Midterm Reviewer For Om and TQM
Midterm Reviewer For Om and TQM
Midterm Reviewer For Om and TQM
A project may be defined as a series of related jobs usually directed toward some major output
and requiring a significant period of time to perform.
Project management can be defined as planning, directing, and controlling resources (people,
equipment, material) to meet the technical, cost, and tithe constraints of the project.
Although projects are often thought to be one-time occurrences, the fact is that many projects
can be repeated or transferred to other settings or products. The result will be another project
output. A contractor building houses or a firm producing low-volume products such as
supercomputers, locomotives, or linear accelerators can effectively consider these as projects
10. Organizations that are willing to allow planned, poorly led projects weakened themselves and
endanger employees by wasting precious resources
9. Organizations that are flattering (e.g. through reengineering, downsizing, or rightsizing) will depend on
projects and project leaders to get work done that was once handled by departments.
8. With rare exceptions, project prime movers believe that project meltdowns are the results of weak
project leadership.
7. More than one lumpy project leadership performance can give you a reputation that will repel future
project leadership.
6. Project work is often disguised by the use of the word team: if you find yourself on or leading teams,
you’re probably working with others to complete a project.
5. The abilities that tare required to organize and carry out successful projects will enhance other
aspects of your job
4. Leading successful projects is the best way to prove your promotability to the people who make those
decisions.
3. The best way to promote effective project leadership is to set examples that are so powerful and
positive that others wouldn’t dare do less.
2. Project leaders seldom get better until they know how to do it right.
1. If you’re not getting better, you’re getting worse as you det older.
STRUCTURING PROJECTS
Before the project starts, senior management must decide which of three organizational structures will
be used to the project to the parent firm pure project, functional project, or matrix project.
PURE PROJECT
Tom Peters predicts that most of the world's work will be "brainwork," done in semipermanent networks
of small project-oriented teams, each one an autonomous, entrepreneurial center of opportunity, where
the necessity for speed and flexibility dooms the hierarchical management structures we and our
ancestors grew up with. Thus, out of the three basic project organizational structures, Peters favors the
pure project (nicknamed skunk works) where a self-contained team works full-time on the project
ADVANTAGES
The project manager has full authority over the project
Team members report in one boss.
They do not have to worry about dividing loyalty with a functional area manager
Lines of communication are shortened.
Decisions are made quickly
Team pride, motivation, and commitment are high.
DISADVANTAGES
Duplication of resources. Equipment and people are not shared across projects.
Organizational goals and policies are ignored, as team members are often both physically
and psychologically removed from headquarters
The organization falls behind in its knowledge of new technology due to weakened
functional divisions
Because team members have no functional area home, they worry about life after project,
and project termination is delayed
FUNCTIONAL PROJECT
At the other end of the project organization spectrum is the functional project, housing the project
within a functional division.
ADVANTAGES
A team member can work on several projects.
Technical expertise is maintained within the functional area even if individuals leave the
project or organization.
The functional area is a home after the project is completed. Functional specialists can
advance vertically.
A critical mass of specialized functional-area experts creates synergy solutions to a project's
technical problems.
DISADVANTAGES
Aspects of the project that are not directly related to the functional area get short- changed.
Motivation of team members is often weak.
Needs of the client are secondary and are responded to slowly.
MATRIX PROJECT
The classic specialized organizational form, "the matrix project," attempts to blend properties of
functional and pure project structures. Each project utilizes people from different functional areas. The
project manager (PM) decides what tasks and when they will be performed, but the functional managers
control which people and technologies are used. If the matrix form is chosen, different projects (rows of
the matrix) borrow resources from functional areas (columns). Senior management must then decide
whether a weak, balanced, or strong form of a matrix is to be used. This establishes whether project
managers have little, equal, or more authority than the functional managers with whom they negotiate
for resources.
ADVANTAGES
Communication between functional divisions is enhanced
A project manager is held responsible for successful completion of the project.
Duplication of resources is minimized.
Team members have a functional "home" after project completion, so they are less worried
about life-after-project than if they were a pure project organization.
Policies of the parent organization are followed. This increases support for the project.
DISADVANTAGES
There are two bosses. Often the functional manager will be listened to before the project
manager.
After all, who can promote you or give you a raise? It is doomed to failure unless the PM has
strong negotiating skills
Suboptimization is a danger, as PMs hoard resources for their own project, thus harming other
projects.
Note that regardless of which of the three major organizational forms is used, the proj ect manager is
the primary contact point with the customer. Communication and flexibility are greatly enhanced
because one person is responsible for successful completion of the project.
Exhibit 3.2 shows the WBS for an optical scanner project. The WBS is important in organizing a project
because it breaks the project down into manageable pieces. The number of levels will vary depending on
the project. How much detail or how many levels to use depends on the following:
The level at which a single individual or organization can be assigned responsibility and
accountability for accomplishing the work package.
The level at which budget and cost data will be collected during the project.
NETWORK-PLANNING MODELS
The Critical Path Method (CPM) – was developed for scheduling maintenance shutdowns at chemical
processing plants owned by Du Pont. CPM is based on the assumptions that project activity times can
be estimated accurately and that they do not vary.
– Determining scheduling information about each activity in the project is the major goal of CPM
techniques
The Program Evaluation and Review Technique (PERT) – was developed for the U.S. Navy's Polaris
missile project. PERT was developed to handle uncertain time estimates.
Critical path of activities in a project – is the sequence of activities that form the longest chain in terms
of their time to complete. If any one of the activities in the critical path is delayed, then the entire
project is delayed.
Consider that you have a group assignment that requires a decision on whether you should invest in a
company. Your instructor has suggested that you perform the analysis in the following four steps:
A. Select a company.
B. Obtain the company's annual report and perform a ratio analysis
C. Collect technical stock price data and construct charts
D. Individually review the data and make a team decision on whether to buy the stock.
three-time estimate approach – introduces the ability to consider the probability that a project will be
completed within a particular amount of time. The assumption needed to make this probability estimate
is that the activity duration times are independent random variables if this is true, the central limit
theorem can be used to find the mean and the variance of the sequence of activities that form the
critical path.
central limit theorem – says that the sum of a group of independent, identically distributed random
variables approaches a normal distribution at the number of random variables increases in the case of
project management problems, the random variable is the expected time (ET) for each activity. For this
the expected time to complete the critical path activities is the sum of the activity times.
TIME-COST MODELS – extension of the CPM that consider the trade-off between the time required to
complete an activity and cost. Often referred to as “crashing” the project
The basic assumption in minimum-cost scheduling is that there is a relationship between activity
completion time and the cost of a project. On one hand, it costs money to expedite an activity; on the
other, it costs money to sustain (or lengthen) the project. The costs associated with expediting activities
are termed activity direct costs and add to the project direct cost. Some may be worker-related, such as
overtime work, hiring more workers, and transferring workers from other jobs, others are resource-
related, such as buying or leasing additional or more efficient equipment and drawing on additional
support facilities. The costs associated with sustaining the project are termed project indirect costs
overhead, facilities, and resource opportunity costs, and, under certain contractual situations. penalty
costs or lost incentive payments. Because activity direct costs and project indirect costs are opposing
costs dependent on time, the scheduling problem is essentially one of finding the project duration that
minimizes their sum, or in other words, finding the optimum point in a time-cost trade-off.
The procedure for finding this point consists of the following five steps (further explained in exhibit 3.8).
1. Prepare a CPM-type network diagram. For each activity this diagram should list:
Normal cost (NC): the lowest expected activity costs
Normal time (NT): the time associated with each normal cost.
Crash time (CT): the shortest possible activity time.
Crash cost (CC): the cost associated with each crash time
2. Determine the cost per unit of time (assume days) to expedite each activity. The relationship
between activity time and cost may be shown graphically by plotting CC and CT coordinates and
connecting them to the NC and NT coordinates by a concave, convex, or straight line-or some
other form, depending on the actual cost structure of activity performance.
3. Compute the critical path. For the simple network we have been using, this schedule would take
10 days. The activity that has the long duration is the critical path
4. Shorten the critical path at the least cost. The easiest way to proceed is to stan with the normal
schedule, find the critical path, and reduce the path time by one day using the lowest-cost
activity.
5. Plot project direct, indirect, and total-cost curves and find the minimum-cost schedule.
MANAGING RESOURCES
In addition to scheduling each task, we must assign resources. Modern software quickly highlights
overallocations situations in which allocations exceed resources. To resolve overallocations manually, you
can either add resources or reschedule. Moving a task within its slack can free up resources. Mid to high-
level project management information systems (PMIS) software can resolve overallocations through a
"leveling" feature. You can specify that low-priority tasks should be delayed until higher-priority ones are
complete, or that the project should end before or after the original deadline.
TRACKING PROGRESS
A tracking Gantt chart – superimposes the current schedule onto a baseline plan so deviations are easily
noticed. If you prefer, a spreadsheet view of the same information could be output. Deviations between
planned start/finish and newly scheduled start/finish also appear, and a "slipping filter" can be applied to
highlight or output only those tasks that are scheduled to finish at a later date than the planned
baseline. Management by exception can also be applied to find deviations between budgeted costs and
actual costs
Activities – is a piece of work within a project that consume time. The completion of all the
activities of a project marks the end of the project.
Immediate predecessor – activity that needs to be completed before another activity