Sixth Semester BBA Degree Model Examination


BBA6B13 - Management Science
Date: March 2023 2023
Time: 2.5 Hours Maximum marks: 80

Section - A
Answer Atleast 10 Questions
Each Question Carries 3 Marks
Ceiling: 30 marks

1. Write any two applications of LPP.

2. What do you mean by an objective function of an LPP?

3. Define Transportation Problem.

4. Define Optimistic Time estimates.

5. Define PERT.

6. What is meant by critical path?

7. What is Float?

8. Explain EOL.

9. What is Independent Float?

10. Explain minimax criterion.

11. State any two uses of network analysis.

12. What is Decision Trees?

13. What do you mean by Degeneracy in a Transportation Problem?

14. Define dummy activity.

15. Define optimal solution.

Section - B
Answer At least 5 Questions
Each Question Carries 6 Marks
Ceiling: 30 marks

16. Discuss the application areas of Operations Research

17. Discuss the difference between CPM and PERT.

18. Explain the methods of finding the initial feasible solution in Transportation Problem.

19. Draw a network Diagram.

Activity: A B C D E F G
Predecessors: - - A B C,D E F

1
20. From the Following pay off tables find the suitable strategy by using
a) Maximax b) Maximin c) Minimax regret

A1 A2 A3
S1 3 6 0
S2 5 5 5
S3 8 2 6
S4 -1 0 4

21. Use the graphical method to solve the following LPP.

M inimize

z = 3x1 + 2x2
Subject to
5x1 + x2 ≥ 10
x1 + x2 ≥ 6
x1 + 4x2 ≥ 12
x1 , x2 ≥ 0

22. Determine an initial basic feasible solution to the following TP by using VAM

D1 D2 D3 D4 Supply
A 11 13 17 14 250
B 16 18 14 10 300
C 21 24 13 10 400
Demand 200 225 275 250

23. What are the limitations of OR?

Section C
Answer any two Questions
Each Question Carries 10 Marks

24. Discuss the models of Operations Research.

25. From the following table find


a) Expected Monetary Value (EMV)
b) Expected Opportunity Loss (EOL)
c) Expected value of Perfect Information (EVPI)
P (S1) = 0.6 P (S2) = 0.1, P (S3) = 0.2, P (S4) = 0.1

A1 A2 A3
S1 3 6 0
S2 5 5 5
S3 8 2 6
S4 -1 0 4

26. The time estimates for the activities of a PERT network are given.
a)Draw the project network.
b)Identify Critical Path.
c) Find Standard Deviation.

2
Activiy t0 tm tp
1-2 1 1 7
1-3 1 4 7
1-4 2 2 8
2-5 1 1 1
3-5 2 5 14
4-6 2 5 8
5-6 3 6 15