C.10 Parapet
D. Block Work
100 thick hollow block work (Ground
D.1 floor)
150 thick hollow block work (Ground
D.2 floor)
200 thick hollow block work (Ground
D.3 floor)
200 thick solid block work (Ground
D.4 floor)
200 thick block work “Thermal
D.5 insulated” (Ground floor)
TOTAL OF D
E. Plaster works
F. External finishes
F.1 Full Epoxy system
F.2 Granite
G. Floor finishes
G.1 Graniti tile (B.C Dhs)
H. Skirting
H.1 Terrazzo
H.2 Granite
H.3 Marble
I. Wall finish
I.1 Granite (B.C Dhs/m²)
J. Ceiling finishes
J.1 Emulsion paint
K. External works
K.1 8 cm interlock in two color
K.3 Curbstone
K.5 Garage
ELECTRICAL/ CATV/
O.
INSTALLATION
P. Gas Works
PLUMBING & DRAINAGE
Q.
INSTALLATION
R. A/C Works
S. Other works
S.1 Cupboards for kitchen
S.2 Mirror
S.3 Counters
TOTAL OF S
Any item of work not included in this B.O.Q which is essential for the
satisfactory completion of the project, the Contractor has to add the
same in this list or to be considered elsewhere in their offer
%
1.50%
10%
20%
6%
6%
2%
3%
1%
2%
1.50%
3%
4%
5%
6%
10%
0.50%
7%
0.50%
1%
10%