Moseleo Estimates
Moseleo Estimates
Moseleo Estimates
A SITE PREPARATION
Materials Cost
Site Clearing and Demolition mᶾ 3.00 300.00 900.00
Filling & Compaction mᶾ 2.70 300.00 810.00
Materials 4,995.00
Labor 1,300.00
Direct Cost 6,295.00
C MASONRY WORK
Column 1 (.25x.25x5.8) (4pcs)
Cement bags 10.00 195.00 1,950.00
Sand cu. m. 0.73 550.00 398.75
Gravel cu. m. 1.45 1,270.00 1,841.50
Beam (.20x.20x16.40)
Cement bags 5.00 195.00 975.00
Sand cu. m. 0.33 550.00 180.40
Gravel cu. m. 0.66 1,270.00 833.12
Slab 1 (Ground)
Cement bags 8.00 195.00 1,560.00
Sand cu. m. 0.58 550.00 319.00
Gravel cu. m. 1.16 1,270.00 1,473.20
Slab 2 (Roofdeck)
Cement bags 13.00 195.00 2,535.00
Sand cu. m. 0.92 550.00 506.00
Gravel cu. m. 1.84 1,270.00 2,336.80
CHB Walls
4" C.H.B. pcs 275.00 19.00 5,225.00
Cement bags 12.00 195.00 2,340.00
Sand cu. m. 0.83 550.00 453.75
Materials 26,174.66
Labor 8,125.00
Direct Cost 34,299.66
D REINFORCEMENT WORK
Columns
16mm Ø Def. Bars pcs 53.00 376.70 19,965.10
10mm Ø Def. Bars pcs 6.00 148.40 890.40
#16 Tie Wire rolls 4.00 70.00 280.00
Beam
12mm Ø Def. Bars pcs 17.00 213.95 3,637.15
10mm Ø Def. Bars pcs 16.00 148.40 2,374.40
#16 Tie Wire rolls 2.00 195.00 390.00
Footing
10mm Ø Def. Bars pcs 10.00 148.40 1,484.00
#16 Tie Wire rolls 2.00 70.00 140.00
Slab
12mm Ø Def. Bars pcs 20.00 213.95 4,279.00
#16 Tie Wire rolls 2.00 70.00 140.00
CHB Walls
10mm Ø Def. Bars pcs 10.00 148.40 1,484.00
#16 Tie Wire rolls 2.00 195.00 390.00
Labor Cost Days # of Laborer Rate/day
Laborer 3 5.00 325.00 4,875.00
Materials 35,454.05
Labor 4,875.00
Direct Cost 40,329.05
E TILE WORK
24"x24" Granite Tiles (Tomb) pcs 220.00 30.00 6,600.00
24"x24" Tiles pcs 165.00 85.00 14,025.00
(Ground and second floor)
12"x24" Wall Tiles (Altar) pcs 14.00 120.00 1,680.00
12"x12" Ceramic Flr. Tiles (CR) pcs 80.00 12.00 960.00
16"x16" Ceramic Wall Tiles-Glazed pcs 25.00 80.00 2,000.00
(concrete chair)
Tile Adhesive bags 5.00 220.00 1,100.00
Tile Grout bags 3.00 53.90 161.70
4" Ø Metal Cutting Disk pcs 2.00 360.00 720.00
Fine Sand mᶾ 1.00 700.00 700.00
Masonry Cement bags 2.00 230.00 460.00
Materials 28,406.70
Labor 2,925.00
Direct Cost 31,331.70
F PAINT WORK
Acrylic Latex Paint Primer gal 2.00 780.00 1,560.00
Flat wall Latex White gal 2.00 750.00 1,500.00
Sapal Water Proofing gal 0.67 1,450.00 965.70
Paint Neutralizer gal 0.50 230.00 115.00
7" Roller Brush pcs 3.00 70.00 210.00
2" Paint Brush pcs 5.00 45.00 225.00
1" Masking tape pcs 2.00 30.00 60.00
Materials 4,635.70
Labor 650.00
Direct Cost 5,285.70
H METAL WORKS
Gate 1 (2mx2.1m) 4 leaf set 1.00 -
2"x3" Rectangular Bar pcs 1.00 925.00 925.00
1"x1" Square Bar pcs 4.00 248.00 992.00
12mm Round bars pcs 4.00 186.00 744.00
Welding Rod kl 3.00 75.00 225.00
Materials 23,508.50
Labor 8,227.98
Direct Cost 31,736.48
I Plumbing Works
Wash closet Ordinary pcs 1.00 700.00 700.00
250l PVC barrel (Septic vault) pcs 1.00 1,500.00 1,500.00
2” ø Pvc Pipe pcs 4.00 125.00 500.00
2” 90 Deg PVC elbow pcs 6.00 79.00 474.00
Solvent can 1.00 82.00 82.00
Teflon roll 1.00 35.00 35.00
Stainless Floordrain pcs 1.00 135.00 135.00
Labor Cost Days # of Laborer Rate/day
Labor 650.00
Direct Cost 4,076.00
S UM MA R Y
BILL OF QUANTITIES
Submitted by:
KENDEL L. ESPERAS
Proprietor/Manager
XI.10 SIGNAGES lot 1.00 -
a. LPCC lot 1.00
b. Provincial Seal unit 1.00
N
#NAME?
#NAME?
#NAME?
#NAME? per sq.m
#NAME?
8,955,000.00
#NAME?
5,874,820.85 5,874,820.85
#DIV/0!
#DIV/0!