Project Schedule

Uploaded by

thejohnnyvins
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
15 views

Project Schedule

Uploaded by

thejohnnyvins
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

PROJECT SCHEDULE

No. Project Activity Duration (days) Predecessor


0 MOBILIZATION
0.a Set up barricades and signs 1
1 SITE WORK
1.a Clear Lot 1 0.a
1.b Strip Topsoil and Stockpile 1 1.a
1.c Stake Lot for Excavation 1 1.b
1.d Excavate for foundation 2 1.a, 1.c,
2 FOUNDATION, BEAMS, COLUMNS
2.a Layout footings 1 1.d
2.b Dig footings and Install Reinforcing 1 2.a
2.c Footing Inspection 0 2.b
2.d Pour and pin footing, and beams, and dry 3 8.f
2.e Pour basement columns and beams, and dry 3 8.a
2.f Pour 1st floor columns and beams, and dry 3 8.b
2.g Pour 2nd floor columns and beams, and dry 3 8.c
2.h Pour loft columns and beams, and dry 3 8.d
3 FRAMING
3.a Steel delivery 0 2.d
3.b 1st floor deck and wall framing 1 2.e
3.c 2nd floor deck and wall framing 1 2.f
3.d Set and frame roof trusses 1 2.h
3.e Frame basement slab and walls 1 4.a
3.f 1st floor deck columns and beams 1 4.i
3.g 2nd floor deck columns and beams 1 4.k
3.h Loft deck columns 1 4.m
4 CONCRETE SLABS
4.a Basement Slab preparation 1 2.d, 3.a
4.b Termite treatment basement slab 1 3.e
4.c Slab inspection 0 4.b
4.d Pour basement slab 2 4.c, 5.a
4.e Prepare garage slab 1 4.d
4.f Termite treatment garage slab 1 4.e
4.g Pour garage slab 2 4.f
4.h 1st floor deck slab preparation 1 3.b
4.i Pour 1st floor slab 2 4.h
4.j 2nd floor deck slab preparation 1 3.c
4.k Pour 2nd floor slab 2 4.j
4.l Loft slab preparation 1 2.g
4.m Pour loft slab 2 4.l
5 PLUMBING ROUGH-IN
5.a Plumbing sub-slab 1 3.e
5.b Plumbing layout 1 5.a
5.c Plumbing rough-in 1 5.b
5.d Plumbing sub-slab and rough-in inspection 0 5.b, 5.c
6 ELECTRIC ROUGH-IN
6.a Set electric boxes 1 3.e
6.b Install electric service panel 1 3.e
6.c Electrical Walk-through 1 6.a, 6.b
6.d Electrical Rough-wire 1 6.c
6.e Electrical wiring inspection 0 6.c, 6.d
7 MASONRY
7.a Basement CHB Walls 2 4.j
7.b Basement plastering 1 7.a
7.c 1st floor CHB Walls 2 4.l
7.d 1st floor plastering 1 7.c
7.e 2nd floor CHB walls 2 2.h
7.f 2nd floor plastering 1 7.e
8 FORMWORKS AND CARPENTRY
8.a Basement columns 0.25 4.d
8.b 1st floor columns preparation 0.25 3.f
8.c 2nd floor columns preparation 0.25 3.g
8.d Loft floor columns preparation 0.25 3.h
8.e Ceiling works 1 3.d
8.f Footing preparation 0.25 2.c
9 ROOFING
9.a Roofing sheet installed 1 8.e
10 Exterior Finishes (Fences, Patio, Sidewalks, 2 4.g, 9.a
plaster)
11 Floor Finishes (Tiles and Ceramics) 3 12
12 Paint 4 7.b, 7.d, 7.f, 9.a
13 Interior Trim
13.a Install Interior Doors 1 11
13.b Install Cabinetry 1 11
14 PLUMBING TRIM
14.a Set Fixtures 1 5.d, 11,12
14.b Final Plumbing Inspection 0 14.a
15 Exterior Landscaping 1 10
16 ELECTRICAL FINAL TRIM
16.a Switch and plug 1 6.e, 12
16.b Install fixtures 1 12
16.c Final Electrical Inspection 0 16.b
17 HARDWARE
17.a Door hardware 1 13.a
17.b Bath hardware 1 13.a
17.c Mirrors 1 17.b
17.d Shower doors 1 17.b
17.e Final building inspection 0.25 14.b, 15, 16.c, 17.c,
17.d
17.f Use and Occupancy certificate 0.5 17.e
17.g First walk-thru 0.25 17.e
18 FINAL PUNCH-OUT
18.a Punch out walk-thru list 0.25 17.g
18.b Trim and Adjust Doors 0.5 17.e, 18.a
18.c Paint Touch-up 1 18.b
19 CLEANING
19.a Rough Clean 1 18.b
19.b Final Clean 1 19.a
20 Final Walk-Through 1 19.b
21 Move-In 1 20