P169698 LIG Annex4 Specifications - Jvari Mestia
P169698 LIG Annex4 Specifications - Jvari Mestia
P169698 LIG Annex4 Specifications - Jvari Mestia
2
4.3 ADSS cable Installation ......................................................................................................... 17
5 Placing / Resting Joint Closures, Ducts, and Optical Fiber (OF) Cables .............................. 19
3
11.1 General Requirements .......................................................................................................... 24
15.2 The Cable Raceway System must fulfill the following requirements: .................................... 37
4
1 Introduction
This document describes the technical norms and directives that have to be used during the
infrastructure building process.
Documents requested by the Employer described in this document, including (not only) data sheets,
schedules, certificates, reports of quality and origin, and so on, should be verified by the Engineer's
conclusion in the manner described by the agreement and only after that be presented to Open
Net.
All materials should be installed according to the installation instructions in this document.
Any deviation from any agreement/consent mentioned in this document, as well as from the
established route/technical requirements or infrastructure relocation, must be carried out in
accordance with the rules and procedures described in the contract.
The Contractor must meet the technical requirements of other infrastructure owners (the owner
of linear infrastructure such as roads, other utilities, etc.). If it is determined that minimum
requirements cannot be obtained during the project design or infrastructure construction phase,
the Contractor must agree on the corresponding change with representatives of the Employer and
the respective owners of the infrastructure.
On the construction site (at the access and aggregation points as well) Contractor must deploy a
special A3 banner with special informative text (see photo below) (the Employer will provide vector
format).
5
2 Underground Civil Works
2.1 Dimensions of Trenches
2.1.1 Standard Trench
1. The Contractor is responsible for performing all the required excavation/trenching works and must
provide all the tools/machines (equipment) required in order to perform such works.
2. Wherever possible, the route of the trench must be straight.
3. Along the road infrastructure with the asphalt or concrete surface, in case there is no sufficient
distance between a planned trench and road infrastructure, and there is the possibility of
damaging the road surface, works must be done with a special trenching machine (such as Walk-
Behind trenchers, Micro-trencher).
6
2.3 Backfilling
1. During the installation of the ducts, for the fill of the trench, it is permittable to use three types of
materials:
I. Sand bed material - sand or stone fully free soil.
II. Selected fill material - soil containing stones, not exceeding 10 mm diameter.
III. General fill material - soil containing stones, not exceeding 40 mm diameter.
2. Before installation of the duct(s), the bottom of the trench must be leveled and freed from stones;
3. A layer of sand bed at least 10 cm thickness for duct systems must be prepared (1st layer of sand
bed).
4. The Corresponding number of HDPE 40 mm duct(s) must be arranged on the 1st layer of the sand
bed.
5. The newly installed duct(s) must be covered and compacted by a 20 cm Sand bed material (2nd
layer of the sand bed).
6. After the 2nd layer of the sand bed, a warning tape must be arranged (at least 20 cm above the
ducts' surface).
7. After placing the 1st warning tape, the trench should be filled with 30 cm of Selected fill material.
8. After the layer of Selected fill material, the bottom side warning tape must be arranged.
9. After the Selected fill material, a 2nd warning tape must be installed (at least 30 cm above the 1st
warning tape and a maximum of 30 cm from ground level)
10. After placing the 2nd layer of warning tape, the trench should be fully filled with General fill
material.
11. During the filling of the trench, every layer must be compacted separately.
12. The Contractor is authorized to use the removed soil for backfilling purposes. During the
backfilling, the Contractor must follow the above-described requirements.
13. The Employer/Engineer reserves the right to control the trench-filling process selectively.
14. Ducts must be installed quickly and without delay; trenches and pits ready for duct laying must not
be kept open for more than 3 (three) days.
15. Only short trench sections with newly placed installations are allowed to remain open overnight.
7
16. For mandatory safety issues, the open trench section must be isolated with safety warning tape
and road safety signs throughout the whole section.
8
2.7 Warning Tape(s) and utility markers
2.7.1 Warning Tape
1. The warning tape must be made from PE or PP with additives and be 15 cm to 20 cm wide. It must
be
2. durable and yellow color.
3. On the warning tape must be written the following text in Georgian and English languages, in black
color letters, as shown in the Figure below (which will be provided by the Employer in vector format)
9
7. The design of the utility markers must be confirmed with the Employer. The design of the writing is
shown below (will be provided by the Employer in vector format):
10
7. The Contractor must state if there are any load limitations/installation constraints for their
provided manholes. The Contractor must indicate the dimensions of their available / offered
plastic manholes.
8. OPEN NET's logo, phone number, and address of the webpage on the lid of the manhole must be
factory-made, as it is shown in the picture below.
1. The bottom of the pits for plastic manholes must be leveled and freed of stones and must always
be prepared with a 10 cm thick layer of lean concrete of strength class ≥C8/10.
2. The adjustment of height and adaption of inclination of the plastic manhole to the actual paved
surface is achieved by customizable cover parts. The plastic manhole must be installed according
to the installation instructions provided by the manufacturer.
3. For purposes of hydro isolation (only in cases where groundwater is present), before putting sand
on concrete manholes, the outer layer of the manhole must be covered with bitumen (or other
relevant isolation material), and after the installation of the manhole, its inner layer must also be
covered with bitumen (or other relevant isolation material) for the hydro isolation purposes.
12
3.1.5 Duct Integrity Test
1. After completion of a segment, when ducts are jointed and terminated in manholes, the
Contractor is responsible for providing duct integrity tests (DIT).
2. The maximum allowable loss of air pressure is 30% in one hour.
3. Test reports should be generated and signed by the Engineer.
13
3.2.3 Materials
1. The Contractor must provide an HDPE duct that is also composed of Anti-oxidants and pigments.
The offered ducts and their supporting materials must be unaffected by water, oil, oxidizing
Agents, salinity, aggressive soil, sand, fungi, bacterial or electrolytic impacts, etc.
2. The Contractor must not use those materials that will adversely affect the long-term mechanical
strength of the HDPE.
3. For all quoted ducts and the supporting materials, the Contractor must provide datasheets/related
documents, along with the Engineer's conclusion that they meet the specified requirements.
4. The Contractor must offer ducts that must be homogeneous throughout; all surfaces must be
clean, smooth, and without any visible cracks, grooves, blisters, wrinkles, dents, beat marks, or
foreign inclusions.
5. The ends of the ducts must be free from sharp edges.
6. The ducts must have a two-layer construction.
7. The inner layer must be equipped with special grooves (see picture below).
8. The Contractor must provide a duct with an outer diameter of 40 mm in accordance with the
following table:
5. Due to technical purposes on certain sections (e.g., terrain, road crossing points, etc.), the
Contractor may change the installation height and depth of the pole in agreement with the
Employer.
6. During the design stage, the Contractor must plan an aerial cable route in a manner that minimizes
crossing the road and keeps the line of sight on the same side of the road. Frequent crossing of the
roads is not recommended and may not be allowed during the design approval by the Employer.
7. When calculating the distance between the poles, the Contractor, based on the climatic conditions
(including ice cover), terrain, and wind, should consider the recommendations and best practices
in the world. However, the maximum allowable distance between the poles is 40 meters.
8. The outer diameter of all types of poles must be at least 108 mm and the wall thickness of at least
4 mm.
9. The head of the pole must be welded hermetically.
16
10. Where required, the poles must be equipped with reflective strips. At least three reflective strips
should be installed on the pole between 50-90 cm above the level of the surface. The minimum
height of each strip must be at least 7 cm.
17
ADSS Cable Placement - Moving Reel Method with an Aerial Lift
2. In the moving reel or drive-off method, the cable is paid off the top of the cable reel carried by a
moving vehicle as it drives along the pole line. The cable is placed into a "J" hook or block fitting
bolted to the support structure for temporary support. This procedure continues as the cable reel
moves along the cable line until a "dead-end" pole is reached. A "dead-end" pole is either a start
or ending support or support in which the cable route is misaligned by 10° or more. At this point,
the cable is tensioned and terminated into "dead-end" fittings.
3. Sufficient slack must be provided at each splice point to enable the splice to be made and to
provide for any cable maintenance. This slack length shall equal the height of the cable on the
support structure plus the distance from the support structure to the location of the splice in its
vehicle or tent. In addition, at least 5 meters of fiber must be provided to make the splice. When
the splice has been completed, the splice closure shall be safely mounted on the support structure.
4. The excess cable shall be wrapped inside special storage frames or and mounted on the existing
cable near the splice closure.
5. When the cable has been placed and held by its support structures, it shall be tensioned to the
specified tension level for the cable size and weight and affixed to the dead-end structure. The
cable is then removed from each of its intermediate supports and transferred to the permanent
support, which will remain loose on the cable until the tensioning is completed.
18
Picture: Dead-End tension procedure and Supports kit
1. The Contractor is responsible for the placing/resting of joint closures (herein after closures), ducts,
and FO cables.
2. When arranging fiber optic infrastructure underground, the fiber optic cable and the closures must
be installed in manholes.
3. The excess lengths of Cables must be cut off, transported, and stored.
19
6.1 Service Specifications - Termination of Cables and Ducts
1. At Aggregation Points, the Contractor must terminate the FO cables and ducts, passing through
the wall ducts inside the Container/Box/Building, and terminate the FO cable on the Optical
Distribution Frame (ODF).
2. At Access Points, the Contractor must terminate and connect the FO cables to the outdoor ODF,
while the HDPE duct must be terminated at the pole and connected to the metal duct situated on
the pole intended for the ODF.
3. At the existing Connection point, the newly installed FO cable must be spliced to the existing FO
cable cores.
4. At the new Connection point, the FO cables must be terminated at fiber optic splice closure (for
future extension).
5. The Contractor shall carry out the construction of the inlet channel.
6. Prevent ingress of water and gas into the buildings and/or containers/boxes.
7. The material used/offered must be halogen-free and fire-resistant.
7 Pulling of FO Cables
7.1 Service Specifications – Pulling manually
1. Short-length cables (not longer than 100m) can be pulled in by hand into a duct using a cable grip,
but only up to 150N pulling forces.
2. Pushing cable by hand is not allowed.
20
8.1.1 Blowing-in of Optical Fiber Cables into HDPE Ducts
1. This method is suitable for placing optical fiber cables in HDPE ducts.
2. The standard delivery length must be blown in the ducts:
• in one direction,
• in one work step and
• at a maximum speed of 100 m/min
3. Before blowing the cable in the duct, the Contractor must do the Duct Integrity Tests (DIT).
4. During the Duct Integrity Tests, a 30% loss of air pressure in the duct during the one hour is
acceptable.
5. Installing more than one cable in a single pipe is prohibited.
21
f) providing traffic guiding bars, pointers, or rails and cones.
2. During the installation, the bending radius requirements of the fiber must be fulfilled.
a) The hinged feature of the trays must provide protection for the fiber as well as facilitate
easy access and identification. An extra length, for example, between 650 mm and 2050
mm of each fiber at either side of the splice must be able to be stored in each splice tray;
at least 10 re-splices must be possible.
b) The splice holder must be used for crimp splice protection.
c) The thickness of the Universal Mounting System must be 6 mm: 1 UMS (6 mm).
3. Organizer splicing tray, Single element -assembly
a) The tray must be designed appropriately for 12 fibers and take up 12 fusion splices
separately.
22
9.1.5 Cable Length Measurements As-Built
1. Cable length markings must be provided on the cable Fiber, and cable sheath length
measurements of the completely installed cables must be taken after each fusion of the cables.
These measurements must be included in the corresponding maps and diagrams.
23
9.1.13 Checks and Test Measurements during Cable Installation
1. The Contractor must perform OF tests during cable installation and must measure the level of the
optical signal.
2. The Contractor must perform bidirectional tests of attenuation at 1310nm and 1550nm and return
loss, verifying that the measured results coincide with the defined permissible ones.
3. If measurement results are unsatisfactory, the fault(s) must be identified and located using the
OTDR tool.
4. The individual fibers must be checked for continuity and for not being mixed up amongst each
other before the final closing of the closure.
5. Termination of fibers in cassettes at all ends (ODF, boxes) must follow the numbering/counting
sequence of the bundle/fiber color code, which has to be agreed upon with the Employer.
6. The Contractor must rectify any identified errors, irregularities, or faults during the rollout.
7. If the splice loss value indicated by the fusion splice equipment is ≤ 0.15 dB, the value is accepted,
and the splice point must be put into the respective place of the splice cassettes. If the splice loss
value is > 0.15 dB, the splice must be repeated (max. three times).
8. If the loss value still exceeds the permissible value, the fusion splice work must be stopped, and a
further course of action must be taken in order to improve the situation.
9. All the results must be recorded by the Contractor in the relevant project documentation and
handed over to the Employer.
10 Sealing of Ducts
10.1 General Conditions
The Contractor is responsible for the adequate sealing of all Ducts.
11 FO Cable Marking
11.1 General Requirements
1. All cables must have tags in cable vaults, manholes, and cable pulling boxes. Marker tags must be
resistant to environmental conditions such as light, water, acid, rodents, temperature, etc.
24
2. The cables must be marked with cable type, cable number, and similar additional information
relevant for easy cable identification. The Contractor is invited to propose a marking format.
3. All incoming and outgoing cables (including underground cables) of the sleeves must be marked.
4. The tags must be fixed in such a way that they can be easily identified.
5. The marking must withstand severe conditions of high humidity and temperature.
6. Their writing must be readable and durable and must not fade away even when being exposed to
ultraviolet sunlight.
7. The material must be resistant to aggressive concentrations of acid, gases, and base prevailing in
the air and soil.
8. The Contractor must provide marking tags and structure for the cables and fibers based on the
picture below and agree on it with the Employer.
Cable Fiber
OpenNet
Location/Rack
Location/ Rack
Point A Point A Number/ODF Number/
number/ODF Number
ODF Port Number
Location/Rack
Point B Closure Number Point B
Number/ODF Number/
ODF Port Number
652D/Number of Fibers
Length between points
Cable type and # in the Cable/Cable Full length of fiber
A and point B (Meters)
Number
9. The marking labels/tapes must be waterproof and in light color, marked with printed tape or metal
plate, and fastened to the cable with an appropriate clamp.
25
12 Characteristics and Composition of FO Cables
12.1 General requirements
1. During the rollout, different types of FO Cables will be used. As part of the response, the Contractor
must provide the specifications of the cables (and their naming conventions), that they will use for
the project.
1. According to the International Standard (e.g., ITU, ETSI), which describes the type and composition
by letters and numbers, the cable code for optical fiber underground outdoor and Aerial cables
must be used.
2. The cable coding for the Outdoor FO Cable is subject to approval by the Employer. The Employer
retains the right to request adjustments to the cable coding if required.
3. The single-mode Low Water Peak fiber utilized in the optical fiber cable must meet ITU
recommendation G.652. (Category D), "Characteristics of a single-mode optical fiber cable".
4. The Contractor's offered conventional OF fiber cable must meet the attributes of G.652.D, defined
in ITU-T Recommendation G.652.
5. For cables in ducts, the cable must be without Laminated Aluminum Polyethylene tapes.
6. The aerial cables must have at least 24 and not more than 48 fibers.
7. The underground cables must have at least 48 and not more than 144 fibers (excluding the line
segment going to the Access Point).
8. In case of full utilization of the existing fibers intended for any particular Access Point (excluding
the line segment going to the Access Point), a cable with more fibers should be used. In case when
144 fiber cores cable is fully utilized, the Contractor shall deploy the additional FO cable.
9. The cable must be suitable for external usage in ducts.
10. Optical fibers must be placed inside PC/PBT loose buffer tubes.
11. Each buffer tube must contain 12 fibers.
12. The optical fibers contained in a tube buffer (loose tube) must have a clearance between the fibers
and the inside of the container sufficient to allow for thermal expansions of the tube buffer without
constraining the fibers.
13. Each optical fiber must consist of a Germania-doped silica Fiber surrounded by a concentric glass
cladding.
14. The solid glass optical fibers must consist of a cylindrical Fiber and cladding covered by either an
ultraviolet-cured acrylate or other suitable coatings.
15. Each fiber must be continuous throughout its length.
16. The FO underground cable must have a double jacket and aramid yarn reinforcement.
17. The outer jacket must provide the cable with a tough, flexible, protective covering that can
withstand exposure to sunlight, atmosphere temperatures, and to stresses reasonably expected
in normal installation and service.
26
18. The fiber must be coated with an acrylate protective coating.
19. To prevent the ingress of water into the fiber and water migration, a suitable filling compound or
water-blocking elements must be applied to the interior of the loose fiber tubes and into the
interstices of the fiber.
20. The normal temperature ranges for cables must meet the following requirements:
a) Operation -30 ºC to +70 ºC (-22 F to +158 F)
b) Storage and Shipping -40 ºC to +70 ºC (-40 F to +158 F)
c) Installation -10 ºC to +60 ºC (+14 F to +140 F)
21. The maximum tensile strength must be at least 2700 Newton (600 pound force) for short-term
pulling works and 601 Newton (135 pound force) for long-term.
22. The minimum bend radius must be:
• Minimal installation bending radius: 20 x OD
• Minimal operational bending radius: 10 x OD.
23. The Contractor must specify the minimum bending radius of their offered FO cables.
24. The cable must be designed and manufactured for a predicted operating lifetime of at least 20
years. In this context, the attenuation of the installed cable at the operating wavelength(s) must
not exceed values specified in this document and specified standards.
25. All the fibers in the cable must be of the same type and origin.
26. There must be no fiber splice in a delivery length.
27. It must be possible to identify each individual fiber throughout the length of the cable.
28. The sheath must be hermetic, without folds, cracks, blisters, or other defects, and reasonably
circular. The sheath must be well-fitted to avoid longitudinal water penetration.
29. Each fiber must be distinguishable by means of color coding in accordance with The ITU- T L.78
Standards, "Optical Fiber Cable Color Coding."
30. The central member must consist of a dielectric, glass-reinforced plastic (GRP)/Fiber-Reinforced
Plastic(FRP)). The purpose of the central member is to provide tensile strength and prevent
buckling. The central member must be over-coated with thermoplastic when required.
31. Loose tubes containing fibers must be distinguishable by means of color coding in accordance with
The ITU-T L.78 Standards, "Optical Fiber Cable Color Coding" .
32. The nominal radial thickness of the sheath is defined as the average thickness during production.
However, the mean value must not be less than (90 %) of the nominal thickness.
33. The minimum thickness must not at any point be less than 85% of the nominal thickness of the
sheath. The thickness is determined by the method indicated in IEC 189-1 Para 2.2.1 and 2.2.3.
34. The cable diameter is determined by the method indicated in IEC 189-1 Para 2.2.2.
35. The fiber must comply with the data given in ITU.T Recommendation (G-652.D).
27
36. The cable sheath outer surface must be covered by the text with the name (OPEN NET) and year
of manufacture. The information must be repeated at intervals of not more than 150 mm, must
be readable and durable, and not fade away even when exposed to ultraviolet sunlight.
37. Trunk/distribution cable must be provided in units with a length between 2,000 and 6,000 m.
38. Neither the inner or outer surfaces of the OF jacket must exhibit visible cracks, splits, tears, holes,
splits, blisters, or other openings.
39. OF must be equipped with proper protection from termites.
40. The provided cable should meet the following testing standards and requirements.
a) Attenuation: The attenuation coefficient measured in a cable delivery length must be ≤ 0.35
dB/km as a mean value of all fibers in the cable in the wavelength range 1285-1330 nm,
while in the wavelength range 1530-1570 nm, it must be ≤0.21 dB/km.
b) For any cable, no fiber must have an extra attenuation due to non-homogenous or other
defects in the fiber, of more than 0.15 dB, in addition to the attenuation coefficient
measured in a cable delivery length, for both ranges of wavelength.
c) Total Dispersion: The zero-dispersion wavelength must be between 1310 – 1324 nm as a
mean value for all fibers in a cable delivery length.
d) IEC 60794-1-2 G7 (or equivalent), Tests applicable to tubes must be used to measure a
tube's kink characteristics.
e) Mechanical characteristics of cable: the ITU-T L.87, section 8.2 – Test methods for
mechanical characteristics of cable recommendations should be taken into account such as
meet the following test standards: IEC 60794-1-2 E1; IEC 60794-1-2 E3; IEC 60794-1-2 E4;
IEC 60794-1-2 E6; IEC 60794-1-2 E7; IEC 60794-1-2 E11A; IEC 60794-1-2 F1; IEC 60794-1-2
F5
f) All optical fibers must be 100% attenuation tested, and the results of the tests must be
shown in the corresponding data papers.
g) The Contractor should provide the refractive index of the fiber as well as the jacket, as well
as the schedule of the fiber refraction index.
41. The Contractor must provide related documents and/or data sheets and/or certificates to the
Engineer for make sure and confirm that provided FO cables meet the requirements mentioned
above.
42. The Contractor must provide technical specifications for each FO cable as well as their adherence
to the requirements described in this chapter (it must be approved by an engineer). The
information must contain at least the following:
a) Type of FO cable
b) Color code (is given in the next chapter) and data sheets (specifications) in accordance with
the parameters and requirements of this document.
c) Fibers per tube (pcs)
d) Number of tubes (pcs)
e) No. of Fiber Fibers (pcs)
f) No. of Dummy Elements (pcs)
g) Outer cable Diameter (mm)
h) Weight of Cable (kg/km)
i) Min. Permissible Bending Radius (not under tensile load during cable installation) (mm)
j) Min. Permissible Bending Radius (under tensile load during cable blowing/laying/pulling)
(mm)
k) Standard Delivery Length (m)
28
l) Attenuation coefficient (dB/km) at 1310nm and 1550nm
m) Polarization mode dispersion coefficient
n) Mode field diameter
o) Mode field concentricity error
p) Mode field non-circularity
q) Cladding diameter
r) Cladding non-circularity
s) Cable cut-off wavelength
t) Appropriate standards for FO cables
u) Tube diameter
v) Outer diameter
w) Fiber colors
x) Tape
y) Jacket material
z) Jacket thickness
Additionally, aerial cable (with the above mention parameters), must be shotgun resistant (ballistic
protection), with double jackets and adapted for bad climates and high snow/ice Load.
29
12.3.2 Color Code of Tubes
1. The tubes must bear a color on their outer surface to simplify fiber identification.
2. The Contractor must specify the color code of tubes that they will use and which international
standards they will follow for color coding.
1. Connectors must be of high quality for durable functionality and long life. The insertion loss (IL)
must be small, whereas the optical return loss (ORL) must be high.
2. For that reason, the standard single-mode fiber connector must be of type SC/UPC.
3. Connectors must comply with IEC 61755.
4. The following target values for Insertion Loss and Optical Return Loss must be fulfilled by the
Contractor's offered single-mode fiber UPC connectors:
a) Insertion Loss ≤0.25 dB.
b) Optical Return Loss ≥ 50 dB.
31
9. In the 2m radius around the pole, a concrete or asphalt surface of at least 5cm must be arranged.
10. The outer diameter of the pole must be at least 108 mm and the wall thickness of at least 4 mm.
11. The head of the pole must be welded hermetically.
12. Boxes:
a) The boxes must be equipped with the Open Net logo and corresponding writings as in the
picture below (the Employer will provide the vector format)
32
13.4 Big Aggregation Points
1. Before starting all types of work, the Contractor must deploy an informative banner (Chapter 1.1)
at all aggregation points.
2. The Contractor shall provide reinforced concrete foundations for the aggregation Telecom
shelter/containers; the underground structure has to be painted with bitumen.
3. The concrete foundation for the containers should be:
• Raised at least 300mm above ground level;
• The area of the foundation must be a minimum of 10 cm wider than the outer area of the
container.
• A concrete slab of the foundation should be arranged on the entirety area of the floor and
fully fill it.
33
4. The Contractor has to organize the fundament in such a manner that it is appropriate for the
installation of the chosen containers. The works have to be done in accordance with the
international construction and officially used standards of Georgia.
5. A manhole has to be installed outside the foundation
6. The container's door must be accessible directly from the street; If there is no possibility, the
container and door location should be agreed upon with the Employer.
7. The Telecom shelter/Container shall be factory assembled and mast meet the following
requirements:
1. Must meet or exceed the IP65 standards
2. Size shell be 4m X 3m X 2.5m (LxWxH) or 4m X 2.5m X 2.5m, or in case of different
dimensions (minimum area - 10 m2) it must be agreed upon the Employer.
3. The container shall be of so-called "sandwich construction" insulated with a material of
polyurethane. In the case of metal (such as iron or steel) surface it must be painted or
galvanized).
4. The surface of the sandwich must be clean, smooth, and without any visible cracks,
grooves, blisters, wrinkles, dents, beat marks, or foreign inclusions.
5. The thickness of the sandwich panel should be not less than 100mm.
6. All components of the Telecom shelter/Telecom Container shall be fire-resistant.
7. All metal components shall be corrosion-protected (galvanized or painted).
8. The use of wooden parts is restricted.
9. The container shall be water and dust-proof.
10. The surface of the floor must be dielectric.
11. The container's floor must be durable and resistant to high loads of 6kN/m2 or more (such
as a full rack (60X80) with a battery, with a total weight of 600 kg).
12. The roof shall be homogeneous and completely cover the entire perimeter of the Telecom
shelter/Container.
13. The Roof load coefficient shall be a minimum 3KN/m2 .
14. Must be equipped with factory pre-installed Min. 2 plugs and min. 3 lamps (2 inside and 1
outside near the door)
15. Must be equipped with factory pre-installed Cable Raceway System
16. The container's door must be water and dust proof.
17. The container's door must be equipped with factory pre-installed water and dust proof 3-
point lock.
18. The lifetime of a container in service shall not be less than 20 years.
8. If the container is located outside the existing fence, in order to avoid outside damage, the
container Contractor must ensure the fencing of the location. The height of the fence must be 1
meter (from the ground), installed into the concrete, and it must be made of solid metal. The color
and design of the fence must be agreed upon with the OPEN NET.
9. A minimum of 8 lead-ins 40mm ducts from inside the container to the manhole outside of the
foundation have to be installed.
10. All steel containers shall be painted in a color agreed with the Employer.
11. An aggregation container must be equipped with an AC power distribution box (PDU), which
should be connected to the electrical circuit (phase 3). The Contractor is responsible for the
agreement with the local electricity service providers, preparation for the required
documentation, and connection to the circuit.
34
12. The container must be equipped with 2 units of 42U-48U (60X80) telecommunication rack and
with the cable raceway system for cable placement and vertical cable management system
between racks.
13. In the container must be installed FO cable automatic monitoring system. Technical specifications
and requirements are described in Chapter 17.
14. Within 3 meters of the container, a Pole has to be assembled in accordance with the parameters
described in Chapter 13.3
15. 12 ducts going to the box must be organized, out of which 8 will be terminated in the manhole and
4 outside of the manhole, at the pole near the cabinet, by underground method
16. There shall be two separate grounding systems provided for each container and terminated on the
separate copper ground bus bar:
a) The grounding resistance must not exceed 4 ohms for each system.
b) The copper ground bus bar should be:
▪ wall/surface-mounted;
▪ at least 7 mm thick;
▪ at least 50 mm width;
▪ at least 200 mm in length;
▪ stand at least 70 mm from the backboard or wall;
▪ at least with 15 pre-drilled holes.
Ground cable should be made with copper, Cross section (cable size) at least 25 mm², and
yellow/Green.
See the example below: The cabinet has to be installed in such a manner to have the possibility of
installing AC, battery array, and other assisting equipment, as shown in the pictures below.
35
• The area of the foundation must be a minimum of 10 cm wider than the outer area of the
container;
• A concrete slab of the foundation should be arranged on the entire perimeter of the floor
and fully fill it.
4. The Contractor has to organize the fundament in such a manner that it is appropriate for the
installation of the chosen cabinets. The works have to be done in accordance with the International
construction and officially used standards of Georgia.
5. A manhole has to be installed outside the foundation.
6. The cabinet's doors must be accessible directly from the street. If there is no possibility, the cabinet
and door location should be agreed upon with the Employer.
7. If the cabinet is located outside the existing fence, in order to avoid outside damage, the container
Contractor must ensure the fencing of the location. The height of the fence must be 1 meter (from
the ground), installed into the concrete, and it must be made of solid metal or concrete. The color
and design of the fence must be agreed upon with the OPEN NET.
8. Minimum 4 lead-in 40mm ducts from inside the cabinet to the manhole outside of the foundation
have to be installed
9. There shall be one separate grounding system provided for each container and terminated on the
separate copper ground bus bar:
a) The grounding resistance must not exceed 4 ohms for each system.
b) The copper ground bus bar should be:
▪ wall/surface-mounted;
▪ at least 7 mm thick;
▪ at least 50 mm width;
▪ at least 200 mm in length;
▪ stand at least 70 mm from the backboard or wall;
▪ at least with 15 pre-drilled holes.
Ground cable should be made with copper, Cross section (cable size) at least 25 mm², and
yellow/Green.
10. The cabinet's design must be against vandalism and extreme weather conditions.
11. The cabinet must be a factory-made outdoor network cabinet and meet or exceed the IP65
standards.
12. The cabinet shall be made of stainless steel/aluminum and must be equipped with a double-layer
design for the body.
13. The cabinet shall consist of two adjacent spaces with 2 front doors and an anti-theft lock.
14. In the cabinet's equipment space must be installed a 19-inch rack system with a minimum 24U
space for each side.
36
14 Optical Distribution Frames and FO Termination
14.1 General Requirements ODFs
1. The fibers must be terminated at the Optical Distribution Frames (ODF).
2. The fibers must be placed in a Single Fiber Management System (SFMS) Cassette individually.
3. Only Single Fiber Management System (SFMS) cassettes must be used in all ODFs.
4. The type of ODF must be properly proposed during the design by the Contractor.
5. The ODF must meet the following minimal requirements:
a) Shall include Fiber Management System cassette.
b) Shall include multiple shelves for splicing and patching.
c) Shall include Patch Cable Guiding Channels.
d) ODFs for the Aggregation point should be with sliding panel, placed in Standard 42U-48U
19-inch floor mounted rack. Rack and ODF should have patch cords management and
routing guides with storage shelves also fiber guides to ensure the optical fiber bending
radius is always greater than 30mm.
e) ODFs must be fully equipped with SC/UPC adapters and be able to terminate all fibers of
the incoming cable.
f) Separate ODF must be installed for each incoming cable
g) Shall include colored guide tubes (12 different colors) for the fibers from each cable tray
h) Shall include flexible conduit from opened cable to splice/patch-rack
6. The ODF systems must be capable of accommodating not less than 24 fibers.
7. Access to each of the system racks must be possible through the front and rear entry.
8. A fiber identification system with labeling facilities must be provided.
9. After fulfillment of the project, The Contractor must provide ODF Diagrams, including Fiber
Occupation Schemes.
10. Cassettes in the Splice Shelves must be numbered;
11. Cassettes and connectors in the patch shelves must be numbered;
12. The Contractor is responsible for the supply, storage, transportation, and installation of the ODF.
15.2 The Cable Raceway System must fulfill the following requirements:
1. Must ensure a secure and stress-free environment for protecting fiber optic cables
2. It must be in a bright color in order to provide clear identification, high visibility, and diverse fiber
optic cable pathways
3. It must be a system that has a smart design, supporting the following features such as to be safe,
robust, fast, efficient, free of stress, modular, customized and easy to install/modify and reusable,
easily extendable, and fire resistant
4. Must be designed to protect and route fiber optic patch cords and multi-fiber cable assemblies
37
5. Must be able to mount on the top of ETSI racks and/or on the ceiling of the exchange center
equipment room and/or under the raised floor
6. Must support straight channels and curved fittings to be specifically engineered to prevent fibers
from exceeding the minimum bend radius requirement
7. Must allow ease of change or extension without the need to remove the existing fiber or suspend
the services
8. It must be made out of low smoke zero halogens (LSZH), and the enclosed design must ensure the
fiber optic cables are fully protected
9. Must ensure that all plastic-based products used are fire-resistant and halogen-free to avoid the
risk of harming personnel, transmission, and any other equipment installed, rescuers, and the
buildings in case of fire
10. Must ensure that all plastic-based products must be ROHS (Restriction of Hazardous Stances
Directive) compliant
11. Must support self-supporting straight section up to a maximum span of 2 meters
12. Must ensure that a 50mm minimum bend radius is maintained throughout the system regardless
of the raceway size installed
13. Must be designed so that the clearly defined cable routing paths keep cables organized, using less
space and avoiding the tangled mess of cables
14. Must not contain PVC at any part of the offered fiber raceway and its components
15. Fiber Optic Raceway System can select any of the following dimensions:
a) Fiber Raceway 2x2 inch System
b) Fiber Raceway 2x6 inch System
c) Fiber Raceway 4x4 inch System
d) Fiber Raceway 4x6 inch System
e) Fiber Raceway 4x12 inch System
f) Fiber Raceway 4x24 inch System
38
4. The Contractor must verify during the tests that the installed cables/fibers are free of deformations
and reflections.
4. The Contractor must perform the testing of P2P Fiber Links, measuring the following, but not
limited to:
a) The fiber attenuation/insertion loss (IL).
39
b) Link Loss.
c) Optical Return Loss (ORL).
5. Whenever deviations from the target values are detected during acceptance test measurements,
these deviations need to be analyzed and corrected by the Contractor.
Aggregation points must be equipped with the standalone FO cable automatic monitoring system (FO-
AMS). The system shall constantly (24/7) monitor the fiber cable performance based on OTDR
measurement methods. The monitoring system configuration, rules, parameters, and FO cable cores
for monitoring must be agreed upon with the Employer.
The FO-AMS shall be installed in aggregation points provided below in the table. The Contractor must
provide, configure, and install the equipment in 19" racks and connect each port to the aggregation
ODFs with FO patch cords using the connection scheme provided by OPEN NET (connection scheme
will be provided after creation of the FO core distribution diagram described in the Chapter 9.1.11). All
materials (such as patch cords, rack-ears, power supply, etc.) required for performing the works are
the Contractor's responsibility.
The number of devices per site and their port capacity is provided in the table below:
The monitoring system shall have the possibility to monitor fiber cores (with active links as well). The
WDM principle shall be used to split the Data and fiber monitoring wavelengths in a single fiber core.
The filters shall be used on the receiving end to filter OTDR measurement signal and avoid interference
with data network equipment. The system shall be compatible with C and L band data traffic.
Additionally, all required components shall be provided to monitor 2 fiber cores (with active links) from
each aggregation. The filters quantity shall be sufficient to be installed in 2 different
geographical locations.
40
3. Equipped with a user-friendly web interface and an open API interface based on SNMP and
REST.
4. Integrating it into the centralized monitoring and management system must be possible.
5. The principle of fiber monitoring shall be based on OTDR measurements.
6. The device must be rack mountable, maximum - 1RU (19" rack mounts included).
7. The device must have an ethernet port for remote access.
8. The device must be equipped with a console or similar type of local access.
9. The device must support DHCP or static IP address configuration.
10. All connections on the device (both optical and electrical) must be on the front panel.
11. The device must be able to compare the actual OTDR measurements with a user's specified
reference OTDR trace.
12. It must be equipped with a dual power supply (DC - 48V).
13. Operating temperature: -5 to 50 degrees Celsius.
14. Wavelength: 1621-1654 nm (considering the measurement accuracy).
15. Optical Budget / Dynamic range: at least 40 dB.
16. Event Dead zone: 1m or better.
17. Attenuation Dead zone: 3m or better.
18. Pulse width: 5ns to 20μs.
19. OTDR line port Insertion Loss: <1.2dB.
20. OTDR line port Return Loss with connectors: > 50 dB.
1. Each standalone unit shall have the following functionality in its interface:
2. Notifications:
41
a) SNMP and REST API (over HTTP/HTTPS) support.
b) Possibility to send SNMP traps to other OSS/NMS.
c) Email notifications.
d) Email must contain measurement results provided in .sor format.
e) Email text must contain at least: test unit name, Event date and time, Alarm severity, the
distance of fiber fault, and GPS coordinates of fault location.
18 Additional information
1. The cables on the backbone segment Jvari-Khaishi-Mestia must have at least 96 fibers.
2. At the connection point - "Mestia-Jvari-Chkhorotskhu-conn-point", the newly installed FO cable
must be spliced to the OPEN NET’s existing FO cable at the same location.
42