ARCTIC LNG 2 LLC

EXCEPTION REQUEST RFC ✘ AOC


Client Name : ARCTIC LNG 2 LLC Project Name : ARCTIC LNG 2

Contractor : CASCADE ENGINEERING Project No.: 079332

EXCEPTION No: EXP-GBS2-0029 Description:


Module No.: 2-TMP-005
System No.: 270 LNG train 2 - Service and Instrument Air System
Sub-System No.: 270-U-02 Air Compressor Package B
Type of Exception (Select applicable)
Tags ✘ QCF form ✘ Punch List NCR Document
If Other provide Details:
Disciplines included under this Exception (Select)
Civil and
Structure
✘ Mechanical Piping ✘ Electrical Instrumentation Telecoms
HVAC Safety Equip Painting Building ✘ Other
Equipment / Tagged Items to be covered under the Exception Request. Ensuring to address all aspects
Details of Exception Include including Pre-Commissioning / Commissioning and Start-up impacts that this exception may have.

Tag Tag Description QCF Type No: Reason for Exception


Work in progress as per JC 2TMP005-22-270-
2-TMP-005A-270-
Piping Insulation 2200-CL02A 1431301 0294
WA-00018-01_W
Forecast Completion 29-Feb-2024
Work in progress as per JC 2TMP005-22-270-
2-TMP-005B-270-
Piping Insulation 2200-CL02A 1432773 0294
WA-00018-01_W
Forecast Completion 29-Feb-2024
Work in progress as per JC 2TMP005-22-270-
2-TMP-005B-270-
Piping Insulation 2200-CL02B 1438575 0294
WA-00018-01_W
Forecast Completion 29-Feb-2024
Work in progress as per JC 2TMP005-22-270-
2-TMP-005A-270-
Piping Insulation 2200-CL02B 1440184 0294
WA-00018-01_W
Forecast Completion 29-Feb-2024
Work in progress as per JC 2TMP005-22-270-
2-TMP-005B-270-
Piping Insulation 2200-CL02P 1442633 0294
WA-00018-01_W
Forecast Completion 29-Feb-2024
Work in progress as per JC 2TMP005-22-270-
2-TMP-005A-270-
Piping Insulation 2200-CL02P 1446059 0294
WA-00018-01_W
Forecast Completion 29-Feb-2024
After completion of insulation activities.
EHT2-12912-A HEATING CABLE (Secondary) 1650-EFR01I 2745986
Forecast Completion 02-Mar-2024
1650- After completion of insulation activities.
EHT2-12912-A HEATING CABLE (Secondary) 2745987
EFR10H Forecast Completion 02-Mar-2024
After completion of insulation activities.
EHT2-12912-B HEATING CABLE (Secondary) 1650-EFR01I 2745989
Forecast Completion 02-Mar-2024

1650- After completion of insulation activities.


EHT2-12912-B HEATING CABLE (Secondary) 2745990
EFR10H Forecast Completion 02-Mar-2024

After completion of insulation activities.


EHT2-60202-A HEATING CABLE - INSTRUMENT (Secondary) 1650-EFR01I 2751872
Forecast Completion 02-Mar-2024

1650- After completion of insulation activities.


EHT2-60202-A HEATING CABLE - INSTRUMENT (Secondary) 2751873
EFR10H Forecast Completion 02-Mar-2024

270-K-120 AIR COMPRESSOR CR10 3259399 After completion of PCC activities

Detail Mitigation Measures (Provide Details of Mitigation measures that Contractor will implement)

Exception Originator Detail

1
EXP-GBS2-0001
ARCTIC LNG 2 LLC

EXCEPTION REQUEST RFC ✘ AOC


Client Name : ARCTIC LNG 2 LLC Project Name : ARCTIC LNG 2

Contractor : CASCADE ENGINEERING Project No.: 079332

Name: Alister Mackinnon Signature:

Position: Completion Manager Date: 11.21.2023


CTR Approval Signatories
Construction Manager Commissioning Manager
Name: Michel Swaidan

Signature:

Date:
Company Approval Signatories
Company Representative
Name:

Signature:

Date:

Approval Required Required for every Exception

2
EXP-GBS2-0001

You might also like