PKG II Schedule B
PKG II Schedule B
PKG II Schedule B
Appendix A-I
Index map
SCHEDULE - B
(See Clause 2.1)
DEVELOPMENT OF PROJECT HIGHWAY
Development of the Project Highway shall include detailed design, including plan & profile
within available proposed ROW and construction of the Project Highway as described in
Schedule-B and Schedule-C. The alignment plans of the Project Highway are given in
Annex-III of Schedule A. The proposed plan & profile, locations of different
structures/drains/service & slip road/RE walls, chainages of different structures/drains/
service & slip road/RE walls, length of different structures/drains/service & slip road/RE
walls etc. of the project highway as indicated in the Schedule A, Schedule B, Schedule C
and their Annexures. Based on site/design requirement, the Concessionaire shall finalize
Detailed Design including plan & profile of the project highway and submit the same to
Authority & its Engineer for acceptance, before the start of the execution of project.
Based on accepted design including Plan & profile prepared by the Concessionaire, the
detailed work program shall be prepared along with commensurate deployment of all
resources and get approved from Engineer before start of civil work.
Rehabilitation and augmentation shall include 4 Lane with Paved shoulders configuration
as described in Annexure-I of this Schedule-B and in Schedule-C.
The Project Highway shall be designed and constructed in conformity with the
Specifications and Standards specified in Annexure-I of Schedule-D
Annexure – I
(Schedule – B)
Description of the Project
The Project Highway shall generally follow the horizontal alignment shown in the plan
specified in Annexure- III of Schedule-A, unless otherwise specified by the Authority.
Notwithstanding anything to the contrary contained in this Agreement or IRC:SP:84- 2019,
the proposed plan & profile, locations of different structures/drains/service & slip
road/RE walls, chainages of different structures/drains/service & slip road/RE walls,
length of different structures/drains/service & slip road/RE walls etc. of the project
highway as indicated in the Schedule A, Schedule B, Schedule C and their Annexures shall
be treated as minimum requirement Based on site/design requirement, the
Concessionaire shall finalize their Detailed design(development stage) including plan &
profile of the project highway and submit the same to Authority & its Engineer for its
consent/approval and safety audit by safety auditor, before the start of the execution of
project.
The designs so approved shall not be in contradiction with the scope of project. For
avoidance of doubt, the provisions mentioned in schedule B & C cannot be changed only
the design of the components is to be submitted for consent/approval
1.2.2 In case of depressed median, a minimum of 0.6 metre wide edge strip adjacent to
carriageway in either direction shall be paved. In case of flushed median, the metal beam
(thrie beam) crash barrier shall be provided on either side of the median.
1.2.3 A suitable paving (paver blocks, etc.) shall be proposed for flushed median to
prevent spreading of soil on carriageway
Design Chainage
Sl No Length (Km) Remarks
From To
NA
2.3.4 Realignments: The existing road shall be improved to the standards as specified in
the manual at the following locations:
Design Chainage
Sl No Length (Km) Remarks
From To
Nil
2.3.5 Bypasses : The existing road shall be bypassed to the standards as specified in the
manual at the following locations:
2.5.2 Paved shoulders and strip on median side shall be of same specification and pavement
composition as of main carriageway
2.5.3 The overlay on the main carriageway pavement and on the paved shoulders shall be
uniform in thickness and composition.
2.5.4 In Built-up sections, footpaths/fully paved shoulder shall be provided with width
1.5m/2.5m respectively.
2.5.7 The Design Specification of paved shoulder shall conform to the requirements
specified in paragraph 5.11 of the manual.
2.5.8 The earthen shoulder of 2.0m width on shoulder side shall be provided with top 150
mm on earthen shoulder with well graded naturals and morrum gravel crust stones or
combination thereof, confirming to l 401 of MoRTH specification.
2.5.9 The earthen shoulder of 1.0m width on median side shall be provided with top 150
mm on earthen shoulder with well graded naturals and morrum gravel crust stones or
combination thereof, confirming to Clause 401 of MoRTH specification to fix MBCB and
confirm placement requirement of MBCB.
2.6.1 In case of VUP/LVUP/SVUP, the proposed structure, the finish road level in
VUP/LVUP/SVUP shall be kept 150 mm above the ground level/service road/cross
road(whichever is higher) to ensure that these VUP/LVUP/SVUP don’t become water
accumulation points.
2.6.2 The vertical and horizontal clearance at the underpasses shall be as per manual.
2.7 Lateral and vertical clearances at Overpasses
2.7.1 Lateral and vertical clearances for overpasses shall be as per the Manual.
2.7.2 Lateral clearance: The width of the opening at the Overpasses shall be as follows:
Nil
2.8.4 Slip Road: The height of embankment of slip road shall confirm to manual.
The Slip roads shall be constructed at the locations and for the lengths indicated below:
Straight Length:
Tapper Length:
Length (m)
Sl no From To
LHS RHS
A separator between main carriageway and service/slip road shall be provided to prevent
the pedestrians, local vehicles and animals entering the highway.
Note:
1. Above length of the service/slip roads is minimum specified. The actual length of the
service/slip/connecting roads shall be determined by the Concessionaire in accordance with
the approved plan & profile and design approved from the Independent Engineer. Any
increase/decrease up to 5 percent length from the length specified in this Clause of
Schedule-B shall not constitute a Change of Scope. Any additional length shall be dealt in
Change of Scope.
2. The Acceleration, deceleration lane, right turning storage lane, entry/exit lanes shall
be constructed in addition to length given in above table and shall be deemed to be part of
the scope and no Change of Scope shall be considered for the same.
2.9 Grade Separated Structures: Grade separated structures shall be constructed as per
paragraph 2.13 of the Manual. Proposed levels at structure locations as shown in plan &
profile specified in Annexure-III of schedule A are minimum requirement and only for
guidance and any increase in levels shall not constitute any change of scope. Entry/Exit
arrangement from main carriageway shall be 50m before/after the start/end of approach
road to grade separator i.e. start/end of valley curve. RCC barrier shall start from start of
valley curve and end after grade separator at end of valley curve.
The sub-structure shall be continued in the median portion with RCC barrier wherever
superstructure has not been proposed in median portion. .
50m long MBCB Safety barriers on structure approaches shall be provided on all four faces of
each structure. MBCB provided towards median side of each structure shall be joined on ends
in semi-circular shape.
0.75m wide footpaths shall be provided at grade intersection below structures for each
direction of pedestrian movement.
Super
Minimum
Design LHS RHS Structure Span
Sr. Vertical Skew
Chainage Roadway Roadway Provision Arrangement Remarks
No. Clearance Angle
(Km) Width (m) Width (m) in (m)
(m)
Median
Both Side:
SH 363
(Kanigiri
Titupati
Road)
RHS:
Towards
1 715.468 11 11 No 1x30 5.5 0
Inukurthy
LHS:
Towards SH
355
(Podalakur
Somsila
Road)
Both Side:
SH 446
(Manuolu
Podalakur
Road)
2 725.988 11 11 No 1x30 5.5 37 RHS:
Towards
Veerampalli
LHS:
Towards
Biradavolu
Design Typical
Sr. Name of Span Total
Chainage Cross Remarks
No structure Arrangement (m) Width (m)
(km) Section
Nil
2.9.8 Details of Ramps, Cross Roads and Connecting Roads at Interchanges (IC)
Note:
1. Any variations in the lengths of TCS as specified in the above table shall not
constitute a Change of Scope,
2. Lengths mentioned in the above list for cross section types concerned to structures
are inclusive of structure length.
3. Retaining wall/ RE wall shall be provided to full height on all structures.
4. Toe wall (0.6 m ht) or retaining wall to be provided where ROW is restricted and
water bodies along the proposed highway on the sections specified in Schedule-B.
5. Chainages may be adjusted according to location of structures as per drawings.
6. Fig 2.2A, Fig 2.2B & Fig 2.2C, are modified figures of Fig 2.2 of Manual.
The service road pavement composition shall be continued on cross roads of the
intersections for the specified length (of 30m at grade and then to be merged with
cross road with 2% slope) and grade separated intersections.
Properly designed intersections shall be provided at the locations and of types and
features given in the tables below:
Note : Layout, Geometric Design and Typical Cross Sections of Major Junction is included in
Annexure to schedule-B.
Note : Layout, Geometric Design and Typical Cross Sections of Major Junction is included
by in Annexure to schedule-B.
The cross road at the junctions which are having a level difference from the main
carriageway, are to be improved at the level of main carriageway for the length of
30 metre and then to be merged with the cross road at the gradient not more than
1:50.
3. For minor / major layout for left-in / left out arrangement with physical islands with
hazard marking. Where there is space constraint to provide physical islands, the effect
of junction kept wide opened can be avoided by ghost island with marking.
4. For U-turn, Self-Regulated U-Turn facility shall be created. as per fig 3.6 of manual
2. Junction improvement under grade separators shall be carried out as per manual
with proper entry/exit to cross roads and slip/service roads, etc. Auxiliary lanes
including storage, acceleration and deceleration lane along with physical islands to
be provided.
4. Intersection Layout, Entry/Exit, Right Turning Lane, U-Turns, Geometric Design and
Typical Cross Sections of Interchange shall be included by DPR consultant in
Annexure to schedule-B.
5. Only Entry or Exit shall be designed at any location (provision of entry/exit by ghost
island not permitted).
Based on site/design requirement, the Concessionaire shall design the alignment plans
and profiles of the project highway based on site/design requirement mentioned in
Schedule B with approval from the Independent Engineer within the available Right of
Way. However, it is clarified that bottom of subgrade level shall be at-least 1000 mm
above HFL/Existing ground level for a greenfield/ bypass stretch.
The side slopes shall not be steeper than 2H:1V. In case, there is a ROW constraint than,
suitable soil retaining structures shall be provided.
For stability of slope upto 3 metre height the turfing can be adapted. For the slope from
3-6 metre suitable geocell, geo-grid, geo-green etc. can be provided with suitable
drainage chutes as per IRC 56 . For the slope more than 6 metre height a complete slope
stability analysis as per IRC:75 shall be done and the slopes shall be compulsory protected
with stone pitching within stone masonry grid structure of 4x4 metre and suitable
drains/chutes etc. shall be provided for effective drainage of the water.
5 Pavement design
5.1 Pavement design shall be carried out in accordance with Section 5 of the Manual.
5.2 Type of Pavement and Design requirement
The pavement shall be flexible type for entire length of project highway except for toll
plaza locations where rigid pavement shall be provided.
5.2.3 The pavement for service road/slip road shall be designed for projected traffic of
20MSA. Subject to minimum as follows:
i. Service roads in Built-up areas for minimum 20 MSA
5.3 In order to meet the intended functional requirement of respective pavement layers
on main carriageway, the minimum thickness of respective pavement layers for main
carriageway and connecting/cross/service/slip road/entry/exit locations,
acceleration/ deceleration lane, right turning lanes shall, however, in no case be
less than as given below:
5.3.1 Main carriageway, paved shoulder, median side paved strip, entry/exit locations,
acceleration/ deceleration lane, right turning lanes (Flexible) with CTB/CTSB
Subgrade 500
CTSB 200
CTB 110
WMM/AIL(Aggregate 100
Interlayer)
BC 50
Design Chainage
Sr. No. Overlay Pavement Composition Remarks
From To
Nil
6 Roadside Drainage
6.1 Drainage system including surface and subsurface drains for the Project Highway
including cross roads shall be provided as per section 6 of the manual. RCC Drain cum
footpaths shall conform to the cross- sectional features as given in Annexures to Schedule
B and shall be provided as under:
Details of RCC Drain cum footpath (Width 1.5m & depth starting from 1 m)
Length(m)
Sl no From(m) To(m)
LHS RHS
1 699335 699610 275 275
2 704780 705048 268 268
3 705060 705290 230 230
4 708230 708635 405 405
5 708647 709050 403 403
6 710670 711067 397 397
7 711088 711295 207 207
Length(m)
Sl no From(m) To(m)
LHS RHS
8 711305 711410 105 105
9 715150 715453 303 303
10 715483 715842 359 359
11 725570 725813 243 243
12 725828 725973 145 145
13 726003 726308 305 305
14 730900 731147 247 247
15 731168 731420 252 252
Total 8288
length(m) Side
Sl No From To LHS RHS
1 712800 713000 200 000 LHS
2 713000 713190 190 190 Both Side
3 713630 713920 290 290 Both Side
Total Length 1160
6.2 Unlined Drains: other than above mentioned locations shall be provided in the entire
project length which gets terminated at all cross road locations. In case, the definite outfall
is not available, a rain water harvesting system shall be provided at the deepest location
for dispersal of water.
6.3 Median Drain
Lined drain shall be provided in the center of the median at super elevation locations and
depressed median. Draining of storm water from one carriageway to other carriageway is
not permitted. the Concessionaire shall design the median drain based on site/design
requirement mentioned in Schedule D with approval from the Independent Engineer and
shall be connected with the nearest culvert/outfall.
Details of Median Drain:
A suitable drainage arrangement for draining storm water from Underpass and Subways shall be
provided.
Vertical Drop-down drainage pipes with suitable cleaning provision shall be provided at
suitable interval. Drainage fixtures and dropdown pipes shall be of rigid, corrosion resistant
material not less than 100mm dia. The Storm water of main carriageway draining on service
road is not permitted.
7 Design of Structures
7.1 General
Project Highway is proposed to be constructed to Four Lane configuration Special vehicle
loading is to be considered in design of all bridges, culverts and structures.
All structures except structures wherever expansion joints have been provided, the
pavement layers shall be continued over the structures for smooth riding quality of the
project highway. These structures shall be designed considering the dead load of WMM/ CTB
and above layers
All major structures will be designed preferably as continuous slab to reduce the number of
expansion joints on the MJB/ ROBs/ flyover/ Interchange etc.
7.1.1 All bridges, culverts and structures shall be designed for IRC class Special Vehicle
(SV) loading as per IRC: 6 and constructed in accordance with section-7 of the
manual and shall conform to the cross-sectional features and other details
specified therein.
7.1.2 The overall Width of the structures shall be as given in Para 7.3 of Annex-I of
Schedule-B.
7.1.3 The Safety Barrier and Footpath on Bridges and RoB shall continue on approaches.
The footpath shall be provided with paved surface & railing till the embankment
height is more than 3m.
Details of Structures with footpaths
Sl Location Footpath
No At km Width (m) Footpaths & Barriers(Extreme side of carriage ways)
1 703.638 1.5 1.5m wide footpath with crash barriers in M.C.W. Bridge
2 704.433 1.5 1.5m wide footpath with crash barriers in M.C.W. Bridge
3 707.298 1.5 1.5m wide footpath with crash barriers in M.C.W. Bridge
4 707.983 1.5 1.5m wide footpath with crash barriers in M.C.W. Bridge
5 709.398 1.5 1.5m wide footpath with crash barriers in M.C.W. Bridge
6 711.293 1.5 1.5m wide footpath with crash barriers in M.C.W. Bridge
7 711.908 1.5 1.5m wide footpath with crash barriers in M.C.W. Bridge
8 717.500 1.5 1.5m wide footpath with crash barriers in M.C.W. Bridge
9 717.692 1.5 1.5m wide footpath with crash barriers in M.C.W. Bridge
10 719.191 1.5 1.5m wide footpath with crash barriers in M.C.W. Bridge
11 719.358 1.5 1.5m wide footpath with crash barriers in M.C.W. Bridge
12 719.503 1.5 1.5m wide footpath with crash barriers in M.C.W. Bridge
13 720.153 1.5 1.5m wide footpath with crash barriers in M.C.W. Bridge
14 721.098 1.5 1.5m wide footpath with crash barriers in M.C.W. Bridge
15 725.123 1.5 1.5m wide footpath with crash barriers in M.C.W. Bridge
16 725.818 1.5 1.5m wide footpath with crash barriers in M.C.W. Bridge
17 729.533 1.5 1.5m wide footpath with crash barriers in M.C.W. Bridge
1.5 1.5m wide footpath with crash barriers in M.C.W. Bridge
731.620
18 on either side
19 732.365 1.5 1.5m wide footpath with crash barriers in M.C.W. Bridge
20 734.823 1.5 1.5m wide footpath with crash barriers in M.C.W. Bridge
21 736.698 1.5 1.5m wide footpath with crash barriers in M.C.W. Bridge
22 737.098 1.5 1.5m wide footpath with crash barriers in M.C.W. Bridge
23 737.754 1.5 1.5m wide footpath with crash barriers in M.C.W. Bridge
24 738.040 1.5 1.5m wide footpath with crash barriers in M.C.W. Bridge
7.2 Culverts
7.2.1 Overall width of all culverts shall be equal to the roadway width of the
approaches. The overall width of culverts shall be including width of main
carriageway and slip/service roads/ entry ramps/ exit ramps/ accelerations
/deceleration lanes etc. All culverts shall also be continued in median and in gap
between main carriageway and service road.
7.2.2 New/Reconstruction of existing culverts: The existing culverts at the following
locations shall be re-constructed as new culverts:
The following existing Culverts to be reconstructed as RCC BOX culverts
Existing Remarks
Sl. Design Existing Proposed Proposed Skew
Culvert
no Chainage Span Span Type angle
Type
1 699.307 RCC BOX 2 x 1.4 1X5 RCC BOX 0 Nala
2 709.340 HPC 1 X 0.6 1 X 4.0 RCC BOX 0 Canal
Existing
Sl. Design Existing Proposed Proposed Skew
Culvert Remarks
no Chainage Span Span Type angle
Type
Nil
Note: The overall width of the above culverts shall include width of main carriageway
and slip/service roads/ramps, in case there is any slip/service roads/ramps.
Drains for field channel as per site condition and modification to the irrigation
requirement shall be part of scope.
Note:
1. The overall width of the above culverts shall be equal to Roadway width including
median & slip/service roads/ramps, in case there is any slip/service roads/ramps.
Any additional Barrel length required as per site conditions shall not constitute a
Change of Scope.
The following additional culverts to be proposed at the connecting roads for
drainage purpose
Sl.
Chainage Proposed Span Proposed Type Length Side
no
Sl.
Chainage Proposed Span Proposed Type Length Side
no
7.2.6 Floor protection works shall be carried out as specified in the relevant IRC codes
and specifications.
7.2.7 Utility ducts in Greenfield section (including realignments) in form of NP-4 Hume
Pipe dia 600 mm shall be provided across the Project Highway @ 0.50 km c/c and
along with inspection chamber where directed for crossing of utilities anywhere as
per manual requirements. Location for such utility crossing shall be finalized in
consultation with Independent Engineer/NHAI.
7.3 Bridges
7.3.1 Existing bridges to be re-constructed/widened:
i. Existing bridges at the following locations shall be reconstructed as new structures:
Major Bridges
Remarks
Sl. Design Existing Existing Proposed Proposed Skew
no Chainage Type Span Span Type angle
Nil
Minor Bridges
Proposed Remarks
Sl. Design Existing Existing Proposed Proposed Width Skew
no chainage Type Span Span Type angle
MCW SR
NIL
ii. Existing narrow bridges at the following locations shall be retained and widened:
Remarks
Sl. Design Existing Existing Proposed Proposed Skew
no Chainage Type Span Span Type angle
Nil
Nil
7.3.2 Additional New Bridges: New bridges at the following locations on the Project
Highway shall be constructed. GADs for the new bridges are attached in the
drawings folder.
New major bridges to be constructed at the following locations:
Typical
Total Proposed
Sl. Design Propose Proposed Cross Skew
Width Remarks
no Chainage d Span Type section of angle
MCW SR Manual
2 x 12.5 Fig 7.2AA Irrigation
1 707.298 4 X 35.0 PSC Girder NA
0 tank
2 711.908 3 x 24.0 PSC Girder 2 x 12.5 NA Fig 7.2AA 35 Nala
2 x 12.5 Fig 7.2AA Irrigation
3 721.098 5 X 30.0 PSC Girder NA
0 tank
2 x 12.5 Fig 7.2AA Irrigation
4 736.698 5 x 30.0 PSC Girder NA
0 tank
2 x 12.5 Fig 7.2AA Surplus
5 737.082 3 x 40.0 PSC Girder NA
6 weir
Typical
Total Proposed
Sl. Design Propose Proposed Cross Skew
Width Remarks
no Chainage d Span Type section of angle
MCW SR Manual
2 x 12.5 Fig 7.2AA Surplus
6 737.754 4 x 35.0 PSC Girder NA
0 weir
Sl Typical Remark
no Design Proposed Proposed Width Width Cross Skew s
Chainage Span Type of MCW of SR section of Angle
Manual
1 2x NA Fig 7.2AA
703.638 1 X 8.0 RCC SLAB Nala
12.5 0
2 2x NA Fig 7.2AA
704.436 1 X 10.0 RCC SLAB Nala
12.5 0
3 2x NA Fig 7.2AB
704.611 5 X 6.0 RCC BOX Nala
15.5 59
4 RCC T 2x NA Fig 7.2AA
707.986 1 X 14.0 Canal
GIRDER 12.5 0
5 1X6.0+ 2x NA Fig 7.2AA
709.423 RCC BOX Canal
5X5.0 12.5 66
6 2x 2x Fig 7.2BA
711.300 1 X 10.0 RCC SLAB Nala
11.0 8.5 32
7 2x NA Fig 7.2AA
717.500 1 X 10.0 RCC SLAB Nala
12.5 31
8 RCC T 2x NA Fig 7.2AA
717.694 1 X 10.0 Nala
Girder 12.5 55
9 2x NA Fig 7.2AA
719.196 1 X 10.0 RCC SLAB Nala
12.5 0
10 2x NA Fig 7.2AA
719.360 1 X 10.0 RCC SLAB Nala
12.5 30
11 RCC T 2x NA Fig 7.2AA
719.526 4 X 10.0 Nala
Girder 12.5 54
12 RCC T 2x NA Fig 7.2AA
720.157 2 X 10.0 Nala
GIRDER 12.5 38
13 RCC T 2x NA Fig 7.2AA
725.124 1 X 24.0 Canal
Girder 12.5 19
14 2x 2x Fig7.2BA
725.820 3 X 5.0 RCC BOX Canal
11.0 8.5 21
15 2x NA Fig 7.2AA
726.593 4 X 5.0 RCC BOX Nala
12.5 78
16 RCC T 2x NA Fig 7.2AA
729.535 1 X 12.0 Nala
Girder 12.5 18
17 2x NA Fig 7.2AA
731.624 1 x 10.0 RCC SLAB Nala
12.5 17
18 2x 2x Fig 7.2BB
732.367 1 X 10.0 RCC SLAB Nala
11.0 10.5 16
Sl Typical Remark
no Design Proposed Proposed Width Width Cross Skew s
Chainage Span Type of MCW of SR section of Angle
Manual
19 RCC T 2x NA Fig 7.2AA
734.820 3 X 12.0 Nala
Girder 12.5 50
20 RCC T 2x NA Fig 7.2AA
735.828 1 x 10.0 Nala
Girder 12.5 45
21 2x NA Fig 7.2AA
738.040 5 X 10.0 RCC SLAB Nala
12.5 0
7.3.3 The railings of existing bridges shall be replaced by crash barriers at the following
locations:
Design Chainage Length
Sr. No Remarks
From To (km)
Nil
Design Total
Sr. Proposed Span Type of super- Skew
Chainage Width Remarks
No. Arrangement (m) structure Angle
(Km) m)
composite girder
2 X 36 + 1 X 72 + 2
1 701.400 + Bow String 60 2 x 12.3 Yet to be
X 18 approved
girder
composite girder
3 x 36 + 1 x 60 + 2
2 724.038 + Bow String 14 2 x 12.3 Yet To Be
x 18 Approved
girder
composite girder
2 x 36 + 1 x 54.0 +
3 738.615 + Bow String 0 2 x 12.3 Approved
2 x 18
girder
Note:
7.6 FoB/Skywalks
8.1 Traffic control devices and road safety works shall be provided in accordance with
Section 9 of the IRC:SP:84-2019.
End Treatment of Steel barriers/Rope Barrier shall be specified i.e. (Modified Eccentric Loader
Terminal) MELT or P-4 confirming to EN 1317-4, TT, MBCB barrier to Concrete Barrier
Thrie Beam crash barrier proposed both side of median at the following locations.
Thrie Beam has been proposed at the following high Embankment locations
Thrie beam crash barrier proposed at the following locations due to super elevation Portion
Sl
From To Length(m) Side
No
1 704752 705365 613 RHS
2 713567 713995 428 RHS
3 730607 731378 771 LHS
4 732486 732716 230 RHS
Total Length 2042 Total
9 Roadside Furniture
The safety barriers shall be provided at the following hazardous location such as
ponds ,well electric sub station ,electric tower,split carriageway etc .
Location Stretch
Sr. No. LHS/RHS
From (Km) To (Km)
11 Special Requirement:
For LVUP/SVUP
Design Chainage
Sl No Length(m) Side Avg Height(m)
From To
1 699338 699580 484 BHS 6.63
2 700575 700813 476 BHS 6.6
3 700820 701317 994 BHS 6.67
4 703800 704085 570 BHS 6.83
5 704092 704150 116 BHS 5.63
6 704810 705040 460 BHS 5.6
7 705060 705260 400 BHS 5.07
8 706740 707205 930 BHS 7.9
9 707212 707225 26 BHS 7.47
10 708260 708629 738 BHS 5.27
11 708649 709020 742 BHS 5.27
12 710700 711061 722 BHS 5.93
13 711089 711286 394 BHS 7.8
14 711304 711380 152 BHS 6.1
15 714000 714070 140 BHS 7.83
16 714077 714100 46 BHS 7.83
17 722000 722183 366 BHS 5.37
18 722190 722400 420 BHS 5.27
19 727850 728051 402 BHS 6.57
20 728058 728500 884 BHS 6.9
21 730930 731144 428 BHS 6.73
22 731172 731390 436 BHS 8.5
23 732200 732358 316 BHS 5.9
24 732368 732388 40 BHS 7.3
25 732395 732675 560 BHS 6.5
26 736200 736403 406 BHS 7.57
27 736417 736620 406 BHS 8.3
Total Length 12054
At AUP locations
Sl no From To Length(m) Side AvgHt (M)
1 701900 702146 492.00 BHS 9.50
2 703474 703800 652.00 BHS 7.77
Total length(km) 1144
For ROB :
Sl no From To Length(m) Side Avg Ht (M)
1 701495 701900 810.00 BHS 11.17
2 723280 723920 1280.00 BHS 8.63
3 724130 724760 1260.00 BHS 9.10
4 738068 738531 926.00 BHS 11.57
5 738699 738970 542.00 BHS 10.43
Length 4898
2m Height
Side
Sl. From To Length(m)
No.
1 735570 735600 60 Both Sides
Total Length= 60
Deducting CD Length= 24
Net Length= 36
2m Height
Chainage
SL No. Length(m) Side
From To
1 706450 706535 85 LHS
Sr. No. Design Well Dimension Well Depth Filling Slab on Top Remarks
Chainage Material for of Well
Well Yes/No
Nil
13 Shifting of Utilities
Shifting of obstructing existing utilities indicated in Schedule A to an appropriate location in
accordance with the standards and specifications of concerned Utility Owning Department is part
of the scope of work of the Contractor/Concessionaire. The bidders may visit the site and assess
the quantum of shifting of utilities for the project before submission of their bid. Copy of utility
relocation plan is enclosed. The specifications of concerned Utility Owning Department shall be
applicable and followed.
Note I:
No change of scope shall be admissible and no cost shall be paid for using different type/spacing/
size/specifications in shifted work in comparison to those in the existing work or for making any
overhead crossings to underground as per requirement of Utility Owning Department and/or
construction of Contractor/Concessionaire project highway. The contractor/concessionaire shall
carry out joint inspection with Utility Owning Department and get the estimates from Utility
Owning Department. The assistance of the Authority is limited to giving forwarding letter on the
proposal of contractor/concessionaire to Utility Owning Department whenever asked by the
Contractor/Concessionaire*. The decision/ approval of Utility owning Department shall be binding
on the Contractor/Concessionaire*
b). The supervision charges at the rates/charges applicable of the Utility Owning Department
shall be paid directly by the Authority to the Utility owning Department as and when
Contractor/Concessionaire* furnishes demand of Utility Owning Department along with a copy of
estimated cost given by the latter.
c). The dismantled material /scrap of existing Utility to be shifted/ dismantled shall belong to
the Contractor/Concessionaire* who would be free to dispose-off the dismantled material as
deemed fit by them unless the Contractor/Concessionaire is required to deposit the dismantled
material to Utility Owning Department as per the norms and practice and, in that case the amount
of credit for dismantled material may be availed by the Contractor/Concessionaire* as per the
estimate agreed between them.
d). The utilities shall be handed over after shifting work is completed to Utility Owning
Department to their entire satisfaction. The maintenance liability shall rest with the Utility
Owning Department after handing over process is complete as far as utility shifting works are
concerned.
14 Work Zone Traffic Management Plans Annexure-ii Schedule B- Typical Cross Sections
The traffic diversion plans shall be prepared as per IRC SP 55 for smooth flow of traffic and safety.
A diversion plan shall be proposed for construction of Culvert, Grade Separated Structures,
Bridges, RoB/RUB, etc. and traffic management plan for widening/ reconstruction of
carriageway.