MAINTENANCE MANUAL
1.0 GENERAL
1.1 Type and Designation 03
1.2 Main Application and Scope 03
1.3 Service Condition 03
1.4 Technical Ratings 03
8.0 CONCLUSION 42
It has been designed for a system voltage of 145kV. The product introduces self-blast
interrupter. Each pole has one breaking chamber and all three poles are installed on one
frame, this along three-pole mechanical inter-operation by a single spring operating
mechanism to achieve local and remote electrical control or local manual control.
The breaker consists of three single poles, which are mounted on the same frame, for 3
phase mechanical interoperation by one spring operating mechanism.
The interrupter is in the uppermost of the product while the support porcelain and frame
(driving system and SF6 gas pipe are installed inside) are installed on the circuit breaker
support structure. The spring operating mechanism is installed on the front of the frame.
The general layout and installation foundation of the circuit breaker is shown in Figure 1. For
detail dimension and parts descriptions, please refer to approved general arrangement
drawings.
1900 1900
INTERRUPTER
CHAMBER
1280
INSULATOR
TERMINAL
PAD
SUPPORT
INSULATOR
5725
(190 MAX)
1400
2050
2200
2-7
2-14
2-2
2-4
2-8
2-3
2-13
2-5
2-9
2-12
2-6 2-10
2-11
2-15 2-16
2-17
3-3
3-1
3-4
3-5
3-6
3-7
4-1 4-10
4-2 4-11
4-12
4-3 4-13
4-4 4-14
4-15
4-5 4-16
4-6
4-17
4-7
4-8
4-9 4-18
4-19
Insulation rod (4-9) is used to connect the operating rod (4-18) and the piston rod (4-16). Its
other main function includes the insulation of live internal parts from earth. The SF6 gas
within the lower porcelain is common with that inside the interrupter porcelain.
2.1.3 Absorbent
Absorbent (4-1) is placed inside the interrupter cover and is used for keeping the SF6 gas
dry. It also absorbs deteriorate gas resulting from arc decomposition. The absorbent must be
replaced when the interrupter cover is removed for service, maintenance, etc.
It is mounted at the bottom of the support porcelain to achieve a dynamic (movable) seal by
compressing sealing discs with spring. The dismantling of the linear hermetically sealing
device at site is generally NOT RECOMMENDED. This is to safeguard the proper
functioning of the device at all times. Extra care and caution must be practiced during
assembly and inspection.
ARC
FIXED ARC CONTACT
MOVING ARC
NOZZLE
CONTACT
6-2
6-3
6-4
The driving mechanism of the breaker connects the individual interrupter poles with the
operating mechanism, which in turn transfers the operating force to the moving contact
system of the breaker
The closing spring is charged by a ratchet and pawl arrangement, which is driven by an
electric motor, while the opening spring is charged by the closing action of the mechanism;
through a set of bevel gears. A system of latches is used to maintain the circuit breaker in its
intended position, i.e. open or closed position.
The moving contacts of the puffer interrupters in each phase column are operated via a
system of inter-phase drive links by a mechanism which utilizes separate springs for opening
and closing operations.
The construction and the working principle of the spring operating mechanism are illustrated
in Figure 7.
CAM (i)
CIRCUIT BREAKER (a) OPENING SPRING (b)
LEVER (l) SHOCK ABSORBER (v)
RATCHET SHAFT (s) CLOSING SPRING (c)
A
PAWL (j) CAM SHAFT (r)
MAIN DRIVE SHAFT (t) B RATCHET WHEEL (d)
PIN (q) CLOSING HOLDING LATCH (e)
LEVER (k) ANTI-CLOSING PIN (w)
PIN (o) CLOSING TRIGGER (f)
TRIP HOLDING LATCHED (m) CLOSING COIL (g)
ROLLET (u) ANTI-PIMPING LEVER (p)
TRIP TRIGGER (n) ANTI-TRIPPING PIN (x)
Figure 7A
CLOSED POSITION TRIP COIL (h)
(CLOSING SPRING CHARGED)
Figure 7B Figure 7C
OPEN POSITION CLOSED POSITION
(CLOSING SPRING CHARGED) (CLOSING SPRING DISHARGED)
2) Trip holding latch (m) is free to turn clockwise and disengages from pin (o) which is
secured to lever (k).
3) The torque exerted by opening spring (b) upon levers (l) and (k) is now unopposed and
they rotate anti-clockwise.
4) Circuit breaker (a) is OPENED through a drive link connected to arm ‘B’ of lever (l). The
mechanism configuration of OPENING operation is shown in Figure 7B.
2) Closing holding latch (e) is now free to turn anti-clockwise and disengages from pin (q),
which is secured to ratchet wheel.
3) The torque exerted by closing spring (c) is now unrestrained and cam (i) is driven anti-
clockwise against roller (u) thus give impact of clockwise rotation to levers (k) and (l)
4) Opening spring (b) is charged by the motion of arm ‘A’ of lever (l) whilst at the same time
the interrupter is CLOSED by the motion of arm ‘B’ of lever (l).
5) Pin (o) engages automatically with trip holding latch (m), which is locked by trip trigger
(n) so providing a restraint against charged opening spring (b).
The mechanism configuration on CLOSING operation is shown in Figure 7C but before the
re-charging of the closing spring begins.
WARNING
a) This pin should be used only to prevent unintentional and unsafe operations during
maintenance or inspection of the circuit breaker. The anti tripping/closing pin is removed
prior to breaker put into service.
b) Do not use the above torque value for covers with flexible gaskets, but tighten to
compress gasket thickness by 1/3 only; this ensures weather tightness.
a) The appropriate electrical supplies must be available for the opening coils, closing coil
and closing spring charging motor.
b) The local/Off/Remote selector switch located in the mechanism housing must be set to
the correct position.
This density meter is located inside the mechanism housing, and has two sets of contacts.
One set of contacts provides an alarm indication when the gas pressure falls to a level of 5.5
bar.
The other set prevents operation if gas pressure falls to a level of 5.0 bar. However, we are
pleased to inform that the circuit breaker is able to interrupt short circuit current at 5.0 bar
and were proven during the type test.
E VALVE
The temperature-compensating feature of the switch avoids alarms and lockouts due to
normal pressure variations associated with ambient temperature changes. The pressure
gauge has a color-coded face for ease of reading from a distance
The SF6 gas system consists of SF6 gas density meter, inlet valve E and valves A, B, C, D
and SF6 gas piping. The SF6 gas system is illustrated in Figure 9.
Valve E is in closed position under normal condition. When SF6 gas density drops, an alarm
is activated. SF6 gas refilled can be carried out through the supply inlet even when the circuit
breaker is in operation (energized). Valve D and E physically located inside the mechanism
box assembly.
PREPARATION OF
FOUNDATION INSTALLATION
SINGLE PHASE
INTERRUPTER
TERMINAL ASSEMBLY
SECONDARY WIRING
STROKE MEASUREMENT
APPLY WATERPROOF
COMMISSIONING
3.2.1 Inspection
When the switchgear is delivered to the site, the customer must inspect all the received
components thoroughly according to the packing list. If any abnormalities are observed,
kindly contact Tenaga Switchgear Sdn. Bhd. (Business Development Dept.) at the soonest
possible.
b) Avoid vigorous shock (stress) on switchgear components during loading and unloading.
d) When lifting porcelain bushing from the crate, extra caution must be practiced, as the
porcelain is susceptible to damage when handle carelessly.
e) Inspect all components to ensure that they are free from damage.
3.2.3 Storing
If the switchgear does not intend for immediate installation, it must be kept in an elevated,
dry; clean area and strictly shielded from water and moisture.
It is advisable to leave the heater in the operating mechanism Switched On and the
thermostat set to 5oC above the ambient temperature (in Malaysia, set the thermostat at
±35oC, other places outside Malaysia, check the local ambient temperature) at all time.
e) Circuit breaker is evacuated and filled with 0.5bar of SF6 gas before delivery. At site, if
inspection reveals nothing peculiar, SF6 gas can be filled instantly.
f) Before filling of SF6 gas, the bottle and the SF6 gas filling piping and associated
accessories must be completely dry and clean from dust and any foreign particles,
before any filling take place.
g) As the circuit breaker is only filled with 0.5bar of SF6 gas when it leaves the factory, care
must be taken not to open the SF6 gas valve at site.
h) After completing installation, strictly avoid fast closing and opening operation before SF6
gas is filled at rated pressure. The manual operating device may be used to perform the
slow opening and closing operations.
OPERATION & MAINTENANCE MANUAL LW9-145 GCB REV. 01 - JAN 2009
Page 18 of 42
a) Before operating the circuit breaker manually, the closing and opening preventive pin
must be removed, and electric supply must be turned off.
b) Once the circuit breaker is delivered to site, ensure that appropriate care is taken when
handling the components. This will guarantee that the circuit breaker will perform as
intended without any problem.
Slow closing/opening
operation
Ratchet spanner
2
Slow closing/opening
3 Bearing
operation
d) Repeat the above process for other poles. Dust free tissue
paper
OPERATION & MAINTENANCE MANUAL LW9-145 GCB REV. 01 - JAN 2009
Page 21 of 42
a) Please note that each bushing engraved
with phase identification followed by a
serial number at the bottom part of each
support bushing as follow, A XXXXXX, B
XXXXXX and C XXXXXX, e.g. A 123456.
TO CRANE
PROTECTION
BRACKET
Figure A.
TO CRANE
Figure B.
Figure C.
Spanner
Alcohol
SF6 gas pipe
connection to
5 Dust free tissue
circuit breaker
paper
pole
Sealing gum
Figure D.
b) Fix lifting rod (10-8) on lever 11 through bottom hole of housing mechanism and put
sleeve plate (10-4) around nut (10-9).
c) Rotate nut (10-9) clockwise to open the circuit breaker or rotate anti-clockwise to close
the circuit breaker.
d) For manual opening operation, press the tripping magnet to release the interlock pin and
closing control latch.
b) Insert sleeve rod (10-1) and sleeve spanner (10-3) into the hexagon hole of the ratchet
wheel.
10-1
10-11
CHARGING 10-2
10-10 10-3
10-9
10-8 10-12
10-7
10-6
CLOSE
10-5 OPEN
10-4
10-1 Rod
10-2 Ratchet shaft
10-3 Spanner
10-4 Sleeve spanner
10-5 Bushing
10-6 Cover plate
10-7 Mechanism box
10-8 Lifting rod
10-9 Nut
10-10 Bearing
10-11 Bending lever
10-12 Closing spring charge
Figure 10. Manual operating device assembly
b) Connect test lamp (or buzzer) between the top and bottom terminal of the interrupter.
Manually operate to open the circuit breaker and measure the distance of A1 and B1.
c) Manually close the circuit breaker, when the test lamp just begin to light (or buzzer just
begin to buzz), this is the position at instant of contact touching, measure the distance of
A2.
d) Continue close operation until the manual operating mechanism become loose. This is
the close position, measure the distance of A3 and B2.
e) Carry out calculation according to Table 10 and compare it with the technical
requirement whether it is satisfactory.
f) Circuit breaker is at open position, closing spring in charging condition, measure gap G3
between roller and charging position cam.
Travel of piston
Operating
of mech. B2 - B1 100 mm Straight edge
mechanism
A3
A) OPEN POSITION B) JUST TO CLOSE POSITION C) CLOSE POSITION
B1 B2
G
B
=
1.
4±
0.
3
The checking must ensure that all requirements (as per Table 3) are satisfied. When
measuring the tripping magnet clearance, product must be in closed position.
Insert tripping preventive pin (12-6) into operating mechanism for measurement. When
measuring the closing magnet clearance, product must be in open position. Insert closing
preventive pin into operating mechanism for measurement.
Adjustment of dimensions G: Loosen nut (12-1), turn plunger bar to move the knocking
position of the plunger.
Adjustment of dimension D & E: Loosen nut (13-2), turn plunger bar to move the knocking
position of the plunger.
Note: It is to be noticed that the magnet clearances are interrelated. When any adjustment
is made, check to confirm that all dimensions complies with the requirement, before
tightening the screws into place.
NUT (12-1)
BOLT (12-2)
OPENING COIL (12-5) NUT (12-3)
PLUNGER (12-4)
F = 2.8~3.2mm
STROKE
ANTI OPEN PIN (12-6) PLUNGER (12-8)
G = 0.8~1.2mm
C = 5.0~5.5mm
SUPPORT (13-7)
STROKE
COIL (13-6)
LATCH (13-9)
E = 1.0~2.0
Evacuation at site is not necessary. However, remember to first inspect the SF6 gas
pressure gauge before filling the gas to the rated operating pressure.
The gauge reading should be equivalent to the factory-filled pressure. If not, the circuit
breaker has to be evacuated until it reaches at least -1.0 bar. Only then the SF6 gas be filled.
Refer figure 14 for evacuation and filling of SF6 gas.
2. Open the valve on the product (valve A to E). After vacuum reaches -1.0 bar, continue
evacuation for another 30 minutes.
3. Before stopping the vacuum pump, close valve “E” (14-1) first, followed by all other
valves on the equipment. This is to avoid the loss of vacuum in the equipment.
2. Open valve A, then at the same time open valve D and valve E (Refer to Fig 6). Use
small amount of SF6 gas inside the interrupters to blow out the air in the pipe, then close
valve D and valve E.
4. When connecting gas pipe adapter (14-2) and valve E, first leave a gap. Open the bottle
valve and the regulator valve at the SF6 bottle slowly.
5. Use small amount of SF6 gas from the bottle to blow out the air in the pipe, then close
regulator valve. Quickly tighten adapter (14-2).
7. Adjust regulator valve and valve of SF6 bottle, so as to maintain the outlet pressure of the
regulator valve at 2.0 bar - 5.0 bar.
8. Observe the SF6 gas density meter inside the circuit breaker’s operating mechanism box.
When the reading reaches the specified pressure in Table 5, (with a tolerance of +0.3
bar), close valve E first; then close the bottle valve and regulator valve.
9. Remove gas filling hose adapter (14-2) and fix cover plate of valve (14-9). The filling of
gas has now been completed.
14-4
Use the SF6 gas leakage detector to inspect all sealing surfaces of the interrupter and the
SF6 gas piping. If there is no leakage, the product is considered to be in good order.
If any leakage is found, wrap with plastic film and leave it for 24 hours. Check the density of
the SF6 gas inside the plastic film as shown in Fig. 16. If the SF6 gas density is
unacceptable, the sealing is deemed to be damaged. As such, the necessary corrective
action needs to be performed.
3.11 Testing
Precaution
When SF6 gas pressure is lower than 4.0 bar, NO OPERATION IS ALLOWED.
The SF6 gas pressure in the piping will slowly increase. Detect the pressures at which the
SF6 gas filling and the SF6 gas interlock reset functions operate. The test results must
comply with the requirement specified in Table 4.
b) Check to confirm that the shaft pin and the retaining ring are correctly installed.
c) SF6 gas must be at rated pressure and all valves should be in correct positions.
d) Leave local-remote switch in the required position. Confirm that the Auto-Manual switch
is positioned at the Auto contact.
f) Check if that all cover plates have been tightened. Remember to remove any foreign
object on the mechanism box and the frame.
g) Confirm that the trip and close preventive pins have been released.
This must only be done after the final inspection. For all bolts and nuts of the positioning
cover plate, also apply waterproof gum on them. Upon completion of the above work, the
product is ready for operation.
Since the SF6 gas is hermetically sealed, the losses are negligible. As such, the proposed
inspection and maintenance schedules are tailored to focus on the operating mechanism
and other moving parts and assemblies.
Overhaul inspection Every 12 years shown in table Long out of operation, overhaul
12 each part.
4.2 Safety
WARNING
Before attempting examination and/or overhaul of any item of equipment, it is essential that
the concerned maintenance staff and the operational staff shall be made aware of and
complies with the following:
a) The station safety regulation or its equivalent legislative safety documentation relevant to
the site, the general plant area and the particular equipment involved.
b) The Station Safety Regulations, or its equivalent, relating to the handling of SF6 gas and
SF6 gas insulated equipment.
c) Any station or board ‘Code of Practice’ relating to the handling of components which
have been subjected to arced SF6 gas.
e) The necessary authorization to perform service must be obtained, which should be in the
form of a ‘permit to work’ license, or its equivalent, in accordance with the station
operating procedures.
Warning
Prior to maintenance of the circuit breaker, ensure that the following conditions have been
met. It is also recommended that, whenever possible, the energy stores in both the opening
spring and closing spring are released.
4) CLOSE the circuit breaker. This operation discharges the energy stored in the closing
spring, but causes the opening spring to become charged.
5) OPEN the circuit breaker. This operation discharges the energy stored in the opening
spring.
6) Switch off the MCB of the closing and tripping control circuits.
7) Lock the LOCAL/OFF/REMOTE selector switch located inside the mechanism housing in
the OFF position.
8) If access is required to component within the phase columns, then first evacuate the SF6
gas.
4.4 Note
Certain aspects of maintenance may require the circuit breaker to remain in the CLOSED
position, with both the closing spring and opening spring in the charged condition. In these
circumstances, the recommended procedure prior to commencing maintenance is as
follows:-
1) Lock the LOCAL/OFF/REMOTE selector switch in the LOCAL position and padlocked.
2) Insert the anti-closing and anti-tripping pins into position inside the operating mechanism.
3) Switch off the MCBs of the closing and tripping control circuits and also the closing
spring charging motor circuit.
APPLY
SEALING 17-2 18
GUM
17-3 18
17-4
17-8
APPLY
SEALING
GUM
17-11
TOP
TERMINAL
17-9 FLANGE
(DO NOT DAMAGE
(D) PORCELAIN) (E)
17-12 17-14
17-13
17-15
Do not remove the two positioning pins (17-1) because this is for position guiding after
completed the overhaul of circuit breaker.
Carefully remove the fix arc contact seat. Inspect the fix arc contact (17-11), if there is any
damage. If necessary to replace, use spanner (17-10) as shown in Figure 16 to remove it.
Remove and inspect the moving arc contact (17-15) and replace it with new one if required.
Use spanner (17-14) as shown in figure 17 to loosen or to tighten the moving arc contact.
Use alcohol to clean “O” ring groove. The sealing surface must not have any scratches and
must be free from dirt to avoid leakage. Strictly follow the application of sealant gum as
describe in Table 15.
When assembly of fix arc contact seat (17-4) and interrupter bushing (17-3), use positioning
pin (17-5) for positioning. Use sandpaper no. 400 or greater to polish the terminal pad (17-6).
5 Attached O” ring.
"O" RING
2. Manual closing is 2.1 Incorrect adjustment Check and adjust gaps ‘D’, and
not possible. of, or mechanical fault ‘E’ and stroke ‘C’ before replace
in closing coil moving closing coil in faulty. (Refer
elements. Table 2 and Figure 12)
5. Gas pressure is 5.1 Gas leakage caused Carry out gas leakage test to
too low. by incorrect sealing of identify source of leakage, and
components. take remedial action. Increase
gas pressure to rated value.
8.0 CONCLUSION
The data furnished in this manual are for the guidance of qualified installation and operating
personnel. In case of doubts in the meaning or interpretation of the information given, kindly
contact Sales And Marketing Department, Tenaga Switchgear Sdn. Bhd.
The circuit breaker would provide satisfactory service upon adhering to the
recommendations provided herein. Due to continuous improvement, the equipment may
differ in details from that described in this manual.