The program management plan is a single, formal, dynamic document that outlines how the program is to be managed,
executed, and controlled. It contains the overall program governance, information on components (initiatives and projects),
benefits realization, related management plans and procedures, timelines, and the methods used to plan, monitor, and control
the program as it progresses. This document evolves with the program and will be updated to reflect any relevant changes
throughout program execution. This document should ensure there are no surprises through execution on how the program is
managed or decisions are made.
This document is also the final source of all approved changes to budget, schedule, scope, success criteria, and benefits when
it comes time to close the program and assess program success. The program management plan is part of the Portfolio
Management Group’s program benefit delivery phase of the life cycle and is required for all programs.
Input into the program management plan may come from many different sources including, but not limited to, Sponsor, senior
leadership, program and/or component intake proposal(s), program and/or project charter(s) and business case(s), initial
analysis/research done when proposing the program or components, subject matter experts within business unit(s), program
governance bodies, and other stakeholders (such as staff, students, faculty).
The author is the Program Manager for the program. The document should initially be reviewed by and approved by the
Program Sponsor (recorded in the revision history) and program governance.
Instructions
1. Write preliminary program management plan and create required baselines (budget, scope, benefits, and roadmap).
Obtain agreement from teams and governance, and approval from sponsor. Record revisions and approvals in the
Revision History
2. Execute the document according to the documented management plans.
3. Update the document, as required, to reflect approved program changes as the program evolves.
4. Before program completion, make any final updates and use the final schedule, budget and expenditures, success
criteria, benefit, scope, et cetera to assess program success during program closure.
5. Upload to TeamDynamix
Next Steps
Execute the program according to the strategies and plans laid out in this document. Update this document to reflect any
approved changes during program execution. Reflect final program results in this document at the end of the program and use
this document during program closure to assess program success.
Page | 1
File Location: [option to enter file storage location]
Program Management Plan – [Insert Program Name]
Table of Contents
Program Definition......................................................................................................................................4
Program Description................................................................................................................................4
Program Overview...............................................................................................................................4
Program Vision....................................................................................................................................4
Business Need.....................................................................................................................................4
Program Outcome and Deliverables....................................................................................................4
Program Scope........................................................................................................................................4
Program Components..............................................................................................................................4
Program Dependencies...........................................................................................................................5
Program Constraints................................................................................................................................5
Program Success Criteria.........................................................................................................................6
Program Management Plans.......................................................................................................................6
Benefits and Benefits Realization Management......................................................................................6
Benefits Realization Management.......................................................................................................6
Baseline Benefits.................................................................................................................................6
Current Benefits..................................................................................................................................7
Roadmap and Schedule Management.....................................................................................................7
Schedule Management........................................................................................................................7
Baseline Roadmap and Schedule.........................................................................................................7
Current Roadmap and Schedule..........................................................................................................7
Budget and Cost Management................................................................................................................7
Cost Management...............................................................................................................................7
Baseline Budget...................................................................................................................................8
Current Budget....................................................................................................................................8
Other Management Plans........................................................................................................................8
Component Management...................................................................................................................8
Scope Management.............................................................................................................................8
Change Management..........................................................................................................................8
Page | 2
File Location: [option to enter file storage location]
Program Management Plan – [Insert Program Name]
Stakeholder Management...................................................................................................................9
Communication Management.............................................................................................................9
Procurement Management.................................................................................................................9
Staffing Management..........................................................................................................................9
Risk & Issue Management.................................................................................................................10
Program Governance.................................................................................................................................10
Governance Committee(s).....................................................................................................................10
Governance Decision Making Approach................................................................................................10
Governance Reviews.............................................................................................................................10
Revision History.........................................................................................................................................11
Page | 3
File Location: [option to enter file storage location]
Program Management Plan – [Insert Program Name]
Program Definition
Program Sponsor: [insert name, title]
Program Manager: [insert name]
Estimated Program Start Date: [insert date] Actual Program Start Date: [insert date]
Estimated Program End Date: [insert date] Actual Program End Date: [insert date]
Program Description
The overview of the program should be documented in the program charter, so provide a link to that
document. State the program vision, as documented in the program charter, and record any changes to
the vision here. The description should link to the documented business need in the charter and/or
business case being addressed by the program, and capture the intended outcome and deliverables of
the program. The Program Charter, intake form, and business case are good references for this section,
initially, although this information may have to be changed in this section and kept up to date as the
program evolves.
Program Overview
[Insert link to program charter for an overview of the program]
Program Vision
[Insert Program Vision]
Business Need
[Insert link to program charter and/or business case where business need already documented]
Program Scope
State the scope of the program (what is in and out of scope), keeping in mind that scope items in a
program will relate to business results, not tactical delivery items. The scope statement in the Program
Charter can be used as a starting point. This section provides the opportunity to expand upon the
charter scope in more detail, and record approved changes to scope as the program evolves. This
section will always contain the up to date scope, with changes recorded in the revision history of this
document. Approved scope changes will also have been documented on Change Requests.
Page | 4
File Location: [option to enter file storage location]
Program Management Plan – [Insert Program Name]
Program Components
Describe the components (projects and initiatives) for this program. The component type will be either
initiative or project. The status column should indicate whether the component is proposed, approved
but not started, in progress, or complete. The Program Charter, intake form, and business case are good
references to start this section. Information in this section will change and have to be updated as the
program evolves.
Mark the high priority components with an ‘*’ in front of the name. When tradeoffs have to be made
during execution due to resourcing and other constraints, these the components that will take priority
over the others.
* in front of component name indicates high priority components when tradeoffs due to constraints are necessary during execution
Program Dependencies
This section should contain the list of program dependencies. Dependencies between components should
be documented here, as well as any external dependencies that may affect the program. Information in
this section will change and have to be updated as the program evolves. Program component
dependencies may best be illustrated with a network diagram.
Program Constraints
List the constraints (restrictions that could affect the performance of the program that limit resources
(people and budget), schedule, or scope and could affect quality) of the program.
Page | 5
File Location: [option to enter file storage location]
Program Management Plan – [Insert Program Name]
Describe any criteria for prioritizing components within the program while managing constraints (for
example, if resources are constrained and a component has to be delayed, how is it decided which
component is delayed).
The program charter is a good reference to start this section. Information in this section will change and
have to be updated as the program evolves.
Baseline Benefits
Insert or link to the baseline (initial) benefits register. The benefits can be maintained within the benefits
register template, or the table from the template could be copied here and filled out. Obtaining these
Page | 6
File Location: [option to enter file storage location]
Program Management Plan – [Insert Program Name]
benefits are the point of establishing a program for the scope of work to be done. The benefits should be
specific, measurable, have an expected delivery date (with benefits being realized throughout the
duration of the program), and have somebody assigned responsibility.
[Insert link to Benefits Register, or copy benefits register table here to maintain]
Current Benefits
Create or link to the current, updated version of the benefits register (reflecting realized benefits, and
approved changes to benefits (dates, measures, responsibility, removal or addition of benefits, etc). The
benefits can be maintained within the benefits register template, or the table from the template could be
copied here and maintained throughout program execution, according to the benefits management
plan. Obtaining these benefits are the point of establishing a program for the scope of work to be done.
The benefits should be specific, measurable, have an expected delivery date (with benefits being realized
throughout the duration of the program), and have somebody assigned responsibility.
[Insert link to Current Benefits Register, or maintain current benefits register table here to maintain]
Page | 7
File Location: [option to enter file storage location]
Program Management Plan – [Insert Program Name]
Baseline Budget
Insert or link to the baseline (initial) budget developed for the program.
Current Budget
Insert or link to the current, updated version of the program budget and expenditures that reflects any
approved budget changes during program and component execution, as well as expenditures to date.
Scope Management
Provide a description of the following: who has the authority and responsibility for scope management,
how the scope is defined, how the scope is measured and verified (e.g. quality checklists, scope baseline,
benefits register, etc.), the scope change process (which may already be documented in the change
control process), and who is responsible for approving program scope and accepting final program
benefit(s).
Page | 8
File Location: [option to enter file storage location]
Program Management Plan – [Insert Program Name]
Change Management
Provide a description of the program’s change control process (this would be for changes to do with the
program scope, roadmap/timing, and results). Program changes are normally responses to updated
business drivers or constraints. This section should include: where change requests are to be stored and
how they will be tracked & monitored, identification of who has approval authority for changes, and who
can submit requests for change. The scope of change in this section should include changing scope of
the program, adding/removing components, changing benefits, changes to budget, terminating
components, changes in timelines that affect benefit delivery, et cetera.
Stakeholder Management
This section should contain the list of stakeholders, and outline any specific plans for managing these
stakeholders. Insert or link to the stakeholder register. Stakeholders can be maintained within the
stakeholder register template, or the table from the template could be copied here and maintained
during program execution within this document. The primary stakeholder(s) should be clearly identified
within the register.
Describe how the stakeholders will be managed, including how often the stakeholders will be monitored
and the register updated, who is responsible, who is involved in gathering information for the register,
and identifying strategies for managing stakeholder groups, and how stakeholders will be managed at
component levels vs program level.
Communication Management
Link to the communications plan for the program, or copy the communications plan template and
maintain the communications plan here. This communications plan should be updated regularly and be
based on expectations of stakeholders, program governance, and program teams. The communication
plan should account for how communication will be handled between the Program Manager and the
component teams as well.
Procurement Management
Provide a description of the necessary steps and responsibilities for procurement from the beginning to
the end of the program. Include separation of responsibility for sub-programs, projects and initiatives.
Depending on the program, this section may require the Program Manager to work closely with
Procurement, a Licensing Coordinator, etc. Include information on who is responsible for contract
negotiations, approvals, maintaining the vendor relationship and monitoring vendor progress against
contract and statements of work.
Page | 9
File Location: [option to enter file storage location]
Program Management Plan – [Insert Program Name]
Staffing Management
Provide a description of how the program will be staffed and how staff will be managed. List key
resources and times/durations they are needed, as well as any required program staff training to
prepare them. Also include strategy for staffing sub-programs, projects and initiatives. Include any
information on reporting relationships and/or dotted reporting relationships, staff performance issues,
and how escalations will be handled if staff availability is an issue.
[Insert Risk & Issue Management Plan and link to RAID log]
Program Governance
Governance Committee(s)
Describe the program governance structure (diagrams may be used with this description). Describe the
roles and responsibilities of each governing group, outlining decision making authority, and overall
interest/focus/purpose of the group within the program. Document how often the governing groups will
meet, who will chair, and who attends the meetings (as a member and as a reference source, when
required). If there is a terms of reference documented for the group, provide a link to it.
Page | 10
File Location: [option to enter file storage location]
Program Management Plan – [Insert Program Name]
Governance Reviews
Stage gate/Milestone reviews
This section outlines stage gate or milestone reviews and their requirements. This section should outline
when the reviews will be held, what will be reviewed, and the data to be reviewed prior to determining
whether to move on to the next stage.
This section outlines when and how often program performance will be reviewed by the group(s),
focusing on the overall performance and management of the program. This section should also describe
the required program performance information that must be provided to the group(s) in support of these
reviews.