Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

0 0 21119123912111ProjectReport

Download as pdf or txt
Download as pdf or txt
You are on page 1of 13

Rajasthan State Highways Development Programme

PPP Division, PWD


Consultancy Services for Preparation of Feasibility Report of
Two-Laning of Km 0.0 to Km 63.485 of SH-25 comprising the
section from Gangapur to Sikandra

PROJECT REPORT

October-2015

 CENTRO DE ESTUDIOS DE RIALS Y CONTROL DE OBRA, S.A.


 AVANZA ENGINEERING PVT.LTD.
 SHP CONSULTING ENGINEERS.
Office Address: D – 75, Near BSNL Office, Vaishali Nagar, Jaipur - 302021
PUBLIC WORKS DEPARTMENT Consultancy Services for Preparation of Feasibility Report of
Two-Laning of Km 0.0 to Km 63.485 of SH-25 comprising the
Government of Rajasthan
section from Gangapur to Sikandra
Feasibility Report

Executive Summary
E1 Project Background
Govt. of Rajasthan has announced development of 20000 kms highways during next 5 years.
Projects and schemes are being identified for implementation of the announcement. Planning
commission, New Delhi was also approached for selected projects to get 20% VGF from GoI.
Several rounds of meetings held at Planning Commission for identification of road stretches,
working out packages, finalization of various documents and working out timeline etc.
This Feasibility Report details the approach, methodology and work plan for carrying out
feasibility study of the following road grouped under package-13
Project Road Considered for Study
The project road starts at Km 0.0 near Gangapur at NH-11B and ends at Km 63.485 at NH-11
junction in Sikandra. The design length is 63.485 Km

S No Description of Road Length (Km)

1 Gangapur to Sikandra 63.485

E2 Present Study
The Study consists of the following:
 feasibility study including survey and investigation
 preliminary project designs and cost estimates
 preparation of technical schedules

E3 Traffic Studies and Analysis


The traffic data were collected on the study corridor and relevant information obtained on traffic
flow characteristics including classified traffic volume, hourly and daily traffic variation and travel
pattern and vehicle load characteristics. The following primary surveys were conducted to
assess the present traffic scenario:
 Classified Traffic Volume Counts
 Axle Load Survey
 Pedestrian Crossing Surveys
 Turning Movement Count

E3.1 Present Traffic Scenario


Project road sections witness annual average daily traffic (AADT) in the range of 2,571-4,442
vehicles (2,864 – 4,283 PCUs). Composition of cars is in the range of 10-16percent, mini buses
and buses is in the range of 2-3.5percent. Among commercial vehicles, mini LCVs and LCVs is
in the range of 2-3percent and all categories of trucks together constitute about 3-4percent in
total traffic.
The AADT so obtained at all the traffic survey locations are projected at a uniform growth rate of
5% for all categories of vehicles as mentioned in the TOR. The year in which the project road
reaches its design service volume at LOS-B is worked out for intermediate lane and 2-lane
configuration. The results are tabulated Table E-1.

CEMOSA/AVANZA/SHP iAugust 2015


PUBLIC WORKS DEPARTMENT Consultancy Services for Preparation of Feasibility Report of
Two-Laning of Km 0.0 to Km 63.485 of SH-25 comprising the
Government of Rajasthan
section from Gangapur to Sikandra
Feasibility Report

Table E-1: Year of Achieving DSV (PCUs/day)


Traffic I-Lane 2-Lane
Loc No. Location (PCUs/Day) LOS-B LOS-B
Y-2015
DSV-6000 DSV-15000
1 Km-12 2864 2031 Beyond 2045
2 Km-39 4283 2022 2041
3 Km-58 3610 2026 2045
Average 3586 2026 2045
LOS-B: Level of Service-B, DSV-Design Service Volume
To estimate the Equivalent Standard Axle Load of traffic, axle load surveys were carried out at
one location at Km 58.0. Based on the Spectrum of Axle loads and analysis of axle load data,
the resulting VDFs are as given in Table E-2.
Table E-2: Vehicle Damage Factors
Location Direction LCV Buses 2-AT 3-AT MAV
Gangapur to Sikandra 0.01 0.05 1.13 7.06 10.51
Km 58 Sikandra to Gangapur 0.03 0.05 4.80 7.91 -
Both Directions 0.017 0.05 3.07 7.45 10.51
Adopted value for the project road 1.00 1.00 5.0 8.0 10.5

The major commodity types being carried along the Project Road comprise machinery,
agricultural products chemical and pharmaceuticals, iron, steel and manufacturing goods.
E4 Engineering Surveys and Investigations
The Consultants have carried out engineering surveys and investigations along the Project
Road. These include: topographic surveys, road inventory and condition survey, alignment
study, pavement investigations, Benkelman beam deflection, pavement surface roughness,
hydrological study, environmental study, axle load survey, condition surveys for bridges and
structures and exploration and selection of construction materials.
E5 Road Alignment
The alignment has been studied, based on physical features and other constraints at site viz.
Land acquisition, Utilities, Construction activities, presence of religious structures etc. It has
been observed that Optical Fibre Cable (O.F.C.) is running along the road alignment.
Symmetrical widening has been proposed and through built-up area except at locations of sharp
horizontal curves.
E6 Existing Road: Inventory

E6.1 Land use and Terrain


Project road traverses through plain, rolling and hilly terrain. Land use being predominantly
barren and interspersed with built-up sections.
E6.2 Horizontal Alignment
The majority of the existing curves have radii not in conformity to SH standards for the chosen
design speed. These locations need geometric improvement. Existing curves having radii for
design speed lower than 50 Kmph were improved.

CEMOSA/AVANZA/SHP iiAugust 2015


PUBLIC WORKS DEPARTMENT Consultancy Services for Preparation of Feasibility Report of
Two-Laning of Km 0.0 to Km 63.485 of SH-25 comprising the
Government of Rajasthan
section from Gangapur to Sikandra
Feasibility Report

E6.3 Vertical Profile


Topographic survey data reveals that majority of longitudinal gradients except in hilly (ghat)
sections is less than 2 percent and maximum gradient at some over bridge approaches is
around 2.5 per cent.
E6.4 Carriageway, Shoulder and Roadway width
Existing road has 7.0m dual carriageway with 0.6-0.7m wide median for a length of 0.15Km
(0.2%) at end of the project road, 2lane wide carriageway for 32Km (48%) length, intermediate
lane for 25 Km (38.3%) and balance 9.0Km (13.5%) length has carriageway width of 3.75-5.0m.
0.5m to 2.0m granular shoulder exists in the rest of the length. 58km length of road has
bituminous surface and about 8Km length has rigid pavement. The roadway width varies from 6
to 10 m.
E6.5 Roadside Drains
There are no channelized regular longitudinal drains in most part of the project section.
E6.6 Utilities
Low-tension overhead electrical lines are running along the highway and cross the highway at
certain locations. While widening the road, the utility lines located on the new carriageway or
widening portion would need shifting. At intersections of the cross-roads and locations of traffic
facilities, there may be a need for relocation of a few electric and telephone poles during
execution stage.
E7 Pavement Condition
Detailed pavement condition surveys bring out the following salient aspects:
Pavement condition survey by visual method was carried out on the Project Road to assess the
condition of existing pavement. The % distress is compared with criteria for classification of
pavement sections as per IRC: 81-1997.
17% of project road length is in good condition, 39% in fair condition and 44% in poor condition.
Pavement Composition: The existing pavement consists of bituminous layers, WBM and
granular sub base. The minimum existing thickness excluding subgrade is about 430 mm. The
composition of various layers of the pavement in above reaches is summarised here under:
Pavement layer Thickness
Bituminous courses 20 to 70 mm
WBM 270 to 520 mm
Sub Base 130 to 300 mm
Pavement Deflection and sub grade strength: The BBD values vary between 0.43 mm to
0.77mm along the project road.
The CBR value at sub grade level is 5-8% at various locations along the project road.
E8 Improvement Proposals
The standards have been formulated for design speed of 100 kmph, in general, but not less
than 60 kmph in plain terrain. In built-up sections the existing geometric will be improved
without any social impacts. The granular shoulder of 2.5 m has been proposed. Camber of 2.5
percent has been adopted for the carriageway and paved shoulder and 3.0% for earth
shoulders. Super-elevation adopted is restricted to 7 per cent.

CEMOSA/AVANZA/SHP iiiAugust 2015


PUBLIC WORKS DEPARTMENT Consultancy Services for Preparation of Feasibility Report of
Two-Laning of Km 0.0 to Km 63.485 of SH-25 comprising the
Government of Rajasthan
section from Gangapur to Sikandra
Feasibility Report

The last 0.20 Km section of project road shall have 4 lane divided carriageway (CC pavement
reconstruction) with 1.2m median and rest of the length shall have 7m wide carriageway.
E9 Pavement Design

E9.1 Main Carriageway


The design inputs i.e. CBR value (effective CBR of 7% is considered for design) for the
proposed subgrade material, Traffic loading in terms of cumulative standard axles in million
(MSA) considered for pavement design have been summarized in Table E-3. Base and sub
base layers have been designed for 15 years and surface layers have been designed for 8
years.
Table E-3: Design Inputs for Flexible pavement
Entire Project Road length
Design Parameter
2-Lane with Granular Shoulder
Design Period, Years (Base & Sub-base) 15
Design Period, Years (Wearing Course) 8
CBR (Effective) 7%
Traffic Loading (MSA) for 15 years 10 (actual 5.65)
Traffic Loading (MSA) for 8 years 5 (actual 2.51)

The pavement composition and layer thicknesses as per IRC: 37 –2012 considering the above
design parameters are presented in Table E-4.

Table E-4: Pavement Layer Thicknesses (mm)

Pavement Composition New Construction

Bituminous Concrete (BC) 40


Dense Bituminous Macadam (DBM) 50
Wet Mix Macadam (WMM) 250
Granular Sub base (GSB) 230
Subgrade (Effective CBR=7%) 500

The thickness of DBM & BC overlay have been designed considering the subgrade strength,
total required thickness and available thickness of existing pavement.
Project road sections with poor condition shall have GSB (total=230mm) layer for the entire
width of formation and two layers of WMM (total=250mm) for the entire carriageway width and
surface layers were recommended over WMM layer.
The proposed pavement composition and layer thicknesses considering the above design
parameters are presented in Table E-5 for various category of pavement surface conditions
(good/fair, poor) recorded and for new construction.

CEMOSA/AVANZA/SHP ivAugust 2015


PUBLIC WORKS DEPARTMENT Consultancy Services for Preparation of Feasibility Report of
Two-Laning of Km 0.0 to Km 63.485 of SH-25 comprising the
Government of Rajasthan
section from Gangapur to Sikandra
Feasibility Report

Table E-5: Proposed Pavement Layer Thicknesses (mm)


Widening &
Reconstruction
Strengthening
Sections New
Pavement Composition Sections
Construction
Widening Central Widening Central
Portion portion Portion portion
Bituminous Concrete (BC) 40 40 40 40 40
Dense Bituminous Macadam (DBM) 50 - 50 50 50
Wet Mix Macadam (WMM) 250 - 250 250 250
Granular Sub base (GSB) 230 - 230 230 230
Subgrade (Effective CBR=7%) 500 - 500 - 500

E9.2 Shoulders
Shoulder has been designed as a single unit with main carriageway with 2.5m as granular
shoulder.

E10 Bridges and Culverts


The engineering studies included inventory and condition survey of the existing bridges and
cross drainage structures, development of scheme for widening of bridges and cross drainage
structures and design of new bridges, if any.
No major bridges were observed along the project road
There are 49 nos culverts and 6 nos minor bridges. Majority of the culverts have also been
inspected and found to be structurally functional. Some additional culverts are proposed for
efficient cross drainage.
The slab and pipe culverts details are presented in the following Table E-6 with their
improvement proposal.
Table E-6: Details of Culverts
Structure Condition
Type of Total
Proposed for Proposed for
Structure Numbers Retained
Widening Reconstruction
Hume pipe 23 13 3 7
RC Slab 20 7 7 6
Causeway 6 - - 6
The details of structures provided across the irrigation canals are provided in the following
Table E-7 along with the suggested improvement.
Table E-7: Details of Minor Bridges
Structure Condition
Type of Total
Structure Numbers Proposed for Proposed for
Retained
Widening Reconstruction
RC Slab 6 4 2 -

E11 Road bridges over Railway lines


No RUB, ROB and at-grade railway level crossing were observed along the project road.

CEMOSA/AVANZA/SHP vAugust 2015


PUBLIC WORKS DEPARTMENT Consultancy Services for Preparation of Feasibility Report of
Two-Laning of Km 0.0 to Km 63.485 of SH-25 comprising the
Government of Rajasthan
section from Gangapur to Sikandra
Feasibility Report

E12 Toll Plaza


Project road is proposed with two toll plazas, for its entire length. The tentative locations and
section length for tolling purpose are presented in Table E-8

Table E-8: Tentative Tolling Sections


Toll Road
Toll TVC
Section Tentative Toll Plaza Location Section
Plaza location
Length km
Gangapur to Nadauti Km 12.6 (PWD Km 13) TP-1 28.0 Km 12
Nadauti to Sikandra (NH-11) Km 56.450 (PWD Km 58) TP-2 35.5 Km 58

E13 Wayside Amenities & Truck Lay bye


Wayside amenity and truck lay byes are not envisaged as part of the project proposal.

E14 Cost Estimate


The unit rates for various items of works have been worked out on the basis of BSR PWD
Rajasthan.
The estimated total construction cost of the Project is Rs. 110.74 Cr.
Total Project Cost (at 15% additional over 2015 cost) is Rs. 127.35 Cr.

E15 Financial Analysis


Project is not found financially viable for VGF less than 40% on BOT (Toll) basis.

E16 Social Impact Assessment


Provided in a separate attachment

E17 Environmental Impact Assessment


Provided in a separate attachment

CEMOSA/AVANZA/SHP viAugust 2015


PUBLIC WORKS DEPARTMENT Consultancy Services for Preparation of Feasibility Report of
Two-Laning of Km 0.0 to Km 63.485 of SH-25 comprising the
Government of Rajasthan
section from Gangapur to Sikandra
Feasibility Report
1. Project Description
1.1. Background
Govt. of Rajasthan has announced development of 20,000 kms highways during next 5
years. Projects and schemes are being identified for implementation of the announcement.
Planning commission, New Delhi was also approached for selected projects to get 20% VGF
from GoI. Several rounds of meetings held at Planning Commission for identification of road
stretches, working out packages, finalization of various documents and working out timeline
etc.
For time bound implementation of PPP projects GoR has shown commitment by introducing
a first ever comprehensive ‘Raj. State Highways Bill-2014’. The bill has been passed by
Rajasthan State Legislative Assembly on 09-04-2015.
The Governor of Rajasthan acting through the Chief Engineer (Roads), Public Works
Department, Government of Rajasthan (the “Authority”) is engaged in the development of
state highways and as part of this endeavour, the Authority has decided to undertake
package wise shortlisted road sections (the “Project”) through Public Private Partnership (the
“PPP”) on Design, Build, Finance, Operate and Transfer (the "DBFOT") basis.
Authority has decided to conduct feasibility studies for determining the technical feasibility
and financial viability of all Highways comprising the Project. If found technically feasible and
financially viable, the Highways under the Project may be awarded on DBFOT basis to a
private entity (the “Concessionaire”) selected through a competitive bidding process. The
Project would be implemented in accordance with the terms and conditions stated in the
concession agreement to be entered into between the Authority and the Concessionaire (the
“Concession Agreement”).
In pursuance of the above, the Authority has decided to carry out the process for selection of
a Technical Consultant, a Financial Consultant and a Legal Adviser for preparing the
Feasibility Report and bid documents. The Financial Consultant will develop the revenue
model and assist the Authority in the bidding process. The Legal Adviser will review the draft
concession agreement based on the Model Concession Agreement for State Highways
through Public Private Partnership (the “MCA”) read with the Manual of Standards and
Specifications. The Technical Consultant shall prepare the Feasibility Report in accordance
with the Terms of Reference specified (“TOR”).
1.2. Project Road Details
The shortlisted roads were grouped under various packages for carrying out feasibility
studies. Further to the bidding process, package-13 consisting of four roads as mentioned
below were assigned to technical consultant M/s CEMOSA, AVANZA and SHP for carrying
out feasibility study on individual road basis, vide LOI dated 12/05/2015 and subsequently
agreement for carrying out consultancy was signed on 22/05/2015.
Package-13 Road Details

Highway No Description of Road Length (Km)

Highway - 1 Mandrayal to Karauli 37.5

CEMOSA/AVANZA/SHP 7August 2015


PUBLIC WORKS DEPARTMENT Consultancy Services for Preparation of Feasibility Report of
Two-Laning of Km 0.0 to Km 63.485 of SH-25 comprising the
Government of Rajasthan
section from Gangapur to Sikandra
Feasibility Report
Highway - 2 Sikandra to Gangapur 63.5

Highway - 3 Dholpur to Rajakhera (Border) 45.0

Highway - 4 Mahwa to Govindgarh 65.0

Total = 211.0

This report details the findings of feasibility study of the following road grouped under
package-13. Project road lies under Sawai Madhopur, Karauli and Dausa districts
Project Road Considered for Study

Highway No Description of Road Length (Km)

Highway - 1 Gangapur to Sikandra 63.5

Figure 1-1: Location Map of Project Road

CEMOSA/AVANZA/SHP 8August 2015


PUBLIC WORKS DEPARTMENT Consultancy Services for Preparation of Feasibility Report of
Two-Laning of Km 0.0 to Km 63.485 of SH-25 comprising the
Government of Rajasthan
section from Gangapur to Sikandra
Feasibility Report

Km 63.5 NH-11
Junction at Sikandra

Km 0.0 NH-11B
Junction at Gangapur

1.3. Objectives of the Feasibility Study


The main objective of the Consultancy services is to establish the technical and financial
viability for the selected project roads.
The objective of this consultancy is to undertake feasibility studies and prepare road specific
feasibility Reports for all highways comprising the project for the purpose of firming up the
Authority’s requirements in respect of development and construction of the project and
project facilities and enabling the prospective bidders to assess the Authority’s requirements
in a clear and predictable manner with a view to ensuring:
(i) enhanced safety and level of service for the road users;
(ii) superior operation and maintenance enabling enhanced operational efficiency of the
Project;

CEMOSA/AVANZA/SHP 9August 2015


PUBLIC WORKS DEPARTMENT Consultancy Services for Preparation of Feasibility Report of
Two-Laning of Km 0.0 to Km 63.485 of SH-25 comprising the
Government of Rajasthan
section from Gangapur to Sikandra
Feasibility Report
(iii) minimal adverse impact on the local population and road users due to road
construction;
(iv) minimal adverse impact on environment;
(v) minimal additional acquisition of land; and
(vi) phased development of the Project for improving its financial viability consistent with the
need to minimise frequent inconvenience to traffic that may be caused if additional
works are undertaken within a period of seven years from the commencement of
construction of the Project.

1.4. Scope of Work


Scope of Services According to the Terms of Reference of the Study, the consultancy is to
cover the following
 Feasibility Study;
 Bidding documents on commercial format

1.4.1. Feasibility Study


Following surveys, investigations and design activities are envisaged during the of the
feasibility study
 Traffic surveys
 Axle load survey
 Pavement Invesigations
 Sub-soil investigation along the alignment for the road as well as the bridge.
 Detailed soil and material survey for the purpose of pavement design and for
ascertaining the suitability of road construction material.
 Preliminary designs and cost estimates for different alternatives
 Environmental and Social impact assessment of all alternatives.
 Selection of best alternative for the pavement as well as the bridge
 Economic analysis and financial viability of the project on commercial format

1.4.2. Bidding documents on commercial format (PPP)


Following activities are envisaged during the of the Bidding Docs finalisation
 Preparation of indicative BOQ, rate analysis & cost estimates.
 Preparation of Schedules A, B, C, D, R and H of Concession Agreement

1.5. Progress to-Date


This section summarizes the work that has been carried out to-date. Analysis of the data
already collected is in hand and it is not considered relevant to this Feasibility Report to
provide details of this analysis since this report focuses on the detailed methodology and
work program for the study. However where the data collected is relevant to the detailed
methodology the information is presented in the following section.
1.6. Staff Mobilization
Following the Agreement dated 22/05/2015, the mobilization of Key Personnel is shown in
the Staffing Schedule in Table 1-1.

CEMOSA/AVANZA/SHP 10August 2015


PUBLIC WORKS DEPARTMENT Consultancy Services for Preparation of Feasibility Report of
Two-Laning of Km 0.0 to Km 63.485 of SH-25 comprising the
Government of Rajasthan
section from Gangapur to Sikandra
Feasibility Report
Table 1-9: Mobilization Dates of Key Personnel

Name Position Mobilisation Date


Mr. T R Sharma Senior Highway Engineer cum Team Leader 28/05/2015
Mr. H L Prakash Traffic Cum Safety Expert 28/05/2015
Mr. Mahendra Raj Urs S K Bridge Engineer 28/05/2015
Mr. John George Surveyor 28/05/2015
Mr. Yogesh Kumar Financial Analyst 28/05/2015
Mr. Devendra Goyal Environmental Expert 28/05/2015
Highway Design Engineer 03/06/2015
Bridge Engineer 03/06/2015
Pavement cum Material Engineer 03/06/2015
Geo-technical Expert 03/06/2015
Hydrologist 03/06/2015
Environment analyst 03/06/2015
Social Analyst 03/06/2015
Quantity Engineer 03/06/2015
Surveyor1 03/06/2015
Surveyor2 03/06/2015
Surveyor3 03/06/2015
CAD Draughtman 1 03/06/2015
CAD Draughtman 2 03/06/2015

1.7. Project Meeting


A meeting was held on 28/05/2015 between the Nodal officer and Consultant team to
discuss the proposed methodology that is likely to be adopted for the project roads feasibility
study analysis. The issues of suitable pavement treatment options and realistic unit costs to
be adopted for analysis were discussed.

S No Description of Events Date

1 Mobilisation Meeting 28/05/2015

2 Project Site Visit (Surveys & Investigations) with 20/06/2015


Project Director

3 Meeting & presentation to Superintending Engineer 28/07/2015


on supplementary Inception report

4 Project Site Visit with Project Director for finalization 13/08/2015


of project proposal

CEMOSA/AVANZA/SHP 11August 2015


PUBLIC WORKS DEPARTMENT Consultancy Services for Preparation of Feasibility Report of
Two-Laning of Km 0.0 to Km 63.485 of SH-25 comprising the
Government of Rajasthan
section from Gangapur to Sikandra
Feasibility Report
1.8. Feasibility Report Structure
Executive Summary
1. Project Background
2. Socio-Economic Profile
3. Design Standards
4. Inventory and Condition Surveys
5. Traffic Surveys
6. Engineering Surveys and Investigations
7. Preliminary Road Design
8. Preliminary Design of Structures
9. Cost Estimates
10. Economic and Financial Analysis
11. Discussions and Conclusions

CEMOSA/AVANZA/SHP 12August 2015

You might also like