that the
infrastructure necessary for the export of power is in place or does it involve a guarantee that the grid
will take all power that the Contractor is able to produce?

● What is the timing for the commencement of this obligation? Does the obligation cease at the relevant
target date of completion? If not, does its nature change after the date has passed?

● What is the obligation of the Project Company to provide grid access in cases where the Contractor’s
commissioning/facility is unreliable? Is it merely a reasonableness obligation?

● Is the relevant grid robust enough to allow for full testing by the Contractor – for example, the
performance of full load rejection testing?

● What is the impact of relevant national grid codes or legislation and their interaction with both the EPC
Contract and the PPA? Does the facility comply with the generator performance standards and any
other AEMO requirements for a project of this nature? Given the evolving technology in this sector and
the changing landscape in respect of applications to connect to the grid, it is not uncommon for new or
updated requirements to be implemented in the intervening period between contract execution and
completion of practical works.

Many EPC Contracts are silent on these matters or raise far more questions than they answer. The
Project Company’s failure will stem from restrictions imposed on it under either the PPA or the Connection
Agreement or both, so the best answer is to accurately ‘back to back’ the Project Company’s obligations
under the EPC Contract (usually to provide an extension of time or costs) with the PPA and Connection

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 13


Agreement. This approach will not eliminate the risk associated with grid access issues, but will make it
more manageable.

A variety of projects we have worked on in Asia, and more recently in Australia, have incurred significant
amounts of time and costs in determining the grid access obligations under the EPC Contract. This
experience has taught us that it is a matter which must be resolved at the contract formation stage.
Therefore, we recommend inserting the clauses in Appendix 3.

Interfacing of commissioning and testing regimes


It is also important to ensure that the commissioning and testing regimes in the EPC Contract mirror the
requirements for commercial operation under the PPA. Mismatches can result in delays, lost revenue and
liability for damages under the PPA or concession agreement, all of which have the potential to cause
disputes.

Testing/trialling requirements under both contracts must provide the necessary Project Company
satisfaction under the EPC Contract and offtaker satisfaction under the PPA. Relevant testing issues that
must be considered include:

● Are differing tests/trialling required under the EPC Contract and the PPA? If so, are the differences
manageable for the Project Company or likely to cause significant disruption?

● Is there consistency between obtaining handover from the Contractor under the EPC Contract and
commercial operation? It is imperative to prescribe back-to-back testing under the relevant PPA and
the EPC Contract which will result in smoother progress of the testing and commissioning and will
better facilitate all necessary supervision and certification. It must not be forgotten that various
certifications will be required at the Lender level. The last thing Lenders want is the process to be held
up by their own requirements for certification. To avoid delays and disruption, it is important that the
Lenders’ engineer is acquainted with the details of the project and any potential difficulties with the
testing regime so that any potential problems can be identified early and resolved without impacting on
the commercial operation of the solar facility.

● Is the basis of the testing to be undertaken mirrored under both the EPC Contract and the PPA? For
example, on what basis are various performance tests to be undertaken? Are they to be undertaken
on a per unit basis or a facility output basis?

● What measurement methodology is being used? Are the correction factors to be applied under the
relevant documents uniform? Are references to international standards or guidelines to a particular
edition or version? Is there an order of precedence where standards or guidelines conflict?

● Are all tests necessary for the Contractor to complete under the EPC Contract able to be performed as
a matter of practice?

Significantly, if the relevant specifications are linked to guidelines such as the World Bank environmental
guidelines, consideration must be given to changes that may occur in these guidelines. The EPC Contract
reflects a snapshot of the standards existing at a time when that contract was signed. The actual
construction of the project may be undertaken a number of years after that date, which may allow
mismatches if legislation or guidelines have changed in the interim. It is important that there is certainty as
to which standard applies for both the PPA and the EPC Contract. Is it the standard at the time of entering
the EPC Contract or is it the standard that applies at the time of testing?

Consideration must be given to the appropriate mechanism to deal with potential mismatches between
the ongoing obligation of complying with laws and the Contractor’s obligation to build to a specification
agreed at a previous time. Consideration must also be given to requiring satisfaction of guidelines as
amended from time to time. The breadth of any change of law provision will be at the forefront of any
review.

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 14


The above issues raise the importance of the testing schedules to the EPC Contract and the PPA. The
size and importance of the various projects to be undertaken mean that the days are gone where
schedules could be attached at the last minute without review. Discrepancies between the relevant testing
and commissioning requirements will only serve to delay and distract all parties from the successful
completion of testing and reliability trials.

These are all areas where lawyers can add value to the successful completion of projects by being alert
to and dealing with such issues at the contract formation stage.

Warranty and design life requirements for key component parts


Subject to the Owner’s right (if any) to free issue specified key component parts, the Contractor will
primarily be responsible for procuring the equipment required for the facility. Whilst this may be left
entirely to the Contractor to determine, to ensure a degree of Project Company control over the
technology used or the suppliers involved in the project, the EPC Contract will typically set out a selection
of approved suppliers for key component parts, from which the Contractor may then appoint at its own
discretion. As a result, the Contractor is expected to stand behind its supply chain and its decision to use
certain equipment manufacturers at the expense of others and must warrant that the equipment used is
capable of the expected design life as set out in the performance specification. Other warranties may
include that the equipment is new and unused, the equipment utilises proven technology that has been
operated commercially on projects of similar size and scale and is capable of being insured.

In addition to this design life warranty, key component parts (including spare parts) will be subject to
manufacturer warranties. For example, in solar projects, the following parts are typically classified as key
component parts:

● panels

● trackers

● module supports (i.e. racking)

● inverters

● batteries.

The Contractor must provide the Project Company with fully assignable warranties for warranted
component parts for the duration outlined in the performance specification. This gives the Project
Company (or its appointed O&M Operator) the ability to make a direct claim against the manufacturer if
any defects occur during the project life. The Contractor is liable for such defects during the duration of
the warranty period, provided that its liability will be limited after the defects liability period under the
contract to the collateral warranties obtained and collated. Lenders will also take security over those
warranties, adding a further layer of protection in respect of defects.

Free issue by the Project Company


The concept of free issue of equipment by an Owner is relatively standard practice in other industries and
is now being considered in the solar industry in the context of the generation equipment. In particular, the
free issue of generation equipment enables the Project Company to procure the equipment at a lower
cost using market advantage, such as where the Project company may be better positioned to negotiate
better pricing or warranty conditions than appointed Contractor(s), including in relation to their:

● size and reputation

● existing relationships and influences, with institutional equity investors often having stronger supply
relationships than Contractors

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 15


● the attractiveness of large-scale projects or pipelines of projects, leading to a steady line of work for
suppliers.

The reduction in Contractor overheads (i.e. head office costs) associated with the procurement of major
items of generation equipment combined with limited Contractor preliminaries due to reduced insurances,
site accommodation etc. required from the reduced scope will ultimately be reflected in a lower overall
Contract price.

This control over the appointment of generation equipment suppliers and the possible reduction in the
contract price may increase risk for the Project Company. In some instances, Contractors have been
reluctant to accept underperformance risk for generation equipment procured by the Project Company,
i.e. they are unable to commit to a turnkey solution backed by performance guarantees and a
compensation regime for underperformance. However we believe that free issue does not increase the
risk profile for Contractors and does not materially change the status quo. The generation equipment will
still be delivered to a designated handover spot on site in the same manner as a standard form EPC
Contract; the only difference will be the party responsible for the procurement of that supply prior to its
arrival. The reticence from Contractors is mostly commercial and linked to the loss of margins on the
procurement of the generation equipment. This loss can be offset on utility-scale projects or portfolios of
projects which promise large packages or pipelines of work. Further, with much larger solar projects
becoming more prevalent, the impact of the contingent liability of a supply chain failure (let alone an
actual failure) on the balance sheet of a Contractor may result in a rethink, albeit all parties (including
Lenders) need to carefully understand and work through the appropriate allocation of responsibility for a
failure to meet the performance guarantees and defects.

Underperformance can also be mitigated in the agreement between the Project Company and the
generation equipment supplier (Supply Agreement) and the EPC Contract. Under the Supply
Agreement, the generation equipment supplier will provide collateral warranties for the benefit of the
Contractor or each party would enter into a tripartite agreement in relation to the quality and performance
of the equipment. Lenders will also take security over the Project Company’s rights under those
arrangements (including the Supply Agreement). The EPC Contract will entitle the Contractor to attend
(with the Project Company) any factory acceptance tests conducted on the generation equipment, in a
similar manner to the standard approach where the Project Company may attend such tests when the
equipment is procured by the Contractor. The generation equipment will need to pass those tests and be
of a suitable quality to be installed, tested and commissioned. In any event, generation equipment
suppliers will also provide long-term warranties (in addition to the aforementioned collateral warranties)
for their equipment: the warranties will be for the benefit of the Project Company (in the case of free
issue) or assigned to the Project Company from the Contractor (in the case of standard form EPC
Contract, as outlined above) and Lenders will also take security over those warranties, adding a further
layer of protection in respect of underperformance.

As mentioned above, the Project Company will assume responsibility for the delivery of the free issue
generation equipment to a designated delivery point on site in the same way that the Contractor would
arrange for the delivery of other equipment to that delivery point. The Contractor will not be responsible
for delay in delivery to site unless the delay is caused by the Contractor’s inability to receive the
generation equipment procured by the Project Company at the designated delivery point. The Contractor
will only take the risk of damage to the free issue generation equipment after it has been delivered to the
designated delivery point at the project site.

However, if the free issue generation equipment is damaged prior to installation (e.g. during shipment or
unpacking) and replacements are required, the Contractor will need to be able procure the replacement
equipment. A tripartite agreement between the generation equipment supplier, the Project Company and
the Contractor is recommended which provides the Contractor with the benefit of the Project Company’s
right to place additional orders for supply should breakages occur. The collateral warranties described
above can also be captured in this tripartite agreement.

In advance of entering into the tripartite agreement, the Contractor will require details of the generation
equipment supply agreement and the prices charged, though this information may be commercially

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 16


sensitive to the supplier and the supplier must agree to this approach from the outset (and is in fact bound
to enter the tripartite agreement as per the terms of the supply contract). Given that the Contractor will be
responsible for the generation equipment after delivery until the end of the defect liability period, the
collateral warranties in the tripartite agreement must be in place for the duration of this period or the
tripartite agreement must otherwise allow the Contractor to claim directly against the equipment supplier.

After the defect liability period, the Project Company’s rights against the generation equipment supplier
will continue, though may be subject to a similar tripartite arrangement with the appointed O&M Operator.
On occasion, the Contractor may agree to be responsible for the delivery of the generation equipment
from the factory and be responsible for the insurance and customs clearance and the payment of all costs
including import duties and taxes, though this will be subject to negotiation and the best commercial
outcome for each party.

The Project Company will also take price fluctuations and foreign exchange risk for the generation
equipment, though the Supply Agreement should contain clearly defined parameters to hold price (or
restrict price increases above agreed thresholds) and limit foreign exchange exposure, in a similar
manner to standard form EPC Contract wording in relation to contract price.

The diagram below summarises the contracts and agreements recommended for free issue of generation
equipment (in this example, panels) in an EPC structure:

An example of EPC Contract free issue wording is included in Appendix 4.

Interface issues between stakeholders and Contractors


At a fundamental level, it is imperative that the appropriate party corresponds with the relevant project
stakeholders. The Project Company must ensure the EPC Contract states clearly that it is the appropriate
party to correspond with any government agencies or authorities and the offtaker. Any uncertainty in the
EPC Contract may unfortunately see the Contractor liaising directly with these third parties and possibly
risking the relationship of the Project Company with key influencers, customers and long-term neighbours.
Significantly, it is the Project Company that must develop and nurture an ongoing and long-term
relationship with key stakeholders, particularly the offtaker. On the other hand, it is the Contractor’s prime
objective to complete the project on time or earlier at a cost that provides it with significant profit. The

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 17


clash of these conflicting objectives in many cases does not allow for such a smooth process. Resolving
these issues at the EPC Contract formation stage is imperative.

Key performance clauses in power


EPC Contracts
Rationale for imposing liquidated damages
Almost every construction contract will impose liquidated damages for delay and impose standards in
relation to the quality of construction. Most, however, do not impose PLDs. EPC Contracts impose PLDs
because the achievement of the performance guarantees has a significant impact on the ultimate success
of a project. Similarly, it is important the solar facility commences operation on time given the liability the
Project Company will have under other project agreements. This is why DLDs are imposed. DLDs and
PLDs are both used to motivate the Contractor to fulfil its contractual obligations.

The law of liquidated damages


As previously discussed, liquidated damages must be a genuine pre-estimate of the Project Company’s
loss. If liquidated damages are more than a genuine pre-estimate, they will be a penalty and
unenforceable. There is no legal sanction for setting a liquidated damages rate below that of a genuine
pre-estimate; however, there are the obvious financial consequences.

In addition to being unenforceable as a penalty, liquidated damages can also be void for uncertainty or
unenforceable because they breach the ‘prevention principle’. Void for uncertainty means, as the term
suggests, that it is not possible to determine how the liquidated damages provisions work. In those
circumstances, a court will void the liquidated damages provisions. The prevention principle was
developed by the courts to prevent owners from delaying Contractors and then claiming DLDs. It is
discussed in more detail below in the context of extensions of time.

Prior to discussing the correct drafting of liquidated damages clauses to ensure they are not void or
unenforceable, it is worth considering the consequences of an invalid liquidated damages regime. If the
EPC Contract contains an exclusive remedies clause the result is simple – the Contractor will have
escaped liability unless the contract contains an explicit right to claim damages at law if the liquidated
damages regime fails.

If, however, the EPC Contract does not contain an exclusive remedies clause, the non-challenging party
should be able to claim at law for damages it has suffered as a result of the challenging party’s
non-performance or defective performance. What then is the impact of the caps in the now-invalidated
liquidated damages clauses?

The position is unclear in common law jurisdictions, and a definitive answer cannot be provided based
upon the current state of authority. It appears the answer varies depending upon whether the clause is
invalidated due to its character as a penalty or because of uncertainty or unenforceability. Our view of the
current position is set out below. We note that whilst the legal position is not settled, the position
presented below does appear logical.

● Clause invalidated as a penalty: When liquidated damages are unenforceable because they are a
penalty (i.e. they do not represent a genuine pre-estimate of loss), the liquidated damages or its cap
will not act as a cap on damages claims at general law. We note that it is rare for a court to find
liquidated damages are penalties in contracts between two sophisticated, well-advised parties.

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 18


● Clause invalidated due to acts of prevention by the Project Company: Where a liquidated
damages clause is invalidated due to an act of prevention by the Project Company for which the
Contractor is not entitled to an extension of time, the liquidated damages or its cap will not act as a
cap on damages claims at general law.

A liquidated damages clause which is unworkable, or too uncertain to ascertain what the parties intended,
is severed from the EPC Contract in its entirety and will not act as a cap on the damages recoverable by
the principal from the Contractor. Upon severance, the clause is, for the purposes of contractual
interpretation, ignored.

However, it should be noted that the threshold test for rendering a clause void for uncertainty is high, and
courts are reluctant to hold that the terms of a contract, in particular a commercial contract where
performance is well advanced, are uncertain.

Drafting of liquidated damages clauses


Given the role liquidated damages play in ensuring EPC Contracts are bankable, and the consequences
detailed above of the regime not being effective, it is vital to ensure that liquidated damages clauses are
properly drafted so that Contractors cannot avoid their liquidated damages liability on a legal technicality.

Therefore, it is important from a legal perspective to ensure DLDs and PLDs are dealt with separately. If a
combined liquidated damages amount is levied for late completion of the works, it risks being struck out
as a penalty because it will overcompensate the Project Company. However, a combined liquidated
damages amount levied for underperformance may under-compensate the Project Company.

Our experience shows that there is a greater likelihood of delayed completion than there is of permanent
underperformance. One of the reasons why projects are not completed on time is that Contractors are
often faced with remedying performance problems. This means, from a legal perspective, if there is a
combination of DLDs and PLDs, the liquidated damages rate should include more of the characteristics of
DLDs to protect against the risk of the liquidated damages being found to be a penalty.

If a combined liquidated damages amount includes an NPV or performance element, the Contractor will
be able to argue that the liquidated damages are not a genuine pre-estimate of loss when liquidated
damages are levied for late completion only. However, if the combined liquidated damages calculation
takes on more of the characteristics of DLDs, the Project Company will not be properly compensated if
there is permanent underperformance.

Drafting of the performance guarantee regime


Now that it is clear that DLDs and PLDs must be dealt with separately, it is worth considering, in more
detail, how the performance guarantee regime should operate. A properly drafted performance testing
and guarantee regime is important because the success or failure of the project depends, all other things
being equal, on the performance of the solar facility.

The major elements of the performance regime are:

● testing

● guarantees

● liquidated damages.

Liquidated damages are discussed above. Testing and guarantees are discussed below.

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 19


Testing
Performance tests may cover a range of areas. Two of the most common are functional tests and
performance tests.

● Functional tests/ factory acceptance tests: These test the functionality of certain parts of the solar
facility prior to shipping to site (or on occasion, upon arrival at site). They are usually discrete tests
specific to items of equipment which do not test the solar facility as a whole. Liquidated damages do
not normally attach to these tests. Instead, they are absolute obligations that must be complied with. If
not, the solar facility will not reach the next stage of completion and, in the case of factory acceptance,
delivery to the project site.

● Performance tests: These test the ability of the solar facility to meet the performance criteria
specified in the contract and occur at commercial operation and again in the following years. We
typically see performance ratio testing used in the utility-scale solar industry. The Contractor will be
liable for PLDs if the actual performance ratio (PR) is less than the Guaranteed PR during commercial
operation performance tests and post-commercial-operation performance tests.

Upon completion of the commercial operation performance tests, for the Project Company to issue a
commercial operation certificate, the actual PR must be above the Minimum PR (typically set at 95–98%
of the Guaranteed PR).

If the Minimum PR is not achieved during the commercial operation performance tests, the Contractor
may make modifications, remedy defects and retest to achieve at least the Minimum PR until it reaches
the cap of its liability for DLDs. If the commercial operation performance tests demonstrate that the plant
is performing below the Guaranteed PR (but above the Minimum PR), the Project Company may issue
the certificate of commercial operation and withhold the final contract payment (typically equivalent to
5–10% of the contract price).

Although the commercial operation performance tests are performed over seven days (so will not give an
accurate representation of the performance for an entire calendar year), the result is corrected for
seasonality and temperature, and the Contractor may declare a day’s tests results inadmissible under
certain conditions (subject to a maximum cap on the number of times) in the commercial operation
performance testing schedule.

As part of the commercial operation performance tests, the Contractor must also calculate the total of the
nameplate values of the rated power of the PV modules installed (Installed DC Capacity). The
Contractor guarantees that the Installed DC Capacity will be no less than the Guaranteed DC Capacity
and will be liable by way of PLDs an amount of [x]% for each 1% (pro rated for part thereof) by which the
Installed DC Capacity falls short of the Guaranteed DC Capacity.

The Guaranteed PR should be set at a level of performance at which it is economic to accept the solar
facility. Lender’s input will be vital in determining what this level is. However, it must be remembered that
Lenders have different interests to the Owner. Lenders will, generally speaking, be prepared to accept a
solar facility that provides sufficient income to service the debt. However, in addition to covering the debt
service obligations, the Owner (and the Owner’s equity sponsors) will also want to receive a return on
their equity investment and satisfy the requirements of any PPA. If that will not be provided via the sale of
electricity because the Contractor has not met the performance guarantees, the Owner will have to rely
on the PLDs to earn their return. In some projects, the guarantee tests occur after handover of the solar
facility to the Project Company. This means the Contractor no longer has any liability for DLDs during
performance testing.

In our view, it is preferable, especially in project-financed projects, for handover to occur after completion
of performance testing. This means the Contractor continues to be liable for DLDs until either the solar
facility operates at the guaranteed level or the Contractor pays PLDs where the solar facility does not
operate at the guaranteed level. Obviously, DLDs will be capped (usually at 15–20% of the contract
price); therefore, the EPC Contract should give the Project Company the right to call for the payment of

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 20


the PLDs and accept the solar facility. If the Project Company does not have this right, the problem
mentioned above will arise; namely, the Project Company will not have received its solar facility and will
not receive any DLDs as compensation.

As noted above, it is common for the Contractor to be given an opportunity to modify the solar facility if it
does not meet the performance guarantees on the first attempt. This is because the PLD amounts are
normally very large and most Contractors would prefer to spend the time and the money necessary to
remedy performance instead of paying PLDs. Not giving Contractors this opportunity will likely lead to an
increased contract price both because Contractors will over-engineer the solar facility and will build a
contingency for paying PLDs into the contract price. The second reason is because in most
circumstances the Project Company will prefer to receive a solar facility that operates at 100% capacity.
The right to modify and retest is another reason why DLDs should be payable up to the time the
performance guarantees are satisfied.

If the Contractor is to be given an opportunity to modify and retest, the EPC Contract must deal with who
bears the costs of the additional resources and consumables required to undertake the retesting. The
cost of the fuel in particular can be significant and should, in normal circumstances, be to the Contractor’s
account because the retesting only occurs if the performance guarantees are not met at the first attempt.

Technical issues
Ideally, the technical testing procedures should be set out in the EPC Contract. However, for a number of
reasons, including the fact that it is often not possible to fully scope the testing program until the detailed
design is complete, the testing procedures are usually left to be agreed during construction by the
Contractor, the Project Company’s representative or engineer and, if relevant, the Lenders’ technical
adviser. However, a properly drafted EPC Contract should include the guidelines for testing.

The complete testing procedures must, as a minimum, set out details of:

● Testing methodology: Reference is often made to standard methodologies, for example, the
American Society of Mechanical Engineers methodology. References will need to identify if specific
versions or editions are relevant.

● Testing equipment: Who is to provide it, where it is to be located, and how sensitive must it be?

● Tolerances: What is the margin of error?

● Ambient conditions: What atmospheric conditions (including radiation, cloud cover and dust) are
assumed to be the base case? Testing results will need to be adjusted to consider any variance from
these ambient conditions.

● Attendees: Who may attend? And who pays for such attendance? Sufficient notice will also be
required to allow travel arrangements for attendees.

In addition, for utility-scale solar projects with multi-units the testing procedures must state those tests to
be carried out on a per unit basis, per package basis and those on the basis of an entire facility. This will
be particularly relevant for larger, giga-sized projects which involve multiple stages and different
testing/commissioning periods.

Provision of consumables during testing


The responsibility for the provision of consumables required to carry out the performance tests must be
clearly set out in the EPC Contract. In general, the Contractor will be responsible.

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 21


Example
An example of the performance testing and guarantee regime we have used on a number of projects is
included in Appendix 1.

These example clauses are only extracts from a complete contract and ideally should be read as part of
that entire contract and, in particular, with the clauses that deal with DLDs, PLDs, liability, and the scope
of the Contractor’s obligations, including any fitness for purpose warranties and termination. Nonetheless,
they do provide an example of how a performance testing and liquidated damages regime can operate.

The process is best illustrated diagrammatically. The flowchart below demonstrates how the various parts
of the performance testing regime should interface.

Performance guarantees and testing

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 22


Key general clauses in EPC
Contracts – Delay and extensions
of time
The prevention principle
As noted previously, one of the advantages of an EPC Contract is that it provides the Project Company
with a fixed completion date. If the Contractor fails to complete the works by the required date, it is liable
for DLDs. However, in some circumstances the Contractor is entitled to an extension of the date for
completion. Failure to grant an extension for a delay caused by the Project Company can void the
liquidated damages regime and set time at large. This means the Contractor is only obliged to complete
the works within a reasonable time.

This is the situation under contracts governed by common law7 due to the ‘prevention principle’. The
prevention principle was developed by the courts to prevent employers (i.e. Project Companies) from
delaying Contractors and then claiming DLDs.

The legal basis of the prevention principle is unclear and it is uncertain whether you can contract out of
the prevention principle. Logically, given most commentators believe the prevention principle is an
equitable principle, explicit words in a contract should be able to override the principle. However, the
courts have tended to apply the prevention principle even in circumstances where it would not, on the
face of it, appear to apply. Therefore, there is a certain amount of risk involved in trying to contract out of
the prevention principle. The more prudent and common approach is to accept the existence of the
prevention principle and provide for it in the EPC Contract.

The Contractor’s entitlement to an extension of time is not absolute. It is possible to limit the Contractor’s
rights and impose preconditions on the ability of the Contractor to claim an extension of time. A relatively
standard extension of time (EOT) clause would entitle the Contractor to an EOT for:

● an act, omission, breach or default of the Project Company

● suspension of the works by the Project Company (except where the suspension is due to an act or
omission of the Contractor)

● a variation (except where the variation is due to an act or omission of the Contractor)

● force majeure

that cause a delay on the critical path8 and about which the Contractor has given notice within the period
specified in the contract. It is permissible (and advisable) from the Project Company’s perspective to
make both the necessity for the delay to impact the critical path and the obligation to give notice of a
claim for an extension of time conditions precedent to the Contractor’s entitlement to receive an EOT. In
addition, it is usually good practice to include a general right for the Project Company to grant an EOT at
any time.

7
It can arise in civil law countries as well; it will depend on the relevant provisions of the code in those countries. For example, the PRC contract law
contains articles that entitle a contractor to an extension of time for employer-caused delays.
8
The critical path is the path on the construction program that shows the dates when certain activities must be completed by in order to achieve
completion by the specified date.

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 23


However, this type of provision must be carefully drafted because some courts have held (especially
when the Project Company’s representative is an independent third party) that the inclusion of this clause
imposes a mandatory obligation on the Project Company to grant an extension of time whenever it is fair
and reasonable to do so, regardless of the strict contractual requirements. Accordingly, from the Project
Company’s perspective, it must be made clear that the Project Company has complete and absolute
discretion to grant an EOT and that it is not required to exercise its discretion for the benefit of the
Contractor.

Similarly, following some recent common law decisions, the Contractor should warrant that it will comply
with the notice provisions that are conditions precedent to its right to be granted an EOT.

We recommend using the wording in Appendix 2.

Concurrent delay
In the suggested EOT clause, one of the subclauses refers to concurrent delays. This is relatively unusual
because most EPC Contracts are silent on this issue. For the reasons explained below we do not agree
with that approach.

A concurrent delay occurs when two or more causes of delay overlap. It is important to note that it is the
overlapping of the causes of the delays not the overlapping of the delays themselves. In our experience,
this distinction is not often made, which leads to confusion and sometimes disputes. More problematic is
when the contract is silent on the issue of concurrent delay and the parties assume the silence operates
to their benefit. As a result of conflicting case law it is difficult to determine who, in a particular fact
scenario, is correct. This can also lead to protracted disputes and outcomes contrary to the intention of
the parties.

There are a number of different causes of delay which may overlap with delay caused by the Contractor.
The most obvious causes are the acts or omissions of the Project Company.

The Project Company often has obligations to provide certain access rights, materials or infrastructure to
enable the Contractor to complete the works. The timing for the provision of that material or infrastructure
(and the consequences for failing to provide it) can be affected by a concurrent delay.

For example, the Project Company is usually obliged, as between the Project Company and the
Contractor, to provide a transmission line to connect to the solar facility by the time the Contractor is
ready to commission the solar facility. Given that the construction of the transmission line can be
expensive, the Project Company is likely to want to incur that expense as close as possible to the date
that commissioning is due to commence. It will also be subject to what can be agreed with the grid
operator in the Connection Agreement, which itself will be subject to the grid operator’s available
resources and the grid’s capacity and other commitments. If the Contractor is behind schedule under the
EPC Contract, the Project Company may seek to delay the commencement of works required in respect
of the transmission line to allow the EPC Contract works to ‘catch up’ and avoid the potential for delay
costs to be incurred under the Connection Agreement. In the absence of a concurrent delay clause, this
action by the Project Company, in response to the Contractor’s delay, could entitle the Contractor to an
extension of time.

Concurrent delay is dealt with differently in the various international standard forms of contract.
Accordingly, it is not possible to argue that one approach is definitely right and one is definitely wrong. In
fact, the right approach will depend on which side of the table you are sitting.

In general, there are three main approaches for dealing with the issue of concurrent delay. These are:

● Option one: The Contractor has no entitlement to an extension of time if a concurrent delay occurs.

● Option two: The Contractor has an entitlement to an extension of time if a concurrent delay occurs.

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 24


● Option three: The causes of delay are apportioned between the parties and the Contractor receives
an extension of time equal to the apportionment. For example, if the causes of a ten day delay are
apportioned 60:40 between the Project Company and Contractor, the Contractor would receive a six
day extension of time.

Each of these approaches is discussed in more detail below.

Option one: Contractor not entitled to an extension of time for concurrent delays

A common, Project Company friendly, concurrent delay clause for option one is:

If more than one event causes concurrent delays and the cause of at least one of those events,
but not all of them, is a cause of delay which would not entitle the Contractor to an extension of
time under [EOT clause], then to the extent of the concurrency, the Contractor will not be entitled
to an extension of time.

Nothing in the clause prevents the Contractor from claiming an extension of time under the general
extension of time clause. What the clause does do is to remove the Contractor’s entitlement to an
extension of time when there are two or more causes of delay and at least one of those causes would not
entitle the Contractor to an extension of time under the general extension of time clause.

For example, if the Contractor’s personnel were on strike and during that strike the Project Company
failed to approve drawings in accordance with the contractual procedures, the Contractor would not be
entitled to an extension of time for the delay caused by the Project Company’s failure to approve the
drawings.

The operation of this clause is best illustrated diagrammatically.

Example 1: Contractor not entitled to an extension of time for Project Company caused delay

In this example, the Contractor would not be entitled to any extension of time because Contractor Delay 2
overlaps entirely the Project Company delay. Therefore, using the example clause above, the Contractor
is not entitled to an extension of time to the extent of the concurrency. As a result, at the end of Contractor
Delay 2 the Contractor would be in eight weeks delay (assuming the Contractor has not, at its own cost
and expense, accelerated the works).

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 25


Example 2: Contractor entitled to an extension of time for Project Company caused delay

In this example, where there is no overlap between the Contractor and the Project Company delay
events, the Contractor would be entitled to a two week extension of time for the Project Company delay.
Therefore, at the end of the Project Company delay the Contractor will remain in six weeks delay,
assuming no acceleration.

Example 3: Contractor entitled to an extension of time for a portion of the Project Company
caused delay

In this example, the Contractor would be entitled to a one week extension of time because the delays
overlap for one week. Therefore, the Contractor is entitled to an extension of time for the period when
they do not overlap i.e. when the extent of the concurrency is zero. As a result, after receiving the one
week extension of time, the Contractor would be in seven weeks delay, assuming no acceleration.

From the Project Company’s perspective, we believe this option is both logical and fair. For example, if, in
Example 2, the Project Company delay was a delay in the approval of drawings and the Contractor delay
was the entire workforce being on strike, what logic is there in the Contractor receiving an extension of
time? The delay in approving drawings does not actually delay the works because the Contractor could
not have used the drawings given its workforce was on strike. In this example, the Contractor would suffer
no detriment from not receiving an extension of time. However, if the Contractor did receive an extension
of time it would effectively receive a windfall gain.

The greater number of obligations the Project Company has, the more reluctant the Contractor will likely
be to accept option one. Therefore, it may not be appropriate for all projects.

Option two: Contractor entitled to an extension of time for concurrent delays

Option two is the opposite of option one and is the position in many of the Contractor-friendly standard
forms of contract. These contracts also commonly include provisions for extension of time to the effect

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 26


that the Contractor is entitled to an extension of time for any cause beyond its reasonable control. This, in
effect, means there is no need for a concurrent delay clause.

The suitability of this option will obviously depend on which side of the table you are sitting. This option is
less common than option one but is nonetheless sometimes adopted. It is especially common when the
Contractor has a superior bargaining position.

Option three: responsibility for concurrent delays is apportioned between the parties

Option three is a middle-ground position that has been adopted in some of the standard form contracts.
For example, the Australian Standards construction contract AS4000 adopts the apportionment approach.
The AS4000 clause states:

34.4 Assessment

When both non-qualifying and qualifying causes of delay overlap, the superintendent shall apportion the
resulting delay to WUC according to the respective causes’ contribution. In assessing each EOT the
Superintendent shall disregard questions of whether:

● WUC can nevertheless reach practical completion without an EOT

● the Contractor can accelerate, but shall have regard to what prevention and mitigation of the delay has
not been effected by the Contractor.

We appreciate the intention behind the clause and the desire for both parties to share responsibility for
the delays they cause. However, we have some concerns about this clause and the practicality of the
apportionment approach in general. For example, what if the qualifying cause of delay was the Project
Company’s inability to provide access to the site and the non-qualifying cause of delay was the
Contractor’s inability to commence the works because it had been boycotted by unions. How should the
causes be apportioned? In this example, the two causes are both 100% responsible for the delay.

In our view, an example such as this where both parties are at fault has two possible outcomes. Either:

● the delay is split down the middle and the Contractor receives 50% of the delay as an extension of
time

● the delay is apportioned 100% to the Project Company and therefore the Contractor receives 100% of
the time claimed.

The delay is unlikely to be apportioned 100% to the Contractor because a judge or arbitrator will likely
view that as unfair, especially if there is a potential for significant liquidated damages liability. We
appreciate that the above is not particularly rigorous legal reasoning; however, the clause does not lend
itself to rigorous analysis.

In addition, option three is only likely to be suitable if the party undertaking the apportionment is
independent from both the Project Company and the Contractor.

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 27


Exclusive remedies and fail
safe clauses
It is common for Contractors to request the inclusion of an exclusive remedies clause in an EPC Contract.
However, from the perspective of the Project Company, the danger of an exclusive remedies clause is
that it prevents the Project Company from recovering any type of damages not specifically provided for in
the EPC Contract.

An EPC Contract is conclusive evidence of the agreement between the parties to that contract. If a party
clearly and unambiguously agrees that their only remedies are those within the EPC Contract, they will be
bound by those terms. However, the courts have been reluctant to come to this conclusion without clear
evidence of an intention of the parties to the EPC Contract to contract out of their legal rights. This means
if the common law right to sue for breach of EPC Contract is to be contractually removed, it must be done
through very clear words.

Contractor’s perspective
The main reason for a Contractor insisting on the Project Company being subject to an exclusive
remedies clause is to have certainty about its potential liabilities. The preferred position for a Contractor
will be to confine its liabilities to what is specified in the EPC Contract. For example, an agreed rate of
liquidated damages for delay and, where relevant, underperformance of the solar facility. A Contractor will
also generally require the amount of liquidated damages to be subject to a cap and for the EPC Contract
to include an overall cap on its liability.

Project Company’s perspective


The preferred position for the Project Company is for it not to be subject to an exclusive remedies clause.
An exclusive remedies clause limits the Project Company’s right to recover for any failure of the
Contractor to fulfil its contractual obligations to those remedies specified in the EPC Contract. For this
reason, an exclusive remedies clause is an illogical clause to include in an EPC Contract from the
perspective of the Project Company because it means that the Project Company must draft a remedy or
exception for each obligation. This represents an absurd drafting position.

For example, take the situation where the EPC Contract does not have any provision for the recovery of
damages other than liquidated damages. In this case, if the Contractor has either paid the maximum
amount of liquidated damages or delivered the solar facility in a manner that does not require the
payment of liquidated damages (i.e. it is delivered on time and performs to specification) but subsequent
to that delivery the Project Company is found to have a claim, say for defective design which manifests
itself after completion, the Project Company will have no entitlement to recover any form of damages as
any remedy for latent defects has been excluded.

The problem is exacerbated because most claims made by the Project Company will in some way relate
to performance of the solar facility and PLDs were expressed to be the exclusive remedy for any failure of
the solar facility to perform in the required manner.

For example, any determination as to whether the solar facility is fit for purpose will necessarily depend
on the level and standard of the performance of the solar facility. In addition to claims relating to fitness for
purpose, the Project Company may also wish to make claims for, amongst other things, breach of
contract, breach of warranty or negligence. The most significant risk for the Project Company in an EPC
Contract is where there is an exclusive remedies clause and the only remedies for delay and
underperformance are liquidated damages. If, for whatever reason, the liquidated damages regimes are

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 28


held to be invalid, the Project Company would have no recourse against the Contractor as it would be
prevented from recovering general damages at law, and the Contractor would escape liability for late
delivery and underperformance of the solar facility.

Fail safe clauses


In the case of an exclusive remedies clause, the Project Company must ensure all necessary exceptions
are expressly included in the EPC Contract. In addition, drafting must be included to allow the Project
Company to recover general damages at law for delay and underperformance if the liquidated damages
regimes in the EPC Contract are held to be invalid. To protect the position of the Project Company (if
liquidated damages are found for any reason to be unenforceable and there is an exclusive remedies
clause), we recommend the following clauses be included in the EPC Contract:

[ ].1 If clause [delay liquidated damages] is found for any reason to be void, invalid or otherwise
inoperative so as to disentitle the Project Company from claiming delay liquidated damages, the
Project Company is entitled to claim against the Contractor damages at law for the Contractor’s
failure to complete the works by the date for practical completion.

[ ].2 If [ ].1 applies, the damages claimed by the Project Company must not exceed the amount
specified in item [ ] of Appendix [ ] for any one day of delay and in aggregate must not exceed the
percentage of the EPC Contract price specified in item [ ] of Appendix [ ].

These clauses (which would also apply to PLDs) mean that if liquidated damages are held to be
unenforceable for any reason, the Project Company will not be prevented from recovering general
damages at law. However, the amount of damages recoverable at law may be limited to the amount of
liquidated damages that would have been recoverable by the Project Company under the EPC Contract if
the liquidated damages regime had not been held to be invalid (see discussion above). For this reason,
the suggested drafting should be commercially acceptable to a Contractor as its liability for delay and
underperformance will be the same as originally contemplated by the parties at the time of entering into
the EPC Contract.

In addition, if the EPC Contract excludes the parties’ rights to claim their consequential or indirect losses,
these clauses should be an exception to that exclusion. The rationale is that the rates of liquidated
damages are likely to include an element of consequential or indirect losses.

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 29


Force majeure
Force majeure clauses are almost always included in EPC Contracts. However, they are rarely given
much thought unless and until one or more parties seek to rely on them. Generally, the assumption
appears to be that the risk will not affect us or the force majeure clause is a legal necessity and does not
impact on our risk allocation under the contract. Both of these assumptions are inherently dangerous,
and, particularly in the second case, incorrect. Therefore, especially in the current global environment, it is
appropriate to examine their application.

Force majeure is a civil law concept that has no real meaning under the common law. However, force
majeure clauses are used in contracts because the only similar common law concept – the doctrine of
frustration – is of limited application. For that doctrine to apply, the performance of a contract must be
radically different from what was intended by the parties. In addition, even if the doctrine does apply, the
consequences are unlikely to be those contemplated by the parties. An example of how difficult it is to
show frustration is that many of the leading cases relate to the abdication of King Edward VIII before his
coronation and the impact that had on contracts entered into in anticipation of the coronation ceremony.

Given that force majeure clauses are creatures of contract, their interpretation will be governed by the
normal rules of contractual construction. Force majeure provisions will be construed strictly and in the
event of any ambiguity the contra proferentem rule will apply. Contra proferentem literally means ‘against
the party putting forward’. In this context, it means that the clause will be interpreted against the interests
of the party that drafted and is seeking to rely on it. The parties may contract out of this rule.

The rule of ejusdem generis, which literally means ‘of the same class’, may also be relevant. In other
words, when general wording follows a specific list of events, the general wording will be interpreted in
light of the specific list of events. In this context it means that when a broad catch-all phrase, such as
‘anything beyond the reasonable control of the parties’, follows a list of more specific force majeure
events, the catch-all phrase will be limited to events analogous to the listed events. Importantly, parties
cannot invoke a force majeure clause if they are relying on their own acts or omissions.

The underlying test in relation to most force majeure provisions is whether a particular event was within
the contemplation of the parties when they made the contract. The event must also have been outside the
control of the contracting party.

There are generally three essential elements to force majeure:

● it can occur with or without human intervention

● it cannot have reasonably been foreseen by the parties

● it was completely beyond the parties’ control and they could not have prevented its consequences.

Given the relative uncertainty surrounding the meaning of force majeure, we favour explicitly defining
what the parties mean. This takes the matter out of the hands of the courts and gives control back to the
parties. Therefore, it is appropriate to consider how force majeure risk should be allocated.

Drafting force majeure clauses


The appropriate allocation of risk in project agreements is fundamental to negotiations between the
Project Company and its Contractors. Risks generally fall into the following categories:

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 30


● risks within the control of the Project Company

● risks within the control of the Contractor

● risks outside the control of both parties.

The negotiation of the allocation of many of the risks beyond the control of the parties (for example, latent
site conditions and change of law) is usually very detailed so that it is clear which risks are borne by the
Contractor. The same approach should be adopted in relation to the risks arising from events of force
majeure.

There are two aspects to the operation of force majeure clauses:

● the definition of force majeure events

● the operative clause that sets out the effect on the parties’ rights and obligations if a force majeure
event occurs.

The events which trigger the operative clause must be clearly defined. As noted above, it is in the
interests of both parties to ensure that the term force majeure is clearly defined.

The preferred approach for the Project Company is to define force majeure events as being any of the
events in an exhaustive list set out in the contract. In this manner, both parties are aware of which events
are force majeure events and which are not. Clearly, defining force majeure events makes the
administration of the contract, and in particular the mechanism within the contract for dealing with force
majeure events, simpler and more effective.

An example exhaustive definition is:

[ ].1 An Event of Force Majeure is an event or circumstance, or combination of events or circumstances,


which:

(a) is beyond the reasonable control of the party affected (Affected Party);

(b) causes or results in default or delay in the performance by the Affected Party of any of its obligations
under this Contract;

(c) is without the fault or negligence of the Affected Party or its Personnel; and

(d) the Affected Party could not reasonably have been expected to have prevented, avoided or
overcome by exercising a standard of skill, care and diligence consistent with that of a prudent,
competent and experienced person in the circumstances,

provided that such event or circumstance is limited to the following:

(e) acts of terrorism as defined in Part 5.3 of the Criminal Code Act 1995 (Cth);

(f) riot, war, invasion, act of foreign enemies, hostilities (whether war be declared or not), civil war,
rebellion, revolution, insurrection of military or usurped power;

(g) ionising radiation or contamination, radioactivity from any nuclear fuel or from any nuclear waste
from the combustion of nuclear fuel, radioactive toxic explosive or other hazardous properties of any
explosive assembly or nuclear component;

(h) strikes at national level or Industrial Matters at a national level in Australia by Personnel not
employed or otherwise engaged by the Affected Party, its Subcontractors or its suppliers and which
affect an essential portion of the Works but excluding any Industrial Matter which is specific to the
performance of the Works or this Contract; and

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 31


(i) earthquake, cyclone, lightning, fire emanating from outside the Site, meteorite and/or explosion.

[ ]. 2 For the avoidance of doubt, an Event of Force Majeure does not include:

(a) mechanical or electrical breakdown or failure of Equipment;

(b) an event or circumstance caused by an act or omission of the Affected Party;

(c) financial hardship or a lack of, or an inability to use, money or available funds for any reason;

(d) failure of a supplier to supply goods or services to the Contractor under the relevant supply
agreement unless the failure to do so is an Event of Force Majeure affecting that supplier; or

(e) a supplier's failure to supply or transport Consumables, goods or Equipment under the relevant
supply agreement.

An operative clause will act as a shield for the party affected by the event of force majeure so that a party
can rely on that clause as a defence to a claim that it has failed to fulfil its obligations under the contract.
An operative clause should also specifically deal with the rights and obligations of the parties if a force
majeure event occurs and affects the project. This means the parties must consider each of the events it
intends to include in the definition of force majeure events and then deal with what the parties will do if
one of those events occurs.

An example of an operative clause is:

[ ].1 Neither party is responsible for any failure to perform its obligations under this Contract, to the
extent it is prevented or delayed in performing those obligations by an Event of Force Majeure provided
that:

(a) the Contractor’s obligation to achieve Commercial Operation by the Date for Commercial Operation
will not be suspended on account of an Event of Force Majeure and it is acknowledged that the Date
for Commercial Operation will be adjusted for any delay caused by the Event of Force Majeure to the
extent provided for in this clause 42; and

(b) the Owner’s obligation to make any payment under this Contract is not suspended on account of an
Event of Force Majeure.

[ ].2 Where there is an Event of Force Majeure, the Affected Party must immediately notify the other
party in writing giving:

(a) full particulars of the Event of Force Majeure;

(b) details of each of the obligations prevented or delayed by the Event of Force Majeure;

(c) the reasons for the Event of Force Majeure preventing that party from, or delaying that party in,
performing its obligations under this Contract;

(d) the proposed actions for mitigating the consequences of the Event of Force Majeure; and

(e) the estimated time required to overcome the Event of Force Majeure.

[ ].3 If, following the issue of any notice referred to in clause [ ].2, the Affected Party claiming relief
receives or becomes aware of any further information relating to the Event of Force Majeure (and/or any
failure to perform), it must provide that further information to the other party as soon as reasonably
possible.

[ ].4 The Affected Party must mitigate the impact or consequences of the Event of Force Majeure
(including incurring any reasonable expenditure of funds and rescheduling manpower and resources)

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 32


upon its performance of its obligations under this Contract and minimise any resulting delay in the
performance of its obligations under this Contract.

[ ].5 The Affected Party is not relieved from liability under or in connection with this Contract to the
extent that it is not able to perform, or has not in fact performed, its obligations under this Contract due to
its failure to comply with its obligations under clause [ ].4.

[ ].6 Notwithstanding any provision to the contrary in this clause [ ], neither party will be required to
expend more than reasonable sums of money in mitigating or overcoming the consequences of the Event
of Force Majeure. No regard will be taken of the particular financial circumstances of the party.

[ ].7 Upon cessation of the Event of Force Majeure, the Affected Party must, as soon as reasonably
practicable, recommence the performance of its obligations under this Contract. Where the Affected Party
is the Contractor, the Contractor must provide a revised Program in the Approved Form, no later than 10
Business Days after the Event of Force Majeure ceases, rescheduling the Works to minimise the effects
of the prevention or delay caused by the Event of Force Majeure.

[ ].8 An Event of Force Majeure does not relieve a party from liability for an obligation which arose
before the occurrence of that Event of Force Majeure, nor does an Event of Force Majeure affect any
obligation to pay money in a timely manner which matured prior to the occurrence of that Event of Force
Majeure.

[ ].9 The Contractor has no entitlement and the Owner has no liability for:

(a) any costs, Losses or the payment of any part of the Contract Price during an Event of Force
Majeure; and

(b) any delay costs in any way incurred by the Contractor due to an Event of Force Majeure.

In addition to the above clause, it is important to appropriately deal with other issues that will arise if a
force majeure event occurs. For example, as noted above, it is common practice for a Contractor to be
entitled to an extension of time if a force majeure event impacts on its ability to perform the works.
Contractors also often request costs if a force majeure event occurs. In our view, this should be resisted.
Force majeure is a neutral risk in that it cannot be controlled by either party. Therefore, the parties should
bear their own costs.

Another key clause that relates to force majeure events is the Contractor’s responsibility for care of the
works and the obligation to reinstate any damage to the works prior to completion. A common example
clause is:

[ ].1 The Contractor is responsible for the care, custody and control of the Works and the Solar Farm
until the Commercial Operation Date.

[ ].2 The Contractor must promptly make good, at its own cost, any loss or damage that may occur to
the Works from any cause other than an Excepted Risk.

[ ].3 The Contractor is also responsible for any loss or damage to the Works caused by the Contractor
or its Personnel in the course of any work performed.

[ ].4 In the event of loss or damage caused by any Excepted Risk, the Contractor must, promptly and
to the extent directed by the Owner, rectify the loss or damage and such rectification will be deemed a
Variation.

[ ].5 If the Owner does not direct the Contractor to make good any loss or damage to the Works
caused by an Excepted Risk, the Owner may either:

(a) order a Variation, excluding the performance of that part of the Works lost, destroyed or damaged;

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 33


(b) make good, or procure that a third party make good, the loss or damage to the Works itself; or

(c) terminate this Contract under clause [ ].

This clause is useful because it enables the Project Company to, at its option, have the damaged section
of the project rebuilt as a variation to the existing EPC Contract. This will usually be cheaper than
recontracting for construction of the damaged sections of the works.

COVID-19 and force majeure


The COVID-19 pandemic and international and domestic mitigation responses have impacted and will
likely continue to impact manufacturing and supply of key equipment and materials used in the
construction of solar energy facilities in Australia.

Contractors are currently dealing with the delay or disruption in procurement of the necessary equipment
and materials, and we are aware of some Contractors notifying project owners of delays to construction
timelines, milestones and completion dates. For other projects currently in the development phase,
parties are hurriedly revisiting their contracts to understand (and possibly renegotiate) the impending legal
and financial implications.

Given that the virus is no longer a new development and major economies of the world are now
progressing into a ‘living with COVID-19’ phase, we expect to see a greater emphasis on the
categorisation of both COVID-19 and similar outbreaks in definitions of force majeure going forward.
Clearly defined objective criteria will provide greater certainty over generic references and subjective
terminology. Going forward, when negotiating force majeure definitions and drafting, we recommend
considering the following:

● adding an additional condition precedent specifying that the Contractor must make enquiries as to the
availability of solar panels from the intended supplier to inform the construction program and next
steps

● requesting detailed mitigation plans from Contractors outlining proposed suppliers and supply routes
that set out clear and obtainable alternatives in the event of an outbreak or the imposition of
restrictions in response to an outbreak

● expanding the definition of force majeure events to explicitly include any of the following terms:

- a ‘health crisis within Australia’

- an ‘epidemic’

- a ‘health crisis declared to be a Public Health Emergency of International Concern by the World
Health Organization occurring within Australia or internationally’

- a ‘pandemic’

● expanding the definition of force majeure event to explicitly include Australian authority directives
which impact the import of goods from international suppliers and directives from international
authorities preventing the exporting of goods to Australia.

For more information, please see PwC’s COVID-19 and the Solar Industry.9

9
‘COVID-19 and the Solar Industry’, PwC, March 2020: https://www.pwc.com.au/legal/assets/legal-covid19-solar-industry-040320.pdf

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 34


Operation and maintenance
Operating and maintenance manuals
As part of its contract deliverables, the Contractor will be required to prepare a detailed operating and
maintenance manual (O&M manual).

The EPC Contract should require the Contractor to prepare a draft of the O&M manual within a
reasonable time to enable the Project Company, the Operator and possibly Lenders to provide comments,
which can be incorporated into a final draft at least six months before the start of commissioning.

The draft should include all information that may be required for start up, all modes of operation during
normal and emergency conditions and maintenance of all systems of the solar facility. The final form of
O&M manual should also contain all data books, purchase orders, performance test results and
inspection records relating to the solar facility and a record of any warranty obligations for key component
parts.

Operating and maintenance personnel


It is standard for the Contractor to be obliged to train the operations and maintenance staff supplied by
the Project Company. The cost of this training will be built into the Contract price. It is important to ensure
the training is sufficient to enable such staff to be able to efficiently, prudently, safely and professionally
operate the solar facility upon commercial operation. Therefore, the framework for the training should be
described in the appendix dealing with the scope of work (in as much detail as possible). This should
include the standards of training and the timing for training.

The Project Company’s personnel trained by the Contractor will also usually assist in the commissioning
and testing of the solar facility. They will do this under the direction and supervision of the Contractor.
Therefore, in the absence of specific drafting to the contrary, if problems arise during commissioning
and/or testing the Contractor can argue they are entitled to an extension of time, etc. We recommend
inserting the following clause:

[ ].1 The Project Company must provide a sufficient number of competent and qualified operating and
maintenance personnel to assist the Contractor to properly carry out commissioning and the commercial
operation performance tests.

[ ].2 Prior to the date of commercial operation, any act or omission of any personnel provided by the
Project Company pursuant to GC [ ].1 is, provided those personnel are acting in accordance with the
Contractor’s instructions, directions, procedures or manuals, deemed to be an act or omission of the
Contractor and the Contractor is not relieved of its obligations under this contract or have any claim
against the Project Company by reason of any act or omission.

Spare parts
The Contractor is usually required to provide, as part of its scope of works, a full complement of spare
parts (usually specified in the appendices covering the scope of work or the specification) to be available
at the commencement of commercial operation.

Further, the Contractor should be required to replace any spare parts used in rectifying defects during the
defects liability period, at its sole cost. There should also be a time limit imposed on when these spare
parts must be back in the store, and, subject to the location of the project, a requirement to keep spare
parts in a secure location within the vicinity of the project site. It is normally unreasonable to require the

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 35


spare parts to have been replaced by the expiry of the defects liability period because that may lead, for
some items with long lead times, to an extension of the defects liability period.

The Project Company also may wish to have the option to purchase spare parts from the Contractor on
favourable terms and conditions (including price) for an agreed period, typically the initial term of the PPA.
In that case, it would be prudent to include a term that deals with the situation in which the Contractor is
unable to continue to manufacture or procure the necessary spare parts. This provision should cover the
following:

● written notification from the Contractor to the Project Company of the relevant facts, with sufficient time
to enable the Project Company to order a final batch of spare parts from the Contractor

● the Contractor should deliver to, or procure for the Project Company (at no charge to the Project
Company), all drawings, patterns and other technical information relating to the spare parts

● the Contractor must sell to the Project Company (at the Project Company’s request) at cost price (less
a reasonable allowance for depreciation) all tools, equipment and moulds used in manufacturing the
spare parts, to the extent they are available to the Contractor, provided it has used its reasonable
endeavours to procure them.

The Contractor should warrant that the spare parts are fit for their intended purpose, and that they are of
merchantable quality. At worst, this warranty should expire on the later of:

● the manufacturer’s warranty period on the applicable spare part

● the expiry of the defects liability period.

Dispute resolution
Dispute resolution provisions for EPC Contracts could fill another entire paper. There are numerous
approaches that can be adopted depending on the nature and location of the project and the particular
preferences of the parties involved.

However, some general principles should be adopted, including:

● having a staged dispute resolution process that provides for internal discussions and meetings aimed
at resolving the dispute prior to commencing action (either litigation or arbitration)

● obliging the Contractor to continue to execute the works pending resolution of the dispute

● not permitting commencement of litigation or arbitration, as the case may be, until after commercial
operation of the solar facility. This provision must make exception for the parties to seek urgent
interlocutory relief (i.e. injunctions) and to commence proceedings prior to the expiry of any limitations
period. If the provision does not include these exceptions, it risks being unenforceable

● providing for consolidation of any dispute with other disputes which arise out of or in relation to the
construction of the solar facility. The power to consolidate should be at the Project Company’s
discretion.

If you would like more information on dispute resolution, ask us for a copy of our paper on preferred
approaches to be taken in respect of dispute resolution regimes in various Asian jurisdictions including
the PRC, Philippines, Thailand, Vietnam and Taiwan.

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 36


Appendix 1 – Example clause:
Performance testing and guarantee
regime
1. Commercial Operation Tests
Commercial Operation Tests

1.1 After the successful completion of Commissioning under clause [ ] and as soon as the Solar Farm
has, in the opinion of the Contractor, satisfied all the requirements for Commercial Operation (other
than the passing of the Commercial Operation Tests), the Contractor must notify the Owner’s
Representative in writing that the Solar Farm is ready for the Commercial Operation Tests.

1.2 The Contractor must undertake the Commercial Operation Tests in accordance with Schedule [ ].

1.3 Where, prior to Commercial Operation for the Solar Farm, one or more modules is capable of
generating and exporting electricity to the Transmission System, the parties must cooperate in
good faith to ensure that the revenue associated with the export of electricity and sale of any
accompanying Green Benefits is maximised. The Contractor acknowledges and agrees that:

(a) the Owner is entitled to all the benefit of all early electricity that may be generated from the
Solar Farm during the Precommissioning, Commissioning and the Commercial Operation
Tests or otherwise; and

(b) nothing in this Contract imposes any restrictions on the Owner from selling any electricity
generated during the Commercial Operation Tests.

Commercial Operation

1.4 After completion of the Commercial Operation Tests, the Contractor must notify the Owner’s
Representative and the Lenders’ Representative in writing that the Solar Farm has, in the opinion
of the Contractor, reached the stage of Commercial Operation. That notice must, if applicable, also
include the Contractor’s list of Punch List Items and a program for expeditiously completing those
Punch List Items.

1.5 The Owner’s Representative must, promptly, and not later than five Business Days after receipt of
the Contractor's notice under clause 1.4, either:

(a) issue a Certificate of Commercial Operation certified by the Lender’s Representative stating
that the Solar Farm has reached Commercial Operation and the date on which the Solar
Farm reached Commercial Operation; or

(b) notify the Contractor that the Solar Farm has not achieved Commercial Operation, and
provide the reasons why, including any Defects.

1.6 If the Owner’s Representative notifies the Contractor of any Defects pursuant to clause 1.5(b), the
Contractor must promptly correct those Defects and must repeat the procedures described in
clauses 1.4 to clause 1.5 until the Owner issues a Certificate of Commercial Operation that is also
certified by the Lenders’ Representative.

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 37


1.7 Despite any other provision of this Contract, no payment and no partial or entire use or occupancy
of the Site, the Works or the Solar Farm by the Owner (whether during the Commercial Operation
Tests or otherwise) in any way constitutes an acknowledgment by the Owner that Commercial
Operation has occurred, nor does it operate to release the Contractor from, or otherwise affect,
reduce or limit any of the Contractor's warranties, obligations or liabilities under or in connection
with this Contract.

1.8 Upon the issue of the Certificate of Commercial Operation, the Contractor must handover care,
custody and control of the Solar Farm to the Owner or the Operator under the Operation and
Maintenance Agreement if so directed by the Owner.

1.9 Notwithstanding that all the requirements for the issue of the Certificate of Commercial Operation
have not been met, the Owner may at any time, in its absolute, sole and unfettered discretion,
issue the Certificate of Commercial Operation. The issue of the Certificate of Commercial
Operation in accordance with this clause 1.9 will not operate as an admission that all the
requirements of Commercial Operation have been met, and does not prejudice any of the Owner's
rights, including the right to require the Contractor to satisfy the requirements of Commercial
Operation, nor does it release the Contractor from any of its warranties, obligations or liabilities
under or in connection with this Contract.

1.10 If the Owner issues the Certificate of Commercial Operation under clause 1.9, the Contractor must:

(a) do all things reasonably necessary to assist the Owner to ensure that the requirements for
the issue of a Certificate of Commercial Operation are met; and

(b) pay Performance Liquidated Damages in accordance with clause [ ].

1.11 Following achievement of Commercial Operation, the Contractor must within the time period stated
in the Deliverables Submission Schedule finalise and submit to the Owner each of the Post
Commercial Operation Deliverables.

Punch List Items

1.12 The Contractor must rectify or complete within the time stated in the Certificate of Commercial
Operation each of the Punch List Items (and the Punch List Items must be appended to the
Certificate of Commercial Operation). In the event that the Contractor fails to do so, the Owner may
arrange for the outstanding work to be done and the cost of such works will be certified by the
Owner and the Lenders’ Representative and deducted from the Contract Price or (at the Owner’s
option) paid to the Owner by Contractor. The Owner may also have recourse to the Punch List
Guarantee in accordance with clause [ ].

2. Final Completion
Post Commercial Operation Tests

2.1 The Contractor must give the Owner and the Lenders’ Representative prior written notice of when
it intends to carry out the Post Commercial Operation Tests in accordance with the requirements of
Schedule [ ].

2.2 The Contractor must give the Owner and the Lenders’ Representative prior written notice of when
it intends to carry out the Post Commercial Operation Tests in accordance with the requirements of
Schedule [ ].

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 38


2.3 As soon as reasonably practicable after receipt of a notice under clause 2.1, the Owner must issue
a notice to the Contractor and the Lenders’ Representative specifying the date for commencement
of the Post Commercial Operation Tests in accordance with the requirements of Schedule [ ].

Final Completion

2.4 The Contractor must notify the Owner’s Representative and the Lenders’ Representative at least
30 Business Days before the whole of the Works and Solar Farm will, in the opinion of the
Contractor, reach the stage of Final Completion.

2.5 The Contractor must notify the Owner’s Representative and the Lenders’ Representative in writing
that the Solar Farm has, in the Contractor’s opinion, reached the stage of Final Completion.

2.6 The Owner’s Representative must promptly, and not later than five Business Days after receipt of
the Contractor's notice under clause 2.3, either:

(a) issue a Certificate of Final Completion, as certified by the Lenders’ Representative, stating
the Solar Farm has reached Final Completion and stating the date on which the Solar Farm
reached Final Completion; or

(b) notify the Contractor in writing of any Defects that must be remedied before Final Completion
can be achieved.

2.7 If the Owner’s Representative notifies the Contractor of any outstanding Defects under clause
2.5(b), the Contractor must correct those Defects and must repeat the procedures described in
clauses 2.3 and 2.5 until the Owner issues a Certificate of Final Completion. The Certificate of
Financial Completion must also be certified by the Lenders’ Representative.

2.8 A Certificate of Final Completion issued under clause 2.5(a) will discharge of each party's
obligations under this Contract except for:

(a) obligations in relation to Spare Parts and Warranted Components;

(b) indemnities given under this Contract;

(c) warranties given under this Contract;

(d) Wilful Misconduct relating to the Works and Solar Farm or any part thereof;

(e) any Latent Defects in the Works and Solar Farm or any part thereof which were not apparent
at the end of the Defects Liability Period, or which would not have been disclosed upon
reasonable inspection at the time of the issue of the Certificate of Final Completion;

(f) any Serial Defect;

(g) unresolved issues the subject of any Dispute, which is referred to the Dispute Resolution
Panel for resolution under clause [ ] within five Business Days after the Certificate of Final
Completion is issued under clause 2.5(a); and

(h) any obligations that are expressly stated in this Contract to or by their nature survive
completion, expiry or termination of this Contract.

2.9 Despite any other provision of this Contract, no partial or entire use or occupancy of the Site, the
Works or the Solar Farm by the Owner after Commercial Operation in any way constitutes an
acknowledgment by the Owner that Final Completion has occurred, nor does it operate to release
the Contractor from any of its warranties, obligations or liabilities under this Contract including:

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 39


(a) the satisfactory performance of its obligations during the Defects Liability Period and Latent
Defects Period;

(b) the carrying out of the Performance Tests; and

(c) meeting the Performance Guarantees.

3. Performance Guarantees and Liquidated Damages


Performance Guarantees

3.1 The Contractor warrants that the Solar Farm and all component parts will meet the Performance
Guarantees.

Performance Tests

3.2 The Contractor must undertake the Performance Tests in accordance with clause 1 and clause 2
to establish that the whole of the Works, Solar Farm and all component parts achieve the
Performance Guarantees.

Minimum Performance Guarantees not met

3.3 If the Contractor does not meet one or more of the Minimum Performance Guarantees during the
Commercial Operation Tests, the Owner or the Lenders’ Representative may require the
Contractor to:

(a) at the Contractor's cost and expense, make the changes, modifications or additions to the
Solar Farm or any part of the Solar Farm as may be necessary to meet the Minimum
Performance Guarantees;

(b) notify the Owner or the Lenders’ Representative (as relevant) upon completion of the
necessary changes, modifications or additions; and

(c) subject to the Owner’s rights under clauses 3.4, [ ] and [ ], continue to repeat the
Performance Test until the Minimum Performance Guarantees have been met and certified
by the Lenders’ Representative.

3.4 Subject to clause 1.9, if the Contractor does not meet one or more of the Minimum Performance
Guarantees by the date it has incurred and is liable for Delay Liquidated Damages up to the Delay
Liquidated Damages Cap, the Owner may:

(a) require the Contractor to complete the Works and achieve Commercial Operation;

(b) have the Works or any part of the Works completed by itself or by others and the Contractor
must pay the Owner's costs in doing so;

(c) require the Contractor to grant the Owner such reduction in the Contract Price as may be
agreed, or in default of agreement, determined by an Independent Expert in accordance with
the procedure set out at clauses [ ] to [ ] to be a reasonable reduction, with reference to the
ongoing delay, any incomplete Works and the effect on the Project by an, and the Contractor
must promptly pay to the Owner such reduction unless the parties agree otherwise; or

(d) if the Actual PR (as that term is defined in Schedule [ ]) is 50% or less of the Guaranteed PR
(as that term is defined in Schedule [ ]), reject the Works and the Solar Farm and
immediately terminate the Contractor's engagement under this Contract, and the Owner is
entitled to recover from the Contractor an amount to be agreed (that includes all sums paid in

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 40


respect of the Works together with the cost of dismantling the Works, clearing the Site and
returning Equipment to the Contractor or otherwise disposing of the Equipment), or in default
of agreement, determined by an Independent Expert in accordance with the procedure set
out at clauses [ ] to [ ].

The Owner’s rights and remedies under this clause 3.4 will survive termination of this Contract.

Commercial Operation Performance Guarantees not met

3.5 If, after carrying out the Commercial Operation Tests under clause 1.2, the Contractor meets all of
the Minimum Performance Guarantees but does not meet one or more of the Commercial
Operation Performance Guarantees, the Contractor must:

(a) at its cost and expense, make the changes, modifications or additions to the Solar Farm or
any part of the Solar Farm as may be necessary to meet the Commercial Operation
Performance Guarantees;

(b) notify the Owner upon completion of the necessary changes, modifications or additions; and

(c) subject to the Owner’s rights under clauses 1.9 and 3.16, continue to repeat the Commercial
Operation Tests until all of the Commercial Operation Performance Guarantees have been
met.

Performance Liquidated Damages for failure to achieve the Commercial Operation Performance
Guarantees

3.6 Subject to clause 1.9, if the Contractor does not meet all of the Commercial Operation
Performance Guarantees by the date it has incurred or is liable for Delay Liquidated Damages up
to the Delay Liquidated Damages Cap, then provided that the Minimum Performance Guarantees
have been met, the Contractor must pay to the Owner the Performance Liquidated Damages to
the Owner in the amounts and at the times specified in Schedule [ ].

Post Commercial Operation Performance Guarantees not met

3.7 If the Contractor does not meet the Post Commercial Operation Performance Guarantees in
accordance with the procedures and timing set out in Schedule [ ], the Contractor must pay
Performance Liquidated Damages to the Owner in the amounts and at the times specified in
Schedule [ ].

Satisfaction of Performance Guarantees

3.8 The Owner’s entitlement to the payment of Performance Liquidated Damages under clauses
1.10(b), 3.6 and/or 3.7 (as applicable) will be in satisfaction of the Performance Guarantees.

Due and Payable

3.9 The Performance Liquidated Damages must be invoiced by the Owner in accordance with the
timing specified in Schedule [ ] and payment must be made by the Contractor within 10 Business
Days of the date of the invoice. If at the expiration of those 10 Business Days, the amount invoiced
is not paid, that amount will be a debt due and payable to the Owner on demand and will be
deducted from any payments otherwise due from the Owner to the Contractor. The Owner may
also have recourse to the Security provided under this Contract.

Fair and reasonable pre estimate

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 41


3.10 The parties agree that the Performance Liquidated Damages specified in Schedule [ ] are a
genuine, fair and reasonable pre estimate of the damages likely to be sustained by the Owner as a
result of the Contractor's failure to achieve the relevant Performance Guarantees.

No Relief

3.11 The Contractor agrees that payment of the Performance Liquidated Damages does not affect, limit
or reduce the Contractor's obligation to achieve Commercial Operation and Final Completion or
from any other warranties, obligations or liabilities under or in connection with this Contract
(including its obligations under clause [ ]).

3.12 Subject to clause 3.14, the payment of Performance Liquidated Damages under this clause 3 is in
addition to any liability of the Contractor for Delay Liquidated Damages.

Aggregate Liability

3.13 The aggregate liability of the Contractor for the Performance Liquidated Damages will not exceed
the Performance Liquidated Damages Cap.

Overall aggregate liability for Liquidated Damages

3.14 The overall aggregate liability of the Contractor for both Delay Liquidated Damages and
Performance Liquidated Damages under this Contract will not exceed the Aggregate Liquidated
Damages Cap.

No Benefit

3.15 The Contractor is not entitled to the benefit of the exclusion in clause [ ] in any claim for
Performance Liquidated Damages by the Owner against the Contractor for failure to achieve the
Performance Guarantees.

Rights at Law

3.16 If this clause 3 (or any part) is found for any reason to be void, invalid or otherwise inoperative so
as to disentitle the Owner from claiming Performance Liquidated Damages, the Owner is entitled
to claim against the Contractor for damages at law for failure to achieve any of the Performance
Guarantees. Such damages must not exceed the aggregate liability for Performance Liquidated
Damages specified in clauses 3.13 and 3.14.

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 42


Appendix 2 – Example clause:
Extension of time regime
1. Extension of Time
Notice

1.1 The Contractor must immediately give notice to the Owner’s Representative of all incidents,
circumstances or events (Events) of any nature affecting or likely to affect the progress of the
Works which might be reasonably expected to result in a delay to the Works achieving Commercial
Operation by the Date for Commercial Operation.

Further Notice

1.2 Within 10 Business Days after the date of the notice issued under clause 1.1, the Contractor must
give a further notice to the Owner’s Representative which must include:

(a) the material circumstances of the Event including the cause or causes;

(b) the nature and extent of any delay caused by or likely to be caused by the Event;

(c) the corrective action already undertaken or to be undertaken;

(d) the effect on the critical path noted on the Program;

(e) whether in its opinion, the Event qualifies as one which entitles the Contractor to an extension
of time to the Date for Commercial Operation under clauses 2.6 and 2.7;

(f) the period, if any, by which in its opinion the Date for Commercial Operation should be
extended; and

(g) a statement that it is a notice under this clause 1.2.

Continuing Events

1.3 Where:

(a) an Event has a continuing effect; or

(b) the Contractor is unable to determine whether the effect of an Event will actually cause delay
to the progress of the Works so that it is not practicable for the Contractor to give notice
under clause 1.2,

the Contractor must submit to the Owner’s Representative:

(a) a statement to that effect with reasons together with interim written particulars (including
details of the likely consequences of the Event on progress of the Works and an estimate of
the likelihood or likely extent of the delay); and

(b) at intervals of 10 Business Days or less, further interim written particulars until the actual
delay caused (if any) is ascertainable, at which time the Contractor must as soon as
practicable but in any event within 30 Business Days give a final notice to the Owner’s
Representative including the particulars specified in clause 1.2.

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 43


Determination by Owner

1.4 Within 30 Business Days after receipt of the notice in clause 1.2 or the final notice in clause 1.3, the
Owner must issue a notice notifying the Contractor's Representative:

(a) whether the relevant Event qualifies as one which entitles the Contractor to an extension to
the Date for Commercial Operation under clauses 1.5 and 1.6; and

(b) if it does, the period, if any, by which the Date for Commercial Operation is to be extended.

Causes of Delay

1.5 Subject to the provisions of this clause 1, the Contractor is entitled to an extension of time to the
Date for Commercial Operation as the Owner assesses where a delay to the achievement of
Commercial Operation is caused by any of the following events, whether occurring before, on or
after the Date for Commercial Operation:

(a) any Owner Act of Prevention;

(b) a Variation, except where that Variation is caused by an act, omission or default of the
Contractor or its Personnel;

(c) a Connection Works Delay;

(d) a suspension of the Works under clause 4, except where that suspension is caused by an
act, omission or default of the Contractor or its Personnel; or

(e) an Event of Force Majeure.

1.6 For the avoidance of doubt, any act which the Owner or its Personnel is entitled or authorised to do
under this Contract will not be an act for the purposes of clause 1.5(a).

Extension of Time

1.7 Despite any other provisions of this clause 1 and notwithstanding that the Contractor is not entitled
to or has not claimed an extension of time to the Date for Commercial Operation, the Owner may,
at any time in its absolute, sole and unfettered discretion, grant an extension of the Date for
Commercial Operation. The Owner has no obligation to grant, or to consider whether it should
grant, an extension of time and is not required to exercise this discretion for the benefit of the
Contractor.

Conditions precedent to entitlement to extension of time

1.8 If the Contractor fails to submit the notices required under clauses 1.1, 1.2 and 1.3 within the
specified time periods, or fails to comply with any other notice requirement under this Contract
regarding the Event (including, in the case of a Force Majeure Event, the notice under clause [ ]):

(a) the Contractor will have no entitlement to an extension of time; and

(b) the Contractor must comply with the requirements to perform the Works by the Date for
Commercial Operation.

Principles of law

1.9 The Contractor agrees that any principle of law or equity which might otherwise render the Date for
Commercial Operation immeasurable and any Delay Liquidated Damages or Performance
Liquidated Damages unenforceable, does not apply to this Contract.

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 44


1.10 For the avoidance of doubt, a delay to the Date for Commercial Operation caused by any Owner
Act of Prevention will not cause the Date for Commercial Operation to be set at large.

1.11 Nothing in clause 1.10 will prejudice any right of the Contractor to claim an extension of time under
this clause 1 or delay costs under clause 2 for that delay.

Time is not set at large

1.12 Neither the:

(a) failure of the Owner to grant an extension of time to the Date for Commercial Operation under
this clause 1 or at all; or

(b) existence of any Dispute between the Contractor and the Owner as to the Contractor's
entitlement to, or the extent of, any extension of time to the Date for Commercial Operation,

will cause the Date for Commercial Operation to be set at large or prevent the Owner from subsequently
exercising its discretion under clause 1.7.

Must impact critical path

1.13 It is a further condition precedent of the Contractor's entitlement to an extension of time that:

(a) the Contractor is or actually will be prevented from achieving Commercial Operation by the
Date for Commercial Operation by an Event, and the Event qualifies as one which entitles the
Contractor to an extension of time to the Date for Commercial Operation under clauses 1.5
and 1.6; and

(b) the relevant delay is demonstrable on an assessment of the actual and then current critical
path to achieving Commercial Operation by the Date for Commercial Operation.

Acceleration

1.14 The Owner may, at any time prior to the Commercial Operation Date, direct the Contractor's
Representative to accelerate the Works for any reason, including as an alternative to granting an
extension of time to the Date for Commercial Operation.

1.15 Within 10 Business Days of its receipt of the direction under clause 1.14, the Contractor must
advise the Owner’s Representative as to whether it can reasonably comply with the direction, with
details of any additional costs the Contractor will incur (if any) in complying with the direction.

1.16 Subject to the Contractor’s obligation to mitigate, if complying with the direction under clause 1.14
will cause the Contractor to necessarily incur additional costs in performing the Works, subject to
clause [ ] and except where the direction was issued as a consequence of the failure of the
Contractor to fulfil its obligations under this Contract, the Contractor may be entitled to its additional
cost and margin (which must not exceed 10% collectively and includes profit and overhead). The
Owner (on advice from the Lenders’ Representative) must assess and decide, as soon as
reasonably practicable, the extra costs necessarily incurred by the Contractor.

1.17 The Owner (on advice from the Lenders’ Representative) must assess and decide, as soon as
reasonably practicable, any reduction of the Contract Price due to any cost savings resulting from
the Contractor complying with an acceleration direction under clause 1.14 and the Owner will be
entitled to reduce the Contract Price by that amount.

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 45


Sole Entitlement

1.18 Without limiting the Contractor’s rights under clauses 1 and 2, an extension of time granted under
this clause 1 and any delay costs under clause 2 are the Contractor's sole entitlements to any
Claim for delay, including delay caused by the Owner, whether in breach of contract or otherwise
and is in substitution for and excludes the Contractor's other rights and remedies, including the right
to recover damages under or in connection with this Contract or any applicable Law in respect of
any such delay.

Concurrent causes of delay

1.19 If there are two or more events which constitute concurrent causes of delay and at least one of
those concurrent causes is a cause of delay which would not entitle the Contractor to an extension
of time under this Contract, the Contractor is not entitled to an extension of time for the period of
that concurrency.

Survival

1.20 This clause 1 survives the completion, expiry or termination of this Contract.

2 Delay Costs
Contractor may claim

2.1 Where the Contractor has been granted an extension of time for a delay under clause 1.5(a), and
has necessarily incurred extra cost as a direct consequence of the delay, the Contractor must give
to the Owner’s Representative notice of its Claim for delay costs at the same time as the notice
referred to in clause 1.1 or the final notice in clause 1.2 (as the case may be), including all available
particulars and supporting documentation and a statement that it is a notice under this clause 2.1.

Delay costs

2.2 Delay costs in connection with extensions of time pursuant to:

(a) clause 1.5(b) must be dealt with under clause 3 (Valuation of Variations) only;

(b) clause 1.5(d) must be dealt with under clause 4 (Suspension Costs) only; and

(c) clause 1.5(e) must be dealt with under clause 5 (Force Majeure Costs) only.

No other right

2.3 In all other circumstances, an extension of time, if any, is the limit of the Contractor's entitlement for
delay.

Owner must assess

2.4 Subject to clause 2.5, the Owner must assess and decide as soon as reasonably practicable after
receipt of the notice referred to in clause 1.1 or clause 1.2 (as the case may be) the extra costs
necessarily incurred by the Contractor, which does not include off Site overheads, profit or loss of
profit.

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 46


Condition precedent

2.5 It is a condition precedent of the Contractor's entitlement to recover any amount representing extra
costs necessarily incurred under clause 2.1 that the Contractor has provided the notices referred to
in clause 2.1.

Sole Entitlement

2.6 The sums payable under this clause 43 are the Contractor's sole entitlement to compensation for
delay or disruption, including, delay or disruption caused by the Owner, whether in breach of
contract or otherwise and is in substitution for and excludes the Contractor's other rights and
remedies, including the right to recover damages under or in connection with this Contract or any
applicable Law.

3. Valuation of Variations
3.1 The valuation of the Variation must be calculated as follows:

(a) by agreement between the parties;

(b) failing agreement between the parties within 10 Business Days after submission of the
Contractor's Variation proposal, under the unit rates specified in Schedule [ ]; or

(c) where there are no relevant unit rates specified in Schedule [ ], the Owner’s Representative
(on advice from the Lenders’ Representative) will determine the valuation based on
reasonable rates and prices. If the Contractor disputes the Owner’s Representative’s
valuation, the matter can be referred to dispute resolution under clause [ ].

4. Suspension Costs
4.1 If the Contractor’s performance of its obligations is suspended or the rate of the Contractor’s
progress is reduced pursuant to clause [ ];

(a) the Date for Commercial Operation may be extended in accordance with clause 1; and

(b) the Owner must pay to the Contractor any direct extra costs necessarily incurred by the
Contractor as a result of the suspension or reduction (not including any off Site overheads,
profit or loss of profit) except where the suspension or reduction was necessary due to any
act, omission, default or breach of this Contract by the Contractor or its Personnel.

5. Force Majeure Costs


5.1 The Contractor has no entitlement and the Owner has no liability for:

(a) any costs, Losses or the payment of any part of the Contract Price during an Event of Force
Majeure; and

(b) any delay costs in any way incurred by the Contractor due to an Event of Force Majeure.

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 47


Appendix 3 – Example clause:
Grid access regime
1 Transmission System
Coordinating connection to Transmission System

1.1 The Contractor must coordinate the Works, the Connection Works, and the connection of the Solar
Farm to the Transmission System. The Contractor must liaise with the Transmission Network
Service Provider, Government Authorities, the Owner and any Contractors undertaking the
Connection Works to avoid delays in connecting the Solar Farm to the Transmission System.

1.2 The Contractor’s obligations to coordinate with the Transmission Network Service Provider with
respect to Connection Works obligations will require the Contractor to take into account the
requirements of the Grid when designing, constructing and commissioning the Works and the
Connection Works.

1.3 The Contractor must complete, or procure the completion of, the Connection Works:

(a) in the manner specified in the Works Specification and the Project Agreements; and

(b) on or before the date which is [date to be determined by the TNSP in accordance with the
terms of the Connection Agreement].

1.4 The Contractor must ensure that the Works connect to, and fully interface with, the Connection
Works.

Transmission System

1.5 On the Date for First Synchronisation the Owner must ensure that there is in place a Transmission
System (other than the Connection Works) which is capable of receiving the generated net output
the Solar Farm is physically capable of producing at any given time.

Owner’s obligation

1.6 The Owner’s obligation to ensure that the Transmission System is in place is subject to the
Contractor satisfying its obligations under clauses 1.1 and 1.4 in accordance with this Contract.

1.7 The Contractor acknowledges and agrees that, except as expressly provided for in clauses [ ] and
[ ], the Owner is not liable for, or in connection with, any Claim (and the Contractor is not entitled to
make any Claim) arising out of, or in connection with the Owner’s breach of clause 1.5.

Readiness for First Synchronisation

1.8 The Contractor must notify the Owner within five Business Days of it achieving readiness for First
Synchronisation.

First Synchronisation before Date for First Synchronisation

1.9 If the Contractor notifies the Owner that First Synchronisation is likely to take place before the Date
for First Synchronisation, the Owner must endeavour, but is under no obligation to ensure, that the
Transmission System is in place and the Connection Works have been completed, to enable First

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 48


Synchronisation to take place in accordance with the Contractor’s revised estimate of First
Synchronisation.

No deemed Commercial Operation

1.10 The Contractor acknowledges that there will not be any deemed Commercial Operation as a result
of the connection of the Solar Farm to the Transmission System or the sale of any electricity.

Regulatory Framework

1.11 The Contractor must perform the Works, in particular in relation to the connection of the Solar Farm
to the Transmission System, to ensure that the Owner is able to comply with, and the Works and
the Solar Farm comply with the relevant requirements of the Regulatory Framework.

Avoidance of damage or interference to Transmission System

1.12 The Contractor must perform the Works, in particular in relation to the connection of the Solar Farm
to the Transmission System, to ensure that:

(a) any interference to the Transmission System is minimised; and

(b) damage to the Transmission System is avoided.

Reporting of interference

1.13 The Contractor must promptly report to the Owner’s Representative any interference with and
damage to the Transmission System.

Additional obligations

1.14 Without derogating from the Contractor’s obligations under this clause 1, in carrying out any test
which requires the Contractor to supply electricity to the Transmission System, the Contractor
must:

(a) issue a notice to the Owner’s Representative at least 24 hours prior to the time at which it
wishes to so supply, detailing the testing or Commissioning and including the Contractor’s
best estimate of the total period and quantity (in MWh per half hour) of that supply;

(b) promptly notify the Owner’s Representative if there is any change in the information
contained in such notice; and

(c) do all things necessary to assist the Owner (including cooperating with the Transmission
Network Service Provider and complying with its obligations under clause 1.5),

so that the Owner can comply with its obligations under the Regulatory Framework and the Project
Agreements

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 49


Appendix 4 – Example clause:
Free issue
1. Free Issue of Panels
Panel Price

1.2 The Contractor acknowledges that as at the Execution Date, the Contract Price includes an
indicative price for Panels as set out in Schedule [ ] (Tender Panel Price).

1.3 The Owner may request prior to the issue of a Notice to Proceed that the Contractor provides its
confirmed price for the Panels.

1.4 Within five Business Days of receipt of the Owner’s request under clause 1.2, the Contractor must
obtain a revised quotation from a Nominated Subcontractor and submit to the Owner the
Contractor’s Revised Panel Price, which must:

(a) consist of the amount of the revised quotation from the relevant Nominated Subcontractor;

(b) consist of the percentage margin set out in clause [ ] of this Contract; and

(c) not be more than the Tender Panel Price (Revised Panel Price).

1.5 If the Principal has not exercised its Option to Free Issue Panels under clause 1.5 and the Revised
Panel Price is less than the Tender Panel Price, the Contract Price will be decreased by the
difference. The net cost savings between the Tender Panel Price and Revised Panel Price will be
shared in equal portions between the parties. In no case will the amount payable by the Principal
on account of the Panel Price be more than the Tender Panel Price.

Option to Free Issue Panels or Nominate Subcontractor

1.6 The Owner may at its sole discretion, by written notice given to the Contractor on or before the
Notice to Proceed, either:

(a) exercise its Option to Free Issue Panels by giving the Contractor a notice in the form of Part
B of Schedule [ ]; or

(b) nominate to the Contractor the supplier of the Panels (Nominated Subcontractor) and direct
the Contractor to subcontract with the Nominated Subcontractor for the supply of Panels.

1.7 The Contractor has no right of rejection in respect of a nomination or direction issued in accordance
with clause 1.5, unless the type of Panels to be supplied by the Nominated Subcontractor would
materially alter the preliminary design of the Project set out in Schedule [ ].

Option to Free Issue Panels

1.8 Commencing upon the issue of a notice by the Owner under clause 1.5(a), the parties must
perform their obligations under this Contract on the basis that the Contract Price, the Works
Specification and the provisions of this Contract will be adjusted as set out in Schedule [ ].

1.9 For the avoidance of doubt:

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 50


(a) the Owner is not under any obligation whatsoever to exercise; and

(b) the Owner is not entitled to make, nor will the Owner be liable upon, any Claim from the
Contractor in respect of it not exercising,

any Option to Free Issue Panels.

1.10 The exercise of any Option to Free Issue Panels by the Owner under clause 1.5(a) will not:

(a) relieve the Contractor from its liability or obligations (including those arising out of any
warranties given under this Contract);

(b) limit or otherwise affect the Owner’s rights against the Contractor or the Contractor’s rights
against the Owner (including those arising out of any warranties given under this Contract); or

(c) entitle the Contractor to make a Claim, including an extension of time, except as provided for
under this Contract (including under clause [ ] in Schedule [ ].

Nomination or Novation of Supply Agreement

1.11 The Contractor agrees that the Owner may assign the benefit or novate to the Contractor the
supply agreement entered into between the Owner and the Panel supplier following the exercise of
the Owner’s Option to Free Issue Panels under clause 1.5(a) in the agreed form in Schedule [ ]
(Supply Agreement).

1.12 If the Owner directs an assignment or novation of the Supply Agreement, the Contractor must:

(a) accept the assignment by signing a deed of assignment; or

(b) accept the novation by signing a deed of novation.

1.13 Unless the Supply Agreement is assigned or novated to you in accordance with clause 1.11, the
Owner will procure the:

(a) warranties for the Panels for the duration of the Warranted Component Part Period for Panels
from both the manufacturers, agents and suppliers of the Panels; and

(b) performance guarantee from the Nominated Subcontractor.

1.14 The warranties and performance guarantee will be in both the name of the Owner and the
Contractor as warrantee or guarantee (as applicable) and warrant or guarantee (as applicable) for
the Warranted Component Part Defect Period for the Panels and the Panels will comply with all the
requirements of this Contract.

Contractor’s Obligations for the Panels

1.15 The Contractor will remain responsible for obtaining the warranties for the Panels from the installer
of the Panels in accordance with the Warranted Component Parts.

1.16 If the Contractor is required by clause 1.5(b) or clause 1.10 to enter into a subcontract, or to
execute a deed of assignment or novation for the Supply Agreement the Contractor must proceed
promptly to do so and must notify us in writing as soon as the subcontract, assignment or novation
has been affected.

1.17 Where the Owner does not exercise its discretion to exercise any Option to Free Issue Panels and
does not nominate a Nominated Subcontractor in accordance with clause 1.5(b), the Contractor

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 51


must procure the supply of the Panels in accordance with the scope of Works set out in Schedule 1
for an amount equal to or less than the Tender Panel Price set out in Schedule [ ].

1.18 Where any part of the Tender Panel Price for supplying the Panel is not spent, then the amount not
spent is to be deducted from the Contract Price. The Contractor must provide to the Owner
evidence of the cost of supplying the Panels under clause 1.16. The Contractor will not be entitled
to any increase in the Contract Price above the Tender Panel Price.

1.19 Despite any other provision of this Contract:

(a) the Contractor is appointed to act as the Owner’s agent for the purpose of managing the
supply of the Panels under a Supply Agreement;

(b) the Contractor is responsible to the Owner for the Panels supplied by the Nominated
Subcontractor to the same extent that the Contractor is responsible for any other part or parts
of the Work or supply of Equipment under the Contract;

(c) the Contractor will not be relieved by any liability or obligation, including in respect to Defects,
under the Contract because the Nominated Subcontractor supplied the Panels;

(d) the Contractor accepts and is responsible to the Owner for the design obligations in respect
of the Works, including incorporating the Panels supplied by the Nominated Subcontractor
into the final design as set out in Schedule 1;

(e) the Contractor may rely on the performance guarantee from the Nominated Subcontractor to
the extent there is a Defect with the Panels;

(f) any matter within the control of a Nominated Subcontractor must be taken within the
Contractor’s reasonable control whether as the Owner’s agent for the Supply Agreement or in
accordance with a subcontract, assignment or novation of the Supply Agreement in
accordance with clause 1.5(b) or clause 1.10;

(g) the Owner has no obligation or liability to the Contractor for any act, omission, default, breach
of contract or insolvency of a Nominated Subcontractor arising from the subcontract with the
Contractor under clause 1.5(b) or the assignment or novation of the Supply Agreement under
clause 1.10; and

(h) the Contractor must not, without the prior written consent of the Owner, do any act or thing
which:

(i) varies, assigns or novates any of your rights or obligations under any subcontract with a
Nominated Subcontractor; or

(j) changes the scope of, or requirements for, work to be provided by a Nominated
Subcontractor.

1.20 The Contractor must not terminate a subcontract or novated or assigned Supply Agreement for the
supply of the Panels from the Nominated Subcontract without the written approval of the Owner
(which is not to be unreasonably withheld) and as early as possible the Contractor must notify the
Owner of the intention to terminate and reasons.

Replacement of Nominated Subcontractor

1.21 Despite any other provision of the Contract, if at any time for any reason:

(a) the Contractor is unable to enter into a subcontract with a Nominated Subcontractor under
clause 1.5(b) or effect a deed of assignment or novation of the Supply Agreement under
clause 1.10;

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 52


(b) the Nominated Subcontractor repudiates or abandons the subcontract or Supply Agreement;
or

(c) the subcontract or Supply Agreement with a Nominated Subcontractor is terminated, then:

(d) the Contractor must request that the Owner nominate an alternative Nominated
Subcontractor;

(e) if the Owner does not nominate an alternative Nominated Subcontractor within 10 Business
Days after the Contractor’s request, the Contractor may proceed with the part or parts of the
Work or supply of the Equipment under the Contract as if it were not Subcontract Work; and

(f) the Contractor must have no Claim whatsoever by reason of the Owner taking up to 10
Business Days after the Contractor’s request to nominate an alternative Nominated
Subcontractor or failing to nominate an alternative Nominated Subcontractor.

1.22 Subject only to clause 1.6, the Contractor must comply with any nomination or replacement
nomination of a Nominated Subcontractor directed by the Owner regardless of the impact of the
nomination on the Date for Commercial Operation. The Contractor will not be entitled to an
extension of time for any delays to the Date for Commercial Operation caused by the acts or
omissions, appointment or termination of a Nominated Subcontractor.

No relief and horizontal defences to Supply Agreement

1.23 The parties acknowledge and agree that the Contractor:

(a) has read and understood the Supply Agreement; and

(b) accepts responsibility for and assumes the risk of all interface and coordination issues arising
out of or in connection with the interface and coordination of the performance of the supply of
the Panels with the Works under this Contract with the procurement and supply of the Panels
under the Supply Agreement (as applicable) for the Panels.

1.24 The Contractor will not be entitled to make a Claim, to a payment of any sum from the Owner or to
relief from any obligation to make payment to the Owner or relief from or reduction of any other
liability, obligation or duty arising out of or in connection with this Contract including:

(a) any extension of time;

(b) any relief from liability for Delay Liquidated Damages or Performance Liquidated Damages or
reduction in the Contract Price;

(c) to meet the Commercial Operation Performance Guarantees;

(d) any relief from liability for any other damages;

(e) any relief for deductions from payments;

(f) any relief from liability to rectify Defects;

(g) any increase in the Contract Price; or

(h) payment of any costs incurred,

which arises out of or in connection with any act or omission of the Nominated Subcontractor, whether
under or in connection with this Contract or the Supply Agreement.

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 53


1.25 The Contractor waives any and all rights, under contract, tort or otherwise at law, to assert any and
all defences which the Contractor may have to a Claim by the Owner for the non performance,
inadequate performance or delay in performance under or in connection with this clause 1.

PwC | Integrated Infrastructure | EPC Contracts in the solar industry 54


© 2022 PricewaterhouseCoopers. All rights reserved.
PwC refers to the Australia member firm, and may sometimes refer to the PwC network.
Each member firm is a separate legal entity. Please see www.pwc.com/structure for further details.
This content is for general information purposes only, and should not be used as a substitute for
consultation with professional advisors.
Liability limited by a scheme approved under Professional Standards Legislation.
PWC200399997

You might also like