Etihad Rail Stage 2 Project C0306 - PACKAGE 2C Design & Build Contract (Dubai) DCP3F - Technical Specifications - Bridges and Railway Structures
Etihad Rail Stage 2 Project C0306 - PACKAGE 2C Design & Build Contract (Dubai) DCP3F - Technical Specifications - Bridges and Railway Structures
Etihad Rail Stage 2 Project C0306 - PACKAGE 2C Design & Build Contract (Dubai) DCP3F - Technical Specifications - Bridges and Railway Structures
Dan Irish
Prepared 06-JAN-2021
Design Manager / WSP
Xu Yue
Verified 12-JAN-2021
Technical Director / CRGT
Ubaidullah Khan
Quality Process Approval 12-JAN-2021
Project QA/QC Manager / CRGT
Sun Shangxing
Approved 12-JAN-2021
Project Director / CRGT
Location/
Contract No. - - Discipline - Type - Sequence Number - Revision
Subdivision
C 0 3 0 6 - S 0 2 - E C B - F S - 3 0 0 0 0 - 0 0
This document including its attachments is the property of Etihad Rail. It contains confidential proprietary information and may be legally privilege. The
reproduction, distribution, utilization or communication of this document, or any part thereof, is strictly prohibited unless expressly permitted by Etihad Rail.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 1 OF 122
Version Log - Internal
This document including its attachments is the property of Etihad Rail. It contains confidential proprietary information and may be legally privilege. The
reproduction, distribution, utilization or communication of this document, or any part thereof, is strictly prohibited unless expressly permitted by Etihad Rail.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 2 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
Table of Contents
Acronyms and Abbreviations............................................................................................................ 10
1 Introduction ........................................................................................................................ 11
1.1 Scope of this Specification ................................................................................................ 11
1.2 Design Responsibilities ..................................................................................................... 11
1.3 Construction Specifications .............................................................................................. 12
1.4 Reference Documents ...................................................................................................... 12
1.5 Approvals .......................................................................................................................... 13
1.6 Temporary Works ............................................................................................................. 13
1.7 Shoring works ................................................................................................................... 14
1.7.1 Required Submissions .......................................................................................... 14
1.7.2 Design criteria ...................................................................................................... 16
1.8 QA/QC and Records .......................................................................................................... 17
2 General................................................................................................................................ 18
2.1 Fire Resistance of Structure and Emergency Access ........................................................ 18
2.2 Earthing and Bonding........................................................................................................ 18
2.3 Vehicle Parapets for Over-Bridges (Road over Rail) ......................................................... 18
2.4 Handrails for Under-Bridges (Rail over Road) ................................................................... 19
2.4.1 Metal Handrail ..................................................................................................... 19
2.5 Provisions for Train Derailment ........................................................................................ 25
2.6 Crash Barriers.................................................................................................................... 26
2.7 Utility Diversion and Protection Structures ...................................................................... 26
2.8 Lighting.............................................................................................................................. 26
2.9 Noise Barriers.................................................................................................................... 26
2.10 Drainage ............................................................................................................................ 27
2.10.1 Drainage pipe ....................................................................................................... 27
2.11 Erosion Protection ............................................................................................................ 28
2.12 Mechanically Stabilized Embankment (MSE) Wall ........................................................... 28
2.13 Soil investigation ............................................................................................................... 28
2.14 Foundation design ............................................................................................................ 29
2.15 Excavation ......................................................................................................................... 29
2.15.1 General................................................................................................................. 29
2.15.2 Disposal of Excavated Materials .......................................................................... 29
2.15.3 Dewatering and Drainage .................................................................................... 29
2.15.4 Backfill .................................................................................................................. 31
2.16 Ground Movement and Monitoring ................................................................................. 31
2.16.1 General................................................................................................................. 31
2.17 Precondition Surveys ........................................................................................................ 33
3 Concrete Pile Foundations .................................................................................................... 34
3.1 General.............................................................................................................................. 34
3.2 Piling Design ...................................................................................................................... 34
3.3 Pile Construction Records ................................................................................................. 34
3.4 Placing Concrete under Water or Support Fluid ............................................................... 34
3.5 Finishing Pile Heads .......................................................................................................... 35
3.6 Pile Testing ........................................................................................................................ 35
3.7 Maintained Compression Load Testing of Piles ................................................................ 36
3.8 Integrity Testing of Piles ................................................................................................... 36
3.9 Rectification of Failure of MLT Pile ................................................................................... 37
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 3 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 4 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
4.9.1 General................................................................................................................. 60
4.9.2 Formed Surfaces .................................................................................................. 60
4.9.3 Remedial Treatment of Formed Surfaces ............................................................ 61
4.9.4 Unformed Surfaces .............................................................................................. 61
4.9.5 Special Finishes .................................................................................................... 61
4.10 Testing of Samples Cut from the Works ........................................................................... 62
4.11 Concrete Repairs ............................................................................................................... 62
4.11.1 Assessment .......................................................................................................... 63
4.11.2 Identification of Defects ...................................................................................... 63
4.11.3 Repairs to Cracks.................................................................................................. 63
4.11.4 Preparation of Surfaces around cracks ................................................................ 64
4.11.5 Repairs to Honeycombing and Voids in Concrete ............................................... 64
4.12 Failure to Meet Specified Requirements .......................................................................... 65
4.13 Records ............................................................................................................................. 66
5 Reinforcing Steel .................................................................................................................. 67
5.1 General.............................................................................................................................. 67
5.2 Normal Reinforcement ..................................................................................................... 67
5.3 Stainless Steel Reinforcement .......................................................................................... 67
5.4 Epoxy Coated Reinforcement Bars ................................................................................... 67
5.5 Binding Wire ..................................................................................................................... 67
5.6 Dowel Bars ........................................................................................................................ 67
5.7 Manufacturer’s Test Certificate ........................................................................................ 67
5.8 Delivery ............................................................................................................................. 68
5.9 Bar Schedules and Shop Drawings .................................................................................... 68
5.10 Storage and Bending ......................................................................................................... 68
5.11 Fixing Reinforcement ........................................................................................................ 69
5.12 Welding of Reinforcement ................................................................................................ 69
5.13 Cover ................................................................................................................................. 69
5.14 Minimum Test Requirement ............................................................................................. 70
5.15 Failure to Meet Specified Requirements .......................................................................... 70
6 Precast Concrete .................................................................................................................. 71
6.1 General.............................................................................................................................. 71
6.2 Moulds .............................................................................................................................. 71
6.3 Casting............................................................................................................................... 72
6.4 Marking ............................................................................................................................. 72
6.5 Curing ................................................................................................................................ 72
6.6 Handling Stacking and Transportation.............................................................................. 72
6.7 Failure to Meet Requirements .......................................................................................... 72
7 Pre-stressed Concrete Works ............................................................................................... 73
7.1 General.............................................................................................................................. 73
7.2 Details of Design ............................................................................................................... 73
7.3 Shop Drawings .................................................................................................................. 73
7.4 Materials ........................................................................................................................... 74
7.4.1 Pre-stressing Steel and Anchorages..................................................................... 74
7.4.2 Steel Wire............................................................................................................. 74
7.4.3 Bars ...................................................................................................................... 74
7.4.4 Post-tensioning Anchorages and Coupler............................................................ 75
7.4.5 Identification and Testing .................................................................................... 75
7.4.6 Pre-tensioning Tendon Testing ............................................................................ 75
7.4.7 Post- tensioning Tendon Testing ......................................................................... 76
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 5 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 6 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 7 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 8 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
Tables
Table 1: Requirements for Support Fluids (Bentonite)
Table 2: Acceptable Movement of Verticality Loaded Pile
Table 3: Additional Mineral Material Properties for CEM | Cement
Table 4: Additional Mineral Material Properties for Microsilica
Table 5: Tests on Aggregates for Acceptance
Table 6: Frequency of Routine Tests on Aggregates
Table 7: Properties of Concrete Grades
Table 8: Indicative Concrete Mix Criteria
Table 9: Additional Inspection and Testing Requirements
Table 10: Formed Finishes
Table 11: Unformed Finishes
Table 12: Dimensional Tolerances on Precast Units
Table 13: Mortar Proportions by Volume
Table 14: Properties for Coating Effectiveness
Table 15: Additional Requirements for Waterproofing Membranes
Table 16: Additional Requirements for Waterproofing Membranes
Table 17: Elastomer physical properties
Table 18: Table of Actual Condition of Drawing
Table 19: Number and Format of Copies to Be Submitted
Table 20: Key Elements of the Structure Requiring Regular Maintenance
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 9 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 10 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
1 Introduction
1.1 Scope of this Specification
1 This Technical Specification covers the technical requirements for design and construction of Over-
Bridges (Road over Rail) and Under-Bridges (Rail over Road) and civil structures (collectively referred to
in this Technical Specification as Rail Structures), including culverts, underpasses and utility protection
structures.
2 All contractor queries relating to this Technical Specification or the Drawings will be submitted to the
Engineer promptly in writing in the form of a Technical Query (TQ) for clarification and instructions.
3 Management Plans and Procedures that are referenced in this Specification are Contractor documents,
except for plans and procedures that are specified as Engineer documents.
4 Where anywhere in the Specifications or the Contract reference is made to the agreement, consent,
acceptance or the like of the Engineer such agreement, consent, acceptance or the like will be obtained
in writing through submittals, inspection requests or other similar communications process as agreed in
advance with the Engineer.
5 The notification by the Engineer of his agreement, consent, acceptance or the like to any submission by
the Contractor will in no way lessen the Contractor’s duties and responsibilities under the Contract to
supply the Works complete fit for purpose and in compliance with all of the Contract Documents.
6 For the avoidance of doubt, any expressed or implied approval or acceptance of any of the Contractor’s
work by the Engineer will not transfer any responsibility or liability for said work from the Contractor to
the Engineer.
7 This specification should be read in conjunction with the Package 2C Durability Report issued by the
contractor. Document Reference is C0306-S02-ECB-RP-30018
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 11 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 12 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
– Road & Transport Authority (Dubai); Current Design Circulars; Structural Design Criteria for Bridge and
Underpasses
– Dubai Municipality General Specifications
– Dubai Municipality Geometric Design Manual for Dubai Roads
– Jebel Ali Free Zone Authority
– American Petroleum Institute (API) 1102 Steel Pipelines Crossing Railroads and Highways
– Concrete Society CS 163: Guide to Design of Concrete Structures in Arabian Peninsula CIRIA report
147: Design and Construction of joints in concrete structures
– CIRIA Publication C660 : Early-age thermal crack control in concrete
– CIRIA Publication C577 – Guide to construction of reinforced concrete in the Arabian Peninsula
– CIRIA Report R146 – Design and Construction of joints in Concrete Structures
– UIC 774-3, UIC 777-2R, UIC 776-2 – Track/Bridge interaction
5. Other Documents of particular application are listed in the Contract. The Contractor will advise the
Engineer in writing of any deviations from the specified Standards and Regulations.
6. In regard to conflict (if any) between any of the referenced documents, the more strict requirement will
govern.
1.5 Approvals
1. The Contractor is responsible for receiving all necessary approvals for design and construction.
2. The Contractor will ensure that all codes and other requirements of all relevant agencies are met in
design and construction.
3. Any Code and/or Standards used will in each instance be the latest edition or issue, and the most recent
revision, amendment or supplement adopted.
4. Where the requirements of more than one Code or Standard are applicable, the more restrictive will
govern.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 13 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
7 The Contractor will inspect temporary works daily as specified in the Employers Requirements to ensure
that they are safe and have not been damaged due to construction, environment exposure or
vandalism.
8 The Contractor will appoint in writing a suitably qualified temporary works coordinator responsible for
temporary works management and including ensuring compliance with all laws and regulations in
respect of the temporary works of private and public bodies and of Government departments, agencies
and other organisations.
9 The qualified temporary works coordinator will appoint temporary works supervisors to ensure that the
temporary works have been constructed in accordance with the Shop drawings and specifications. All
temporary works will be tagged and inspected in line with the permit system established for the project.
10 The Contractor will maintain a register for all temporary works required on the project.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 14 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 15 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 16 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 17 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
2 General
2.1 Fire Resistance of Structure and Emergency Access
1. The Contractor will carry out study to specify the fire resistance of the structural elements based on the
location and functional requirement of the structure.
2. All structural elements will have minimum two hours fire resistance, and protective coating to be applied
where necessary.
3. For protection structures crossing oil and gas utilities, concrete material will be used with appropriate
minimum fire resistance that is designed to withstand increased heat flux from a jet fire that results from
loss of containment from a pipeline (eg from pipeline containing LPG, jet fuel, or natural gas, etc)
4. Emergency egress points will be provided for long multi-span bridge structures in accordance with NFPA
130 requirements.
5. Contractor to also refer to the Civil Technical Specs C306-S02-EGE-FS-30001
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 18 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
3. For the span length of the Over-Bridge, the high containment parapet will have the safety fence from the
top of the parapet and extending a minimum height of 2.0m above the top of parapet level.
4. The safety fence will be extended on top of the normal containment parapet, with a minimum 2.0m
height from top of parapet, for a length of not less than 5m from each end of the bridge and will
terminate in a further transition reducing to 1.0m high at a distance of 10m from the end of the bridge.
5. The safety fence will compose of steel post with wire mesh.
6. Metal rails affixed to the top of concrete parapets will be in accordance with BS6779 Part 3.
7. Unless accepted otherwise by the Engineer, all such metal will be Hot-dip Galvanized steel as per ASTM
A123.
1. Company specializing in high quality architectural metal fabrication and installation with minimum of five
(5) years documented experience (most recent 1 year). Aluminum extrusion manufacturers for aluminum
must possess five (5) years experience or better.
2. Fabricate and install architectural metalwork and sundries to withstand the anticipated imposed loadings
without failure including excessive deflection, structural defects, flaws in finishes and other defects in
the Work
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 19 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
3. Design shop drawings under direct supervision of a professional structural engineer experienced
in design of this work and licensed in the region in which the project is located.
2.4.1.1.3 Materials
A. Materials – Miscellaneous
B. Materials – Aluminum
2. Sheet Aluminum: ASTM B 209 (ASTM B 209M), 5052 alloy, H32 or H22 temper. Aluminum-Alloy Drawn
Seamless Tubes: ASTM B 210 (ASTM B 210M), 6063 alloy, T6 temper.
3. Aluminum-Alloy Bars: ASTM B 211 (ASTM B 211M), 6061 alloy, T6 temper. E. Bolts, Nuts,
Rivets, Screws and Washers: Stainless steel.
4. Welding Materials: AWS D1.2/1.2M:2003; type required for materials being welded.
5. Isolation tape: Polymer alloy film with elastomeric coating, 30 mils thick, specifically designed for
corrosion and electrolytic protection of embedded metals, where risk of bimetallic contact exists.
Shims
1. At connections subject to thermal movement or other movement, separate all pairs of moving surfaces
with friction reducing pads. Pads shall have minimum 3mm thickness, shall sufficiently reduce friction
to permit movement, shall be resistant to wear, shall be positively retained in position (open ended
slots are not acceptable). Pads shall not be subjected to heat damage from welding or cutting or to
excessive pressure from over-tightening of bolts.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 20 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
2. Shims which transfer shear forces (tending to slide on shim against another) shall be steel plates, set
in a staggered pattern and fillet welded to each other and to the adjacent steel surfaces. The shims
and welds shall be structurally designed to support the applied loads.
3. Plastic shims are acceptable at static connections for which the shims transfer only compressive
forces.
1. Do not use metals that are corrosive or incompatible with materials joined.
2. Provide concealed fasteners for interconnecting metal work components and for attaching them to
other work, unless exposed fasteners are unavoidable or are the standard fastening methods.
3. Provide flat-head machine screws for exposed fasteners, unless otherwise indicated on drawings.
4. Anchors: Proprietary-made anchors shall all be stainless steel SS316 for cast-in type or expansion-
type as appropriate for the particular application. Anchors shall be threaded or wedge-type; fabricated
from corrosion- resistant Stainless Steel, in accordance with referenced standards. Powder coated
anchor screw caps shall be provided for exposed locations with matching colour of the handrail.
2.4.1.1.4 Welding
1. Welding of Aluminum
a) Welding of Aluminum shall be done in the factory and in conformance to BS EN 1011- 4:2000.
b) Weld shall use insert gas process using an electric arc with a protective envelope of argon gas.
Oxy-acetylene welding is not permitted as a substitute. Do not solder aluminum.
a) All welded exposed joints shall be suitably ground flush with adjoining material and neatly finished
to harmonies therewith.
b) Wherever material has been sunken or depressed by welding operation, such depressions shall
be suitably hammered and peened flush to adjoining surface, and if necessary, again ground to
eliminate low spots.
c) All ground surfaces shall be smooth, consistent with good workmanship.
d) Care shall be exercised in all grinding operations to avoid excessive heating of metal and
metal discoloration. In all cases grain of rough grinding shall be removed by successive polishing
operations.
e) Texture of final polishing operation shall be uniform and smooth, consistent with reasonable
care and good workmanship.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 21 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
f) General finish of all equipment shall be of high grade. The Contractor shall seek approval from
the Engineer should there be doubt as to what constitutes acceptable standard of workmanship.
g) Butt joints and contact joints, wherever they occur, shall be close fitting, flush and shall not require
solder as filler.
h) Wherever brake bends occur, they shall be free of under extrudence and where such brakework
does match uniform appearance of material, all such marks shall be removed by suitable grinding,
polishing and finishing.
i) Wherever sheared edges occur, they shall be free of burrs, fins or irregular projections and shall
be finished over such sheared edges.
j) Where mitres or bull nosed corners occur, they shall be neatly finished with under edge of material
neatly ground to uniform condition and in no case are overlapping materials to be acceptable.
a) All fixings and anchoring of architectural metal work shall be concealed, unless specifically shown
on the drawings. If indicated on the drawings, exposed flush countersunk screws or bolts, are to
be located unobtrusively; consistent with design of structure, except where specifically noted
otherwise in the drawings.
b) Supply components required for anchorage of metal fabrications. Fabricate anchoring and related
components of same material and finish as metal fabrication, except where specifically noted
otherwise.
c) All architectural metals shown on the drawings as curved so be fabricated to the required radius.
Segmented panels will not be accepted.
d) Prior to crating, finished panels shall be inspected for blemished, chips and for flatness.
e) Any panel not meeting the requirements of this specification shall be rejected. Items found
damaged at any time shall not be installed
1. Anodized Aluminum Surfaces: Comply with AA DAF-45 for aluminum finishes. Apply one coat of
bituminous paint to concealed aluminum surfaces in contact with cementitious or dissimilar materials.
Component and design details to be submitted to the Engineer for approval.
1. Thermal Movements
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 22 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
a) Provide handrails and railings that allow for thermal movements resulting from maximum change
(range) in ambient and surface temperatures by preventing buckling, opening of joints,
overstressing of components, failure of connections, and other detrimental effects.
2. Control of Corrosion
Prevent galvanic action and other forms of corrosion by insulating metals and other materials from
direct contact with incompatible materials. Use materials that do not stain exposed surfaces of
panel finishes and joint materials
2.4.1.2.2 REFERENCES
2.4.1.2.3 SUBMITTALS
B. Product Data:
C. Selection Samples: For each finish product specified, two complete sets of color chips
representing manufacturer's full range of available colors and patterns.
D. Verification Samples: For each finish product specified, two samples, minimum size 6
inches (150 mm) square representing actual product, color, and patterns.
E. Shop Drawings: Include details of materials, construction and finish. Include relationship
with adjacent construction.
C. Source Limitations: Provide each type of product from a single manufacturing source to
ensure uniformity.
D. Mock-Up: Construct a mock-up with actual materials in sufficient time for Engineer’s
review and to not delay construction progress. Locate mock-up as acceptable to Engineer
and provide temporary foundations and support.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 23 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
A. Store and handle in strict compliance with manufacturer's written instructions and
recommendations.
2.4.1.2.7 SEQUENCING
A. Ensure that products of this section are supplied to affected trades in time to prevent
interruption of construction progress.
2.4.1.2.8 WARRANTY
A. Manufacturer's Warranty: Provide manufacturer's standard limited warranty not less than
10 years.
2.4.1.2.9 MANUFACTURERS
plus or minus 1.8 degrees F (20 degrees C plus or minus 1 degree C) using No.
610 Scotch cellophane tape and subjected to a 3T 180 degree bend and tape pull
test.
e. Film Integrity: During first 25 years of exposure, paint film shall have no evidence
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 24 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
f. Chalking, ASTM D4214, Method A: For the first 20 years, vertical installations
shall not chalk more than a No. 8 rating, and non-vertical installations shall not
chalk more than a No. 6 rating.
g. Color Change, ASTM D2244: For the first 25 years, vertical installations shall not
change color more than five (5) delta E color units and non-vertical installations
shall not change color more than seven (7) delta E color units.
2.4.1.2.11 EXAMINATION
A. Do not begin installation until substrates have been properly constructed and prepared.
2.4.1.2.12 PREPARATION
B. Prepare surfaces using the methods recommended by the manufacturer for achieving the
best result for the substrate under the project conditions.
2.4.1.2.13 INSTALLATION
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 25 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
2.8 Lighting
1 Provisions for external lighting level will be made in all Bridge structures as per relevant highway agency
and/or local authority requirements and standards and General Civil Works C0306-S02-EGE-FS-0001
which covers general lighting .
2 Application and technical performance specifications will comply with Technical Specification: MEP
Services for Doc No: X0231-S23-EAM-FS-00001.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 26 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
2.10 Drainage
1 Bridge drainage will consist of all necessary furnishings, gullies, pipes, channels, grates and frames on
bridge decks to collect surface water from the structures and drain pipes which are connected to the
collection system by hoppers.
2 The gully and channel grates and frames may be of cast iron or structural steel with or without integral
cast hoppers.
3 In the absence of integral cast hoppers, fabricated uPVC or GRP hoppers will be provided.
4 For Over-Bridges and underpasses, the drainage design will follow the relevant local Municipality
requirements and any other relevant Authority as outlined in the General Civil Works Technical
Specifications -C0306-S02-EGE-FS-10000-00-Technical Specs-Civil Works.
5 Drainage culverts are to be provided at low points where flow paths meet the alignment.
6 Backfill materials behind abutments and wing walls will be granular, free-draining materials Earthwork
Technical Specifications to prevent build-up of hydrostatic pressure behind the wall. C0306-S02-ECE-FS-
30000
7 Drainage structures including box/pipe culverts will be designed in accordance with General Civil Works
Technical Specifications. C0306-S02-ECE-FS-3000
2.10.1Drainage pipe
1 The pipe and fittings inside the concrete pier and bridge shall be uPVC non-pressure pipes manufactured
and tested to BS EN 1401 – 1 : 2009 .
2 UPVC pipes shall be installed in accordance with the manufacturer’s guidelines, pipes shall be with BSI
kite marked
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 27 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
3 UPVC fittings shall be injection moulded factory made and kite mark certified and shall conform to BS EN
1401-1
4 Fabricated fitting may be permitted only for non-standard fittings not shown in Pipe manufactures
Technical Catalogue
5 uPVC pipes shall be capable of withstanding ultraviolet degradation. A rodent inhibitor shall be
incorporated in the material of the pipe. Pipes shall be manufactured with integral flexible rubber ring
joints made to BSEN 681-1: 1996 EPDM type ‘D’ material and kite marked.
6 uPVC pipes for gravity pipelines shall be SN4 stiffness class and have a standard dimension ratio, D :t
(diameter to thickness), of between 35 and 45
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 28 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
2.15 Excavation
2.15.1 General
1 The Contractor will perform all underground excavation, as well as that required in open cuts, in
accordance with this Specification or as required by the Contract.
2 Except where otherwise specified in this Section, all excavations will comply with the requirements of
the Earthworks Specification (C0306-S02-ECE-FS-30000).
3 Prior to commencing any excavation for temporary or permanent works, the Contractor will prepare and
submit appropriate designs, drawings and method statements relating to his proposed methods of
working.
4 Such methods will ensure that there is no damage to or deterioration of the final surfaces of the
excavations and ensure that surface settlement and distortion to adjacent structures are kept to
acceptable limits.
5 The Contractor will provide suitable excavation support (i.e. shoring) for deep excavations near existing
structures and seek Engineer’s approval before commencement of excavation in compliance with Clause
1.6 Temporary Works.
6 The Contractor will carry out excavation with the utmost care to minimise movement, subsidence and
damage to overlying and adjacent properties and to the Works.
7 All necessary precautions will be taken in order to prevent softening or deterioration of excavated
surfaces through exposure.
8 Excavation will be carried out in sections, limited to lengths, depths and widths as appropriate to the
ground conditions, to the equipment and the conditions and the excavation will be taken out to the lines
and levels specified with minimum over-break.
9 Where necessary to ensure the safety and security of the Works, excavation for underground Works will
be continuous by day and night, unless the Works are demonstrated to be safe and are inspected by the
Contractor at appropriate intervals.
10 Where the excavation is to be discontinued for any period of time the face must be supported in a such
manner that ground movement prevented.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 29 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
2 Dewatering plans will provide details on the proposed dewatering equipment, sequence of installation,
discharge control and removal, and means for compliance with all environmental, health and safety
plans and procedures and requirements of applicable Government Authorities with regard to treating
ground water extraction prior to discharge.
3 The plan will include estimated flow quantities and sediment control measures to comply with relevant
Emirate local government Authority applicable regulations.
4 In areas where high pressure aquifer is expected, installation of depressurization systems will be
considered.
5 Upon completion of the installation of depressurization system and prior to excavation, the Contractor
will carry out a multiple well pumping test from wells capable of functioning for the intended duration of
the dewatering works, to demonstrate the adequacy of the pumping system and cut-off wall.
6 The ground water drawdown within excavations will be not less than one metre below excavation level.
7 The drawdown system design will be consistent with the design of the excavation and the relevant
standards governing the design, including any requirement to limit ground settlement surrounding the
proposed excavation.
8 For all dewatering methods used, the design and construction of both the Temporary and Permanent
Works will include for adequate groundwater cut-offs in order to control any change in groundwater
table in the ground surrounding the dewatered area from the typical expected fluctuations, to within
acceptable limits.
9 In the absence of any specific design criteria, and where control of groundwater drawdown is required,
then the drawdown of the water outside the cut-off wall will be limited to 2m below the lowest
recorded groundwater level prior to commencement of the dewatering.
10 The Contractor will keep all underground areas substantially free from water by providing drains,
ditches, pipes, pumps, sumps, etc. to drain water away.
11 The Contractor will provide necessary dewatering system that shall have the necessary capacity and
backup. The level of backup shall be specified by the Contractor in his method statement, for Engineer
approval.
12 The Contractor will submit to the Engineer details of his proposals for dealing with water from any
source prior to commencing underground work.
13 Where removal of groundwater by pumping is required then the Contractor will provide, install, operate
and maintain all necessary pumps, piping and other equipment required, including sufficient numbers of
standby pumps and generators to serve during periods of breakdown or maintenance.
14 Where water bearing seams, fissures or broken ground is yielding undesirably large quantities of water,
the Contractor will grout such seams, fissures or broken ground to stem the same.
15 The Contractor will provide devices for measuring the quantities of water removed from underground
excavations, by pumping or by gravity as the case may be, as per environmental requirements.
16 The Contractor will treat the discharge water to comply with environmental standards and remove any
suspended particles and/or other contaminants before discharge.
17 This may include providing settlement tanks before discharge to a sewer/storm drain or a water
treatment facility.
18 The dewatering contractor shall keep the site free from flood water.
19 JV should refer to the Etihad Rail Approved EIA report- X0231-S02-EWA-RP-00004& 00005-AA
20 Prior to start of any dewatering works on the project site, the dewatering contractor shall confirm:
• The location of all underground services and structures (e.g. excavating trial pits, and arrange work to
prevent damage to any services or structures);
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 30 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
• The detailed design of the dewatering system including proposed equipment, number of wells, and
Anticipated flow rates along with his proposed installation and testing procedures are suitable to
ensure proper functioning of the dewatering system in the ground conditions indicated by the results
of the geotechnical and hydrogeological investigations.
• A site specific calculation is to be conducted during construction
• The final dewatering design shall include as a minimum a detailed assessment of available ground
investigation and pumping test reports, discharge and drawdown calculations for the different
construction stages with a numerical groundwater flow model, evaluation of required number of wells
(including sufficient contingency), well layout, well design, well depths, monitoring system and type
of dewatering system and discharge points
2.15.4 Backfill
1 Backfill material general specifications will be in accordance with Earthwork Technical Specifications
C0306-S02-ECE-FS-30000.
2 The Contractor will submit for Approval his proposals for ensuring that all voids between any of his
Temporary works left in position and any structures are completely filled with Approved material.
3 These proposals will also include measures for ensuring that all voids are completely filled during the
removal of Temporary Works.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 31 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
10 Response Levels will include Alert, Action and Alarm Levels, and these will be defined by the Contractor
and are to be implemented as part of the instrumentation and monitoring Works.
11 Ground and structure monitoring will be established a minimum of 2 months prior to commencement of
any ground excavation, ground treatment or dewatering.
12 The Contractor will collect and interpret the instrumentation data, evaluate whether the response to
construction activities is reasonable, and carry out the Response Actions.
13 The frequency of the monitoring readings will be agreed with the Engineer, and monitoring records and
data will be made accessible to the Engineer as required.
14 The Contractor will inform the Engineer within 24 hours should an instrument reading reach an Alert
Level.
15 The Engineer may instruct the Contractor to submit a Detailed Plan of Action before an Action Level
status is reached.
16 The Detailed Plan of Action will include actions to be implemented for reaching the Alert Level and
Action Level.
17 The Contractor will implement the Response Actions identified in the Detailed Plan of Action for
reaching Alert Level.
18 Where in the opinion of the Engineer instrument reading trends indicate that an Action Level may also
be reached, then the Contractor will implement the Response Actions for reaching Action Level.
19 Should any instrument readings reach an Action Level then the Contractor will implement the Response
Actions for reaching the Action Level.
20 These actions will limit further excavation-induced movements and changes in groundwater and
piezometric levels, and control vibrations, to maintain the structural integrity of adjacent structures /
buildings and utilities.
21 The Contractor will take all necessary steps so that the Alarm Level is not reached. Work may then only
proceed if the Response Actions have been implemented and are in the opinion of the Engineer shown
to be effective.
22 The Contractor will make appropriate amendments to the Detailed Plan of Action where necessary.
23 Should any instrument readings reach an Alarm Level then the Contractor will implement emergency
Response Actions to diminish the deformations and ground responses including suspension of works.
24 The Contractor will submit a complete report for review of the construction methods, full history of
movements and Response Actions to be taken related to construction sequence for the Engineer
Approval.
25 Work may only resume upon the written instruction of the Engineer.
26 Data collected in the field by the Contractor will be stored in the “Instrumentation Database” developed
and maintained by the Contractor throughout the duration of the Contract.
27 The Contractor will be responsible for the daily entry of instrumentation data into the Instrumentation
Database.
28 The Contractor will make the Instrumentation Database accessible to the Engineer, the Engineer’s staff
and third parties as authorized by the Engineer.
29 During the course of the Works, the Contractor will submit instrumentation and monitoring
interpretative reports to the Engineer on a weekly or monthly basis as required.
30 Monitoring locations will be discussed with the local authorities and the JV will submit method
statements for the monitoring where required. Within the ER contract there are not specific locations
where instrumentation and monitoring are required. The impact assessment and monitoring plan would
be submitted to the authority for review and approval during the NOC application process.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 32 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 33 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 34 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
4 Control tests for density will be carried out daily on the support fluid using suitable apparatus.
5 The measuring device will be calibrated to read within 0.01 g/ml.
6 For average solid conditions the results will generally be within the ranges stated in Table 1 below.
Table 1: Requirements for Support Fluids (Bentonite)
Property to be Measured Range of Results @ 20oC Test method From the American
Petroleum institute (API) Publication
RP13B
Density Less than 1.10 g/ml Mud Density Balance
Fluid Loss Less than 40ml 30-minute test
Viscosity 30-90 seconds or less than 20 cP Marsh Cone method or Fann
Viscometer
Shear Strength (10-minute gel 1.4 – 10 N/m2 or 4 – 40 N/m2 Shearometer or Fann Viscometer
strength)
7 The tremie pipe will extend to the base of the boring and a sliding plug will be placed in the boring to
prevent direct contact between the first charge of concrete in the tremie pipe and the water or drilling
fluid.
8 At all times during concreting, the tremie pipe will penetrate the previously placed concrete and will not
be withdrawn from the concrete until completion of concreting.
9 Sufficient quantity of concrete within the pipe will be maintained at all times to ensure that the pressure
from it exceeds that from the water or drilling fluid.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 35 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
4 Where a number of structures are in proximity to each other they may be considered as one site if the
geotechnical data provided by the Contractor for each structure location is proved to be equivalent to
the satisfaction of the Engineer.
5 The Contractor will construct at least one trial pile (which is not a Contractor works pile) which will be
tested by Maintained Compression Load Test (MLT) to 200% of the design working load at each bridge
site and the MLT results will be submitted for the acceptance of the Engineer prior to construction of
permanent piles.
6 The Trial pile will not be incorporated into or made part of the Permanent Works.
7 In case of soil inconsistency, additional non-working pile test will be done as directed by the Engineer.
8 Calliper logging for entire pile bore for piles diameter more than 1000mm will be carried out before
concreting according to ASTM D 6167-97.
9 Test piles (≥ 1000 mm in diameter) will be installed with displacement transducers at the pile head.
10 Dial gauges will not be used on these piles without the prior acceptance of the Engineer.
11 Three displacement transducers will be fixed, spaced at 120° part.
12 Piles will be instrumented with strain gauges and Each pile is to be instrumented with four levels of
strain gauges.
13 First level will be near the pile head and last near the pile toe to assess the load transferred to the pile
toe.
14 Each of these levels will have four strain gauges spaced at 90° apart.
15 Strain gauges will be accurate to within a tolerance of 1µ strain
16 Pile instrument is required only for non-working piles test.
Movement under Working Load Movement under 150% of Working Load Movement under 200%
Working Load
3 The residual set of any working load test pile measured 24 hours after removal of the load will not
exceed the differential settlement used in design or 6mm, whichever is the lesser.
4 Testing will be in compliance with BS8004.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 36 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
3 Testing will be carried out by a specialist firm competent in the interpretation of test data.
4 The Contractor will give all available details of the ground conditions, pile dimensions and construction
method to the specialist firm before the commencement of integrity testing in order to facilitate
interpretation of the tests.
5 The test results and findings will be recorded and made available within 7 days of the completion of each
phase of testing.
6 The report will contain a summary of the method of interpretation including all assumptions,
calibrations, corrections, algorithms and derivations used in the analyses.
7 If the results are presented in graphical form, the same scales will be used consistently throughout the
report.
8 The units on all scales will be clearly marked and uniquely referenced for each pile and cross- referenced
on the record drawings.
9 In the event that any anomaly is found in the results indicating a possible defect in the pile the
Contractor will demonstrate that the pile is satisfactory for its intended use or will carry out remedial
works which may include pile replacement or downgrading, (in addition to remedial work); in all cases,
the Contractor will seek acceptance from the Engineer.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 37 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
4.2 Concrete
4.2.1 Cementitious Materials
1 Each type of cementitious material will be obtained from a primary single source acceptable to and
approved by the Engineer in good time before ordering or confirming any order.
2 Secondary sources for cementitious materials proposed by the Contractor will be accepted as contingent
and be subject to the Engineer’s approval.
3 Acceptance of materials and sources does not relieve the Contractor of the responsibility to produce
concrete that meets all of the specified requirements.
4 The Contractor’s proposal will include test certificates along with the information requested herein.
4.2.2 Cement
1 Portland cement will comply with quality control and test requirements of BS EN 196 and BS EN 197.
2 CEM 1 will comply with the supplementary mineral material properties as described in Table 3
Table 3: Additional Mineral Material Properties for CEM | Cement
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 38 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
Moisture ≤ 3.0%
SiO2 ≥ 85.0%
Cl ≤ 0.01%
2 The method of incorporation of the silica fume into the mix will be subject to the approval of the
Engineer.
3 The Contractor will submit a method statement describing the plant and equipment proposed for
batching and mixing and the timing of addition of the silica fume to the mix.
4 The method statement will be supported by a letter from the silica fume supplier approving the
methodology.
4.2.6 Water
Water used in concrete and curing will comply with quality control and testing requirements of BS EN 1008.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 39 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
6 Cementitious material which has been manufactured for longer than 6 months on the proposed date of
delivery to the site will be inspected, sampled and tested for compliance as delivered by an accepted
independent laboratory.
7 No cementitious materials to be incorporated into any works on site will contain lumps.
4.3 Aggregates
4.3.1 General
1 Aggregate will be from sources approved by the Engineer.
2 Aggregate will not be composed of or contain any inclusions of materials likely to cause staining or
otherwise to disfigure finished concrete surfaces.
3 Fine and coarse aggregates for all types of concrete will comply in all respects with the requirements of
BS EN 12620, BS 882 of 1992, ASTM C33.
4 Maximum size of aggregates will not exceed 20mm.
5 Any aggregates which do not comply in respect of cleanliness will be mechanically washed in clean, fresh
water complying with Clause 2.4 to remove clay, silt, salts and any adherent coatings and other
impurities in order to comply.
4.3.2 Grading
1 Grading of fine aggregates will generally fall within Zone M only of Table 4 of BS 882 except that other
grading may be used where tests and trials on concrete verify its suitability.
2 Coarse aggregates will be prepared as single sized aggregates and blended to produce a graded
aggregate complying with BS EN 882 for the nominal aggregate size indicated on the Drawings.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 40 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
2. Visual examination of fine and BS 812 Fine aggregates to be free from all organic matter
coarse aggregates (standard colour or lighter). Equivalent to test for Organic
Impurities in fine aggregates
5. Clay, fine silt and fine dust ASTM C117 3.0% max for natural sands (Uncrushed rock)
(material finer than BS 0.075 5.0% max for crushed stone sands for Fine aggregates
sieve)
1.0% max for coarse aggregates
7. Flakiness Index BS 812 25% max for all coarse aggregate test fractions
8. Elongation Index BS 812 25% max for all coarse aggregate test fractions
10. Specific Gravity of coarse and BS 812 Minimum SSD 2.65 for Coarse Aggregate (CA) Minimum
fine aggregates SSD of 2.55 for Fine Aggregate (FA).
11. Water Absorption of coarse and BS 812 2.0% Max for Coarse aggregate and Fine aggregate
fine aggregates
13. Organic Impurities in fine ASTMC40 Fine aggregates to be free from all organic matter
aggregate (standard colour or lighter)
14. Aggregate Crushing Value BS 812 23% max for Standard test
15. “Ten per cent Fines” Value BS 812 Not less than 100kN
16. Aggregate Impact Value BS 812 25% max for Standard test fraction
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 41 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
19. Total Chloride (Cl) BS 812 Part 118 0.03% max in coarse aggregates by weight 0.06% max in
fine aggregates by weight
20. Voided Shell Content BS 812 Part 106 3% max in material retained on a BS 2.36mm sieve
21. Cement– Aggregate Reactivity ASTM C277 Aggregates may initially be assessed for its reactivity in
ASTM C289 accordance with ASTM C289 and if potential reactivity is
ASTM C342 indicated, then mortar bar tests in accordance with ASTM
ASTM C586 C227 shall be carried out. Cement-Aggregate
Combination ASTM C227: Limits :6 month expansion
0.10% max.
3 The laboratory will be a suitable independent laboratory in respect of both availability of facilities and
competence of personnel.
4 The Engineer may require witnessing the sampling and the tests.
5 Part of each sample submitted for source acceptance will be used for concrete trial mixes and part will
be retained as a reference sample for comparison with subsequent deliveries.
6 Subject to the results of the testing being satisfactory, the Engineer will require trial concrete mixes to
be made and tested, all as specified herein, prior to acceptance of a particular source of aggregate.
1. Grading BS 812 Part 103 Each 2 weeks or per 100m³ whichever is more
frequent
2. Material finer than BS 812 Part 103 Each 2 weeks or per 100m³ whichever is more
0.075 mm frequent³
3. Clay lumps and ASTM C142 Each 2 weeks or per 100m³ whichever is more
Friable Particles frequent³
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 42 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
5. Organic impurities BS 1377, ASTM C40 More frequent of monthly or per 200m3
8. Shell content BS 812 Part 106 Each 2 months or per 100 m3 whichever is more
frequent.
9. Particle shape BS 812 Part 105.1 Each 2 months or per 100 m3 whichever is more
frequent.
11. Acid soluble sulphates BS 812 Part Each 12 concrete days if result is more than 75% of the limit
S03 118 snd each 2 months if result is less than 75% of the limit
14. Drying shrinkage(2) [BS EN 1367-4] At the start of the project and whenever there is a
BS812 Part 120 change in the source of supply
15 Potential reactivity of ASTM C295, C289 At the start of the project of aggregates and wherever
aggregates(2): there is a change in the source of supply
16. Moisture variation by In accordance with the Specification but not less than
moisture meters t w i c e daily
6 Where the chloride content is variable, it may be necessary to test every load using the rapid field test
(Quantab test): in the event of disagreement regarding the results of the field test, laboratory testing
(Volhard test) in accordance with BS196 or BS812 as appropriate will be used to determine chloride
content.
7 Drying shrinkage and potential reactivity of aggregates will be determined initially at the start of the
project and then whenever there has been a change of source or whenever there has been a change of
quality of the aggregates.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 43 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
4.4 Admixtures
4.4.1 General
1 The use of admixtures will be proposed by the Contractor as part of his design of the concrete mix and
will comply with the requirements of BSEN934 or ASTM C494.
2 The proposed admixtures will be certified by the supplier as compatible with all of the requirements of
the Specification and free from any chemicals detrimentally reactive with any constituent of the
concrete or the embedded reinforcement.
3 The addition of calcium chloride, accelerators and air-reducing agents, will not be permitted, unless
otherwise accepted by the Engineer.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 44 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
4 Concretes incorporating Silica Fume will incorporate a super plasticising admixture specially formulated
to aid dispersion of the silica fume throughout the mix.
5 The admixture will be certified as suitable for the intended purpose by the concrete mix designer and
details of the proposed admixture will be submitted to the Engineer for approval.
6 No consignment of admixture will be delivered to site, except for pre-production testing of concrete
mixes, until all test results are proved satisfactory.
4.4.2 Dosing
1 Admixtures will be introduced into the mix by means of acceptable automatic dosing equipment that
feeds a fixed quantity of admixture into the mixer at the same time as water is added to the mix or in
accordance with the manufacturer’s recommendations.
2 This equipment will be maintained daily and a measuring cylinder suitable for checking the calibration
will always be available.
3 The Contractor will ensure that his batch plant has an accessible outlet pipe to enable these calibration
tests to be carried out.
4 All chemical admixtures will be introduced to the concrete mix in liquid form and if made up into that
form by the Contractor, they will be subject to satisfactory testing by the Engineer prior to use.
5 The dispensing device will:
a) Be capable of delivering the specified amount to within + 3% of the quantity of admixture in each
batch.
b) Have provision for dispensing the admixture directly into a container so that accuracy can be checked.
The equipment will include a glass-measuring cylinder for calibration.
c) Have a sight glass to allow a visual check on the type and quantity of admixture being dispensed.
d) Have an effective anti-foaming device if admixtures used are subject to foaming.
4.4.4 Dosing
1 Admixtures will be introduced into the mix by means of acceptable automatic dosing equipment that
feeds a fixed quantity of admixture into the mixer at the same time as water is added to the mix or in
accordance with the manufacturer’s recommendations.
2 This equipment will be maintained daily and a measuring cylinder suitable for checking the calibration
will always be available.
3 The Contractor will ensure that his batch plant has an accessible outlet pipe to enable these calibration
tests to be carried out.
4 All chemical admixtures will be introduced to the concrete mix in liquid form and if made up into that
form by the Contractor, they will be subject to satisfactory testing by the Engineer prior to use.
5 The dispensing device will:
a) Be capable of delivering the specified amount to within + 3% of the quantity of admixture in each
batch.
b) Have provision for dispensing the admixture directly into a container so that accuracy can be checked.
The equipment will include a glass-measuring cylinder for calibration.
c) Have a sight glass to allow a visual check on the type and quantity of admixture being dispensed.
d) Have an effective anti-foaming device if admixtures used are subject to foaming.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 45 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
4.4.6 Fibres
1 If fibres are to be added to the concrete mixture the products will be supported by a British Board of
Agreement Certificate or other accepted independent certification to confirm product characteristics
and successful project history.
2 Fibres will be composed of virgin polypropylene and will be either monofilament or fibrillated provided
that the selected fibres do not adversely affect the capillary absorption properties of the mixture (i.e.
their use does not increase the capillary index (Ic) above the value obtained from the control mixture).
3 Optimal fibre dosage in terms of effect upon workability, strength, and capillary properties will be
determined by making comparative tests of companion specimens from the proposed mixture, both
with and without fibres, to be submitted to the Engineer prior to mixture verification.
4 Strength tests on standard laboratory specimens of fibre concrete will be in full compliance with the
strength requirements of this specification.
5 Consistency (Slump) tests of fibre concrete will be at least 75mm, and the concrete will be highly mobile
when vibration is introduced.
6 The capillary Index (Ic) determined from capillary suction tests of fibre concrete carried out on three
tests specimen from three individual field cured cube specimen (either 100 or 150mm size) at 7 days of
age (normal wet curing period).
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 46 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
3 The Contractor may propose methods to mix ordinary Portland cement and ground granulated blast
furnace slag in the mixer as an alternative method to supply of a cement formed by crushing cement
clinker and GGBS together in manufacturing plant conditions.
4 This alternative method will be used only if the proposed combination is produced in controlled
conditions in accordance with BS 8500-1 and is fully compliant in all its properties with a plant prepared
combination.
5 The Contractor will be responsible for the design of the concrete mix conforming with the performance
requirements set out in the design and the durability report C0306-S02-ECB-RP-30018 and for
demonstrating that the proposed mix meets all of the performance requirements.
6 The mix designs will take account of the requirements for concrete durability: as a minimum, reinforced
concrete will be considered to be subject to severe or very severe exposure conditions.
7 Before placing any concrete in the Permanent Works the Contractor will obtain the acceptance of the
Engineer for his designed mix.
8 The target design mean strength of each concrete mix will be 1.64 times the standard deviation of test
results for that mix which will be taken as not less than 3.5MPa where insufficient test results are
available to determine a statistically relevant standard deviation for the mix.
9 The Contractor will advise the Engineer of the qualified Ready Mix Concrete Supplier that he is proposing
to use at least 45 days prior to placing concrete.
10 The Engineer will verify the acceptability of the Supplier and the mix design requirements.
11 Any acceptance of the design mix will be deemed withdrawn if there is change in the constituent
element of the mix.
12 The Contractor will design a new mix to suit the changed constituents to obtain Engineers acceptance
prior to its use in the permanent works.
13 Mix design will be submitted to the Engineer at least 30 days prior to placing concrete.
14 Concrete mix trials will be submitted to the Engineer at least 21days prior to concrete placing.
Concrete Max. Binder Content (kg/m3) Max. Water/ Min. Coarse Max. Free
Grade Aggregate Cement ratio Aggregate (%) Water (%)
(Cylinder/Cube Size (mm) (l/m3)
) (N/mm2)
Min. Max.
20/25 20 - 250 - - -
(blinding,
benching, etc.)
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 47 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
Concrete Max. Binder Content (kg/m3) Max. Water/ Min. Coarse Max. Free
Grade Aggregate Cement ratio Aggregate (%) Water (%)
(Cylinder/Cube Size (mm) (l/m3)
) (N/mm2)
Min. Max.
Structural Mix Design Indicative Binder Proportions Range Additional Initial surface
Element Reference Strength member or Absorption Test
(Cylinder/C OPC GGB SF coating (ISAT) to BS
ube) (%) S (%) (%) 1881 Pt. 208
(N/mm2) ml/m2/sec (10
minutes)
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 48 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
Structural Mix Design Indicative Binder Proportions Range Additional Initial surface
Element Reference Strength member or Absorption Test
(Cylinder/C OPC GGB SF coating (ISAT) to BS
ube) (%) S (%) (%) 1881 Pt. 208
(N/mm2) ml/m2/sec (10
minutes)
2 Water / Cement ratio will be determined as the ratio of the combined volume in litres of water and all
liquid additives to the total weight in kilogrammes of all cementitious materials.
3 Coarse aggregate (considered as the size fraction between 20 and 5mm) will be the percentage of total
volume of the mixture.
4 Each grade of concrete will be designated by its specified 28-day compressive characteristic cylinder
strength according to ASTM C31/C39 or Compressive strength of Cubes as per BS 1881 Part 116 in Mega
Pascals followed by the nominal maximum size of aggregate in millimetres and such other unique coding
as will be determined from the durability report.
5 Workability will be such as to enable the concrete to be fully compacted without segregation around the
reinforcement, pre-stressing ducts and other inserts detailed on the Contractor’s drawings, and to
completely fill the formwork and provide the specified surface finish under prevailing climatic
conditions.
6 Concrete mixtures will be designed for a minimum slump (consistency) as shown below. Concrete Slump
- the use of high percentage of GGBS in concrete mixes may cause difficulties in handling concrete
(pumping, placing, finishing...); therefore, it is recommended to specify and accept higher slumps for
such mixes in order to avoid any addition of water to the concrete mix on the construction site.
a) 100 mm ±25 where concrete is to be placed in water-free shaft and,
b) 175mm ±25 where concrete is to be placed by tremie method under drilling fluid
c) 200+/-40mm where concrete mixes are placed by pumping method
7 The above values will not be altered unless approved otherwise by the Engineer in special conditions
such as placement of concrete on sloped surfaces.
8 Where pumped concrete is used, this slump requirement will apply at the point of discharge.
9 The Contractor will prepare and complete full trials upon concrete mix designs for each grade of
concrete to be used in the Works.
10 The Concrete strength will be defined in terms of the 28-day characteristic cylinder strength or cube
strength
11 The strengths will be those assumed for the design of the structure and will be achieved by the
Contractor in the finished Works.
12 Prior to using any concrete mix in the Works, and as directed by the Engineer, a minimum of two sample
trial panels for each mix will be cast using the formwork material to be used in the Works and containing
a representative arrangement of reinforcement, particularly for congested reinforcement arrangements,
to confirm the workability and finishes attainable.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 49 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
13 The panels will be no less than 1m2 on each formed face in trial panels.
14 Should the Engineer reject any sample panel, the Contractor will take such action as may be necessary
until a sample comprising two test panels will be acceptable.
15 All concrete will be capable of being transported and readily compacted by the accepted method into a
dense homogeneous mass without segregation, bleeding or plastic cracking: surface cracking or other
types of surface pattern cracking will be grounds for rejecting concrete as cast.
16 Bleeding will not exceed 0.5% after 1 hour from completion of mixing nor 1.5% maximum when tested in
accordance with ASTM C232 Method B.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 50 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
x. Splitting tensile of concrete cylinder as per ASTM C496, at 7 and 28 days. Limit= 0.7*SQRT(fck).
xi. Depth of water penetration as per BS EN 12390 at 28 days
xii.Water absorption of hardened concrete as per BS 1881 P122 at 28 days
xiii.
Rapid Chloride permeability test to ASTM C1202 at 28 days
xiv.Chloride Migration Coefficient test to NTB 492, at 28 days - Range - Refer to Durability report C0306-
S02-ECB-RP-30018
8 Mixture verification will be accepted and progress with the concrete works approved by the Engineer
when the results of the above tests are in accordance with the requirements of this Specification.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 51 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
4.6.4 Workability
1 The workability of the fresh concrete will be such that the concrete is suitable for the conditions of
handling and placing so that after compaction it surrounds all reinforcement, tendons and ducts and
completely fills the formwork.
2 Workability will be measured for Each Truck or at such time as directed by the Engineer Using Slump
Test to BSEN 12350 part-2 Only.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 52 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
4 No concrete will be placed in a foundation until the extent of excavation and the character of bearing
material have been verified and no concrete will be placed in any structure until the placement of
reinforcing steel and the adequacy of the forms and falsework have been inspected by the Engineer.
5 Concrete will not be placed in any part of the Works until the Engineer’s acceptance has been notified.
6 If concrete has not started within 24 hours of such acceptance being given, a new inspection request will
be submitted to the Engineer.
7 Concreting will then proceed continuously over the area between construction joints.
8 Prior to placing any concrete on natural surfaces a blinding concrete will be laid to a minimum of 100mm
thickness.
9 This blinding will be suitably cured prior to subsequent concrete placement.
10 The blinding will be clean and free from any dust or impurities prior to subsequent concrete placement.
11 The timetable for a pour of concrete is to be so arranged that no face of concrete will be left more than
30 minutes before fresh concrete is deposited against it or more than 90 minutes after the mixing of the
concrete forming the face (90 minutes from the introduction of water to the mix).
12 No concrete work will be stopped or temporarily discontinued within forty-five (45) centimetres of the
top of any finished surface, unless such work is finished with a coping having a thickness less than forty-
five (45) centimetres in which case the joint will be made at the under edge of the coping.
13 Concrete will be deposited in horizontal layers to a compacted depth not exceeding 400mm where
internal vibrators are used or 300mm in all other cases.
14 Concrete will not be dropped into place from a height exceeding 2m.
15 When trunking or chutes are used, they will be kept clean and used in such a way as to avoid
segregation.
16 Where steep slopes are required for placing concrete with chutes, the chutes will be equipped with
baffle boards or being short lengths that reverse the direction of the movement.
17 Chutes and the use of chutes must be agreed with the Engineer prior to their use.
18 All chutes will be kept clean and free from coating of hardened concrete by thoroughly flushing with
water after each run.
19 The water used for flushing will be discharged clear of the concrete already in place.
20 No concrete will be placed in flowing water.
21 Underwater concrete will be placed in position by tremies, or by pipeline from the mixer.
22 Where the concrete is placed by the tremie, its size and method of operation will be in accordance with
BS 8004.
23 During and after concreting under water, pumping or dewatering operations in the immediate vicinity
will be suspended.
24 Concrete placed below ground level, excepting only piles, caissons or barrettes, will be protected on its
outside faces using polyethylene sheeting, bitumen rubber latex emulsion flexible damp and vapour-
proof liquid membrane conforming to BRE Digest No. 54, or similar.
25 Concrete will not be subjected to disturbance between 4 hours and 24 hours after compaction.
26 Re-compaction of the upper layers of deep lifts to prevent of anneal plastic settlement cracking will be
subject to the approval of the Engineer.
27 Mixture verification will be in accordance with Section 4.5.3.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 53 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
2 Concrete will not be placed if the rate of evaporation of water exceeds 1kg/m²/hr.
3 The contractor will record the ambient temperatures three times daily.
4 Temperature of concrete will be monitored; and when concrete is deposited it will have a temperature
of not less than 15 degrees Celsius and not more than 30 degrees Celsius
5 In case that the atmosphere temperature not falling within the above prescribed range as mentioned in
4.7.2.4 , then the contractor will propose methods of insulation (heating or cooling) to ensure that the
above temperature range is achieved.
6 In all cases the Contractor will seek the Engineer acceptance prior to placing concrete. The temperature
of the concrete when placed shall not exceed 30 deg.C nor shall concrete be mixed or placed when the
shade air temperature is 40 deg.C or above, or is expected to reach such a level during concreting,
without special permission from the Engineer
7 Hot weather increases the temperature of fresh concrete causing increased concrete water demand,
accelerated concrete shrinkage loss, increased rate of setting leading to placing and finishing difficulties,
increased tendency for plastic shrinkage cracking, increased concrete temperature resulting in lower
ultimate strength and increased potential for thermal cracking.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 54 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
Sampling Test
ITEM Test Frequency Rate
Method Method
b. Steel
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 55 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
Sampling Test
ITEM Test Frequency Rate
Method Method
as
per:
c. Concrete
1. Air content, as per BS EN BSEN BSEN Once at the time of mix design of
123501-7:2000 12350-1 12350-7 concrete or as directed by the
Engineer.
2. Flexural strength of Prism as BSEN BSEN Once at the time of mix design of
per BS EN 12390-5 12350-1 12390-5 concrete or as directed by the
Engineer.
3. Bleeding as Per ASTM C232 BS 1881 - C 232 One at the time of mix design of
concrete or as directed by the
101 Engineer.
4. Splitting Tensile of Conc. BS 1881 - C-496 One at the time of mix design of
Cylinder as per ASTM C- 101 concrete or as directed by the
496:1996 & others Engineer.
5. Depth of Water Penetration (BS BSEN 12350-1 BSEN 12390-8 For Severe or Very
EN 12390 P-8:2000) Severe Exposure Conditions each
500m3 or every 6 months; and for
all other concrete each 500m3 or
every 6 months or as directed by
the Engineer.
6. ISAT as per BS 1881- p-208 BS 1881- BS 1881 - For Severe or Very Severe Exposure
101 Part 208 Conditions each 500m3 or every 6
months; and for all other concrete
each 500m3 or every 6 months or
as directed by the Engineer.
7. Water absorption of Hardened BS 1881- 1881-122 For Severe or Very Severe Exposure
Conc. As per BS 1881 P122 101 Conditions each 500m3 or every 6
months; and for all other concrete
each 500m3 or every 6 months or
as directed by the Engineer.
8. Rapid chloride permeability BS 1881 - ASTM C 1202 For Severe or Very Severe Exposure
101 Conditions each 500m3 or every 6
months; and for all other concrete
each 500m3 or every 6 months or
as directed by the Engineer.
9. Slump test - as per BS 1881 P102 BS 1881- BS-1881- 102 From each transit mixture load
101 arrived at site
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 56 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
Sampling Test
ITEM Test Frequency Rate
Method Method
10. Concrete Mix Design (Mixing All mixes are to be designed once
and Sampling in the lab) as per BS for verification and approval.
1881 P125 & In Site (Sampling) as
per BS 1881 P 101
11. Kerbs-as per BS 7263 BS 7263-1 BS 7263-1 Sample to be taken from each
batch of upto 1000 kerb in whole
consignment
For further durability testing that the contractor will follow please refer to the project durability report C0306-
S02-ECB-RP-30018
4.8.2 Construction
1 Load test on false work to be carried out without additional cost to Contract.
2 As directed by the Engineer, the Contractor will verify the settlement at site under the scaffolding by
doing plate loading test.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 57 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
3 All formwork will be of such quality and strength as will ensure rigidity throughout the placing, ramming,
vibration and setting of the concrete without visible deflection.
4 The Contractor is responsible for the integrity of the formwork.
5 All formwork will be so constructed that there will be no loss of material from the concrete.
6 After setting, the concrete will be in the position and of the shape and dimensions prescribed.
7 The finished surface of exposed concrete will be of a quality specified on the drawings.
8 All curved surfaces will be formed with plywood or steel of a quality and construction to provide the
required finish within tolerance.
9 The plywood to be marine ply or three layers of poly-urethane varnish to be applied to commercial
plywood.
10 Where internal metal ties are permitted, they or their removable parts will be extracted without damage
to the concrete and the remaining holes filled with mortar.
11 No permanently embedded metal part will have less than specified cover to the reinforcement unless its
durability is assured so as not to adversely affect the durability and design life of the element in which
the part is embedded.
12 After completion of construction of any formwork and falsework, or part thereof, and prior to loading
falsework, the Contractor and the independent consulting engineer who checked the falsework design,
will certify in writing that the executed falsework has been checked and no deviation from the certified
detailed drawings has been found.
13 No formwork and falsework will be used for construction of the Works without this certification.
14 The Contractor will in all cases request the acceptance of the formwork by the Engineer in sufficient time
to allow an inspection to be made and will not commence concreting until such acceptance is obtained.
15 The period between the Contractor’s request for acceptance and his intention to commence concreting
will be not less than one clear normal working day and the Engineer’s may require a longer period if, in
his opinion, the formwork is of such complexity as to require it.
16 Acceptance of the formwork by the Engineer will not absolve the Contractor of his responsibilities under
the Contract.
17 The Contractor will construct the formwork and falsework in accordance with the submitted Shop
Drawings.
18 Variations from the formwork and falsework Shop Drawings will not be permitted unless the Engineer is
provided with revised Shop Drawings that have been stamped, signed and dated by an independent
Consulting Engineer registered in United Arab Emirates.
19 Tie Rods (i.e. tension/anchorage bars, RHS, SHS, CHS or Angle sections) to be used for thin structural
elements, thin walls/columns, retaining walls, and wing walls, etc. as per construction requirements and
developed by Contractor’s design.
20 The Contractor will be responsible to remove and re-construct any damaged structural member due to
formwork or false work failure at his own cost.
4.8.3 Tolerance
1 The formwork will be set to such lines and levels as to ensure that the following tolerances are not
exceeded in structures as cast.
2 For all buried concrete:
a) Generally, deviation from line by + 25mm or -12mm
b) Additionally, for concrete surfaces that are to be waterproofed, abrupt irregularities in the surface
finish will not exceed 3mm
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 58 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
3 For visible soffits, edge beams, sides of parapets and the like: +/- 3mm but not more than 3mm in 3.5m.
4 For all other concrete: +/- 6mm but not more than 3mm in 3.5m.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 59 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
Class F1 As struck. Used only for concealed work and will be the as-cast surface Inside box girder sections
produced using closely jointed sawn timber boards, planked formwork,
plywood, sheet metal or other suitable proven form material. The surface
will be free from voids and honeycombed areas.
Class F2 The irregularities in the finish will be no greater than those obtained from
the use of wrought thickness square edged boards arranged in a uniform
pattern. The finish is intended to be left as struck but imperfections such as
fins and surface discolouration will be made good by methods approved by
the Engineer.
Class F3 The formwork will be lined with a material agreed with the Engineer to Exposed faces of piers,
provide a smooth finish of uniform texture and appearance. This material abutments, bridge decks,
will leave no stain on the concrete and will be so joined and fixed to its parapets and curbs and such
backing that it imparts no blemishes. It will be of the same style and other surfaces where smooth,
obtained from only one source throughout. The Contractor will make good uniform surfaces are required.
any imperfections in the finish as required by the Engineer. Internal ties and
embedded metal parts will not be allowed.
Class F4 The requirements for Class F4 are as for Class F3 except that internal ties
and embedded metal parts will be permitted. The ties will be positions to a
regular pattern.
2 Permanently exposed concrete surfaces to Classes F4, F3 and F2 finish will be protected from rust and
stains of all kinds.
3 Unless otherwise described in the Contract, all formwork joints for exposed surfaces of concrete to Class
F2, F3 and F4 finish will form a regular pattern with horizontal and vertical lines continuous throughout
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 60 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
each structure and all construction and movement joints will coincide with these horizontal or vertical
lines.
Class U1 The concrete will be uniformly levelled with a screed board to produce a plain,
textured or ridged surface to the profile shown on the Construction Drawings. Plain
texture surface will be obtained by screeding or light brushing, and will not have
abrupt irregularities exceeding 3 mm. No further work will be applied to the surface
unless it is used as a first stage for a Class U3 finish.
Class U2 After the concrete, has hardened sufficiently to prevent laitance from being worked Exposed faces of
to the surface, a Class U1 finish will be floated by hand or machine sufficiently to slab tracks (if any).
produce a uniform surface free from screed marks.
Class U3 When the moisture has disappeared, and the concrete has hardened sufficiently to
prevent laitance from being worked to the surface, a Class U1 finish will be steel-
trowelled under firm pressure to produce a dense, smooth uniform surface free from
trowel marks.
Class U4 This finish is for concrete areas that are to receive waterproofing systems as agreed Bridge decks,
with the Engineer. The concrete will be uniformly levelled to a U3 finish. The pile cap,
accuracy of the finished surface will be such that it does not deviate from the
required profile by more than +/- 5mm over a 3m gauge length or have any abrupt abutment/piers top
irregularities more than 3mm. Prior to the installation of the deck waterproofing surface
system the surface will be lightly sand blasted to remove laitance. Any plastic cracks
must then be sealed using low viscosity epoxy before application of the
waterproofing membrane.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 61 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 62 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
III. Or if the summation of crack widths over a 2m portion of an element should not exceed 1mm
(recognising that the minimum practical width for measurement is around 0.15mm), and cracking
greater than this should also be injected
4.11.1Assessment
Key stages in the assessment process are:
• assessment of the condition of the structure;
• identification of causes of deterioration;
• deciding the options for protection and repair;
• selection of the appropriate principle(s) of protection and repair;
• selection of methods;
• definition of properties of products and systems;
• specification of maintenance requirements following protection and repair
The condition assessment and identification of causes of deterioration should always be completed to
determine if repairs are required to ensure the design life is met.
4.11.3Repairs to Cracks
It is expected that some cracking to concrete will occur during construction. Where cracking occurs, the crack
The cause of the cracking should be determined, as:
• it may be possible to alter construction techniques to reduce or eliminate the further
cracks; and
• it is required to select an appropriate repair type and material.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 63 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
The Contractor shall prepare a detailed method statement covering the methods and materials (including
suppliers) to be employed for each item of work and shall be submitted to the Engineer for approval.
i. Type 1 – General assessment to be carried out and crack To be repaired during surface preparation
using filler of the coating materials.
ii. Type 2- General assessment to be carried out and crack to be repaired using solvent free, high strength
epoxy adhesive suitable for repairing and bonding, in accordance to the Manufacturer’s
recommendations and instructions. If depth exceeds the reinforcement cover then injection to be
used
iii. Type 3- Crack mapping required. To be repaired using a two component, low viscosity, moisture
insensitive, solvent free epoxy resin, in accordance to the Manufacturer’s recommendations and
instructions.
iv. Type 4- Crack mapping to be done. To be repaired by resin Injection process, in accordance to the
Manufacturer’s recommendations and instructions.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 64 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
Where concrete is to be removed by high pressure water jetting, the water shall be clean, fresh and obtained
from a Public Utility Undertaking. The Contractor shall not add chemicals to the water. Safety measures shall
comply with the Code of Practice for the Use of High Pressure Water Jetting Equipment, produced by the
Safety Committee of the Water Jetting Association. The Contractor shall employ a suitably qualified and
experienced personal with adequate training and certification e.g. as a member of the Water Jetting
Association or similar. A lightweight electric demolition hammer may be used for final trimming of the area
broken out.
Water arising from high pressure water jetting operations shall be contained near the working area, and not
be allowed to drain away into any hidden areas of existing structures. Water arising shall be deemed to be
contaminated.
Discharge of contaminated water into surface water sewers (including highways drains), watercourses, the
sea and the ground shall be prohibited. Discharge to a foul sewer shall only be permitted if written consent
from the local sewerage provider has been obtained in advance of disposal. Contaminated water may be
treated on site to remove contamination (e.g. particulates and high pH) and subsequently discharged,
however the Contractor shall obtain from the relevant environmental regulator or water authority, prior
consent to the water cleaning process and method. Otherwise contaminated water from high pressure water
jetting shall be collected and transported off-site for legal and registered disposal. Only registered waste
carriers will be permitted for this. The Contractor shall provide a certificate stating that this has been done,
listing the licensed carrier and waste disposal point used.
Prior to commencement of high pressure water jetting, the Contractor shall submit a detailed method
statement of the proposed cutting operations indicating the direction and location of cutting, the type and
performance of pump equipment, nozzle type and diameter and the proposed nozzle pressures, pump output
power and details of any protective screens.
The surface of the base concrete remaining after high pressure water jetting shall be dense with no significant
localised peaks and no loose particles of aggregate or surface cracking. Near vertical faces shall not contain
surface overhangs that might trap air during concreting.
Care is to be taken to minimise mechanical damage to exposed reinforcement. Exposed reinforcement shall
be kept clear for visual inspection and shall be photographed.
Note that during concrete breakout, the concrete around all partially exposed reinforcement should be cut
back to 20-30mm behind the reinforcement (to ensure good bond between the repair mortar and the
reinforcement) and the reinforcement should be cleaned to a standard of SA2 ½ to BS EN ISO 8501 before
applying the repair mortar. Note that treatment of reinforcement and surface preperation, casting and curing
of the repair products are key to the performance of the repair.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 65 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
4.13 Records
1 Records will be kept by the Contractor of the positions in the Works of all batches of concrete, of their
grade, and of all test cylinders, cores or other specimens taken from them.
1 Copies of these records will be supplied to the Engineer as soon as results are available, and on a regular
basis.
2 In particular, results of seven-day strength tests will be made available to the Engineer within two days
of testing.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 66 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
5 Reinforcing Steel
5.1 General
1 Non-metallic reinforcement may be proposed for use subject to its acceptance for use by the Engineer.
2 Non-metallic reinforcement will be in accordance with the appropriate international standards.
3 Cracks or any deformities in rebar shall not be allowed for site use
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 67 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
3 The test certificates will state that these materials have been tested and found to comply in all respects
with the requirements of the relevant Standards.
5.8 Delivery
1 Construction
a) Load test on false work to be carried out without additional cost to Contract.
b) As directed by the Engineer, the Contractor will verify the settlement at site under the scaffolding by
doing plate loading test.
2 Each tag will show the manufacturer’s test number and batch number, mill certificates with heat number
or other designation that will identify the bars with the certificate issued for that batch steel.
3 Steel fabric reinforcement will be delivered in flat sheets which are to be clearly marked with the British
Standard or manufacturer’s reference number and the nominal weight per square metre.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 68 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
2 Steel reinforcement required to be bent will be bent cold in such a manner that the material is not
damaged in any way and in accordance with BS 8666 unless otherwise noted on the bar bending
schedules.
3 Bending will be carried out within a covered enclosure having a concrete floor.
5.13 Cover
1 The concrete cover will be stated on the design and shop drawings and will be measured from the
surface of structural, non-structural, spacer or any other steel items closest to the formwork.
2 Tolerance to cover will be as specified in the durability report and in the design.
3 No concrete will be poured if the required covers are not achieved throughout each area to be
concreted and the Contractor will rectify non-compliant cover prior to concreting.
4 All concrete surfaces are to be surveyed by the Contractor as soon as is practicable upon the removal of
formwork and actual cover readings recorded.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 69 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
5 The cover surveys are to be carried out using a calibrated electronic cover meter and the results will be
submitted in a format as agreed with the Engineer.
6 Remedial action plans will be prepared by the Contractor if this survey identifies deficiencies in the as-
built covers.
7 When the permanent works resume, and immediately prior to casting the new permanent concrete, the
protective system shall be cleaned of any salts (chlorides and sulphates) and any debris, oils or other
substances which may affect the bond with the new concrete. This treatment and surface preparation
shall be as per any relevant instructions in the manufacturer’s information sheets, to receive the
permanent concrete with adequate bond to the coating system. The treatment shall include roughening
of the surface of the coating system.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 70 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
6 Precast Concrete
6.1 General
1 The Contractor will submit the Shop drawings of the precast girders for the approval of the Engineer
before the start of work.
2 Any fabrication by the Contractor without written permission from the Engineer will be at the
Contractor's risk.
3 Any members not fabricated in accordance with accepted shop drawings will be rejected by the
Engineer.
6.2 Moulds
1 The sides and soffits of the moulds for precast concrete will be strongly constructed, closely jointed and
perfectly smooth, and will be so designed by the Contractor that they can be taken apart and
reassembled readily.
2 They will be accurately dimensioned and will retain their shape both in line and dimensions during pre-
casting.
3 Moulds will be capable of developing required pre-camber along the length of the precast elements.
4 The bottom surface of girders at the bearing areas will be in a true level plane, which does not vary by
more than 2 mm from a true straight edge placed in any direction across the bearing area.
5 Joints are to be caulked where necessary to prevent leakage of “fines” from the mix.
6 The moulds are to be strongly stayed on the outside to prevent bulging or distortion during the
compaction of the concrete.
7 For reinforced concrete members, a length tolerance of + 3mm will be permitted in 6 meters with an
overall tolerance of not more than +10mm in the total length of any unit.
8 For all prestressed members the length, cross-section dimensions and straightness of precast concrete
will be measured at 28 +/- 2 days after casting or as otherwise agreed with the Engineer.
9 Unless otherwise stated, allowable dimensional variations will not exceed the values in Table 12.
Table 12: Dimensional Tolerances on Precast Units
Length Variation
Up to 3m + 6mm
3 to 4.5m + 9mm
4.5 to 6m + 12mm
6m to 24m + 18mm
Above 24m +25mm
Cross Section (each direction) Variation
Up to 500mm + 6mm
500 to 750mm + 9mm
Greater than 750mm Not greater than 12mm
Bow (Deviation from intended line) Variation
Up to 3m + 6mm
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 71 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
Length Variation
3 to 6m + 9mm
6 to 12m + 12mm
12 to 18m + 18mm
Above 18m +25mm
6.3 Casting
1 Precast units will be cast in one complete operation.
6.4 Marking
1 All precast units will have impressed upon them in a convenient and conspicuous position, the date of
manufacture and such distinguishing letters or numbers.
2 Marking will not be done on exposed faces.
3 As-built records will clearly identify the location of each uniquely identified precast unit. The marking
should be cross referenced with the required cylinder tests for traceability as part of QC requirement.
6.5 Curing
1 All precast units will be cured in accordance with the requirements for severe exposure concrete.
2 Steam curing may be used in factory conditions subject to the results of trials to confirm no detrimental
effect to the concrete.
3 The curing methods and duration will be determined from durability study.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 72 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 73 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
4 The shop drawings will also show, in addition to the tendons and strands, the placement, sizes, and
details of the reinforcement steel as called for in the post-tensioned concrete work.
5 Shop drawings will be prepared showing formwork and method and types of bracing.
6 Shop drawings will be submitted at least 4 weeks in advance of the start of the affected work.
7 All shop drawings, computations and related data will be accompanied by design data indicating that the
forces indicated on the design drawings are obtainable and that all post-tensioning hardware is
adequate to transmit these forces.
8 Any fabrication by the Contractor without written permission from the Engineer will be at the
Contractor's risk.
9 Any members not fabricated in accordance with accepted shop drawings will be rejected by the
Engineer.
7.4 Materials
7.4.1 Pre-stressing Steel and Anchorages
1 Strands will be uncoated seven wire strands complying with the requirements of AASHTO M203 (ASTM
A416) Supplement S1 (low relaxation) or Stress relived seven wire low relaxation super stabilised strands
complying with BS 5896 or to meet the local authority requirements or as shown on the detailed design
drawings.
2 Pre-stressing strand, however manufactured, will be in coils of sufficiently large diameter to ensure that
the strand pays off straight.
3 Prior to shipment of the strands from the manufacturer's plant, the Contractor will submit for
acceptance by the Engineer, typical stress-strain curves obtained from the mill (or accepted independent
laboratory) test performance on the strands proposed for use.
7.4.3 Bars
1 Bars will be uncoated high strength bars complying with the requirements of AASHTO M275 (ASTM
A722).
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 74 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
2 Bars with greater minimum ultimate strength, but otherwise produced and tested in accordance with
AASHTO M275 (ASTM A722) may be used provided they have no properties making them less
satisfactory than the specified material.
3 Pre-stressing bars as delivered will be straight.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 75 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
7.4.9 Ducts
1 Duct will be of ferrous metal sheaths, mortar-tight cast into the girders and will be hot dip galvanized.
2 The system of ducts, duct connectors, grouting connections, vents, vent connectors, drains, transition to
anchorages and caps for anchors will form a complete encapsulation for the tendon which is resistant to
ingress of air and water.
3 Ducts will be of proven corrosion resistant durable material.
4 Ducts will be tested to BS EN 523-Table 2, Section 8.3 and BS EN 524 of minimum thickness 0.4mm.
5 The system will be fully compatible with the pre-stressing anchorages, couplers and other details.
6 Where ducts are non-conductive, metal parts of the anchorages will be electrically bonded to the
adjacent reinforcement at each end of the tendon and electrical continuity of the structure over the
length of the tendon will be confirmed by testing.
7 Polyethylene duct will not be used when the radius of curvature of the tendon is less than 9 metres.
8 Rigid polyethylene ducts for use where the tendon is not embedded in concrete will be rigid pipe
manufactured in accordance with ASTM D2447, ASTM F714, ASTM D2239, or ASTM D30. For external
applications, such duct will have an external diameter to wall thickness ratio of 21 or less.
9 For applications where polyethylene duct is exposed to sunlight or ultraviolet light, carbon black will be
incorporated into the polyethylene pipe resin in such amount to provide resistance to ultraviolet
degradation in accordance with ASTM D1248.
10 Where sheaths are used the number of joints will be kept to a practicable minimum and each joint
adequately sealed against the ingress of any material.
11 Joints in adjacent sheaths will be staggered by at least 300mm.
12 Sheaths will be kept free of any matter detrimental to the bond between the sheath and the grout and,
except for material sealing a sheath joint, between the sheath and the concrete.
13 The nominal thickness of duct strip shall be 0.45mm. PT ducts shall be in accordance BS EN 523 and BS
EN 524. Primary production tests are dimensions, to-and-fro bending and leak tightness test.
14 Ducts shall be tested to Determination of lateral load resistance (BS EN 524), Determination of Tensile
load resistance (BS EN -524), Determination of flexural behaviour of steel strips sheets (BS EN 524)
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 76 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 77 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 78 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
2 The total number of strands in an individual tendon may be pulled into the duct as a unit, or the
individual strand may be pulled or pushed through the duct.
3 Anchorage devices or block-out templates for anchorages shall be set and held so that their axis
coincides with the axis of the tendon and anchorplates are normal in all directions to the tendon.
7.6 Tensioning
7.6.1 General Tensioning Requirements
1 Pre-stressing steel will be tensioned by hydraulic jacks so as to produce the forces shown on the detailed
design drawings with appropriate allowances for all losses.
2 For post-tensioned work the losses will also include the anchor set loss appropriate for the anchorage
system employed.
3 The Contractor will submit to the Engineer for review complete details of the method, materials and
equipment he proposes to use in the post-tensioning operations, including any additions or
rearrangement of reinforcement steel from that indicated on the Drawings.
4 Such details will outline the method and sequence of stressing and will include complete specifications
and details of the post-tensioning steel and anchoring devices, working stresses, anchoring stresses, type
of ducts, and all other data pertaining to the post-tensioning operation.
5 Tendons/strands are to be stressed to a jacking load as per AASHTO LRFD requirements of the tendon
ultimate tensile strength, f’s (AASHTO LRFD table 5.9.3-1).
6 The Contractor will provide the jacking stresses values before and after seating as noted in AASHTO
LFRD, Article 5.9.3., as an easy reference for the future construction team at site.
7 The calibration of all the jacking and pressure gauges equipment will be within 6 months, prior to
stressing work commencement.
8 All strands in each tendon, except for those in flat ducts with not more than four strands, shall be
stressed simultaneously with a multi-strand jack.
9 Post-tensioning grout shall meet the grout physical properties stated in Section 10.9 - AASHTO LRFD
Bridge Construction specifications
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 79 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 80 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
Class Cement: lime: sand Masonry cement: sand Cement: sand with plasticizer
5 Mortar will be mixed thoroughly by mechanical means until its colour and consistency are uniform.
6 The constituent materials will be accurately gauged, allowance being made for bulking of sand.
7 Mortar will be made in small quantities only as and when required.
8 Mortar which has begun to set or which has been mixed for a period of more than ½ hour in the case of
a Class I mortar or more than 1 hour in the case of other classes will be discarded.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 81 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 82 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
10 For resinous bedding mortars the substrate will be dry, free from loose dirt and dust and will meet the
conditions specified by the manufacturer.
11 The underside of the base plate will be clean and free from loose rust and loose mill scale at the time of
bedding.
12 No internal metal shims will be allowed to remain in the hardened bedding mortar except where
permitted by the Engineer.
13 The Contractor will submit his proposals for shims for approval by the Engineer.
14 The Contractor will submit a Method Statement detailing the grouting procedures to the Engineer for
review and approval prior to commencement of the works.
8.5 Testing
1 Mortar will not be used in the Works until it has been approved by the Engineer.
2 Every batch of mortar to be used in the Works will be tested by the Contractor.
3 Testing will include flow, compression, expansion, and water absorption and elasticity tests and will be
subject to the approval of the Engineer.
4 No mortar will be incorporated into the Works without written approval by the Engineer.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 83 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
9.2 Properties
The system will, during trials, display the properties in Table 15 when applied in accordance with the
manufacturer’s specification to samples obtained from concrete made without additives.
Table 15: Properties for Coating Effectiveness
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 84 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
Carbon Dioxide Diffusion Resistance Method of testing will be Equivalent to 500mm of 30 N/mm2 concrete
subject to acceptance of Engineer
Reduction in Water Absorption (measured against a control 82% minimum at 28 days when tested at a water cement
concrete sample in accordance with ASTM C642) ratio < 0.50
Adhesion after exposure to salinated fog (NFT 30 062) Minimum 1.0 MPa
Resistance to humidity and heat (NFT 30 802) No loss of adhesion, no cracking, no bubbling, no change
in colour, no dust.
9.3 Primer
The primer shall be a low viscosity reactive silane-siloxane/acrylic blend dissolved in a penetrating organic
carrier. The primer shall have the capability to penetrate and produce a chemically bound hydrophobic barrier
to prevent the passage of chloride and sulphate ions. The primer should also be film forming to condition and
stabilize the substrate prior to the application of the topcoat. The primer should be applied in full accordance
with the manufacturer’s instructions.
9.4 Topcoat
The topcoat shall be a pure aliphatic acrylic resin, decorative, high performance water based, pigmented
coating. It shall have resistance to water, carbon dioxide and other air-born acids and have the ability to allow
the passage of water vapour from within the structure.
The topcoat shall have elastomeric and flexural capabilities and should be applied in strict accordance with
the manufacturer’s instruction.
The system will, during trials, display the following properties when applied in accordance with the
manufacturer's specification to samples obtained from concrete made without additives.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 85 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
4 The Contractor will at his own expense surface coat as many panels as required by the Engineer until a
trial panel has been accepted by the Engineer as satisfactory.
5 The coated panel, when accepted will form the standard against which the corresponding coating in the
works will be judged.
6 No application of the coating in the works will be undertaken until trials have been completed to the
Engineer’s satisfaction.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 86 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
10 Structural Steelwork
10.1 General
1 The Works under this section will be done according to the provisions of the Contract, these
Specifications and Design Criteria; and as shown on the design and shop drawings prepared by the
Contractor.
2 This section is to cover the fabrication of steel members.
3 Before beginning to erect any steel structure, the Contractor will submit to the Engineer for review and
approval for the erection Plan and procedure describing the methods the Contractor intends to use.
10.2 Steelwork
1. Structural steelwork will comply with the requirements specified in the design prepared by the Contractor.
2. The steelwork Contractor is responsible for checking the design of the steel structure, including
connections, for temporary forces which may arise during the erection process and prior to completion of
the permanent structure.
10.4.2 Steelwork
1 Weathering Steel Grade 50W (ASTM A709) has been specified for primary steel members.
2 For other elements, Grade 50 for corrosion-resisting structural steel shapes, plates, and bars as per
ASTM A588/ A588M, if required, may be used.
3 Mill/Manufacturer’s Test Certificate of the following materials shall be produced as specified in Section
10.10.2;
a) Plates and rolled sections
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 87 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
b) Welding consumables
c) Bolts, nut, and washer with mechanical and chemical properties
d) Shear stud connectors
e) Corrosion protection coating materials
10.5 Fasteners
1 All bolts for field splices shall be high-strength friction grip bolts with Associated nuts and washers in
according to ASTM A325/A325M Type 3 or ASTM A490/A490M Type 3 (weathering steel).
2 Nuts (for ASTM A325 and A490 bolts) shall confirm to the requirements of ASTM A563M.
3 Washer shall conform to the standard specification for hardened steel washer AASHTO M293M.
4 HSFG bolts, nuts and Washers will be supplied as per AREMA Chapter 15.
5 The splices shall be checked as slip-critical per AASHTO LRFD 6.13.2.1.1. The contact Surfaces (faying
surface) of the bolted parts are assumed to be CLASS B according to AASHTO 6.13.2.8 and Section 1.4;
Table 15.1.11a of AREMA Chapter 15.
6 Corrosion protection for the slip critical CLASS B according to AASHTO 6.13.2.8 and Section 1.4; Table
15.1.11a of AREMA Chapter 15 shall be proposed by contractor and will be used after approval from
Engineer.
7 Field splices are as per contractor’s requirements.
8 Bolt threads are excluded from the shear plane.
The orientation of bolted splices is to be perpendicular to the top flange except where specific splice geometry
has been shown on the drawings.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 88 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
1 Plates and Rolled 3.1 ASTM A 709 Gr50WF Type A/B/C, Z3, - Mechanical
Sections and Chemical properties.
ASTM A6 – Dimension Tolerance
ASTM A 578 Level B – Ultrasonic Testing
7.1 Weld Visual Inspection 3.4, Visual Weld Defects as per AWS D1.5 Clause 5.6 and
Clause 8 .26.1
Fillet Weld Size AWS D 1.5 Table 4.1 and Table 9.2
7.3 Magnetic Particle Test 3.6, 3.7 AWS D1.5 Clause 8.26.2
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 89 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
10.8 Welding
1 Welding of steelwork will be in compliance with AWS D1.5.
2 All welding will be 100% visual inspected.
3 All butt welds will be Radiographic Test (RT) inspected 100% after stress relieving, subject to Engineers
approval.
4 All fillet welds will be Magnetic Particle Index (MPI) inspected 100%.
5 All bearing stiffener will be Ultra sonic Testing (UT) tested 100%.
6 Weld Electrode specification should conform to AASHTO/ AWS D1.5.
7 All welds shall be on Clean steel. Ensure to remove all coatings, galvanizing, grease, scale, rust, and other
foreign matters in location of weld. Detailing of connections, welding sequences , preheat and inter-pass
temperature method shall be such as to minimize restraint and accumulation and concentration of
through thickness strain due to weld shrinkage.
8 All welded joints visible to be Grind Flush with edge of plates. If the Welding found to be defective,
remedial measures shall be agreed with contractor, engineer, and testing agency before proceeding.
Ensure not to deform the weld while dressing.
10.9 Holing
1 Holes for bolts will be drilled or punched and not gas cut.
2 Bolt locations will be as shown on the design drawings or amended as accepted by the designer in
writing.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 90 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
10.10 Submittals
10.10.1 Drawings
1 Shop-drawings
i. Shop drawings shall be prepared under supervision of qualified professional Engineer and should
include complete details and schedules of fabrication, connection design and assembly of
structural steel members, Joint Geometry, procedures, and diagrams.
ii. Shop Drawings shall show fabrication of structural steel components and shall include the
following:
Detailed construction drawings, along with calculations of connections and temporary works only for
review and approval.
Details of cuts, connections, splices, camber, holes, and other pertinent data.
Include embedment drawings if any.
Indicate welds by standard symbols, distinguishing between shop and field welds, and show size,
length, and type of each weld.
Indicate type, size, and length of bolts, distinguishing between shop and field bolts. Identify
pretensioned and slip-critical high-strength bolted connections.
iii. For structural-steel connections indicated to comply with design loads, include structural
analysis data prepared, signed, and sealed by the qualified professional engineer responsible for
their preparation
iv. Drawings are to be fully coordinated against architectural and MEP drawings to show all
interfaces with the structural steel.
2 Erection Scheme drawings Including Temporary Structure Drawings if any.
3 Red Line Mark-up Drawings
4 As built Drawings
5 Weld Test Plan Drawings
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 91 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
i. Copies of Manufacturer’s test certificates will be in accordance with ASTM A325 Type 3, showing
Chemical Analysis and Physical tests prior to commencement of fabrication.
ii. List of Fasteners along with Manufacturer Credentials.
iii. ITP for Fasteners
10.10.6 Fabrication
1. Inform the Engineer when fabrication is due to start. Do not fabricate steelwork for which the drawings
have not been commented by the Engineer.
2. Before fabricating, ensure that surface condition of steel which is to be coated complies with the
requirements for cleaning given in this Specification.
3. Ensure that fabrication processes do not cause changes in properties of materials resulting in noncompliance
with specified requirements.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 92 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 93 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
16 The Fireproof Coating shall be in accordance with Association for Specialist Fire Protection, ASFP _
Technical Guidance Document – TGD-11.
11.2.4Equipment Requirements
Suitable oil, water and air filtration equipment shall be installed between the air compressor and the blasting
equipment to ensure no contamination occurs.
11.2.5Metal Defects
Any weld spatter, rough weld caps, sharp edges or other metal defects exposed after surface preparation on
all surfaces shall be removed.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 94 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
11.3.2Application Conditions
Coatings shall not be applied under the following conditions for external works.
• When the ambient temperature falls below 5°C, when steel temperature falls below 5°C or the relative
humidity rises above 85%.
• When the ambient temperature is less than 3°C above the dew point.
• When the steel or ambient temperatures are above the temperature recommended by paint
manufacturer.
• When rain, snow, fog, or mist could affect the work area
• In a dust laden atmosphere
• When the amount of moisture likely to be deposited on the surface by condensation or rain immediately
before and after coating, may have a harmful effect on the coating.
• When wind-borne dust may have a harmful effect on the coating.
Every effort shall be made to maintain the conditions above throughout the coating system application.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 95 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
11.3.3Coating Application
1 All components of the coating materials shall be prepared in strict accordance with the coating
manufacturer’s printed requirements.
2 Mixing equipment shall be clean and dry and not contaminate the coating material in any way. No
mixed coating material shall be used beyond its specified pot life or when it is clearly thickening.
3 Prior to use, the base component of 2-pack materials shall be thoroughly mixed using a slow rotating
power mixer before the hardener is added. The hardener shall be added with constant slow rotating
mixer recommended by the coating supplier and the composite mixed until homogeneous.
4 Application can be by brush, roller or spray, as recommended by paint manufacturer.
5 All coats shall be applied without thinning unless recommended by the paint manufacturer and
approved by the Engineer.
6 Coatings shall only be applied to clean, dry surfaces that have been prepared to and meet the
requirements of this Specification unless otherwise agreed by the Engineer. A new coat shall not be
applied over another coat that has any contamination present. Particular notice shall be taken to
ensure no coat is applied over another that is affected by amine bloom.
7 Wet film thickness gauges shall be used regularly to check adequate wet material is applied to
achieve the DFT.
8 Each coat, at whatever thickness applied, shall be free from surface defects, particularly cratering,
pin-holing, blistering, revelling, sagging, bittiness, and cissing.
9 The finished system shall be of an even and uniform appearance.
10 The minimum and maximum over-coating times recommended by the coating manufacturer shall be
complied with and will be temperature dependent.
11 As per AREMA Chapter 15, Page 15-8-37, DFT Shal be measured as per SSPC PA2
12 All gauges shall be calibrated before use, the Engineer shall be provided with calibration records.
Any newly applied coating that is damaged shall be fully re-instated in accordance with this
Specification.
11.3.4Stripe coats
The Contractor shall brush apply an additional stripe coat of at least one high build coat to all angles, welds,
edges, Fasteners and all areas that are difficult to coat
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 96 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
manufacturer’s recommendation in accordance with SSPC Paint and ISO 12944 meeting the
requirements of Research Council on Structural Connections (RCSC) Class B, Appendix A (Slip
coefficient and resistance to tension creep) or unsealed pure zinc or 85/15zinc/aluminium thermal-
sprayed coatings with a thickness less than or equal to 16 mils as per AASHTO LRFD CL 6.13.2.8, to
achieve Slip Coefficient 0.5 as per Section 1.4; Table 15.1.11a of AREMA Chapter 15.
2 The splices shall be checked as slip-critical per AASHTO LRFD 6.13.2.1.1. The contact Surfaces (faying
surface) of the bolted parts are assumed to be CLASS B according to AASHTO 6.13.2.8.
3 Contractor shall propose the Painting system to achieve Class B slip Factor to Engineer for review
and approval before use.
4 The Faying surface under the bolt head, Nut and Washer in contact with steel plate shall be same as
per Clause 3.4.1.1
5 HSFG Bolts, Nuts and Washers shall be supplied in Black condition without any coating.
6 Surface Preparation for Faying surface: unpainted blast-cleaned surfaces to SSPC-SP 6 or better
11.4.2Welded joints
1 The Contractor shall ensure that areas within 200mm of known site welds shall not be painted until
all welding and testing is completed. Where this is not practicable the Contractor shall ensure that
the paint coat is removed by grinding and each coat is stepped back to enable preparation of fusion
faces for welding.
2 Welds and surfaces which have been affected by welding shall receive the preparation and
protective systems which are applied to the parent surfaces.
3 The joints having been made and passed inspection, the parent and joint materials, exposed parts of
bolts, nuts and washers, weld and weld affected areas shall be prepared and painted.
4 All bolted joints shall be sealed against the ingress of moisture. Before painting commences gaps at
joints shall be plugged with approved filler. The perimeter of all joints shall be sealed with
subsequent coats of paint.
11.5 Inspection
1 The Contractor shall be responsible for carrying out all inspection and quality control testing in
accordance with this Specification and Approved Inspection and Test Plan. Personnel undertaking
inspection and quality control testing shall be suitably trained and hold applicable and current
certification. Certification to Level II under the Institute of Corrosion Scheme or equivalent is
required.
2 Inspection and quality control activities shall be adequate to ensure all surfaces are prepared and all
coatings applied to comply with this Specification and the Coating Manufacturer’s
recommendations.
3 Inspection and quality control activities shall include but not be limited to:
a) Surface preparation including surface profile amplitude measurement
b) Mixing of coatings
c) Application of coatings
d) Monitoring of ambient conditions
e) Appearance and DFT of applied cured coatings
f) Recording of batch numbers of materials used
g) Recording of results of inspections and monitoring
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 97 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
h) Adhesion Test for Pull Off Strength of Coatings using portable Adhesion Testers on sample
panels.
4 All site records will be kept in legible hard copy format and shall be computerised daily and available
for review by the Engineer.
5 The Contractor shall permit coating manufacturers to inspect the work in progress, including surface
preparation, and to take samples of their products if required. The Contractor shall not comply with
any directions or requests given by the coating manufacturer's representative unless and until
confirmed in writing by the Engineer.
6 The Contractor shall notify the Engineer of projected dates for start of surface preparation and
coating.
11.6 Protection
1 The Contractor shall protect freshly applied surface coatings from damage. Protect surfaces adjacent
to those being prepared and coated.
2 Stack coated components clear of the ground, separated by timber chocks, and so that ponding does
not occur.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 98 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
12.3 Water-stops
1 Proprietary water-stops/ water bars used at construction joints and for compartments (except
movement joints) shall be compatible with the waterproofing membrane and with the sizes of the
structural elements.
2 Proprietary water-stop for movement joints shall be extruded from high grade PVC compound and shall
be having pre-punched holes for fixing with a torturous water path design.
3 The water stop shall be chemically resistant against water, sea water, alkalis, mineral oil and sewage
conditions
4 Flat Dumbbell plain web water stop shall be used for a Construction joint while for an Expansion joint or
a Contraction joint, a centre bulb water stop shall be used. The width of the water stop shall depend
upon the concrete thickness, the aggregate size, and the position of the reinforcement. In general, the
following shall be taken as a guide to select the width, w of a water stops.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 99 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
1. The water bars shall withstand the water head indicated in the construction documents or permanent
site conditions. Unless noted otherwise, the water bar shall be able to accommodate 20mm expansion
and 10mm shear movement.
2. Water stops shall be placed centrally as a water barrier across the designated joint in in-situ concrete
structures and cast centrally into the edges of adjacent concrete components.
3. The requirement of a water stop shall be indicated in the drawing
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 100 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
Chemical Resistance to dilute acids, to To the levels expected in the most Resistant
dilute alkalis, to sulphates, to chlorides aggressive areas of the Middle East
6 The properties of the waterproofing membrane will not significantly diminish with age.
7 The provision of test data and/or evidence of successful performance of the membrane in climatic
conditions similar to the UAE will be a condition of approval of any waterproofing system.
8 The foundation types in the structures generally consist of pile caps, piles, retaining walls and bridge
abutment. Preparation of concrete surfaces to receive the membrane and method of application of
waterproofing membrane shall be in accordance with the membrane manufacturer's instructions and
requirements.
9 The waterproofing membrane will start 2m below the ground covering part of the pile up to 0.15m
above the ground level. Exposed part of the pier 3m above the finished ground shall be protected with a
liquid waterproofing membrane.
10 The waterproofing system for pile caps and piers can be either loose laid or fully bonded system. Pre-
applied integrally bonded sheet waterproofing membrane, when applied, will be installed above the
blinding concrete which will bond to the underside the pile cap once the concrete is poured, creating an
integral waterproofing system that will prevent water migration. When using loosely laid PVC/HDPE
membrane, the horizontal surface of membrane shall be covered with minimum 50 mm thick concrete
screed. The pile head shall be sealed with solvent free non-shrink epoxy grout
11 Waterproofing for abutment and retaining wall structures is similar to the pile cap, either loose laid or
fully bonded systems. Pre-applied integrally bonded sheet waterproofing membrane, when applied, will
be installed above the blinding concrete which will bond to the bottom of the foundation or base slab.
Post-applied self-adhesive sheet membrane will be applied on the sides and top of the foundation and
wall up to 0.15m above the ground level. Part of the wall 3m above the finished ground will be applied
with liquid waterproofing membrane on all the exposed sides.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 101 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
2 All materials will have a valid Agreement Certificate for Road and Bridge Structures approved by a
member of the UEATC.
3 Waterproofing for bridge decks will be one or two coat, rapid curing and liquid spray applied.
4 Sufficient time will be allowed for the first part to adequately cure prior to the application of the second
coat.
5 The finished membrane will be free of pinholes.
6 Adhesion between the membrane and the concrete will be at least 1.5 MPa average.
7 The membrane will have good flexibility and be able to bridge live cracks of up to 3mm.
8 The membrane will be resistant to water and chloride ion penetration, embrittlement, abrasion, UV
degradations, pedestrian traffic, indentation by hot or cold aggregates and the effect of placing asphalt.
9 It will be protected by a durable board of other protective layer if otherwise it would be in direct contact
with ballast or other unbound aggregate or rock.
10 The membrane will easily accommodate the need for day joints and patch repairs as result of testing for
adhesion or coating thickness.
11 The membrane will comply with the requirements in Table 17.
Table 17: Additional Requirements for Waterproofing Membranes
Adhesion to Concrete Elcometer Test (minimum 3 per 500 m2) 1.5 MPa average
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 102 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
Blisters None
Note: The above properties will also apply for small areas of patch repair that may be required.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 103 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
iii. Quality risks before and after laying the membrane, risk response and risk prevention plans.
iv. Maintaining a register of daily checks for the newly laid membrane from membrane laying stage
until it is covered permanently with concrete/ backfill.
v. Procedure for tests at completion and at switching off dewatering where applicable.
vi. Procedure for maintaining as-built markups for all the works before they are covered or buried.
2. The Contractor shall be responsible for preparing the Method Statement with input from waterproofing
applicator/ sub-contractor. The Method Statement shall be validated by the waterproofing system
manufacturer and applicator before submission.
3. List of QA/QC forms and documents including risk analysis, checklists, and inspection and testing plans
(ITP’s).
4. Shop Drawings
1. Contractor shall be responsible for preparing detailed coordinated general arrangement plans, sections,
and elevations for all construction elements.
2. Waterproofing sub-contractor shall be responsible for marking up all the waterproofing elements in the
project drawings and also preparing as-build drawings.
3. All shop drawings shall be stamped and signed by the waterproofing system manufacturer to confirm
that the details shown on the shop drawings are correct and appropriate to provide a watertight barrier
for the duration of the warranty period as a minimum.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 104 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
13 Bridge Bearings
13.1 General
1 Bearings for Bridge Works will be in accordance with the requirements of AREMA for Rail Structures or
AASHTO for Over-Bridges.
2 The design of the bearing will be carried out by the specialist manufacturer of the bearings.
3 The Contractor will submit at least 4 weeks prior to work commencement detailed design calculations,
shop drawings, method of statement for the work, maintenance, replacement schemes etc. Materials
Test Reports (MTR) will be included in the submittals item.
4 Refer to C0306-S02-ECB-FS-30001-Bearing Specification Rail Bridges and C0306-S02-ECB-FS-30002-
Bearing Specification Road Bridges
5 For overbridges PTFE or equivalent material shall be used wherever is required, as per RTA requirements
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 105 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
14 Finishes to Structures
14.1 General
SECTION INCLUDES
A. Flush Aluminum Access Doors.
B. Aluminum panels.
14.2 Compliance
A. Local Code: Applicable Dubai laws, ordinances, codes, rules and regulations
B. Comply with the applicable requirements of NFPA 101, 130 and 255 relating to this section
14.3 References
A. AAMA 611 - Anodized Architectural Standards.
B. ASTM B 209 - Standard Specification for Aluminum and Aluminum-Alloy Sheet and Plate.
14.4 Materials
1. Stainless steel grade 316
2. Structural steel BS 4
3. Galvanized steel BS EN 10142
4. Aluminum: ASTM B 308
5. Glass: floated toughened glass
6. Brass
7. Bolts: ASTM A 307, A 325, A 345.
8. Grout: non shrink cementatious grouts premixed ready for use requiring addition of water
only, setting time 15 to 30 minutes, developing not less than 25 N/mm². Compressive
strength after one day and expansion of up to 1% to overcome plastic settlement in the unset
material.
9. Paint: epoxy polyurethane or powder organic coating to BS 6496.
10. Primer: Zinc epoxy, suitable for application to items embedded in concrete.
11. Gaskets, weather resistant neoprene.
14.5 Submittals
A. Product Data: Manufacturer's data sheets on each product to be used, including:
1. Fabrication methods, finish and accessories.
2. Preparation instructions and recommendations.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 106 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 107 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
D. Protect materials and finish from damage during handling and installation.
14.8 Sequencing
Ensure that templates and other information required for installation of products of this section are
furnished to affected trades in time to prevent interruption of construction progress.
14.10 Warranty
A. Manufacturer: Provide manufacturer's 5-year warranty against defects in workmanship and materials,
including warping, rotting, paint chipping, decaying or bowing.
B. Installer: Warrant installation procedures and performance for five years against defects due to
workmanship and materials handling.
14.11 Manufacturers
A. Acceptable Manufacturer: Aluminum Doors in the Emirates of the construction phase.
B. Substitutions: Not permitted.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 108 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
14.13 Execution
1 EXAMINATION
A. Do not begin installation until substrates have been properly prepared.
B. Verify that wall surfaces and openings sub-frames are ready to receive frames and are within
tolerances specified.
2 PREPARATION
A. Clean surfaces thoroughly prior to installation.
B. Prepare surfaces using the methods recommended by the manufacturer for achieving
the best result for the substrate under the project conditions.
3 CLEANING
A. Upon completion of installation, thoroughly clean door and frame surfaces in accordance with
AAMA 609.
B. Do not use abrasive, caustic, or acid cleaning agents.
4 PROTECTION
A. Protect products of this section from damage caused by subsequent construction until substantial
completion.
B. Repair damaged or defective products to original specified condition in accordance with
manufacturer's recommendations.
C. Replace damaged or defective products that cannot be repaired to Engineer's acceptance.
5 SCHEDULES
A. Submit program aligned with the main project program
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 109 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
15.2 Joints
15.2.1 Joint Filler and Dowel Bars
1 Joint filler will consist of a compressive non-extruding resin-bonded cork or bitumen impregnated
corkboards.
2 The physical properties of the materials will conform to the requirements of ASTM D-1751.
3 The joint filler will be fully compatible with the surface sealants.
4 The provision of dowel bars through expansion joints will be approved by the
Engineer/Engineer.
5 Dowel bars at movement joints, approach slabs and bearing shelves will be galvanized steel or stainless
steel as shown on the detailed design drawings.
6 Surround to dowels include compressible material sleeves and aluminium slots will be as shown on the
detailed design drawings.
7 Dowel bars will be protected by plastic sleeve at the movement joints and approach slab connection.
8 Dowel bars shall be Grade Stainless steel Alloy 316 austenitic stainless-steel Designation 1.4436 and
strength grade 500 complying with the requirements of BS6744:2001.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 110 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
15.3.2 Materials
1 Proprietary bridge deck Expansion joints will be of an accepted type for each size required and will be
from an manufacture whose products have been proved to be highly satisfactory in similar works and
environmental conditions.
2 Elastomeric bridge deck joints will be provided with a minimum guaranteed service life of 15 years in the
prevailing climatic and loading conditions of the UAE and Gulf Countries.
3 Expansion joint fixings (anchor bolt, nut, washers etc.) should be stainless steel type-316 with a mill
finish confirming to ASTM A276
4 Materials to be used for the installation of expansion joint for bedding and transition strips shall be
recommended by expansion joint manufacturer
5 The joint will be designed to withstand an axle load of up to approximately 35t for Rail Structures and
10t for Over-Bridges.
6 Elastomeric bridge deck joints for Over-Bridges will be skid resistant.
7 The elastomer compound will have the following minimum physical properties as determined by the
following ASTM requirements shown in Table 18:
Table 18: Elastomer physical properties
Hardness D2240 55 5
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 111 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
8 All structural steel for use in the elastomeric expansion joints will conform to the requirements of ASTM
A245 or A36. Structural steel angles and anchors will be fabricated and hot dip galvanised in accordance
with ASTM A153.
9 Anchor bolts for joint seals will be hot dip galvanised in accordance with ASTM A153.
10 Expansion joint system shall be comprised of: 1.) a heat-weldable, thermoplastic-rubber, double-celled
or multi-celled, extrusion with perforated flanges and, 2.) manufacturer’s cold applied elastomeric
nosing.
11 Elastomeric nosing shall be a two-part polyurethane material (epoxies not permitted) mixed with
aggregate with sand particles not to exceed 30-mesh. Nosing material shall be pourable grade material
capable of encapsulating the perforated flanges in a single pour without the laying of a setting-bed or
tack coat. The material shall flow so as to fill voids or irregularities in concrete blockouts and beneath the
perforated flanges of the gland. Material shall cure to flexible (non-rigid) state. So as to ensure proper
mixing, flow ability, and consolidation, mixed nosing material shall have an aggregate loading ratio by
weight of liquid resin to aggregate not exceed 1:2.
12 System to be installed into blockouts on each side of the joint-gap prepared to the dimensions 20mm
deep x 100mm wide.
Final selection of the seal size to be coordinated between manufacturer, designer, and contractor(s) in
consideration of expected movements as a product of structural design and expected temperature
variations, taking into account as-built joint-gap sizes and temperatures at expected installation time.
Width of joint-gaps at time of casting or cutting to be adjusted, if necessary, from baseline temperature
used and specified by designer in determining system suitability.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 112 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
9 The contractor shall provide properly formed and prepared expansion joint openings constructed to the
exact dimensions and elevations shown on manufacturer’s standard system drawings or as shown on the
contract drawings.
10 The contractor shall clean the joint opening of all contaminants immediately prior to installation of
expansion joint system. Repair spalled, irregular or unsound joint surfaces using accepted industry
practices for repair of the substrates in question. Remove protruding roughness to ensure joint sides are
smooth. Refer to Manufacturers Installation Guide for detailed step-by-step instructions.
11 System to be installed by qualified sub-contractors only according to detailed published installation
procedures and/or in accordance with job-specific installation instructions of manufacturer’s field
technician
12 At locations in the bridge where deck drainage channel is to be continued from one deck to another and
not dropped, blockout-mounted, watertight, winged compression seal expansion joint systems to be
provided. The material to accommodate the movement and rotation of the deck and durable under the
live load and extreme weather conditions.
13 Protect the system and its components during construction. Subsequent damage to the expansion joint
system will be repaired. After work is complete, clean exposed surfaces with a suitable cleaner that will
not harm or attack the finish.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 113 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
W = Witness point: i) A work operation that is watched observed or visually examined by the Employer;
ii) The Contractor and the Employer must agree to witness points prior to the start of the work; iii) The
Contractor will notify the Employer in advance of the operation to ensure the Employer can attend the
required witness point.
H = Hold Point: i) A critical operation in which, by prior agreement, the Contractor will notify the Employer
a reasonable time in advance of the operation so that the item may be visually examined, tested or
measured by the Employer to verify conformance with the Contract requirements; ii) The Contractor may
not proceed with work beyond such hold points except by written agreement of the Employer.
R = Review point: i) Review of the Contractor’s Inspection and Testing records by the Employer for
correctness and completeness.
I = Inspection: Responsible for carrying out inspection or test; includes sampling for testing.
S = Surveillance point: i) ‘In process’ monitoring of the Contractor’s activities to the degree necessary for
confidence that the work process/method is in compliance with the established criteria.
MIR: MIR's follow the same process as ITR's and are attached to ITR for processing. Types of Records
to be attached to the MIR's are listed on the MIR form. Employer signs-off the MIR once
Material satisfied, but not any of the Contractors QC Checklists.
Inspection
Request
Employer check that all activities [up to that point, or since last ITR] have been carried out by
ITR:
Inspection the Contractor and that includes checking that the Contractor has filled-in all his QC Checklists
and Test Forms (to be attached to ITR upon submittal). Employer sign-off the ITR once satisfied, but not
Request
any of the Contractors QC Checklists.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 114 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 115 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
The Red-Marked drawings are sent by the Subcontractor to the Contractor’s Field Engineering Manager / Field
Engineer.
Construction supervisor, upon the verification of the compliance of the Red-Marked drawings with the site
conditions, will sign them as responsible for Contractor for the Red-Marked drawings correctness.
The numbers of copies of Red-Marked drawings to be transferred by the Subcontractor to the Contractor are
as per para 15.5.2.
17.3.2As-Built Drawings
Contractor will issue a number of copies of document of the As-built drawings to Engineer as defined at para
15.5.2.
The list of submittals of the As-built drawings will include all, Layouts, Plans, Sections, Alignment, Architectural
& Structural of below disciplines:
EAB Facilities & Building
ECB Structures-Bridges-Viaducts-stations
ECH Highways / Road
ELS Sand Mitigation
EQU Depot & Other Equipment
ERA Rail Alignment / Profile / Cross Section
ERT Track Work
ERS System (Comms / Sig / Radio / E&M / Etc.)
EUE Overhead Line/Traction Power
EUT Utilities
EWA Environmental Impact Assessment
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 116 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
Non-Conformity (NCR)
Incorporated materials
A competent party of Subcontractor (typically the engineering office) will report in the Master Copy all the
above-mentioned information.
Each modification done on a document must be easily traceable.
After implementing modifications to the documents, its modified part will be marked on drawings with the
revision number in a triangle alongside the clouded revision, with all revisions identified and described in a
revision block.
The Red-Marked drawings will be issued to Contractor by the Subcontractor:
Their correctness in respect to site conditions will be reviewed by the Construction supervisor;
Their presentation and their verification in terms of original IFC and shop drawings will be verified by the FEM
/ FE;
Their verification against DCR and FCR will be verified by the FEM / FE;
Their consistency against the NCR will be verified by the QA/QC.
Once the approval life cycle is completed and upon the Contractor acceptance, Subcontractor will issue to
Contractor Red Marked drawings as Rev AA of the As-Built drawings.
Red marked drawings are submitted for review to Engineer as a scan copy in PDF format uploaded and sent
via EPFM. The review process will generate additional “red marks” on the drawings that, once agreed and
clarified with the Contractor, will be uploaded in EPFM.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 117 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 118 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
18 Document Management
18.1 Numbering System
The As-built drawings will be uniquely numbered.
The document type will be changed from ‘DG - Drawing’ to ‘DB – As-built drawing’ retaining the same
document number.
Example: document number C0306-S02-ERA-DG-00001, after approval of As-built, will become C0306-S02-
ERA-DB-00001.
Revision number will be: (To be finalised)
AA for the red marked drawing
AB for the first issue of the as built
00 for the second and final issue of the as built
When required, As-Built drawing can be composed by different sheets.
Document different from drawings modified from the 00 revision will be delivered in the As Built final package
considering revision no 00 for record.
Red marked (rev AA) 2 (A1) 2 CD DGN + pdf 2 (A1) 1 CD DGN + pdf
The number of copies is intended to include also the copies that Engineer/ER will deliver to other stakeholders
as part of the final handover process.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 119 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
Hard copies and soft copies (H+S) must be stored for a minimum 10 years upon release of Final Take Over
certificates.
Once approved, full As Built hard copies must be delivered to the Head Office.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 120 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 121 OF 122
DCP3F – TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
END OF DOCUMENT
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 122 OF 122