Hemp 3116 Operations Research
Hemp 3116 Operations Research
Hemp 3116 Operations Research
The modal :
Maximize Z=30 x1 +20 x 2
Subject 2 x1 + x 2≤100
x 1 + x 2 ≤80
x 1≤40
x 1 , x2 ≥0
(a) If x 1 and x 2 are the number of the boxes produced, use simplex method
to find optimal product mix. What is the optimal value of Z? [10
marks]
(b) If the right hand side value of the first inequality is subjected to change,
compute the feasible range. [5 marks]
(c) Explain the following terms in LPP.
(i) Duality
(ii) Sensitivity analysis [5 marks]
W1 W2
A $14 $11
B $9 #12
C $9 $10
(a) Find the transportation schedule that will minimize the cost by using
north west corner point. [10 marks]
(b) What is the minimum cost that can be used to transport the fertilizer ?
[4 marks]
(c) Explain the term ‘degeneracy’ within the context of transportation
modeling [6 marks]
Activity A B C D E F G H I J
Immediate B - A C A D H A F,G,J H,E
Predecessor
Expected 5 3 2 3 4 8 5 2 2 3
time (days)
(a) Draw an activity on node (AON) network for this project [4 marks]
(b) For each activity compute the earliest start time, earliest finish time
[4 marks]
(c) For each activity compute the latest start time an latest finish time
[4 marks]
(d) For each activity compute the slack time. [2 marks]
(e) Identify the critical path. [2 marks]
(f) Give one advantage lf knowing the slack time of an activity. [2 marks]
(g) What is the project completion time? [2 marks]
(i) how much should the company order at one time given that it
purchases cement at Tzs 600 000/= per tone.
(ii) What is the cycle time?
Assume the company wants to minimize inventory cost [8 marks]
(c) What are the assumptions of the eoq MODEL? [4 marks]
[10 marks]
(b) Discuss two uses of such shortest path problems given in (a) [5 marks]
(c) What is project crashing? [5 marks]
Construction site
Cranes 1 2 3 4
A 90 75 75 80
B 35 85 55 65
C 125 95 90 105
B 45 110 95 115
Find the assignment of the cranes which minimizes distance travelled which
implies minimal cost. [15 marks]