Method Statement For Electrical Works
Method Statement For Electrical Works
Method Statement For Electrical Works
for
Electrical works
CITISCAPE LLC
INDEX
1 PURPOSE
2 SCOPE OF WORKS
3 DEFINITIONS
4 REFERENCES
5 RESOURCES
6 MATERIALS
7 METHODOLOGY
9 RISK ASSESSMENT
Page 6| 7
METHOD STATEMENT
Chapter :
Section :
Version : 00 Electrical works
Issue date : 05.07.2023
1. PURPOSE
The purpose of this method statement is to set out the procedures and controls to be implemented
by Citiscape for Al Furjan - Phase 01 Community ( Landscape, Dog Park, and Multipurpose Play area
Works)
2. SCOPE OF WORK
The scope of work covers the Electrical works as per tender requirements.
3. DEFINITIONS
4. REFERENCES
4.1 Specification
4.2 BOQ
4.3 Tender documents
Page 5| 7
METHOD STATEMENT
Chapter :
Section :
Version : 00 Electrical works
Issue date : 05.07.2023
5. RESOURCES
5.1 Personnel
a. Project Manager
b. Construction Manager
c. Electrical Engineer
d. QA/QC Engineer
e. HSE officer /Engineer
f. Quantity Surveyor
g. Surveyor
h. Electricians
i. Document Controller
j. Operator
k. Helpers
6 MATERIALS
Page 6| 7
METHOD STATEMENT
Chapter :
Section :
Version : 00 Electrical works
Issue date : 05.07.2023
7 METHODOLOGY
7.3 Procedure:
All installation and testing shall be carried out by the regulations of the concerned Authority,
the relevant section of The Contract Specification and Manufacturers recommendations.
Before commencement of any installation activity, the following procedures are required to
be carried out:
Page 5| 7
METHOD STATEMENT
Chapter :
Section :
Version : 00 Electrical works
Issue date : 05.07.2023
All materials, accessories & equipment to be used shall be client and consultant’s approved
type.
All cabling and lighting installation shall be done in accordance with approved shop
drawings and existing local utilities authority regulations and as per consultant’s
approval.
Extra care should be taken while handling the cables to avoid any damage to it.
All electrical work shall be installed as per approved construction drawings.
All electrical work shall be installed in a neat and tidy fashion.
All electrical work should be supervised by qualified engineer / personnel.
All installation and testing shall be carried out by the regulations of the concerned Authority,
the relevant section of the contract Specification and Manufacturers recommendations.
Glanding and earthing of armoured cables shall be carried out in accordance with project &
manufactures specifications / recommendations.
Underground cables to be laid as per the approved & specified depth.
Buried cables and sleeves 800mm from finished grade level
Always connect correct size of cables after calculating the load and voltage drop.
Earthing cable Y/G should be routed wherever necessary and termination to be done
using proper cable lugs.
Cable termination should be proper, neat, using ferules & tags for correct identification.
Continuity test and insulation test to be carried out before the termination of the cables.
Main supply for lighting (from Control Panel)
Raise the lighting poles by crane and put it on its concrete base and make the rods in the
concrete base entering the holes in the pole’s base
Ensure that poles are fixed properly and properly aligned. Make sure that manufacturer’s
recommendation for lighting poles installation shall be adhered.
Fix flood light mounting brackets. Ensure that they are fixed rigidly and properly
Fix the flood light on the brackets. Connect power cables on the fittings and ensure that the
body of the flood lights is properly earthed
Light fixtures to be installed as per the approved installation drawings.
Ensure that the fixtures are correct and approved type.
Ensure all installation checks on light fixtures are carried out before testing.
All cabling and lighting installation shall be done in accordance with approved shop drawings
and existing local utilities authority regulations and as per consultant’s approval.
All electrical installation should be supervised by qualified engineer / personnel.
Page 6| 7
METHOD STATEMENT
Chapter :
Section :
Version : 00 Electrical works
Issue date : 05.07.2023
All Inspection & Tests shall be conducted in accordance with the project requirements.
Citiscape’s representative will be available at site to supervise and monitor the work area.
9 RISK ASSESSMENT
Page 5| 7
RISK ASSESSMENT FORM
Project Landscape, Dog Park, and Multipurpose Play area Works for Al Furjan Districts 1 - 6
Activity ELECTRICAL WORKS
Reference MAF.CSHSE44.RA.004.22
Name Signature Position Date
HSEM
WAQAS MUHAMMAD SADID
Completed By 06..07. 23
(CM IOSH)
Risk After
Description Initial Risk Mitigation
Affected
Control Measures
Sr. Activity Hazard Risk L S R/R L S R/R
Groups
HSE Safety induction
Pre ‐ task briefing / TBT / MSRA to be conducted
Entry of
prior to start the activity.
unauthoriz
PTW must be secured.
ed people Personal
Use only trained electricians / personnel for the
into the Injury.
work.
area. Burn
Ensure that only competent electrician working
1 Mobilization Incompete Electroc A, C, D,E 3 4 12 1 4 4
for installation of misting system.
nt ution
Comply with lockout tagout.
electricians
Ensure a safe system of work of electrical
installations.
Installed electrical signage and warnings.
Barricade the area with proper warning signage.
Never store the materials at access.
(A) Persons at Risk (Affected Groups)
Risk Grading Matrix, Risk Rate
Absolutely Unacceptably High
15 ‐ 25 Extreme Risk Activity or process should not proceed in current form
Unacceptably High
8 ‐ 12 High Risk Activity or process should be modified to include remedial planning and
action and be subject to detailed EHS risk assessment
Acceptable but must be managed at “As Low As Reasonably Practicable”
4 – 6 Moderate Risk (ALARP) Activity or process can operate subject to management and / or
modification
☐ ☐ ☐
OSHAD‐SF – Codes of Practice. CoP 2.0 – Personal Protective Equipment