ch5 MRP
ch5 MRP
ch5 MRP
(MRP)
Assembly
Subassembly
Fabrication
Procurement
1 2 3 4 5 6 7 8 9 10
Time Period (weeks)
Bill of Material (BOM)
• BOM: A listing of all of the raw materials,
parts, subassemblies, and assemblies needed
to produce ONE unit of a product.
Scheduled receipts
Net requirements
Planned order
receipt
Planned order
release
MRP Processing
• Planned-order receipts
– Quantity expected to received at the beginning of
the period
• Planned-order releases
– Planned amount to order in each time period
Example 5.2
Week 1 2 3 4 5 6
Part A Planned order receipt 50 100
Lead time: 1 week Planned order release 50 100
Part B Planned order receipt 50 100
Lead time: 2 week Planned order release 50 100
Part C Planned order receipt 50 100
Lead time: 1 week Planned order release 50 100
Part D Planned order receipt 50 100
Lead time: 1 week Planned order release 50 100
Part E Planned order receipt 50 100
Lead time: 1 week Planned order release 50 100
Exercise
• Using the following product tree, determine the planned order receipts
and release if 200 As are to be produced in week 5. All lead times are one
week excepts for component E, which has lead time of two weeks.
Answer
Week 1 2 3 4 5
Part A Planned order receipt 200
Lead time: 1 week Planned order release 200
• Planned on hand
– Expected inventory on hand at the beginning of each
time period
Available Inventory = Projected on hand– Safety stock– Inventory
allocated to other items
Example 5.3
• Complete the following table. Lead time for the part is two weeks. The
order quantity (lot size) is 100 units
Week 1 2 3 4
Gross requirements 50 45 20
Projected available 75
Net requirements
Planned order receipt
Planned order release
Week 1 2 3 4
Gross requirements 50 45 20
Projected available 75 75 25 80 60
Net requirements 20
Planned order receipt 100
Planned order release 100
Exercise
• Complete the following table. Lead time for the part is two weeks, and the
order quantity is 40. What action should be taken?
Week 1 2 3 4
Gross requirements 20 15 10 20
Projected available 40
Net requirements
Planned order receipt
Planned order release
Answer
Week 1 2 3 4
Gross requirements 20 15 10 20
Projected available 40 20 5 35 15
Net requirements 40 15
Planned order receipt 40
Planned order release
Week 1 2 3 4
Gross requirements 50 250 100 50
Scheduled receipts 200
Projected available 150
Net requirements
Planned order receipt
Planned order release
Week 1 2 3 4
Gross requirements 50 250 100 50
Scheduled receipts 200
Projected available 150 100 50 150 100
Net requirements 50
Planned order receipt
Planned order release 200
Exercise
• Complete the following table. Lead time for the part is two weeks. The lot
size is 100. What is the projected available at the end of week 3? When is
it planned to release an order?
Week 1 2 3 4
Gross requirements 20 65 35 25
Scheduled receipts 40 100
Projected available
Net requirements
Planned order receipt
Planned order release
Answer
Week 1 2 3 4
Gross requirements 20 65 35 25
Scheduled receipts 40 20 100 20 95
Projected available 0 55 0 5
Net requirements 0 0 0 100
Planned order receipt 100 0
Planned order release