Water Cooled Screw Chillers - McQuay
Water Cooled Screw Chillers - McQuay
Water Cooled Screw Chillers - McQuay
!" # $ % &
% '() * " +' ,
Application
Units must be initially started at the job site by a factory trained McQuay service technician. Failure to follow
this startup procedure can affect the equipment warranty.
The standard limited warranty on this equipment covers parts that prove defective in material or
workmanship. Warranty does not cover materials that are subject to natural consumption.
Cooling towers used with McQuay PFS “B” chillers have to be selected according to 24°C ÷ 32°C as
maximum condenser inlet water temperature values.
Installation
Storage
If the chillers have to be stored prior to installation, the following warnings have to be observed.
Store the chillers inside, at ambient temperatures lower than 50°C.
Keep the chillers far from heat sources.
Do not expose the chillers to direct sun light.
Vibration pads
The shipped-loose neoprene vibration pads should be located under the corners of the unit (unless the job
specifications state otherwise). They are installed to be flush with the sides and outside edge of the feet. For
vibration-dampings installation, refer to dimensional drawing of the unit. If no screws are used for fixing the
unit to the floor, install anti-slip rubber between the floor and the vibration-dampings.
Before to deliver the units, refrigerant and oil valves are closed, to insulate the two fluids during the
transport. The valves have to be kept closed till start-up, that has to be performed by McQuay
technicians.
Water Piping
The piping must be supported to eliminate weight and strain on the fittings and connections. Piping must
also be adequately insulated. A cleanable water strainer must be installed in both water inlet lines.
Sufficient shutoff valves must be installed to permit draining the water from the evaporator or condenser
without draining the complete system.
CAUTION
To avoid tubes damages on heat exchangers tubes, cleanable water strainer must be installed in
both water inlet lines. Filter mesh size has to be 1mm.
Tee
Electrical connections must be made to 5 and 23 terminals of M1 terminal board for the evaporator, to 5 and
8 terminals for the condenser. Flow switch contact quality must be suitable for 24 VAC, low current (16ma).
Flow switch wire must be in separate conduit from any high voltage conductors (115 VAC and higher).
CAUTION
Freeze notice: neither the evaporator nor the condenser is self-draining;
both must be blown out to help avoid damage from freezing.
The piping should also include thermometers at the inlet and outlet connections and air vents at the high
points.
The water heads can be interchanged (end for end) so that the water connections can be made at either end
of the unit. If this is done, new head gaskets must be used and control sensors relocated.
In cases where the water pump noise can be objectionable, vibration isolation sections are recommended at
both the inlet and outlet of the pump. In most cases, it will not be necessary to provide vibration eliminator
sections in the condenser inlet and outlet water lines. But they can be required where noise and vibration are
critical.
Cooling tower
If cooling tower is used, a balancing valve is recommended. Some form of temperature control is also
required if cooling tower water should be very cold. Unit microprocessor includes the control for cooling tower
fans. Therefore it is suggested to make the relevant wiring connections.
Water treatment
Before every start-up, clean and flush the cooling water circuit. Make sure tower blowdown or bleed-off is
operating. It should be recognized that atmospheric air contains many contaminants that increase the need
for proper water treatment. The use of untreated water can result in corrosion, erosion, sliming, scaling or
algae formation. McQuay Italia S.p.A. assumes no responsibility for the results of untreated or improperly
treated water.
Operating Range
60
50
Condenser leaving temperature - °C
40
30
20
10
0
-10 -5 0 5 10 15 20
Evaporator leaving tem perature - °C
Note: the use of glycol is necessary for evaporator leaving water temperature below +3°C.
Flow rates below the minimum values shown in the evaporator and condenser pressure drop curves, may
cause freeze-up problems, scaling and poor control. Flow rates above the maximum values shown in the
evaporator and condenser pressure drop curves will result in unacceptable pressure drops, excessive
erosion and tube vibrations potential cause of tubes failure.
Safety valves
Each system will be equipped with a safety valve on condenser and evaporator in order to release the
refrigerant charge in case of faulty operation. Most codes require that relief valves be vented to the outside,
and this is a desirable practice for all installations.
CAUTION
To prevent injuries for R134a inhalation, avoid releasing the refrigerant in the atmosphere or inside.
The relief valves have to be vented to the outside, according to the rules in force in the country of the
installation. The installer is responsible for sizing the bleeder pipes and connecting the relief valves
to them.
Electrical connections
Wire size must be in accordance with the nameplate data and the rules in force.
McQuay Italia S.p.A. assumes no responsibility for the results of improperly electrical connections.
CAUTION
Connections to terminals must be made with copper lugs and copper wire.
Qualified and licensed electricians must perform wiring. Shock hazard exists.
Power wiring to compressors must be in proper phase sequence. For this reason, phase monitor is supplied
as standard.
Voltage unbalance
Extreme voltage unbalance in a three-phase system is the cause of increase in motor temperature. The
voltage unbalance between phases must not exceed 2%, according to the following calculation.
unbalance % = (Vx-Vm) x 100
Vm
Vx= phase with the maximum unbalance
Vm= avarage voltage
Control circuit
McQuay PFS unit’s circuit control is supplied with 110 Vac power.
Move the ON/OFF switch controller (Q0) to the “off” position every time unit operation is not required.
Inside the controller are installed connecting terminals for the water flow lock. See the wiring diagram to
operate the correct connection on the field. The purpose of the water flow interlocked switch is avoiding the
compressor operation till the evaporator and condenser pumps are able to grant the correct water flow. The
flow switch or the differential pressure switch is an accessory supplied by McQuay Italia upon request
however necessary to be installed on the unit.
It is recommended to let the microprocessor controlling the pumps for a better plant system.
In case of external control on the pumps use the following procedure.
Evaporator water pump:
• start-up the pump 2 minutes before turn on the unit;
• switch off the pump 5 minutes after turn off the unit.
Condenser water pump:
• start the pump 30 seconds before turn on the unit;
• switch on the pump 1 minute after the last compressor is off.
When the unit is not operating the condenser pump must be always off.
Operation
Operator responsibilities
It is important that the operator become familiar with the equipment and the system before attempting to
operate the chiller. In addition to reading this manual, the operator should study the operation manual for the
controller and the wiring diagram furnished with the unit before starting, operating, or shutting it down.
During the initial startup of the chiller the McQuay technician will be available to answer any questions and
instruct in the proper operating procedures.
It is recommended that the operator maintain an operating log for each individual chiller unit. In addition, a
separate maintenance log should be kept of the periodic maintenance and servicing activities.
This McQuay chiller represents a substantial investment and deserves the attention and care normally given
to keep this equipment in good working order. If the operator encounters abnormal or unusual operating
conditions, it is recommended that a McQuay service technician be consulted.
P Water cooled
F Flooded
S Screw compressor
“B” Release
1 N° of compressors
2
Evaporator
The evaporator is flooded shell-and-tube with the refrigerant out the tubes and the water inside them.
Normally no maintenance and service operation is required. When it is necessary to replace a tube it is easy
to remove the old one.
Condenser
The condenser is shell-and-tube with the refrigerant out the tubes and the water inside them. The condenser
tubes are externally finned and expanded on the tube plate. All units have an integrated subcooling in the
condenser also equipped with a safety valve. If required it is possible to remove and replace the tubes.
Expansion valve
The expansion valve is directly controlled by a refrigerant level sensor placed on the condenser. The system
controls the refrigerant liquid level, to grant an adequate operation of the expansion valve, completely
flooding the integrated sub-cooling section of the shell-and-tube condenser.
A solenoid valve controlled by the microprocessor is installed on the expansion valve body. It allows the
automatic control of pump-down function and the valve opening during the shutdown period.
The adequate positioning of liquid sensor and an appropriate refrigerant charge (factory executed) allow an
efficient and reliable unit operation.
Clear refrigerant sight glasses are located on the condenser and evaporator shells to verify immediately the
adequate charge.
Compressors
The compressor is controlled by a special motor, installed on the end of the main driving shaft. It consists of
two screwed cast iron element: the main one includes all moving parts as the main rotor and the two
satellites, the second element includes the three-phases 2-poles electric motor.
The gas flows through the electric motor, cooling the windings before entering the suction ports. Sensors
inside the windings motor constantly monitor the temperature preventing from dangerous overheating. A
terminal box including the connectors for thermistors and power lines is located up to the motor casing.
The compressor moving elements executing the compression include 3 rotating parts, there are neither
reciprocating nor eccentric motions inside the compressor. Basic elements are the main rotor and two
exactly opposed gate rotors tightly meshing each other. A specially shaped synthetic material placed
between the main rotor and the satellites executes tightness seal during the compression. The main shaft
fixing both the motor and the main rotor is supported by 3 ball bearings. This system is balanced both
statically and dynamically before the assembly. Two large closing flanges are also installed on the
compressor sides for an easy access to the satellites, rotor, shaft and bearings without influencing the
assembly tolerances.
Compression process
With the single-screw compressor the refrigerant suction, compression and discharge process is operated
by a continue flow for each satellite. During this operation the volume is progressively reduced compressing
the refrigerant. After the compression, the gas is discharged through the ports properly designed. See figure
3 for suction, compression and discharge cycle.
2.
Upon further rotation of the main rotor , the
flutes which have been open to the suction
chamber engage with the teeth of the other
A
star rotor. This coincides with each flute being
progressively sealed by the main rotor. Once
the flute volume is closed off from the suction
chamber, the suction stage of the
c
compression cycle is complete. b
a
3.
3. Compression
As the main rotor turns, the volume of gas
trapped within the flute is reduced as the
length of the flute shortens and compression
occurs.
c
b
a
4.
4. Discharge
As the star rotor tooth approaches the end of Discharge
a flute, the pressure of the trapped vapour Gas
reaches a maximum value occurring when the
leading edge of the flute begins to overlap the
triangular shaped discharge port.
Compression immediately ceases as the gas A
is delivered into the discharge manifold. The
star rotor tooth continues to scavenge the flute
b
until the flute volume is reduced to zero. This
compression process is repeated for each a
flute/star tooth in turn.
While the compression process described
above is occurring in the upper half of the
compressor, there is an identical process B
taking place simultaneously in the lower half
using star B, thus each main rotor flute is used
twice per rotor revolution (one by one tooth in
each star). The compression process may be
likened to an assembly of six double-acting
cylinders (the main rotor flutes) in which the
star rotor teeth move as pistons (always in the
same direction).
B A
NC NC
Piston Slide
Spring
Unload
Oil Pressure + Spring Force > Suction/Discharge Differential Pressure = Slide and Piston Move Towards Unload
B A
Oil Supply Oil Vent
De-energised Energised
(Closed) (Open) Compressor Loading
Load
Suction/Discharge Differential Pressure > Spring Force = Slide and Piston Move Towards Load
CAPACITY CONTROL ACTION SOLENOID VALVE SOLENOID VALVE
A B
Load compressor
Oil is vented from the capacity control cylinder. The action of the suction/
discharge differential pressure on the slide/piston assembly overcomes the Energised (open) De-energised (close)
force of the unloading spring and moves the slide valve towards the
maximum load position.
Unload compressor
High pressure oil is admitted to the capacity control cylinder. Oil pressure
supplements the force of the spring acting on the unload side of the piston.
The combined force is sufficient to overcome the action of the De-energised (close) Energised (open)
suction/discharge differential pressure and move the slide valve towards the
minimum load position.
1
Start-up Start Compressor Starts Compressor
Requested (Loading Inhibited) Permitted to Load
Lubricating oils
Besides lubricating the bearing and other moving parts, the oil has the equally important task of granting the
seal during the compression, improving the efficiency. The amount of oil injected is therefore well in excess
than required for lubrication alone.
Lubricating oil approved for use with McQuay screw compressor is Mobil Artic 68 or ICI Emkarate RL68H.
Liquid injection
Within the nominal operating range (7°C leaving evaporator water temperature, 35°C leaving condenser
water temperature) McQuay PFS B units do not require any device for cooling the discharge gas or the oil.
When the operating conditions exceed the standard values (leaving condenser water temperature higher
than 40°C), the compressor requires the oil cooling kit defined as “liquid injection”.
That system, standard supplied on all PFS B units’ heat pump and heat recovery versions, is directly
monitored by the microprocessor installed on the unit depending on the oil temperature inside the separator.
Figure 6 shows the liquid injection circuit.
At normal operating condition and when the compressor is off, the solenoid valve (A), that controls the liquid
injection, should be also off. If the oil temperature exceeds the set point value settled in the microprocessor,
the system energises the solenoid valve (A) that injects the liquid refrigerant inside the dedicated port. The
oil temperature gradually decreases down to the set point minus the control differential when the
microprocessor de-energises the solenoid valve (A). The liquid injection may activate during plant starting
and/or during unloading conditions.
Discharge
Line
To Oil Separator
Heating elements
The compressor and the oil separator are supplied with resistances for heating the compressor and the oil
inside the separator, to prevent the migration and the condensation of the refrigerant during shutdown unit.
The auxiliary circuit should be energised for at least 12 hours prior to start up compressor. The compressor
and oil temperatures should be sufficiently high before starting the system lowering at the minimum problems
of lubrication and liquid blows. The microprocessor monitors directly the oil temperature and inhibits the
compressor starting if the oil temperature is not at least 5°C higher than the evaporating saturation
temperature. In that condition the compressor status will be: “Off: Oil Heating”. For granting the good
operation of the heating resistances, regularly verify their power input.
System security
Phase monitor
Freeze protection
Regulation type
Proportional + integral + derivative modulation on input probe the evaporator water (T = ± 0,2°C)
MicroTech II C+ terminal
MicroTech II C+ terminal has following features:
• 4-lines by 20-characters liquid crystals display back lighted
• Remotable key-pad (connection by RJ11 jack)
• “Clear language display
• Key-pad consisting of 15 keys
• Multilanguage
• No volatile memory for data storage
• General faults alarm led
• 4-levels password access to modify the set values
• Service report displaying running hours and general conditions
Compressors rotation
McQuay PFS B water cooled units automatically alternate the starting sequence of compressors for
balancing starts number and running hours.
On “automatic mode”, the compressor with the lower number of starts is activated as first. If both
compressors are running, in case of need, the first one to be stopped is the one with the highest working
hours.
Phase monitor
The phase monitor provides protection against phase loss and phase reversal. Whenever any of these
conditions occurs, a contact opens disabling the start-up or disconnecting the system.
When energising the unit, the phase monitor relay closes and the microprocessor enables the compressors
for operation. If the output relay does not close, the microprocessor releases the alarm “Phase Monitor”. In
that case perform the following tests:
1. Using an external phase tester, verify that R/S/T phases sequence is correct. A correct rotation is
required for compressor operation. If phases sequence correction is required, turn off the unit and invert
two phases on the main power supply line.
2. Turn on the unit. The phase monitor relay should now close.
3. If the alarm is still on, verify with a voltmeter the phase’s presence.
PlantVisorTM
TM
The units can be monitored locally or via modem by PlantVisor supervision program that runs on PC under
Windows 2000-XP.
TM
PlantVisor is the best solution:
• To centralize all the information in one local or remote PC
• To check all the parameters of the connected units
• To be kept updated about the alarms by modems or printers
• Data record for temperature, pressure and humidity
• Printouts of alarms, parameters and graphs
• To control several plants located in different geographical areas from a central station
TM
PlantVisor allows:
• Display and modification of the microprocessors parameters
• Protection of the main parameters by multiple password levels
• Record of data and graphics
• Display, print-out and record of the alarms
Ordinary maintenance
Refrigerant circuit
The refrigerant circuit maintenance consists of recording all operating conditions and ensures the correct oil
and refrigerant quantity. (See maintenance program and the operating data at the end of this bulletin).
During each inspection, the following data should be recorded: oil pressure, suction pressure, discharge
pressure, condenser water temperature, evaporator water temperature. Changes in sub-cooling and/or
discharge superheating could be due to low refrigerant charge. The right discharge superheating value at full
load should be included between 8°C and 15°C with R134a refrigerant, while the sub-cooling included
between 3,5°C and 6,0°C (at full load).
EVAPORATOR
WATER
OUTLET
CONDENSER
WATER
INLET
Refrigerant charge
PFS B units are designed to operate with R134a refrigerant. DO NOT USE any other refrigerant other than
R134a.
WARNING
Ensure the correct water flow inside the evaporator and condenser while adding or removing the refrigerant
to prevent from tubes freezing.
Freezing damages invalidates the warranty conditions.
WARNING
DO NOT OVERCHARGE THE SYSTEM
Excessive refrigerant charge increases the gas level in the evaporator contributing to the oil migration into
the evaporator, which may trigger alarm for lack of oil into the compressor.
All units are shipped factory charged with a full operating charge of refrigerant. However if a unit must be
recharged at the jobsite following are recommendations to apply. PSF B units are more sensitive to
overcharging therefore it is preferable a slightly undercharge of refrigerant. The optimum charge allows the
unit to run with a correct refrigerant flow at all operating conditions.
Note: As the unit changes the load, the sub-cooling will vary, but should become stable shortly; however it
should never go below 3°C. The sub-cooling will vary somewhat with evaporator and condenser leaving
water temperatures.
A refrigerant leak could be such small to have little effect on the circuit or could be such severe to cause the
unit to shut down for operation of safety protections.
Procedure to charge a moderately uncharged PFS B unit.
1. Connect the refrigerant tank to the service-filling valve located on the evaporator.
2. Open the refrigerant cylinder and charge the unit weighing the gas – or – charge the unit during the
compressor/s operation until the evaporating pressure allows the compressors running at full load.
3. With compressors running at 100%, add the refrigerant checking the evaporator gas level does not
exceed the last tubes row.
Electrical System
Maintenance of the electrical system involves the general requirement of keeping contacts clean and
connections tight and checking on specific items as follows:
The compressor current draw should be checked and compared to nameplate value. Normally, the actual
current will be lower, since the nameplate rating represents full load operation.
Inspection must verify that the oil heaters are operative. The heaters can be checked by ammeter
reading. They should be energised whenever power is available to the control circuit and the compressor
is inoperative. When the compressor runs, the heaters are de-energised.
At least once a quarter, all equipment protection controls except compressor overloads and high
pressure switches should be made to operate and their operating points checked. A control can shift its
operating point as it ages, and this must be detected so the controls can be adjusted or replaced. Pump
interlocks and flow switches should be checked to be sure they interrupt the control circuit when tripped.
Thermal relays and high pressure switches have to be checked separately at the test bench.
Absorbed current for electrical heaters in the compressor is about 4,1 A, while it is about 1,4 A for the oil
separator.
The contactors in the motor starter should be inspected and cleaned quarterly. Tighten all terminal
connections.
The compressor motor resistance to ground should be checked and logged semi-annually. This log will
track insulation deterioration. A reading of 50 MΩ or less indicates a possible insulation defect or
moisture and must be further checked.
CAUTION
Never Megger a motor while in a vacuum. Severe motor damage can result.
Seasonal Servicing
Prior to shutdown periods and before starting up again, the following service procedures must be completed.
Annual Shutdown
Where the chiller can be subject to freezing temperatures, the condenser and chiller must be drained of
all water. Dry air blown through the condenser will aid in forcing all water out. Removal of condenser
heads is also recommended. The condenser and evaporator are not self-draining and tubes must be
blown out. Water permitted to remain in the piping and vessels can rupture these parts if subjected to
freezing temperature.
Forced circulation of antifreeze through the water circuits is one method of avoiding freeze up.
WARNING
McQuay International assumes no responsibility for the results of untreated or improperly treated
water.
Annual Startup
This is a good time to check all the motor winding resistance to ground. Semi-annual checking and recording
of this resistance will provide a record of any deterioration of the winding insulation. All new units have well
over 100 MΩ resistance between any motor terminal and ground.
1. The control circuit must be energised at all times, except during service. If the control circuit has been off
and oil is cool, energise oil heaters and allow 24 hours for heater to remove refrigerant from the oil
before starting.
2. Check and tighten all electrical connections.
3. Replace the drain plug in the cooling tower pump if it was removed at shutdown time the previous
season.
4. Install fuses in main disconnect switch (if removed).
5. Reconnect water lines and turn on supply water. Flush condenser and check for leaks.
Repair of System
Pumping Down
If it becomes necessary to pump the system down, extreme care must be used to avoid damage to the
evaporator from freezing. Always make sure that full water flow is maintained through the chiller and
condenser while pumping down. To pump the system down, close all liquid line valves. With all liquid line
valves closed and water flowing, start the compressor. Pump the unit down until the MicroTech II controller
cuts out. Use a portable condensing unit to complete the pump down, condense the refrigerant, and pump it
into the condenser.
A pressure regulating valve must always be used on the drum being used to build the system pressure.
Also, do not exceed the test pressure given above. When the test pressure is reached disconnect the gas
cylinder.
Pressure Testing
No pressure testing is necessary unless some damage was incurred during shipment. Damage can be
determined upon a visual inspection of the exterior piping, checking that no breakage occurred or fittings
loosened. Service gauges should show a positive pressure. If no pressure is evident on the gauges, a leak
Leak Testing
In the case of loss of the entire refrigerant charge, the unit must be checked for leaks prior to charging the
complete system. This can be done by charging enough refrigerant into the system to build the pressure up
to approximately 70 kPa and adding sufficient dry nitrogen to bring the pressure up to a maximum of 850
kPa. Leak test with an electronic leak detector. Halide leak detectors do not function with R-134a. Water flow
through the vessels must be maintained anytime refrigerant is added or removed from the system.
WARNING
Do not use oxygen or a mixture of R-22 and air to build up pressure
as an explosion can occur causing serious personal injury.
To build up pressure, pressure regulating valve must be used. If pressure test is requested, disconnect the
refrigerant cylinder before performing the test.
If any leaks are found in welded or brazed joints, or it is necessary to replace a gasket, relieve the test
pressure in the system before proceeding. Brazing is required for copper joints.
After making any necessary repair, the system must be evacuated as described in the following section.
Evacuation
After it has been determined that there are no refrigerant leaks, the system must be evacuated using a
vacuum pump with a capacity that will reduce the vacuum to at least 130Pa ≅1mmHg).
A mercury manometer, or an electronic or other type of micron gauge, must be connected at the farthest
point from the vacuum pump. For readings below 130Pa, an electronic or other micron gauge must be used.
The triple evacuation method is recommended and is particularly helpful if the vacuum pump is unable to
obtain the desired 130Pa of vacuum. The system is first evacuated to approximately 660Pa ≅5mmHg). Dry
nitrogen is then added to the system to bring the pressure up to zero.
Then the system is once again evacuated to approximately 230Pa ≅2mmHg). This is repeated three times.
The first pulldown will remove about 90% of the noncondensables, the second about 90% of that remaining
from the first pulldown and, after the third, only 0,2% noncondensables will remain.
NOTE
It is of utmost importance that all local, national, and international regulations concerning the
handling and emission of refrigerants are observed.
I. Compressor
A. Performance Evaluation (Log & Analysis) * O
B. Motor
• Meg. Windings X
• Ampere Balance (within 10%) X
• Terminal Check (tight connections, porcelain clean) X
C. Lubrication System
• Oil Lines Temperatures O
• Oil Solenoid Valve Operation X
• Oil Analysis X
• Oil Appearance (clear color, quantity) O
• Oil Filter Change X
• Oil change if indicated by oil analysis X
D. Unloading Operation
• Compressor Loads:
Record Motor Amps X
• Compressor Unloads:
Record Motor Amps X
E. Internal Compressor Check X
II. Controls
A. Operating Controls
• Check Settings and Operation X
• Check Unloading Setting and Operation X
• Verify Load Balance Operation X
B. Protective Controls
• Test Operation of:
Alarm Relay X
Pump Interlocks X
High and Low Pressure Cutouts X
High Discharge Temperature Cutout X
Oil Pump Pressure Differential Cutout X
III. Condenser
A. Performance Evaluation O
B. Test Water Quality X
C. Clean Condenser Tubes X
E. Seasonal Protection X
IV. Evaporator
A. Performance Evaluation (Log Conditions And Analysis) O
B. Test Water Quality X
C. Clean Evaporator Tubes (as required) X
E. Seasonal Protection X
V. Expansion Valves
A. Performance Evaluation X
Key: O = Performed by in-house personnel X = Performed by McQuay Service personnel
NOTE
Some compressors use power factory correction capacitors. Capacitors must be disconnected from
the circuit to obtain a useful Megger reading. Failure to do so will produce a low reading. In handling
electrical components, only fully qualified technicians must attempt service.
NOTE
This checklist must be completed and sent to the local McQuay service location two weeks prior to
start-up.