Geotechnical Design of Large Openings Fo
Geotechnical Design of Large Openings Fo
Geotechnical Design of Large Openings Fo
ABSTRACT: The paper summarizes the methodological approach considered for the geotechnical
design of large underground openings, with particular reference to the authors´ experiences on a
number of projects developed for mining operations in Chile. The stepwise design approach includes
the geotechnical model, the assessments of the stress field, relevant boundary conditions, the analysis
of the rock mass behavior and the ground-support interaction, additionally addressing the
construction baseline scheme and some significant aspects associated to the construction stage. Two
case histories of large underground facilities developed for the mining sector in Chile, where this
methodology has been implicitly applied and proven adequate, are presented to illustrate typical
challenges and conditions faced by the design and construction of these types of underground
structures.
1 INTRODUCTION
Figure 1. Geotechnical Design Methodology applied for Large Openings (Gomes A., 2013).
dynamic/seismicity loads, groundwater and mentioned previously (see Table 1). Similarly,
presence of minerals) and assessed for the the degree of utilization of the support elements
preliminary geometrical layout and proposed are checked in terms of load, energy absorption
excavation sequence and support. Typically, and deformation for each analyzed scenario is
simplified analytical and empirical methods, assessed, to check for compliance with the
together with elastic tridimensional numerical required structural safety factors.
analysis (B.E.M.) are carried out for an earlier The process is interactive, allowing an
assessment of the ground response to optimization of the initially proposed excavation
unsupported excavation. Depending on the sequence and support.
results obtained, a first optimization and
adjustment of the general opening(s) layout can
be carried out, before more complexes 2.6 Construction Baseline Scheme
numerical analyses are carried out to obtain a The previous design stages allow the
more detailed assessment of the ground establishment of a construction baseline scheme
behavior (e.g. discontinuous modelling). and associated compensation clauses, where
Results obtained from the analyses are specific excavation sequences and support
compared with predefined failure and stability measures are defined and specified. Since
evaluation criteria, such as those shown in the geotechnical analyses are intrinsically affected
following Table 1. by uncertainty - both in terms of input data and
inherently limitations of engineering tools – the
Table 1. Examples of Stability Evaluation Criteria. design shall ideally be treated in probabilistic
Parameter Variables terms and be properly expressed in the
Stress concentration σ1 / UCS contractual documents to allow for flexibility
Shear failure potential (σ1 – σ3) and an adequate risk management during the
Deformation of roof and walls δV/B; δV/H construction stage. A risk management plan
Relaxation or tensile stresses (σ3) shall be outlined, identifying all possible
Critical level of strains (ε3)
Mohr-Coulomb failure criteria f(σ1, σ3)
geotechnical and natural risks, deviations and
Hoek-Brown failure criteria f(σ1, σ3) critical aspects that can negatively affect the
* Acceptable levels may vary in function of the construction. Those risks shall be controlled
ground composition, presence of nearby openings, during the construction, supported by a
functional requirements, etc. continuous mapping and monitoring of the
actual ground and support behavior
(observational approach), as an inherent part of
2.5.3 Ground-Support Interaction the design process.
The preliminary excavation sequence and
support systems, including opportunity of
installation of temporary and permanent 3 CONSTRUCTION ASPECTS
support, are considered for the analyses of the
ground-support interaction (system behavior) Even though constructability aspects are largely
for different combinations of ground quality defined in the earlier design stages, a detailed
(range of expected key parameters’ variation). analysis of existing interferences, ventilation
Numerical modelling can be either continuous requirements, effective working time,
or discontinuous, iso- or anisotropic, based on transportation of muck and personnel, HSEC
various available methods (e.g. F.E.M., F.D.M., issues, accreditation time, among other relevant
D.E.M.) and with application of different factors, shall also be carried out by the
constitutive models and failure criteria (e.g. contractor in close cooperation with the client
Hoek-Brown, Mohr-Coulomb, etc.). The most (Mine owner), as to reach a realistic cost and
suitable methods are chosen in function of the time estimation. The construction baseline
rock mass composition and the type of failure scheme shall be revised and made its own by the
mechanism to be analyzed (e.g. squeezing, Contractor, which shall plan in detail how the
brittle failure, structurally controlled failure, design will be properly developed on site to
creep, etc.). fulfill the expected contractual performance
Results are compared to pre-specified (e.g. time, costs, quality, safety, etc.). This is a
acceptance criteria for the rock mass, as main issue, particularly considering the fact that
the mine is permanently in operation, with its
4
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
own working schedules and agenda, which must against rock falling). Cement or chemical pre-
be catered for by the contractor. The grouting or ground treatment can be locally
construction shall be followed by an required to improve the ground or to control
engineering supervision, which shall make the water inflow in weak zones.
necessary design adjustments in function of the Another major construction issue is the
effective ground conditions and behavior. adequate control of the blasting damage and
Caverns and large openings are typically over-breaks and the avoidance of geometric
excavated with the use of Drill and Blast deviations, particularly as the openings are
methods. Road headers can be also be applied in typically excavated simultaneously from
weaker and less abrasive rock masses, also to different headings and a final irregular geometry
avoid blasting vibration acting on nearby can negatively affect the opening stability,
structures. However, to the author´s knowledge, increasing the need of maintenance or even
there is no record of use of road-headers for generating the need of major repair works.
cavern excavation in Chile.
Excavation works usually starts from the
access tunnels, which shall reach the top of the 4 CASE HISTORIES
caverns, allowing the excavation of a central
pilot tunnel, which is further enlarged to
4.1 Andina Mine – PDA Phase I - Caverns
materialize the cavern roof. Whereas the roof
geometry and structural function requires a for Operational Facilities
more careful excavation sequence, benches The Andina Mine of Codelco, which has both
(walls) can generally be excavated more surface and underground mining operations, is
massively with consideration of larger located at an elevation of 3.000m, at the Andes
excavation blocks and rounds (except in poor Cordillera, in a zone with abrupt geography,
rock conditions). high altitude and adverse climate. For these
conditions, the underground installation of the
operational facilities is a natural and efficient
solution.
The Project PDA Phase I comprises the
expansion of the mining production from 25k to
60k tons/day with the construction of new major
underground structures (~200.000 m3 of
excavations) for housing of operational
facilities, such as crush and milling chambers,
copper concentrate flotation systems, ore chutes,
electrical rooms, among other facilities, in
Figure 3. Example of Excavation Sequence (ACT, 2008) addition to the already existing infra-structure.
The typical ground support system is
customarily constituted by shotcrete, plain or
reinforced with wire mesh or fibers, grouted
bolts and cables and ground anchors in
particular cases. Longer cables have the
advantage that they can be more easily installed
in limited headroom conditions and therefore
are frequently used as long term rock support,
whereas shorter bolts can be used for advance
purposes (temporary support). In some cases, a
permanent inner in situ concrete lining is
provided, depending on the usage and functional
requirements of the opening (e.g. vertical ore Figure 4. View of Main Underground works – PDA Phase
1 – Andina Mine
chutes). On the other end, there can be cases of
openings constructed without provision of
linings, and supported only with bolts and These large openings were located at close
cables and light wire meshes in walls (to protect vicinity to each other and to the existing
5
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
facilities, being excavated in fair quality adits, built specifically for the new facilities, as
Granodiorite (RMR 55 to 58) with the presence well as through the existing underground
of some localized major structures (faults). The tunnels and structures. The remote site location,
openings were located within one of the valley the limited working space and restrictions
slopes, away from the ore extraction sectors, so imposed by the mine operation required a strict
that rock cover varied from about 80m to a coordination of works between contractor and
minimum of about 50m due to the natural slope. the mine, logistic for access, transport of muck,
The caverns presented vertical walls and curved ventilation, etc.
roofs, generally with large span and height (e.g. The construction was followed by monitoring
milling cavern with 28mx37x58m). Chutes were and continuous mapping of geological
cylindrical-shaped with an inner diameter of up conditions. Particular attention was given to the
to 23m and heights of up to 30m. structural conditions, which in some areas
For this case, the geo-structural conditions of showed the presence of major structures (faults)
the rock were a key issue, so that the analyses with loose infilling and water inflow, which
were carried out with both continuous and required special excavation methodology and
discontinuous 3D numerical modelling (to ground treatments. These facilities’
verify the effect of major structural systems). constructions finished and they are operational
The detail design also included wedge stability since December 2010.
analysis and analysis of the ground-support
behavior with specific 2D and 3D models.
Analyses results showed that compressive stress
concentrations were of minor significance, so
that the greatest challenges corresponded to the
reinforcement of zones with relevant ground
relaxation and tensile stresses, and zones with
the presence of major faults and dikes.
Figure 6. Excavation of Crusher Chamber at PDA Phase 1
(photo by Aura/Compax/Tecsa JV, 2006)
large openings for crush chambers and material Pardo, 2006). Besides, in some cases, these
handling system are also located at the openings could also be affected by the stress
perimeter of some productive sectors´ footprint redistribution caused by the mining activity (e.g.
(mining polygon), within the so-called mafic abutment stresses due to the rock caving
complex (denominated CMET) and constituted process)
by diabases, porphyric basalts and gabbros, with
strong alteration and multi-directional
stockwork (previously classified as Andesite
primary rock), being also crossed by some
intrusions and dikes. The mentioned openings
are built in depths that go in excess of 1000m in
certain cases, i.e., under the effect of high stress Cavern
conditions.