Technical Data Sheet

EPICON HB-300

Standard Paint specifications of "Handbook for corrosion protection of steel road bridges", March 2014, by Japan Road Association

Type of paint High-build epoxy resin paint


Characteristics 1) Good durability.
2) High build type and good workability.
3) Good adhesion property and physical property to shock resistance.

Paint properties Mixing ratio : Base : Hardener = 85 : 15 by weight


Base : Hardener = 75 : 25 by volume
Color : N-7.0, N-8.5
Density : 1.54 ± 0.05 g/mL
by Roller, brush by Airless spray
Coverage : 500 g/㎡ X 2 1100 g/㎡
0.325 L/㎡ X 2 0.714 L/㎡
Dry Film Thickness : DFT : 150 μm X 2 DFT : 300 μm
Wet Film Thickness : WFT : 215 μm X 2 WFT : 430 μm

Drying time : Temp. 5℃ 10 ℃ 20 ℃ 30 ℃


Set-to-touch 3 hrs. 2.5 hrs. 1.5 hrs. 1 hr.
Tack free 20 hrs. 15 hrs. 8 hrs. 6 hrs.
Pot life (20℃) 3 hrs.
Painting interval (min) (20℃) 1 day
Painting interval (max) (20℃) 10 days

Painting conditions Weather conditions : Atomospheric temperature : Minimum 5 ℃


Relative humidity : Maximum 85 %
Painting method : Roller, Burush, Airless spray
For airless spray : Tip No. : Graco 623 - 723
Paint output pressure : 14.7 - 17.7 MPa (150 - 180 kgf/c㎡)
Spray gun speed : 60 - 80 cm/sec.
Thinner : EPOXY THINNER A
CHUGOKU THINNER CMP-31
Thinning ratio : For roller / brush : Maximum 10% by weight
For airless spray : Maximum 20% by weight
Surface preparation The surface to be painted shall be clean (free from rust, dust, oil and other foreign materials) and dry.
The surface temperature shall be higher than 3 ℃ or more against the due point.

Packing style 20L set

Shelf life Base : 12 months from production date


Hardener : 12 months from production date
Note 1) Please refer to Safety Data Sheet (SDS) for the further information.
2) Fire shall be noted. Ventilation shall be maintained during painting and drying time until full cured.
3) Base and Hardener shall be mixed in according to the above mixing ratio. Firstly, Base shall be stirred until
becoming uniform. Secondly, Hardener is added. The mixed paint shall be stirred until the both of Base and
Hardener become uniform. After then, Thinner is added and stirred until the mixed paint become uniform.
4) It is recommended to be diluted by thinner as less as possible in order to get the sufficient DFT.
5) It is recommended to mix the necessary quantity because of pot life.
6) In case of the painting interval to be exceeded, all the surface to be painted shall be cleaned and roughened by
sand paper.

7) Coverage indicaed is based on "Handbook for corrosion protection of steel road bridges", March 2014, by Japan Road Association.

8) This data sheet contains the best and latest of our knowledge according to the "Handbook for corrosion protection of steel road bridges"
,March 2014, by Japan Road Association, and subject to change witout notice.