CM-PM-PMP-S#01 (130823)
CM-PM-PMP-S#01 (130823)
CM-PM-PMP-S#01 (130823)
Deputy PM
Assistance PM
Section Manager
1 2 3 5 6 7
4
Technical Manager Construction Manager QA/QC Manager QS Manager HSE Manager Procured Manager HR Manager
Site Site Site Head Office Site/Head Office Head Office Head Office
Surveyors Structural engineers QA/QC engineers Site QS engineers HSE officers/engineers Site purchasers Site administrator
Architectures Finishing engineers Contract engineers Site stoke controller Site securities
Technical engineers Forman
Structural designer
@Copyright by: Professional Engineering (PMP) Prepared by: Prof. Voek Pitou
MANAGER SKILL NEEDED
Construction Technology
Pre-stressed concrete
Budget Plan/Tracking
Labor Plan/Tracking
Strength of material
N
Structural analysis
Procurement Plan
Problem solving
Task delegation
Communication
Steel structure
Responsibility
T
ARC Drawing
STR Drawing
Cost analysis
Risk analysis
Presentation
SI
Leadership
Team work
Negotation
Motivation
Honestly
PO
Contract
Patient
1 2 3 1 2 3 4 5 6 7 8 9 10 11 12 13 13 1 2 3 4 5 6 7 8 9 10 1 2 3 4 5 6 7 8 9 10 11
HARD-SKILL SOFT-SKILL
Project Manager 100% 100% 70% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 80% 80% 80% 80% 80% 80% 80% 80% 80% 80% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
Construction Manager 100% 100% 70% 50% 70% 100% 100% 100% 100% 100% 100% 60% 60% 100% 70% 60% 70% 70% 70% 70% 70% 70% 70% 70% 70% 70% 100% 100% 70% 100% 100% 100% 100% 100% 60% 80% 100%
Technical Manager 100% 100% 100% 80% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 80% 100% 80% 100% 70% 70% 100% 100% 100% 80% 100%
QS Manager 100% 100% 100% 100% 100% 80% 80% 100% 100% 70% 70% 80% 100% 70% 100% 70% 70% 100% 80% 60% 80% 100%
QA/QC Manager 100% 100% 100% 100% 70% 70% 70% 70% 70% 70% 70% 70% 70% 70% 70% 70% 100% 100% 100% 100% 50% 70% 100% 100% 70% 100%
HSE Manager 100% 90% 60% 100% 70% 70% 100% 70% 100%
Procurement Manager 80% 50% 100% 100% 80% 80% 70% 80% 100% 90% 70% 100% 100% 50% 100%
@Copyright by: Professional Engineering (PMP) Prepared by: Prof. Voek Pitou
PROJECT PHASES DIAGRAM
1 2 3 4
BIDDING/PLANNING EXECUTIVE MONITORING CLOSE-OUT
Project Manager 30% Project Manager 100% Project Manager 100% Project Manager 100%
QS Manager 100% Construction Manager 100% Construction Manager 100% Construction Manager 100%
QA/QC Manager 30% HSE Manager 50% HSE Manager 100% HSE Manager 60%
HSE Manager 30% Technical Manager 50% Technical Manager 100% Technical Manager 50%
Technical Manager 40% Procurement Manager 50% Procurement Manager 100% QA/QC Manager 100%
QS Manager 50%
2-Weeks Master-Schedule
1 3
BIDDING/PLANNING EXECUTIVE MONITORING CLOSE-OUT
2 4
1 month Master-Schedule
@Copyright by: Professional Engineering (PMP) Prepared by: Prof. Voek Pitou
BIDDING STAGE AND MANAGER JD
STAGE TEAM INVOLVED TASK DESCRIPTIONS INVOLVED PERSON NOTIFICATION
2 Site visit
2 Inspection Flow
@Copyright by: Professional Engineering (PMP) Prepared by: Prof. Voek Pitou
BIDDING STAGE AND MANAGER JD
2 HSE regulation
@Copyright by: Professional Engineering (PMP) Prepared by: Prof. Voek Pitou
EXECUTIVE STAGE AND MANAGER JD
6 Plan assigments
5 HSE MANAGER 1 Prepare for safety protection both internal & exteranl site
DEPUTY PROJECT MANAGER 4 Expenses tracking (Material & Labor) CONSTRUCTION MANAGER
@Copyright by: Professional Engineering (PMP) Prepared by: Prof. Voek Pitou
MONITORING STAGE AND MANAGER JD
3 TECHNICAL MANAGER 1 Prepare shop drawing & method statement for submission to consultant
SURVEYORS 4 Doing indcution course for necessary techniques and method during construction
SITE ARCHITECTURES 7 Check revised drawing gotten from consultant to control VO work
TECHICAL ENGINEERS
6 Prepare for defect report and follow up with site team for rectifying work
7 Lead & conduction necessary testing work and submit report to client
5 HSE MANAGER 1 Follow up & control safety work on site daily under construction
@Copyright by: Professional Engineering (PMP) Prepared by: Prof. Voek Pitou
MONITORING STAGE AND MANAGER JD
HSE ENGINEERS 4 Prepare and submit weekly safety report to project manager
3 Prepare Variation Order BoQ (if any) and submit to client to approve
7 PROCURE. MANAGER 1 Tracking and follow up with material purchase order with suppliers
3 Control PR, PO, and DO with construction team, stoke controller & suppliers
STOKE CONTROLLER
@Copyright by: Professional Engineering (PMP) Prepared by: Prof. Voek Pitou