04 App C.11 Geotechnical
04 App C.11 Geotechnical
04 App C.11 Geotechnical
APPENDIX C.11
Geotechnical Assessment
GENESIS ENERTRAG KOMAS (PTY) LTD
FINAL
WSP
THE PAVILION, 1ST FLOOR
CNR PORTSWOOD AND BEACH ROAD, WATERFRONT
CAPE TOWN, 8001
SOUTH AFRICA
Signature
Signature
Signature
Report number 1 1 1
PREPARED BY
AUTHORISED BY
KOMAS WIND ENERGY FACILITY & ASSOCIATED POWER LINE & ELECTRICAL INFRASTRUCTURE WSP
Project No. 41102874 January 2021
GENESIS ENERTRAG KOMAS (PTY) LTD Page iii
PRODUCTION TEAM
CLIENT: GENESIS ENERTRAG KOMAS (PTY) LTD
Andrea Gibb
WSP
KOMAS WIND ENERGY FACILITY & ASSOCIATED POWER LINE & ELECTRICAL INFRASTRUCTURE WSP
Project No. 41102874 January 2021
GENESIS ENERTRAG KOMAS (PTY) LTD Page v
TABLE OF 1 INTRODUCTION ................................................................... 1
CONTENTS 1.1
1.2
Project Background and Aims ...................................................... 1
KOMAS WIND ENERGY FACILITY & ASSOCIATED POWER LINE & ELECTRICAL INFRASTRUCTURE WSP
Project No. 41102874 January 2021
GENESIS ENERTRAG KOMAS (PTY) LTD Page vii
8 GEOTECHNICAL IMPACT ASSESSMENT ............... 11
REFERENCES ..................................................................................... 1
FIGURES
Figure 1. Location of the proposed Komas WEF and grid
servitude (Created by report authors during
this report’s generation for use in the
assessment as described in this report. Source
data: Base map from OpenStreetMap and
OpenStreetMap Foundation). ................................................ 1
Figure 2. Site geological setting (Created by report authors
during this report’s generation for use in the
assessment as described in this report. Source
data: 2916 Springbok 1:250 000 Geological
Map, 2001). .......................................................................................... 5
Figure 3. Regional Terrain (Created by report authors during
this report’s generation for use in the
assessment as described in this report. Source
data: Google Maps). ...................................................................... 6
Figure 4. Komas WEF site topography (Created by report
authors during this report’s generation for use
in the assessment as described in this report.
Source data: National Geo-spatial Information
(NGI) 1:50 000 topocadastral maps accessed at
https://gis.elsenburg.com/apps/cfm)............................... 7
Figure 5. Distribution of recorded earthquakes in vast area
surrounding the site (Incorporated Research
Institutions for Seismology, iris.edu/hq/). ................... 10
ANNEXURES
A SPECIALIST CURRICULUM VITAE
B IMPACT ASSESSMENT METHODOLOGY
WSP KOMAS WIND ENERGY FACILITY & ASSOCIATED POWER LINE & ELECTRICAL INFRASTRUCTURE
January 2021 Project No. 41102874
Page viii GENESIS ENERTRAG KOMAS (PTY) LTD
1 INTRODUCTION
1.1 PROJECT BACKGROUND AND AIMS
WSP Environmental (Pty) Ltd (WSP) has performed a geological assessment of the proposed Komas Wind Energy Facility
(WEF) and grid infrastructure in the Nama Khoi Local Municipality, Northern Cape. The site is located approximately
35km southeast of Kleinsee and 53km southwest of Springbok while the proposed grid servitude extends from the site
northwards to the R355 road that joins Kleinsee and Springbok (Figure 1).
The site is being evaluated for future development as a permanent renewable energy generation facility. The primary
objective of the investigation is to perform an interpretive general assessment of the impacts of the proposed
development on the geotechnical conditions or vice versa.
Figure 1. Location of the proposed Komas WEF and grid servitude, please note the proposed Substation
area includes the Battery Energy Storage System (BESS) (Created by report authors during this report’s
generation for use in the assessment as described in this report. Source data: Base map from
OpenStreetMap and OpenStreetMap Foundation).
WSP KOMAS WIND ENERGY FACILITY & ASSOCIATED POWER LINE & ELECTRICAL INFRASTRUCTURE
January 2021 Project No. 41102874
Page 2 GENESIS ENERTRAG KOMAS (PTY) LTD
Requirements of Appendix 6 – GN R326 EIA Regulations 7 April 2017 Addressed in the Specialist
Report
should be authorised, any avoidance, management and mitigation N/A
measures that should be included in the EMPr, and where applicable, the
closure plan;
o) a description of any consultation process that was undertaken during the N/A
course of preparing the specialist report;
p) a summary and copies of any comments received during any consultation N/A
process and where applicable all responses thereto; and
q) any other information requested by the competent authority. N/A
2) Where a government notice gazetted by the Minister provides for any Comply with the Assessment
protocol or minimum information requirement to be applied to a specialist Protocols that were published on
report, the requirements as indicated in such notice will apply 20 March 2020, in Government
Gazette 43110, GN 320. This
specifically includes Part A, which
provides the Site Sensitivity
Verification Requirements where a
Specialist Assessment is required
but no Specific Assessment
Protocol has been prescribed. As
at September 2020, there are no
sensitivity layers on the Screening
Tool for Geotechnical features. Part
A has therefore not been compiled
for this assessment
2 SPECIALIST INFORMATION
The report was prepared by Dr Robert Leyland, a professionally Registered Natural Scientist (Engineering Geologist)
with 11 years of experience. The report was reviewed by Dr Jon McStay, an engineering geologist with 28 years of
experience. The curriculum vitae of both specialists are included as Annexure A to this report.
WSP KOMAS WIND ENERGY FACILITY & ASSOCIATED POWER LINE & ELECTRICAL INFRASTRUCTURE
January 2021 Project No. 41102874
Page 4 GENESIS ENERTRAG KOMAS (PTY) LTD
corner is a small ridge that reaches 400m above sea level. This ridge related to the occurrence of Khurisberg Subgroup
rock outcrops mapped just outside the site boundary in that area.
Figure 2. Site geological setting, please note the proposed Substation area includes the BESS (Created by
report authors during this report’s generation for use in the assessment as described in this report. Source
data: 2916 Springbok 1:250 000 Geological Map, 2001).
A greater percentage of the land within the site and the region that surrounds the site area is occupied by shrubland
with some patches of barren land (Department of Environmental Affairs, South African National Land-Cover, 2018).
Minor mines and quarries are indicated on road that crosses the central part of the servitudes but aerial photograph
interpretation of these indicates them to be minor borrow pits, likely for gravel road maintenance. The northernmost
parts of the servitude line show the mine workings of the Dikgat Mine Diamond Mine (currently non-operational).
Figure 3. Regional Terrain, please note the proposed Substation area includes the BESS (Created by report
authors during this report’s generation for use in the assessment as described in this report. Source data:
Google Maps).
WSP KOMAS WIND ENERGY FACILITY & ASSOCIATED POWER LINE & ELECTRICAL INFRASTRUCTURE
January 2021 Project No. 41102874
Page 6 GENESIS ENERTRAG KOMAS (PTY) LTD
Figure 4. Komas WEF site topography, please note the proposed Substation area includes the BESS
(Created by report authors during this report’s generation for use in the assessment as described in this
report. Source data: National Geo-spatial Information (NGI) 1:50 000 topocadastral maps accessed at
https://gis.elsenburg.com/apps/cfm).
5 SOIL COVER
The expected soil conditions are interpreted primarily from the data on Land Types sourced from the online Agricultural
Geo Referenced Information System (AGIS), produced by the Institute of Soil, Climate and Water (Agricultural Research
Council, 2007) and supplemented by a knowledge of the geological setting and experience.
The Komas WEF site is characterized by 3 Land Types, Ai 13, Ah38 and Hb 80 with a fourth (Ib123) only being present in
small ridge area along the south-eastern corner. A summary of the soil conditions relevant to the geotechnical
assessment of each Land Type is given in Table 2. The grid servitude areas cross areas of the same Land Types as the site
and a small area of Land Type Af17 north of the Buffels River.
All land classes are characterized by sandy top soils with minimal clay contents. The majority of the Land Types have
shallow soils but the depth limiting material is rarely rock. In most cases soil depth is limited by pedocrete layers such
as calcrete and silcrete (dorbank) or a gleyed clay horizon. In the servitude areas the soils are expected to be similar to
that in the WEF site area.
The major soil categories in all the Land Types are all sandy soils that are free draining but in some cases plinthic
(partially or fully indurated) layers are expected.
Table 2. Summary of soil properties in in Land Type encountered on the Komas WEF site and the associated
grid servitude.
DEPTH AVERAGE AVERAGE
LAND TOPSOIL CLAY
LIMITING DEPTH DEPTH MAJOR SOIL CATEGORIES
TYPE %
MATERIALS (mm) CLASS
ca, ka, db, 67% Free draining structureless
Ah38 904 901-1200mm 1.3
ne, gc 23% Excessively drained sandy
68% Free draining structureless
Ai13 gc, ne 955 901-1200mm 3.0
13% Structureless with plinthic horizon
43% Excessively drained sandy
16% Structureless with plinthic horizon
Hb80 R, ka 861 601-900mm 2.1
16% Shallow soils on rock
<10% Free draining structureless
Af17 Rare 1271 >1200 93% Free draining structureless 4.0
64% Rock
Ib123 R 168 <300mm 3.0
17% Shallow soils on rock
R: Rock, ca: accumulation of carbonates of alkali earths, ka: indurated calcrete, db: dorbank, ne: unconsolidated material,
gc: gleyed clay.
6 GEOTECHNICAL CONDITIONS
6.1 INTRODUCTION
The following sections describe the expected geotechnical conditions as inferred from the known geological and
topographical conditions.
6.3 EROSION
The low site gradients coupled with the arid environment make the likelihood of soil erosion unlikely. The presence of
strong winds coupled with the generally sparse vegetation does result in a high risk of soil erosion by wind. As such
areas disturbed during construction will result in additional soil erosion. Wind erosion is however a slower process and
as such no significant erosion is expected. The WEF site does contain some very localized sandy deposits that are likely
to be aeolian deposits.
Along both grid servitudes there is evidence of minor erosion in the Buffels River vicinity but this appears to be related
to a localized outcrop of Khurisberg Subgroup rocks.
WSP KOMAS WIND ENERGY FACILITY & ASSOCIATED POWER LINE & ELECTRICAL INFRASTRUCTURE
January 2021 Project No. 41102874
Page 8 GENESIS ENERTRAG KOMAS (PTY) LTD
6.5 FOUNDATION RECOMMENDATIONS
The conditions at the Komas WEF site are such that the use of shallow foundation solutions is feasible and will prevent
the need for excessive excavations in pedocretes or hard rock. The proposed structures are however very tall and
subject to high moments which require the foundations to prevent overturn. The use of a foundation anchoring system
will therefore be required as an alternative to deep excavated bases. The proposed base footprints will require detailed
geotechnical investigations to ensure the foundation design accounts for the geotechnical characteristics of the
predocrete and bedrock conditions.
Along the servitude line the use of shallow foundations for grid infrastructure with similar foundations anchoring
systems is recommended to prevent the need for excessive excavations.
6.6 GROUNDWATER
The groundwater across the entire proposed development area is expected to be located in deep fractures in the
bedrock. Groundwater is not expected to affect the development and no shallow water table is expected, with the
exception of localised accumulations after rainfall episodes.
The natural groundwater in the fractured rock aquifer may be slightly to highly saline and does not always meet the full
requirements for drinking water.
Figure 5. Distribution of recorded earthquakes in vast area surrounding the site (Incorporated Research
Institutions for Seismology, iris.edu/hq/).
7 GEOTECHNICAL ASSESSMENT
7.1 FOUNDATION CONDITIONS
Wind turbines are normally founded on large round or square raft-like concrete bases with a central base surrounded
by a concrete raft with the size depending on the overall height of the mast. The mast structures are not particularly
heavy in terms of foundation loading, as the load is distributed evenly over the large foundation area. However, the
masts are subjected to high wind shear and thus dense soil with a moderate to high shear strength and bearing capacity
is required for founding. Therefore foundation conditions are a key constraint on engineering costs and affect project
feasibility.
WSP KOMAS WIND ENERGY FACILITY & ASSOCIATED POWER LINE & ELECTRICAL INFRASTRUCTURE
January 2021 Project No. 41102874
Page 10 GENESIS ENERTRAG KOMAS (PTY) LTD
The rock condition in this area is generally considered favourable for founding the masts. However the metamorphic
nature of the sub-outcrop can result in highly variable and unpredictable rock mass properties. This can result in
significant lateral variations in excavation and anchoring conditions. Additionally the presence of superficial pedocrete
deposits over weaker soils can result in inadequate foundation conditions for the bases.
In general founding depth would be approximately 2.0m, which will result in some difficult excavation and potentially
the need for rock blasting to create an even rock surface for casting the base. The removal of some indurated pedocrete
horizons may also be required. The bearing capacity in the bedrock is expected to be well in excess of the required
bearing capacity for the anticipated loads of the operating wind turbines.
8 GEOTECHNICAL IMPACT
ASSESSMENT
The geotechnical impact assessment of the proposed Komas WEF and associated grid servitude development was
performed according to the methodology provided and included in Annexure B of this report. The assessment considers
the entire development but the three main parts of the development, namely large structures (turbines and pylons),
cable trenches and access roads are the primary consideration. The impacts are presented separately for the WEF
development (Table 3) and the grid servitude (Table 4).
Construction
Decommissioning
Cumulative Impacts
Construction
Decommissioning
Cumulative Impacts
WSP KOMAS WIND ENERGY FACILITY & ASSOCIATED POWER LINE & ELECTRICAL INFRASTRUCTURE
January 2021 Project No. 41102874
Page 2 GENESIS ENERTRAG KOMAS (PTY) LTD
9 CONCLUSIONS AND
RECOMMENDATIONS
The completed desktop assessment of the geotechnical conditions at the proposed development site and grid servitude
of the Komas WEF has shown the site to be generally suitable for the proposed development. The proposed development
should, from a geotechnical impact perspective, be authorised. There is no preferred grid servitude option with respect
to the geotechnical impact assessment.
The most significant geotechnical condition that will affect the development is the expected hard excavation conditions.
It is therefore recommended that shallow foundations that are anchored to the bedrock are considered. This will require
a detailed study of the rock mass and pedocrete properties at the wind turbine locations. The excavation conditions will
also affect the trench excavation costs negatively.
Minimal slope stability issues are expected as slope areas are minimal. No other problem soils or problem geotechnical
conditions are expected on site.
Access roads can be developed as gravel road with suitable wearing-course to protect the subgrade likely being obtained
from local calcrete deposits.
The impacts of the development have been assessed and all geotechnical impacts are considered to have a very low
significance.
REFERENCES
Agricultural Research Council, 2007. Land types of South Africa, 1:250 000 map and memoir series. ARC-Institute
for Soil, Climate and Water. Pretoria, South Africa.
Fernández L.M., and Du Plessis A., 1992. Seismic hazard maps for Southern Africa. Published by the Government printer
for the Geological Survey of South Africa (presently known as the Council for Geoscience).
Department of Environmental Affairs, South African National Land-Cover, 2018. Dataset downloaded from
https://egis.environment.gov.za/gis_data_downloads.
ANNEXURES
ASPECIALIST
CURRICULUM
VITAE
JON McSTAY, B.Sc.H, Ph.D
Director (Engineering and Environmental Geologist),
Environment and Energy
CAREER SUMMARY
An engineering and environmental geologist with twenty five years of consulting
experience, Dr Jon McStay has considerable experience in geotechnical site
investigation and ground engineering for buildings, major infrastructure, roads, ports
and harbours.
His key experience includes, Geotechnical Investigations, Geophysical Investigations,
Engineering Geology and Ground Engineering, Marine Geotechnical and Reclamation
and Expert Witness
Dr McStay was Lecturer in Engineering Geology at the University of Cape Town from
1989 to 1995.
— Firgrove Rolling Stock Depot, Cape Town, Western Cape, South Africa (2014):
Project leader. Geotechnical investigations of existing structures and heavy crane
gantries for refurbishment and extension to rolling stock repair depot. Client:
PRASA.
— Cape Flats 3 Bulk Sewer, Cape Town, South Africa.(2013 ) Project leader.
Geotechnical investigation of bulk sewer. Client : City of Cape Town.
— Labadi Beach Hotel, Accra, Ghana, Africa (2010): Project leader. Geotechnical
investigation for beachside hotel and resort development. Client: Constant
Capital
— Maputo Waterfront, Mozambique, Africa (2010): Project leader. Geotechnical
investigations for multi-storey structures with deep basements for beachfront
development. Client: CR Holdings.
— Cape Town Stadium, Cape Town, Western Cape, South Africa (2006-2010):
Project Leader. Geotechnical discipline responsible for all ground engineering
and remediation of contaminated land for the 2010 FIFA World Cup Stadium and
Green Point Urban Park. Including quality assurance of all foundations and bulk
earthworks. Client: City of Cape Town.
— SARC Khayelitsha Rail, Cape Town, Western Cape, South Africa (2005): Project
leader Detailed in-situ testing to determine elastic modulus and compressibility
of carbonate sands for founding road over rail bridges. Client: SARC.
— Garden Route Shopping Mall, George, Western Cape, South Africa (2004):
Project leader. Geotechnical investigation of foundation conditions, piling
specifications and earthworks for regional shopping centre. Client: Arcus Gibb.
— Sonangol Headquarter Building, Luanda, Angola, Africa (2000-2001): Project
leader. Geotechnical investigation and design of piled foundations for a 20 storey
building with a deep basement. Client: Sonangol.
— US Consulate Steenberg, Cape Town, Western Cape, South Africa (2001-2005):
Project leader. Preliminary geotechnical and environmental site investigation and
site geologist for detailed geotechnical investigation and construction supervision
of new office building foundations and earthworks, including driven cast in-situ
piles. Client: US OBO and Hensel Phelps.
— Century City, Cape Town, Western Cape, South Africa (1995-2001): Project
leader. Geotechnical investigations for site planning and specific investigations
and foundation design specifications for Theme Park, various office buildings and
associated infrastructure. Client: Monex.
Marine Geotechnical
— Port of Pemba Oil and Gas Hub, Mozambique, Africa (2014): Project leader.
Geotechnical investigations, including onshore and offshore drilling and testing.
Design review of geotechnical aspects of quaywall design and reclamation works.
Client: ENILS.
— Port of Walvis Bay, North Port Expansion, Namibia, Africa (2013-2014):
Geotechnical review consultant for port expansion projects, including offshore
and onshore geotechnical drilling investigations and assessment of sediment
quality for offshore disposal. Client: Namport.
— Port of Durban – Bayhead, Durban, KwaZulu-Natal, South Africa (2014): Project
Leader. Geotechnical investigation for waste handling facilities. Client: Transnet
National Ports Authority (TNPA).
— Port of Durban Pier 1 Phase 2, Durban, KwaZulu-Natal, South Africa (2012):
Geotechnical review consultant. Geotechnical review of foundation conditions.
Client: Transnet National Ports Authority (TNPA).
Page 2 of 3
JON McSTAY, B.Sc.H, Ph.D
Director (Engineering and Environmental Geologist),
Environment and Energy
Page 3 of 3
ROBERT LEYLAND, Ph.D., M.Sc.
Principal Consultant & Engineering Geologist,
Environment & Energy
CAREER SUMMARY
An engineering and environmental geologist, Robert Leyland, has worked in both
consulting and research environments for 12 years. During this time he gained field
experience by performing mapping, geotechnical, geological and hydrogeological
investigations and project management as a project leader. His fields of experience
include investigations for large commercial developments, geological pavement
material investigations, pipeline and shallow foundation investigations, aquifer
exploration and vulnerability mapping.
EDUCATION
Geotechnical foundation South African Council for Natural Scientific Profession, SACNASP
investigations Professional Natural Scientist – Geological Science
Geological pavement South African Institute for Engineering and Environmental SAIEG
material investigations Geologists
Engineering Geology Association of Engineering Geologists AEG
assessments
Soil and groundwater PROFESSIONAL EXPERIENCE
contamination
investigations Geotechnical investigations
— Geotechnical Investigation for the detailed engineering design for the
LANGUAGES rehabilitation of Kolongo Landfill, Bangui, Central African Republic (2020).
English Geotechnical Investigation Lead. Geotechnical investigation including on site
rotary percussion drilling, regional soil profiling, groundwater investigation
Afrikaans and capping material assessment. Client: UNOPS.
— Geotechnical Investigation for the proposed upgrades of Port Victotia Quay,
Mahe, Seychelles (2019): Geotechnical Investigation Lead. Comprehensive
geotechnical investigation including seismic surveys, core drilling and offshore
sediment sampling. Client: Seychelles Port Authority / Project Planning &
Management (Ltd).
— Geotechnical investigation at Mananga Weir in the Komati River, Mananga,
eSwatini (2019): Geotechnical Investigation Lead. Core drilling and sediment
sampling from floating river barge. Client: Climate Resilient Infrastructure
Development Facility (CRIDF).
— Geotechnical Investigation for Biomass Power Plant development in Northern
Namibia (2019). Geotechnical Investigation Lead. Comprehensive geotechnical
investigation including gravity surveys, electrical resistivity surveys, core
drilling and trial pitting. Client: Nampower / Burmeister & Partners (Pty) Ltd.
— Geotechnical Investigation of Proposed Brewery Site, Marracuene,
Mozambique (2018): Project manager and lead consultant. Comprehensive
ROBERT LEYLAND, Ph.D., M.Sc.
Principal Consultant & Engineering Geologist,
Environment & Energy
Page 2 of 5
ROBERT LEYLAND, Ph.D., M.Sc.
Principal Consultant & Engineering Geologist,
Environment & Energy
Page 3 of 5
ROBERT LEYLAND, Ph.D., M.Sc.
Principal Consultant & Engineering Geologist,
Environment & Energy
AWARDS
Page 4 of 5
ROBERT LEYLAND, Ph.D., M.Sc.
Principal Consultant & Engineering Geologist,
Environment & Energy
evidence from case studies. Journal of the South African Institute of Civil
Engineering. Vol. 58, No 1, pp 26-33.
Presentations
— Leyland, R.C. and McStay, L. 2016. Geological investigations for the future
expansion of the SADC Gateway Port of Walvis Bay, Namibia: influence of
terrestrial and marine sedimentology on Port development. 35 th International
Geological Congress, ICC Cape Town, August 2016,
— Leyland, R.C., Witthüser, K.T. and van Rooy, J.L. 2006. Vulnerability mapping in
the Cradle of Humankind World Heritage Site. Proceedings of the 8th
conference on limestone hydrology. Neuchatel, Switzerland, pp 173-178.
— Leyland, R.C. and Schneider, M. 2009. Regional Description of the Groundwater
Chemistry of the Kruger National Park (KNP) using Multivariate Statistics.
Fourth Biennial Groundwater Conference, Somerset West. 15-18 November
2009
— Leyland, R.C. The development of a strategic slope management system for use
in South Africa. In, Williams, A.L., Pinches, G.M., Chin, C.Y., McMorran, T.J. and
Massey, C.I. (Eds.). Geologically Active. Proceedings of the 11th IAEG Congress,
Auckland, New Zealand, 5-10 September, 2010, pp 1265-1277.
— Leyland, R and Paige-Green, P., 2011. A simple slope hazard management
system for the South African Primary Road Network. 8th International
Conference on Managing Pavement Assets, Santiago, Chile, November, 2011.
— Leyland, R.C, 2014. A case study of intelligent compaction used in road
upgrades. 12th IAEG Congress, Turino, Italy, 15-19 September 2014.
— Leyland, R.C, 2014. Some variations in petrography of South African Karoo
Dolerites and the effects thereof on aggregate properties. 12th IAEG Congress,
Turino, Italy, 15-19 September 2014.
Page 5 of 5
BIMPACT
ASSESSMENT
METHODOLOGY
Impact Assessment Methodology
Note from the CSIR: The following impact assessment must be used to assess the potential impacts and
significance thereof.
As per the DEFFT Guideline 5: Assessment of Alternatives and Impacts, the following methodology is applied to
the prediction and assessment of impacts and risks. Potential impacts and risks have been rated in terms of the
direct, indirect and cumulative:
Direct impacts are impacts that are caused directly by the activity and generally occur at the same time and at
the place of the activity. These impacts are usually associated with the construction, operation or maintenance
of an activity and are generally obvious and quantifiable.
Indirect impacts of an activity are indirect or induced changes that may occur as a result of the activity. These
types of impacts include all the potential impacts that do not manifest immediately when the activity is
undertaken or which occur at a different place as a result of the activity.
Cumulative impacts are impacts that result from the incremental impact of the proposed activity on a common
resource when added to the impacts of other past, present or reasonably foreseeable future activities.
Cumulative impacts can occur from the collective impacts of individual minor actions over a period of time and
can include both direct and indirect impacts.
Nature of impact/risk - The type of effect that a proposed activity will have on the
environment.
Spatial extent – The size of the area that will be affected by the impact/risk:
o Site specific;
o Local (<10 km from site);
o Regional (<100 km of site);
o National; or
o International (e.g. Greenhouse Gas emissions or migrant birds).
Reversibility of the Impacts - the extent to which the impacts/risks are reversible
assuming that the project has reached the end of its life cycle (decommissioning
phase):
o High reversibility of impacts (impact is highly reversible at end of project life
i.e. this is the most favourable assessment for the environment);
o Moderate reversibility of impacts;
o Low reversibility of impacts; or
o Impacts are non-reversible (impact is permanent, i.e. this is the least
favourable assessment for the environment).
With the implementation of mitigation measures, the residual impacts/risks are ranked
as follows in terms of significance:
Very low = 5;
Low = 4;
Moderate = 3;
High = 2; and
Very high = 1.