As 7
As 7
As 7
CHAPTER 8
CHAPTER
REVENUE BASED
ACCOUNTING
STANDARDS
UNIT 1 : ACCOUNTING STANDARD 7
CONSTRUCTION CONTRACTS
LEARNING OUTCOMES
After studying this unit, you will be able to comprehend the provisions
of AS 7 related with:
♦ Disclosures.
Work in Progress
Final outcome
determined after
Long term Peculiar no. of years from
projects Features of year of
Construction commencement of
construction
contracts
Allocation of contract
revenue and contract cost
tothe accounting period in
which construction work is
performed
The above discussion clearly indicates that there are two parties to the
construction contract. Thus, if there is an entity which requires its engineering
division to construct a machine for the production division, this would not meet
the scope of AS 7. It will be addressed by AS 10 (Property, plant and equipment)
and will be accounted as a case of self-constructed asset.
1.2 INTRODUCTION
Accounting Standard 7 prescribes the principles of accounting for construction
contracts in the financial statements of contractors. The focus of the standard is
to determine when the contractor should recognise contract revenue and contract
costs in the statement of profit and loss.
(a) contracts for the rendering of services which are directly related to the
construction of the asset, for example, those for the services of project
managers and architects; and
(b) contracts for destruction or restoration of assets, and the restoration of the
environment following the demolition of assets.
Contracts specifically
Contracts for
negotiated for the Contracts for
rendering of services
construction of an asset or destruction or
related to
combination of assets that restoration of assets.
construction of assets
are closely interrelated
Example 1
Entity XY contracts with AB to construct 2 residential buildings in the same
premises. The construction of both buildings will begin simultaneously. Building
material, construction work, and other related activities will go on in parallel to
provide cost savings to entity XY. This also helps AB achieve a timely completion of
the two buildings and negotiate a consolidated price for the two buildings.
The above example suggests that there is a single contract negotiated to construct
two buildings that are closely interrelated and interdependent in terms of their
ultimate purpose and use. Therefore, this represents a Construction Contract.
Example 2
H, a sole-proprietor, contracts with M/s DM Construction, to dismantle his office
premises and construct it from scratch.
In the given case, the construction contract includes both demolition as well as
construction of a new building.
(a) When a contract covers a number of assets, the construction of each asset
should be treated as a separate construction contract when:
(ii) each asset has been subject to separate negotiation and the
contractor and customer have been able to accept or reject that part of the
contract relating to each asset; and
(ii) the contracts are so closely interrelated that they are, in effect, part of
a single project with an overall profit margin; and
(c) A contract may provide for the construction of an additional asset at the
option of the customer or may be amended to include the construction of
an additional asset. The construction of the additional asset should be
treated as a separate construction contract when:
(ii) the price of the asset is negotiated without regard to the original
contract price.
Illustration 1
XYZ construction Ltd, a construction company undertakes the construction of an
industrial complex. It has separate proposals raised for each unit to be
constructed in the industrial complex. Since each unit is subject to separate
negotiation, he is able to identify the costs and revenues attributable to each
unit. Should XYZ Ltd, treat construction of each unit as a separate construction
contract according to AS 7?
Solution
As per AS 7 ‘Construction Contracts’, when a contract covers a number of assets,
the construction of each asset should be treated as a separate construction
contract when:
(a) separate proposals have been submitted for each asset;
(b) each asset has been subject to separate negotiation and the contractor and
customer have been able to accept or reject that part of the contract
relating to each asset; and
(c) the costs and revenues of each asset can be identified.
Therefore, XYZ Ltd. is required to treat construction of each unit as a separate
construction contract.
In a fixed price contract, the price is agreed as fixed sum or a fixed rate per unit
of output. In some cases, the contract may require the customer to pay additional
sums to compensate the contractor against cost escalations.
Fixed price contracts are common in case of public tenders (construction of roads,
flyovers, office buildings). Such constructions usually have a budgeted costs and
the public entity does not intend to spend more than the tender amount. At the
same time, there can be various reasons where the cost of construction may
increase. For example, a sudden increase in wage rates, construction material
costs, may require the contractor to add cost-escalation clauses and recover
from the contractee. These cost escalations still meet the category of fixed price
contracts.
A cost-plus contract is a construction contract in which the contractor is
reimbursed for allowable or otherwise defined costs, plus percentage of these
costs or a fixed fee.
Cost-plus contracts are common in case there is uncertainty of measurement of
costs or time of completion. In such cases, a contractor does not expect to bear
the loss due to those uncertainties. For example, if the scope of the contract
cannot be fully assessed in the contract, both parties may agree to cost-plus
contracts.
Under such contracts, the contractor is compensated for the costs incurred by
him plus agreed profit-margin.
∗
Claims are only included in contract revenue when it is probable that the customer will accept the
claim and such claim amount can be measured reliably
∗∗
Incentives are only included in the contract revenue when it is probable that the specified
performance standards will be met or exceeded, and such incentive payment can be measured
reliably)
Contract Revenue
Illustration 2
Solution
Total Revenue after considering the escalation costs, claims and incentives:
`
Fixed Price: 5.00 crore
Incentive for early completion 0.50 crore
Material costs recovery (to the extent of 20%) 0.40 crore
Labour costs recovery (Actual increase is less than 30%) 0.30 crore
[1.20 crore x 25%]
Total Contract Revenue 6.20 crore
Add: Variation to the contract 1.00 crore
Add: Claims recoverable from XY 0.20 crore
Total Contract Revenue 7.40 crore
(B) Contract costs should comprise:
(i) costs that relate directly to the specific contract;
(ii) costs that are attributable to contract activity in general and can be
allocated to the contract; and
(iii) such other costs as are specifically chargeable to the customer under
the terms of the contract.
Contract Costs
NOTE:
1. Examples of costs that relate directly to a specific contract include:
(a) site labour costs, including site supervision
(b) costs of materials used in construction
The outcome of a cost-plus contract can be estimated reliably when all the
following conditions are satisfied:
(i) it is probable that the economic benefits associated with the contract will
flow to the enterprise; and
(ii) the contract costs attributable to the contract, whether or not specifically
reimbursable, can be clearly identified and measured reliably.
Flowchart depicting the conditions under which the outcome of a construction
contract can be reliably estimated:
Also, AS 7 provides that whenever total contract cost is expected to exceed the
total contract revenue, the loss should be recognised as an expense immediately.
We may argue that why would an entity enter into a loss-making contract. It can
happen that after having entered into the construction contract, there is a sudden
rise in the costs which was not expected, nor are these covered under the cost-
escalation clause. Another reason, is that, an entity may enter into a loss-making
contract is to penetrate the market. Therefore, it is not uncommon for companies
to sometimes enter into loss-making contracts.
Under the prudence concept, we must always make a provision for all
expected losses.
Solution
Profit & Loss Account
90 90
20X2-X3 To Construction 89 20X2-X3 By Contract Price 110
costs (55% of Contract
(for 55% work) Price)
To Net Profit 21
(for 55% work)
110 110
Customer’s Account
(a) revenue should be recognised only to the extent of contract costs incurred
of which recovery is probable; and
Illustration 4
PQ & Associates undertakes a construction contract the details of which are
provided below:
Total Contract Value ₹40 lakh
The work has started some time ago and there is an uncertainty with respect to the
outcome of the contract due to expected changes in regulations. PQ is certain that
it would be able to recover the costs incurred to date.
Solution
In the given case, revenue and costs can only be recognised to the extent of the
costs incurred and those which are expected to be recovered. Therefore, the
profit & loss statement would appear as under:
When the uncertainties that prevented the outcome of the contract being
estimated reliably cease to exist, revenue and expenses associated with the
construction contract should be recognised by the percentage completion
method.
Example 4
X Ltd. commenced a construction contract on 01/04/X1. The contract price agreed was
reimbursable cost plus 10%. The company incurred ₹1,00,000 in 20X1-X2, of which cost
of ₹90,000 is reimbursable. The further non-reimbursable costs to be incurred to
complete the contract are estimated at ₹5,000. The other costs to complete the contract
could not be estimated reliably. The Profit & Loss A/c extract of X Ltd. for 20X1-X2 is
shown below:
Solution
Profit & Loss Account
` 000 ` 000
By Contract Price
To Construction Costs 100 99
(90+9)
To Provision for loss 5 Net loss 6
105 105
This method may be useful in case of contracts where cost is closely monitored by
the contractor. This method could be more commonly used in case of private
contracts to construct office buildings, machinery or equipment.
Actual cost incurred
= ×100
Estimated total cost
Assume that the contract period is 2 years. The contract is 100% completed by
Year 2. Actual costs incurred is the same as total estimated costs to complete
(Cost incurred to date plus estimated cost to complete).
Solution
` `
To Construction costs 390 By Contract Price 360
To Provision for loss 20 By Net Loss 50
410 410
` `
To Construction costs 260 By Contract Price 240
By Reversal of Provision 20
for loss
260 260
1.11 DISCLOSURE
(a) An enterprise should disclose:
Particulars `
Costs incurred xxx
Plus: Recognised profits xxx
Less: Recognised losses xxx
Less: Progress billings xxx
Amount xxx
If above amount is positive- Gross amount due from
customers
If above amount is negative- Gross amount due to
customers
Illustration 6
A firm of contractors obtained a contract for construction of bridges across river
Revathi. The following details are available in the records kept for the year ended
31st March, 20X1.
( ` in lakhs)
Total Contract Price 1,000
Work Certified for the cost incurred 500
Work yet not Certified for the cost incurred 105
Estimated further Cost to Completion 495
Progress Payment Received 400
To be Received 140
The firm seeks your advice and assistance in the presentation of accounts keeping
in view the requirements of AS 7 issued by your institute.
Solution
(a) (` in lakhs)
Amount of foreseeable loss:
Total cost of construction (500 + 105 + 495) 1,100
Less: Total contract price (1,000)
Total foreseeable loss to be recognized as expense 100
According AS 7, when it is probable that total contract costs will exceed total
contract revenue, the expected loss should be recognized as an expense
immediately.
(b) (` in lakhs)
Contract work-in-progress i.e. cost incurred to date
are ₹ 605 lakhs
Work certified 500
Work not certified 105
605
This is 55% (605/1,100 × 100) of total costs of
construction.
(c) Proportion of total contract value recognized as revenue:
` in lakhs
Contract revenue 550
Contract expenses 605
Recognised profits less recognised losses (100)
Progress billings ` (400 + 140) 540
Retentions (billed but not received from contractee) 140
Gross amount due to customers 35
Method of revenue recognition (use of percentage completion method)
Method of determining state of completion (based on proportionate cost
Illustration 7
On 1st December, 20X1, Vishwakarma Construction Co. Ltd. undertook a contract
to construct a building for ` 85 lakhs. On 31st March, 20X2, the company found
that it had already spent ` 64,99,000 on the construction. Prudent estimate of
additional cost for completion was ` 32,01,000. What amount should be recognized
in the statement of profit and loss for the year ended 31st March, 20X2 as per
provisions of Accounting Standard 7 (Revised)?
Solution
`
Cost incurred till 31 March, 20X2
st
64,99,000
Prudent estimate of additional cost for completion 32,01,000
Total cost of construction 97,00,000
Less: Contract price (85,00,000)
Total foreseeable loss 12,00,000
XY Ltd. agrees to construct a building on behalf of its client GH Ltd. on 1st April
20X1. The expected completion time is 3 years. XY Ltd. incurred a cost of ` 30 lakh
up to 31st March 20X2. It is expected that additional costs of ` 90 lakh. Total
contract value is ` 112 lakh. As at 31st March 20X2, XY Ltd. has billed GH Ltd. for
` 42 lakh as per the agreement. Assume that the work is completed to the extent of
75% by the end of Year 2.
1. Revenue to be recognized by XY Ltd. for the year ended 31st March 20X2 is
(a) ` 28 lakh
(b) ` 42 lakh
(c) ` 30 lakh
(d) ` 32 lakh
2. Total expense to be recognised in Year 1 is
(a) ` 30 lakh
(b) ` 120 lakh
(c) ` 38 lakh
(d) ` 36 lakh
3. Revenue to be recognised for year 2 is
(a) ` 84 lakh
(b) ` 42 lakh
(c) ` 56 lakh
(d) ` 28 lakh
Below information relates to Questions 4 – 5
M/s AV has presented the information for Contract No. XY123:
Total contract value ` 370 lakh
Machine used for 3 years for the contract. Original cost of the machine is ` 100
lakh. Expected useful life is 15 years.
Estimated future costs to be incurred to complete the contract: ` 80 lakh.
Loss on contract to be recognised is:
(a) ` 40 lakh
(b) ` 10 lakh
(c) ` 90 lakh
(d) ` 50 lakh
Theory Questions
7. It is argued that profit on construction contracts should not be recognised
until the contract is completed. Please explain whether you believe that this
suggestion would improve the quality of financial reporting for long-term
construction contracts.
8. A contractor has entered into a contract with a municipal body for
construction of a flyover. As per the contract terms, the contractor will receive
an additional ` 2 Crore as incentive if the construction of the flyover were to
be finished within a period of two years from the start of the contract. The
contractor wants to recognize this revenue since in the past he has been able
to meet similar targets very easily.
(Amount ` in lakhs)
Year 1 Year 2 Year 3
Initial Amount for revenue agreed in 9,000 9,000 9,000
contract
Variation in Revenue (+) - 200 200
Contracts costs incurred up to the reporting 2,093 6,168* 8,100**
date
Estimated profit for whole contract 950 1,000 1,000
*Includes ` 100 lakhs for standard materials stored at the site to be used in
year 3 to complete the work.
**Excludes ` 100 lakhs for standard material brought forward from year 2.
The variation in cost and revenue in year 2 has been approved by customer.
11. RT Enterprises has entered into a fixed price contract for construction of a
tower with its customer. Initial tender price agreed is ` 220 crore. At the
start of the contract, it is estimated that total costs to be incurred will be
` 200 crore. At the end of year 1, this estimate stands revised to ` 202
crore. Assume that the construction is expected to be completed in 3 years.
During year 2, the customer has requested for a variation in the contract. As
a result of that, the total contract value will increase by ` 5 crore and the
costs will increase by ` 3 crore.
ANSWERS/SOLUTIONS
MCQ
Theory Questions
7. Usually, construction contracts are long term nature i.e., the contracts are
entered in one accounting period, however, the work performed will flow into
more than one accounting year. If the profit on construction contracts is not
recognised over the construction period, then the costs incurred during the
earlier years of the contract would be recognised without any corresponding
revenue. This will result in losses for initial years followed high profits in future
years.
The current treatment under AS 7 results in matching of revenue and
associated costs as they are recognised during the same period. Also, the
current accounting incorporates the prudence concept as any foreseeable
losses are accounted for immediately.
Therefore, AS 7 results in a fair representation of the underlying financial
substance of the transaction.
8. The contractor’s view is not entirely correct in considering the variation as a
part of contract revenue. There is an argument that he has been able to
complete similar contracts within stipulated time. However, each contract
needs to be assessed in isolation with respect to the specific challenges
associated with the timing and uncertainty in completion.
Accordingly, the contractor needs to validate the assumptions with respect to
the specific contract. Only after that assessment is done, the incentive of ` 2
crore may be included within the contract revenue.
Practical Questions
9. The amounts of revenue, expenses and profit recognized in the statement of
profit and loss in three years are computed below:
(Amount in ` lakhs)
Up to the Recognized Recognized in
reporting in previous current year
date years
Year 1
Revenue (9,000 x 26%) 2,340 - 2,340
Expenses (8,050 x 26%) 2,093 - 2,093
Profit 247 - 247
Year 2
Revenue (9,200 x 74%) 6,808 2,340 4,468
Expenses (8,200 x 74%) 6,068 2,093 3,975
Profit 740 247 493
Year 3
Revenue (9,200 x 100%) 9,200 6,808 2,392
Expenses (8,200 x 100%) 8,200 6,068 2,132
Profit 1,000 740 260
Working Note:
10. Statement showing the amount of profit/loss to be taken to Profit and Loss
Account and additional provision for the foreseeable loss as per AS 7
Cost of Construction ` `
Material used 71,00,000
Labour Charges paid 36,00,000
Add: Outstanding on 31.03.20X2 38,00,000
2,00,000
Hire Charges of Plant 10,00,000
Other Contract cost incurred 15,00,000
Cost incurred upto 31.03.20X2 1,34,00,000
Add: Estimated future cost 33,50,000
Total Estimated cost of construction 1,67,50,000
Degree of completion (1,34,00,000/1,67,50,000 x 100) 80%
Revenue recognized (80% of 1,50,00,000) 1,20,00,000
Total foreseeable loss (1,67,50,000 - 1,50,00,000) 17,50,000
Less: Loss for the current year (1,34,00,000 - 1,20,00,000) 14,00,000
Loss to be provided for 3,50,000
11. (a) Stage of completion = Costs incurred to date / Total estimated costs
Year 1: 52.52 crore / 202 crore = 26%
Year 2: (154.20 crore – 2.50 crore) / 205 crore = 74%
Year 3: 205 crore / 205 crore = 100%
(b) Profit for the year