Final Detailed Design Report
Final Detailed Design Report
Final Detailed Design Report
FINAL DETAILED
ENGINEERING DESIGN
REPORT
(FINAL DETAIL DESIGN REPORT)
MAY, 2021
Draft Detailed Report
TABLE OF CONTENTS
i
Draft Detailed Report
ii
Draft Detailed Report
v
Draft Detailed Report
vii
Draft Detailed Report
viii
Draft Detailed Report
xi
Draft Detailed Report
xiii
Draft Detailed Report
LIST OF TABLES
xvi
Draft Detailed Report
xvii
Draft Detailed Report
LIST OF FIGURES
Figure 4.11: Goig Feeder Station at Goig Bus Station ................................ 112
Figure 4.12: Feeder Station at Africana Road ............................................. 113
Figure 4.13: Feeder Station at Sam Nujoma Road (University Feeder
Station) .................................................................................... 114
Figure 4.14: Feeder Station at Igesa Road ................................................. 114
Figure 4.15: Feeder Station at Savei Road ................................................. 115
Figure 4.16: Feeder Station at Lugalo - Mwenge Feeder Station ................ 116
Figure 4.17: Boko Basihaya Bus Terminal: A Single platform at the
centre split between BRT and Feeders Terminal Station. ....... 117
Figure 4.18: (B): Mbuyuni/Sala Sala Bus Terminal: A “two platforms at
the centre” with “BRT outside and Feeder inside” Bus
Terminal, ................................................................................. 118
Figure 4.19: Mwenge Bus Terminal at Mwenge (a single platform at the
centre) ..................................................................................... 119
Figure 4.20: Morocco extended Bus Terminal (a single platform at the
centre) ..................................................................................... 119
Figure 4.21: Kivukoni extended Bus Terminal (an inside terminal” with
“multiple platforms) .................................................................. 120
Figure 4.22: Mbuyuni Depot Building with 414 vehicle parking (design
details of the building in separate drawings). .......................... 125
Figure 4.23: SIMU 2000 Depot Building with 333 parking lots ((design
details of the building in separate drawings). .......................... 128
Figure 4.24: Vehicle parking lots (203 lots) at Sala Sala / Mbuyuni
including Park and Ride parking (109 lots) .............................. 129
Figure 5.1: Salender Bridge ...................................................................... 133
Figure 5.2: Mlalakuwa River Bridge .......................................................... 134
Figure 5.3: Mbezi River Bridge .................................................................. 134
Figure 5.4: Tegeta River Bridge ................................................................ 135
Figure 5.5: Single cell box culvert and pipe culverts ................................. 144
Figure 5.6: Single cell box culvert ............................................................. 145
Figure 5.7: Typical bridge cross section (at middle of existing bridges) .... 149
Figure 5.8: Typical bridge cross section (Salender Bridge) ....................... 150
Figure 7.1: Dar es Salaam height datum referred to Mean Sea level ........ 168
Figure 7.2: Sample of Monumented Control Point along the road ............. 169
xix
Draft Detailed Report
Figure 7.3 Refer to location map below showing datum points used
and new road control points established. ................................ 169
Figure 7.4: Location map........................................................................... 170
Figure 7.5: Time for observation ............................................................... 171
Figure 7.6: Date of observation ................................................................. 171
Figure 7.7: Static GPS Survey operations along the road, Source
Kunhwa survey October 2019 ................................................. 172
Figure 8.1: Generalized Geology and Geologic Section of Tanzania
(Semkimwa P. M et al, 2005) .................................................. 183
Figure 8.2: Soil Map of Tanzania including Dar es Salaam Features ........ 184
Figure 8.3: Drilling works at Selander Bridge (BH02) and Mbuyuni
Interchange (BH01) ................................................................. 186
Figure 8.4: Drilling works at Tegeta Bridge. .............................................. 187
Figure 8.5: Standard Penetration Tests carried on the site at borehole 1
(BH01) with sample recovery at Lugalo Bridge ....................... 190
Figure 8.6: Groundwater level measurement at the boreholes .................. 191
Figure 8.7: Soil strata and profiles from core box at Tegeta Bridge .......... 192
Figure 8.8: Soil strata layout and profiles from core box at Lugalo
Bridge ...................................................................................... 192
Figure 8.9: Soil strata layout and profiles from core box at Mlalakuwa
Bridge ...................................................................................... 192
Figure 8.10: Soil strata layout and profiles from core box at Selander
Bridge ...................................................................................... 193
Figure 8.11: Soil strata layout and profiles from core box at Mbuyuni
Junction Interchange ............................................................... 193
Figure 8.12: Soil strata layout and profiles from core box at Goba
Junction Interchange ............................................................... 193
Figure 8.13: The graph of f1 vs. PI (Stroud and Buter) for determination
of shear strength ..................................................................... 207
Figure 8.14: Relationship between swell index and liquid limit for clay
soil Chen, 1988) ...................................................................... 210
Figure 8.15: Drilling works at Super-Lugalo and Morocco Station using
Rotary Drilling equipment and Hand Auger respectively. ........ 217
xx
Draft Detailed Report
xxi
Draft Detailed Report
xxiii
Draft Detailed Report
xxiv
Draft Detailed Report
xxvii
Draft Detailed Report
xxviii
Draft Detailed Report
xxx
Draft Detailed Report
xxxi
Draft Detailed Report
1.0 INTRODUCTION
1.1 Project Background
Dar es Salaam City is the largest city in Tanzania has approximately five million
inhabitants accounting for around 40 percent of the urban population. The city is
expected to more than double its population by 2030, reaching 10 million. This
makes the city one of the fastest-growing cities in the world. It is also the third
fastest growing city in Africa, growing at an average rate of 5.8 percent annually
over 2002–2012. It is the country’s principal center of commerce and industry
and also an important terminal for air, sea, and road transport.
The studies conducted by GOT/JICA Master Plan Study on 2008, indicated that
90% of Dar es Salaam residents walk, cycle or take a bus ride to work. The
study showed that 56% of the Dar es Salaam residents make a walking trip,
41% make a trip by using public transport “Daladala”, and 3% make a trip by
using motorized two and three wheelers and private cars.
Dar es Salaam like many other cities around the world is faced with a
tremendous challenge of providing residents access to jobs, education, and
public services, all while not exhausting the finite environmental, social, and
economic resources available to them. An over dependence and prioritization of
single-occupant vehicles has exacerbated air and noise pollution, traffic
congestion, sprawling development, and traffic fatalities.
Thus, the high increase in population in Dar es Salaam has led to an increase in
transportation demand and hence high congestion and poor environmental and
safety conditions. The imposition of large-scale rise in private cars on walking
and living spaces has developed undesirable living environment and increase
demand of necessary infrastructure which is beyond the City capacity in terms
of roads, parking, etc. For this reason, Dar es Salaam need to invest in a more
complete set of sustainable mobility options that shift people away from driving
cars, while simultaneously reforming their planning policies to develop around
dense corridors with public transport and accessible amenities. At the heart of
this strategy is providing high-quality public transport for all people.
1
Draft Detailed Report
Bus Rapid Transit (BRT) has risen to the task of providing high-quality transport,
particularly during the past decade to cities around the globe. With roots in
South America, BRT began in Curitiba, Brazil in 1972, and it is a cost-effective,
bus-based rapid transit system, which can achieve high capacity, speed and
service quality. The system accomplishes this through a combination of
features: segregated bus lanes that are typically median aligned, off-board fare
collection, level boarding, bus priority at intersections, and other quality-of-
service elements (examples include information technology and effective
branding).
The project will upgrade the public transport system from the current minibuses
(Daladala) to high-quality bus-based mass transit system which is operated on
specialized infrastructure with adequate incentive to offer affordable mobility,
sustainable urban environment and better quality of life to urban population, of
all income levels. The first phase of the BRT system was planned in 2007 and
began operating on May 16, 2016.The entire system is operated by Dar es
Salaam Rapid Transit Agency (DART). The implementation of all phases of the
BRT system is expected to be completed in 2030.
2
Draft Detailed Report
Kunhwa Engineering & Consulting Co. Ltd in JV with M/s Seoul Housing &
Communities Corporation and M/s Dongsung Engineering Co. Ltd., in
Association with M/s Aqgola Engineering & Management Services Ltd., to carry
out Design and supervision of 30.15kms of Bus Rapid Transit System Phase 4
in Dar es Salaam City.
The designed infrastructure consists of not only the roadwork that form the
busway and mixed traffic but also a range of other components, the
infrastructure components include:
i. Busway infrastructure;
ii. Mixed traffic infrastructure;
iii. Stations;
iv. Intermediate transfer stations;
v. Terminals;
vi. Depots;
vii. Control center;
viii. Traffic control signals;
ix. Integration infrastructure;
x. Park and ride facilities;
xi. Landscape;
xii. Public utilities.
The design covers three main areas being the infrastructure design (in the
physical location), the network plans (the service plans) and the organizational
and institutional management plan.
3
Draft Detailed Report
4
Draft Detailed Report
5
Draft Detailed Report
Further to the above reports, the following reports which falls under the
Infrastructure Design, have been presented as standalone reports as per
Client’s request:
i. Bus Technical Specifications Report
ii. ITS Report
iii. OFC Report
iv. Drainage Report
v. Materials Report
vi. Structural Report Lot 1
vii. Structural Report Lot 2
viii. Traffic and Transportation Report.
6
Draft Detailed Report
In this project the consultant acknowledges the conceptual design for the BRT
Phase 4 which was done by MS LOGIT Consultants in 2018. This conceptual
design will form a base for our preliminary and detailed Engineering design,
modifications will be done on the conceptual design to suit requirements of the
design standards and site condition.
The Consultant has carried out detailed design of the road with respect to the
agreed design criteria presented in the inception report and interim report, Since
the month of September 2019 the geometric design team has been working on
site and office carrying out investigations on various alignments, assessing and
designing the horizontal and vertical alignments taking into consideration of the
following factors.
7
Draft Detailed Report
District Roads: - comprising of all other major roads within a district other than
the above three categories. District Roads should at least connect centres of
Division (TARAFA) or main centres of production of the above main roads.
Major Feeder Roads: - comprising of all roads other than the 4 categories
above which connects Wards (KATA).
8
Draft Detailed Report
Our proposed roads for BRT phase 4 is divided into five links which are already
classified as shown in the Table below
The minimum design criteria of these roads’ sections in accordance with the
RGDM, based on the above classification, are discussed below.
From the desk study carried out by the consultant and previous traffic surveys
undertaken by TANROADS Regional Manager office Dar es salaam, the
proposed roads fell within design class 1 (DC1)
9
Draft Detailed Report
Road Carriageway
Shoulder Median
Design reserve Roadway
Surface Lane width width
class width width [m] Width No. of
width [m] [m]
[m] [m] lanes
[m]
Gravel
DC6 40 8.0 6.0 3.0 2 2 x 1.0
or paved
From the table above the proposed roads will be designed as dual carriageway
roads adopting the dimensions stated above for DC1.
The 9.0m median have been proposed in consideration of bus lanes (BRT)
lanes
2.3.2 Terrain
The terrain classification can be defined in the following cross slope ranges:
Flat terrain : ≤ 10%
Rolling terrain : > 10% and < 25%
Hilly terrain : 25% to 60%
Mountainous : > 60%
10
Draft Detailed Report
The proposed roads generally traverse in two terrain categories as shown in the
table below.
The desirable and minimum design speeds related to the design class versus
type of terrain, is shown in Table below, adopted from RGDM 2011.
From the table above the recommended design speed is 120km/h however the
proposed roads are passing on planned urban area and therefore the
operational speed will be limited to 50km/h in CBD and 60Km/h outside of CBD
11
Draft Detailed Report
Two vehicles have been recommended for use in the design of the proposed
roads. The passenger car has been used for speed-related standards and the
bus for standards relating to maneuverability, typically at intersections. All
geometry and turning movements of the busways shall accommodate an
AASHTO BUS-45 design vehicle. The bus also dictates the maximum
permissible gradient. Designs, however will be checked to ensure that larger
vehicles, such as WB-15 Semi-trailer vehicles, can be accommodated within the
total width of the travelled way, even though they may encroach on adjacent or
even opposing lanes.
Turing templates recommended in the MoW Geometric design manual will been
used for establishing the layout of intersections and median openings. Swept
path analysis using Autodesk Vehicle tracking software will be carried out in all
intersections., U-turns and median openings to ensure save turning movement.
Recommended minimum turning radius are shown on Table 2.7 below
Table 2.7: Minimum turning radii
Vehicle Radius
Passenger Car (P) 6.8
Single unit truck (SU) 10.0
Bus (B) 11.5
Articulated vehicle (ARCTIC) 11.0
12
Draft Detailed Report
At stations, the lane width at a station platform may be reduced to 3.3 meters,
where passing lane is provided.
13
Draft Detailed Report
2.4.3 Grading
The design drawings shall clearly depict the limits of permissible construction
disturbance, which shall include only those areas necessary for construction of
the proposed facilities. Requirements for clearing, grubbing, and removing
unsuitable materials shall be defined. In areas where fill slopes may encroach
upon properties adjacent to right-of -way, the use of retaining structures should
be considered. The flattest practical and economically beneficial cut and fill
slopes shall be utilized up to a maximum of two horizontals to one vertical
(1.5:1Cut/fill slopes have been designed to conducive to the establishment of
permanent vegetation for erosion control/slope stabilization.
14
Draft Detailed Report
Table 2.10: Recommended Side Slopes Ratios vs fill heights are shown
in the table below
Side Slope
Height (m)
Vertical: Horizontal
Table 7-5: Recommended Back Slope Ratios Vs Material Type are shown in the
table below
15
Draft Detailed Report
The proposed Widths of mixed traffic lanes is 3.25m, in sections where the road
corridor is not sufficient the consultant will discuss with the client and prepare up
with design exceptions.
16
Draft Detailed Report
17
Draft Detailed Report
At this section BRT phase 4 will be connected to BRT Phase 3, The consultant
has already established communication with the BRT Phase 2 consultant on
harmonizing the design of the tie-in point. This section is categorized as Central
Business District (CBD) with narrow corridor of about 30m The Existing road
consists of dual carriageway of asphalt concrete, closed drain, curbed earth
median ranging from 2m to 2.5m and walkway lane.
Cross section Elements Proposed during conceptual stage and detailed design
stage are presented in the table below
18
Draft Detailed Report
Ali Hassan Mwinyi road (from the junction of Ohio Street to Selander
Bridge) (1.30 km).
The Existing road consists of dual carriageway of asphalt concrete road with 2
lanes of 3.5m on each side, 0.5m closed drain on each side, 3.0m continuous
right turn lane separated with charter bars and 3.0m walkway on both sides and
a small verge on each side making a total of 30m.
Cross section Elements Proposed during conceptual stage and detailed design
stage are presented in the table below
19
Draft Detailed Report
20
Draft Detailed Report
Ali Hassan Mwinyi road (from Selander Bridge to Morocco) (4.62 km).
This section has a Right of Way (ROW) of 60metres, the existing road cross
section is comprised of two types of typical cross sections.
Salender Bridge to ST-Peter Junction
ST Peters Junction to Morroco Junction
a dual carriageway of asphalt concrete road with 2 lanes of 3.5m on each
side, 0.5m closed drain on each side, 3.0m continuous right turn lane
separated with charter bars and 3.0m walkway on both sides and a small
verge on each side making a total of 30m.
21
Draft Detailed Report
Cross section Elements Proposed during conceptual stage and detailed design
stage are presented in the table below
Cross section Conceptual Detailed Remarks
Element Design Design
Bike Way/Service NIL 3.5 The road is passing on commercial
Rd plots; hence provision of combined
bikeway/service road is necessary.
Service road will be limited in short
segments by Bulbouts
Walkway 3.0m 2.0 Footpath have been provided with
clear width at a height of 200mm from
carriageway
Storm Water Catch Basin Curb Inlet Existing u-shape drains and open
Drainage 0.5m Drain 1.0m drains have been replaced with
kerbinlet drain system
Mixed Traffic 3.5m dual 3.5m dual
Lanes carriageway carriageway
Median Mix- 0.5m 0.5m
T/BRT
BRT Lane 3.5m 3.5m
between Stations
BRT Lane at 2lanes of 2 lanes of
Station 3.5m each 3.5m each
Median BRT/BRT 7.0m Wide 0.5m Ghost This will save space for NMT facilities
Raised however it will require relocation of
existing drain at the existing median
22
Draft Detailed Report
23
Draft Detailed Report
This section was already constructed with BRT in mind, the existing road is
comprising of (7.0m) four lanes dual carriageway, 9.0median and 1.5m
24
Draft Detailed Report
25
Draft Detailed Report
and A spur on Sam Nujoma Road from its junction with New Bagamoyo
Road to Ubungo junction (4 km).
This section was already constructed with BRT in mind, the existing road is
comprising of (7.0m) four lanes dual carriageway, 19.0median, 2.0m walkways
on each side and 5.0m service road on each side, this section is constructed
with trapezoidal lined drainage system. Our proposal is to fit the bus lanes at
the median without causing major disturbance to the existing facilities. The
proposed cross-section elements are shown in the table below
26
Draft Detailed Report
Palm At this section the available corridor is 26m, which is not enough to build a BRT
Beach Station without affecting the road side properties. To accommodate the BRT
Station Station at this section the following have been adopted
Km 1+300 • A 4.0m wide BRT Station have been adopted
to km • A 3.5 m Lane have been adopted for BRT without a physical barrier
1+550 between BRT and Mixed traffic, this will allow BRT bus to use mixed traffic
lane as overtaking lane
• Two lanes of 3.5m have been provided for mixed traffic on each side
• Walkways have been reduced to 1.0m
27
Draft Detailed Report
Selander The consultant received both the concept design from LOGIT and the critical
bridge to Intersection design which was designed by another consultants. The Concept
Ubalozi design from Logit proposed to raise the BRT corridor from Palm Beach Bus Stand
Km 1+600 to Selander bridge Bus stand. This concept will reduce the number of conflicts
to km which would be introduced by the BRT buses at the two junctions (Ali Hassan
3+300 Mwinyi Rd with United nations Rd and Ali Hassan Mwinyi rd with Barak Obama rd)
however the conflicts within the mixed traffic lane will remain the same. This
concept is partially accepted as we expect reduction on mixed traffic volume after
opening of New Selander Bridge which is now under construction. However, we
did not accept introduction of traffic signal where the bridge crosses the mixed
traffic lanes as it will create a short leg between the roundabout and the crossing
point.
The consultant proposed to construct a new bridge (90m) to replace the old
Selander bridge, this bridge will be used by mix traffic from CBD, the existing
bridge which is currently being used by traffic from CBD will b fully used by BRT
to/fro CBD. To reduce number of conflicts stated above we will make the United
Nations Rd intersection 2 phase only by restricting right turn movement from UN
Rd to Ali Hassan Mwinyi rd and change the Barak Obama junction to left in left out
only as we expect decrease in traffic after opening of New Selander Bridge.
28
Draft Detailed Report
This option will save huge cost of building the elevated bridge for BRT corridor and
also allow continuous flow of traffic by reducing number of stops.
29
Draft Detailed Report
Mlalakuwa A new bridge has been proposed in between the two-existing bridge, this bridge
Bridge will be exclusively used by BRT buses only.
Km
10+075
Bondeni The existing pedestrian bridge at Bondeni Bus station have been retained the road
Pedestria have beed designed to pass through the bridge openings. New pedestrian ramp
n Bridge will be constructed to connect with Bondeni BRT station
12+750
30
Draft Detailed Report
Bondeni A new bridge has been designed between the two existing bridges, the bridge will
Bridge Km be used exlusively by BRT buses, Mixed traffic and NMT facilities have been
12+975 maintained to the existing bridges.
Mbuyuni An underpass have been designed at km 18+900 to link the BRT Terminal with the
Depot North BRT Depot a maximum grade of 6% have been attained at the ramp and a
clea height of 5.5m have been provided at the underpass tunel.
31
Draft Detailed Report
The following activities elucidate the preparation of base plans in more detail:
Format survey data to suit the requirements of highway design software
environment;
Download the data into software;
Define main corridor features by joining the points of centerline, edge of
pavement, embankment toe line;
Join the points with same description codes for all physical features like rivers,
buildings, religious structures, shops, telephone poles, electric poles, cross
roads etc. within the above specified limits;
32
Draft Detailed Report
Establish break lines for features such as edge of the road, shoulder, top and
bottom of ditches, etc.;
Insert the details of existing cross drainage structures such as bridge number,
span arrangement etc.;
Gradient Information
Vertical curve information of the existing and designed road
2.7.1 Gradients
Vehicle operations on gradients are complex and depend on a number of
factors: severity and length of gradient; level and composition of traffic; and the
number of overtaking opportunities on the gradient and in its vicinity.
The project road traverses through flat to rolling terrain hence the road gradient
has been applied to suit both economy and safety.
In the new design where the road passes through flat terrain, the proposed road
geometry follows closely the vertical geometry of the existing road.
34
Draft Detailed Report
35
Draft Detailed Report
Huge fill is also expected at SIM 2000 Depot as the depot as the depot is
located in water logged area therefore the finished levels have been raised by
1.0m average to keep the pavement layers away from moisture.
Station Remarks
36
Draft Detailed Report
Lugalo Camp
Access
Km 12+000
The following figures show details of the features included in walkways and
bicycle paths along the whole corridor. The figure shows ramps and devices for
the blind at crosswalks. Ramps extend through the whole sidewalk at corners
and the whole crosswalk at pedestrian crossings. They are designed to help
wheelchairs users and elderly use the pedestrian facilities. Tactile strips are
provided for blind users
37
Draft Detailed Report
The next figure shows the proposed handrail along ramps, particularly useful for
the elderly and blind
Audible signals at pedestrian crossings to help the blind have been specified in
the specifications for pedestrian crossing facilities
38
Draft Detailed Report
39
Draft Detailed Report
40
Draft Detailed Report
2.12 Intersections
All options had similar intersection and interchange locations. The type of
intersections varies by from one option to another because of the difference in
roadway geometry. This section will discuss the details of the intersections
proposed. The U-turns intersections shown in the concept plans have been
adopted. The consultant carried out Geometric design and signalization
analysis to determine which junctions will be signalized to properly manage
intersection control delay.
This intersection is
41
Draft Detailed Report
located at km 0+850.
The junction is
designed as a 3-phase
intersection. The
following movements
have been allowed.
Phase 1: Through
Movement to and from
CBD
Phase 2: Through
Movement (East/West)
from Magoe Street to
Ufukoni Rd.
Phase 3: Right turn
movements from
Magoe St and Ufukoni
Rd to Alihassan Mwinyi
Rd
A Signalised oval
roundabout has been
designed at km 2+625,
this roundabout
connects Kinondoni Rd
on the West, Ali
Hassan Mwinyi rd to
the North, kenyata Rd
to the East and Ali
Hassan mwinyi rd to
the South. The
roundabout has been
designed to operate as
a signalised
intersection. The mixed
traffic will undergo
rotary movement
around the circle until
when the BRT Bus
approaches the
roundabout where the
mixed traffic will be
stopped to allow the
BRT Bus to cut through
the roundabout.
Intersection is located
at km 3+200 at KCB
Bank near Dar Free
Market Mall) This
intersection will allow
Traffic from Kaunda
Drive make a right turn
to Ali Hassan Mwinyi
rd. U turn for North
Bound traffic from the
mall will be through
Bongoyo Street
42
Draft Detailed Report
U-Turn is located at km
3+575 (near total fuel
station near
Haileselasie rd.) The
U-turn will allow North
bound traffic along Ali
Hassan Mwinyi rd to
make a U-turn back to
Ali Hassan Mwinyi rd.
similarly South bound
traffic along Ali Hassan
Mwinyi rd will be
allowed to make a U-
turn back to Ali Hassan
Mwinyi rd.
St Peter Junction km
3+850 (have been
designed to allow right
turn movement for East
bound traffic from
Selander Bridge to
Haile Selassie rd
Traffic from from hale-
Selasie rd will not be
allow to make a right
turn to Ali Hassan
Mwinyi rd.
43
Draft Detailed Report
U-Turn is located at km
4+250 (near Namanga
Junction) The U-turn
will serve as a right
turn facility to all traffic
between Madai street
and Ruhinde Street
and North Bound traffic
from Kimweri rd
Namanga -Intersection
(km 4+400) have been
opened to allow Right
turn movement for
traffic from AliHassan
Mwinyi rd to Kimweri rd
44
Draft Detailed Report
U-Turn is located at km
6+100 (at Victoria near
Victoria Fuel Station)
The U-turn will allow
South bound traffic
along New Bagamoyo
rd. to make a U-turn
back to New
Bagamoyo rd.
U-Turn is located at km
6+675 (signalised
intersection near Green
Acres House opposite
to Merry Water) The U-
turn will allow North
bound traffic along
New Bagamoyo rd. to
make a U-turn back to
New Bagamoyo rd.
U-Turn is located at
km 6+850
(signalised
intersection at
Makumbusho) The
45
Draft Detailed Report
U-Turn at km 7+450
(signalised
intersection at
Millennium Towers)
The U-turn will allow
North bound traffic
along New
Bagamoyo rd. to
make a U-turn back
to New Bagamoyo
rd. Similarly, South
bound traffic along
New Bagamoyo rd.
to make a U-turn
back to New
Bagamoyo rd.
U-Turn is located at
km 8+200 The U-
turn will allow North
bound traffic along
New Bagamoyo rd.
to make a right turn
to Shekilango rd or
make a U-turn back
to Bagamoyo rd.
Traffic from
Kijitonyama will be
utilize this U-turn to
make a right turn to
New Bagamoyo rd.
46
Draft Detailed Report
Bamaga Junction
(km 8+300) have
been opened to
allow right turn
movement for traffic
from Shekilango rd
to Bagamoyo Rd
The junction is
located at km 9+775,
it has been designed
as a two-phase
signalized junction to
allow right turn to
New Bagamoyo rd.
U-turn have been
provided at km
10+000 to allow
North bound traffic
along New
Bagamoyo rd. to
make a U-turn back
to New Bagamoyo
Road.
47
Draft Detailed Report
U-Turn is located at
km 10+825
(signalised
intersection at
Makongo) The U-
turn will allow North
bound and South
bound traffic along
New Bagamoyo rd.
to make a U-turn
back to New
Bagamoyo rd. The
U-turn will also
facilitate traffic
movements from
East and West
connecting roads to
this military area.
U-Turn is located at
km 11+275
(signalised
intersection at
Lugalo) The U-turn
will allow traffic from
South bound traffic
along New
Bagamoyo rd. to
make a U-turn back
to New Bagamoyo
rd. also The U-turn
at km 11+425 will
allow traffic from
North bound traffic
along New
Bagamoyo rd. to
make a U-turn back
to New Bagamoyo
rd.
48
Draft Detailed Report
The intersection is
located at km
12+350 (signalised
intersection at Kawe
junction) This
intersection will
function as a U-turn
for South bound
traffic along New
Bagamoyo rd. who
wants to make a U-
turn back to New
Bagamoyo rd. The
intersection will also
be utilized by Traffic
from Kawe to make
a right turn to
Bagamoyo rd and
traffic from Mwenge
to make a right turn
to Kawe.
U-Turn is located at
km 13+650
(signalized
intersection at
TankiBovu) The U-
turn will allow South
bound traffic along
New Bagamoyo rd.
to make a U-turn
back to New
Bagamoyo rd and
North bound traffic
along New
Bagamoyo rd. to
make a U-turn back
to New Bagamoyo
rd. This U-turn will
also facilitate right
turn movement for
access roads from
Kawe Mizimuni and
Goba.
49
Draft Detailed Report
Goba junction km
14+325
The intersection
have been opened to
allow right turn
movement from
Goba to Bagamoyo
rd. Righ turn from
Bagamoyo rd to
Goba has notbeen
allowed. Traffic from
Bagamoyo rd to
Goba will utilize the
U-turn at km13+650.
U-Turn is located at
km 15+175 (i.e.
Interchick signalized
intersection) The U-
turn will allow South
bound traffic along
New Bagamoyo rd.
to make a U-turn
back to New
Bagamoyo rd and
also provide access
to traffic heading to
the west to make a
right turn at this spot
50
Draft Detailed Report
U-Turn is located at
km 15+575 (near
IMTU) The U-turn
will allow North
bound traffic along
New Bagamoyo rd.
to make a U-turn
back to New
Bagamoyo rd and
provide access to
East bound traffic.
U-Turn is located at
km 16+225 (Jogoo
and Africana) The U-
turn will allow South
bound traffic along
New Bagamoyo rd.
to make a U-turn
back to New
Bagamoyo rd. and
also allow North
bound traffic along
New Bagamoyo rd.
to make a U-turn
back to New
Bagamoyo rd. The
U-turn will provide
access to West
bound and East
bound traffic
51
Draft Detailed Report
U-Turn is located at
km 17+100 (Africana
junction) The U-turn
will allow North
bound traffic along
New Bagamoyo rd.
to make a U-turn
back to New
Bagamoyo rd.
U-Turn is located at
km 19+375 (at JKT)
The U-turn will allow
North bound traffic
along New
Bagamoyo rd. to
make a U-turn back
to New Bagamoyo
rd.
U-Turn is located at
km 19+750 (at
Scansca) The U-turn
will allow South
bound traffic along
New Bagamoyo rd.
to make a U-turn
back to New
Bagamoyo rd. and
also allow traffic from
North bound traffic
along New
Bagamoyo rd. to
make a U-turn back
to New Bagamoyo
rd.
52
Draft Detailed Report
U-Turn is located at
km 22+050 (at Wazo
Junction) The U-turn
will allow South
bound traffic along
New Bagamoyo rd.
make a U-turn back
to New Bagamoyo
rd. make a U-turn
back to New
Bagamoyo rd.
U-Turn is located at
km 22+975 (at Kibo
complex) The U-turn
will allow North
bound along New
Bagamoyo rd. to
make a U-turn back
to New Bagamoyo
rd.
Showing natural ground levels, horizontal and vertical curve details, running
chainage, cross-section chainages, side drain’s location, description and
references to all drainage works, location of bench marks, location of road
furniture, any other relevant information.
53
Draft Detailed Report
Figure 0-1:-Typical Plan and Profile Drawing generated through AutoCAD Civil
3D
These show the construction details for the bridge superstructure and
substructure, including any protection works.
Soil Plans
These plans will show the location of borrow and quarry sites and
characteristics of soil for various sections of the route using appropriate scale.
Auxiliary Works
All other necessary construction features requiring design drawings have been
shown using appropriate scales in the book of drawings
54
Draft Detailed Report
Critical study and design of flood prone areas between Mbezi River to Africana.
55
Draft Detailed Report
According to the Terms of Reference (ToR), the consultancy service covers four
major roads as shown below.
3.4.1 Climate
3.4.1.1 Temperature
The temperature is stable through the year. Averages of the maximum and
minimum temperature are 31oC and 19oC respectively. Rainy season (March,
April and May) becomes hot; the maximum temperature is over 32 oC.Dry
season becomes relatively cool, the maximum temperature is lower than 30 oC
3.4.1.2 Rainfall
Annual rainfall is 1124mm in total. The season is divided into dry and rainy
season. March, April and May are rainy season.
56
Draft Detailed Report
From June to February is the dry season. Rainy days in a month during dry
season are 5 days in average. From June to September becomes very dry and
the rainfall is less than 30mm per month.
Lowland
The Lowland has an elevation of lower than 5m above sea level. These are
consisting of marshy areas and swampy areas widely spread where soft soil is
thick and drainage condition is bad
Plat Plain
Flat plain and terrace areas are observed in the area of above sea level
between 5m and 20m. These areas with minor local hollows extend along the
coast with some kilometers wide. Geological, its origin was a coastal plain
associated with the local terrace (Msasani Peninsula) which is formed due to
pat time marine backward movement
Hill Terrace
Gentle hilly areas are observed in the area of sea level between 20m and 60m,
which is predominant part of the residential area of Dar-Es-Salaam. Ground
surface consists of residual weathered limestone.
57
Draft Detailed Report
Hill to mountain
Hill and mountainous areas can be observed in the western area of Dar-es-
Salaam at approximately 30km inland area from the coast. Undulation to
mountainous areas can be observed in the western area of Dar-Es-Salaam at
around 30km inland area from the coast.
Land here is covered by buildings and roads majority of which are tarmac roads
and few are gravel roads. The buildings are used as residential houses and
others for industrial purposes. Some farming of horticultural products is
commonly done on river valleys particularly Msimbazi valley
There are open areas that exist particularly along stream courses and have
mostly artificial trees and grass. Light to dense forests are on the upstream part
of Msimbazi, Mlalakuwa, Mbezi and Tegeta catchments.
This urbanization has resulted into increased storm water runoff that passes in
between houses down to some water courses into which liquid and solid wastes
58
Draft Detailed Report
are thrown in and course hazardous environment and retardation to the water
flow.
3.5.1 Maps
As mentioned above, drainage area is an important factor for calculating Runoff.
Maps related to the site were obtained before proceeding to site. The following
maps were purchased from the Mapping division of Ministry of Lands:
59
Draft Detailed Report
Rainfall data for Dar-es-salaam Airport and Wazo Hill is presented in Appendix
2.
60
Draft Detailed Report
The rainfall depths measured by rain gauges are point rainfalls which have to
be reduced to depths that are reasonably uniform over an area.
The Area Reduction Factor (ARF) reduces the point rainfall to a value that is
uniform over the entire catchment. It is computed based on the following
relationship
ARF=1-0.044A0.275
where A is catchment area in square kilometers (km2).
61
Draft Detailed Report
Only the first two methods have been used here because their requirements
have been met in this case.
3.6.6 Freeboard
Freeboard is the vertical clearance between the maximum design water level
and the bridge soffit. It is normally provided for bridges to make sure that
floating debris including tree trunks pass safely. A freeboard also takes care of
the local afflux. Guidelines for Free board are available in different standards.
According to FHWA is the following equation:
Table 3.4: The table below summarizes the culvert design criteria:
MINIMUM VERTICAL
DISCHARGE (m 3/sec)
CLEARANCE (mm)
0.30 150
0.30-3.0 450
3.0 -30.0 600
30.0 - 300 900
Over 300 1200
62
Draft Detailed Report
Freeboard calculations are carried out together with bridge rating curve. After
hydrological computations to determine 100year peak discharge for a river
crossing, a rating curve is established and a height for 100year peak is
obtained. Then check if the chosen bridge size has the minimum clearance.
Bridge rating curves for Msimbazi, Mlalakuwa, Mbezi and Tegeta rivers are
presented in Appendix 3.7
3.6.7 Freeboard
The following specifications shall apply in the Review.
All structures to be constructed of reinforced concrete
The bridge openings to be designed for peak flows with a minimum of 0.6m
freeboard between the maximum water level and the bridge soffit.
For culverts, the ratio of the upstream water head (H) and the height (h) of the
culvert to H/h> 1.2
63
Draft Detailed Report
64
Draft Detailed Report
65
Draft Detailed Report
Q=0.278 x C x IP x A x F (1)
where Q=flood peak across drainage structure (m3/s)
C=runoff coefficient
IP=rainfall intensity (mm/hr) at the time of concentration
and for selected probability p
A= catchment area (km2)
F=Area Reduction Factor
The time taken by the storm runoff to travel from the most remote area of the
catchment to the point of exit is the concentration time Tc (hours). This time Tc,
determines the rainfall intensity to be used in the Rational Method and is
calculated by empirical formulas such as the Bransby-William’s formula:
Tc=0.615 x L/ (A0.1 x S0.2) (2)
where L=length of main stream in km
S=slope of main stream (%) and
66
Draft Detailed Report
The Rational Method assumes uniform rainfall over the entire catchment area,
which is a reasonable assumption for smaller catchment areas.
The runoff coefficient, C, which is the proportion of rainfall that results into storm
runoff, is estimated on the basis of three factors- topography of catchment,
permeability of soils and vegetation cover shown in Table 3.7 and Table 3.8
below.
67
Draft Detailed Report
The two tables above are fairly comparable; however, Table 3.1 seems to be
more elaborative and so it has been adopted in this study.
y = 64.991x-0.538
R² = 0.9909 2yr
y = 99.879x-0.538 10yr
R² = 0.9909
y = 117.44x-0.538 25yr
R² = 0.9909
y = 130.47x-0.538 50yr
R² = 0.9909 100yr
y = 143.4x-0.538
R² = 0.9909 Power (2yr)
Power (10yr)
Duration
(Hrs.)
Figure 3.1: Rainfall Intensity-Duration- Frequency Curves
In the power equations above, y stands for Rainfall Intensity (mm/hr) and x for
Duration (hrs) =time of concentration Tc (hrs).
The concentration time is computed from equation (2) above and Area
Reduction Factor F from equation (3). These are inserted in equation (1) to get
the peak design discharges.
68
Draft Detailed Report
69
Draft Detailed Report
The peak floods for higher return periods are estimated based on the 10-year
peak flood.
The model assumes that the catchment can be modelled as a linear reservoir
the input into which is rainfall and the output is the catchment runoff.
This peak flow factor is defined as the ratio of peak flow Qp and average flow
Qavg during the base time TB, that is,
F = Qp/Qavg
Where: P is the total storm rainfall (mm) during time period equal to
the base time TB.
Y is the initial retention (mm)
CA is the contribution area coefficient and
A is the catchment area (km2)
70
Draft Detailed Report
Average Flow
For the hydrograph time base TB, storm rainfall P and a total volume of runoff
RO, the average flow Qavg is calculated as
Qavg = 0.93* RO m3/s
3600* TB
The base time is estimated as
TB = TP + 2.3K + TA
where TP is rainfall time (hours), the time when rainfall intensity remains
at a high level
K is the catchment lag time (hours) and
TA is the additional time for flood wave attenuation (hours).
The 10-year Storm Rainfall
The 10-year storm rainfall P can be determined for a given catchment
area A and a given rainfall base time TB as
P = RTB *ARF
were
RTB is the 10-year point rainfall during the base time TB and
ARF is an area reduction factor which indexes the rainfall variability in
space. It considers the reduction of the rainfall with increasing catchment
area.
For Tanzania, ARF can be determined using the equation
ARF = 1.0 - 0.04T-1/3 A1/2
The 10-year rainfall RTB during the base time TB is calculated from the
expression
RTB = RRTB * R 10/24.
where RRTB is the rainfall ratio that indexes the rainfall
variability in time and is given by
RRTB =TB/24*(24+b)/ (TB+b)) n
b and n are empirical zone dependent indices for rainfall given in
the TRRL EAFM Report as b=0.33 and n=0.76 for the zone on
which the project road lies.
71
Draft Detailed Report
Rainfall
The TRRL EAFM Report 706 gives the values
r 10:2 = 1.64 and
R 2:24 = 80 mm so that
R 10:24 = 131.2 mm over the study area.
Annual maximum 24-hour rainfall data has provided representative
rainfall statistics over the study area. The data is shown in Table 3.10
below and plotted in Figure 3.11.
Initial Retention Y
Initial retention is the rainfall entering the reservoir without creating
outflow. It is calculated from the balance of evapo-transpiration and
rainfall since the last storm having given significant runoff.
In dry and wet zones in Tanzania the probability that the soils are at field
capacity is quite high and therefore initial retention is assumed here to be
Y = 0.
72
Draft Detailed Report
The recession time TR for the surface flow estimated as TR = 2.3K where K is
the lag time.
he attenuation time of the flood wave TA in the stream system estimated from
the equation
73
Draft Detailed Report
TA = 0.028 * L/ (QAvg ¼ * SC ½)
were
L is the stream length,
QAvg is the estimated average discharge and
SC is the stream slope.
The rainfall time TP and the lag time K were selected respectively from
Tables 3.13 and 3.14 below.
Table 3.13: Rainfall Time (Tp) for East Africa 10-year Storms
Zone Index “n” Rainfall Time (TP)
Inland zone 0.96 0.75
Coastal zone 0.76 4.0
Kenya-Aberdare Uluguru zone 0.85 2.0
The details and results of the hydrological calculations, including the various
parameters that characterize each of the study catchments, are shown in
Appendix 3. This table in Appendix 3 is a self-contained table where all the
catchment variables are conveniently lumped and used to compute the design
discharges, iteratively, for return periods 10, 25, 50 and 100 years.
74
Draft Detailed Report
75
Draft Detailed Report
Climate Zones
Climate zones are classified in three groups as mentioned below.
Arid and semi-arid - mean annual rainfall below 800mm
Humid - mean annual rainfall between 800mm 1600mm
Rain forests - mean annual rainfall above 1600mm
Run-Off Coefficients
There are four factors which influence the amount of run-off coefficient. These
are soil type, slopes, vegetation and catchment wetness.
The soil type classification is generally very subjective and will not consider
variation over total catchment. There are 5 classes which correspond directly to
the permeability classification. Values of soil and Slope classes are listed in
Table 3.1 6 and Table 3.17.
76
Draft Detailed Report
Regression equations for ORSTROM and TRRL are representing the basic run-
off coefficient as given below.
For humid catchments:
Cs = 0.53 – 0.12L + 0.08S
For semi-humid catchments (small catchments)
Cs = 0.96 – 0.12L + 0.08S
For humid catchments (big catchments)
Cs = 0.53 – 0.12L + 0.08S –bV A
b =0.04 (I1 and I2 soils)
b =0.02 (I3 and I4 soils)
It Run-off of semi-arid catchments decreases with area and the range is limited
by the area factor and their validity is limited to 100km2.There are run-off rates
for larger catchments.
77
Draft Detailed Report
Storm duration
Time taken for the surface run – off to drain into the river system
Time for the river to reach the bridge site
The equation for the hydrograph base time is
Tb= C x A/ c 2
Where:
Tb hydrograph base time (h)
A Catchment area (km2)
S Slope class
C a constant which is 20 for semi-arid and 30 for humid catchments
78
Draft Detailed Report
Forest 1.7
Average Flow and Design Peak in Fiddes and Watkins, the equation for
average flow during base time is given by:
Q = 0.278 Ca PA/Tb
Where:
Ca contributing area
P area design storm
A catchment area
Tb hydrograph base time
The design peak flow is then given by
Q= F. Q
with F being a peak factor.
79
Draft Detailed Report
The design Peak flow for the Msimbazi catchment having an area greater than
200km2 have been calculated using Generalized Tropical Flood Model and the
results are summarized below and presented in Appendix 4.2.
Table 3.22: Design peak flows for Msimbazi catchment area for each
return period
The road passes through very low and trouble spot which requires special
attention in this design report. These areas are Morocco to Mwenge, Mbezi
Beach area at Goba junction, Africana area and Rafia. The structures are
either non-existence or inadequate.
80
Draft Detailed Report
The hydrological capacity shows that a double cell 1.5mx 1,5m box culvert is
adequate as it can take 6.0m3/s while the quantity of flow is 3.53m3/s assuming
conservatively h/hw of 1.20 and a 10yrs return period.
81
Draft Detailed Report
The hydrological and hydraulic capacity shows that the structure is inadequate.
It is proposed to have two cells box culverts 1500mmx1200mm with a capacity
of 4.42m3/s.
82
Draft Detailed Report
ongoing Morocco Mwenge project does not have a culvert in its project
implementation works. It is therefore to install a double 1.5mx1.5m
83
Draft Detailed Report
The hydrological and hydraulic capacity shows that the structures are
inadequate as they can offer 4.90m3/s while the quantity of flow is 19.64m3/s
assuming conservatively h/hw of 1.0m and a 25yrs return period. In view of the
hydraulic capacity required, double cell 1.50mx4.0m box culvert with a capacity
of handling quantity of flow of 19.0m3/s has been proposed with full protection
works to the access road.
84
Draft Detailed Report
The hydrological and hydraulic capacity shows that the structures are
inadequate as they can offer 4.90m3/s while the quantity of flow is 6.28m3/s
assuming conservatively h/hw of 1.0m and a 25yrs return period. In view of the
hydraulic capacity required, double cell 1.2mx3.0m box culvert with a capacity
of handling quantity of flow of 4.90m3/s has been proposed with full protection
works to the access road.
The hydrological and hydraulic capacity shows that the structures are adequate
as they can offer 47.90m3/s while the quantity of flow is 36.28m3/s assuming
conservatively h/hw of 1.0m and a 25yrs return period. In view of the above, the
existing box culvert is adequate.
The hydrological and hydraulic capacity shows that the existing structure is
inadequate as they can offer 2.00m3/s while the quantity of flow is 6.28m3/s
assuming conservatively h/hw of 1.0m and a 25yrs return period. In view of the
above, the existing box culvert need an additional box culvert of 1.5m x4.0m.
85
Draft Detailed Report
The hydrological and hydraulic capacity shows that the existing structure is
inadequate as take 2.00m3/s while the quantity of flow is 6.28m3/s assuming
conservatively h/hw of 1.0m and a 25yrs return period. In view of the above, the
existing box culvert need an additional box culvert of 3.0m x1.2m.
86
Draft Detailed Report
87
Draft Detailed Report
88
Draft Detailed Report
Table 3.24:
Coordinates Station
Type of Size No of
No. Stream Name
Eastings Northings structure in(m) cells
Dar es Salaam Rainfall Station data has been used to establish the Intensity-
Duration-Frequency (IDF) curves shown below.
89
Draft Detailed Report
Therefore, the government of Tanzania has set up a Centre for Climate Change
Studies (CCCS) at University of Dar es Salaam in order to study and coordinate all
activities related to Climate Change in all sectors. Other countries are also engaged
in addressing Climate change impact. Lessons learned from other countries with
similar climatic conditions can be adapted in Tanzania.
The following table lists these events and what measures may be used to minimize
the impacts.
Table 3.25: Possible Climate Change Events, Risks and General Mitigation
Measures
Climate event Risks to the road Measures
Heavy rain for longer Water overtopping on road crest Increase road level to at least 0.5 m
periods Increased capacity of moistures and over the maximum flood level
decreased cohesion of soil and Erosion protection
increased seepage and infiltration Increase capacity of culverts Build
across road body up weirs and spillways
Drainage system over capacity of Increase capacity of compaction
and increase drainage erosion (lower moisture percentage)
Embankment instability or loss, road Decrease hydrodynamic force of
wash away water through planting grass
• Use resistant materials for building
roads
Storm events Destabilizations of bridges Trees
(Typhoons, Cyclones) blocking the roadway Damage to Increase capacity of spillways and
and extreme winds traffic signs culverts
Embankment protection through
tree plantings
Increase road inspections
Decrease road traffic during storms
90
Draft Detailed Report
3.15.2 Drainage
A good drainage system conveys water from the surface of the road, as well from the
different layers of the road structure, to a safe exit (stream or cross drainage
structure). The drainage system also intercepts surface water flowing towards the
road and conveys water across the road in a controlled fashion.
The destructive power of water increases exponentially as its velocity increases.
Therefore, water must not be allowed to develop sufficient volume or velocity so as
to cause excessive wear along ditches, at culverts or along exposed running
surfaces, cuts or fills.
The presence of excess water within the roadway will adversely affect the properties
of the materials with which it was constructed. Cut or fill failures, road surface
erosion and weakened subgrades followed by a mass failure are all products of
inadequate or poorly-designed drainage.
3.15.3 Drainage
Climate change may increase rainfall intensity which will increase the risk for
overflow and destruction of roads. The cross drainage of the roads, mainly culverts,
bridges and spillways should be modified to be resilient to climate change. New box
or pipe culverts can be added or existing culverts can be increased in size.
Box culverts. The size of the culverts very much depends of the flow of water and the
height of embankment to be able to accommodate the culvert. It is important to
consider erosion problems around culverts where rapid flow is expected. Especially
vulnerable is the outlet of culverts where embankment protection should be
considered. Stone pitching is recommended.
91
Draft Detailed Report
92
Draft Detailed Report
Table 3.26:
Name of Regime Bridge Q silt Coefficient Dmax
River Width Width (designed) factor (m) (Scour
(Lasey) (designed) m3/sec (f) depth)
Msimbazi 98. 72. 663 1 2 6.76
Mlalakuwa 35 30 53.38 1 1 6.66
Mbezi 76 30 247.29 1 1 6.66
Tegeta 72 30 222.64 1 1 6.21
Dmax is measured from top water level, therefore scour below riverbed level is in the
cover of 2,0m. It is recommended to construct pier cap at 3.0m below riverbed.
However, there are problems with some of the culverts which need attention. Some
culverts are not provided, small in capacity and in wrong position and have no outlets
for emptying storm water which runs through them. The Culverts are mentioned here
below:
i. The proposed dia.900mm culvert at km 3+550 at corner Ali Hassan
Mwinyi/ Mkwawa Road
ii. The proposed double dia 900mm culvert at km 4+660, corner Ali Hassan
Mwinyi road and Best bite
iii. The proposed single 3000mmx1500mm box culvert at km 5+525, corner
Bagamoyo road and Chato road
iv. The proposed single 1200mm pipe culvert at km 6+950, near Victoria
Towers
v. The proposed double 1500mm x1500mm box culvert at km 9+175, near
Mikochen area/Aspen
vi. The proposed double 4000mmx1200mm box culvert at km 23+275 near
Tegeta Rabininsia
vii. The proposed double 4000mmx1200mm box culvert at km 24+075 at Kibo
Cement/Namanga
93
Draft Detailed Report
94
Draft Detailed Report
As earlier said in the architecture report for phase five (BRT 5), Dar es Salaam Bus
Rapid Transit system (DART), is a transport system in which buses traverse the bus
routes passing through bus stations, bus feeder stations, bus terminals and at the
end of day park at depots for cleaning, refueling and maintenance. Therefore, such
stations and depots are also critical parts of BRT 4 infrastructure that provide spaces
and facilities for the boarding and alighting, transfer of passengers from one
bus/BRT system to another and periodic maintenance, cleaning, fueling and parking
of buses for the efficient operation of the Transit system.
From the Architecture report on the existing situation and conditions of the BRT4
routes, we noted the LOGIT Concept Report proposing a number and types of the
Terminals, Bus Stations and Bus Depots. As such and looking at the prevailing
conditions, we have adopted the proposals as presented and our task is to produce
architectural drawings for the same as proposed.
95
Draft Detailed Report
96
Draft Detailed Report
The architectural design of the roofs are similar to those of BRT5 to avoid having
many varied designs in the same system, such when the whole BRT system is
completed, there should be at least three roof design types: that is that one in BRT1,
BRT2 as designed, and our designed curved roof system. As it was designed in
BRT5, stepped barrel roof provides for natural light but also avoiding the rain into the
bus stations. The doors have been designed to accommodate sliding automatic
doors in operation. The types of buses used are the 18 m. articulated buses 12 m.
long unarticulated buses.
From the study of the existing situation, there are a total of 44 stations varying is size
said here above. There are 39 bus stations on the route from Ally Hassan Mwinyi
Road and Bagamoyo Road to Boko Basihaya (DAWSCO DEPOT) the names of
which are shown on the road design drawings, and 5 bus stations from Simu 2000
road junction and Sam Nujoma Road to Mwenge (i.e., University (Magufuli Hostel),
Kivulini, Mlimani City, Lufungira, and Mwenge).
97
Draft Detailed Report
has been achieved by having on level boarding and alighting. Thus, a cantilevered
900mm high 500 mm wide platform is provided, which meets the bus floor on the
same level. A Ticketing booth has been provided with facility for queuing on the
outside to avoid congestion in the bus station. However, it is envisaged that most of
the ticket purchases will be done outside the station.
Firm control of the passengers is necessary since only those within the station will be
allowed to board the buses. Hence, the use of sliding doors and turnstiles has been
extensively used.
Regarding facilities for staff, we have added a bay or two each with a length of 2.4
meters to each ticketing area of the big/large stations (Mbuyuni station at St. Peters’,
Lugalo Station and Goigi Station) to accommodate staff washrooms, one per each
sex. Thus, the lengths of these stations have increased to accommodate this
change. This shall also necessitate construction of waste water treatment facility
(septic tanks and cesspools) at each station. Elevated water supply tanks each with
a capacity 10,000 litre shall be located at the outer side of the road way to supply
water to the washrooms as shown. Where a sewer line is available (e.g. along
Bagamoyo Road from Mwenge to Makumbusho), possible connection of these
facilities to the existing sewer line is possible.
98
Draft Detailed Report
Figure 4.1: Elevated water tank to supply water to the station staff
washrooms (as per DART requirements and recommendations).
99
Draft Detailed Report
Bagamoyo Road along East – West require sun shading devices which help to
reduce solar load from getting into the longer sides (elevations) of the building. The
two curved steel frames on each side of the station spanning from ground to ground
serve to emphasise the dynamic flow and as decorative element which at the same
time is used to support or carry the solar panels which are used as sources of
energy for the stations. Sam Nujoma Road which runs almost north–south is directly
affected by the morning and evening suns. So, care is to be taken to ensure proper
sun-shading devices are provided.
100
Draft Detailed Report
6. Bus Station Type VI: 273.6 meters in length and the width of 3.5 meters –
Staggered station. Here, LOGIT proposed 269m with Operational return.
All the station widths include boarding and alighting platforms of 500 mm wide at all
entrances and alighting doors. Our designs are based on modular design with a
basic design module of 2.4 m and standard ramp of 9.6 m long giving a slope ratio of
1:10.7. Here below we describe the stations sequentially for better understanding of
same.
As such, each station type in BRT 4 is a multiple of one module without or with a
connector or connectors and either half module (20.4m). A module constitutes of 17
bays of 2.4m making 40.8 m in length with a constant width of 4.0m center to center.
The connector or connectors each constitutes 13 bays of 2.4m or 31.2 m; or 15 bays
of 2.4 m or 36 m in length. An apron of 500 mm width is provided on each side at the
entrance for boarding and alighting. Type VIII which is a staggered station has 15
bays of 2.4 m or 36m connector and four modules of 17 bays of 2.4 m or 40.8 m all
totaling 268m. The station types are as follows: -
101
Draft Detailed Report
102
Draft Detailed Report
103
Draft Detailed Report
104
Draft Detailed Report
105
Draft Detailed Report
106
Draft Detailed Report
buses making the total with of the station to be 4m as seen in the sketch here below.
The plans and details of the designs are presented in a separate bundle of drawings.
107
Draft Detailed Report
Table 4.1: Table indicating the size, platform operations, number of stations
per type, number of subs stops, docking positions, passenger
design capacity, width of station and number of turnstiles.
Type Size Platform No. of Location Sub Docking Passenger Width No. of
Stations stops positions design Turnstiles
capacity
1 62.4x5P Bi- 1 Tanki 1 2 80 5 5
directional Bovu
2 136.4X5P Bi- 32 Others 2 3 140 5 10
directional
3 160.8X5OP Bi- 1 Mbuyuni 2 4 160 5 10
directional
160.8X9OP Bi- 2 Simu2000 2 4 160 9 22
directional / LMH at
Mwenge
5 228.8X9OP Bi- 1 Goig 3 6 240 9 22
directional
6 273.6x4SP Bi- 1 Ohio 2 3 140 4 6
directional Street
(N)/Red
Cross
9 Total number of 38
stations
It is understood also that the stations will be in use from 05 00hrs to midnight as the
case is in BRT 1, depending on the Bus Operator. Thus, adequate provision has
been made for internal and external lighting. Solar panels shall be used to generate
solar energy that shall be used for lighting at night hours in case TANESCO power is
out.
108
Draft Detailed Report
In order to reduce the variety of materials during the operation of DART, we have
used materials which can easily be found in the local market as opposed to materials
used in BRT 1. As such, the materials have been carefully chosen to comply with
durability needs, low maintenance, aesthetics and functional requirements etc. Table
4.3 shows the primary materials to be used on the project.
109
Draft Detailed Report
110
Draft Detailed Report
111
Draft Detailed Report
112
Draft Detailed Report
113
Draft Detailed Report
Figure 4.13: Feeder Station at Sam Nujoma Road (University Feeder Station)
114
Draft Detailed Report
115
Draft Detailed Report
Bus terminal stations are complex in nature and accommodate a range of functional
spaces such as waiting spaces, ticket queuing area, ticketing office building, check in
or check out points, ablution block to serve both male and female including facilities
for those with disabilities. In addition, the bus terminal stations have to have feeder
stations to receive Dala Dala buses including parking areas for private passenger
cars
116
Draft Detailed Report
iii) The “Next to terminal” with “a single platform at the centre”, at Mwenge
and Morocco; and
iv) An “Inside terminal” with “multiple platforms”.
There are three (3) new Bus terminals on BRT4 route, one at Mwenge,
Mbuyuni/Sala Sala and Boko Basihaya (DAWASCO Depot) and two terminals for
extension of two BRT1 bus terminals of Kivukoni and Morocco. Here below we
present the designs of the terminals as follows:
Figure 4.17: Boko Basihaya Bus Terminal: A Single platform at the centre
split between BRT and Feeders Terminal Station.
Sala Sala Bus Terminal (Figure 4.18), “two platforms at the center” with “BRT
outside and Feeder inside”, is located Mbuyuni/Sala Sala on the New Bagamoyo
117
Draft Detailed Report
Roads. It is a terminus of buses plying the BRT4 from Magogoni Ferry through
Mwenge, Lugalo Barracks to Boko Basihaya. The station shall make it possible for
DART buses to have short routes within the BRT system, allowing or providing
flexibility in the scheduling and planning of the bus operations. The terminal also
provides for Park-and-Ride parking facility where passengers with own private cars
can park in secured parking lots and ride into BRT. The Park-and-Ride has a car
parking capacity of 109 parking spaces. The plans and details of the designs are
presented in a separate bundle of drawings.
Figure 4.18: (B): Mbuyuni/Sala Sala Bus Terminal: A “two platforms at the
centre” with “BRT outside and Feeder inside” Bus Terminal,
118
Draft Detailed Report
The objectives of BRT4 at this terminal is therefore to expand the facility (boarding
and alighting terminal platforms) towards the south on Kawawa Road and introduce
an addition bridge connecting passengers from bus stations on BRT6 route and Ally
Hassan Mwinyi and New Bagamoyo Roads. To achieve these objectives, an
extension of the terminal platforms for boarding and alighting towards the south on
119
Draft Detailed Report
Kawawa Road has been proposed and designed. In addition, a ramp and elevators
have been included for ease of use of the terminal by the physically impaired/or with
physical disabilities. An additional ticketing and turnstiles facilities have been placed
at the first floor of the bridge for passengers from BRT6 and Ally Hassan Mwinyi and
New Bagamoyo Roads. The other offices and toilet facilities have been maintained in
the ground floor platform. The plans and details of the designs are presented in a
separate bundle of drawings.
Figure 4.21: Kivukoni extended Bus Terminal (an inside terminal” with
“multiple platforms)
120
Draft Detailed Report
The objective of BRT4 at this terminal is to expand the facility towards the east by
removing the Dala Dala buses’ platforms and construction of additional boarding and
alighting terminal platforms in their place. To achieve the objective, we added 3 more
platforms (namely 01A - 01B (432m2); 02A - 02B (432m2); and 03A - 03B (345.6m2))
for boarding and alighting. In addition, an additional of entrance with ticketing
building shed (355.32m2) have been designed for passengers from the Magogoni
Ferry to board the BRT Buses, and a security office (14.18m2). Other ticketing
booths and ablution facilities (2 washrooms for people with physical disabilities, 11
washrooms for female, 8 washrooms for male, 8 urinals, 8 hand wash basins (4 for
each sex) Cleaners' room and an office) have been placed on the side of the Fish
Market (from entrance number) to cater for the increased passengers. The plans and
details of the designs are presented in a separate bundle of drawings.
121
Draft Detailed Report
area
10 Total 133.20 165.00 219.00
122
Draft Detailed Report
offices and car or vehicle servicing areas. So a need to meet such criteria cannot be
overemphasized. Here below we provide that we have tried to achieve in the design
of the depots as proposed by LOGIT.
4.8.2 Safety
Safety of employees in the Depot from hazards of fire, electric shock and injuries has
been considered by ensuring following:
(i) Zoning all activities involving heavy machinery to the ground floor
(ii) Zoning of heavy moving parts and machinery away from employees and public
paths as much as possible
(iii) Separation of fuels from possible sources of fire,
(iv) Adequate lighting during day and night
(v) Use of non-slippery floor surfaces
(vi) Column positions away from bus movement as much as possible
(vii) Providing adequate firefighting facilities e.g. underground water storage for
firefighting, fire extinguishers, properly designed escape routes and a dedicated
space for a fire fighting vehicle;
(viii) Providing fire detection and alarm systems
4.8.4 The Sites for The Bus Depot Buildings at SIMU 2000 and Mbuyuni / Sala
Sala
LOGIT has proposed two sites for the Depots. One site is at Mbuyuni/Sala Sala and
the other one is at the SIMU 2000. Our designs have also taken these two sites into
consideration. Due to the difference in sizes of the areas in terms of squares metres,
the capacities of the depots to accommodate the buses differ considerably. The total
123
Draft Detailed Report
area of the SIMU 2000 site is 84,248 square metres. The Mbuyuni/Sala Sala Depot
site is provided in two separate areas. One of the sites on the right of the New
Bagamoyo Road as you head towards Tegeta suits for the location of the depot
administration and maintenance functions. It has a total area of 52,753 square
metres. The site has enough space to accommodate a number of buses. The site to
the left of New Bagamoyo Road is suitable for bus parking, with a total area of
33,757 square metres.
The building for the administration and maintenance functions of the Depot is the
same as that building designed for BRT 5. All the services functions for depots are
as provided for in BRT5. The minimum headroom provided for the bus maintenance
area of the two depot buildings is 12.5m high. The Depot buildings each covers a
total built up area of 3629.52 m2 and the functions are accommodated as follows.
(The drawings for the Depot Building and the parking lots are submitted separately
for ease of reading and referencing).
124
Draft Detailed Report
Figure 4.22: Mbuyuni Depot Building with 414 vehicle parking (design
details of the building in separate drawings).
125
Draft Detailed Report
Annexed to the main Depot building is concrete flat roofed single storey building
standing on concrete columns that houses the generator and air pressure pumping
facilities. The annexure is separated with a 230mm wall from the main depot
building. The generator room is designed to accommodate a containerized
Generator set so as to reduce noise pollution. Capacity of the Generator set to be
provided is explained in the electrical services report. In addition, other building
facilities though small in size are provided serve functions as described below.
126
Draft Detailed Report
small office for the inspector is also provided. The fueling shade is designed to
accommodate 3 fueling pumps allowing 3 buses to fuel at the same time. A gate
house is also provided at the gate to house the security personnel who shall control
movement in and out of the depot of the buses and people.
4.8.11.1 The bus passes through the Visual inspection area where it is checked
to assess whether it is fit for the next day’s operation. If this is the case
it goes for fueling, cleaning and parking.
4.8.11.2 In a situation where the bus is observed to have minor problems but is
fit for the next day’s operation, it is scheduled for corrective
maintenance.
4.8.11.3 Where the bus is considered unavailable for the next day’s operation
after observing major problems, it is sent to the corrective maintenance
127
Draft Detailed Report
4.8.12 Parking Capacities for SIMU 2000 and Mbuyuni/Sala Sala Depots
This phase of BRT system provides for two (2) depots, one at SIMU 2000 and
another at Mbuyuni. Apart from accommodating the administration and maintenance
functions, Depots serve as the main parking facilities for the BRT buses during the
hours of recess or when the buses are not operating. In total the two depots provide
for 759 places or spaces of parking lots as follows:
Figure 4.23: SIMU 2000 Depot Building with 333 parking lots ((design
details of the building in separate drawings).
Simu 2000 has 345 parking lots all accommodating 18m long buses, while
Mbuyuni/Sala Sala has 414 parking lots (that is 229 lots on one site to the left and
185 on the depot building site to the right). In addition, all the Depots have mini petrol
fueling pumps, cleaning areas, tyres repairs area, tyre storage and vehicle inspection
areas. The depot buildings are designed to provide a number of service pits, spares
storage areas, and other maintenance functions.
128
Draft Detailed Report
Figure 4.24: Vehicle parking lots (203 lots) at Sala Sala / Mbuyuni including
Park and Ride parking (109 lots)
It is assumed that the Depot will be in use from 04 00hrs to 0200hrs depending on
the Bus Operator. Thus, adequate provision has been made for internal and external
lighting. It is also assumed that the buses to be used for DART shall be Articulated
Buses with 900mm floor deck height from the level of the road at the entrance. The
design height of the bus is 3.05 and width of 2.5m and length of 18.0m
The platforms and ramps for bus stations, terminal buildings shall be cast in-situ on
high resistance concrete. Size, typology and design will be executed according to
specifications and detailing from structure design. In all bus stations and terminals,
the concrete floor will receive epoxy painting in yellow color. At feeder standpoints or
stations, the floor shall receive glassed finishing with sealant. The tactile floor will be
applied according to the architectonic requirements, 50 cm from the curb line, along
all platform’s extension, at ramps and at all obstacles. The tactile floor fixing has to
129
Draft Detailed Report
follow the recommendation from the fabricant or as per the specifications that meet
BS, BS EN, ASTM, TZS standards and/or any international standards.
Due to the requirement of construction of the bus station and terminal building
structures to allow for rapid duplication and mass production of the units, some of the
materials that shall be used may be susceptible to vandalism as these have been
designed to allow for ease of fixing and coupling, thus it will be necessary to have
additional security arrangements to safeguard equipment and the building fabric from
intentional damage.
130
Draft Detailed Report
131
Draft Detailed Report
From condition survey, it can be proven that most existing drainage structures,
particularly pipe culverts require replacement, in additional to new structures to
comply with the proposed alignment. This was based on following overall criteria
used to rank drainage structures;
1: Very good, no damage, only routine cleaning
2: Good, no immediate action required, minor repairs only
3: Fair, action soon required, major repairs
4: Critical, extensive rehabilitation or replacement required
5: Failed / failing, replacement required
The summary of drainage structures found along the project roads during condition
survey are listed in the Hydrology/Hydraulic Report. Such summary describes types
of drainage structures, defects observed, and recommended measures. See also
Appendix A of this report.
132
Draft Detailed Report
133
Draft Detailed Report
134
Draft Detailed Report
135
Draft Detailed Report
Super structures (RC beams, box girder beams, etc.) in general were inspected for;
Structural connections and joints
• Bearings
• Expansion joints
• Rivets and bolts for the parapet walls
• Deflections
• Clearance profile
• Corrosion and deformations
• Cracks
• Concrete spalling
• Honey-combs
• Exposed reinforcement bars
• Corrosion of reinforcement bars
• Substructures – abutments and piers in concrete
• Cracks
• Deformations
• Concrete spalling
• Exposed reinforcement bars
• Mortar joints for masonry structures
• Rusting
• Bearing banks and foundation joints
• Verticality of abutments and piers
All findings during this phase have been recorded and tabulated for each bridge.
136
Draft Detailed Report
residual concrete strength, and Profometer equipment to determine the size, spacing
of the reinforcing steels and cover concrete to the reinforcing steels, was used to test
each bridge. Summary of results of each bridge is described below while detailed
results is attached in the Appendix B of this report.
Salender Bridge
An average compressive strength of 62.0 MPa of the rebound hammer was obtained
for the abutments, 59.33 MPa for the piers, and 60.0 MPa for the slab deck. Such
results indicate a good quality concrete that suffices structural requirements. In case
of reinforcement steels, 20 mm diameter bars spacing at 120 mm c/c were detected
at the bottom of the slab deck, both main bars and distributions bars. For the piers
and abutments, 20 mm diameter bars spacing at 150 mm c/c were detected for the
vertical reinforcement while 16 mm diameter bars spacing at 150 mm c/c were
detected for horizontal reinforcements. Such results represent sufficient number of
rebars that suffices structural requirements.
Mlalakua Bridge
An average compressive strength of 63.5 MPa of the rebound hammer was obtained
for the pre-stressed beams, and 63.0 MPa for the abutments. Such results indicate a
good quality concrete that suffices structural requirements. Also, based on the as
built structural drawings and structural design calculations reviewed, it is evident that
such a bridge conforms to structural requirements.
Lugalo Bridge
An average compressive strength of 59.5 MPa of the rebound hammer was obtained
for the pre-stressed beams, and 59.0 MPa for the abutments. Such results indicate a
good quality concrete that suffices structural requirements. Also, based on the as
built structural drawings and structural design calculations reviewed, it is evident that
such a bridge conforms to structural requirements.
Tegeta Bridge
An average compressive strength of 59.0 MPa of the rebound hammer was obtained
for the pre-stressed beams, and 54.0 MPa for the abutments. Such results indicate a
good quality concrete that suffices structural requirements. Also, based on the as
137
Draft Detailed Report
built structural drawings and structural design calculations reviewed, it is evident that
such a bridge conforms to structural requirements.
5.6 General
5.6.1 Planning of Structures
The planning of structural elements of the box culverts and bridges is a significant
step that influences functioning and construction of Bus Rapid Transit (BRT) phase
4, within the City of Dar es salaam. It is essential that planning should allow
minimization of the project budget while allowing the project to function in full effect.
Also, aesthetic value of the project, in harmony with the surrounding environment is
also be considered. This section intends to give criteria for selection of important
structural elements for the bridges and box culverts for an effective planning and
construction of BRT Phase 4, based on basic elements stipulated in Table 5.2 below.
Materials;
Materials types – construction materials, i.e., reinforcing steel, concrete materials,
structural steels, etc., which is locally available,
138
Draft Detailed Report
Materials service life –long lasting construction materials, i.e., strong and durable
against permanent and dynamic loading,
Materials flexibility – the same material that can be applied in a wide range, and
Material friendly – materials which are environmentally friendly, i.e., with little or no
environmental impact.
Foundation – foundation bases which are wide enough and capable to withstand
static and dynamic loading,
Structural systems – structural system which is stable against static and dynamic
loading, with low centre of gravity for earthquake resistance,
Structural details – structural members which are designed and detailed observing
rules for durability and seismic design,
Aesthetics – structural members which have good appearance without the need for
special edge units or in-situ masking.
Manufacture/construction;
i. Structural steel self-weight – structural steel members that are within lifting
requirements available in Tanzanian crane capacity,
ii. Formwork for cast in situ and/or pre-cast concrete – formwork which exist
in Tanzanian market, with affordable costs,
iii. Concrete grades – locally available concrete plants capable of producing
required grades of concrete,
iv. Steel grades – required structural steel and reinforcing steel bars grades
which is locally available and no need for importation,
v. Stability during erection – structural members are stable during erection,
and no temporary supports required.
139
Draft Detailed Report
vi. Maintenance
vii. Durability – structural members well detailed to provide good long-term
durability.
viii. Inspection – exposed surfaces that can be easily inspected and
maintained without impair structure stability of the structure.
ix. Client requirements
x. Design life – the specified 100 years and/or more design life that can be
achieved.
xi. Maintenance – a low maintenance of structural members that can be
provided.
xii. Environmentally friendly – the structures improve environmental
friendliness, i.e., between the structure itself and the surrounding
environment.
Part 1:1997; Structural use of concrete – Code of practice for design and
BS construction
8110 Part 2:1985: Structural use of concrete - Code of practice for special
circumstances
BS 1986: Code of practice for foundation
8004
Part 2:1978: Steel, concrete and composite bridges – Specification for loads
Part 4:1990: Steel, concrete and composite bridges – Code of practice for design
concrete bridges
BS
Part 7 & 8:1978: Steel, concrete and composite bridges – Specification for
5400
materials and workmanship, concrete, reinforcement and pre-stressing tendons
Part 9:1983: Steel, concrete and composite bridges – Bridge Bearings
Part 10:1980: Code of Practice for fatigue
BS Part 2 (1991) – Specifications for vehicle containment parapets of concrete
6779 construction
140
Draft Detailed Report
BS 1997: Code of practice for Specification of carbon steel bars for the reinforcement
4449 of concrete
BD Volume 2: Backfilled Retaining Walls and Bridge Abutments
30/87
BD Volume 2: The design of buried concrete box and portal frame structures
31/01
BD Volume 1: Design Manual for Roads and Bridges
37/01
Soil 20 KN/m3
Reinforcing Steel Steel Grade 460 MPa for all reinforcement steel
141
Draft Detailed Report
Ground type B
142
Draft Detailed Report
5.7.1.2 Foundation
Foundations for culverts were designed based on soil properties obtained from the
geotechnical investigation report. Further, design assumed a removal of unsuitable
material with a replacement of suitable and well compacted materials under culverts
based so as to attain minimum Ground Bearing Pressure (GBP).
Load Combinations as per standards are (See Table 8 for loading factors in relevant
standard)
Combination 1: Permanent loads, Vertical Live Loads, Horizontal Live
load Surcharge
Combination 2: Permanent loads, Horizontal Live load Surcharge
Combination 3: Permanent loads, Vertical Live loads
Combination 4: Permanent loads, Live load Surcharge (one side), HA or
HB Traction
Combination 5: Permanent loads, Live load Surcharge (one side), HA or
HB Traction
Combination 6: Permanent loads, Live Loads Surcharge (one side).
143
Draft Detailed Report
The load combinations representing the worst loading possible of the three in
Ultimate Limit State design was used for analysis and design. The combination
giving worst loading possible include permanent, long-term and transient or variable
principal actions, plus long-term restraint actions only.
144
Draft Detailed Report
145
Draft Detailed Report
146
Draft Detailed Report
Table 5.10: The applied span length for the bridge superstructure
Span length (m)
10 20 30 40 50 60 70 80 90 100 110 120
Structure Type
Frame Bridge
T-girder bridge
- Continuous
- Simple
- Continuous
- Simple
- Continuous
- Continuous
147
Draft Detailed Report
- Simple
- Continuous
Truss Bridge
- Simple
- Continuous
Cable-stayed bridge
148
Draft Detailed Report
Figure 5.7: Typical bridge cross section (at middle of existing bridges)
149
Draft Detailed Report
Economy
Not only the material used, but also the safety of the construction work and the
construction budget for the ancillary structures such as the temporary bridge
structure, embankment road, and other temporary structures.
Conditions of construction
The available time frame for construction works, areas of construction, road traffic,
and the influence of vibration and noise.
Location
A bridge over a river shall not interfere with the water flow, and the cross-section of
the structure shall minimize the influence of the scouring of the river.
Aesthetics
The appearance of the bridge shall take the surrounding environments, such as the
urban, rural, or mountainous settings, into consideration.
150
Draft Detailed Report
6
Semi-gravity type
6 13
Reverse T type Adopted
10 20
Rear Buttress type
15
Rigid-frame type
12
Box type
Middle connection 15
type
Cross-section
151
Draft Detailed Report
152
Draft Detailed Report
T-Type Pier
With this design, the interference with the space under the bridge and water flow is
minimized, and the span length can be reduced further than other types, as well. The
suitable design height for this type of pier is around 20.0 m.
π -Type Pier
Advantageous for a skew bridge or in a condition where the bridge need to withstand
lateral force, such as an earthquake, as the design increases the rigidity of the pier.
The appropriate design height for this technology is around 30.0 m.
Table 3.10 below describes the pros and cons for different types of piers. Also, the
pros and cons take in to consideration the foundation depth of the pier, future
changes in the grounds, scouring by the water flow, the location of the bed rock
underneath the foundation, and construction efficiency.
Sectional
View
153
Draft Detailed Report
The loading combinations and partial factor of safety for different loading group
considered for the bridge design is given in Table 3.12, 3.13, and 3.14 respectively.
154
Draft Detailed Report
Earth pressure: retained fill and/or live load surcharge 1.000 1.650
155
Draft Detailed Report
were provided and analyzed to enhance lateral and torsion restraint to longitudinal
beams. The grillage analysis was performed for the superstructure, including
abutments and piers using Midas Civil and Master series design software. Further,
the bridge foundations, were designed based on relevant geotechnical parameters
from geotechnical investigation report.
156
Draft Detailed Report
6.2.1.1 Materials;
Materials types – construction materials, i.e., reinforcing steel, concrete materials,
structural steels, etc., locally available.
Materials service life –long lasting construction materials, i.e., strong and durable
against permanent and dynamic loading.
157
Draft Detailed Report
Roof structure – structural steel roof structures are light as possible to withstand
dead and dynamic impacts.
Foundation – foundation bases are wide enough capable to withstand static and
dynamic loading.
Structural systems – structural system is stable against static and dynamic loading,
with low center of gravity for earthquake resistance.
Structural details – structural members designed and detailed observing rules for
durability and seismic design.
Aesthetics – structural members have good appearance without the need for special
edge units or in-situ masking.
6.2.1.3 Manufacture/construction;
Structural steel self-weight – structural steel members are within lifting requirements
available in Tanzanian crane capacity.
Formwork for cast in situ and/or pre-cast concrete – formwork exist in Tanzanian
market, with affordable costs.
158
Draft Detailed Report
Steel grades – the required structural steel and reinforcing steel bars grades is
locally available and no need to be imported.
Stability during erection – structural members are stable during erection, and no
temporary supports required.
6.2.1.4 Maintenance
159
Draft Detailed Report
Actions on Structure
Part 4:1990: Concrete - Specification for the procedures to be used in sampling,
BS 5328
testing and assessing compliance of concrete
1997: Code of practice for Specification of carbon steel bars for the reinforcement of
BS 4449
concrete
Part 116 (1983) – Testing concrete — Method for determination of compressive
BS 1881
strength of concrete cubes
Part 107 (1983) – Testing concrete — Method for determination of density of
BS 1881
compacted fresh concrete
Part 106 (1983) – Testing concrete — Methods for determination of air content of fresh
BS 1881
concrete
1980: Methods of test for Water for making concrete (including notes on the suitability
BS 3148
of the water)
BS 882 1992: Specification for aggregates from natural sources for concrete
BS 812 Part 102 (1989) – Testing aggregates - Methods for sampling
BS 8004 1996: Code of practice for foundation
BD 30/87 Volume 2: Backfilled Retaining Walls and Bridge Abutments
Structural Steel Design
Part 1:2000: Structural use of steelwork in building - Code of practice for design —
Rolled and welded sections
Part 2:2001: Structural use of steelwork in building - Specification for materials,
fabrication and erection — Rolled and welded sections
Part 3:1990: Structural use of steelwork in building - Design in composite Construction
- Code of practice for design of simple and continuous composite beams
Part 4:1994: Structural use of steelwork in building - Code of practice for design of
BS 5950
composite slabs with profiled steel sheeting
Part 6:1995: Structural use of steelwork in building - Code of practice for design of light
gauge profiled steel sheeting
Part 7:1997: Structural use of steelwork in building - Specification for materials and
workmanship: cold formed sections
Part 8:1990: Structural use of steelwork in building - Code of practice for fire resistant
design
BS 4 Part 1:2005: Structural steel sections - Specification for hot-rolled sections
1986: Specification for covered carbon and carbon manganese steel electrodes for
BS 639
manual metal-arc welding
BS 729 1971: Specification for hot dip galvanized coatings on iron and steel articles
Part 1:1964: Specification for sprayed metal coatings. Protection of iron and steel by
BS 2569
aluminum and zinc against atmospheric corrosion
BS 4360 1990: Specification for weldable structural steels
BS 4190 2014: ISO metric black hexagon bolts, screws and nuts. Specification
BS 3692 2014: ISO metric precision hexagon bolts, screws and nuts. Specification
BS 4320 1968: Specification for metal washers for general engineering purposes. Metric series
Part 2:1991: Hot-rolled structural steel sections. Specification for hot-finished hollow
BS 4848
sections
160
Draft Detailed Report
Actions on Structure
Part 2:1969: Specification for high strength friction grip bolts and associated nuts and
BS 4395 washers for structural engineering. Higher grade bolts and nuts and general grade
washers
1977: Code of practice for protective coating of iron and steel structures against
BS 5493
corrosion
Masonry Design
Part 1 (1981): Pre-cast concrete masonry units. Specification for precast concrete
BS 6073
masonry units
BS 5224 1995: Specification for masonry cement
Part 3 (2005): Code of practice for the use of masonry. Materials and components,
BS 5628
design and workmanship
BS 5390 1976: Code of practice for stone masonry
Timber Design
BS 4978 2007: Visual strength grading of softwood. Specification
Part 2 (2002) - Structural use of timber. Code of practice for permissible stress design,
BS 5268
materials and workmanship
1997: Specification for manufacture of glued structural components of timber and
BS 6446
wood-based panels
161
Draft Detailed Report
components
Part 12:2005: Design of steel structures. Additional rules for the extension of EN
1993 up to steel grades S 700
Part 1:2004: Design of composite steel and concrete structures. General rules and
rules for buildings
BS EN 1994
Part 2:2004: Design of composite steel and concrete structures. General rules.
Structural fire design
DD ENV Part 1:2000: Execution of concrete Structures - Common
13670
Part 1:2005: Design of structures for earthquake resistance – General rules, seismic
actions and rules for buildings
BS EN 1998
Part 5:2009: Design of structures for earthquake resistance – Foundation, retaining
structures
162
Draft Detailed Report
163
Draft Detailed Report
7.1.1 Introduction
The objective of this report is to describe and explain all survey aspects relating to
the project topographic survey and utility survey of Bibi Titi road, Ali Hassan Mwinyi
road [Bibi Titi/Ohio junction to Morocco], Bagamoyo road [Morocco – Mwenge –
Tegeta] and Sam Nujoma road [Mwenge to Ubungo Sim2000] covering
approximately a total length of 30km.
The scope of the survey work required and undertaken for the project included the
following main aspects;
Establishment and observation of GPS Control Points (Primary Network).
Establishment of inter-visible stations/benchmarks along the entire length of the road
(Secondary Network).
164
Draft Detailed Report
The field operation commenced in 2nd September 2019, and field work
accomplished on 30th October 2019.
7.2.2 Equipment
Advanced survey equipment’s (GPS, total station and levels) were used for
survey operation.
165
Draft Detailed Report
Office Work
Three laptops
Leica Geo-office combined software for GPS vectors processing
Leica Geo-office tools for total station data download
Covadis software for traverse computations and CAD drawing
The selection of datum points to be used was done with consideration of the location
of the project route. Second order control points (refer table below) were used as
datum for this project and MLHSD advised us to use these points because they are
166
Draft Detailed Report
reliable and it was used in TAREF11 system conducted by the MLHSD during
control points establishment for the whole country. The points can allow the
transformation of ARC1960 to UTM WGS TAREF11 coordinates system and vice
versa. The following control points were used as planimetric datum.
Planimetric second order control points used as datum; Source the Ministry of Lands
and Human Settlement Development
The main consideration was the spread of these points in project location so as to
able to apply proper checks in all ends of the project.
167
Draft Detailed Report
Figure 7.1: Dar es Salaam height datum referred to Mean Sea level
Source. The Ministry of Lands and Human Settlement Development
These control points (both GPS points and benchmarks) were materialized by
precast concrete monument dimensioned as follows: 60 cm pvc pipe together with
15cm steel reinforcement bar centrally cast within a concrete 0.20 m diameter in
cross section and 0.60m length.
A total of 20 primary points were established for the whole road routes. During
planning some points for bridge Intersection’s project and Mwenge-Morocco section
project was recovered and these points planned to be used for BRT4 survey and to
168
Draft Detailed Report
provide the basis for check the correlation of the previous survey works for the two
projects in relation to ongoing BRT4 design work. All GPS control points were
painted yellow color for easy identification.
The photographs shown in figure1 below illustrate the type of materialization used.
See the details of control points as described in point’s description cards in Appendix
IV-
Point materialized by concrete monument with PVC pipe and iron bar
Section of approximately 3km Primary and Secondary points establishment and observation
G1 BM.
G BM. BM. G G10 BM.1
1 01 1 BM. BM.1 BM.1 BM.2 BM.3 G G10
BM.3
2 3 8 2 2 9
4 7 0 8 3 3 9
Km 0 Km 3
Km 9
Figure 7.3 Refer to location map below showing datum points used and new
road control points established.
169
Draft Detailed Report
170
Draft Detailed Report
satellites and precision can be viewed and hence know the best time for observation
under which you can obtain good number of satellites.
From the diagram above the best observation time was between 08:00AM to 12:00
and from 14:00 to 17:00PM
Mission planning can allow also viewing the individual satellite at the date of
observation
171
Draft Detailed Report
All points were occupied and the time of occupation differed from one point to
another depending on the length of the vector under observation but the minimum
occupation time for shorter vectors of 300m was 30minutes and time increased
according to the length of the vector. Data were downloaded and processed with use
of Leica Geo office combined Software LGO version 8.3. Based on control points
obtained from MLHSD, one point (UGPS.18) was fixed, and the remaining points
(UGP5 & T.08D) were freed in order to check the error closure. After adjustment the
error closure of these points are shown on the table below which are within
tolerance. Accuracy for established GPS-Primary control points;
All GPS vector computations and adjustment details of this project were submitted
refer Appendix 6.1 - 6.3 for computation details.
Figure 7.7: Static GPS Survey operations along the road, Source
Kunhwa survey October 2019
172
Draft Detailed Report
Final Adjusted Coordinates of GPS control points are indicated in Appendix I-2 of
this report and for GPS adjustment report refer to Appendix I-3.
Refer Appendix III for leveling computations details and Appendix I-1 and Appendix
I-2 for final levels of GPS points and all Benchmarks.
Starting from a couple of GPS control points (giving a fixed reference bearing) to the
next couple of GPS control points (also giving a fixed reference bearing) located 3
173
Draft Detailed Report
Km apart, the secondary traverse was performed in order to measure and compute
co-ordinates of the benchmarks. The misclosure observed between inter-visible
couples of GPS control points (angular and horizontal misclosures) were distributed
between the benchmarks constituting the secondary network (when meeting the
required tolerances). The adjusted co-ordinates were computed using Covadis
survey software. All traverse accuracy was checked under the requirement for urban
engineering survey which specify the minimum fractional linear misclosure of 1: 6000
and all traverse computed meet this requirement. Final coordinates of the
benchmarks are indicated in Appendix 6.1 – 6.2 of this report and refer Appendix 6.5
for details of all traverse computations and accuracy achieved.
Final coordinates of the benchmarks are indicated in Appendix I-2 of this report and
refer Appendix III for details of all levelling computations.
174
Draft Detailed Report
Cross-sections were generally surveyed at 25m intervals within the corridor. In order
to produce an accurate digital terrain model and topographical maps, both manmade
and natural features were measured in the following groups
All these features were captured with use of different codes. Finally, the files were
downloaded, checked and processed and produced DTM map using covadis
software. The map produced was used by the highway engineer in design work such
as horizontal alignment, vertical alignment, structure’s location design, volumes of
earth work calculation, haulage and finally used as design guideline tool for different
decisions making during design work. Also, primary and secondary control points
established will be used during construction for setting out work control and in other
design and construction work decision as per engineering discipline guidelines.
175
Draft Detailed Report
176
Draft Detailed Report
177
Draft Detailed Report
BM - Coordinates
Point n° Easting (X) Northing (Y) Height (Z) SF
BM.35 524178.677 9254498.386 33.254 0.999607
BM.36 524063.120 9254806.397 34.954 0.999607
BM.37 523824.962 9255589.699 21.273 0.999607
BM.38 523822.313 9255770.637 22.697 0.999607
BM.39 523755.318 9256143.123 34.948 0.999607
BM.40 523680.748 9256392.612 35.454 0.999607
BM.41 523631.063 9256554.075 33.915 0.999607
BM.42 523568.364 9256763.057 32.200 0.999607
BM.43 523481.633 9257049.349 29.589 0.999607
BM.44 523348.106 9257496.704 32.849 0.999607
BM.45 523221.732 9257922.528 33.835 0.999607
BM43-1 523415.911 9257269.446 30.388 0.999607
BM44-1 523277.395 9257732.324 32.079 0.999607
BM.46 522939.076 9258983.094 32.000 0.999606
BM.47 522863.311 9259263.709 32.626 0.999606
BM.48 522768.777 9259643.201 28.883 0.999606
BM.49 522686.323 9259976.951 25.943 0.999606
BM.50 522593.834 9260352.236 26.336 0.999606
BM.51 522477.479 9260834.058 40.053 0.999606
BM50-1 522551.227 9260531.868 31.903 0.999606
BM.52 521931.862 9261651.536 59.779 0.999606
BM.53 521572.990 9262175.560 52.070 0.999606
BM.54 521410.489 9262376.147 52.336 0.999606
BM.55 521330.184 9262497.503 47.239 0.999606
BM.56 521072.819 9262885.353 27.492 0.999605
BM.57 520907.121 9263132.590 30.726 0.999605
BM.58 520693.032 9263392.333 31.698 0.999605
BM52-1 521804.876 9261833.501 56.153 0.999606
BM55-1 521208.646 9262684.173 34.182 0.999606
BM.59 520001.310 9264175.468 28.090 0.999605
BM.60 519722.386 9264437.232 24.632 0.999605
BM.61 519494.281 9264703.747 23.040 0.999605
BM.63 519270.360 9264985.824 21.404 0.999605
BM.64 519012.788 9265214.041 20.612 0.999604
BM.65 518771.565 9265501.969 20.517 0.999604
BM65-1 518580.725 9265694.924 19.345 0.999604
178
Draft Detailed Report
The project route is located on the East Coastal Plains of Tanzania; areas which
form the low-lying lands and geologically consisting of sedimentary deposits that
range from Paleogene (66Ma) to Quaternary. Typical deposits of this timeline include
Kaolinitic sandstones, coral reef limestone, white buff sands and coral limestone
occurring in Dar es Salaam and alluvial deposits (clay, silt, sand, gravel, which are
recently deposited in the river valleys).
Exploratory boreholes for selected boreholes sites have shown that; silty SAND and
clayey SAND are the most dominant borehole materials for all bridge sites with
exception of Selander Bridge where clayey SAND, gravelly CLAY and limestone rock
is found. For Interchange sites, silty SAND and sandy CLAY are dominant borehole
materials found while clayey SAND appears to be dominant for all pedestrian
crossing sites.
The field test has shown that the SPT N values increase in some locations.
However, there is a decrease in strength with depth for all bridges. This indicates
that, the ground condition is changing depending on formation of the area.
Therefore, the design SPTN shall be based on the depth of the structure, however
179
Draft Detailed Report
the relationship between the depth and strength have been developed for design
purposes.
For Undrained Condition (Clay area), the design SPTN equations have been
developed, with z value taken as 0 at the ground level and increases with depth (m),
below ground level. Undrained shear strength in the clay formation can be
approximated from SPT N results using the equation, Cu= f1 × N where f1 is
obtained from the graph in Figure 5-1 for determination of strength and Undrained
Young’s Modulus, Eu=360xCu.
8.1 Introduction
8.1.1 Background
The investigation started on 25th September 2019 and was carried out by SGC
Limited Consulting Engineers. The field work was scheduled for 45 days, completed
on 9th November 2019.
180
Draft Detailed Report
• To carry out sampling for each borehole in accordance with the codes of
practise, schedule laboratory testing, analysis and interpretation of results
and.
• To make recommendation for foundation design.
8.1.3 Objectives
The principal objective of ground investigation was to establish ground conditions at
the site, sufficient to identify possible foundation solutions for development and
provide parameters necessary for the design and construction of foundations.
To take borehole sampling for carrying out laboratory testing for the purpose of
classifying the soils and other parameters at the site for disposal and remedies of the
ground failure.
The extent of the ground investigation carried out was to provide a general overview
of ground conditions likely to be encountered on site. The investigations carried out
at the site will be suitable for outline, scheme and comprehensive design
development.
181
Draft Detailed Report
Conditions on the site can vary with time and it is recommended that if development
is delayed, then consideration should be given to reviewing the findings of this
report, to ensure they are still valid and assess whether additional sampling and
testing would be required.
8.2.2 Topography
Dar es Salaam is located on the Coastal plains of Tanzania; areas which form the
low-lying lands with a number of hills in the eastern side as typically geological
setting elevations up to 1000 m above sea level (A.S.L). Most areas in the region
have been settled with few areas remaining under cultivation with scattered
settlements. Typical types of soils found include SAND and CLAYS soils with
moderate to good drainage.
The slope characteristics strongly determine the nature and intensity of soil erosion.
Subsequently, the topographical position influences the drainage and moisture
regime and has therefore a direct bearing on engineering foundations. Since the
area lie on the mouth of Indian oceans, vegetation are most mangrove woodland and
part of the soils are due to erosion resulting to consolidation of the natural ground.
8.2.3 Geology
8.2.3.1 Regional Geology
Dar es Salaam is geologically located on the East coastal plain of Tanzania which
was among the result of the Continental rifting process which also led to formation of
the East African Rift System (EARS). The East Coastal plains consist of sedimentary
182
Draft Detailed Report
183
Draft Detailed Report
Soils in Dar es Salaam are evenly distributed as the city lies up to 100m above Mean
Sea level. Generally, the soils are categorized as SAND and loamy SAND with good
drainage properties. Along the project routes, the soils are changing SAND, loamy
SAND and CLAY from Tegeta toward Bibi Titi/Maktaba road Junction via Morocco.
Branch line from Ubungo to Mwenge appears to have silty SAND soils.
184
Draft Detailed Report
Bridges, Interchanges and Pedestrian crossing are presented in the tables 8.1, 8.2
and 8.3 below.
8.3.2 Fieldwork
The setting out of exploratory drilling equipment’s for the first bridge at Tegeta
boreholes was commenced on 25th September 2019 under the supervision of
experienced Engineers and drillers. The Rotary boring equipment’s were used for
drilling works. The drilling works of boreholes for each completed bridge were
terminated at 15.0m, 20m, 26m and 40m depth respectively below the ground level.
In accordance with the Terms of Reference (ToR) and European Standards (EC7) -
BS EN 1997-2:2007, two boreholes were drilled namely BH01 and BH02.
185
Draft Detailed Report
Until 13th October 2019, four (4) bridges were completed for ground investigation as
proposed for two boreholes at each site. The bridges include Tegeta Bridge, Lugalo
Bridge, Mlalakuwa Bridge and Selander Bridge. Investigation for pedestrian
crossings were carried on 19th, 22nd and 30th of October and interchanges on 2nd
to 9th of November 2019.
Figure 8.3: Drilling works at Selander Bridge (BH02) and Mbuyuni Interchange
(BH01)
186
Draft Detailed Report
Standard penetration testing incorporates a small diameter tube with a cutting shoe
known as the ‘split barrel sampler’ of about 650mm length, 50mm external diameter
and 35mm internal diameter. The sampler is forced dynamically using blows from
chain-driven windowless sampler. The cutting shoe is bedded 150mm into the soil
then the number of blows required to drive the sampler each 75mm up to a depth of
300mm is recorded. This is known as the “N” value. The SPT’s values were
187
Draft Detailed Report
measured at the interval of 1.50m deep consecutive up to the terminating depth i.e.
15m and 20m respectively.
The groundwater level was monitored for each borehole within 24 hours at different
time interval of 6 hours for the first 12hours of the first day and thereafter at the same
interval on the second day for each reading. The reading of water level for each
borehole was recorded.
Table 8.4: Standard Penetration test (SPT N) results for boreholes for
Bridges
SPT-N VALUES
TEGETE LUGALO MLALAKUWA SELENDER
BRIDGE BRIDGE BRIDGE BRIDGE
Depth(m
BH01 BH02 BH01 BH02 BH01 BH02 BH01 BH02
)
1.50 20 17 21 6 17 27 41 7
3.00 37 19 38 15 11 24 22 22
4.50 42 21 47 21 11 28 22 50
6.00 43 47 87 14 30 36 11 50
7.50 38 32 42 44 32 38 11 50
9.00 32 36 44 46 40 38 8 77
10.50 32 42 51 68 45 30 7 58
12.00 41 44 67 85 34 35 11 44
13.50 35+ 39 60 46 19 40 12 45
15.00 30 49 65 51 16 35 14 48
16.50 10 73 43 15 53
18.00 40 91 43 17 27
19.50 21 77 50 43 21
21.00 59 28
22.50 30 29
24.00 39 29
25.50 44 31
27.00 30
28.50 35
30.00 46
188
Draft Detailed Report
SPT-N VALUES
TEGETE LUGALO MLALAKUWA SELENDER
BRIDGE BRIDGE BRIDGE BRIDGE
31.50 47
33.00 49
34.50 52
36.00 52
37.50 43
39.00 48
SPT-N VALUES
MBUYUNI INTERCHANGE GOBA INTERCHNAGE
Depth(m) BH01 BH02 BH01 BH02
1.50 10 10 7 8
3.00 15 16 10 13
4.50 16 30 25 22
6.00 25 23 20 23
7.50 27 32 32 15
9.00 21 18 35 24
10.50 36 26 33 27
12.00 46 25 41 34
13.50 48 35 32 52
15.00 40 27 36 63
16.50 30 53
18.00 49 33
19.50 48 41
189
Draft Detailed Report
8.3.3.2 Groundwater
The ground investigation conducted on the various location sites has revealed that,
there is existence of water below the ground level. These locations include Tegeta
bridge and Lugalo bridges and Tegeta Kibaoni and Mwenge junction. The initial
measurement was recorded after 12 hours on the completion of the drilling. The
water variations were recorded 24 hours after initial reading. It should be noted that,
these boreholes were drilled during dry to wet period, therefore it is anticipated that,
during the rainy season the rise of water table would be higher than the wet period
due to the nature and permeability of the soil. However, the rise of water table is not
expected where water rise was not available especially where the drilling place
during wet period and with occasional rains. The ground water rises and variation
records are shown in the table 8.7 below;
190
Draft Detailed Report
Table 8.7: Groundwater rise variation for proposed bridges along New
Bagamoyo road
GROUNDWATER LEVEL
SELANDE
TEGETE LUGALO MLALAKUWA
LOCATION R
BRIDGE BRIDGE BRIDGE
BRIDGE
BH BH
BOREHOLE BH01 BH02 BH01 BH02 BH01 BH02
01 02
INITIAL Reading(m) 13.5 12.4 7.8 5.3 NIL NIL 4.0 NIL
FINAL reading (aft. 24hrs)
11.2 12.0 3.5 4.8 NIL NIL NIL NIL
in meters
191
Draft Detailed Report
sedimentary sediments found deposited in layers over the area. The profiling and
logging of such strata were visualized on site and logging was done by the use of
software. Soil profiling for each borehole were taken as shown in the photo;
Figure 8.7: Soil strata and profiles from core box at Tegeta Bridge
Figure 8.8: Soil strata layout and profiles from core box at Lugalo Bridge
Figure 8.9: Soil strata layout and profiles from core box at Mlalakuwa Bridge
192
Draft Detailed Report
Figure 8.10: Soil strata layout and profiles from core box at Selander Bridge
Figure 8.11: Soil strata layout and profiles from core box at Mbuyuni Junction
Interchange
Figure 8.12: Soil strata layout and profiles from core box at Goba Junction
Interchange
The sequence of strata and ground conditions is will be presented in summary for
each bore on the draft report.
193
Draft Detailed Report
BH01 1.20 4.00 Greyish Green silty CLAY WITH Clayey SAND
SAND
4.00 5.00 Blackish Red silty CLAY with SAND Clayey SAND
5.00 8.20 Grayish Green silty CLAY with Clayey SAND
SAND
8.20 10.00 Greenish Black silty CLAY with Clayey SAND
10.00 15.00 SAND
Greenish Gray silty CLAY with Clayey SAND
SAND
0.00 0.80 Light brown silty soil Decomposed ground
0.80 3.00 Light Gray Clayey SAND Clayey SAND
3.00 5.00 Greyish Green silty CLAY with Clayey SAND
BH02
SAND
5.00 10.00 Light Gray silty CLAY with SAND Clayey SAND
10.00 15.00 Greyish silty SAND Silty SAND
15.00 20.00 Greyish silty SAND Silty SAND
194
Draft Detailed Report
Table 8.11: Summary of boreholes and ground conditions for Lugalo Bridge
Borehole Top (m) Base(m) (m) Description Stratum
(BH)
0.00 1.50 Light brown silty SAND Decomposed ground
BH01 1.50 3.00 Pale yellowish green CLAY with Clayey SAND
SAND
3.00 5.00 Greenish Black silty CLAY with Silty SAND
SAND
5.00 7.00 Brownish Black silty CLAY with Silty CLAY
SAND
7.00 9.00 Dark Greyish Gray silty CLAY with Clayey SAND
SAND
9.00 10.00 Light Greenish Gray CLAY with Clayey SAND
SAND
10.00 12.00 Yellowish Gray clayey SAND Clayey SAND
12.00 15.00 15.00 Greenish Black silty SAND Silty SAND
Table 8.12: Summary of boreholes and ground conditions for Tegeta Bridge
Borehole Top (m) Base(m) Description Stratum
(BH) (m)
0.00 1.00 Blackish silty CLAY with gravel Decomposed ground
1.00 2.20 Light grey clayey silty SAND Silty SAND
BH01
2.20 4.50 Yellowish orange silty SAND Silty SAND
4.50 5.20 Yellowish silty CLAY with sand Clayey SAND
5.20 13.25 Greyish Black Silty CLAY with Silty SAND
13.25 14.00 SANDGray silty CLAY with SAND
Light Silty SAND
14.00 20.00 Yellowish Gray CLAY GRAVEL GRAVELLY Clay
195
Draft Detailed Report
196
Draft Detailed Report
Table 8.15: Summary of boreholes and ground conditions for Tegeta Kibaoni
Pedestrian footbridge
Borehole Top (m) Base(m) Description Stratum
(BH) (m)
0.00 0.30 Whitish Grayish gravel material Fill material/layer
0.30 0.65 Brownish sand soil with gravel SAND
BH01
0.65 1.30 Blackish sand soil SAND
1.30 2.30 Light gray clay SAND Clay SAND
2.30 6.00 Grayish clay SILT Clay SILT
BH02
Table 8.16: Summary of boreholes and ground conditions for Mwenge
pedestrian footbridge
Borehole Top (m) Base(m) Description Stratum
(BH) (m)
0.00 0.20 Grayish sand soil SAND
0.20 0.60 Reddish brown soil with gravel Fill material/layer
BH01 0.60 1.00 Blackish silty sand Silty SAND
1.00 1.60 Dusky gray silty SAND Silty SAND
1.60 6.00 Gray silty SAND Silty SAND
Table 8.17: Summary of boreholes and ground conditions for Mlimani pedestrian
footbridge.
Borehole Top (m) Base(m) Description Stratum
(BH) (m)
0.00 2.00 Dark gray silty CLAY Silty CLAY
2.00 2.40 Medium gray CLAY with SAND Clayey SAND
BH01 2.40 3.00 Dark gray silty CLAY Silty CLAY
0.00 0.80 Reddish brown soil with gravel Fill material/layer
BH 02 0.80 5.20 Grayish silty SAND Silty SAND
5.20 6.00 Medium gray clayey SAND Clayey SAND
BH02
197
Draft Detailed Report
For Interchanges, silty SAND is dominant for Mbuyuni JN interchange while Goba
Junction boreholes indicated to have silty SAND and sandy CLAY materials. Silty
clayey SAND is dominant borehole material found in all the proposed sites for
pedestrian footbridge.
198
Draft Detailed Report
Bridges
Natural Moisture Content (%)
BRIDGE
Min. Max
Tegeta Bridge 3.19 30.54
Lugalo Bridge 4.31 19.56
Mlalakuwa Bridge 4.15 17.99
Selander Bridge 2.83 27.91
Natural Moisture Content range for Tegeta Bridge and Selander Bridge indicate that
the soil keeps water and become wet for long period due to the containment of clay
materials. The presence of high natural water content indicated also that; the
materials contain medium to stiff clay. Moisture content for Lugalo and Mlalakuwa
Bridges has indicated that there is more of SAND materials for explored boreholes
than clay contents.
Interchanges
Natural Moisture Content (%)
INTERCHANGE
Min. Max
Mbuyuni Interchange 5.77 12.30
Goba JCT Interchange 5.40 25.20
Moisture Content range for Goba Junction Interchange indicates that the soil keeps
water and become wet for long period of time due to containment of clay materials.
Low to high content of clay is also indicated from the laboratory test results as soil
behavior changes with depth at this location.
Pedestrian crossing
Natural Moisture Content (%)
PEDESTRIAN CROSSING
Min. Max
Tegeta Kibaoni/Nyuki 8.46 11.41
Mwenge 9.12 15.37
Mlimani 5.97 17.56
199
Draft Detailed Report
Bridges
Bulk Density (kN/m3)
BRIDGE
Min. Max Recommended for foundation
Tegeta Bridge 17.86 18.94 17.9
Lugalo Bridge 17.89 18.94 17.9
Mlalakuwa Bridge 18.73 18.96 18.7
Selander Bridge 18.03 18.95 18.0
Interchanges
Bulk Density (kN/m3)
INTERCHANGE
Min. Max Recommended for foundation
Mbuyuni 18.98 19.97 19.0
Goba 18.86 19.86 18.9
Overpass/Crossing
Bulk Density (kN/m3)
PEDESTRIAN CROSSING
Min. Max Recommended for foundation
Tegeta Kibaoni/Nyuki 18.92 19.89 18.9
Mwenge 18.94 19.85 18.9
Mlimani 19.10 19.45 19.0
Bridges
The Atterberg limit results for bridges have shown that, the soil materials on the site
range from silty SAND to clayey soil of high plasticity. These properties are changing
with the depth below ground level. Summary of Plasticity limits range values is
presented in the table below;
200
Draft Detailed Report
Interchanges
The limit values for interchanges indicate that soil materials on the site range are
mainly silty SAND for Mbuyuni while Goba consist of sand CLAY and silty SAND as
dominant borehole materials. High Liquid limit values for Goba Junction indicates the
presence of clay materials of high plasticity for this site. Summary is presented in the
table below;
Pedestrian crossing
Plasticity Limits for Pedestrian crossing have shown materials on the site are mostly
silty clayey SAND of medium plasticity with relatively minor changes with depth
below the ground level. Summary of Plasticity limits range values is presented in the
table below;
Bridges
Due to existence of silty and cohesive soils (CLAY properties), the materials has
shown to consist of medium to high shrinkage/swelling properties during the tests.
Generally, linear shrinkage for the soils from the boreholes range from 3.21% to
201
Draft Detailed Report
11.07%. This ability of soils to drastically change volume may cause damage to the
structures, such as cracks in the foundation.
Interchanges
Linear Shrinkage (%) Recommended for
No. INTERCHANGE
Min Max foundation design
1. Mbuyuni 3.57 6.43 6.43
2. Goba 1.00 10.71 10.71
Pedestrian crossing
PEDESTRIAN Linear Shrinkage (%) Recommended for
No.
CROSSING Min Max foundation design
1. Tegeta Kibaoni/Nyuki 5.71 11.43 11.43
2. Mwenge 4.29 7.50 7.50
3. Mlimani 5.36 7.86 7.86
202
Draft Detailed Report
Bridges
Shear Strength parameters
Min. Max Recommended for
foundation design
BRIDGE
Interchanges
Shear Strength parameters
Min. Max Recommended for
foundation design
INTERCHANGE
C’ ø’ ()
C’ (kN/m2) ø’ () C’ (kN/m2) ø’ ()
Mbuyuni 12.85 21 15.79 20 16 20
Goba Jn 16.18 18 37.85 15 38 15
Pedestrian crossing
Shear Strength parameters
C’
C’ ø’ ()
C’ (kN/m2) ø’ () (kN/m2) ø’ ()
Tegeta Kibaoni 24.52 20 30.5 20 30 20
Mwenge 13.14 20 19.52 17 19 17
Mlimani 18.53 24 27.95 21 28 21
8.3.5.10 Consolidation
The test results for consolidation has shown the soil consist of coefficient of volume
compressibility, mv and coefficient of compressibility index, C varies as indicated in
the tables below;
203
Draft Detailed Report
Bridges
Consolidation
BRIDGE Min. Max
Mv( m2/kN) Cc Mv (m2/kN) Cc
Tegeta Bridge 0.0332 0.245 0.0363 0.2719
Lugalo Bridge 0.0286 0.207 0.03335 0.2429
Mlalakuwa Bridge 0.0291 0.2041 0.036 0.2685
Selander Bridge 0.0294 0.2135 0.0351 0.2566
Interchanges
Consolidation
INTERCHANGE Min. Max
Mv( m2/kN) Cc Mv (m2/kN) Cc
Mbuyuni 0.012 0.0843 0.0143 0.1056
Goba 0.0165 0.1169 0.0441 0.3351
Pedestrian crossing
Consolidation
PEDESTRIAN
Min. Max
CROSSING
Mv( m2/kN) Cc Mv (m2/kN) Cc
Tegeta Kibaoni 0.0306 0.2276 0.0404 0.3061
Mwenge 0.0174 0.1298 0.0202 0.1531
Mlimani 0.0173 0.123 0.034 0.25
This report has been prepared independently based on the terms of reference
obtained from client representative herein after is called AQGOLA Engineering &
Management Services Limited to carry out Geotechnical Investigation Surveys for
BRT Infrastructures Phase 4. The geotechnical assessment is based on the in-situ
laboratory testing described in this report (Part I. Bridges, Interchanges and
Pedestrian Crossings) together with the soil descriptions on the exploratory borehole
logs and its summary.
204
Draft Detailed Report
8.3.6.2 Classification
One hundred and fifteen (115) tests on particle size distribution were conducted for
all boreholes for bridges of which SPTs samples were taken to the laboratory `for
testing. The laboratory classification has indicated about 14%-45% of total weight of
samples is composed of Silt CLAY. The percentage of Sand varies between 57%-
91%particles while the percentage of gravel is less than 10%. In this case, the
percentage of silt CLAY and clayey SAND indicate that the site has accumulated fine
particles/residual soil transported by sea waves and consolidated into the place for
long time forming loose sand to soft CLAYS.
8.3.6.3 Strength
The field test has shown the SPT N values to increase in some location. However,
there is a decrease in strength with depth for all bridges. This indicates that, the
ground condition is changing depending on formation of the area. The SPTN values
for Tegeta Bridge, SPT-N values ranges from 17 to 44 and with refusal state at
13.5m depth below ground level. For Lugalo Bridge SPT N values range from 6 to 91
with progressive increase for each borehole which indicate increase in strength.
SPT-N values for Mlalakuwa Bridge varies from 11 to 50 with minor changes in SPT
N values due to change in strength while for Selander Bridge SPT N values range
from 7 to 77 with occurrence of change in strength as depth increase.
For Interchanges, SPTN values varies 10 to 49 and 7 to 43 for Mbuyuni and Goba
respectively, therefore 10 and 7 can be taken as design SPTN strength values for
Mbuyuni and Goba interchange.
For Pedestrian crossings, SPTN values varies from 3 to 51 with progressive increase
in SPTN values for each site, however the largest results are not soil characteristics,
therefore the outliers shall be excluded in the design. Therefore, the design SPTN
shall be based on the depth of the structure, however the relationship between the
depth and strength have been developed for design purpose. For this case, the
design SPTN values can be derived from the following equations whereby the initial
measurement is taken at 1.5m below the ground level.
205
Draft Detailed Report
8.3.7 Stiffness
8.3.7.1 Clay Formation
The SPT N for clay formation range between 9 and 23, however the largest results
are not soil characteristics. Therefore, the design SPT N values for bridges shall be
taken as N equals to 22, 17, 15 and 17 for Selander, Mlalakuwa Lugalo and Tegeta
respectively. For interchanges, design SPTN value shall be taken as 10. Design
SPTN values for pedestrian crossing shall be taken as 10, 11 and 13 for Tegeta
Nyuki, Mwenge and Mlimani respectively.
Undrained shear strength in the clay formation can be approximated from SPT N
results using the equation
Cu= f1 × N ………………………………………………. (1) where N is design SPTN on
a clay formation
206
Draft Detailed Report
[Clayton, CIRIA Report 143, Standard Penetration Test (SPT): Methods and Use,
1995]. The Plasticity Index PI for the sampled soil is considered high when it more
than 14%. For the design purposes, the highest PI shall be considered. The value
of f1 may be obtained from Stroud and Butler Graph shown in the figure below.
The Effective Young’s Modulus is found from the equation, E’=0.6Eu (3)
Or in considering volume compressibility, mv, the drained modulus can be deduced
from
207
Draft Detailed Report
mv=1/E’…………………………………………………………………… (4)
[Padfield and Sharrock, CIRIA Special Publication 27, Settlement of
Structures on Clay Soils, 1983]
208
Draft Detailed Report
potential of a soil in comparison is the magnitude of heave of a soil for a given final
water content and loading condition.
209
Draft Detailed Report
Figure 8.14: Relationship between swell index and liquid limit for clay soil
Chen, 1988)
210
Draft Detailed Report
bq = bγ = (1 − α. tanφ′ )2
— the shape of foundation:
sq = 1 + (B′ ⁄L′ ) sin φ′ , for rectangular shape
sq = 1 + sin φ′ , for a square or circular shape
sγ = 1 − 0.3(B′ ⁄L′ , for rectangular shape
sγ = 0.7 , for a square or circular shape
sc = (sq . Nq )⁄(Nq − 1) , for resctangular, square or circular shape
8.3.7.8 Excavations
According to the site assessment, the site does not require specialised technology
for excavations during construction. Care shall be taken when water rises from the
ground which eventually requires prevention either by pumping or using
impermeable wall system. The use of sump pumping or similar to collect water from
excavation during construction is recommended.
211
Draft Detailed Report
Executive Summary
The principal purpose of the site investigation surveys is to recommend the type of
foundation for the proposed development on various, terminals, depots buildings and
BRT stations to be proposed.
The project route is located on the East Coastal Plains of Tanzania; areas which
form the low-lying lands and geologically consisting of sedimentary deposits that
range from Paleogene (66Ma) to Quaternary. Typical deposits of this timeline include
Kaolinitic sandstones, coral reef limestone, white buff sands and coral limestone
occurring in Dar es Salaam and alluvial deposits (clay, silt, sand, gravel, which are
recently deposited in the river valleys). Exploratory boreholes have seen to consist of
mostly silty SAND. CLAY sands are dominated on few boreholes at Tank Bovu and
212
Draft Detailed Report
Mjengoni (UDSM Hostel) where CLAY of high and low plasticity is found
respectively.
Field tests have shown that Standard Penetration Test (SPT-N value) for values for
depots varies from 6 to 45 with progressive increase with depth. Hence for drained
condition, design SPTN values can be taken as equation for straight line; SPTN= 6 +
6Z, where SPT N is starting at 1.5m below ground level. The Young’s Modulus in
Sand/Gravel can be approximated directly by; E’/N = 1.25 MPa (Clayton, CIRIA
Report 143, 1995) where is design SPT N values.
For Undrained Condition (Clay area), the design SPTN= 8 + 3.0 Z, where z is 0 at
1.5m below ground level and increases with depth, in meters, below ground level.
Undrained shear strength in the clay formation can be approximated from SPT N
results using the equation, Cu= f1 × N where f1=4.5 and Undrained Young’s
Modulus, Eu=360xCu.
It is recommended that shallow foundations with structure that can be kept isolated
from the swelling effects of the soils. This consists of pad or strip for Bus stations
surrounded by high quality materials i.e., materials with CBR >15%. For drained sites
such as Mbuyuni and Mawasiliano for short buildings and raft foundation for tall
building greater than two (4) storeys and for areas with low land areas. The building
foundations shall be raised to about 0.9m above ground level to avoid water
ponding.
213
Draft Detailed Report
8.4.1 Objectives
The principal objective of ground investigation was to establish ground conditions at
the site, sufficient to identify possible foundation solutions for development and
provide parameters necessary for the design and construction of foundations.
(i) To take borehole sampling for carrying out laboratory testing for the
purpose of classifying the soils and other parameters at the site for
disposal and remedies of the ground failure.
(ii) To interpreted the ground conditions and laboratory results for
recommendation of suitable foundation for the proposed structure/building.
The extent of the ground investigation carried out was to provide a general overview
of ground conditions likely to be encountered on site. The investigations carried out
at the site will be suitable for outline, scheme and comprehensive design
development.
214
Draft Detailed Report
Conditions on the site can vary with time and it is recommended that if development
is delayed, then consideration should be given to reviewing the findings of this
report, to ensure they are still valid and assess whether additional sampling and
testing would be required.
215
Draft Detailed Report
8.4.3.2 Fieldwork
The setting out of exploratory drilling equipment’s for the first Depot at Mawasiliano
was commenced on 14th October 2019 to under the supervision of experienced
Engineers and drillers. The investigations were conducted in accordance with the
Terms of Reference (ToR) and European Standards (EC7) - BS EN 1997-2:2007.
The Rotary boring equipment’s were used for drilling works. The drilling works for
each completed Depot Terminal was terminated at 4.50m and 6.0m respectively
from the ground level. However, for Bus stations, the drilling works terminated at
3.0m from the ground level.
216
Draft Detailed Report
Figure 8.15: Drilling works at Super-Lugalo and Morocco Station using Rotary
Drilling equipment and Hand Auger respectively.
Standard penetration testing incorporates a small diameter tube with a cutting shoe
known as the ‘split barrel sampler’ of about 650mm length, 50mm external diameter
and 35mm internal diameter. The sampler is forced dynamically using blows from
chain-driven windowless sampler. The cutting shoe is bedded 150mm into the soil
then the number of blows required to drive the sampler each 75mm up to a depth of
300mm is recorded. This is known as the “N” value. The SPT’s values were
measured at the interval of 1.50m deep consecutive up to the terminating depth i.e.
15m and 20m respectively.
The groundwater level was monitored for each borehole within 24 hours at different
time interval of 6 hours for the first 12hours of the first day and thereafter at the same
interval on the second day for each reading. The reading of water level for each
borehole was recorded.
217
Draft Detailed Report
Table 8.20: Standard Penetration test (SPT N) results for boreholes for Depots
and Terminal
SPT-N VALUES
MBUYUNI DEPOT SIMU 2000 DEPOT DAWASA TERMINAL
Depth(m) BH01 BH02 BH03 BH01 BH02 BH01 BH02
1.50 15 18 6 15 14 28 14
3.00 36 38 11 40 30 22 21
4.50 40 45 17 42 23 27 33
6.00 36 25
Table 8.21: Standard Penetration test (SPT N) results for BRT Stations
SPT-N VALUES
Depth (m)
STATION BOREHOLE 1.50 3.00
1 Aga khan BH-01 10 31
2 Selander BH-01 9 14
3 Ubalozi BH-01 29 38
4 Mbuyuni BH-01 10 26
5 Morocco BH-01 8 22
6 Victoria BH-01 18 13
7 Mpakani BH-01 6 18
8 Mlimani-roundabout BH-01 5 14
9 Mjengoni-UDSM Hostel BH-01 3 9
10 Super-Lugalo BH-01 24 19
11 Tank Bovu BH-01 8 17
12 Goig BH-01 6 19
13 Interchick BH-01 10 17
14 Afrikana BH-01 13 16
15 Kituo Kipya BH-01 6 8
16 JKT BH-01 4 6
17 Bondeni BH-01 7 23
18 Azania BH-01 21 26
19 Namanga BH-01 12 18
218
Draft Detailed Report
8.4.3.5 Groundwater
The investigation conducted on the boreholes over the sites has revealed that
depots, terminal and BRT station locations had no water below the ground level. It
should be noted that, these boreholes were drilled during the wet period and
occasional rains, therefore it is not anticipated the rise of water table during the dry
period, however due to nature and the permeability of the soil the influence of water
from external phenomenon such as pipping and collapse of drainage system may
occur.
219
Draft Detailed Report
logging of such strata were visualized on site and logging was done by the use of
software. Soil profiling for each borehole were taken as shown in the photos below;
Figure 8.17: Soil strata layout and profiles from core box at Mawasiliano
Depot (BH01 & BH02)
Figure 8.19: Soil strata layout and profiles from core box at Agha Khan
Station
220
Draft Detailed Report
Figure 8.20: Soil strata layout and profiles from core box at Morocco
Station
Figure 8.21: Soil strata layout and profile from core box at Mjengoni-
UDSM Hostel Station
Figure 8.22: Soil strata and profile from core box at Tank Bovu station
221
Draft Detailed Report
Table 8.22: Summary of boreholes and ground conditions for Mbuyuni Depots
Borehole Top (m) Base(m) Description Stratum
(BH) (m)
0.00 0.40 Blackish top soil Decomposed ground
0.40 2.60 Moderate reddish-brown sandy SILT Sandy SILT
BH01 2.60 4.50 Moderate reddish-brown SILT SILT
0.00 0.80 Dusky brown top soil Decomposed ground
BH 02 0.80 3.70 Moderate reddish-brown SAND SAND
3.70 4.50 Moderate reddish orange SAND SAND
0.00 0.20 Moderate orange pink Sand soil SAND
BH 03 0.20 0.35 Grayish red SAND SAND
0.35 0.60 Very dusky red Sand SAND
BH02
0.60 4.50 Moderate reddish-brown Sand SAND
222
Draft Detailed Report
Table 8.25: Summary of boreholes and ground conditions for BRT stations
AGHA KHAN
Borehole Top (m) Base(m) Description Stratum
(BH) (m)
0.00 0.35 Blackish/reddish soil with gravel Fill material/layer
0.35 1.00 Very dusk red SAND SAND
BH01
1.00 2.20 Moderate brown SAND SAND
2.20 3.00 Grayish silty SAND Silty SAND
SELANDER
Borehole Top (m) Base(m) Description Stratum
(BH) (m)
0.00 0.50 Blackish sand soil SAND
BH01
0.50 0.90 Light brown SAND SAND
0.90 3.00 Whitish orange SAND SAND
UBALOZI
Borehole Top (m) Base(m) Description Stratum
(BH) (m)
0.00 0.30 Blackish sand soil SAND
BH01
0.30 0.70 Moderate reddish-brown silty SAND Silty SAND
0.70 3.00 Light red soil with gravel Fill material/layer
MBUYUNI
Borehole Top (m) Base(m) Description Stratum
(BH) (m)
BH01 0.00 0.20 Blackish top soil(sand) SAND
0.20 3.00 Light red soil with gravel Fill material/layer
MOROCCO
Borehole Top (m) Base(m) Description Stratum
(BH) (m)
0.00 0.40 Blackish top soil with gravel Decomposed ground
BH01
0.40 1.00 Very dusky red silty SAND Silty SAND
1.00 2.80 Moderate reddish-brown silty SAND Silty SAND
2.80 3.00 Soft limestone rock Limestone
VICTORIA
Borehole Top (m) Base(m) Description Stratum
(BH) (m)
0.00 0.20 Blackish top soil Decomposed ground
0.20 0.40 Reddish brown soil with gravel Fill material/layer
BH01
0.40 1.60 Blackish red SAND SAND
1.60 2.50 Grayish SAND SAND
2.50 3.00 Pale red silty SAND Silty SAND
MPAKANI/LUFUNGILA
Borehole Top (m) Base(m) Description Stratum
(BH) (m)
0.00 0.60 Reddish brown sand soil with gravel Fill material/layer
BH01
0.60 1.00 Moderate brown sand SAND
223
Draft Detailed Report
MLIMANI Roundabout
Borehole Top (m) Base(m) Description Stratum
(BH) (m)
0.00 0.25 Blackish top soil Decomposed ground
BH01
0.25 0.50 Reddish soil with gravel Fill material/layer
0.50 2.50 Dark Gray silty CLAY Silty CLAY
2.50 3.00 Medium Gray clayey SAND Clayey SAND
MJENGONI
Borehole Top (m) Base(m) Description Stratum
(BH) (m)
0.00 0.50 Light Gray SAND SAND
BH01
0.50 1.60 Dark Gray silty CLAY Silty CLAY
1.60 3.00 Medium Gray silty CLAY Silty CLAY
SUPER-LUGALO
Borehole Top (m) Base(m) Description Stratum
(BH) (m)
0.00 0.30 Blackish soil with gravel Fill material/layer
BH01
0.30 0.70 Dark red/brown reddish silty CLAY Silty CLAY
0.70 3.00 Brownish-pale red silt SILT
TANK BOVU
Borehole Top (m) Base(m) Description Stratum
(BH) (m)
0.00 0.50 Brownish/reddish brown soil with Fill material/layer
BH01 gravel
0.50 1.25 Blackish CLAY (black cotton clay) CLAY
1.25 3.00 Dark Gray CLAY CLAY
GOIG
Borehole Top (m) Base(m) Description Stratum
(BH) (m)
0.00 3.00 Dusky Gray soft CLAY CLAY
BH01
INTERCHICK
Borehole Top (m) Base(m) Description Stratum
(BH) (m)
0.00 0.25 Blackish soil with gravel Fill material/layer
BH01
0.25 1.00 Dusky Gray clayey SAND Clayey SAND
1.00 3.00 Dusky Gray soft CLAY CLAY
AFRIKANA
Borehole Top (m) Base(m) Description Stratum
(BH) (m)
0.00 2.00 Blackish red sandy SILT Sandy SILT
BH01
2.00 3.00 Grayish red SILT SILT
KITUO KIPYA
Borehole Top (m) Base(m) Description Stratum
(BH) (m)
0.00 0.30 Moderate brown SAND with gravel SAND
224
Draft Detailed Report
JKT
Borehole Top (m) Base(m) Description Stratum
(BH) (m)
BH01 0.00 0.40 Light red soil with gravel Fill material/layer
0.40 3.00 Dusky red sandy SILT Sandy SILT
BONDENI
Borehole Top (m) Base(m) Description Stratum
(BH) (m)
0.00 0.30 Medium gray sand soil SAND
BH01
0.30 1.00 Dusky red sandy SILT Sandy SILT
1.00 3.00 Grayish clayey SILT Clayey SILT
AZANIA
Borehole Top (m) Base(m) Description Stratum
(BH) (m)
0.00 0.30 Dark gray/black soil with gravel Fill material/layer
BH01
0.30 1.60 Blackish clayey SILT Clayey SILT
1.60 3.00 Grayish clayey SAND Clayey SAND
NAMANGA
Borehole Top (m) Base(m) Description Stratum
(BH) (m)
0.00 0.20 Light Gray SAND SAND
0.20 0.45 Reddish brown soil with gravel Fill material/layer
BH01
0.45 0.70 Grayish red SAND SAND
0.70 1.20 Dark gray SAND SAND
1.20 2.20 Light gray SAND SAND
2.20 3.00 Moderate red silty SAND Silty SAND
225
Draft Detailed Report
BRT Stations
Moisture Content values for stations range from 3.26% to 22.95%. Tank Bovu station
has high moisture content due to containment of clay materials which keeps water
and become wet for long period of time. Also, from the test results Agha Khan has
low moisture content values having low to non-plastic soils.
226
Draft Detailed Report
BRT Stations
Bulk density/unit weight values for BRT Stations have been summarized in Table
4.1.
BRT Stations
Generally, plasticity limits for stations range from 10.14% to 35.91%, indicating most
materials from boreholes are of medium plasticity.
227
Draft Detailed Report
Laboratory test results have indicated materials of medium to high plasticity from
Super-Lugalo station to Azania Station with notable high plastic materials at Tank
Bovu. These materials range from silty CLAY to clayey SAND of medium plasticity.
From Agha Khan to Victoria Station together with stations between Ubungo-Mwenge
branch line have indicated low to non-plastic soils. Summary of Plasticity limits range
for station has been presented in Table 4.1.
BRT Stations
For BRT Stations, linear shrinkage for soils range from 4.57% to 10.17% as
indicated I Table 4.1.
228
Draft Detailed Report
BRT Stations
Specific gravity for borehole materials from the stations are presented in Table 4.1.
BRT Stations
The test results for BRT Stations have shown the soil consists shear strength, with
values ranging from C’= 0.88kN/m2 or kPa with angle shearing resistance ø’= 24° to
C’= 29.91kN/m2 or kPa with angle shearing resistance ø’= 18°. From the tests
results, it can be concluded that the materials on the site consist of very soft to soft
clay. The design strength may be taken as 18kPa for Non-Cohesive soils and 30kPa
for cohesive soil areas. Summary of shear strength parameters for BRT Stations has
been presented in Table 4.1
8.4.4.10 Consolidation
The test results for consolidation have shown the soil consist of coefficient of volume
compressibility, mv and coefficient of compressibility index, c. The summary of
coefficients is presented in the table below;
229
Draft Detailed Report
BRT Stations
Consolidation parameters for BRT Stations are presented in Table 4.1
Table 8.27: Summary of results for Geotechnical tested parameters for BRT
Stations
BRT STATION BULK DENSITY SPECIFIC GRAVITY PI(%) LINEAR SHRINKAGE SHEAR STRENGTH CONSOLIDATION
kN/m3 (%) C (kN/m2) Mv (m2/Kg) Cc
1 Aga khan 18.12 2.636 14.21 4.57 13.53 18 0.0272 0.1957
2 Selander 17.92 2.664 0.88 24 0.0307 0.2252
3 Ubalozi 18.49 2.667 19.57 6.43 17.65 19 0.307 0.2252
4 Mbuyuni 19.86 2.671 19.73 6.57 17.75 19 0.0246 0.1758
5 Morocco 18.24 2.654 27.91 7.4 27.46 16 0.0332 0.2458
6 Victoria 17.88 2.667 21.58 7.29 27.16 16 0.0317 0.2305
7 Mpakani/Lufungila 19.24 2.671 19.81 6.14 18.34 18 0.0288 0.2059
8 Mlimani-roundabout 18.47 2.668 19.31 6.21 15.1 19 0.0275 0.1944
9 Mjengoni 18.97 2.668 17.31 6 14.42 20 0.0262 0.186
10 Super-lugalo 19.43 2.669 22.49 5.86 16.38 19 0.0284 0.2027
11 Tank Bovu 19.24 2.676 27.48 7.5 27.95 17 0.0344 0.2556
12 Goig 18.87 2.668 22.07 7.14
13 Interchick 19.61 2.678 24.48 6.57
14 Afrikana 19.44 2.672 21.15 5.86
15 Kituo Kipya 19.88 2.67 28.61 7.86
16 JKT 18.77 2.669 23.6 7.14
17 Bondeni 19.62 2.678 35.91 10.17 29.91 18 0.0401 0.3009
This report has been prepared independently based on the terms of reference
obtained from client representative herein after is called AQGOLA Engineering &
Management Services Limited to carry out Geotechnical Investigation Surveys for
BRT Infrastructures Phase 4. The geotechnical assessment is based on the in-situ
and laboratory testing described in this report (Part II. Depots, Terminal and BRT
230
Draft Detailed Report
Stations) together with the soil descriptions on the exploratory borehole logs and its
summary.
8.4.5.2 Classification
Sixty-five (65) tests on particle size distribution were conducted for all boreholes for
depots, terminal and BRT Stations of which SPTs samples were taken to the
laboratory for testing. The laboratory classification has indicated about 15%-57% of
total weight of samples is composed of Silt CLAY. The percentage of Sand varies
between 60%-95%particles while the percentage of gravel is less than 6%. In this
case, the percentage of silt CLAY and SAND indicate that the site has accumulated
fine particles/residual soil transported by sea waves and consolidated into the place
for long time forming loose sand to soft CLAYS.
8.4.5.3 Strength
Field tests have shown that Standard Penetration Test (SPT-N value) for values for
depots varies from 6 to 45 with progressive increase for each borehole at Mbuyuni.
The design SPTN may be taken as 6. For Simu 2000/Mawasiliano depot and
DAWASA terminal, the SPTN values varies from 14 to 42 therefore the design SPTN
strength may be taken as 14. Therefore, approximately design values for different
strata formation can be expressed as the function of depth using the following
formula;
Therefore, approximately design values for BRT bus stand for different strata
formation can be grouped for various locations of the project as follow;
231
Draft Detailed Report
Table 8.28: Grouped strata formation for various locations of the project
Road Section Design Comments
SPTN
Maktaba Juct to Aga Khan Jct 10 Medium silty SAND
Aga Khan Jct to Selander Bridge 9 Medium silty SAND
Selander Bridge to Morocco 8 Medium silty SAND
Morocco to Mwenge 18 Existence of Porewater pressure and silty
clay/sand area
Mwenge to Superstar (Sam Nujoma 5 Medium to High Clay area
rd)
Superstar to Mawasiliano (Sam 3 High soft Clay area
Nujoma rd)
Mwenge to Lugalo Bridge 19 Silty clay and gravel
Lugalo Bridge to Goba Junction 6 Highly soft Clay area
Goba Junction to Afrikana 10 Medium silty Clay
Africana to Tegeta Kibaoni 6 Gravel sand with clay
Tegeta Kibaoni to Boko 12 Silty Clay with gravel
8.4.5.4 Stiffness
8.4.5.4.1 Clay Formation
The SPT N for clay formation range between 14 and 42 for Simu 2000/Mawasiliano,
6 and 45 for Mbuyuni depot and 14 and 33 for DAWASA Terminal; however, the
largest results are not soil characteristics. Therefore, the design SPT N value shall
be taken as N=14. There is a distinct increase in SPT N value with depth, therefore
design values can be expressed as a function of depth using the following formula;
SPTN= 8 + 3.0 Z, where z is 0 at 1.5m below ground level and increases with depth,
in metres, below ground level.
Undrained shear strength in the clay formation can be approximated from SPT N
results using the equation
232
Draft Detailed Report
Figure 8.23: The graph of f1 vs. PI (Stroud and Buter) for determination
of shear strength
The Effective Young’s Modulus is found from the equation, E’=0.6Eu (3)
Or in considering volume compressibility, mv, the drained modulus can be deduced
from
233
Draft Detailed Report
mv=1/E’…………………………………………………………………… (4)
[Padfield and Sharrock, CIRIA Special Publication 27, Settlement of
Structures on Clay Soils, 1983]
234
Draft Detailed Report
The swell potential of clay can be identified based on the concept of swell index, Is
(Vijayvergiya and Gazzaly, 1973)
IS= Wn/WL Is= 41.14/69.08= 0.60
Where wn= natural moisture content (%)
WL= liquid limit (%)
Swelling potential of the soil is given as a function of the plasticity index
by the formula (Seed et al. 1962) as;
SP=60KIp2.24 where Sp= swelling potential
Ip= plasticity index
K= 3.6×10-5, a factor for clay content between
8% and 65%
Therefore, Sp= 60× 3.6×10-5×32.072.44= 10.22%
From figure, minimum swelling pressure required to prevent volume expansion of the
soil in the proposed site is between 30kPa and 130kPa.
235
Draft Detailed Report
Figure 8.24: Relationship between swell index and liquid limit for clay soil
(Chen, 1988)
236
Draft Detailed Report
bq = bγ = (1 − α. tanφ′ )2
— the shape of foundation:
sq = 1 + (B′ ⁄L′ ) sin φ′ , for rectangular shape
sq = 1 + sin φ′ , for a square or circular shape
sγ = 1 − 0.3(B′ ⁄L′ , for rectangular shape
sγ = 0.7 , for a square or circular shape
sc = (sq . Nq )⁄(Nq − 1) , for resctangular, square or circular shape
8.4.5.5.5 Excavations
According to the site assessment, the site does not require specialized technology
for excavations during construction. Care shall be taken when water rises from the
ground which eventually requires prevention either by pumping or using
impermeable wall system.
The use of sump pumping or similar to collect water from excavation during
construction is recommended. When CLAY materials are encountered during
237
Draft Detailed Report
excavation, the excavation shall be continuing for extra depth between 300-600mm
down and replacement with high quality materials on the same depth i.e. 300-
600mm.
8.4.6.1 Foundations
Bus stations; Shallow foundations with structure that can be kept isolated from the
swelling effects of the soils. This consists of pad or strip surrounded by high quality
materials i.e., materials with CBR >15%. The reinforcement on the foundation and at
plinth level is necessary to avoid differential settlement.
Depot and Terminal Buildings: Shallow foundation for drained sites such as Mbuyuni
and Mawasiliano for short buildings and raft foundation for tall building greater than
two (4) storeys and for areas with low land areas. The building foundations shall be
raised to about 0.9m above ground level to avoid water ponding especially areas
such as DAWASA Terminal.
238
Draft Detailed Report
8.4.6.2 Excavations
The site does not require specialized technology for excavations during construction.
The removal of top soil shall continue between 0.4m to 0.5m depending on the
ground conditions. The occurrence of water rise is predicted during excavation;
hence prevention either by pumping or using impermeable wall system is necessary.
It has recommended the use of sump pumping or similar to collect water from
excavation during construction when encountered.
239
Draft Detailed Report
240
Draft Detailed Report
Approach
Traffic control techniques during construction require three stages of construction of
Bibi Titi Mohammed Road as illustrated in Figures 9.2 to 9.4.
Due to the small width of the existing median, the existing sidewalks will be
constructed for the use of mixed traffic to allow enough space in the mid of the road
for construction of BRT lanes. One side at a time should be the approach so as to
allow non-motorized traffic to use existing walkway pavements on one side while
providing crosswalks at an interval of not more 200m. Due to the restricted right of
way due to existing properties, it is expected that the construction will affect the full
width available. The construction will involve the removal of existing curbs.
After creating path for mixed traffic, motor traffic will be diverted to the prepared path
to create enough corridor for the construction of BRT lanes. In case the section
involves the construction of bus station, the provisional will be made during this
stage.
After completion of BRT lanes, motor traffic from one direction that was diverted
earlier will be diverted to the constructed BRT lanes to allow construction of mixed
traffic lanes. The same will be done for the other direction. Reconstruction of
drainage system shall be done at each section and Pedestrian walkways will be
constructed as required.
241
Draft Detailed Report
242
Draft Detailed Report
In addition:
The traffic should be advised to use the alternative routes if it is not necessary to
pass by the properties near the construction zones, as shown in Figure 5.
243
Draft Detailed Report
244
Draft Detailed Report
Figure 9.6: Existing section with a median, without service road along Ali
Hassan Mwinyi Road
245
Draft Detailed Report
Figure 9.7: Existing section with a median and service road along Ali Hassan
Mwinyi Road
Figure 9.8: Existing section with an auxiliary lane along Ali Hassan Mwinyi
Road
246
Draft Detailed Report
For the section with limited right of way due to existing property, existing walkways
will be re-constructed to allow path of motorized traffic to create enough corridor for
construction of BRT lanes. The approach will be one side at a time to allow non-
motorized traffic to utilize the walkways on the other side with crosswalks provided at
an interval of about 200 m.
For the sections with service roads, the traffic will be diverted to the service roads.
Service roads should first be cleared to provide dual movement (two lanes in one
direction) without major disruption on general traffic operations.
The reconstructed part will then be used as diverted route and the created space will
be used for construction of BRT lanes. Depending on the design, if the BRT lanes
will affect both directions (both parts of dual carriageway), then the provisional
created after reconstructing the service roads or walkways on both sides should
allow at least construction of one BRT lane. In case the section involves the
construction of bus station, the provisional will be made during this stage.
After completion of BRT lanes, motor traffic from one direction that was diverted
earlier will be diverted to the constructed BRT lanes to allow construction of mixed
traffic lanes. The same will be done for the other direction. Reconstruction of
drainage system shall be done at each section and Pedestrian walkways will be
prepared.
247
Draft Detailed Report
Figure 9.9: Traffic management during construction along Ali Hassan Mwinyi
Road - stage 1
Figure 9.10: Traffic management during construction along Ali Hassan Mwinyi
Road - stage 2
248
Draft Detailed Report
Figure 9.11: Existing features along New Bagamoyo Road (Mwenge junction to
Wazo Hill Road and New Bagamoyo Road Intersection).
249
Draft Detailed Report
The section is wide enough, hence the construction of BRT lanes won’t disrupt the
mixed traffic. The traffic disruption will be expected at the intersections and where
there will be U–turns.
250
Draft Detailed Report
lanes, the BRT lanes will be constructed first so that the mixed traffic on one side will
be diverted into BRT lanes and then the same will be applied on the other direction.
Figures 9.14 and 9.15 illustrates the proposed traffic control schemes.
(a)
(b)
Figure 9.13: Traffic control plan during construction for two lanes two ways
251
Draft Detailed Report
Figure 9.14: Traffic control plan during construction for Dual carriage way
252
Draft Detailed Report
important in order to increase visibility. Setting up the proper traffic controls will
reduce the risk of accidents around the construction zone for both during the day and
night times.
In order to protect workers in a roadway work zones, employers must have the
following: -
A comprehensive site- specific safety program (APP)
Temporary traffic control plan in place for the project site
Conducted crew meetings and trained all workers on work site discussing
potential hazards, equipment and blind spot.
Figures 9.16 to 9.19 illustrates different traffic control procedures and tools employed
in work zones.
(a)
(b)
253
Draft Detailed Report
(c)
Figure 9.15: Route Diversion signs
Figure 9.17: Speed limit sign for controlling vehicle speeds at work zone
254
Draft Detailed Report
(a)
(b)
Figure 9.18: Channelizing devices at work zones (Traffic Control devices)
255
Draft Detailed Report
Do not lead pedestrians into direct conflicts with mainline traffic moving through or
around the work site.
Provide positive protection where necessary.
Maintain or replicate existing pedestrian access ways to the greatest extent practical.
Pedestrian access ways through work zones must include provisions for the disabled
at the same level of accessibility as the existing facility or greater.
Ensure passengers have the ability to access transit stops, and to board and depart
transit vehicles safely. Temporary transit access must include provisions for the
disabled at the same level of accessibility as the existing facility or greater
Cyclists should be provided with a travel route that replicates the most desirable
characteristics of a wide paved shoulder or bicycle lane through or around the work
zone.
If the work zone interrupts the continuity of an existing shared use path or bike route
system, provide signs directing cyclists through or around the work zone and back to
the path or route.
256
Draft Detailed Report
The cyclist should not be directed onto the same path used by pedestrians unless
the path is designed for bicycle traffic.
The intersections along BRT 4 corridor have directional peak hour traffic volumes,
with inbound morning traffic, and outbound afternoon traffic. Doing a composite lane
closure analysis would in many cases require night work or create very short
allowable lane closure periods. If a separate lane closure analysis is calculated for
inbound and outbound separately, night work may be avoided, and longer lane
closure periods may be allowed. When a lane closure is necessary, provide an
allowable lane closure period of at least one eight-hour period.
257
Draft Detailed Report
Note: Entrance to Kisutu Resident Magistrate will be provided via the Magore street.
258
Draft Detailed Report
Stage 2: Improve the lanes for mixed traffic from JNIA by diverting the traffic to the
constructed diversion and construct one lane for BRT. Road construction signs
should be placed in proper locations to create smooth diversion of traffic to the
designated zones.
Note: As shown in Figure 9.22, right turning traffic from Posta will turn left to Bibi Titi
Mohamed Road and then utilize the provided U-Turn ahead, traffic from Posta will
also be advised to use Ghana Street then Ohio Street (Green arrows).
Stage 3: Improve the lanes for mixed traffic from Tegeta by diverting the traffic to the
constructed BRT lane and one lane of the improved mixed traffic lanes, also
259
Draft Detailed Report
construct the other BRT lane. Direct the traffic from Posta to use the service road
and provide them with access to merge to the Bibi Titi Mohamed Street and to utilize
the U -Turn. Road construction signs should be placed in proper locations to create
smooth diversion of traffic to the designated zones. Figure 9.23 illustrates the
proposed traffic control procedure.
Note: There is no Right turning of traffic from JNIA, traffic will be advised to use the
next Junction at Ohio Street.
Stage 4: Finally block the access of mixed traffic into dedicated BRT lanes. The Final
Layout of the intersection will be as shown in the Figure 9.24.
260
Draft Detailed Report
9.2.9 Bibi Titi Street Mohammed/Ali Hassan Mwinyi Road Ohio Street
Intersection
Existing
The junction condition existing in project road is as shown in Figure 9.25.
Figure 9.24: Existing Bibi Titi Street Mohammed/ Ali Hassan Mwinyi Road Ohio
Street Intersection
261
Draft Detailed Report
Stage 2: Allow traffic from JNIA and Morocco (Bibi Titi Mohamed Street) to use the
prepared diversion routes and improve the mixed traffic lanes. The traffic from Posta
will be blocked and they will use the next intersection (Maktaba Junction). Lane
widths for the mixed traffic lanes will be minimized, advise traffic for appropriate
manoeuvre. Construct the BRT lanes in the middle of the existing lanes utilizing the
existing mixed traffic lanes, auxiliary lane and the median (Figure 9.27). Improve the
lane utilized by the traffic from Posta as per design.
262
Draft Detailed Report
263
Draft Detailed Report
Stage 3: Allow traffic from Morocco to use BRT lanes and construct the mixed traffic
lanes and all required features as per design (Figure 9.28).
Stage 4: Allow traffic from JNIA to use BRT lanes and construct the mixed traffic
lanes and all required features as per design (Figure 9.29).
264
Draft Detailed Report
Stage 5: Finally block the access of mixed traffic into dedicated BRT lanes. The Final
Layout of the intersection will be as shown in Figure 9.30.
265
Draft Detailed Report
Ali Hassan Mwinyi Road Ufukoni Road/Nkomo Street Intersection (Las Vegas)
Existing: The junction condition existing in project road is as shown Figure 9.31.
266
Draft Detailed Report
267
Draft Detailed Report
Stage 2: Allow traffic from Posta and Morocco to use the prepared diversion routes.
The right turn traffic from Posta to Agha Khan will make U-turn ahead of the
construction area. Lane widths for the mixed traffic lanes will be minimized, advise
traffic for appropriate maneuver. Construct the BRT lanes in the middle of the
existing lanes utilizing the existing mixed traffic lanes, auxiliary lane and the median
(Figure 9.33).
268
Draft Detailed Report
Stage 3: Allow traffic from Morocco/Tegeta to use BRT lanes and construct the
mixed traffic lanes and all required features as per design, as shown in Figure 9.34.
The movements to and from Agha Khan will be restricted at this stage of
construction.
269
Draft Detailed Report
Stage 4: Allow traffic from Posta to use BRT lanes and construct the mixed traffic
lanes and all required features as per design (Figure 9.35).
270
Draft Detailed Report
Stage 5: Finally block the access of mixed traffic into dedicated BRT lanes. The Final
Layout of the intersection will be as shown in Figure 9.36.
271
Draft Detailed Report
9.2.10 Ali Hassan Mwinyi Road Barack Obama Drive Intersection (Palm Beach)
Existing:
The junction condition existing in project road is as shown in Figure 9.37.
Figure 9.36: Ali Hassan Mwinyi Road Barack Obama Drive Intersection
(Palm Beach)
272
Draft Detailed Report
273
Draft Detailed Report
Stage 2: Allow traffic from Posta and Morocco/Tegeta to use the prepared diversion
routes. The right turn traffic from Posta to Agha Khan will not be allowed at this stage
of construction same as right turn traffic from Agha Khan to Morocco. Lane widths for
the mixed traffic lanes will be minimized, advise traffic for appropriate maneuver.
Construct the BRT lanes in the middle of the existing lanes utilizing the existing
mixed traffic lanes and the median (Figure 9.39).
274
Draft Detailed Report
Stage 3: Allow traffic from Morocco/Tegeta to use BRT lanes and construct the
mixed traffic lanes and all required features as per design (Figure 9.40). The
movements to and from Agha Khan will be restricted at this stage of construction.
275
Draft Detailed Report
Stage 4: Allow traffic from Posta to use BRT lanes and construct the mixed traffic
lanes and all required features as per design (Figure 9.41).
276
Draft Detailed Report
Stage 5: Finally block the access of mixed traffic into dedicated BRT lanes. The Final
Layout of the intersection will be as shown in Figure 9.42.
Figure 9.41: Stage 5 construction of Ali Hassan Mwinyi Road Barack Obama
Drive Intersection (Palm Beach)
277
Draft Detailed Report
Stage 2: Allow traffic from Morocco/Tegeta to use the prepared mixed traffic
lanes. The right turn traffic from Muhimbili to Posta will not be allowed at this
stage of construction same as right turn traffic from Morocco to Muhimbili
which will have to use a U-turn provided a head or other diversion route. Lane
widths for the mixed traffic lanes will be minimized, advise traffic for
appropriate maneuver. Construct the BRT lanes in the middle of the existing
lanes utilizing the existing mixed traffic lanes and the median (Figure 9.45).
278
Draft Detailed Report
Stage 3: Allow traffic from Posta to use BRT lanes and construct the mixed traffic
lanes and all required features as per design (Figure 9.46).
279
Draft Detailed Report
Stage 4: Finally block the access of mixed traffic into dedicated BRT lanes. The Final
Layout of the intersection will be as shown in Figure 4.47.
280
Draft Detailed Report
Stage 2: Allow traffic from Posta and Morocco/Tegeta to use the prepared
diversion routes. The right turn traffic from Posta to Osterbay will use the U-
turn ahead of the construction area same as right turn traffic from Kinondoni
to Posta. Same maneuver will be done by the traffic from Morocco/Tegeta and
Osterbay respectively. Lane widths for the mixed traffic lanes will be
minimized, advise traffic for appropriate maneuver. Construct the BRT lanes
in the middle of the existing lanes utilizing the existing mixed traffic lanes and
the median (Figure 4.49).
281
Draft Detailed Report
282
Draft Detailed Report
Stage 3: Allow traffic from Morocco/Tegeta to use BRT lanes and construct
the mixed traffic lanes and all required features as per design. The left turn
traffic from Tegeta/Morocco will be restricted at this stage of construction and
the traffic can use the previous intersection through Kaunda drive (Figure
4.50).
283
Draft Detailed Report
Stage 4: Allow traffic from Posta to use BRT lanes and construct the mixed
traffic lanes and all required features as per design (Figure 4.51).
284
Draft Detailed Report
Stage 5: Finally block the access of mixed traffic into dedicated BRT lanes.
The Final Layout of the intersection will be as shown in Figure 9.52.
285
Draft Detailed Report
Figure 9.54: Stage 1 construction of Ali Hassan Mwinyi Road - Kaunda Drive
Intersection
Stage 2: Allow traffic from Posta and Morocco/Tegeta to use the prepared diversion
routes. The right turn traffic from Posta to Kaunda Drive will use the U-turn ahead of
the construction area. Similar type of right turn maneuver will be done by the traffic
from Kaunda Drive will be made once it turns left to Posta then use the provided U-
turn ahead. Lane widths for the mixed traffic lanes will be minimized, advise traffic for
286
Draft Detailed Report
appropriate maneuver. Construct the BRT lanes in the middle of the existing lanes
utilizing the existing mixed traffic lanes and the median (Figure 9.55).
Stage 3: Allow traffic from Posta to use BRT lanes and construct the mixed traffic
lanes and all required features as per design. The right turn traffic from Posta will
use the maneuver as directed in stage two (Figure 9.56).
287
Draft Detailed Report
Stage 4: Allow traffic from Morocco/Tegeta to use BRT lanes and construct the
mixed traffic lanes and all required features as per design (Figure 9.57).
288
Draft Detailed Report
Stage 5: Finally block the access of mixed traffic into dedicated BRT lanes. The Final
Layout of the intersection will be as shown in Figure 59.
289
Draft Detailed Report
290
Draft Detailed Report
Stage 2: Allow traffic from Posta and Morocco/Tegeta to use the prepared diversion
routes. Lane widths for the mixed traffic lanes will be minimized, advise traffic for
appropriate manoeuvre. Construct the BRT lanes in the middle of the existing lanes
utilizing the existing mixed traffic lanes and the median (Figure 9.61).
291
Draft Detailed Report
Stage 3: Allow traffic from Mwenge/Tegeta/Morocco to use BRT lanes and construct
the mixed traffic lanes and all required features as per design (Figure 9.62).
292
Draft Detailed Report
Stage 4: Allow traffic from Posta to use BRT lanes and construct the mixed traffic
lanes and all required features as per design (Figure 9.63).
293
Draft Detailed Report
Stage 5: Finally block the access of mixed traffic into dedicated BRT lanes. The Final
Layout of the intersection will be as shown in Figure 9.64.
9.2.15 Ali Hassan Mwinyi Road Haile Selassie Road Intersection (St. Peter’s)
Existing
The junction condition existing in project road is as shown in Figure 9.65.
Figure 9.65: Ali Hassan Mwinyi Road Haile Selassie Road Intersection
(St. Peter’s)
294
Draft Detailed Report
Stage 2: The traffic from both directions will be allowed to use the prepared diversion
routes at this stage. Traffic turning right from St. Peter’s (Haile Selassie road) to
Morocco will first turn left to Posta and utilize the U-turns provided ahead. The right
turn traffic from Posta to St. Peter’s (Haile Selassie road) will use the U-turn ahead of
the construction area. Lane widths for the mixed traffic lanes will be minimized,
advise traffic for appropriate maneuver. Construct the BRT lanes in the middle of the
existing lanes utilizing the existing mixed traffic lanes and the median (Figure 9.67).
Stage 3: Allow traffic from Posta to use BRT lanes and construct the mixed traffic
lanes and all required features as per design (Figure 9.68). The right turning traffic
will use the similar manoeuvre as illustrated in Stage 2.
295
Draft Detailed Report
Stage 4: At this stage, allow traffic from Tegeta/Morocco to utilize the BRT lanes
while making sure there is provisional for the left turn traffic from Tegeta/Morocco to
St. Peter’s as shown in Figure 9.69.
296
Draft Detailed Report
Stage 5: Finally block the access of mixed traffic into dedicated BRT lanes. The Final
Layout of the intersection will be as shown in Figure 9.70.
297
Draft Detailed Report
298
Draft Detailed Report
299
Draft Detailed Report
Stage 2: Allow traffic from Posta and Morocco/Tegeta to use the prepared diversion
routes. Lane widths for the mixed traffic lanes will be minimized, advise traffic for
appropriate maneuver. Construct the BRT lanes in the middle of the existing lanes
utilizing the existing mixed traffic lanes and the median (Figure 9.74).
300
Draft Detailed Report
Stage 3: Allow traffic from Mwenge/Tegeta/Morocco to use BRT lanes and construct
the mixed traffic lanes and all required features as per design (Figure 9.75).
301
Draft Detailed Report
Stage 4: Allow traffic from Posta to use BRT lanes and construct the mixed traffic
lanes and all required features as per design (Figure 9.76).
302
Draft Detailed Report
Stage 5: Finally block the access of mixed traffic into dedicated BRT lanes. The Final
Layout of the intersection will be as shown in Figure 9.76.
9.2.17 Ali Hassan Mwinyi Road Old Bagamoyo Road Intersection (Namanga)
Existing
The junction condition existing in project road is as shown in Figure 9.78.
Figure 9.77: Ali Hassan Mwinyi Road Old Bagamoyo Road Intersection
(Namanga) Proposed Construction stages
303
Draft Detailed Report
Stage 1: Prepare the diversion routes for the traffic on the existing service roads and
walkways as shown in Figure 9.79. The traffic signs should be well placed especially
for non-motorized traffic.
Figure 9.78: Stage 1 construction of Ali Hassan Mwinyi Road Old Bagamoyo
Road Intersection (Namanga)
Stage 2: The traffic from both directions will be allowed to use the prepared diversion
routes at this stage. Traffic turning right from Namanga (Old Bagamoyo road) to
Morocco will first turn left to Posta and utilize the U-turns provided ahead. The right
turn traffic from Posta to Namanga (Old Bagamoyo road) will use the U-turn ahead of
the construction area. Lane widths for the mixed traffic lanes will be minimized,
advise traffic for appropriate manoeuvre. Construct the BRT lanes in the middle of
the existing lanes utilizing the existing mixed traffic lanes and the median (Figure
9.80).
304
Draft Detailed Report
Figure 9.79: Stage 2 construction of Ali Hassan Mwinyi Road Old Bagamoyo
Road Intersection (Namanga)
Stage 3: Allow traffic from Posta to use BRT lanes and construct the mixed traffic
lanes and all required features as per design (Figure 9.81). The right turning traffic
will use the similar maneuver as illustrated in Stage 2.
Figure 9.80: Stage 3 construction of Ali Hassan Mwinyi Road Old Bagamoyo
Road Intersection (Namanga)
305
Draft Detailed Report
Stage 4: At this stage, allow traffic from Tegeta/Morocco to utilize the BRT lanes
while making sure there is provisional for the left turn traffic from Tegeta/Morocco to
Namanga as shown in Figure 9.82.
Figure 9.81: Stage 4 construction of Ali Hassan Mwinyi Road Old Bagamoyo
Road Intersection (Namanga)
Stage 5: Finally block the access of mixed traffic into dedicated BRT lanes. The Final
Layout of the intersection will be as shown in Figure 9.83.
Figure 9.82: Stage 5 construction of Ali Hassan Mwinyi Road Old Bagamoyo
Road Intersection (Namanga)
306
Draft Detailed Report
Existing
The features existing in project road are as shown in Figure 9.84.
307
Draft Detailed Report
Figure 9.84: Stage 1 construction of BEST BITE U-TURN - Ali Hassan Mwinyi
Road
308
Draft Detailed Report
Stage 2: Allow traffic from Posta and Morocco/Tegeta to use the prepared diversion
routes. Lane widths for the mixed traffic lanes will be minimized, advise traffic for
appropriate maneuver. Construct the BRT lanes in the middle of the existing lanes
utilizing the existing mixed traffic lanes and the median (Figure 9.86).
Figure 9.85: Stage 2 construction of BEST BITE U-TURN - Ali Hassan Mwinyi
Road
309
Draft Detailed Report
Stage 3: Allow traffic from Mwenge/Tegeta/Morocco to use BRT lanes and construct
the mixed traffic lanes and all required features as per design (Figure 9.87).
Figure 9.86: Stage 3 construction of BEST BITE U-TURN - Ali Hassan Mwinyi
Road
310
Draft Detailed Report
Stage 4: Allow traffic from Posta to use BRT lanes and construct the mixed traffic
lanes and all required features as per design (Figure 9.88).
Figure 9.87: Stage 4 construction of BEST BITE U-TURN - Ali Hassan Mwinyi
Road
311
Draft Detailed Report
Stage 5: Finally block the access of mixed traffic into dedicated BRT lanes. The Final
Layout of the intersection will be as shown in Figure 9.89.
Figure 9.88: Stage 5 construction of BEST BITE U-TURN - Ali Hassan Mwinyi
Road
312
Draft Detailed Report
Existing
The junction condition existing in project road is as shown in Figure 9.90.
313
Draft Detailed Report
314
Draft Detailed Report
Stage 2: The traffic from both directions will be allowed to use the prepared diversion
routes at this stage. Right turn traffic from Mwenge to EFATHA will use the U-turn
provided just after the construction area. Right turners from EFATHA, will first turn
left to the Mwenge direction before the utilize the prepared U-turn ahead of
construction area. Lane widths for the mixed traffic lanes will be minimized, advise
traffic for appropriate manoeuvre. Construct the BRT lanes in the middle of the
existing lanes utilizing the existing median (Figure 9.92).
315
Draft Detailed Report
Stage 3: Allow the traffic from Mwenge to use the constructed BRT lane and
construct/improve the existing mixed traffic lanes and all other facilities as per the
design. After the construction is done on that side, direct the traffic from Bagamoyo
to use the BRT lanes and construct/improve the required facilities as per design
(Figure 9.93).
316
Draft Detailed Report
Stage 4: Finally block the access of mixed traffic into dedicated BRT lanes. The Final
Layout of the intersection will be as shown in Figure 9.94.
317
Draft Detailed Report
318
Draft Detailed Report
Figure 9.95: Stage 1 construction of SUMA JKT U-Turn (New Bagamoyo Road)
319
Draft Detailed Report
Stage 2: Allow traffic to utilize the constructed surfaces and improve the existing
mixed traffic lanes as per design (Figure 9.97).
Figure 9.96: Stage 2 construction of SUMA JKT U-Turn (New Bagamoyo Road)
320
Draft Detailed Report
Stage 3: The Final Layout of the intersection will be as shown in Figure 9.98.
Figure 9.97: Stage 3 construction of SUMA JKT U-Turn (New Bagamoyo Road)
321
Draft Detailed Report
Existing
The features existing in project road section are as shown in Figure 9.99.
322
Draft Detailed Report
323
Draft Detailed Report
Stage 2: Divert the mixed traffic to the prepared roads. Construct the BRT lanes
utilizing the existing median. Improve the existing mixed traffic lanes as per the
design. During this stage, the right turn traffic will be using provided U-turn locations
ahead of construction area (Figure 9.101).
324
Draft Detailed Report
Stage 3: The Final Layout of the intersection will be as shown in Figure 9.102.
325
Draft Detailed Report
Existing
The features existing in project road are as shown in Figure 9.103.
326
Draft Detailed Report
327
Draft Detailed Report
Stage 2: Allow traffic to use the prepared diversion routes. Lane widths for the mixed
traffic lanes will be minimized, advise traffic for appropriate manoeuvre. Construct
the BRT lanes in the middle of the existing lanes utilizing the existing the median
(Figure 9.105).
328
Draft Detailed Report
Stage 3: Allow traffic from Mwenge to use BRT lanes and construct the mixed traffic
lanes and all required features as per design (Figure 106).
329
Draft Detailed Report
Stage 4: Allow traffic from Bagamoyo/Tegeta to use BRT lanes and construct the
mixed traffic lanes and all required features as per design (Figure 9.107).
330
Draft Detailed Report
Stage 5: Finally block the access of mixed traffic into dedicated BRT lanes. The Final
Layout of the intersection will be as shown in Figure 9.108.
331
Draft Detailed Report
Existing
The features existing in project road are as shown in Figure 9.109.
332
Draft Detailed Report
333
Draft Detailed Report
Stage 2: Allow traffic to use the prepared diversion routes. Lane widths for the mixed
traffic lanes will be minimized, advise traffic for appropriate manoeuvre. Construct
the BRT lanes in the middle of the existing lanes utilizing the existing mixed traffic
lanes and the median (Figure 9.111).
334
Draft Detailed Report
Stage 3: Allow traffic from Mwenge to use BRT lanes and improve the mixed traffic
lanes and construct all required features as per design. Then after do the same for
the traffic from Bagamoyo (Figure 9.112).
335
Draft Detailed Report
Stage 4: Finally block the access of mixed traffic into dedicated BRT lanes. The Final
Layout of the intersection will be as shown in Figure 9.113.
336
Draft Detailed Report
9.2.24 New Bagamoyo Road Ally Sykes Road Intersection (Tangibovu U-turn)
Existing
The features existing in project road intersection are as shown in Figure 9.114.
Figure 9.113: New Bagamoyo Road Ally Sykes Road Intersection (Tangibovu
U-turn)
337
Draft Detailed Report
Figure 9.114: Stage 1 Construction of New Bagamoyo Road Ally Sykes Road
Intersection (Tangibovu U-turn)
338
Draft Detailed Report
Stage 2: Allow traffic to use the prepared service roads as diversion routes.
Construct the BRT lanes in the middle of the existing lanes utilizing the existing
mixed traffic lanes and the median. The improvement of lanes for mixed traffic will
also be done at this stage of construction. The right turning traffic at the intersection
will be utilizing the provided U-turns ahead of the construction area (Figure 9.116).
Figure 9.115: Stage 2 Construction of New Bagamoyo Road Ally Sykes Road
Intersection (Tangibovu U-turn)
339
Draft Detailed Report
Stage 3: The Final Layout of the intersection will be as shown in Figure 9.117.
Figure 9.116: Stage 3 Construction of New Bagamoyo Road Ally Sykes Road
Intersection (Tangibovu U-turn)
340
Draft Detailed Report
Existing
The features existing in project road section are as shown in Figure 9.118.
341
Draft Detailed Report
342
Draft Detailed Report
Stage 2: Allow traffic to use the prepared diversion routes which will later serve as
service roads for allowing U-turns. Improve the existing mixed traffic lanes as per
design and complete the construction of all other required facilities as per design
(Figure 9.120).
343
Draft Detailed Report
Stage 3: Finally block the access of mixed traffic into dedicated BRT lanes. The Final
Layout of the intersection will be as shown in Figure 9.121.
344
Draft Detailed Report
Existing
The features existing in project road intersection are as shown in Figure 9.122.
345
Draft Detailed Report
Stage 1: Construct the service roads which will be used as diversion routes for the
traffic on the existing service roads and walkways as shown in Figure 9.123. Also
construct the BRT lanes utilizing the median. The traffic signs should be well placed
especially for non-motorized traffic.
346
Draft Detailed Report
Stage 2: Allow traffic from Mwenge to use the constructed service roads. Close the
existing middle part of the intersection to allow construction of the remaining part of
BRT lanes and to allow the improvement of existing mixed traffic lanes. At this stage,
the right turning traffic will utilize the provided U-turns ahead of construction area
(Figure 9.124).
347
Draft Detailed Report
Stage 3: Allow traffic from Bagamoyo/Tegeta to use BRT lanes and improve the
mixed traffic lanes and all required features as per design (Figure 9.125).
348
Draft Detailed Report
Stage 4: Finally block the access of mixed traffic into dedicated BRT lanes. The Final
Layout of the intersection will be as shown in Figure 9.126.
349
Draft Detailed Report
Existing
The features existing in project road section are as shown in Figure 9.127.
350
Draft Detailed Report
351
Draft Detailed Report
Stage 2: Allow traffic to use the constructed service roads. Close the existing middle
part of the intersection to allow construction of the remaining part of BRT lanes and
to allow the improvement of existing mixed traffic lanes. At this stage, the right
turning traffic will utilize the provided U-turns ahead of construction area (Figure
9.129).
352
Draft Detailed Report
Stage 3: Finally block the access of mixed traffic into dedicated BRT lanes. The Final
Layout of the intersection will be as shown in Figure 9.130.
353
Draft Detailed Report
354
Draft Detailed Report
355
Draft Detailed Report
Stage 2: Allow traffic to use the constructed service roads. Improve the existing
mixed traffic lanes and construct all required facilities as per design. At this stage,
the BRT lanes can be used for mixed traffic to ease congestion at construction area
especially during peak hours (Figure 9.133).
356
Draft Detailed Report
Stage 3: Finally block the access of mixed traffic into dedicated BRT lanes. The Final
Layout of the intersection will be as shown in Figure 9.134.
357
Draft Detailed Report
9.2.29 New Bagamoyo Road Jupiter Street Intersection (and U-turn) (Mbezi
Jogoo)
Existing
The features existing in project road intersection are as shown in Figure 9.135.
Figure 9.134: New Bagamoyo Road Jupiter Street Intersection (and U-turn)
(Mbezi Jogoo)
358
Draft Detailed Report
359
Draft Detailed Report
Stage 2: Divert the traffic into the service roads to create enough space for major
construction. Construct the BRT lanes and improve the existing mixed traffic lanes.
This is the stage to also construct all other facilities as per design (Figure 9.137).
360
Draft Detailed Report
Stage 3: Finally block the access of mixed traffic into dedicated BRT lanes. The Final
Layout of the intersection will be as shown in Figure 9.138.
361
Draft Detailed Report
Existing
The features existing in project road intersection are as shown in Figure 9.139.
Figure 9.138: New Bagamoyo Road Africana Drive Intersection (and U-turn)
362
Draft Detailed Report
363
Draft Detailed Report
Stage 2: Divert the traffic to the constructed service roads. Utilize the existing
median to construct the BRT lanes. Improve the existing missed traffic lanes and
construct other facilities required as per design (Figure 9.141).
364
Draft Detailed Report
Stage 3: Finally block the access of mixed traffic into dedicated BRT lanes. The Final
Layout of the intersection will be as shown in Figure 9.142.
365
Draft Detailed Report
9.2.31 New Bagamoyo Road Salasala Road Bahari Beach Road Intersection
(and U-turn)
Existing
The features existing in project road intersection are as shown in Figure 9.143.
Figure 9.142: New Bagamoyo Road Salasala Road Bahari Beach Road
Intersection (and U-turn)
366
Draft Detailed Report
367
Draft Detailed Report
Stage 2: Divert the traffic to the constructed mixed traffic lanes. In the space created
in the middle part of the intersection, construct the BRT lanes and the inside service
roads. The right turning traffic will use the provided U-tuns on all sides of the
construction area (Figure 9.145).
368
Draft Detailed Report
Stage 3: Finally block the access of mixed traffic into dedicated BRT lanes. The Final
Layout of the intersection will be as shown in Figure 9.146.
369
Draft Detailed Report
Existing
The features existing in project road intersection are as shown in Figure 9.147.
370
Draft Detailed Report
371
Draft Detailed Report
Stage 2: Allow traffic from Tegeta/Bagamoyo to use the prepared BRT lanes.
Improve the existing mixed traffic lanes in the direction towards Mwenge Intersection
(from Tegeta) as shown in Figure 9.149.
372
Draft Detailed Report
Stage 3: Allow traffic from Mwenge to use BRT lanes and improve the mixed traffic
lanes. Construction of all required features as per design will be completed at this
stage (Figure 9.150).
373
Draft Detailed Report
Stage 4: Finally block the access of mixed traffic into dedicated BRT lanes. The Final
Layout of the intersection will be as shown in Figure 9.151.
374
Draft Detailed Report
Figure 9.151: New Bagamoyo Road IPTL Street Intersection (and U-turn)
375
Draft Detailed Report
376
Draft Detailed Report
Stage 2: Divert the traffic to the constructed service roads. Utilize the median
and construct the BRT lanes. At this stage, the mixed traffic lanes will be
improved. Construction of other required facilities will be completed during this
stage (Figure 9.154).
377
Draft Detailed Report
Stage 3: Finally block the access of mixed traffic into dedicated BRT lanes. The Final
Layout of the intersection will be as shown in Figure 9.155.
378
Draft Detailed Report
Existing
The features existing in project road intersection are as shown in Figure 9.156.
Figure 9.155: New Bagamoyo Road Wazo Road Intersection (and U-turn)
379
Draft Detailed Report
380
Draft Detailed Report
Stage 2: Construct the BRT lanes in the middle of the existing lanes utilizing
the existing median (Figure 9.158). The right turning traffic will use the
prepared U-turn locations prepared during stage 1.
381
Draft Detailed Report
Stage 3: Allow traffic from Bagamoyo to use BRT lanes and construct the
mixed traffic lanes and all required features as per design. Also construct the
service roads beside Wazo hill roads that will serve as diversion routes in the
later stage (Figure 9.159).
382
Draft Detailed Report
Stage 4: Allow traffic from Mwenge to use BRT lanes and construct the mixed
traffic lanes and all required features as per design. Close the middle part of
the intersection as shown to allow construction as per design (Figure 9.160).
383
Draft Detailed Report
Stage 5: Finally block the access of mixed traffic into dedicated BRT lanes.
The Final Layout of the intersection will be as shown in Figure 9.161.
384
Draft Detailed Report
Existing
The features existing in project road section are as shown in Figure 9.162.
385
Draft Detailed Report
386
Draft Detailed Report
Stage 2: Divert the traffic into newly constructed mixed traffic lanes. Construct
the BRT lanes utilizing the existing mixed traffic lanes (Figure 9.164).
387
Draft Detailed Report
Stage 3: Finally block the access of mixed traffic into dedicated BRT lanes.
The Final Layout of the intersection will be as shown in Figure 9.165.
388
Draft Detailed Report
Existing
The features existing in project road intersection are as shown in Figure 9.166.
389
Draft Detailed Report
Stage 2: Construct one lane of mixed traffic beside each side of the BRT
lanes after diverting the traffic to the constructed service roads. At this stage,
the roundabout will still operate as a common round about (Figure 9.168).
Stage 3: Allow traffic to use BRT lanes and the constructed single lane for the
mixed traffic. Construct the remaining mixed traffic lanes and all other
required facilities as per design requirements. This will be the last stage for
the movements at the intersection to follow the roundabout rules as the
intersection geometry will be altered (Figure 9.169).
390
Draft Detailed Report
Stage 4: Finally block the access of mixed traffic into dedicated BRT lanes.
The Final Layout of the intersection will be as shown in Figure 166.
Figure 9.170: Sam Nujoma Road University Road Intersection (Mlimani City
Roundabout)
391
Draft Detailed Report
392
Draft Detailed Report
Stage 2: Allow traffic Ubungo to use the constructed BRT lanes. Improve the existing
mixed traffic lanes and construct all other designed facilities. During this stage, the
required widening of the Spur of University road will be undertaken (Figure 9.173).
Stage 3: Allow traffic from Mwenge to use BRT lanes, improve the mixed traffic lanes
and construct all facilities required as per design (Figure 9.174).
393
Draft Detailed Report
Stage 4: Finally block the access of mixed traffic into dedicated BRT lanes. The Final
Layout of the intersection will be as shown in Figure 9.175.
Existing
The features existing in project road intersection are as shown in Figure 9.176.
394
Draft Detailed Report
395
Draft Detailed Report
Stage 2: Divert the mixed traffic into the constructed service roads. The right turning
traffic will be making U-turn ahead of construction area. Improve the existing mixed
traffic lanes and complete the construction of all other facilities including pedestrian
facilities (Figure 9.178).
396
Draft Detailed Report
Stage 3: Finally block the access of mixed traffic into dedicated BRT lanes. The Final
Layout of the intersection will be as shown in Figure 9.179.
397
Draft Detailed Report
Existing
The features existing in project road section are as shown in Figure 9.180.
398
Draft Detailed Report
399
Draft Detailed Report
Stage 2: Divert the traffic into the service roads with good care of non-motorized
traffic. Utilize the existing median to construct the BRT lanes and during this stage,
improve the existing mixed traffic lanes (Figure 9.182).
400
Draft Detailed Report
Stage 3: Finally block the access of mixed traffic into dedicated BRT lanes. The Final
Layout of the intersection will be as shown in Figure 9.183.
401
Draft Detailed Report
402
Draft Detailed Report
Stage 2: Divert the traffic into the constructed service roads. Improve the
existing mixed traffic lanes as well as the remaining middle part of the
intersection. The widening of the Mawasiliano road will be done at this stage
while completing all other required facilities (Figure 9.186).
403
Draft Detailed Report
404
Draft Detailed Report
Stage 3: Open the middle part of the intersection. Construct the BRT lanes in
Mawasiliano road after diverting the traffic to/from Mawasiliano into the widened part
(Figure 9.187).
405
Draft Detailed Report
Stage 4: Finally block the access of mixed traffic into dedicated BRT lanes. The Final
Layout of the intersection will be as shown in Figure 9.188.
406
APPENDICES 3
APPENDIX 3.1
Catchment Areas
Appendix 1. According to COWI Report: Stormwater catchments and main rivers in
Dar-Es-Salaam: Tegeta, Mbezi, Mlalakuwa, Mikocheni, Kijitonyama and Msimbazi
Delineation of Catchment areas of Dar-Es-Salaam from Topographic maps
Msimbazi River Catchment area delineated from Topographic maps: Total area is 268 km2
APPENDIX 3.2
Rainfall data
Julius Nyerere International Airport Monthly Rainfall (mm)
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1966 116.3 81.6 145.7 250.8 217.2 58.8 12.6 49.9 30.6 36.7 19.1 38
1967 30.5 81.6 91 319.7 235 53.4 112.9 40.4 94.1 86 190.5 179.3
1968 5.9 135.3 305.8 417.9 119.3 63.4 3.2 13 15.5 86.9 292.4 109.8
1969 73.2 81.9 202.8 299.1 205.4 21.7 27.3 35.5 24.3 24.8 129.3 15.8
1970 110.7 41.8 80 180.7 126.7 2.2 15.3 9.5 59.1 15.7 20.4 209.4
1971 66.4 50.9 128.4 133.7 185 53 19.9 27.8 3.9 50.2 7.6 93.6
1972 65 74.1 150.1 351.3 263.4 0.3 37.7 14.9 52.7 131.6 176.4 100.8
1973 33.9 27.3 81.9 359 59.2 68 15.5 54 7.8 27.1 8.7 33.6
1974 167.9 6.3 76.1 304 86.5 14.8 41 1.7 24.3 26.2 11.9 2.7
1975 50.8 5 121.8 245 279.8 16.9 9.6 4.2 89.3 19.7 150.6 101.8
1976 14.4 9.1 243.2 278.3 173.4 96 78 3.3 12.5 40.4 26.7 37.4
1977 163.9 36.3 142.9 282 134.8 4.3 8.4 34.1 95.9 48.5 199.3 186.4
1978 65.8 14.8 133.7 428.1 112.6 57.5 24.8 9.5 26.2 35.1 425.1 159.4
1979 201.7 142.8 84 187.7 395.6 91.3 15.2 18.6 26.4 24.9 41.8 85.4
1980 58.8 61.6 103.3 143.5 88.4 0 19.2 42.7 2.4 128.7 238.1 98.5
1981 40.5 8.3 188.2 171.3 191 18.7 2.8 56.1 23 75.1 54.4 219.2
1982 13.8 1.7 58.9 198.9 237.4 138.9 50.3 20 18.5 181.2 264.1 238.3
1983 37.2 61.9 78 224 405.6 39.4 45.9 13.9 6.8 70 15.8 67.2
1984 116.4 0 128.4 441.2 174.2 60.1 28.4 5.1 6.5 104.4 121.1 182.3
1985 93.8 124.1 114.8 135.0 184.0 2.4 62.1 1.4 12.8 33.8 61.7 122.9
1986 35.8 0.4 210.8 398.4 293.5 13.3 1.7 32.6 46.0 109.0 242.7 46.7
1987 21.1 13.9 77.9 160.9 246.5 0.8 16.4 73.6 2.8 40.7 48.1 22.2
1988 183.3 13.2 105.2 245.7 15.3 78.5 9.3 48.2 32.7 8.8 62.4 152.7
1989 268.2 0.0 105.3 259.3 196.5 34.6 5.7 33.7 22.8 72.3 28.0 175.6
1990 110.2 160.9 93.5 271.5 100.3 29.2 29.9 7.3 23.6 29.6 230.2 55.6
1991 92.9 17.3 75.2 17.4 353.0 4.6 28.9 21.7 13.0 25.7 218.6 187.4
1992 9.2 114.6 51.3 325.4 288.1 37.2 34.8 3.1 20.9 2.6 138.3 120.0
1993 71.3 34.8 118.2 322.6 199.4 17.4 14.1 10.1 9.1 109.9 161.5 86.9
1994 54.6 100.1 99.7 289.2 171.1 4.4 50.1 10.0 9.3 69.0 197.7 228.7
1995 12.5 110.1 310.6 264.9 374.2 2.1 7.6 106.5 4.6 163.8 117.1 62.2
1996 90.0 225.8 233.1 223.2 254.2 11.6 14.9 13.5 1.8 108.1 78.5 12.2
1997 1.7 0.3 282.8 167.7 117.4 154.2 5.6 6.1 2.6 250.8 152.0 231.0
1998 107.3 123.7 155.2 319.9 161.6 29.9 2.4 5.0 68.0 58.5 105.7 0.0
1999 30.1 108.9 222.1 258.9 143.4 81.8 60.1 20.4 13.5 27.2 115.0 173.8
2000 1.8 3.5 169.9 222.1 47.6 126.9 29.6 31.1 3.2 6.2 79.2 214.2
2001 64.5 71.3 139.0 296.7 162.5 14.0 19.6 3.9 5.0 6.7 15.5 82.2
2002 81.9 83.5 197.2 569.4 30.1 7.0 32.1 95.4 30.2 51.8 98.9 112.5
2003 20.1 22.2 122.4 13.7 130.8 109.5 26.1 0.9 3.5 22.4 89.2 24.6
2004 77.7 149.8 134.5 297.6 19.3 42.7 0.9 0.6 31.1 93.5 65.5 181.6
2005 154.8 38.9 80.2 119.4 302.6 2.8 14.9 13.8 10.5 124.9 24.5 13.4
2006 6.4 44.0 243.5 226.7 166.4 142.9 15.0 6.5 23.8 78.1 240.9 230.4
2007 8.5 39.4 201.4 181.7 124.2 16.5 2.0 26.2 14.3 70.3 113.7 45.8
2008 52.3 56.1 159.4 303.8 62.4 10.0 6.7 10.4 16.7 95.0 116.8 11.7
2009 17.9 61.8 103.8 240.1 25.2 10.6 1.4 5.8 2.1 38.8 18.2 69.9
2010 14.0 83.2 167.7 362.2 119.0 14.6 7.1 15.8 46.2 0.4 48.7 85.3
2011 4.1 103.8 26.3 224.4 106.7 29.7 11.9 26.3 54.4 31.6 316.5 377.2
2012 3.2 36.4 49.9 263.5 109.6 9.7 3.2 19.2 16.3 0.8 124.0 66.8
2013 67.4 1.6 190.2 179.0 85.8 1.2 2.3 9.1 19.7 37.0 69.3 69.6
2014 0.9 80.6 426.3 449.2 154.5 4.2 7.9 0.5 60.8 20.1 33.9 40.0
2015 50.1 0.8 226.2 161.0 342.5 3.5 8.7 20.9 11.0 15.5 132.6 66.1
2016 154.2 98.7 56.2 352.8 8.6 3.5 1.9 4.3 26.8 0.1 49.6 26.2
WAZOHILL RAINFALL STATION
YEAR JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
1985 92.7 166.4 94.3 158.9 90.9 0 29.6 0.9 6 34.6 30.5 108.8
1986 26.4 0 67.8 295.1 208.7 5.9 1.2 21.5 55.3 84.4 99.7 140.4
1987 54 9 102 187.7 280.8 0 11.3 34.4 0 20.9 12.4 28.9
1988 132.8 3.2 109.9 150.1 27.8 48.6 0 24.8 27.8 30.5 56.4 87.2
1989 232.2 0 25.6 181.8 24.5 0 0 11.5 37.5 39.4 80.9
1990 46.7 97.2 137.9 216 64.8 0 0 9.6 3.2 5.8 190.7 51.3
1991 72.8 4.8 88.8 5.6 191.2 3.2 4.9 29.5 8.8 9.4 104.1 142.5
1992 7.2 20.9 114.9 339.2 109.1 59.9 17.2 0 40 0 90.8 69
1993 78.2 21.4 194 262.7 121.1 0 9.3 20.6 4.8 31.4 73.1 39.2
1994 10.9 94.7 130.2 340 127.6 0 16 0 6.6 94 87.3 m
1995 0 42.4 136 249.5 213.4 0 8.8 81.6 12 80 19.6 49.2
1996 42 33.6 171.6 123 215 4 9.3 0 0 68.4 0 0
1997 0 0 421.9 160.2 97.6 74.8 0 0 8 305.2 83.2 112.6
1998 151.5 42.1 65.7 244.1 190.2 23.7 13 0 16.8 30.4 78.9 m
1999 m m m m m m m m m m m m
2001 0 80 52.8 237.6 139.8 25.6 3.2 0 0 0 29 96.1
2002 72.5 m m m m m m m 52.2 38.7 27.3 16.5
2003 0 0 103.5 48.5 136.1 41.6 3.5 0 0 96.5 0 83.3
2004 11.2 101.2 65.5 125 2.6 43.4 7.4 0 0 155.9 102.1 168.3
2005 0 47 74.3 142.8 211.8 8 0 0 0 0 33.9 0
2006 10.1 42.3 116.4 132.1 111.6 105.3 17.1 0 0 35.1 93.3 185.4
2007 67.3 36 49.6 133.1 246.2 71.1 29 0 30.5 5.7 161.8 49
2008 26.1 4.8 109 212 77.8 1.5 29 0 1.5 126.6 202.3 21.9
2009 31.3 60.2 74.4 107.3 32.7 3.5 3.3 20 0 m m m
2010 54.6 64.8 67.6 294.7 42.9 9.8 5 28 15.6 0 34.3 45.6
2011 0 48.4 45.3 82.7 49.5 5.7 0 25.6 14.9 38 79.4 253.9
Mean 60.78230769
Stdv 14.52898628
α 11.32820413
u 54.24366827
Constant N 0.960
Constant B 0.330
Rainfall Ratio 0.982
Area Reduction Factor 0.982
1 2
Parameters/ Catchment areas 3
Capacity of 663m3/sec
the Bridge
Bridge at Mlalakuwa
LOCATION OF Mlalakuwa River bridge crossing Bagamoyo Road at
BRIDGE Mlalakuwa river. Bridge dimension is L=30m W=10m
H=5.3m
Depth Elevation Manning Roughness Hydraulic Radius Channel slope Wetted Area Velocity Discharge
Remarks
d (m) (m) n R S (%) Perimeter P (m) A (m 2) V (m/s) Q1(m 3/s)
0.0 0.00 0.035 0.00 0.50 0.00 0.00 0.00 0.00
0.5 0.50 0.035 0.49 0.50 81.00 40.00 0.59 23.43
1.0 1.00 0.035 0.98 0.50 82.00 80.00 0.92 73.79
1.5 1.50 0.035 1.45 0.50 83.00 120.00 1.20 143.88
2.0 2.00 0.035 1.90 0.50 84.00 160.00 1.44 230.55
2.5 2.50 0.035 2.35 0.50 85.00 200.00 1.66 331.78
3.0 3.00 0.035 2.79 0.50 86.00 240.00 1.86 446.10
3.5 3.50 0.035 3.22 0.50 87.00 280.00 2.04 572.36
4.0 4.00 0.035 3.64 0.50 88.00 320.00 2.22 709.60
4.5 4.50 0.035 4.04 0.50 89.00 360.00 2.38 857.03
5.0 5.00 0.035 4.44 0.50 90.00 400.00 2.53 1013.96
6.0 6.00 0.035 5.27 0.50 91.00 480.00 2.84 1363.93
MSIMBAZI BRIDGE
Flow Depth vis Discharge
6.0
5.0
4.0
Flow depth (m)
3.0
663m3/sec
h=3.7m
2.0
1.0
0.0
0 200 400 600 800 1000 1200 1400
Discharge (m3/s)
Note:
2 1 Discharge Q1(m3/s)
V =
1 3 2
R S Q = AV
n
MLALAKUWA RIVER HYDRAULIC CAPACITY
DISCHARGE RATING CURVE FOR DIFFERENT WATER LEVELS
Depth Elevation Manning Roughness Hydraulic Radius Channel slope Wetted Area Velocity Discharge
Remarks
d (m) (m) n R S (%) Perimeter P (m) A (m 2) V (m/s) Q1(m 3/s)
0.0 0.00 0.035 0.00 1.00 0.00 0.00 0.00 0.00
0.5 0.50 0.035 0.48 1.00 31.00 15.00 0.82 12.26
1.0 1.00 0.035 0.94 1.00 32.00 30.00 1.27 38.11
1.5 1.50 0.035 1.36 1.00 33.00 45.00 1.63 73.39 H≈1.4m
2.0 2.00 0.035 1.76 1.00 34.00 60.00 1.94 116.20
2.5 2.50 0.035 2.14 1.00 35.00 75.00 2.20 165.32
3.0 3.00 0.035 2.50 1.00 36.00 90.00 2.44 219.85
3.5 3.50 0.035 2.84 1.00 37.00 105.00 2.66 279.11
4.0 4.00 0.035 3.16 1.00 38.00 120.00 2.85 342.54
MLALAKUWA BRIDGE
Flow Depth vis Discharge
4.0
3.5
6.0m
3.0
2.5
2.0
Flow depth (m)
1.0
0.5
0.0
0 50 100 150 200 250 300 350 400
Discharge (m3/s)
Discharge Q1(m3/s)
Note:
2 1
V =
1 3 2
R S Q = AV
n
MBEZI RIVER AT LUGALO HYDRAULIC CAPACITY
DISCHARGE RATING CURVE FOR MBEZI RIVER AT LUGALO
Depth Elevation Manning Roughness Hydraulic Radius Channel slope Wetted Area Velocity Discharge
Remarks
d (m) (m) n R S (%) Perimeter P (m) A (m 2) V (m/s) Q1(m 3/s)
0.0 0.00 0.035 0.00 1.00 0.00 0.00 0.00 0.00
0.5 0.50 0.035 0.48 1.00 31.00 15.00 0.82 12.26
1.0 1.00 0.035 0.94 1.00 32.00 30.00 1.27 38.11
1.5 1.50 0.035 1.36 1.00 33.00 45.00 1.63 73.39
2.0 2.00 0.035 1.76 1.00 34.00 60.00 1.94 116.20
2.5 2.50 0.035 2.14 1.00 35.00 75.00 2.20 165.32
3.0 3.00 0.035 2.50 1.00 36.00 90.00 2.44 219.85 H≈3.4m
3.5 3.50 0.035 2.84 1.00 37.00 105.00 2.66 279.11
4.0 4.00 0.035 3.16 1.00 38.00 120.00 2.85 342.54
4.5 4.50 0.035 3.46 1.00 39.00 135.00 3.03 409.68
5.00 5.00 0.035 3.75 1.00 40.00 150.00 3.20 480.15
4.5
4.0
3.5
3.0
2.5
Flow depth (m)
2.0
h≈ 1.5
1.0
0.5
0.0
0 50 100 150 200 250 300 350 400 450 500
Discharge (m3/s)
Discharge Q1(m3/s)
Note:
2 1
V =
1 3 2
R S Q = AV
n
TEGETA KWA NDEVU RIVER HYDRAULIC CAPACITY
DISCHARGE RATING CURVE FOR TEGETA KWA NDEVU RIVER
Depth Elevation Manning Roughness Hydraulic Radius Channel slope Wetted Area Velocity Discharge
Remarks
d (m) (m) n R S (%) Perimeter P (m) A (m 2) V (m/s) Q1(m 3/s)
0.0 0.00 0.035 0.00 1.00 0.00 0.00 0.00 0.00
0.5 0.50 0.035 0.48 1.00 31.00 15.00 0.82 12.26
1.0 1.00 0.035 0.94 1.00 32.00 30.00 1.27 38.11
1.5 1.50 0.035 1.36 1.00 33.00 45.00 1.63 73.39
2.0 2.00 0.035 1.76 1.00 34.00 60.00 1.94 116.20
2.5 2.50 0.035 2.14 1.00 35.00 75.00 2.20 165.32
3.0 3.00 0.035 2.50 1.00 36.00 90.00 2.44 219.85 H≈3.4m
3.5 3.50 0.035 2.84 1.00 37.00 105.00 2.66 279.11
4.0 4.00 0.035 3.16 1.00 38.00 120.00 2.85 342.54
4.5 4.50 0.035 3.46 1.00 39.00 135.00 3.03 409.68
5.00 5.00 0.035 3.75 1.00 40.00 150.00 3.20 480.15
4.5
4.0
3.5
3.0
2.5
Flow depth (m)
2.0
h≈ 3.4m, Q= 247m3/sec
1.5
1.0
0.5
0.0
0 50 100 150 200 250 300 350 400 450 500
Discharge (m3/s)
Discharge Q1(m3/s)
Note:
2 1
V =
1 3 2
R S Q = AV
n
APPENDIX 3.8
Scour depth calculation for proposed Bridges
APPENDIX 3.8a
SCOUR DEPTH CALCULATIONS FOR MSIMBAZI RIVER BRIDGE FOUNDATIONS :
Design Data
Two boreholes are carried out at this bridge location, BH-1 near pier and BH-2 near abutment.Top layers of
BH-1 and BH-2 consist of normal sand in depth of 0.6m and 1.10m respectively followed by weathered,fine
to medium grained sand
Calculation
Design Data
Two boreholes are carried out at this bridge location, BH-1 and BH-2 near abutments.Top layers of BH-1 and
BH-2 consist of normal sand in depth of 0.6m and 1.10m respectively followed by weathered,fine to medium
grained sand
SPAN ARRANGEMENT = 30
SKEW ANGLE = 0 degree
TYPE OF SUPERSTRUCTURE = RCC solid slab
EFFECTIVE LINEAR WATERWAY (W) = 29 m
DISCHARGE (Q) = 53.29 m3/s
HIGH FLOOD LEVEL (HFL) = 15 m
LOWEST BED LEVEL (LBL) = 12 m
SILT FACTOR (K sf ) = 1.0
TOP OF BOREHOLE BH-1 = 15 m
LEVEL(ABUTMENT) = 12.5 m
Calculation
Two boreholes are carried out at this bridge location, BH-1 and and BH-2 consist of normal sand in depth of
0.6m and 1.10m respectively followed by weathered,fine to medium grained sand
SPAN ARRANGEMENT = 30
SKEW ANGLE = 0 degree
TYPE OF SUPERSTRUCTURE = RCC solid slab
EFFECTIVE LINEAR WATERWAY (W) = 29 m
DISCHARGE (Q) = 247.29 m3/s
HIGH FLOOD LEVEL (HFL) = 15 m
LOWEST BED LEVEL (LBL) = 12 m
SILT FACTOR (K sf ) = 1.0
TOP OF BOREHOLE BH-1 = 15 m
LEVEL(ABUTMENT) = 12.5 m
Calculation
Design Data
Two boreholes are carried out at this bridge location, BH-1 and BH-2 near abutments.Top layers of BH-1 and
BH-2 consist of normal sand in depth of 0.6m and 1.10m respectively followed by fine to medium grained
sand
SPAN ARRANGEMENT = 30
SKEW ANGLE = 0 degree
TYPE OF SUPERSTRUCTURE = RCC solid slab
EFFECTIVE LINEAR WATERWAY (W) = 29 m
DISCHARGE (Q) = 222.64 m3/s
HIGH FLOOD LEVEL (HFL) = 25 m
LOWEST BED LEVEL (LBL) = 20 m
SILT FACTOR (K sf ) = 1.0
TOP OF BOREHOLE BH-1 = 24 m
LEVEL(ABUTMENT) = 21.5 m
Calculation
Discharge
Culvert Summary
Allowable HW Elevation 2.00m Headwater Depth/Height 1.01
Computed Headwater 2.00m Discharge 8.3071m³/s
Elevation
Inlet Control HW Elev. 1.97m Tailwater Elevation 0.00m
Outlet Control HW Elev. 2.00m Control Type Entrance
Control
Grades
Upstream Invert 0.15m Downstream Invert 0.00m
Length 12.00m Constructed Slope 0.012500m/m
Hydraulic Profile
Profile S2 Depth, Downstream 0.94m
Slope Type Steep Normal Depth 0.77m
Flow Regime Supercritic Critical Depth 1.16m
al
Velocity Downstream 4.12m/s Critical Slope 0.004203m/m
Section
Section Shape Box Mannings Coefficient 0.013
Section Material Concrete Span 2.13m
Section Size 2000 x Rise 1.83m
2000 mm
Number Sections 1
Outlet Control Properties
Outlet Control HW Elev. 2.00m Upstream Velocity Head 0.58m
Ke 0.20 Entrance Loss 0.12m
Culvert Summary
Allowable HW Elevation 2.40 m Headwater Depth/Height 0.75
Computed Headwater 2.40 m Discharge 21.06 m³/s
Elevation
Inlet Control HW Elev. 2.36 m Tailwater Elevation 0.00 m
Outlet Control HW Elev. 2.40 m Control Type Entrance
Control
Grades
Upstream Invert 0.12 m Downstream Invert 0.00 m
Length 12.00 m Constructed Slope 0.010000 m/m
Hydraulic Profile
Profile S2 Depth, Downstream 1.21 m
Slope Type Steep Normal Depth 0.98 m
Flow Regime Supercriti Critical Depth 1.43 m
cal
Velocity Downstream 4.41 m/s Critical Slope 0.003551 m/m
Section
Section Shape Box Mannings Coefficient 0.013
Section Material Concrete Span 3.05 m
Section Size 4000 x Rise 3.05 m
2000
Number Sections 1
Culvert Summary
Allowable HW Elevation 2.80m Headwater Depth/Height 0.89
Computed Headwater 2.80m Discharge 41.8476m³/s
Elevation
Inlet Control HW Elev. 2.76m Tailwater Elevation 0.00m
Outlet Control HW Elev. 2.80m Control Type Entrance
Control
Grades
Upstream Invert 0.10m Downstream Invert 0.00m
Length 12.00m Constructed Slope 0.008333m/m
Hydraulic Profile
Profile S2 Depth, Downstream 1.49m
Slope Type Steep Normal Depth 1.25m
Flow Regime Supercritic Critical Depth 1.69m
al
Velocity Downstream 4.62m/s Critical Slope 0.003761m/m
Section
Section Shape Box Mannings Coefficient 0.013
Section Material Concrete Span 3.05m
Section Size 4000 x Rise 3.05m
2000
Number Sections 2
Outlet Control Properties
Outlet Control HW Elev. 2.80m Upstream Velocity Head 0.84m
Ke 0.20 Entrance Loss 0.17m
Culvert Summary
Allowable HW Elevation 3.60m Headwater Depth/Height 1.15
Computed Headwater 3.60m Discharge 30.8814m³/s
Elevation
Inlet Control HW Elev. 3.55m Tailwater Elevation 0.00m
Outlet Control HW Elev. 3.60m Control Type Entrance
Control
Culvert Summary
Grades
Upstream Invert 0.10m Downstream Invert 0.00m
Length 12.00m Constructed Slope 0.008333m/m
Hydraulic Profile
Profile S2 Depth, Downstream 1.96m
Slope Type Steep Normal Depth 1.68m
Flow Regime Supercritic Critical Depth 2.19m
al
Velocity Downstream 5.16m/s Critical Slope 0.004183m/m
Section
Section Shape Box Mannings Coefficient 0.013
Section Material Concrete Span 3.05m
Section Size 4000 x Rise 3.05m
3000
Number Sections 1
Culvert Summary
Allowable HW Elevation 1.08 m Headwater Depth/Height 1.02
Computed Headwater 1.08 m Discharge 0.9325 m³/s
Elevation
Inlet Control HW Elev. 1.02 m Tailwater Elevation 0.00 m
Outlet Control HW Elev. 1.08 m Control Type Entrance
Control
Grades
Upstream Invert 0.15 m Downstream Invert 0.00 m
Length 12.00 m Constructed Slope 0.012500 m/m
Hydraulic Profile
Profile S2 Depth, Downstream 0.46 m
Slope Type Steep Normal Depth 0.43 m
Flow Regime Supercriti Critical Depth 0.57 m
cal
Velocity Downstream 2.81 m/s Critical Slope 0.004868 m/m
Section
Section Shape Circular Mannings Coefficient 0.013
Section Material Concrete Span 0.91 m
Section Size 900 mm Rise 0.91 m
Number Sections 1
Culvert Summary
Allowable HW Elevation 1.44 m Headwater Depth/Height 1.06
Computed Headwater 1.44 m Discharge 2.0392 m³/s
Elevation
Inlet Control HW Elev. 1.36 m Tailwater Elevation 0.00 m
Outlet Control HW Elev. 1.44 m Control Type Entrance
Control
Grades
Upstream Invert 0.15 m Downstream Invert 0.00 m
Length 12.00 m Constructed Slope 0.012500 m/m
Hydraulic Profile
Profile S2 Depth, Downstream 0.64 m
Slope Type Steep Normal Depth 0.57 m
Flow Regime Supercriti Critical Depth 0.78 m
cal
Velocity Downstream 3.26 m/s Critical Slope 0.004559 m/m
Section
Section Shape Circular Mannings Coefficient 0.013
Section Material Concrete Span 1.22 m
Section Size 1200 mm Rise 1.22 m
Number Sections 1
Culvert Summary
Allowable HW Elevation 1.88 m Headwater Depth/Height 1.14
Computed Headwater 1.88 m Discharge 3.9761 m³/s
Elevation
Inlet Control HW Elev. 1.79 m Tailwater Elevation 0.00 m
Outlet Control HW Elev. 1.88 m Control Type Entrance
Control
Grades
Upstream Invert 0.15 m Downstream Invert 0.00 m
Length 12.00 m Constructed Slope 0.012500 m/m
Hydraulic Profile
Profile S2 Depth, Downstream 0.87 m
Slope Type Steep Normal Depth 0.75 m
Flow Regime Supercriti Critical Depth 1.03 m
cal
Velocity Downstream 3.72 m/s Critical Slope 0.004498 m/m
Section
Section Shape Circular Mannings Coefficient 0.013
Section Material Concrete Span 1.52 m
Section Size 1500 mm Rise 1.52 m
Number Sections 1
Culvert Summary
Allowable HW Elevation 2.80 m Headwater Depth/Height 1.48
Computed Headwater 2.80 m Discharge 8.8503 m³/s
Elevation
Inlet Control HW Elev. 2.80 m Tailwater Elevation 0.00 m
Outlet Control HW Elev. 2.74 m Control Type Inlet
Control
Grades
Upstream Invert 0.10 m Downstream Invert 0.00 m
Length 12.00 m Constructed Slope 0.008333 m/m
Hydraulic Profile
Profile S2 Depth, Downstream 1.35 m
Slope Type Steep Normal Depth 1.25 m
Flow Regime Supercriti Critical Depth 1.47 m
cal
Velocity Downstream 4.25 m/s Critical Slope 0.005645 m/m
Section
Section Shape Circular Mannings Coefficient 0.013
Section Material Concrete Span 1.83 m
Section Size 1800 mm Rise 1.83 m
Number Sections 1
21 Football gr. 10+975 524626 9253642 CBX 900 45 3 RHS existing, retain
23 Pump house 11+520 524428 9254048 CBX 900 45 2 RHS existing, retain
25 Sports grnd 11+925 524202 9254511 CBX 900 45 1 RHS existing, retain
26 Sports grnd 12+025 524113 9254730 CBX 900 45 1 RHS existing, retain
29 Goba junct. 15+013 523950 9257118 CBX 4000x1500 45 2 LHS new and retain old cbx
30 Makonde 15+915 523318 9257704 CBX 4000x1500 45 2 RHS new and retain old cbx
1 Mwenge/ Bagamoyo 9+550 0525208 9252569 CBX 1500x1500 45 2 LHS new, to Mlalakuwa river
Time of Concentration
Shallow concetrated and channel travel time calculated
Ti me (i ni ti a l ) ca l cul a ted us i ng the fol l owi ng SCS TR-55 equa ti on:
using the following equation:
where: where:
n = roughness coefficient tt = Travel Time (min)
L = legth of overland flow in meters (150 maximum) L = flow length (m)
P = 2-year, 24-hours rainfall depth
S = average basin slope in percentage V= velocity (m/s)
ti = 15 min
tt = 0 min
Tc = ti+tt = 30 min
Tc (check) = N/A min
Tc (used for calculation) = 30 min
Runoff Coefficient ( C ):
c(f) from Hydrology Design Criteria, 819.2 (1)
The product of Cf times C shall not exceed 1.0
Runoff Coefficient
Frequency Cf C Cf*C Cother This Project ( C )
2-year 1.000 0.9 0.9 0.9
5-year 1.000 0.9 0.9 0.9
10-year 1.000 0.9 0.9 0.9
25-year 1.100 0.9 0.9 0.99
50-year 1.200 0.9 0.9 1.08
100-year 1.250 0.9 0.9 1.125
Time of Concentration
Shallow concetrated and channel travel time calculated
Ti me (i ni ti a l ) ca l cul a ted us i ng the fol l owi ng SCS TR-55 equa ti on:
using the following equation:
where: where:
n = roughness coefficient tt = Travel Time (min)
L = legth of overland flow in meters (150 maximum) L = flow length (m)
P = 2-year, 24-hours rainfall depth
S = average basin slope in percentage V= velocity (m/s)
ti = 30 min
tt = 0 min
Tc = ti+tt = 30 min
Tc (check) = N/A min
Tc (used for calculation) = 30 min
Runoff Coefficient ( C ):
c(f) from Hydrology Design Criteria, 819.2 (1)
The product of Cf times C shall not exceed 1.0
Runoff Coefficient
Frequency Cf C Cf*C Cother This Project ( C )
2-year 1.000 0.9 0.9 0.9
5-year 1.000 0.9 0.9 0.9
10-year 1.000 0.9 0.9 0.9
25-year 1.100 0.9 0.9 0.99
50-year 1.200 0.9 0.9 1.08
100-year 1.250 0.9 0.9 1.125
Time of Concentration
Shallow concetrated and channel travel time calculated
Ti me (i ni ti a l ) ca l cul a ted us i ng the fol l owi ng SCS TR-55 equa ti on:
using the following equation:
where: where:
n = roughness coefficient tt = Travel Time (min)
L = legth of overland flow in meters (150 maximum) L = flow length (m)
P = 2-year, 24-hours rainfall depth
S = average basin slope in percentage V= velocity (m/s)
ti = 30 min
tt = 0 min
Tc = ti+tt = 30 min
Tc (check) = N/A min
Tc (used for calculation) = 30 min
Runoff Coefficient ( C ):
c(f) from Hydrology Design Criteria, 819.2 (1)
The product of Cf times C shall not exceed 1.0
Runoff Coefficient
Frequency Cf C Cf*C Cother This Project ( C )
2-year 1.000 0.9 0.9 0.9
5-year 1.000 0.9 0.9 0.9
10-year 1.000 0.9 0.9 0.9
25-year 1.100 0.9 0.9 0.99
50-year 1.200 0.9 0.9 1.08
100-year 1.250 0.9 0.9 1.125
APPENDIX 6-3
ADJUSTMENT REPORT
Network Adjustment
www.MOVE3.com
(c) 1993-2012 Grontmij
Licensed to Leica Geosystems AG
Project Information
General Information
Adjustment
Type: Minimally constrained
Dimension: 3D
Coordinate system: UTM 37S-ARC 1960 DATUM
Height mode: Ellipsoidal
Number of iterations: 1
Maximum coord correction in last iteration: 0.0001 m (tolerance is met)
Stations
Number of (partly) known stations: 1
Number of unknown stations: 31
Total: 32
Observations
GPS coordinate differences: 96 (32 baselines)
Known coordinates: 3
Total: 99
Unknowns
Coordinates: 96
Total: 96
Degrees of freedom: 3
Testing
Alfa (multi dimensional): 0.1291
Alfa 0 (one dimensional): 5.0 %
Beta: 80.0 %
Sigma a-priori (GPS): 10.0
Adjustment Results
Coordinates
APPENDIX 6-5
TRAVERSE-COMPUTATIONS
COVADIS Calculs Topométriques version 200x-8
(C) Géomédia S.A. 1993-2006
Calculation results
ST: GP.3 X= 525187.446, Y = 9252542.710, Z = 26.903, V0 = 285.7186
Constant(s) X= 525187.446, Y = 9252542.710, Z = 26.903, V0 = 285.7186
Angles calculation
Station X Y Gi V0
GP.3 525187.446 9252542.710 18.0385 285.7186
IDG51 525210.221 9252620.925 353.0845 4.5275
BM.28 525030.161 9252819.337 365.9330 70.6450
BM.29 524898.614 9253041.236 370.3878 251.0698
BM.30 524797.997 9253241.718 370.8698 388.1282
BM.31 524686.130 9253468.890 370.9197 163.0917
BM.32 524573.671 9253697.717 370.6406 264.1956
BM.33 524436.943 9253972.870 370.8261 41.2573
BM.34 524324.411 9254200.998 371.0086 220.0819
BM.35 524178.753 9254498.424 377.1522 338.3949
BM.36 524063.205 9254806.439 379.9591 343.8381
GP.6 523936.080 9255196.837 254.0500
Closure -0.094 -0.046
Results closure
Type Closure.
Planimetric (m) 0.1044
Angular (Gr) 0.1306
Height (m) 0.0119
Fractional Linear misclosure= 1:28000
Results calculation
ST: GP.1 X= 531581.102, Y = 9247518.099, Z = 7.111, V0 = 112.3603
Constante(s) X= 531581.102, Y = 9247518.099, Z = 7.111, V0 = 112.3603
Angles calculation
Station X Y Gi V0
GP.1 531581.102 9247518.099 397.9348 112.3603
BM.1 531573.485 9247752.816 389.9704 75.8634
BM.2 531512.528 9248136.528 394.6740 289.2464
BM.3 531497.021 9248321.455 352.9907 374.5668
IDG.32 531148.861 9248703.966 370.8111 301.5124
IDG.31 531036.689 9248931.228 374.1058 394.9058
BM.4 530992.131 9249034.667 381.0226 261.6988
BM.5 530964.895 9249123.311 380.1588 378.2332
BM.6 530863.410 9249438.320 377.3079 136.4168
IDG.35 530766.348 9249698.994 150.6977
Closure -0.020 -0.027
Results closure
Type closure
Planimétrique (m) 0.0336
Angular (Gr) 0.0055
Height (m) 0.1254
Fractional Linear misclosure= 1:11000
Results calculation
ST: GP.2 X= 529673.359, Y = 9251071.973, Z = 9.548, V0 = 311.5583
Constant(s) X= 529673.359, Y = 9251071.973, Z = 9.548, V0 = 311.5583
Angles calculation
Station X Y Gi V0
GP.2 529673.359 9251071.973 130.3767 311.5583
IDG.38 529949.364 9250929.278 142.3269 289.2396
IDG.37 530239.626 9250701.731 141.6869 6.3271
BM.8 530355.543 9250612.726 175.5758 307.7815
BM.7 530462.602 9250347.503 164.7979 383.6254
IDG.36 530679.516 9249996.041 277.1133
Ferm. -0.076 -0.117
Results closure
Type closure
Planimétrique (m) 0.1393
Angular (Gr) 0.0597
Height (m) -0.0220
Fractional Linear misclosure= 1:71000
Results calculation
ST: GP.102 X= 529429.408, Y = 9251148.264, Z = 10.041, V0 = 309.6057
Constant(s) X= 529429.408, Y = 9251148.264, Z = 10.041, V0 = 309.6057
Angles calculation
Station X Y Gi V0
GP.102 529429.408 9251148.264 309.7959 309.6057
BM.9 529120.325 9251196.203 276.5500 340.8877
IDG.43 529038.752 9251164.718 295.6157 157.7332
IDG.44 528663.307 9251138.821 276.0020 364.7474
BM.10 528510.609 9251078.369 306.2769 7.1230
BM.11 528328.277 9251096.405 280.9156 309.4502
CP.01 528256.638 9251074.262 286.9475 162.5701
BM.12 527944.675 9251009.389 358.5498 373.8662
IDG.45 527916.990 9251045.724 301.0502 387.1444
BM.13 527632.456 9251050.419 326.3741 320.5426
IDG.46 527570.727 9251077.563 336.1404 370.1920
BM.14 527452.538 9251152.934 308.0013 373.7527
BM.15 527212.412 9251183.274 335.5300 245.4811
BM.16 526964.446 9251338.082 311.5562 292.3281
BM.18 526741.878 9251378.933 357.4091 151.6485
BM.19 526576.659 9251587.898 328.5632 34.3206
BM.20 526325.554 9251708.783 354.3497 68.8389
BM.21 526115.576 9251949.611 327.1807 370.3126
BM.22 525794.899 9252095.499 350.1504 76.0525
BM.23 525422.075 9252470.088 339.2332 12.9044
IDG.51 525209.943 9252620.341 218.0087 398.7479
GP.3 525187.205 9252542.115 25.3707
Closure 0.241 0.595
Results closure
Type closure
Planimétrique (m) 0.6425
Angular (Gr) -0.1725
Altimétrique (m) 0.1857
Fractional Linear misclosure= 1:8000
Calculation results
ST: GP.107 X= 523060.353, Y = 9258445.337, Z = 35.447, V0 = 166.9704
Constant(s) X= 523060.353, Y = 9258445.337, Z = 35.447, V0 = 166.9704
Angles computations
Station X Y Gi V0
GP.107 523060.353 9258445.337 385.8667 166.9704
BM.46 522938.975 9258983.060 383.1885 51.4896
BM.47 522863.109 9259263.641 384.4404 318.5043
BM.48 522768.474 9259643.099 384.5613 135.9620
BM.49 522685.920 9259976.815 384.5995 353.1588
BM.50 522593.329 9260352.067 384.9016 63.2926
BM.51 522476.874 9260833.855 372.5294 276.9470
GP.8 522386.412 9261030.321 166.8270
Closure 0.306 0.137
Results closure
Type Closure
Planimétrique (m) 0.3352
Angular (Gr) 0.0791
Height (m) 0.0073
Fractional Linear misclosure= 1:8000
Calculation results
ST: GP.108 X= 522209.393, Y = 9261273.946, Z = 62.387, V0 = 127.8648
Constant(s) X= 522209.393, Y = 9261273.946, Z = 62.387, V0 = 127.8648
Angles calculation
Station X Y Gi V0
GP.108 522209.393 9261273.946 359.6370 127.8648
BM.52 521931.795 9261651.481 361.7638 26.1434
BM.53 521572.857 9262175.450 356.6320 163.9698
BM.54 521410.288 9262375.982 362.7470 67.7972
BM.55 521329.917 9262497.282 362.6916 66.3613
BM.56 521072.485 9262885.078 362.3928 277.0555
BM.57 520906.720 9263132.260 356.0985 89.7326
BM.58 520692.564 9263391.947 352.6865 307.4712
GP.9 520435.447 9263671.735 196.2113
Closure 0.234 0.141
Results calculation
ST: GP.109 X= 520144.894, Y = 9263995.381, Z = 30.085, V0 = 397.0484
Constant(s) X= 520144.894, Y = 9263995.381, Z = 30.085, V0 = 397.0484
Results closure
Type closure
Planimetric (m) 0.3497
Angular (Gr) -0.0333
Height (m) 0.0021
Fractional Linear misclosure= 1:7000
Calculation results
ST: GP.103 X= 525012.216, Y = 9252317.095, Z = 29.917, V0 = 374.6130
Constant(s) X= 525012.216, Y = 9252317.095, Z = 29.917, V0 = 374.6130
Angles calculation
Station X Y Gi V0
GP.103 525012.216 9252317.095 253.1908 374.6130
BM.24 524790.158 9252116.251 244.3194 42.0290
BM.25 524443.766 9251701.786 242.6394 10.8471
BM.26 524235.974 9251439.387 239.5891 106.0561
BM.27 523936.327 9251021.311 240.8041 110.7954
GP.4 523579.544 9250543.063 178.6758
Closure -0.154 0.160
Results closure
Type closure
Planimetric (m) 0.2222
Angular (Gr) 0.0165
Height (m) -0.0423
Fractional Linear misclosure= 1:10000
Calculation results
ST: GP.106 X= 523882.719, Y = 9255309.883, Z = 35.987, V0 = 357.6920
Constant(s) X= 523882.719, Y = 9255309.883, Z = 35.987, V0 = 357.6920
Angles calculation
Station X Y Gi V0
GP.106 523882.719 9255309.883 387.0408 357.6920
BM.37 523824.959 9255589.699 399.0666 169.9136
BM.38 523822.306 9255770.636 388.6704 185.0314
BM.39 523755.308 9256143.121 381.5092 0.7502
BM.40 523680.735 9256392.609 380.9941 99.7781
BM.41 523631.046 9256554.072 381.4429 136.5209
BM.42 523568.343 9256763.053 381.2727 294.4987
BM.43 523481.609 9257049.344 381.5335 33.0585
BM.44 523348.078 9257496.698 381.6333 92.7183
BM.45 523221.700 9257922.522 380.1781 222.9701
GP.7 523145.174 9258160.307 56.5039
Closure. 0.035 0.007
Results closure
Type closure
Planimetric (m) 0.0353
Angular (Gr) -0.0020
Height (m) 0.1505
Fractional Linear misclosure= 1:83000
APPENDIX 6-4
LEVELLING COMPS
Mean
Forward Backward differences
Differences Raw
Point n
FW-BW Elevation
Point Raw Diff Diff Point Raw
n elevation Foreward Backward n elevation (FW+BW)/2
IDG.37 62.020 IDG.37 62.036 IDG.37 14.848
-2.707 0.000 -2.706 -2.706
IDG.38 59.314 IDG.38 59.330 IDG.38 12.142
-2.593 0.002 -2.594 -2.594
GP.02 56.721 GP.02 56.736 GP.02 9.548
0.494 0.003 0.491 0.493
GP.102 57.215 GP.102 57.227 GP.102 10.041
6.240 0.002 6.238 6.239
BM.9 63.455 BM.9 63.465 BM.9 16.280
-1.482 0.000 -1.482 -1.482
IDG.43 61.973 IDG.43 61.983 IDG.43 14.798
-5.198 0.004 -5.203 -5.201
IDG.44 56.775 IDG.44 56.781 IDG.44 9.597
1.000 -0.003 1.003 1.001
BM.10 57.775 BM.10 57.783 BM.10 10.599
0.305 0.000 0.304 0.305
BM.11 58.079 BM.11 58.088 BM.11 10.903
2.626 -0.003 2.630 2.628
BM.12 60.706 BM.12 60.717 BM.12 13.531
-0.672 0.002 -0.674 -0.673
IDG.45 60.034 IDG.45 60.043 IDG.45 12.858
3.495 0.000 3.495 3.495
BM.13 63.529 BM.13 63.539 BM.13 16.354
0.927 0.002 0.925 0.926
IDG.46 64.456 IDG.46 64.463 IDG.46 17.279
2.251 -0.002 2.252 2.251
BM.14 66.707 BM.14 66.715 BM.14 19.531
1.055 -0.002 1.056 1.056
BM.15 67.761 BM.15 67.772 BM.15 20.586
-0.447 -0.005 -0.442 -0.444
BM.16 67.315 BM.16 67.330 BM.16 20.142
0.394 -0.001 0.394 0.394
BM.18 67.708 BM.18 67.724 BM.18 20.536
0.651 0.004 0.647 0.649
BM.19 68.359 BM.19 68.371 BM.19 21.185
0.585 0.002 0.583 0.584
BM.20 68.944 BM.20 68.954 BM.20 21.769
1.388 0.000 1.388 1.388
BM.21 70.332 BM.21 70.342 BM.21 23.157
0.990 -0.002 0.992 0.991
BM.22 71.321 BM.22 71.334 BM.22 24.147
-0.308 0.001 -0.310 -0.309
BM.23 71.013 BM.23 71.025 BM.23 23.839
2.772 0.004 2.767 2.770
IDG.51 73.785 IDG.51 73.792 IDG.51 26.608
0.295 -0.001 0.295 0.295
GP.03 74.080 GP.03 74.087 GP.03 26.903
3.013 -0.001 3.014 3.014
GP.103 77.093 GP.103 77.102 GP.103 29.917
2.977 -0.002 2.979 2.978
BM.24 80.070 BM.24 80.081 BM.24 32.895
6.196 0.006 6.190 6.193
BM.25 86.266 BM.25 86.271 BM.25 39.088
2.373 -0.004 2.377 2.375
BM.26 88.639 BM.26 88.647 BM.26 41.463
3.647 0.000 3.648 3.648
BM.27 92.286 BM.27 92.295 BM.27 45.110
4.770 0.000 4.770 4.770
GP.04 97.056 GP.04 97.052 GP.04 49.880
2.944 -0.005 2.948 2.946
GP.104 100.000 GP.104 100.000 GP.104 52.827
0.003 10km
Forward Differences Backward Mean differences
Point n Raw Elevation
Point n Raw elevation Diff Foreward FW-BW Diff Backward Point n Raw elevation (FW+BW)/2
GP.104 104.5172 GP.104 104.521895 GP.104 52.827
-3.307 0.005 -3.312 -3.310
GP.05 101.2102 GP.05 101.209681 GP.05 49.517
-1.210 -0.001 -1.210 -1.210
GP.105 100.0000 GP.105 100 GP.105 48.307
Forward Differences Backward Mean differences
Point n Raw Elevation
Point n Raw elevation Diff Foreward FW-BW Diff Backward Point n Raw elevation (FW+BW)/2
GP.04 100.214 GP.04 100.213 GP.04 49.880
2.939 0.000 2.939 2.939
GP.104 103.153 GP.104 103.152 GP.104 52.819
4.611 -0.004 4.615 4.613
CP.02 107.764 CP.02 107.767 CP.02 57.432
-2.559 -0.001 -2.558 -2.559
CP.01 105.205 CP.01 105.209 CP.01 54.874
-3.416 0.003 -3.419 -3.418
BRT.58 101.788 BRT.58 101.789 BRT.58 51.456
-1.788 0.001 -1.789 -1.789
BRT.57 100.000 BRT.57 100.000 BRT.57 49.667
-0.001 BRT.57-BRT5 49.690 -0.023
Forward Backward Mean differences
Differences Raw
Point Raw Diff Diff Point Raw Point n
FW-BW Elevation
n elevation Foreward Backward n elevation (FW+BW)/2
IDG.51 100.000 IDG.51 100.000 IDG.51 26.608
0.167 0.001 0.166 0.166
BM.28 100.167 BM.28 100.166 BM.28 26.774
0.336 -0.001 0.338 0.337
BM.29 100.503 BM.29 100.503 BM.29 27.111
-1.217 -0.002 -1.215 -1.216
BM.30 99.286 BM.30 99.288 BM.30 25.895
0.192 0.003 0.189 0.190
BM.31 99.478 BM.31 99.477 BM.31 26.086
0.167 -0.001 0.168 0.168
BM.32 99.645 BM.32 99.645 BM.32 26.253
1.275 -0.001 1.275 1.275
BM.33 100.920 BM.33 100.921 BM.33 27.528
3.219 -0.001 3.219 3.219
BM.34 104.139 BM.34 104.140 BM.34 30.747
2.509 0.005 2.504 2.507
BM.35 106.648 BM.35 106.644 BM.35 33.254
1.704 0.007 1.697 1.701
BM.36 108.351 BM.36 108.341 BM.36 34.954
1.807 -0.006 1.814 1.810
GP.6 110.159 GP.6 110.155 GP.6 36.765
-0.778 -0.002 -0.777 -0.777
GP.106 109.380 GP.106 109.378 GP.106 35.987
-14.714 0.000 -14.715 -14.714
BM.37 94.666 BM.37 94.663 BM.37 21.273
1.425 0.002 1.424 1.425
BM.38 96.091 BM.38 96.087 BM.38 22.697
12.250 0.000 12.250 12.250
BM.39 108.342 BM.39 108.337 BM.39 34.948
0.507 0.003 0.505 0.506
BM.40 108.849 BM.40 108.842 BM.40 35.454
-1.540 -0.002 -1.537 -1.539
BM.41 107.310 BM.41 107.305 BM.41 33.915
-1.714 0.002 -1.716 -1.715
BM.42 105.595 BM.42 105.589 BM.42 32.200
-2.612 -0.001 -2.611 -2.611
BM.43 102.983 BM.43 102.978 BM.43 29.589
3.262 0.004 3.258 3.260
BM.44 106.246 BM.44 106.236 BM.44 32.849
0.986 0.000 0.987 0.987
BM.45 107.232 BM.45 107.222 BM.45 33.835
1.137 -0.007 1.145 1.141
GP.7 108.369 GP.7 108.367 GP.7 34.976
0.473 0.005 0.468 0.471
GP.107 108.843 GP.107 108.835 GP.107 35.447
-3.451 -0.008 -3.444 -3.447
BM.46 105.391 BM.46 105.392 BM.46 32.000
0.629 0.004 0.624 0.626
BM.47 106.020 BM.47 106.016 BM.47 32.626
-3.740 0.006 -3.746 -3.743
BM.48 102.280 BM.48 102.270 BM.48 28.883
-2.937 0.007 -2.944 -2.940
BM.49 99.344 BM.49 99.326 BM.49 25.943
0.396 0.007 0.389 0.393
BM.50 99.740 BM.50 99.715 BM.50 26.336
13.716 -0.003 13.718 13.717
BM.51 113.455 BM.51 113.434 BM.51 40.053
9.312 -0.004 9.316 9.314
GP.8 122.767 GP.8 122.750 GP.8 49.367
13.023 0.004 13.019 13.021
GP.108 135.790 GP.108 135.769 GP.108 62.387
-2.609 0.000 -2.609 -2.609
BM.52 133.181 BM.52 133.160 BM.52 59.779
-7.710 -0.003 -7.707 -7.709
BM.53 125.471 BM.53 125.453 BM.53 52.070
0.267 0.002 0.265 0.266
BM.54 125.738 BM.54 125.718 BM.54 52.336
-5.100 -0.005 -5.095 -5.097
BM.55 120.639 BM.55 120.623 BM.55 47.239
-19.745 0.004 -19.748 -19.747
BM.56 100.894 BM.56 100.874 BM.56 27.492
3.233 -0.001 3.234 3.234
BM.57 104.127 BM.57 104.108 BM.57 30.726
0.973 0.002 0.972 0.973
BM.58 105.101 BM.58 105.080 BM.58 31.698
-0.338 -0.003 -0.335 -0.337
GP.9 104.762 GP.9 104.745 GP.9 31.362
-1.278 -0.003 -1.275 -1.276
GP.109 103.484 GP.109 103.470 GP.109 30.085
0.014
12km
Forward Differences Backward Mean differences
Point n Raw Elevation
Point n Raw elevation Diff Foreward FW-BW Diff Backward Point n Raw elevation (FW+BW)/2
GP.109 100.000 GP.109 100.000 GP.109 30.085
-1.995 0.000 -1.995 -1.995
BM.59 98.005 BM.59 98.005 BM.59 28.090
-3.458 -0.001 -3.458 -3.458
BM.60 94.547 BM.60 94.547 BM.60 24.632
-1.593 -0.003 -1.590 -1.592
BM.61 92.953 BM.61 92.957 BM.61 23.040
-1.635 0.003 -1.638 -1.637
BM.63 91.319 BM.63 91.319 BM.63 21.404
-0.790 0.002 -0.792 -0.791
BM.64 90.528 BM.64 90.526 BM.64 20.612
-0.097 -0.004 -0.093 -0.095
BM.65 90.431 BM.65 90.433 BM.65 20.517
0.037 -0.003 0.040 0.038
GP.10 90.468 GP.10 90.473 GP.10 20.555
-0.674 -0.001 -0.673 -0.673
GP.110 89.794 GP.110 89.800 GP.110 19.882
-0.007
Forward Differences Backward Mean differences
Point n Raw Elevation
Point n Raw elevation Diff Foreward FW-BW Diff Backward Point n Raw elevation (FW+BW)/2
BM.3 100.000 BM.3 100.000 BM.3 5.891
0.211 0.006 0.205 0.208
BM.2 100.211 BM.2 100.205 BM.2 6.099
-0.528 -0.001 -0.528 -0.528
BM.1 99.683 BM.1 99.677 BM.1 5.571
1.540 0.001 1.540 1.540
GP.01 101.224 GP.01 101.217 GP.01 7.111
0.491 0.004 0.487 0.489
DDP.29 101.715 DDP.29 101.705 DDP.29 7.601
0.010
Forward Differences Backward Mean differences
Point n Raw Elevation
Point n Raw elevation Diff Foreward FW-BW Diff Backward Point n Raw elevation (FW+BW)/2
GP.01 100.000 GP.01 100.000 GP.01 7.111
-2.251 0.001 -2.252 -2.252
CP.03 97.749 CP.03 97.748 CP.03 4.860
1.729 -0.005 1.734 1.732
CP.04 99.478 CP.04 99.482 CP.04 6.591
-1.760 0.007 -1.767 -1.764
GP.11 97.718 GP.11 97.714 GP.11 4.828
0.605 0.002 0.602 0.603
GP.111 98.323 GP.111 98.317 GP.111 5.431
0.007
Forward Backward Mean differences
Differences Point Raw
Point Raw Diff Diff Raw
FW-BW n Elevation
n elevation Foreward Backward Point n elevation (FW+BW)/2
BM.44 100.766 BM.44 100.774 BM.44 32.849
-0.869 0.000 -0.869 -0.869
P2 99.896 P2 99.905 P2 31.979
0.104 0.009 0.095 0.099
BM44.1 100.000 BM44.1 100.000 BM44.1 32.079
APPENDIX 6-5
DESCRIPTIONS-CARDS
APPENDIX : DESCRIPTION CARDS
o Establishment Date: JULY 2019
GPS POINT n : DPP.29
UTM ZONE 37S - CLARKE 1880 ELLIPSOID Informations
Easting 531407.293 Nature of Point:
IPC pipe with concrete plus Iron bar
Northing(Y) 9247354.353 inserted at the middle
Chainage:
Elevation(Z) 7.601 Location:
Coordinate system:
Corrections Projection: UTM Zone 37 South
Scale Factor(SF) = 0.999612 These corrections must Ellipsoid: Clark 1880
be applied to distances Datum: Arc 1960
mesured on field from Remarks: Intervisible with GP.1
this point
Photographs
Sketch
o Establishment Date: JULY 2019
GPS POINT n : GP.01
UTM ZONE 37S - CLARKE 1880 ELLIPSOID Informations
Easting(X) 531581.102 Nature of Point:
IPC pipe with concrete plus Iron bar
Northing(Y) 9247518.099 inserted at the middle
Chainage:
Elevation(Z) 7.111 Location:
Coordinate system:
Corrections Projection: UTM Zone 37 South
Scale Factor(SF) = 0.999612 These corrections must Ellipsoid: Clark 1880
be applied to distances Datum: Arc 1960
mesured on field from Remarks: Intervisible with DPP.29
this point
Photographs
Sketch
o Establishment Date: JULY 2019
GPS POINT n : IDG.35
UTM ZONE 37S - CLARKE 1880 ELLIPSOID Informations
Easting(X) 530766.328 Nature of Point:
IPC pipe with concrete plus Iron bar
Northing(Y) 9249698.967 inserted at the middle
Chainage:
Elevation(Z) 6.045 Location:
Coordinate system:
Corrections Projection: UTM Zone 37 South
Scale Factor(SF) = 0.999612 These corrections must Ellipsoid: Clark 1880
be applied to distances Datum: Arc 1960
mesured on field from Remarks: Intervisible with IDG.36
this point
Photographs
Sketch
o Establishment Date: JULY 2019
GPS POINT n : IDG.36
UTM ZONE 37S - CLARKE 1880 ELLIPSOID Informations
Easting(X) 530679.440 Nature of Point:
IPC pipe with concrete plus Iron bar
Northing(Y) 9249995.924 inserted at the middle
Chainage:
Elevation(Z) 6.369 Location:
Coordinate system:
Corrections Projection: UTM Zone 37 South
Scale Factor(SF) = 0.999612 These corrections must Ellipsoid: Clark 1880
be applied to distances Datum: Arc 1960
mesured on field from Remarks: Intervisible with IDG.35
this point
Photographs
Sketch
o Establishment Date: JULY 2019
GPS POINT n : GP.02
UTM ZONE 37S - CLARKE 1880 ELLIPSOID Informations
Easting(X) 529673.359 Nature of Point:
IPC pipe with concrete plus Iron bar
Northing(Y) 9251071.973 inserted at the middle
Chainage:
Elevation(Z) 9.548 Location:
Coordinate system:
Corrections Projection: UTM Zone 37 South
Scale Factor(SF) = 0.999611 These corrections must Ellipsoid: Clark 1880
be applied to distances Datum: Arc 1960
mesured on field from Remarks: Intervisible with GP.102
this point
Photographs
Sketch
o Establishment Date: JULY 2019
GPS POINT n : GP.102
UTM ZONE 37S - CLARKE 1880 ELLIPSOID Informations
Easting(X) 529429.408 Nature of Point:
IPC pipe with concrete plus Iron bar
Northing(Y) 9251148.264 inserted at the middle
Chainage:
Elevation(Z) 10.041 Location:
Coordinate system:
Corrections Projection: UTM Zone 37 South
Scale Factor(SF) = 0.999611 These corrections must Ellipsoid: Clark 1880
be applied to distances Datum: Arc 1960
mesured on field from Remarks: Intervisible with GP.2
this point
Photographs
Sketch
o Establishment Date: JULY 2019
GPS POINT n : GP.03
UTM ZONE 37S - CLARKE 1880 ELLIPSOID Informations
Easting(X) 525187.446 Nature of Point:
IPC pipe with concrete plus Iron bar
Northing(Y) 9252542.71 inserted at the middle
Chainage:
Elevation(Z) 26.903 Location:
Coordinate system:
Corrections Projection: UTM Zone 37 South
Scale Factor(SF) = 0.999608 These corrections must Ellipsoid: Clark 1880
be applied to distances Datum: Arc 1960
mesured on field from Remarks: Intervisible with GP.103
this point
Photographs
Sketch
o Establishment Date: JULY 2019
GPS POINT n : GP.103
UTM ZONE 37S - CLARKE 1880 ELLIPSOID Informations
Easting(X) 525012.216 Nature of Point:
IPC pipe with concrete plus Iron bar
Northing(Y) 9252317.095 inserted at the middle
Chainage:
Elevation(Z) 29.917 Location:
Coordinate system:
Corrections Projection: UTM Zone 37 South
Scale Factor(SF) = 0.999608 These corrections must Ellipsoid: Clark 1880
be applied to distances Datum: Arc 1960
mesured on field from Remarks: Intervisible with GP.3
this point
Photographs
Sketch
o Establishment Date: JULY 2019
GPS POINT n : GP.4
UTM ZONE 37S - CLARKE 1880 ELLIPSOID Informations
Easting(X) 523579.290 Nature of Point:
IPC pipe with concrete plus Iron bar
Northing(Y) 9250543.223 inserted at the middle
Chainage:
Elevation(Z) 49.880 Location:
Coordinate system:
Corrections Projection: UTM Zone 37 South
Scale Factor(SF) = 0.999607 These corrections must Ellipsoid: Clark 1880
be applied to distances Datum: Arc 1960
mesured on field from Remarks: Intervisible with GP.104
this point
Photographs
Sketch
o Establishment Date: JULY 2019
GPS POINT n : GP.104
UTM ZONE 37S - CLARKE 1880 ELLIPSOID Informations
Easting(X) 523259.849 Nature of Point:
IPC pipe with concrete plus Iron bar
Northing(Y) 9250245.87 inserted at the middle
Chainage:
Elevation(Z) 52.827 Location:
Coordinate system:
Corrections Projection: UTM Zone 37 South
Scale Factor(SF) = 0.999607 These corrections must Ellipsoid: Clark 1880
be applied to distances Datum: Arc 1960
mesured on field from Remarks: Intervisible with GP.4
this point
Photographs
Sketch
o Establishment Date: JULY 2019
GPS POINT n : GP.5
UTM ZONE 37S - CLARKE 1880 ELLIPSOID Informations
Easting(X) 523668.827 Nature of Point:
IPC pipe with concrete plus Iron bar
Northing(Y) 9249931.288 inserted at the middle
Chainage:
Elevation(Z) 49.517 Location:
Coordinate system:
Corrections Projection: UTM Zone 37 South
Scale Factor(SF) = 0.999607 These corrections must Ellipsoid: Clark 1880
be applied to distances Datum: Arc 1960
mesured on field from Remarks: Intervisible with GP.105
this point
Photographs
Sketch
o Establishment Date: JULY 2019
GPS POINT n : GP.105
UTM ZONE 37S - CLARKE 1880 ELLIPSOID Informations
Easting(X) 523772.797 Nature of Point:
IPC pipe with concrete plus Iron bar
Northing(Y) 9250056.386 inserted at the middle
Chainage:
Elevation(Z) 48.307 Location:
Coordinate system:
Corrections Projection: UTM Zone 37 South
Scale Factor(SF) = 0.999607 These corrections must Ellipsoid: Clark 1880
be applied to distances Datum: Arc 1960
mesured on field from Remarks: Intervisible with GP.5
this point
Photographs
Sketch
o Establishment Date: JULY 2019
GPS POINT n : GP.06
UTM ZONE 37S - CLARKE 1880 ELLIPSOID Informations
Easting(X) 523935.986 Nature of Point:
IPC pipe with concrete plus Iron bar
Northing(Y) 9255196.791 inserted at the middle
Chainage:
Elevation(Z) 36.765 Location:
Coordinate system:
Corrections Projection: UTM Zone 37 South
Scale Factor(SF) = 0.999607 These corrections must Ellipsoid: Clark 1880
be applied to distances Datum: Arc 1960
mesured on field from Remarks: Intervisible with GP.106
this point
Photographs
Sketch
o Establishment Date: JULY 2019
GPS POINT n : GP.106
UTM ZONE 37S - CLARKE 1880 ELLIPSOID Informations
Easting(X) 523882.719 Nature of Point:
IPC pipe with concrete plus Iron bar
Northing(Y) 9255309.883 inserted at the middle
Chainage:
Elevation(Z) 35.987 Location:
Coordinate system:
Corrections Projection: UTM Zone 37 South
Scale Factor(SF) = 0.999607 These corrections must Ellipsoid: Clark 1880
be applied to distances Datum: Arc 1960
mesured on field from Remarks: Intervisible with GP.6
this point
Photographs
Sketch
o Establishment Date: JULY 2019
GPS POINT n : GP.07
UTM ZONE 37S - CLARKE 1880 ELLIPSOID Informations
Easting(X) 523145.209 Nature of Point:
IPC pipe with concrete plus Iron bar
Northing(Y) 9258160.314 inserted at the middle
Chainage:
Elevation(Z) 34.976 Location:
Coordinate system:
Corrections Projection: UTM Zone 37 South
Scale Factor(SF) = 0.999607 These corrections must Ellipsoid: Clark 1880
be applied to distances Datum: Arc 1960
mesured on field from Remarks: Intervisible with GP.107
this point
Photographs
Sketch
o Establishment Date: JULY 2019
GPS POINT n : GP.107
UTM ZONE 37S - CLARKE 1880 ELLIPSOID Informations
Easting(X) 523060.353 Nature of Point:
IPC pipe with concrete plus Iron bar
Northing(Y) 9258445.337 inserted at the middle
Chainage:
Elevation(Z) 35.447 Location:
Coordinate system:
Corrections Projection: UTM Zone 37 South
Scale Factor(SF) = 0.999607 These corrections must Ellipsoid: Clark 1880
be applied to distances Datum: Arc 1960
mesured on field from Remarks: Intervisible with GP.07
this point
Photographs
Sketch
o Establishment Date: JULY 2019
GPS POINT n : GP.08
UTM ZONE 37S - CLARKE 1880 ELLIPSOID Informations
Easting(X) 522387.118 Nature of Point:
IPC pipe with concrete plus Iron bar
Northing(Y) 9261030.558 inserted at the middle
Chainage:
Elevation(Z) 49.367 Location:
Coordinate system:
Corrections Projection: UTM Zone 37 South
Scale Factor(SF) = 0.999606 These corrections must Ellipsoid: Clark 1880
be applied to distances Datum: Arc 1960
mesured on field from Remarks: Intervisible with GP.108
this point
Photographs
Sketch
o Establishment Date: JULY 2019
GPS POINT n : GP.108
UTM ZONE 37S - CLARKE 1880 ELLIPSOID Informations
Easting(X) 522209.393 Nature of Point:
IPC pipe with concrete plus Iron bar
Northing(Y) 9261273.946 inserted at the middle
Chainage:
Elevation(Z) 62.387 Location:
Coordinate system:
Corrections Projection: UTM Zone 37 South
Scale Factor(SF) = 0.999606 These corrections must Ellipsoid: Clark 1880
be applied to distances Datum: Arc 1960
mesured on field from Remarks: Intervisible with GP.108
this point
Photographs
Sketch
o Establishment Date: JULY 2019
GPS POINT n : GP.09
UTM ZONE 37S - CLARKE 1880 ELLIPSOID Informations
Easting(X) 520435.981 Nature of Point:
IPC pipe with concrete plus Iron bar
Northing(Y) 9263672.176 inserted at the middle
Chainage:
Elevation(Z) 31.362 Location:
Coordinate system:
Corrections Projection: UTM Zone 37 South
Scale Factor(SF) = 0.999605 These corrections must Ellipsoid: Clark 1880
be applied to distances Datum: Arc 1960
mesured on field from Remarks: Intervisible with GP.109
this point
Photographs
Sketch
o Establishment Date: JULY 2019
GPS POINT n : GP.109
UTM ZONE 37S - CLARKE 1880 ELLIPSOID Informations
Easting(X) 520144.894 Nature of Point:
IPC pipe with concrete plus Iron bar
Northing(Y) 9263995.381 inserted at the middle
Chainage:
Elevation(Z) 30.085 Location:
Coordinate system:
Corrections Projection: UTM Zone 37 South
Scale Factor(SF) = 0.999605 These corrections must Ellipsoid: Clark 1880
be applied to distances Datum: Arc 1960
mesured on field from Remarks: Intervisible with GP.09
this point
Photographs
Sketch
o Establishment Date: JULY 2019
GPS POINT n : GP.10
UTM ZONE 37S - CLARKE 1880 ELLIPSOID Informations
Easting(X) 518419.412 Nature of Point:
IPC pipe with concrete plus Iron bar
Northing(Y) 9265878.684 inserted at the middle
Chainage:
Elevation(Z) 20.555 Location:
Coordinate system:
Corrections Projection: UTM Zone 37 South
Scale Factor(SF) = 0.999604 These corrections must Ellipsoid: Clark 1880
be applied to distances Datum: Arc 1960
mesured on field from Remarks: Intervisible with GP.110
this point
Photographs
Sketch
o Establishment Date: JULY 2019
GPS POINT n : GP.110
UTM ZONE 37S - CLARKE 1880 ELLIPSOID Informations
Easting(X) 518260.702 Nature of Point:
IPC pipe with concrete plus Iron bar
Northing(Y) 9266092.306 inserted at the middle
Chainage:
Elevation(Z) 19.882 Location:
Coordinate system:
Corrections Projection: UTM Zone 37 South
Scale Factor(SF) = 0.999604 These corrections must Ellipsoid: Clark 1880
be applied to distances Datum: Arc 1960
mesured on field from Remarks: Intervisible with GP.10
this point
Photographs
Sketch
o Establishment Date: JULY 2019
GPS POINT n : GP.11
UTM ZONE 37S - CLARKE 1880 ELLIPSOID Informations
Easting(X) 532905.700 Nature of Point:
IPC pipe with concrete plus Iron bar
Northing(Y) 9246471.609 inserted at the middle
Chainage:
Elevation(Z) 4.828 Location:
Coordinate system:
Corrections Projection: UTM Zone 37 South
Scale Factor(SF) = 0.999613 These corrections must Ellipsoid: Clark 1880
be applied to distances Datum: Arc 1960
mesured on field from Remarks: Intervisible with GP.111
this point
Photographs
Sketch
o Establishment Date: JULY 2019
GPS POINT n : GP.111
UTM ZONE 37S - CLARKE 1880 ELLIPSOID Informations
Easting(X) 532960.510 Nature of Point:
IPC pipe with concrete plus Iron bar
Northing(Y) 9246566.903 inserted at the middle
Chainage:
Elevation(Z) 5.431 Location:
Coordinate system:
Corrections Projection: UTM Zone 37 South
Scale Factor(SF) = 0.999613 These corrections must Ellipsoid: Clark 1880
be applied to distances Datum: Arc 1960
mesured on field from Remarks: Intervisible with GP.11
this point
Photographs
Sketch
GP.1 529861.007 9245001.056 18.95 0.99961 GP.2 529990.673 9245070.01 19.09 0.99961
GP.2 529990.673 9245070.01 19.09 0.99961 GP.3 530192.996 9245193.212 15.76 0.99961
-129.666 -68.954 146.86 -202.323 -123.202 236.883
GP.3 530192.996 9245193.212 15.76 0.99961
GP.4 530577.534 9245423.333 13.807 0.99961 GP.3 530192.996 9245193.212 15.76 0.99961
GP.5 530764.516 9245497.052 14.11 0.99961 DRG26G 530411.484 9245290.928 14.114 0.99961
GP.6 530888.478 9245572.703 15.124 0.99961 -218.488 -97.716 239.344
GP.7 530985.314 9245640.319 14.709 0.99961 DRG26G 530411.484 9245290.928 14.114 0.99961
GP.8 530323.355 9245392.011 13.969 0.99961 GP.8 530323.355 9245392.011 13.969 0.99961
GP.9 530198.3 9245579.363 15.685 0.99961 88.129 -101.083 134.106
GP.10 529913.244 9245451.538 21.5 0.99961 GP.8 530323.355 9245392.011 13.969 0.99961
GP.11 530041.579 9245432.795 15.542 0.99961 GP.9 530198.3 9245579.363 15.685 0.99961
DRG.26E 530808.756 9245077.824 13.805 0.99961 125.055 -187.352 225.254
DRG26F 530596.734 9245175.291 15.893 0.99961 GP.10 529913.244 9245451.538 21.5 0.99961
DRG26G 530411.484 9245290.928 14.114 0.99961 GP.11 530041.579 9245432.795 15.542 0.99961
-128.335 18.743 129.696
GP.6 530888.478 9245572.703 15.124 0.99961
GP.7 530985.314 9245640.319 14.709 0.99961
-96.836 -67.616 118.106
GP.6 530888.478 9245572.703 15.124 0.99961
GP.5 530764.516 9245497.052 14.11 0.99961
123.962 75.651 145.223