ELIXIER 2 PROJECT

AIR SEPARATION PLANT


FOR NITROGEN
GENERATION
LINDE PROJECT NO.: 1110 A61D ELIXIER PROJECT NO.: 5243
LINDE PROJECT CODE.: MIRFA 1 ELIXIER PROJECT CODE: ELIXIER 2
LINDE DOC. NO.: DESCON-E-PC 1002 ELIXIER DOC. NO.:
LINDE ITEM NO.:
DESCON DOC NO.: MIRFA 1/E/MS-04 PAGE 1 OF 6

METHOD STATEMENT

FOR

CABLE TRAY AND


SUPPORT BRACKETS INSTALLATION

1.0 04-01-2010 ISSUE FOR APPROVAL UMER GHAZI SAJJAD


STATUS ISSUE DATE DESCRIPTION PREPARED CHECKED APPROVED
ELIXIER 2 PROJECT
AIR SEPARATION PLANT
FOR NITROGEN
GENERATION
LINDE PROJECT NO.: 1110 A61D ELIXIER PROJECT NO.: 5243
LINDE PROJECT CODE.: MIRFA 1 ELIXIER PROJECT CODE: ELIXIER 2
LINDE DOC. NO.: DESCON-E-PC 1002 ELIXIER DOC. NO.:
LINDE ITEM NO.:
DESCON DOC NO.: MIRFA 1/E/MS-04 PAGE 2 OF 6

CONTENTS

1. PURPOSE 3

2. SCOPE 3

3. REFERENCES 3

4. ABBREVIATIONS/DEFINITIONS 3

5. RESPONSIBILITIES 3

6. PROCEDURE 4

7. TOOLS & EQUIPMENT 5

8. HSE INSTRUCTIONS 6
ELIXIER 2 PROJECT
AIR SEPARATION PLANT
FOR NITROGEN
GENERATION
LINDE PROJECT NO.: 1110 A61D ELIXIER PROJECT NO.: 5243
LINDE PROJECT CODE.: MIRFA 1 ELIXIER PROJECT CODE: ELIXIER 2
LINDE DOC. NO.: DESCON-E-PC 1002 ELIXIER DOC. NO.:
LINDE ITEM NO.:
DESCON DOC NO.: MIRFA 1/E/MS-04 PAGE 3 OF 6

1. PURPOSE:

The purpose of this method statement is to provide guidelines for the installation and
inspection of cable trays and supports as per project drawings and specification.

2. SCOPE:

This method statement covers the erection / installation of cable trays / cable ways and
supports for electrical/instrument work and to conform to applicable inspections and tests.

3. REFERENCES:

The following documents are considered as reference documents:

 Project specifications.
 Project drawings.
 Project Quality Plan (PQP).
 Inspection & Test Plan (ITP).

4. ABBREVIATIONS/DEFINITIONS:

SM Site Manager
PQP Project Quality Plan
ITP Inspection and test Plan
I/C In -charge
QA&QC Quality Assurance & Quality control
MS Method Statement
PPE Personal Protective Equipment
HSE Health, Safety & Environment
IMTE Inspection, Measuring & Test Equipment
BA Business Area
FRM Form

5. RESPONSIBILITIES:
 Area in charge E&I checks cable ladder/tray drawings, layout and typical installation
drawings for the activity.
 Area supervisor E&I checks that the installation activity is conducted in accordance
with drawings.
 The concerned Quality inspector checks that the relevant work is being carried out in
conformance with project specifications, ITP along with the best engineering practices.
In case of non-conformance, it will be controlled by corrective action request. If an
inspection plan is given by ELIXIER/LINDE, the sequence of inspections will be
followed accordingly.
ELIXIER 2 PROJECT
AIR SEPARATION PLANT
FOR NITROGEN
GENERATION
LINDE PROJECT NO.: 1110 A61D ELIXIER PROJECT NO.: 5243
LINDE PROJECT CODE.: MIRFA 1 ELIXIER PROJECT CODE: ELIXIER 2
LINDE DOC. NO.: DESCON-E-PC 1002 ELIXIER DOC. NO.:
LINDE ITEM NO.:
DESCON DOC NO.: MIRFA 1/E/MS-04 PAGE 4 OF 6

6. PROCEDURE:

Following checks would be performed for the completion of activities, in accordance with
the relevant project specifications and reference documents.

Preparation

 The work is to be conducted with approved drawings and material list documents.
 Marking should be done with reference drawing before installation.
 The route and level of cable trays shown in Grid Station area should be as per
drawing. Any deviation from the drawings shall be agreed with the Contractor and
all changes to be recorded and marked up “as built”.
 In case of any ambiguity for the activity, technical query shall be raised.

Steel Supports Installation

 Approved welder on structure according to specification and site requirements shall


carry out installation of pre-fabricated supports.
 Welded joint's to be cleaned and painted after welding job is completed.
 Cable trays shall be supported at distance of not more than 3m as per specification.
 Cable tray supports to be installed with proper anchor bolts on concrete and welded
on steel structure unless otherwise stated in drawings / specifications.
 Supports to be checked for alignment, verticality and horizontally as per layout
drawings.

Assembling / Fitting

 Fabrication work shall be carried out on cable trays during installation with proper
rectification of sharp edges and final touch up paint shall be carried out.
 All the bends, risers to be checked as per cable tray size requirement.
 Earth bonding links to be checked for tightness.

Steel Supports and Brackets Installation

 Steel supports and brackets to be fabricated and installed in accordance with the
approved construction drawings. All rough edges to be removed and bare steel to
have one coat of primer with paint coating before installation or as per project
specifications.
 Specified sizes of steelwork according to drawings to be used.
 Welding to structures shall be the main fixing medium. The prior permission to be
obtained, if no detail mentioned in the respective drawings.
ELIXIER 2 PROJECT
AIR SEPARATION PLANT
FOR NITROGEN
GENERATION
LINDE PROJECT NO.: 1110 A61D ELIXIER PROJECT NO.: 5243
LINDE PROJECT CODE.: MIRFA 1 ELIXIER PROJECT CODE: ELIXIER 2
LINDE DOC. NO.: DESCON-E-PC 1002 ELIXIER DOC. NO.:
LINDE ITEM NO.:
DESCON DOC NO.: MIRFA 1/E/MS-04 PAGE 5 OF 6

Precautions

 The electrical supply to powered hand tools shall not exceed 110 volts. Where this is
not possible, due to the type of tool being used, the approval of the Contractor’s
representative must be sought. But these electrical supplies must be protected by
ELCBs (Earth leakage circuit breakers) at sending source side.
 All works on electrical equipment shall be in accordance with Contractor’s
representative Lock out/Tag out procedure.
 The temporary electrical network installed for job would be protected by ELCBs (Earth
 leakage circuit breakers) to avoid any accidental contact.

 Tha nguoi dung noi se yeu minh toi mai thoi thi gio day toi se vui hon. Gio nguoi lac loi
buoc chan ve noi xa xoi, cay dang chi rieng minh toi...
http://nhatquanglan1.0catch.com
 extinguishers.
 Suitable fire extinguishers shall be provided in electrical/instrument panel rooms
preferably CO2.
 Panel rooms shall be kept lock and entry should be prohibited for unauthorized
persons.
 Approved proper protected scaffolding shall be used while fixing brackets/supports
and shall be inspected by inspector.
 Cable ladder/tray scrap shall be removed on daily basis.

7. TOOLS AND EQUIPMENTS:

 Correct type, size and weight of tool shall be used for each job.
 Properly insulated and non-conductive tools shall be used for electrical work.
 Screwdrivers - A screwdriver shall have the correct size of tip to fit the slot of the
screw. Screwdrivers shall not be hammered or twisted with pliers or wrenches.
Screwdrivers shall not be carried in the pockets.
 All the power tools should be inspected by LINDE.
 Hammers - Right kind of hammer shall be selected for the job. Eye protection shall be
done all the time during work.
 Chisels - Cutting edges shall be kept sharp. Chisels heads that have mushroomed
shall be repaired. Eye protection shall be worn when using a cold chisel.
 Spanners - Right type and size shall be used.
 Hacksaws - Correct type of blade shall be selected to suit the material to be cut. The
blade should be set in a hacksaw frame so that the teeth are pointing in the forward
direction and sufficient tension shall be applied to ensure the blade is maintained rigid.
ELIXIER 2 PROJECT
AIR SEPARATION PLANT
FOR NITROGEN
GENERATION
LINDE PROJECT NO.: 1110 A61D ELIXIER PROJECT NO.: 5243
LINDE PROJECT CODE.: MIRFA 1 ELIXIER PROJECT CODE: ELIXIER 2
LINDE DOC. NO.: DESCON-E-PC 1002 ELIXIER DOC. NO.:
LINDE ITEM NO.:
DESCON DOC NO.: MIRFA 1/E/MS-04 PAGE 6 OF 6

 Power Tools - All portable power tools shall be stored in clean dry conditions. Power
tools shall not be left lying around the job site where they may be damaged and
inspected by LINDE.

 Rotating tools shall be switched off and held until rotation has completely stopped
before they are set down. Tools shall be disconnected before changing bits, blades,
cutters, or wheels.

 All portable power tools shall be equipped with properly functioning "dead man
switches".

 Grinding Machine - Care shall always be taken to ensure that the grinding wheel is
free from defect before mounting.
 The proper size and type of wheel shall be fitted to the tool so that the maximum
permissible periphery speed of the wheel does not exceed the maximum speed
displayed on the machine. No grinding machine shall be used unless the maximum
speed is clearly marked on the case. All wheels shall be fitted with adequate guards.

8. HSE INSTRUCTIONS:

 All efforts shall be made to keep the environment clean.


 “Scaffolding” and “Welding” shall be adopted to ensure safe working.
 Properly protected scaffolding shall be used while fixing brackets.
 Solid waste such as cable ladder/tray scrap shall be removed on daily basis from the
job site.
 Correct type and size of tool shall be used for each job.
 Fire extinguishers/fire blankets shall be provided at the places of hot work.
 The supervisor shall deliver toolbox talk daily to the workers.
 The following P.P.E shall be used:
 Safety helmets.
 Safety goggles.
 Safety shoes.
 Hand gloves.
 Face shield (during cutting & grinding).
 Welding gloves.
 Welding shield.
 Safety harness.(over scaffolding)