Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

MEP - NCR 03 - Done

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 7

Project: Design and Build construction of G+3

Labor accommodation, kitchen & NON - CONFORMANCE REPORT


Dining
Facility in Al Hamra Industrial zone.
Contract: NCR Ref. No: RAK-OCC-NCR-MEP-03
Contract Ref No: Date: 06 June 2024 Rev: 00

Consultant: HOME OF ARCHITECTURE Discipline: ☐ Architectural ☐Structural


Contractor: ORION CONTRACTING COMPANY ☒ Mechanical ☒ Electrical
☐ HSE
SECTION A – NON-CONFORMANCE

Title / Subject: Non-Standard MEP Works

Cluster / Unit No: ACCOMMODATION BUILDING Subcontractor:


Spec / DWG Ref:
We have observed during site inspection that the poor installation of MEP Works as listed below:

1) 90˚ Tee in Rainwater Pipe at 3rd Floor High Level is prohibited - High Risk (Picture Enclosed)
2) Offset Fitting in FCU’s is not accepted due Pressure Drop issue. Technical Not Accepted (Picture Enclosed)
3) Sanitary Ware Installation without MIR Approval
4) Sanitary Ware Installed without completing H/L Plumbing Works
5) Plaster done Over G.I Ducts & there is no Wooden Boxes for this G.I Duct (Picture Enclosed)

Kindly rectify the works immediately

Attachments: ☒Digital Photos ☐Other: Required Response Date: 06/06/2024


Issued by Client’s Received by Contractor:
Rep Name: Mohd
Taj Signature: Date and Signature:

SECTION B – CONTRACTOR’S DISPOSITION

Corrective Action / Cause / Preventative Measures: Proposed Action Taken ()

1) A waterproof test was conducted by the civil team, and the surface was filled with water, which was
drained through the rainwater system without any issues. A test for rainwater was also conducted.
Completion Status: Work completed
2) This issue is not within our scope of work
Completion Status: N/A
3) Sanitary supply and installation are not within our scope of work
Completion Status: N/A
4) Due to the project's fast paced nature, we carried out all the activities in parallel. We shall provide
the necessary protection for the installed sanitary ware while completing the high-level works.
Completion Status: Completed
5) This issue is not within our scope of work
Completion Status: N/A

Attachments:
NCR – Non-Conformance Report Form –Rev 0 Page 1 of 7
For Contractor: Received by Consultant:

Date and Signature: Date and Signature:


SECTION C – ACCEPTANCE

Disposition: Approved Approved as Noted Not Approved


Consultant’s Comments:

Status: Open/Closed

Consultant’s Rep Signature: Date:

SECTION D – VERIFICATION / NCR CLOSED OUT SATISFACTORILY

Resident Engineer Signature: Date:

NCR – Non-Conformance Report Form –Rev 0 Page 2 of 7


Project Manager Signature: Date:
Distribution
To: Contractor Copies to: Project Record / Employer /Engineer

NCR – Non-Conformance Report Form –Rev 0 Page 3 of 7


NCR – Non-Conformance Report Form –Rev 0 Page 4 of 7
raKez
RAS A L KHAIMAH
ECONOMIC Z O N E
HOME OF ARCHITECTURE
FOR ENGINEERING CONSULTANTS □
-

NCR – Non-Conformance Report Form –Rev 0 Page 5 of 7


raKez
RAS AL KHAIMAH
ECONOMIC ZONE
HOME OF ARCHITECTURE
FOR ENGINEERING CONSULTANTS □
-

NCR – Non-Conformance Report Form –Rev 0 Page 6 of 7


NCR – Non-Conformance Report Form –Rev 0 Page 7 of 7

You might also like