Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Method Statement For Electrical Works

Download as pdf or txt
Download as pdf or txt
You are on page 1of 14

Method Statement

for
Electrical works

CITISCAPE LLC

By: Shifaz Sathar


Reviewed by: Shareesh Nalpadi
Approved by:
METHOD STATEMENT
Chapter :
Section :
Version : 00 Electrical works
Issue date : 05.07.2023

INDEX

SL.NO DESCRIPTION PAGE NO

1 PURPOSE

2 SCOPE OF WORKS

3 DEFINITIONS

4 REFERENCES

5 RESOURCES

6 MATERIALS

7 METHODOLOGY

8 INSPECTION & TESTING

9 RISK ASSESSMENT

Page 6| 7
METHOD STATEMENT
Chapter :
Section :
Version : 00 Electrical works
Issue date : 05.07.2023

1. PURPOSE

The purpose of this method statement is to set out the procedures and controls to be implemented
by Citiscape for Al Furjan - Phase 01 Community ( Landscape, Dog Park, and Multipurpose Play area
Works)

2. SCOPE OF WORK

The scope of work covers the Electrical works as per tender requirements.

3. DEFINITIONS

PQP : Project Quality Plan


MS : Method Statement
ITP : Inspection & Test Plan
ITL : Independent Testing Laboratory
IR : Inspection Request
MIR : Material inspection Request
WIR : Work Inspection Request
HSE : Health, Safety & Environment
PM : Project Manager
CM : Construction Manager
QAQC : Quality Assurance/Quality Control
IFC : Issued for Construction
SD : Shop Drawing

4. REFERENCES

4.1 Specification
4.2 BOQ
4.3 Tender documents

Page 5| 7
METHOD STATEMENT
Chapter :
Section :
Version : 00 Electrical works
Issue date : 05.07.2023

5. RESOURCES

5.1 Personnel

a. Project Manager
b. Construction Manager
c. Electrical Engineer
d. QA/QC Engineer
e. HSE officer /Engineer
f. Quantity Surveyor
g. Surveyor
h. Electricians
i. Document Controller
j. Operator
k. Helpers

5.2 Plant & Equipment’s

a. JCB Telescopic (As required)


b. Tipper Pick up
c. Water tanker
d. Compactor/roller
e. Plate compactor
f. Safety PPE & Safety Gears /Harness

6 MATERIALS

All required materials used will be in accordance with contract documents.

SL.NO MATERIAL DESCRIPTION MANUFACTURER /SUPPLIER REMARKS


1 Cables TBC As per MS
2 Flood Lights TBC As per MS
3 Duct Pipes TBC As per MS
4 Warning tapes TBC As per MS
5 Earthing System materials TBC As per MS

Page 6| 7
METHOD STATEMENT
Chapter :
Section :
Version : 00 Electrical works
Issue date : 05.07.2023

7 METHODOLOGY

7.1 Pre-site checks:

 Prior to start of construction and installation, site conditions to be checked


against the approved layout drawings
 Citiscape shall ensure that all required permits and NOC’s are availed and
approved before the commencement of the scope of works

7.2 Delivery to site:

 As required, Forklifts or boom loaders will be used to unload the materials on


site in the prescribed storage locations.
 Delivered material shall be stored at designated lay down area and shall always
be subject to inspection.

7.3 Procedure:

Method: Excavation for Cable Ducts.

 As built service drawings to verified by Citiscape to predetermine any clashes in construction.


 Exclusion zone barriers and warning signage will be set up around excavations to prevent any
unauthorized access by others into work zones.
 Citiscape surveyors will then proceed to mark out the areas for excavation.
 A task briefing and walk of work area will take place to ensure all labour & machine operatives
are aware of the task ahead.
 All operatives involved in this task will have read, understood & signed the Safe system of
work to carry out these works of which a copy will be filed in Citiscape site office for review.
 The machines will access the area directed by a Citiscape banks man.
 Before excavation starts trial, pits will be made to ensure the area is clear of services and in
accordance with the as built drawings.
 When all the above is complete the bobcats and excavators will then proceed to excavate pre-
determined areas to design specification.
 The excess debris will be loaded into a truck as works progress and stock pilled in an agreed,
pre-determined designated area.
 If at any point warning tape for any services become exposed Citiscape shall coordinate with
Consultant representative for further action.

Method: Installation of Cable Ducts and Cables

 All installation and testing shall be carried out by the regulations of the concerned Authority,
the relevant section of The Contract Specification and Manufacturers recommendations.
 Before commencement of any installation activity, the following procedures are required to
be carried out:

Page 5| 7
METHOD STATEMENT
Chapter :
Section :
Version : 00 Electrical works
Issue date : 05.07.2023

All materials, accessories & equipment to be used shall be client and consultant’s approved
type.
 All cabling and lighting installation shall be done in accordance with approved shop
drawings and existing local utilities authority regulations and as per consultant’s
approval.
 Extra care should be taken while handling the cables to avoid any damage to it.
 All electrical work shall be installed as per approved construction drawings.
 All electrical work shall be installed in a neat and tidy fashion.
 All electrical work should be supervised by qualified engineer / personnel.

 All installation and testing shall be carried out by the regulations of the concerned Authority,
the relevant section of the contract Specification and Manufacturers recommendations.

Method: Cabling & Installation of Electrical Items/ Equipments

 Glanding and earthing of armoured cables shall be carried out in accordance with project &
manufactures specifications / recommendations.
 Underground cables to be laid as per the approved & specified depth.
 Buried cables and sleeves 800mm from finished grade level
 Always connect correct size of cables after calculating the load and voltage drop.
 Earthing cable Y/G should be routed wherever necessary and termination to be done
using proper cable lugs.
 Cable termination should be proper, neat, using ferules & tags for correct identification.
 Continuity test and insulation test to be carried out before the termination of the cables.
 Main supply for lighting (from Control Panel)

 4-Core x 4-16mm² diameter CU/XLPE/SWA/PVC,


 3-Core x 4-10mm² diameter CU/XLPE/SWA/PVC &
 1-Core x 4-16 mm² diameter CU/PVC (Earth Cable)

Method: Installation of Light Fixtures (Flood Lights)

 Raise the lighting poles by crane and put it on its concrete base and make the rods in the
concrete base entering the holes in the pole’s base
 Ensure that poles are fixed properly and properly aligned. Make sure that manufacturer’s
recommendation for lighting poles installation shall be adhered.
 Fix flood light mounting brackets. Ensure that they are fixed rigidly and properly
 Fix the flood light on the brackets. Connect power cables on the fittings and ensure that the
body of the flood lights is properly earthed
 Light fixtures to be installed as per the approved installation drawings.
 Ensure that the fixtures are correct and approved type.
 Ensure all installation checks on light fixtures are carried out before testing.
 All cabling and lighting installation shall be done in accordance with approved shop drawings
and existing local utilities authority regulations and as per consultant’s approval.
 All electrical installation should be supervised by qualified engineer / personnel.

Page 6| 7
METHOD STATEMENT
Chapter :
Section :
Version : 00 Electrical works
Issue date : 05.07.2023

8 INSPECTION & TESTING

All Inspection & Tests shall be conducted in accordance with the project requirements.

Citiscape’s representative will be available at site to supervise and monitor the work area.

9 RISK ASSESSMENT

Risk assessment enclosed

Page 5| 7
 
RISK ASSESSMENT FORM 
Project  Landscape, Dog Park, and Multipurpose Play area Works for Al Furjan Districts 1 - 6
Activity  ELECTRICAL WORKS
Reference  MAF.CSHSE44.RA.004.22
 
  Name  Signature  Position  Date 
  HSEM 
WAQAS MUHAMMAD SADID  
Completed By  06..07. 23 
 (CM IOSH) 

Reviewed By  Mohammad Al sheikh    Construction Manager  06..07. 23 

Approved by              Pooviah Authithan    Project Manager  06..07. 23 


 

Risk After 
Description  Initial Risk  Mitigation 
Affected 
Control Measures 
Sr.  Activity  Hazard  Risk  L  S  R/R  L  S  R/R 
Groups 
 HSE Safety induction  
 Pre ‐ task briefing / TBT / MSRA to be conducted 
 Entry of 
prior to start the activity.  
unauthoriz
 PTW must be secured. 
ed people   Personal 
 Use only trained electricians / personnel for the 
into the  Injury. 
work. 
area.   Burn  
 Ensure that only competent electrician working 
1   Mobilization   Incompete  Electroc  A, C, D,E   3  4  12   1  4  4 
for installation of misting system. 
nt  ution  
 Comply with lockout tagout.  
electricians    
 Ensure  a  safe  system  of  work  of  electrical 
   
installations.  
 
 Installed electrical signage and warnings. 
 
 Barricade the area with proper warning signage. 
 Never store the materials at access. 

Page 1 of 7 CSHSE44 Version R0


 
Risk After 
Description  Initial Risk  Mitigation 
Affected 
Control Measures 
Sr.  Activity  Hazard  Risk  L  S  R/R  L  S  R/R 
Groups 
 Provide training for manual handling personnel 
 Provide adequate safety signage  
 All  personnel  shall  wear  approved  Mandatory 
PPE. 
 Proper supervision, guidance, instructions must 
have observed at all times. 
 Proactive Supervision. 
 Maintain good housekeeping at all the times. 
Ensure  that  workers  will  follow  the 
demobilization safety procedure 
 Ensure  the  protection  of  personnel  working 
adjacent/nearby  to  road  is  fully  barricaded  & 
signage been installed. 
 Ensure  that  third  party  services  is  being 
protected and secured. 
 
 Provide approved RAMS 
 All  excavation  should  comply  with  the 
 Existing  requirements of  
undergroun  Obtain  current  utility  drawings  from  service 
d  provider;  obtain  required  permits  from  the 
utilities/serv concerned authorities. 
Service/Utility  ices   Electrocu  Ensure  to  use  the  Cable  Avoidance  Tool  (CAT) 
Identification –  Slip, trip  tion   prior to excavate.  
2  contact  and falls   Personal   A,B&C  3  3  9   Employees should ensure that, where required  1  3  3 
underground   Insufficient  injury    by the risks involved by the excavation, a permit 
utilities.  barriers     to  work  system  should  be  implemented  for 
 Collapse of  excavations  that  complies  with  the 
excavation   requirements  of  Ensure  cable  detector  is 
 Noise   calibrated used by competent person. 
   Hand excavation or trial pit to be done to locate 
existing services. 
 Provide adequate toolbox talk. 

Page 2 of 7 CSHSE44 Version R0


 
Risk After 
Description  Initial Risk  Mitigation 
Affected 
Control Measures 
Sr.  Activity  Hazard  Risk  L  S  R/R  L  S  R/R 
Groups 
 PPE like coveralls, helmet, safety shoes, shields 
and gloves to be provided and inspected before 
used. 
 Adequate supervision 
 Cable  detector  to  be  used  to  locate 
underground services.  
 Plan  to  eliminate  the  need  to  manually  lift  by 
using  lifting  equipment  e.g.  forklift  truck  or 
pallet trolley 
 Review the task, the individual’s capability, the 
load itself and the working environment. Where 
 Lifting heavy  necessary clear any unwanted materials. 
loads Lifting   Check the load prior to lift. Where the load can 
 Chronic 
awkward  be split into smaller ones. 
injury 
loads   Check  environment  for  space  constraints, 
 Disability 
 Twisting  uneven,  untidy  ground,  and  variation  in  work, 
 Severe 
while lifting  surfaces/height,  poor  lighting  and  extremes  of 
back pain 
Manual handling   Poor  temperature/humidity 
 Muscle 
works   underfoot   Check  individual’s  strength  limits  /  physical 
3  strain   A, C  3  4  12  1  4  4 
conditions  disabilities.  Where  necessary  team  handling  to 
 Cable installation         Being 
 Top heavy  be done. 
struck 
bending   Ensure  adequate  rest  periods/recovery  periods 
 Aggravatin
 Previous  are followed between lifts/activities. 
g previous 
back   Use gloves that offer adequate protection and 
condition 
problems  aid grip. 
 Back pain 
 Sharp edges   Proper lifting techniques will be followed: 
 Slips/trip/fall   Position in front of the load with legs balanced 
and spread equal to shoulder width. 
 Bend the knees to reach the bottom of the load 
to get a grip; do not bend the spine. 
 Lift  load  slowly  by  gradually  straightening  the 
legs. 

Page 3 of 7 CSHSE44 Version R0


 
Risk After 
Description  Initial Risk  Mitigation 
Affected 
Control Measures 
Sr.  Activity  Hazard  Risk  L  S  R/R  L  S  R/R 
Groups 
 Do  not  twist  spine  if  you  need  to  change 
direction; turn whole body instead. 
 Carry the load as close to your body and as high 
as your waist. 
 Where possible unloading of materials from the 
delivery  truck  should  be  close  to  the  storage 
area. 
 Workers  to  be  adequately  trained  and 
instructed  in  manual  handling  techniques 
including adequate supervision. 
 
 Ensure  the  conditions  of  the  hand  tools  are 
good, when obtaining from the stores. 
 Hand tools shall not be kept on walkways  
 Hand tools shall be kept in tool boxes whenever 
not in use. 
 All tools shall be inspected for any damages on 
 Damaged 
daily basis and at regular intervals 
tools 
Use of Hand tools    Injury to   Store  keeper  will  inspect  all  the  new  tools 
 Improvised 
4  the   A & C   3  3  9  before issuing to site.  1  3  3 
         tools 
person   Ensure that no homemade/make shift tools are 
 Sharp edges 
used at site 
 
 Ensure the operatives are wearing hand gloves 
during the activity. 
 Workers must be adequately instructed on safe 
working  procedures  through  toolbox  and/or 
pre‐start briefing. 
 Any damage tools will be removed from service. 
Waste   Untrained   Comply the waste management system 
 ‐Fall, slip 
Management  workers.   Ensure  that  waste  management  procedure 
and trip  
5  (Housekeeping at   Poor   A, B, C, D E   3  3  9  implemented   1  3  3 
 ‐Personal 
the workplace after  housekeepi  Waste  segregation  and  proper  disposal  of 
injury 
the task, & waste  ng  construction waste material.  

Page 4 of 7 CSHSE44 Version R0


 
Risk After 
Description  Initial Risk  Mitigation 
Affected 
Control Measures 
Sr.  Activity  Hazard  Risk  L  S  R/R  L  S  R/R 
Groups 
disposal &   Environmen  Ensure that waste material been transported to 
segregation)  tal factors   the designated and approved dumpsite by ADM 
 Fire hazards   Workers must be trained and aware and comply 
  with the housekeeping plan on the site. 
 TBT on housekeeping to be given to all. 
 Removal  of  all  waste  from  work  after  the 
completion of activity. 
 Where  possible,  packaging  materials  shall  be 
removed from the site the earliest opportunity 
in order to reduce the fire load   
 Materials to be stacked and stored properly. 
 All  waste  to  be  placed  in  designated 
corresponding  waste  skips/  bins  provided  for 
final  disposal  as  per  site  waste  management 
policy. 
 Area must be clear at all times to avoid fall, slip 
and trip hazard. 
 Strict supervision, guidance, instructions must 
have observed at all times. 
 Ensure  the  working  area  is  clean  before 
leaving. 
 Ensure all waste generated after work should 
be  remove  and  dispose  it  on  proper  waste 
disposal.  
 Supervisor  to  check  work  areas  at  close  of 
working day 
 Reduce   Vehicle  speed  shall  be  reduced,  keeping  a 
 Fog  visibility or  longer gap from the vehicle in front. 
 Heavy rain  vehicles or   Warning alarms (audio and visual) for plant and 
6  Adverse weather   Wind/sandst pedestrian  A,B,C  3  4  12  equipment  1  4  4 
orm  s   Use of high visibility clothing. 
 Hot & humid   Increase   Lights to be used in poor visibility  
stopping   Good housekeeping ion place  

Page 5 of 7 CSHSE44 Version R0


 
Risk After 
Description  Initial Risk  Mitigation 
Affected 
Control Measures 
Sr.  Activity  Hazard  Risk  L  S  R/R  L  S  R/R 
Groups 
distance,   Regular  workplace  inspection,  equipment 
slip and  plant, excavations, fences support, etc.) 
trip   In case of flooding, stop the work, secure the 
 Flooding,  equipment and plant, clear surrounding area. 
unstable   Regular check and maintenance  
structures   Secure  the  high  risk  items,  including 
 Objects  scaffolding,  cranes  during  the  extreme  high 
overturned wind  
, blown, or   Avoid  driving  or  walking  during  the  sand 
loosing  storms or the extreme winds. 
 Heat   Regular  breaks  during  the  hot  season  and  all 
stress,  shall adhere to the UAE law (during summer no 
stroke  work from 12.30 until 300 pm) 
   Wearing the appropriate PPE 
 Adequate  &  well  shaded  area  with  air 
conditioner  shall  be  provided  for  all  the 
operatives during the hot season. 
 Adequate  drinking  water  &  other  alternative 
fluids shall be provided to avoid dehydration. 
 Regular  awareness  trainings  &  campaigns 
covering the heats stroke and stress  
 

(A) Persons at Risk (Affected Groups) 

A: Employees involved with task / activity  B: Employees not involved in task / activity  C: Contractors / Sub‐Contractors 

D: Office / Project Visitors  E: Members of the Public  F: Young Persons / Pregnant Woman 

 
                    Risk Grading Matrix, Risk Rate 

Page 6 of 7 CSHSE44 Version R0


 
PROBABILITY  SEVERITY 
Insignificant (1)  Minor (2)  Moderate (3)  Major (4)  Catastrophic (5) 
Rare (1)  1  2  3  4  5 
Possible (2)  2  4  6  8  10 
Likely (3)  3  6  9  12  15 
Often (4)  4  8  12  16  20 
Frequent/Almost Certain (5)  5  10  15  20  25 
 

Absolutely Unacceptably High 
15 ‐ 25  Extreme Risk  Activity or process should not proceed in current form 
Unacceptably High 
8 ‐ 12  High Risk  Activity or process should be modified to include remedial planning and 
action and be subject to detailed  EHS risk assessment 

Acceptable but must be managed at “As Low As Reasonably Practicable” 
4 – 6  Moderate Risk  (ALARP) Activity or process can operate subject to management and / or 
modification 

1 – 3  Low Risk  No action required unless escalation of risk is possible. 

 
                     

          ☐    ☐  ☐       

OSHAD‐SF – Codes of Practice. CoP 2.0 – Personal Protective Equipment 

Page 7 of 7 CSHSE44 Version R0

You might also like