Acmas - BB Company Solutions

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 4

Given Information

Machinery 282,000
UL (SLD) 4
ACI 100,000
IT % 30%
DR % 12%
Dep 70500
Solving ACIAT
ACIAT
ACI 100,000 *
Dep 70,500 *
ACIAT
A. What is the IRR of this project?
IRR Investment /
282,000
IRR 3.0938
Comparing IRR Factors
11%
3.102 3.093
0.009is 11%, because 3.093
Answer: The IRR of this project
is much closer to 3.102 than 3.037. In which 3.102
corresponds to 11%.
40,000
15,000
40,000
B. Find NPV
PV 0.636 Cash Inflows
PVA 3.037 91,150 * 3.037 276822.6

Cash Outflows
282,000 * 1 282,000
NPV -5,177

0.7 70000 C. Find PI


0.3 21150 276,823 / 282,000 98.16%
91150
D. Get 12% IRR
ACIAT 5,177 / 3.037 1704.643
91150 1704.643 / 0.7 2435.204
2435.204 + 100,000 102,435

12% E. Find NPV, if asset is depreciated over 3 years


3.037 Cash Inflows
0.056
s 11%, because 3.093 70,000 * 3.037 212,590
7. In which 3.102 28,200 * 2.402 67,736
280,326
Cash Outflows
282,000 * 1 282,000
NPV -1,674

F. Find NPV, if +12,000 WC


Cash Inflows
91,150 * 3.037 276822.6
12,000 * 0.636 7632
284454.6

Cash Outflows
282,000 * 1 282,000
12,000 * 1 12,000
294,000
NPV -9,545
Original NPV -5,177
Decrease 4,368

G. Find NPV, if asset is replaced


ACIAT
100,000 * 0.7 70000
DTS
70,500 - 6,250 64,250
64,250 * 0.3 19275
ACIAT 89275
Cash Inflows
89,275 * 3.037 271128.2
- 25,000 15,000
* 0.3 4500 Cash Outflows
- 4500 35,500 282,000 * 1 282,000
35,500 * 1 -35,500
246,500

NPV 24,628