0 0 21119123912111ProjectReport
0 0 21119123912111ProjectReport
0 0 21119123912111ProjectReport
PROJECT REPORT
October-2015
Executive Summary
E1 Project Background
Govt. of Rajasthan has announced development of 20000 kms highways during next 5 years.
Projects and schemes are being identified for implementation of the announcement. Planning
commission, New Delhi was also approached for selected projects to get 20% VGF from GoI.
Several rounds of meetings held at Planning Commission for identification of road stretches,
working out packages, finalization of various documents and working out timeline etc.
This Feasibility Report details the approach, methodology and work plan for carrying out
feasibility study of the following road grouped under package-13
Project Road Considered for Study
The project road starts at Km 0.0 near Gangapur at NH-11B and ends at Km 63.485 at NH-11
junction in Sikandra. The design length is 63.485 Km
E2 Present Study
The Study consists of the following:
feasibility study including survey and investigation
preliminary project designs and cost estimates
preparation of technical schedules
The major commodity types being carried along the Project Road comprise machinery,
agricultural products chemical and pharmaceuticals, iron, steel and manufacturing goods.
E4 Engineering Surveys and Investigations
The Consultants have carried out engineering surveys and investigations along the Project
Road. These include: topographic surveys, road inventory and condition survey, alignment
study, pavement investigations, Benkelman beam deflection, pavement surface roughness,
hydrological study, environmental study, axle load survey, condition surveys for bridges and
structures and exploration and selection of construction materials.
E5 Road Alignment
The alignment has been studied, based on physical features and other constraints at site viz.
Land acquisition, Utilities, Construction activities, presence of religious structures etc. It has
been observed that Optical Fibre Cable (O.F.C.) is running along the road alignment.
Symmetrical widening has been proposed and through built-up area except at locations of sharp
horizontal curves.
E6 Existing Road: Inventory
The last 0.20 Km section of project road shall have 4 lane divided carriageway (CC pavement
reconstruction) with 1.2m median and rest of the length shall have 7m wide carriageway.
E9 Pavement Design
The pavement composition and layer thicknesses as per IRC: 37 –2012 considering the above
design parameters are presented in Table E-4.
The thickness of DBM & BC overlay have been designed considering the subgrade strength,
total required thickness and available thickness of existing pavement.
Project road sections with poor condition shall have GSB (total=230mm) layer for the entire
width of formation and two layers of WMM (total=250mm) for the entire carriageway width and
surface layers were recommended over WMM layer.
The proposed pavement composition and layer thicknesses considering the above design
parameters are presented in Table E-5 for various category of pavement surface conditions
(good/fair, poor) recorded and for new construction.
E9.2 Shoulders
Shoulder has been designed as a single unit with main carriageway with 2.5m as granular
shoulder.
Total = 211.0
This report details the findings of feasibility study of the following road grouped under
package-13. Project road lies under Sawai Madhopur, Karauli and Dausa districts
Project Road Considered for Study
Km 63.5 NH-11
Junction at Sikandra
Km 0.0 NH-11B
Junction at Gangapur