G.R. No. 71998-99
G.R. No. 71998-99
G.R. No. 71998-99
71998-99
Constitution Statutes Executive Issuances Judicial Issuances Other Issuances Jurisprudence International Legal Resources AUSL Exclusive
THIRD DIVISION
EMILIANO R. DE LOS SANTOS, SPOUSES NORMA A. PADILLA and ISIDORO L. PADILLA and the HEIRS OF
FRANCISCO DAYRIT, petitioners,
vs.
THE HON. INTERMEDIATE APPELLATE COURT, HON. JUDGE CICERRO C. JURADO and EDILBERTO
CADIENTE, respondents.
ROMERO, J.:
Questioned in the instant petition for review on certiorari is the Decision of the then Intermediate Appellate Court1
affirming the December 1, 1982 order of the then Court of First Instance of Rizal, Branch XXII at Pasig2 in civil
Cases Nos. 46800 which states in toto:
It appearing that the construction of the road and creek in question was a project undertaken under the
authority of the Minister of Public Works, the funding of which was the responsibility of the National
Government and that the defendants impleaded herein are Edilberto Cadiente and Nestor Agustin and
not the Republic of the Philippines which cannot be sued without its consent, this court hereby resolves
to dismiss these two (2) cases without pronouncement as to costs.
SO ORDERED.
Civil Cases Nos. 46800 and 46801 were both filed on July 13, 1982 by petitioners who are co-owners under TCT
No. 329945 of a parcel of land located in Barrio Wawa, Binangonan, Rizal with an area of nineteen thousand sixty-
one (19,061) square meters. In Civil Case No. 46800, petitioners alleged in the petition for prohibition that in
October 1981, without their knowledge or consent, Lorenzo Cadiente, a private contractor and the Provincial
Engineer of Rizal constructed a road nine (9) meters wide and one hundred twenty-eight meters and seventy
centimeters (128.70) long occupying a total area of one thousand one hundred sixty-five (1,165) square meters of
their land.
Petitioners added that aside from the road, the said respondents also constructed, without their knowledge and
consent, an artificial creek twenty three meters and twenty centimeters (23.20) wide and one hundred twenty-eight
meters and sixty-nine centimeters long (128.69) occupying an area of two thousand nine hundred six (2,906) square
meters of their property. Constructed in a zig-zag manner, the creek meandered through their property.
Alleging that it completed, the road and the creek would "serve no public profitable and practicable purpose but for
respondents' personal profit, to the great damage and prejudice of the taxpayers and the petitioners," the same
petitioners invoked their rights under Art. IV Secs. 1 and 2, of the Bill of Rights of the 1973 Constitution and prayed
for the issuance of restraining order or a writ of preliminary injunction to stop the construction. They also prayed that
after hearing on the merits, judgment be rendered: (1) declaring illegal the construction of the road and artificial
creek which was made without their knowledge and consent, "without due process and without just compensation
and in violation of the provision of statute law and of the Philippine Constitution;" (2) issuing a permanent prohibition;
(3) ordering respondents to pay petitioners "jointly and collectively" P15,00.00 as attorney's fees and P600.00 for
each appearance, and (4) ordering the respondents to pay the costs of the suit.3
https://lawphil.net/judjuris/juri1993/jun1993/gr_71998_99_1993.html 1/4
9/30/24, 9:54 AM G.R. No. 71998-99
An action for damages, Civil Case No. 46801 on the other hand, was founded on Art. 32, paragraphs 6 and 7 of the
Civil Code and the constitutional provisions on the right against deprivation of property without due process of law
and without just compensation.
Thereafter, the two cases were consolidated. On November 11, 1982, the Solicitor General filed a motion to dismiss
both cases on the following grounds: (a) with respect to Civil Case No. 46800, the pendency of Civil Case No.
46801 which involved the same parties and cause of action; (b) both cases were in reality suits against the state
which could not be maintained without the State's consent; and (c) lack of cause of action.
Consequently, the lower court issued the aforequoted Order of December 1, 1982. Their motion for the
reconsideration of said Order having been denied, petitioners elevated (to) the cases to this Court through an
"appeal by certiorari" which was docketed as G. R. No. 63610. The Second Division of this Court, however, referred
the cases to the then Intermediate Appellate Court pursuant to Sec. 16 of the Interim Rules.4 In due course, the
Appellate court rendered a Decision on May 22, 1985 which disposed of the cases thus:
Accordingly, the two actions cannot be maintained. They are in reality suits against the state which has
not given its consent to be sued (Minister [sic] vs. CFI, 40 SCRA 464; Isberto vs. Raquiza, 67 SCRA
116; Begosa v. Chairman, PVA, 32 SCRA 466). Appellants' remedy lies elsewhere.
Appellants assert that the taking of their property in the manner alleged in these two cases was without
due process of law. This is not correct. The appealed order has not closed the door to appellants right,
if any, to just compensation for the alleged area of their land which was expropriated. The court below
dismissed the cases for lack of consent on the part of the state to be sued herein. We repeat
appellants' remedy for just compensation lies elsewhere.
WHEREFORE, the order appealed from is in full accord with the evidence and the law and is hereby
therefore affirmed in all its parts. Costs against appellants.
SO ORDERED.5
Consequently, petitioners elevated the cases to this Court through a petition for review on certiorari. The petition is
anchored on the ruling of the Court in Amigable v. Cuenca6 which states: ". . . . where the government takes away
property from a private landowner for public use without going through the legal process of expropriation or
negotiated sale," a suit may properly be maintained against the government.
That the principle of state immunity from suit cannot be invoked to defeat petitioners' claim has long been settled. In
Ministerio v. Court of First Instance of Cebu,7 the Court held:
. . . . The doctrine of governmental immunity from suit cannot serve as an instrument for perpetrating
an injustice on a citizen. Had the government followed the procedure indicated by the governing law at
the time, a complaint would have been filed by it, and only upon payment of the compensation fixed by
the judgment, or after tender to the party entitled to such payment of the amount fixed, may it "have the
right to enter in and upon the land so condemned" to appropriate the same to the public use defined in
the judgment. If there were an observance of procedural regularity, petitioners would not be in the said
plaint they are now. It is unthinkable then that precisely because there was a failure to abide by what
the law requires, the government would stand to benefit. It just as important, if not more so, that there
be fidelity to legal norms on the part of the officialdom if the rule of law were to be maintained. It is not
too much to say that when the government takes any property for public use, which is conditioned upon
the payment of just compensation, to be judicially ascertained, it makes manifest that it submits to the
jurisdiction of a court. There is no thought then that the doctrine of immunity from suit could still be
appropriately invoked.
We find the facts of the Ministerio case on all fours with the instant cases insofar as the fact that the respondent
government officials executed a shortcut in appropriating petitioners' property for public use is concerned. As in the
Amigable case, no expropriation proceedings were initiated before construction of the projects began. In like
manner, nowhere in his pleadings in the cases at bar does the Solicitor General mention that the fact that
expropriation proceedings had in fact been undertaken before the road and artificial creek were constructed. Thus,
quoting the answer of the defendants in Civil Case No. 46801, the Solicitor General summarized the facts which
defendants considered as constituting justification for the construction as follows:
10. The construction of the road and creek in question on the property which at the time was said to be
public property, was initiated, and construction effected, through the usual and ordinary course, as
shown by the following:
https://lawphil.net/judjuris/juri1993/jun1993/gr_71998_99_1993.html 2/4
9/30/24, 9:54 AM G.R. No. 71998-99
a. November 5, 1979 — Engr. Data who was the incumbent District Engineer submitted
(thru channels) plans, program of works and detailed estimates for approval of higher
authorities, thru the initiation of Mayor Ynares and Assemblyman Gilberto Duavit;
b. February 18, 1980 — Regional Director Eduardo L. Lagunilla, MPW Region IV, EDSA,
Quezon City endorsed said request to the Minister of Public Works;.
c. February 13, 1981 — Assemblyman Gilberto Duavit sent a hand-written follow-up note
regarding the project;
d. June 17, 1981 — The undersigned defendant Nestor Agustin was designated Chief
Civil Engineer of the Rizal Engineer District, Vice Engr. Cresencio Data who reached his
compulsory retirement age;
e. September 23, 1981 — Funds in the amount of P588,000.00 was released for partial
implementation of the project. The total amount requested was P1,200,000. 00;
f. October 19, 1981 — The undersigned submitted a request to the MPWH Central Office
seeking authority to effect implementation of the project;
g. October 29, 1981 — The Regional Director approved the plans and program of works
for the project in the amount of P588,000.00;
h. November 11, 1981 — The Honorable Minister Jesus S. Hipolito granted the request to
undertake the implementation of the project;
k. November 23, 1982 — P249,000.00 was released for improvement (deepening and
diverting of flow) of Binangonan River which was a complimentary structure of
Binangonan port system;
l. April 9, 1982 — Implementation was started. Contract for this project was approved by
the Regional Director in favor of EDILBERTO CADIENTE CONSTRUCTION;
m. May 21, 1982 — Deepening slightly of the adjacent portion of the rock bulkhead was
completed.
The construction of the roadway and deepening of the creek was designated to generate for the
municipality of Binangonan, Rizal more benefits in the form of substantial revenue from fishing industry,
parking area, market rentals, development site, and road system improvements. The area covered by
said public improvements is part of the Laguna Lake area which is submerged in water even during dry
season. The municipal mayor of Binangonan, Rizal stated that said area is public property.8
Public respondents' belief that the property involved is public, even if buttressed by statements of other public
officials, is no reason for the unjust taking of petitioners' property. As TCT No. 329945 shows, the property was
registered under the Torrens system in the names of "Emiliano R. de los Santos, married to Corazon Dayrit; and
Norma Alabastro, married to Isidro L. Padilla" as early as March 29, 1971. Had the public respondents, including the
other officials involved in the construction, performed their functions by exercising even the ordinary diligence
expected of them as public officials, they would not have failed to note that the property is a private one. A public
infrastructure losses its laudability if, in the process of undertaking it, private rights are disregarded. In this
connection, the Court said in Republic v. Sandiganbayan:9
It can hardly be doubted that in exercising the right of eminent domain, the State exercises its jus
imperii, as distinguished from its proprietary rights of jus gestionis. Yet, even in that area, it has been
held that where private property has been taken in expropriation without just compensation being paid,
the defense of immunity from suit cannot be set up by the State against an action for payment by the
owner.
Public respondents' assertion that the project had been completed on May 21, 1982 meets strong opposition from
the petitioners who insist that the project "until now is not yet finished."10 This factual issue needs determination
which only the trial court can undertake. Thus, the need for a full blown trial on the merits. We do not subscribe to
the appellate court's suggestion that the remedy of the petitioners "lies elsewhere."
https://lawphil.net/judjuris/juri1993/jun1993/gr_71998_99_1993.html 3/4
9/30/24, 9:54 AM G.R. No. 71998-99
The filing of another case to determine just compensation is superfluous. The issue may be threshed out below for
practical reasons in the event that it is shown later that it is no longer possible to prohibit the public respondents
from continuing with the public work. As held in the Amigable case, damages may be awarded the petitioners in the
form of legal interest on the price of the land to be reckoned from the time of the unlawful taking.
WHEREFORE, the petition is hereby GRANTED and Civil Cases Nos. 46800 and 46801 shall be REMANDED to
the lower court for trial on the merits after the Republic of the Philippines shall have been impleaded as defendant in
both cases.
# Footnotes
1 Associate Justice Porfirio V. Sison, ponente, Associate Justices Abdulwahid A. Bidin and Marcelino R.
Veloso, concurring.
4 Rollo, p. 19.
5 Rollo, p. 22.
8 Comment of Public Respondents, pp. 3-5, quoting the Motion to Dismiss, pp. 4-5, which in turn lifted
the answer in Civil Case No. 46801 of Nestor Agustin, represented by then Solicitor General Estelito P.
Mendoza, Assistant Solicitor General Ruben E. Agpalo and Solicitor Gloria Fermo-Berin, pp. 3-4 (Rollo,
pp. 42-44).
https://lawphil.net/judjuris/juri1993/jun1993/gr_71998_99_1993.html 4/4