PROYEK : RUMAH SAKIT MECCA NUSANTARA

LOKASI : Way Tenong, Lampung Barat


PERIHAL : 1. Volume Pas. Batu Kali Dinding Penahan Tanah
2. Volume Pas. Bronjong

1. Volume Batu Kali dan Pasangan Bronjong

A1 A2
No SEGMEN T (M) L (M)
Ba (M) Bb (M) T (M) A (M2) V (M3) D B V (m³)

1 A 6.00 20.83 0.50 2.00 6.00 7.5 156.2 1.00 3.00 62.5
2 B 16.00 43.87 0.80 3.50 16.00 34.4 1509.1 2.75 6.50 784.2
3 C 16.00 24.76 0.80 3.50 16.00 34.4 851.7 2.75 6.50 442.6
4 D 26.00 28.40 1.00 4.50 26.00 71.5 2030.6 4.50 10.50 1341.9
5 E 26.00 36.98 1.00 4.50 26.00 71.5 2644.1 4.50 10.50 1747.3
6 F 26.00 17.30 1.00 4.50 26.00 71.5 1237.0 4.50 10.50 817.4
7 G 16.00 40.98 0.80 3.50 16.00 34.4 1409.7 2.75 6.50 732.5
8 H 14.00 96.74 0.80 3.00 14.00 26.6 2573.3 2.50 5.75 1390.6
9 I 9.00 40.04 0.50 2.50 9.00 13.5 540.5 2.00 3.75 300.3
10 I' 5.00 32.60 0.50 1.75 5.00 5.6 183.4 1.00 3.00 97.8
11 J 9.00 20.33 0.50 2.50 9.00 13.5 274.5 1.50 4.00 122.0
12 K 9.00 33.60 0.50 2.50 9.00 13.5 453.6 1.50 4.00 201.6
13 L 7.00 51.67 0.50 2.00 7.00 8.8 452.1 1.00 3.50 180.8
14 M 2.00 17.36 0.50 1.25 2.00 1.8 30.4 0.00 0.00 0.0
15 N 2.00 12.49 0.50 1.25 2.00 1.8 21.9
16 O 2.00 27.69 0.50 1.25 2.00 1.8 48.5
17 P 4.00 33.38 0.50 1.50 4.00 4.0 133.5
18 Q 4.00 40.66 0.50 1.50 4.00 4.0 162.6
19 R 6.00 14.71 0.50 1.50 6.00 6.0 88.3 1.00 3.00 44.1
20 S 4.00 46.54 0.50 1.50 4.00 4.0 186.2
21 T 5.00 16.98 0.50 1.50 5.00 5.0 84.9 1.00 3.00 50.9
22 U 5.00 51.44 Area = 8.0 M² 411.5
BR

23 V 5.00 69.24 Area = 8.0 M² 553.9


ON
JO

24 W 9.00 63.03 Area = 20.0 M² 1260.6


NG

25 X 6.00 31.13 0.50 2.00 6.00 7.5 233.5 1.00 3.00 93.4
26 Y 10.00 44.22 0.80 2.75 10.00 17.8 784.9 2.25 4.00 398.0
27 Z 10.00 8.03 0.80 2.75 10.00 17.8 142.5 2.25 4.00 72.3
28 A1 10.00 36.98 0.80 2.75 10.00 17.8 656.4 2.25 4.00 332.8
29 A2 10.00 36.98 0.80 2.75 10.00 17.8 656.4 2.25 4.00 332.8
30 A3 4.00 19.17 0.50 1.50 4.00 4.0 76.7
31 A4 4.00 36.36 0.50 1.50 4.00 4.0 145.4
32 A5 4.00 2.00 0.50 1.50 4.00 4.0 8.0
33 A6 4.00 14.94 0.50 1.50 4.00 4.0 59.8
34 A7 4.00 20.58 0.50 1.50 4.00 4.0 82.3
35 A8 3.00 18.16 0.50 1.25 3.00 2.6 47.7
36 A9 3.00 44.58 0.50 1.25 3.00 2.6 117.0

29 1 3 24.79 0.5 1.25 3 2.6 65.1


30 2 7 32.68 0.5 2 7 8.8 286.0 1.00 3.50 114.4
31 3 14 26.22 0.8 3 14 26.6 697.5 2.50 5.75 376.9
32 4 14 52.41 0.8 3 14 26.6 1394.1 2.50 5.75 753.4
33 5 5 5.97 0.5 1.75 5 5.6 33.6 1.00 3.00 17.9
34 6 5 4.6 0.5 1.75 5 5.6 25.9 1.00 3.00 13.8
35 7 4 16.45 0.5 1.5 4 4.0 65.8
36 8 2 2.5 0.5 1.25 2 1.8 4.4
37 9 5 42.17 0.5 1.75 5 5.6 237.2 1.00 3.00 126.5
38 10 5 2.83 0.5 1.75 5 5.6 15.9 1.00 3.00 8.5
39 11 5 6.1 0.5 1.75 5 5.6 34.3 1.00 3.00 18.3
40 12 4 11.22 0.5 1.5 4 4.0 44.9
41 13 2 3.61 0.5 1.25 2 1.8 6.3
42 14 9 15.94 0.5 2.5 9 13.5 215.2 1.50 4.00 95.6
43 15 9 8.17 0.5 2.5 9 13.5 110.3 1.50 4.00 49.0
44 16 9 9.03 0.5 2.5 9 13.5 121.9 1.50 4.00 54.2
45 17 9 14.71 0.5 2.5 9 13.5 198.6 1.50 4.00 88.3
46 18 6 7.33 0.5 2 6 7.5 55.0 1.00 3.00 22.0
47 19 5 8.74 0.5 1.75 5 5.6 49.2 1.00 3.00 26.2
48 20 4 5.61 0.5 1.5 4 4.0 22.4
49 21 3 7.6 0.5 1.25 3 2.6 20.0
50 22 2 5.04 0.5 1.25 2 1.8 8.8
51 23 2 3 0.5 1.25 2 1.8 5.3
52 24 2 6.2 0.5 1.25 2 1.8 10.9
53 25 3 5.47 0.5 1.25 3 2.6 14.4
54 26 4 5.54 0.5 1.5 4 4.0 22.2
55 27 5 7.63 0.5 1.75 5 5.6 42.9 1.00 3.00 22.9
56 28 6 9.08 0.5 2 6 7.5 68.1 1.00 3.00 27.2
57 29 6 12.69 0.5 2 6 7.5 95.2 1.00 3.00 38.1
58 30 5 8.97 0.5 1.75 5 5.6 50.5 1.00 3.00 26.9
59 31 4 19.06 0.5 1.5 4 4.0 76.2
60 32 3 8.24 0.5 1.25 3 2.6 21.6
61 33 3 14.85 0.5 1.25 3 2.6 39.0
62 34 3 8.62 0.5 1.25 3 2.6 22.6
63 35 3 17.72 0.5 1.25 3 2.6 46.5
64 36 3 5 0.5 1.25 3 2.6 13.1
65 37 3 17.39 0.5 1.25 3 2.6 45.6
66 38 3 8.49 0.5 1.25 3 2.6 22.3
67 39 3 12.51 0.5 1.25 3 2.6 32.8
68 40 3 20.46 0.5 1.25 3 2.6 53.7
V. DPT BATU BELAH 22477.6 11426.0
V. DPT BATU BRONJONG 2226.0

2. Volume Pipa Tanam


Luas Total Dinding Diatas Jalan dan Tanah 782.4 M3
Jumlah Titik Pipa 2,5" 391.2 Titik L pipa = 1.2 M'
V = 469.4 M'
NG
JO
ON
BR
PROYEK : RUMAH SAKIT MECCA NUSANTARA
LOKASI : Way Tenong, Lampung Barat
PERIHAL : Volume Pekerjaan Perkerasan Jalan

I. Pekerjaan Perkerasan Jalan Beton


a. Pekerjaan Pelat Beton

No SEGMEN L (m) B (m) H (m) At (m²) V (m³)

1 I 111.9 6.5 0.30 727.4 218.2


2 II 124.1 6.5 0.30 806.7 242.0
3 III 111.8 7.0 0.20 782.6 156.5
4 IV 48.0 8.5 0.20 408.0 81.6
5 V 16.0 9.0 0.20 144.0 28.8
411.8 2868.6 727.1

b. Pekerjaan Pembesian
Volume Pembesian / m2
Dia. Tulangan = 13 mm As = 132.73 mm² W = 1.04 kg/m

Volume Pembesian 1 m2
Jarak Tul Arah x = 0.25 m Jlh / m = 4 W = 4.17 kg
Jarak Tul Arah y = 0.25 m Jlh / m = 4 W = 4.17 kg
Total (Vbesi) = 8.34 kg/m2

V total Besi = At x 1,1Vbesi/m2


= 26303.91 kg

c. Pekerjaan Bekisting
L Total = 411.80 m'
Tinggi Bekisting = 0.35 m 2 Sisi
V Beksiting = 288.26 m2

d. Pekerjaan Pondasi Bawah (Base) Soil Cement

No SEGMEN L (m) B (m) H (m) At (m²) V (m³)

1 I 111.9 6.5 0.40 727.4 290.9


2 II 124.1 6.5 0.25 806.7 201.7
3 III 111.8 7.0 0.25 782.6 195.7
4 IV 48.0 8.5 0.25 408.0 102.0
5 V 16.0 9.0 0.25 144.0 36.0
826.3
II. Pekerjaan Perkerasan Jalan Flexibel
a. Pekerjaan Pondasi Bawah (Sub Base)
Luas Total = 3679.2 M
Tinggi = 0.4 M
V = 1471.7 M3

b. Pekerjaan Pondasi Atas (Base)


Luas Total = 3679.2 M
Tinggi = 0.2 M
V = 735.84 M3

c. Pekerjaan Lapisan Penutup (Burtu)


Luas Total = 3679.2 M
Tinggi = 0.02 M
V = 73.584 M3

d. Pekerjaan Lapisan Resap Pengikat


Luas Total = 3679.2 M
Tinggi = 1 M2 = 1 Ltr
V = 3679.2 Ltr

e. Pekerjaan Lapisan Perekat


Luas Total = 3679.2 M
Tinggi = 1 M2 = 0.5 Ltr
V = 1839.6 ltr

f. Pekerjaan Laston Lapis Aus (AC -WC)


Luas Total = 3679.2 M
Tinggi = 0.05 M
V = 183.96 M3
Bj = 1.81 Ton/m3
Berat = 332.97 Ton

III. Pekerjaan Pasangan Kanstin


L Total = 2585.7 m'
PROYEK : RUMAH SAKIT MECCA NUSANTARA
LOKASI : Way Tenong, Lampung Barat
PERIHAL : Volume Pekerjaan Conblock

A. Pekerjaan Conblock

No Elevasi At (m²) Vt (m²)

1 + 1066 - -
2 + 1069 2787.0 2786.97
3 + 1075 1697.9 1697.87
4 + 1074,
5 +1076, 26920.3 19089.39
6 +1080
23574.2

B. Pekerjaan Pasir Urug Conblock

No Elevasi At (m²) H (m) V (m³)

1 + 1066 - - -
2 + 1069 2787.0 0.05 139.3
3 + 1075 1697.9 0.05 84.9
4 + 1074,
5 +1076, 19089.4 0.05 954.5
6 +1080
1178.7

C. Pekerjaan Dinding Panel


Panjang Dinding Total = 433.36 m'
PROYEK : RUMAH SAKIT MECCA NUSANTARA
LOKASI : Way Tenong, Lampung Barat
PERIHAL : Volume Sloof, Balok Dan Kolom Pembagi

DIMENSI
No Item
b (m) h (m)
1 Sloof 0.2 0.35
2 Balok 0.2 0.35
3 Kolom 0.2 0.35

1. Volume Pengecoran Sloof, Balok Dan Kolom

V
n V Sloof V Balok
H (m) L (m) n Sloof n Balok Kolom
Kolom (m3) (m3)
(m3)

5 136.6 1 2 34 9.6 19.1 12.0


6 88.4 1 2 22 6.2 12.4 9.3
7 84.4 1 2 21 5.9 11.8 10.3
9 141.8 1 3 35 9.9 29.8 22.3
10 126.2 1 3 32 8.8 26.5 22.1
14 175.4 1 4 44 12.3 49.1 43.0
16 109.6 1 4 27 7.7 30.7 30.7
26 82.7 1 8 21 5.8 46.3 37.6
945.1 66.2 225.7 187.3
Jumlah Total 479.1

2. Volume Pembesian
Sloof = 8,137.1
Balok = 34,305.59
Kolom = 24,157.82

3. Volume Bekisting
V(m2)
PSloof = 945.1 330.77
PBalok = 3224.2 1128.5
PKolom = 2675.3 936.35
Perhitungan Berat Baja Tulangan :

Berdasarkan Gambar Kerja :


Sloof 20x35
A. Dimensi Penampang :
1b = 0.2 m Cover = 0.025 m
2h = 0.35 m L Penjangkaran = 0.1 m

3 Volume / m' = 0.07 m3/m'

4 1 m3 / 0.07 m3/m = 14.29 m'

B. Tulangan Pokok :

5 Jumlah Tulangan = 6 bh

6 Panjang Total Tul = 85.71 m'

7 Panjang 1 Btg = 12 m

8 Jumlah Btg Tul = 7.14 Btg

9 Berat Besi 1 Btg Dia. = 13 mm = 12.50 Kg/Btg

10 Berat Tul / m3 = 89.31 Kg/m3

C. Sengkang :

11 Panjang 1 Sengkang = 1.00 m'

12 Jarak Sengkang = 0.175 m

13 Jumlah Sengkang = 83.00 bh

14 Panjang Tot Sengkang = 83 m'

15 Jumlah Btg = 6.92 Btg

16 Berat Besi 1 Btg Dia. = 8 mm = 4.74 Kg/Btg

17 Berat Tul / m3 = 32.75 Kg/m3

D. Bendrat = - Kg/m3

E. Total Berat (B+C+D) = 123.00 Kg/m3

Berdasarkan Gambar Kerja :


Balok 20x35
A. Dimensi Penampang :
1b = 0.2 m Cover = 0.025 m
2h = 0.35 m L Penjangkaran = 0.1 m
3 Volume / m' = 0.07 m3/m'

4 1 m3 / 0.07 m3/m = 14.29 m'

B. Tulangan Pokok :

5 Jumlah Tulangan = 8 bh

6 Panjang Total Tul = 114.29 m'

7 Panjang 1 Btg = 12 m

8 Jumlah Btg Tul = 9.52 Btg

9 Berat Besi 1 Btg Dia. = 13 mm = 12.50 Kg/Btg

10 Berat Tul / m3 = 119.08 Kg/m3

C. Sengkang :

11 Panjang 1 Sengkang = 1.00 m'

12 Jarak Sengkang = 0.175 m

13 Jumlah Sengkang = 83.00 bh

14 Panjang Tot Sengkang = 83 m'

15 Jumlah Btg = 6.92 Btg

16 Berat Besi 1 Btg Dia. = 8 mm = 4.74 Kg/Btg

17 Berat Tul / m3 = 32.75 Kg/m3

D. Bendrat = - Kg/m3

E. Total Berat (B+C+D) = 152.00 Kg/m3

Berdasarkan Gambar Kerja :


Kolom 20x35
A. Dimensi Penampang :
1b = 0.25 m Cover = 0.025 m
2h = 0.35 m L Penjangkaran = 0.1 m

3 Volume / m' = 0.0875 m3/m'

4 1 m3 / 0.0875 m3/m = 11.43 m'

B. Tulangan Pokok :

5 Jumlah Tulangan = 8 bh
6 Panjang Total Tul = 91.43 m'

7 Panjang 1 Btg = 12 m

8 Jumlah Btg Tul = 7.62 Btg

9 Berat Besi 1 Btg Dia. = 13 mm = 12.50 Kg/Btg

10 Berat Tul / m3 = 95.22 Kg/m3

C. Sengkang :

11 Panjang 1 Sengkang = 1.10 m'

12 Jarak Sengkang = 0.15 m

13 Jumlah Sengkang = 77.00 bh

14 Panjang Tot Sengkang = 84.7 m'

15 Jumlah Btg = 7.06 Btg

16 Berat Besi 1 Btg Dia. = 8 mm = 4.73 Kg/Btg

17 Berat Tul / m3 = 33.40 Kg/m3

D. Bendrat = - Kg/m3

E. Total Berat (B+C+D) = 129.00 Kg/m3


DAFTAR HARGA SATUAN UPAH DAN BAHAN KOTA BANDAR LAMPUNG 2016 (TRW KE-3)

Uraian Satuan Harga Ket.


NO
Rp. Rp.
1 2 3 4 5
A. UPAH
1 Mandor Oh 110,000
2 Kepala Tukang Oh 100,000
3 Pekerja Oh 75,000
4 Pekerja Terampil Oh 80,000
5 Operator Terlatih Oh 110,000
6 Pembantu Operator Oh 75,000
7 Sopir Terlatih Oh 95,000
8 Pembantu Sopir Oh 75,000
9 Penjaga Malam Oh 75,000
10 Tukang Batu Oh 95,000
11 Tukang Besi Oh 95,000
12 Tukang Besi Konstruksi Oh 95,000
13 Tukang Cat Oh 95,000
14 Tukang Gali Oh 95,000
15 Tukang Kayu Oh 95,000
16 Tukang Khusus Aluminium Oh 95,000
17 Tukang Las Konstruksi Oh 95,000
18 Tukang Las Biasa Oh 95,000
19 Tukang Pipa Oh 95,000
20 Instalatur Listrik Oh 100,000
21 Asisten Instalatur Listrik Oh 80,000
22 Ahli Bor Oh 110,000
23 Operator Bor Oh 110,000
24 Pembantu Operator Bor Oh 75,000
25 Surveyor Geodesi Oh 110,000

Uraian Satuan Harga Ket.


NO
Rp. Rp.
1 2 3 4 5
B BAHAN
Air Liter 50
Akustik Arm Strong Ukuran 30 x 120 cm Lbr
Akustik 30 x 30 cm Lbr
Akustik 30 x 60 cm Lbr
Akustik 60 x 120 cm Lbr
Alat Bantu ( set @ 3 alat) Set
Alang - alang Ikat
Alluminium B Kg
Alluminium C Kg
Alluminium strip M'
alumunium foil M2 8,000
Ampelas Lbr 8,000
Asbes Gelombang 1.50 x 1.05 m x 4 mm Lbr
Asbes Gelombang 1.80 x 0.92 m x 5 mm Lbr
Asbes Gelombang 1.80 x 1.08 m x 6 mm Lbr
Asbes Gelombang 2.00 x 0.92 m x 5 mm Lbr
Asbes Gelombang 2.10 x 1.05 m x 4 mm Lbr
Asbes Gelombang 2.10 x 1.08 m x 3 mm Lbr
Asbes Gelombang 1.80 x 0.8 m x 3 mm Lbr
Asbes Gelombang 1.80 x 1,08 m x 3 mm Lbr
Asbes Gelombang 2,25 x 0,92 m x 5 mm Lbr
Asbes Gelombang 2,25 x 0.92 m x 5 mm Lbr
Asbes Gelombang 2.40 x 1.05 m x 4 mm Lbr
Asbes Gelombang 2.40 x 1.08 m x 6 mm Lbr
Asbes Gelombang 2.70 x 1.05 m x 4 mm Lbr
Asbes Gelombang 2.70 x 1.08 m x 6 mm Lbr
Asbes Gelombang 3.00 x 1.05 m x 4 mm Lbr
Asbes Gelombang 3.00 x 1.08 m x 6 mm Lbr
Asbes Gelombang Kecil Lbr 45,885
Asbes semen Tebal 4 mm M2
Asbes semen Tebal 5 mm M2
Asbes semen Tebal 6 mm M2
Aspal Kg
Badkip Bh
Bahan Bakar Minyak Ltr
Baja Ringan M2 285,000
Bak cuci Stainless steel Bh
Bak Mandi Fiberglass Volume 0,30 M3 Bh
Bak Fiberglass Volume 1,00 M3 Bh
Bak Fiber 50.50.5 Bh 200,000
Bak Fiber 50.50.5 Bh 275,000
Bambu Ø 6 - 8 / 600 cm Btg 8,400
Bata Merah/Batu Bata Bh 400
Batako Bh 4,000
Batu Apung Kg
Batu Belah Hitam (pondasi) M3 253,000
Batu Belah Putih (pondasi) M3 215,000
Batu belah 15 cm/20 cm M3
Batu belah 10 cm/15 cm M3 268,000
Batu Belah 5 / 20 M3
Batu pecah 5 - 7 cm M3 308,100
Batu Granito Kg
Batu Muka Bali Gren M2
Batu Muka Kota agung M2
Batu Muka Palimanan M2
Batu Kerikil M3
Batu Koral M3
Batu Paras M2
Batu Split 1/2 cm M3 334,300
Batu Split 2/3 cm M3 326,212
Batu Split 3/5 cm M3 304,000
Batu Tempel Hitam Bh
Bentonit Kg
Besi angkur diameter 8 mm Kg
Besi beton Kg
Besi Jaring Kawat Baja Kg
Besi lis kaca (1 x 1) cm Kg
Besi plat baja Kg
Besi Profil Kg
Besi Baja IWF Kg 14,000
Besi Baja Siku Kg 14,000
Besi strip tebal 2 mm Kg
Besi strip tebal 5 mm Kg
Besi Beton Polos Kg 15,000
Besi Beton Ulir Kg 16,000
Bilik bambu M2
Box Meter Unit 59,000
Box Zekring/Termis 2 Group Bh 184,000
Box Zekring/Termis 3 Group Bh 187,450
Bubungan Genteng Beton Bh 8,500
Bubungan Genteng Kodok Bh 3,450
Bubungan Genteng Mantili Bh 3,450
Bubungan Genteng Plentong Bh 4,600
Bubungan Genteng Zincalume Pasir M' 78,545
Bubungan Genteng Zincalume Polos M' 62,790
Bubung Stel Gelombang 0.92 m Lembar
Carpet M2
Carpet 80% Wool, 20% Nylon M2
Cat Tembok Kg 50,000
Cat Antara Kg
Cat Genteng Kg 172,000
Cat Taman Kg 150,000
Cat Dasar Kg 45,000
Cat Kayu Kg 57,000
Cat Meni Kg 65,000
Cat Meni besi Kg
Cat Penutup Kg
Cat Besi Kg 67,000
Cat Marka Jalan Kg
Conblock M2 300,000
Dempul Kg 20,000
Dempul Jadi Kg
Dolken Kayu Kelas III Ø 8 - 10/400 cm Btg 37,950
Door Closer Bh
Door Holder Bh
Door Stop Bh
Engsel Angin Bh
Engsel Jendela Psg 30,000
Engsel Pintu Psg 45,000
Eternit (240 x 120 x 0,3) cm M2 51,980
Floor Drain Stainless 2"(Saringan Air) Bh 45,000
Floor Drain Stainless 3"(Saringan Air) Bh
Floor Drain Plastik 2"(Saringan Air) Bh
Floor Drain Plastik 3"(Saringan Air) Bh
Floor hardener Kg
Floor Hardener Ferrovax Kg
Formika Lbr
Formite/penjaga jarak begisting Bh
Genteng Beton Bh 6,500
Genteng Mantili Bh 10,000
Genteng Keramik Bh
Genteng Bubung Keramik Lbr
Genteng Bubung Kodok Bh
Genteng Bubung Palentong Bh
Genteng Kodok Bh
Genteng Metal Zincalume Polos M2 166,750
Genteng Metal Zincalume Pasir M2 189,750
Genteng Palentong Bh 2,400
Genteng Palentong Super Bh
Genteng Decra Bond M2

Glass Block Bh 33,600


Grass Blok Bh 22,000

Grafel Pak 3 - 6 mm Bh
Gymfloor M2
Gypsum board 9 mm Lbr 70,000
Grendel Jendela Set 21,000
Grendel pintu Bh 22,000
Hak Angin / Pengait Set 20,000
Harplek 1 x 1 m Lbr 22,000

Hollow Block 20 Bh
Hollow Block 15 Bh
Hollow Block 10 Bh
Ijuk Kg
Jendela nako (rangka + kaca 5 mm) M2

Kabel Pompa 3 x 2,5 mm M' 16,500


Kabel Listrik NYM 2 x 1,5 Rol 300,000
Kabel Listrik NYM 2 x 2,5 Rol 432,000
Kabel Listrik NYM 3 x 2,5 Rol 568,250

Kaca Buram M2
Kaca Cermin Tebal 5 mm M2
Kaca Cermin Tebal 6 mm M2
Kaca Cermin Tebal 8 mm M2
Kaca Patri Tebal 5 mm M2
Kaca Polos Tebal 12 mm M2
Kaca Polos Tebal 3 mm M2
Kaca Polos Tebal 5 mm M2
Kaca Polos Tebal 8 mm M2
Kaca Wireglass Tebal 5 mm M2
Kanstin Cetak Bh 15,000
Kapur Padam M3
Kapur Sirih Kg
Karpet M2
Kawat Beton Kg 18,500
Kawat Bronjong Kg 18,000
Kawat Burung M2
Kawat diameter 4 mm Kg
Kawat Duri Kg 20,700
Kawat Harmonika M2 20,700
Kawat Kassa M2
Kawat las listrik Kg
Kawat Nyamuk M2 23,000
Kayu Bakar M3 180,000
Kayu Balok kls. I M3 10,350,000
Kayu Balok kls. II M3 4,370,000
Kayu Balok kls. III M3 4,255,000
Kayu Balok kls. IV M3 2,012,500
Kayu Kasau kls. I M3 10,350,000
Kayu Kasau kls. II M3 4,140,000
Kayu Kasau kls. III M3 4,140,000
Kayu Kasau kls. IV M3 2,012,500
Kayu Papan kls. I M3 10,350,000
Kayu Papan kls. II M3 4,370,000
Kayu Papan kls. III M3 4,255,000
Kayu Papan kls. IV M3 2,012,500
Kayu Reng kls. I M3 9,775,000
Kayu Reng kls. II M3 4,140,000
Kayu Reng kls. III M3 4,140,000
Kayu Reng kls. IV M3 2,012,500
Kayu Kelas I (Balok) M3
Kayu Kelas I (Papan) M3
Kayu Kelas II ( 2 x 3 Cm) M3
Kayu Kelas II ( 3 x 4 Cm) M3
Kayu Kelas II ( 5 x 7 cm) M3
Kayu kelas II (balok) M3
Kayu Kelas II (Papan) M3
Kayu Kelas III ( 3 cm x 20 cm) M3
Kayu Kelas III ( 5 x 7 cm) M3
Kayu Kelas III (Balok) M3
Kayu kelas III (papan) M3
Kayu Kelas IV M3
Kayu Profil M'
Kayu Terentang M3
Keramik 10 x 20 Polos M2 58,000
Keramik 20 x 20 Polos M2 50,000
Keramik 20 x 20 Warna M2 65,000
Keramik 25 x 25 Polos M2 55,000
Keramik 25 x 25 Warna M2 57,000
Keramik 30 x 30 Polos M2 48,000
Keramik 30 x 30 Warna M2 58,000
Keramik 40 x 40 Polos M2 60,000
Keramik 40 x 40 Warna M2 65,000
Keramik 50 x 50 Polos M2 76,000
Keramik 50 x 50 Warna M2 80,000
Keramik 60 x 60 Polos M2
Keramik 60 x 60 Warna M2
Keramik 80 x 80 Polos M2
Keramik 80 x 80 Warna M2
Keramik 100 x 100 Polos M2
Keramik 100 x 100 Warna M2
Keramik Artistik 10 x 20 cm M2
Keramik Artistik 5 x 20 cm M2
Kloset Duduk Keramik (Natural) Bh 2,178,000
Kloset Jongkok Keramik Bh 300,000
Kloset Duduk / Monoblok Bh
Kloset Jongkok Porselen Bh
Kloset Jongkok Teraso Bh
Kolom Beton Pracetak 17 x 17 x 300 cm Bh 382,800
Koral Beton M3
Kran Air Bh
Kuas Bh
Kunci Lemari Bh
Kunci Selot Bh
Kunci Silinder Bh
Kunci Tanam Bh
Kunci Tanam Antik Bh
Kunci Tanam Biasa Bh
Kunci Tanam Kamar Mandi Bh
Klem Pipa PVC Diameter 1" Bh
Klem Pipa PVC Diameter 1/2" Bh
Klem Pipa PVC Diameter 3" Bh
Klem Pipa PVC Diameter 3/4" Bh
Klem Pipa PVC Diameter 4" Bh
Knee "L" PVC Diameter 1" Bh
Knee "L" PVC Diameter 1/2" Bh
Knee "L" PVC Diameter 3" Bh
Knee "L" PVC Diameter 3/4" Bh
Knee "L" PVC Diameter 4" Bh
Knee Gip dia 3/4" Bh
Lampu Baret 40 Watt Bh
Lampu Pijar 25 Watt Bh
Lampu Pijar 40 Watt + Vitting Bh
Lampu SL 18 watt Bh
Lampu SL 24 Watt Bh
Lampu sport 100 watt + instalasi tanam Bh
Lampu sport 100 watt lengkap Bh
Lampu TL 1 x 20 Watt Bh
Lampu TL 2 x 20 Watt Bh
Lampu TL = 1 x 20 Watt Lengkap Bh
Lampu TL = 2 x 20 Watt Lengkap Bh
Lem Kayu Kg
Lem vinyl Kg
Lis Kayu Profil Uk. 2 x 3 cm M'
Lis Kayu Profil Uk. 2 x 4 cm M'
Lisplank Zincalume M'

List gypsum profil 5 cm M' 15,000


List gypsum profil 10 cm M' 20,000
List gypsum profil 15 cm M' 23,000
List gypsum profil 20 cm M' 30,000

Mangkokan Listrik (Durados) Bh 53,000

Marmer 30 x 30 cm M2 187,000
Marmer 40 x 40 cm M2 285,700
Marmer 50 x 50 cm M2 325,700
Marmer 60 x 60 cm M2 350,700
Marmer 80 x 80 cm M2
Marmer 100 x 100 cm M2

Lt. Vinyl Karet 30 x 30 kwl I Bh


Mata Bor Diameter 4" Bh
Mata Bor Diameter 6" Bh
Mata Bor Diameter 8" Bh
Meni ( Read Lead ) A Kg
Meni ( Read Lead ) B Kg
Minyak Bekisting Ltr
Mozaik 30 x 30 cm Bh

Minyak Bensin (Premium) Subsidi Ltr 7,300


Minyak Bensin Non Subsidi (Industri) Ltr 10,950
Minyak Cat Ltr 25,000
Minyak Pelumas / Oli Ltr 34,500
Minyak Solar Subsidi Ltr 6,900
Minyak Solar Non Subsidi (Industri) Ltr 12,500
Minyak Thiner Ltr 19,000
Multipleks 9 mm Lbr 125,000
Multipleks 12 mm Lbr 161,000
Nok Asbes Set 30,000

Nok Asbes Paten 0,92 m Lbr


Nok Asbes Rata 0,92 m Lbr
Nok Asbes Rata 1,05 m Lbr
Nok Genteng Beton Lbr
Nok Genteng Metal Lbr
Nok standar 40 cm 18, swg 22 M2
Nok Stel Gelombang 0.92 m Lbr
Nok Stel Gelombang 1,05 m Kg
Nok Stel Gelombang 1,08 m Kg
Paku Kg 18,000
Paku Asbes Kg 24,000
Paku Cacing Kg 26,000
Paku Seng Kg 28,750
Paku Skrup Kg 26,000
Paku Tripleks Kg 25,000
Panel Pompa Unit 3,500,000
Pas. Instalasi Listrik Titik 211,240

Paku 1 cm - 2,5 cm Kg
Paku 12 cm Kg
Paku 5 cm - 10 cm Kg
Paku 5 cm - 12 cm Kg
Paku 5 cm - 7 cm Kg
Paku 7 cm - 10 cm Kg
Paku anti karat Bh
Paku Biasa ½" - 1" Kg
Paku Biasa ½" - 1" atau Sekrup Kg
Paku Biasa 1/2" - 1" Kg
Paku Biasa 2" - 5" Kg
Paku Hak Pnjang 15 cm Kg
Paku Pancing 60 x 230 Kg
Paku skrup 1 cm - 2,5 cm Bh
Paku skrup 10 cm Kg
Paku Skrup 3.5" Bh
Paku/skrup 5 cm Kg'
Paku Tripleks Kg
Parquet M2
Parquet Jati M2
Pasir Beton M3 264,500
Pasir Pasang M3 190,000
Pasir Silika Kg
Pasir Urug M3 180,550
Paving Block Tebal 6 cm Bh 2,000
Paving Block Tebal 8 cm Bh 2,300

Paving Block Tebal 6 cm Type Segienam Bh


Paving Block Tebal 8 cm Type Segienam Bh
Panel Beton Pracetak Lbr 288,840
Pelat Asbes tebal 4 mm Lbr
Pelat Asbes tebal 5 mm Lbr
Pengencer Ltr

Penangkal Petir Unit 3,320,635

Perancah Kayu M3
Perekat Kg
Pintu Allumunium M2
Pintu gulung besi M2
Pintu lipat bahan PVC M2
Pipa Beton Ø 100 cm Bh
Pipa Beton Ø 20 cm Bh
Pipa Galvanis Ø ½" Btg 188,000
Pipa Galvanis Ø ¾" Btg 241,000
Pipa Galvanis Ø 1" Btg 371,000
Pipa Galvanis Ø 1¼" Btg 490,000
Pipa Galvanis Ø 2" Btg 745,000
Pipa Galvanis Ø 4" Btg 1,779,000
Pipa Galvanis Ø 6" Btg 2,851,000

Pipa PVC tipe AW Ø ½" Btg 18,920


Pipa PVC tipe AW Ø ¾" Btg 25,685
Pipa PVC tipe AW Ø 1" Btg 35,475
Pipa PVC tipe AW Ø 1½" Btg
Pipa PVC tipe AW Ø 2" Btg 77,770
Pipa PVC tipe AW Ø 2½" Btg
Pipa PVC tipe AW Ø 3" Btg 151,525
Pipa PVC tipe AW Ø 4" Btg 248,490
Pipa Screen Diameter 4" Btg
Pipa Screen Diameter 6" Btg
Pipa Tanah Ø 15 cm Btg
Pipa Tanah Ø 20 cm Btg
Plamir Kg
Plamir Tembok Kg 53,000
Plitur Jadi Ltr 60,950
Plat perletakan Bh
Plat sudut Bh
Plint Keramik Artistik 10 x 10 cm Bh
Plint Keramik Artistik 10 x 20 cm Bh
Plint Keramik Artistik 5 x 20 cm Bh
Plint Ubin Granito 10 x 30 cm Bh
Plint Ubin Granito 10 x 40 cm Bh
Plint Ubin PC Abu - abu 15 x 20 cm Bh
Plint Ubin PC Abu-abu 10 x 30 cm Bh
Plint Ubin PC Abu-abu 10 x 40 cm Bh
Plint Ubin PC Warna 10 x 20 cm Bh
Plint Ubin PC Warna 10 x 30 cm Bh
Plint Ubin PC Warna 10 x 40 cm Bh
Plint Ubin Teraso 10 x 30 cm Bh
Plint Ubin Teraso 10 x 40 cm Bh
Plywood tebal 4 mm Uk. (120 x 240) cm Lbr
Plywood tebal 4 mm Uk. (90 x 220) cm Lbr
Plywood tebal 9 mm Lbr

Polycarbonat Lbr 200,000


Reservoir Tower Air Fiber 0,5 M3 Bh 800,000
Reservoir Tower Air Fiber 1 M3 Bh 1,450,000

Porselen 10 x 20 cm putih Bh
Porselen 10 x 20 cm warna Bh
Porselen 11 x 11 cm putih Bh
Porselen 11 x 11 cm warna Bh
Porselen 15 x 15 cm putih Bh
Porselen 15 x 15 cm warna Bh
Porselen 20 x 20 cm warna Bh
Pompa Air Jet Pump Unit
Pompa Summersible kap 2-3 Liter/Detik Unit
Profil alluminium M'
Profil Alluminium " T " M'
Profil CT 6407-07 M'
Profil kaca M'
Profil reng RT.15 Btg
Profil U.85-06 Btg
Ramset Bh
Rel Pintu Dorong Bh
Residu Ltr
Residu atau Ter Ltr
Rolling Door Alluminium M2 476,000
Roster Beton 15/20 Bh 46,000
Rumput Gajah Mini / Australia M2 49,500
Rumput Golf M2 27,500
Roof Light Fiberglass Lbr
Sabun Kg
Saklar Single / Tunggal Bh 27,600
Saklar Double Bh 38,525
Saklar Triple Bh 43,000
Seal tape Bh
Sealant Tube
Semen Abu -abu Kg
Semen Merah M3
Semen Nat Kg
Semen Portland (50 kg) Kg 1,300
Semen Putih (50 kg) Kg 1,804
Semen Warna Kg
Seng Gelombang 3" x 6" BJLS 27 Lbr 43,000
Seng Gelombang BJLS 30 Lbr 54,600
Seng Plat 3" x 6" BJLS 27 Lbr 39,500
Seng Plat 3" x 6" BJLS 30 Lbr 55,200
Sirtu M3
Sisalation / Alluminium Foil M2
Shock lurus PVC Diameter 3" Bh
Shockdrat dalam Gip Diameter 1" Bh
Shockdrat dalam Gip Diameter 1/2" Bh
Shockdrat dalam Gip Diameter 4" Bh
Shockdrat dalam PVC Diameter 3" Bh
Shockdrat dalam PVC Diameter 3/4" Bh
Shockdrat dalam PVC Diameter 4" Bh
Shockdrat luar Gip Diameter 1" Bh
Shockdrat luar Gip Diameter 1/2" Bh
Shockdrat luar Gip Diameter 4" Bh
Shockdrat luar PVC Diameter 3" Bh
Shockdrat luar PVC Diameter 3/4" Bh
Shockdrat luar PVC Diameter 4" Bh
Shower air Bh
Skrup fixer
Soda Api Kg 30,000
Stop Kontak Bh 25,000
Strorox - 100 Kg
Talang Zincalume M'
Talang Fiber M' 53,000
Tali Ijuk Kg 10,000
Tanah Liat M3
Tanah Urug Pilihan M3 150,000
Tarikan Jendela Bh 15,000
Teak Oil Ltr
Thinner Ltr
Teakwood t = 5 mm Lbr 120,800
Teer / Residu Ltr 24,400

Teakwood tebal 4 mm, Uk. 90 cm x 220 cm Lbr


Teakwood tebal 4 mm, Uk. 120 cm x 240 cm Lbr
Tepung gypsum Kg
Terali Besi 2 x 3 M'
Terawang (Roster) Buah
Tripleks tebal 3 mm Lbr 55,000
Tripleks tebal 5 mm Lbr 75,000

Ubin Abu -abu 20 x 20 cm Bh


Ubin Abu -abu 30 x 30 cm Bh
Ubin Abu -abu 40 x40 cm Bh
Ubin Granito 30 x 30 cm Bh
Ubin Granito 40 x 40 cm Bh
Ubin Keramik 10 x 33 cm Bh
Ubin Keramik 15 x 15 cm Bh
Ubin Keramik 15 x 20 cm Bh
Ubin Keramik 20 x 20 cm Bh
Ubin Keramik 25 x 25 cm Bh
Ubin Keramik 30 X 30 cm Bh
Ubin Keramik 33 x 33 cm Bh
Ubin Keramik 33 x 33 cm anti slip Bh
Ubin Keramik 10 x 20 cm Bh
Ubin Keramik 10 x 33 cm Variasi Bh
Ubin Keramik Artistik 10 x 20 cm Bh
Ubin Teraso 30 x 30 cm Bh
Ubin Teraso 40 x 40 cm Bh
Ubin Warna 20 x 20 cm Bh
Ubin Warna 30 x 30 cm Bh
Ubin Warna 40 x 40 cm Bh
Urinoir Keramik Lengkap Bh 2,190,000
Vernis Ltr
Vinyl Bh
Vinyl Asbes 30 x 30 cm Bh
Vinyl karet Bh
Vinyl Karet 30 x 30 cm KL I Bh
Vinyl Karet 30 x 30 cm KL II Bh
Vinyl Motif Kembang ex DN Bh
Vinyl Wall Covering lebar 50 cm M2
Wall Paper M'
Wastafel Keramik Lengkap Bh 1,500,000
Water Meter Bh 300,000
Water Drain + Asesories Set
Tarikan Jendela Bh
Grendel Pintu Tanam Bh

SEWA PERALATAN
1 Alat Bantu untuk Pek.Pengeboran Jam
2 Alat Bantu. Jam
3 Sewa Alat Longingtest Jam
4 Sewa Generator Jam
5 Sewa Mesin Bor Tanah Jam
6 Sewa Pompa Jam
7 Sewa Stemper Kodok Hk 200,000
8 Sewa Alat Las Listrik Jam
9 Sewa Alat Perakitan besi Jam
10 Kompresor, Blasting Pot , Selang Dan Nozzle Jam
11 Sewa Dump Truck 5 T Jam
12 Sewa Alat Water Pass/Theodolit Hari
13 Compressor Jam
14 Dump Truck Jam
6 (TRW KE-3)
ANALISA HARGA SATUAN PEKERJAAN BANGUNAN GEDUNG DAN PERUMAHAN

Kode Analisaa Kebutuhan Satuan Indeks

A. PEKERJAAN PERSIAPAN
Analisa A.1 1 m' Pagar Sementara dari Kayu tinggi 2 m
Bahan Dolken Kayu Kelas III Ø 8 - 10/400 cm Batang 1.2500
Semen Portland Kg 2.5000
Pasir Beton M3 0.0050
Koral Beton M3 0.0090
Kayu Kelas III ( 5 x 7 cm) M3 0.0720
Paku 5 cm - 12 cm Kg 0.0600
Residu Liter 0.4000
Tenaga Kerja Tukang Kayu OH 0.2000
Pekerja OH 0.4000
Kepala Tukang OH 0.0200
Mandor OH 0.0200
Jumlah Harga per Satuan Pekerjaan
Analisa A.2 1 m' Pagar Sementara dari Seng Gelombang tinggi 2 m
Bahan Dolken Kayu Kelas III Ø 8 - 10/400 cm Batang 1.2500
Semen Portland Kg 2.5000
Pasir Beton M3 1.2000
Koral Beton M3 0.0090
Kayu Kelas III ( 5 x 7 cm) M3 0.0720
Paku 5 cm - 12 cm Kg 0.0600
Cat Meni Besi Liter 0.4500
Tenaga Kerja Tukang Kayu OH 0.2000
Pekerja OH 0.4000
Kepala Tukang OH 0.0200
Mandor OH 0.0200
Jumlah Harga per Satuan Pekerjaan
Analisa A.3 1 m' Pagar Sementara dari Kawat Duri tinggi 1.8 m
Bahan Dolken Kayu Kelas III Ø 8 - 10/400 cm Batang 1.0000
Semen Portland Kg 2.0000
Kawat Duri Kg 25.0000
Pasir Beton M3 0.0050
Koral Beton M3 0.0090
Paku 5 cm - 12 cm Kg 0.0600
Tenaga Kerja Tukang Kayu OH 0.2000
Pekerja OH 0.3000
Kepala Tukang OH 0.0200
Mandor OH 0.0200
Jumlah Harga per Satuan Pekerjaan
Analisa A.4 1 m' Pek. Pengukuran kembali (site) & Pemasangan Bowplank
Bahan Kayu Kelas III ( 5 x 7 cm) M3 0.0120
Paku 5 cm - 12 cm Kg 0.0200
Kayu Kelas III ( 3 cm x 20 cm) M3 0.0070
Tenaga Kerja Tukang Kayu OH 0.1000
Pekerja OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0050
Jumlah Harga per Satuan Pekerjaan
Analisa A.5 1 m² Pek. Kantor Direksi Keet , dengan lantai plesteran
Bahan Dolken Kayu Kelas III Ø 8 - 10/400 cm Batang 1.2500
Kayu Kelas IV M3 0.1800
Paku 5 cm - 12 cm Kg 0.8500
Besi strip tebal 5 mm Kg 1.1000
Semen Portland Kg 35.0000
Pasir Pasang M3 0.1500
Pasir Beton M3 0.1000
Koral Beton M3 0.1500
Bata merah Buah 30.0000
Seng Plat 3 x 6 BJLS 28 Lembar 0.2500
Jendela nako (rangka + kaca 5 mm) M2 2.0000
Kaca Polos tebal 5 mm M2 0.0800
Kunci Tanam Buah 1.0000
Plywood tebal 4 mm Uk. (120 x 240) cm Lembar 0.0600
Tenaga Kerja Tukang Kayu OH 2.0000
Tukang Batu OH 1.0000
Pekerja OH 2.0000
Kepala Tukang OH 0.3000
Mandor OH 0.0500
Jumlah Harga per Satuan Pekerjaan
Analisa A.6 1 m² Pembuatan Gudang Semen dan Alat - alat
Bahan Dolken Kayu Kelas III Ø 8 - 10/400 cm Batang 1.7000
Kayu Kelas IV M3 0.2100
Paku 5 cm - 12 cm Kg 0.3000
Semen Portland Kg 10.5000
Pasir Beton M3 0.0300
Koral Beton M3 0.0500
Seng Gelombang BJLS 32 Lembar 1.5000
Tenaga Kerja Tukang Kayu OH 2.0000
Pekerja OH 1.0000
Kepala Tukang OH 0.2000
Mandor OH 0.0500
Jumlah Harga per Satuan Pekerjaan
Analisa A.7 1 m² Pembuatan Rumah Jaga / Konstruksi Kayu
Bahan Dolken Kayu Kelas III Ø 8 - 10/400 cm Batang 3.0000
Kayu Kelas IV M3 0.2760
Paku 5 cm - 12 cm Kg 0.7000
Seng Gelombang BJLS 32 Lembar 1.5000
Tenaga Kerja Tukang Kayu OH 1.5000
Pekerja OH 1.0000
Kepala Tukang OH 0.1500
Mandor OH 0.0500
Jumlah Harga per Satuan Pekerjaan
Analisa A.8 1 m2 Membersihkan Lapangan dan Perataan
Tenaga Kerja Pekerja OH 0.1000
Mandor OH 0.0500
Jumlah Harga per Satuan Pekerjaan
Analisa A.9 1 m² Pembuatan Bedeng Buruh
Bahan Dolken Kayu Kelas III Ø 8 - 10/400 cm Batang 1.7000
Kayu Kelas IV M3 0.2100
Paku 5 cm - 12 cm Kg 0.3000
Semen Portland Kg 10.5000
Pasir Beton M3 0.0300
Koral Beton M3 0.0500
Seng Gelombang BJLS 32 Lembar 0.0500
Plywood tebal 4 mm Uk. (90 x 220) cm Lembar 1.5000
Tenaga Kerja Tukang Kayu OH 2.0000
Pekerja OH 1.0000
Kepala Tukang OH 0.2000
Mandor OH 0.0500
Jumlah Harga per Satuan Pekerjaan
Analisa A.10 1 m² Pembuatan Bak Adukan ( 40 x 50 x 20 ) cm
Bahan Kayu Terentang M3 0.1860
Paku 5 cm - 12 cm Kg 0.3000
Kayu Kelas III ( 5 x 7 cm) M3 0.0140
Tenaga Kerja Tukang Kayu OH 2.0000
Mandor OH 0.0500
Jumlah Harga per Satuan Pekerjaan
Analisa A.11 1 m² Pembuatan Stegger dari Bambu, ( 40 x 50 x 20 ) cm
Bahan Bambu Ø 6 - 8 / 600 cm Batang 1.0000
Tali Ijuk Kg 0.2500
Tenaga Kerja Tukang Kayu OH 2.0000
Pekerja OH 1.0000
Kepala Tukang OH 0.2000
Mandor OH 0.0500
Jumlah Harga per Satuan Pekerjaan
Analisa A.12 1 m² Pembuatan Jalan Sementara
Bahan Batu Belah 5 / 20 M3 0.1500
Batu pecah 5 - 7 cm M3 0.0900
Pasir Pasang M3 0.0100
Tenaga Kerja Tukang Kayu OH 1.0000
Mandor OH 0.0500
Jumlah Harga per Satuan Pekerjaan
Analisa A.13 1 m³ Bongkaran Beton Bertulang
Tenaga Kerja Pekerja OH 8.0000
Mandor OH 0.4000
Jumlah Harga per Satuan Pekerjaan
Analisa A.14 1 m² Bongkaran Dinding Tembok Bata Merah
Tenaga Kerja Pekerja OH 0.2000
Mandor OH 0.0100
Jumlah Harga per Satuan Pekerjaan
Analisa A.15 1 m² Bongkar Atap
Tenaga Kerja Pekerja OH 0.0500
Mandor OH 0.0100
1 M3 Jumlah Harga per Satuan Pekerjaan
Analisa A.16 1 m² Bongkaran Lantai
Tenaga Kerja Pekerja OH 0.1000
Mandor OH 0.0100
Jumlah Harga per Satuan Pekerjaan
Analisa A.17 10 m³ Bongkaran Kasau dan Reng
Tenaga Kerja Tukang kayu OH 0.2500
Kepala Tukang OH 0.0250
Pekerja OH 1.0000
Mandor OH 0.0500
10 M3 Jumlah Harga per Satuan Pekerjaan
1 M3 Jumlah Harga per Satuan Pekerjaan
Analisa A.18 10 m³ Bongkaran Plapond
Tenaga Kerja Tukang kayu OH 0.6000
Kepala Tukang OH 0.0600
Pekerja OH 2.0000
Mandor OH 0.1000
10 M3 Jumlah Harga per Satuan Pekerjaan
1 M3 Jumlah Harga per Satuan Pekerjaan
Analisa A.19 10 m³ Bongkaran Kap
Tenaga Kerja Tukang kayu OH 6.0000
Kepala Tukang OH 0.6000
Pekerja OH 4.0000
Mandor OH 0.2000
10 M3 Jumlah Harga per Satuan Pekerjaan
1 M3 Jumlah Harga per Satuan Pekerjaan
Analisa A.20 1 Titik Pembuatan Bouplank (Uitzet)
Bahan Kayu Kelas IV M3 0.0200
Tenaga Kerja Tukang kayu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0450
Jumlah Harga per Satuan Pekerjaan
Analisa A.21 Uitzet dengan Water Pass/Theodolit 1 Hari
Peralatan Sewa Alat Water Pass/Theodolit Set 1.0000
Tenaga Kerja Pekerja Terampil OH 0.2500
Surveyor Geodesi OH 0.0250
Jumlah Harga per Satuan Pekerjaan
B. PEKERJAAN TANAH
Analisa B.1 Menggali 1 M3 Tanah Biasa sedalam 0 - 1 Meter
Tenaga Kerja Pekerja OH 0.7500
Mandor OH 0.0250
Jumlah Harga per Satuan Pekerjaan
Analisa B.2 Menggali 1 M3 Tanah Biasa sedalam 1 - 2 Meter
Tenaga Kerja Pekerja OH 0.9000
Mandor OH 0.0450
Jumlah Harga per Satuan Pekerjaan
Analisa B.3 Menggali 1 M3 Tanah Biasa sedalam 2 - 3 Meter
Tenaga Kerja Pekerja OH 1.0500
Mandor OH 0.0670
Jumlah Harga per Satuan Pekerjaan
Analisa B.4 Menggali 1 M3 Tanah Keras sedalam 0 - 1 Meter
Tenaga Kerja Pekerja OH 1.0000
Mandor OH 0.0320
Jumlah Harga per Satuan Pekerjaan
Analisa B.5 Menggali 1 M3 Tanah Cadas Kedalaman 0 - 1 Meter
Tenaga Kerja Pekerja OH 1.5000
Mandor OH 0.0600
Jumlah Harga per Satuan Pekerjaan
Analisa B.6 Menggali 1 M3 Tanah Lumpur Kedalaman 0 - 1 Meter
Tenaga Kerja Pekerja OH 1.2000
Mandor OH 0.0450
Jumlah Harga per Satuan Pekerjaan
Analisa B.7 Mengerjakan 1 M2 stripping tebing setinggi 0 -1 meter
Tenaga Kerja Pekerja OH 0.0500
Mandor OH 0.0050
Jumlah Harga per Satuan Pekerjaan
Analisa B.8 Membuang 1 m3 tanah sejauh 15 meter
Tenaga Kerja Pekerja OH 0.3300
Mandor OH 0.0100
Jumlah Harga per Satuan Pekerjaan
Analisa B.9 Mengurug kembali 1 M3 galian
Tenaga Kerja Pekerja OH 0.2500
Mandor OH 0.0080
Jumlah Harga per Satuan Pekerjaan
Analisa B.10 Memadatkan 1 m 3 tanah (per 20 cm)
Tenaga Kerja Pekerja OH 0.5000
Mandor OH 0.0500
Jumlah Harga per Satuan Pekerjaan
Analisa B.11 Mengurug 1 m3 pasir urug
Bahan Pasir Urug M3 1.2000
Tenaga Kerja Pekerja OH 0.3000
Mandor OH 0.0100
Jumlah Harga per Satuan Pekerjaan
Analisa B.12 Pengangkutan 1 M3 Tanah Keluar Proyek
Peralatan Sewa Dump Truck 5 T Jam 0.2500
Tenaga Kerja Pekerja OH 0.2500
Jumlah Harga per Satuan Pekerjaan
Analisa B.13 Memasang 1 m 3 Lapisan pudel campuran 1 KP : 3 PP : 7 TL untuk stabilisasi Tanah
Bahan Kapur padam M3 0.1350
Pasir Pasang M3 0.4000
Tanah liat M3 0.9480
Tenaga Kerja Pekerja OH 0.0800
Tukang Batu OH 0.4000
Kepala Tukang OH 0.0400
Mandor OH 0.0800
Jumlah Harga per Satuan Pekerjaan
Analisa B.14 Memasang 1 m 3 Lapisan pudel campuran 1 KP : 5 TL untuk stabilisasi tanah
Bahan Kapur padam M3 0.2480
Tanah liat M3 1.2400
Tenaga Kerja Pekerja OH 0.8000
Tukang Batu OH 0.4000
Kepala Tukang OH 0.0400
Mandor OH 0.0800
Jumlah Harga per Satuan Pekerjaan
Analisa B.15 Memasang 1 m 2 lapisan ijuk tebal 10 cm , untuk bidang resapan.
Bahan Ijuk Kg 6.0000
Tenaga Kerja Pekerja OH 0.1500
Mandor OH 0.0150
Jumlah Harga per Satuan Pekerjaan
Analisa B.16 Mengurug 1 m 3 sirtu padat untuk peninggian lantai bangunan
Bahan Sirtu M3 1.2000
Tenaga Kerja Pekerja OH 0.2500
Mandor OH 0.0250
Jumlah Harga per Satuan Pekerjaan
C. PEKERJAAN PONDASI
Analisa C.1 Memasang 1 m 3 pondasi batu belah, campuran 1 PC : 3 PP
Bahan Batu belah 15 cm/20 cm M3 1.2000
Semen Portland Kg 202.0000
Pasir Pasang M3 0.4850
Tenaga Kerja Pekerja OH 1.5000
Tukang Batu OH 0.7500
Kepala Tukang OH 0.0750
Mandor OH 0.0750
Jumlah Harga per Satuan Pekerjaan
Analisa C.2 Memasang 1 m 3 pondasi batu belah, campuran 1 PC : 4 PP
Bahan Batu belah 15 cm/20 cm M3 1.2000
Semen Portland Kg 163.0000
Pasir Pasang M3 0.5200
Tenaga Kerja Pekerja OH 1.5000
Tukang Batu OH 0.7500
Kepala Tukang OH 0.0750
Mandor OH 0.0750
Jumlah Harga per Satuan Pekerjaan
Analisa C.3 Memasang 1 m 3 pondasi batu belah, campuran 1 PC : 5 PP
Bahan Batu belah 15 cm/20 cm M3 1.2000
Semen Portland Kg 136.0000
Pasir Pasang M3 0.5440
Tenaga Kerja Pekerja OH 1.5000
Tukang Batu OH 0.7500
Kepala Tukang OH 0.0750
Mandor OH 0.0750
Jumlah Harga per Satuan Pekerjaan
Analisa C.4 Memasang 1 m 3 pondasi batu belah, campuran 1 PC : 6 PP
Bahan Batu belah 15 cm/20 cm M3 1.2000
Semen Portland Kg 117.0000
Pasir Pasang M3 0.5610
Tenaga Kerja Pekerja OH 1.5000
Tukang Batu OH 0.7500
Kepala Tukang OH 0.0750
Mandor OH 0.0750
Jumlah Harga per Satuan Pekerjaan
Analisa C.5 Memasang 1 m 3 pondasi batu belah, campuran 1 PC : 8 PP
Bahan Batu belah 15 cm/20 cm M3 1.2000
Semen Portland Kg 91.0000
Pasir Pasang M3 0.5840
Tenaga Kerja Pekerja OH 1.5000
Tukang Batu OH 0.7500
Kepala Tukang OH 0.0750
Mandor OH 0.0750
Jumlah Harga per Satuan Pekerjaan
Analisa C.6 Memasang 1 m 3 batu kosong (anstamping)
Bahan Batu belah 15 cm/20 cm M3 1.2000
Pasir Urug M3 0.4320
Tenaga Kerja Pekerja OH 0.7800
Tukang Batu OH 0.3900
Kepala Tukang OH 0.0390
Mandor OH 0.0390
Jumlah Harga per Satuan Pekerjaan
Analisa C.7 Memasang 1 m 3 pondasi siklop, 60% beton campuran 1 PC : 2 PB : 3 KR dan 40% batu belah
Bahan Batu belah 15 cm/20 cm M3 0.4800
Semen Portland Kg 194.0000
Pasir Beton M3 0.3120
Koral Beton M3 0.4680
Besi Beton Kg 126.0000
Kawat Beton Kg 1.8000
Tenaga Kerja Pekerja OH 3.4000
Tukang Batu OH 0.8500
Kepala Tukang OH 0.0850
Mandor OH 0.1700
Jumlah Harga per Satuan Pekerjaan
Analisa C.8 Memasang 1 m3 pondasi sumuran, diameter 100 cm
Bahan Batu belah 15 cm/20 cm M3 0.4500
Semen Portland Kg 194.0000
Pasir Beton M3 0.3120
Koral Beton M3 0.4680
Tenaga Kerja Pekerja OH 2.4000
Tukang Batu OH 0.8000
Kepala Tukang OH 0.0800
Mandor OH 0.1190
Jumlah Harga per Satuan Pekerjaan
Analisa C.9 Memasang 1 m 3 pondasi batu belah, campuran 1 KP : 1 SM : 2 PP
Bahan Batu belah 15 cm/20 cm M3 1.2000
Kapur padam M3 0.1700
Semen Merah M3 0.1700
Pasir Pasang M3 0.3400
Tenaga Kerja Pekerja OH 1.5000
Tukang Batu OH 0.7500
Kepala Tukang OH 0.0750
Mandor OH 0.0750
Jumlah Harga per Satuan Pekerjaan
Analisa C.10 Memasang 1 m 3 pondasi batu belah, campuran 1 PC : 3 KP : 10 PP
Bahan Batu belah 15 cm/20 cm M3 1.2000
Semen Portland Kg 61.0000
Kapur padam M3 0.1470
Pasir Pasang M3 0.4920
Tenaga Kerja Pekerja OH 1.5000
Tukang Batu OH 0.7500
Kepala Tukang OH 0.0750
Mandor OH 0.0750
Jumlah Harga per Satuan Pekerjaan
Analisa C.11 Memasang 1 m 3 pondasi batu belah, campuran ¼ PC : 1 KP : 4 PP
Bahan Batu belah 15 cm/20 cm M3 1.2000
Semen Portland Kg 41.0000
Kapur padam M3 0.1310
Pasir Pasang M3 0.5230
Tenaga Kerja Pekerja OH 1.5000
Tukang Batu OH 0.7500
Kepala Tukang OH 0.0750
Mandor OH 0.0750
Jumlah Harga per Satuan Pekerjaan
D. PEKERJAAN DINDING
Analisa D.1 Memasang 1 m 2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata,campuran spesi 1 PC : 2 PP
Bahan Bata Merah Buah 140.0000
Semen Portland Kg 43.5000
Pasir Pasang M3 0.0800
Tenaga Kerja Pekerja OH 0.6000
Tukang Batu OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0300
Jumlah Harga per Satuan Pekerjaan
Analisa D.2 Memasang 1 m 2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata,campuran spesi 1 PC : 3 PP
Bahan Bata Merah Buah 140.0000
Semen Portland Kg 32.9500
Pasir Pasang M3 0.0910
Tenaga Kerja Pekerja OH 0.6000
Tukang Batu OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0300
Jumlah Harga per Satuan Pekerjaan
Analisa D.3 Memasang 1 m 2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata,campuran spesi 1 PC : 4 PP
Bahan Bata Merah Buah 140.0000
Semen Portland Kg 26.5500
Pasir Pasang M3 0.0930
Tenaga Kerja Pekerja OH 0.6000
Tukang Batu OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0300
Jumlah Harga per Satuan Pekerjaan
Analisa D.4 Memasang 1 m 2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata,campuran spesi 1 PC : 5 PP
Bahan Bata Merah Buah 140.0000
Semen Portland Kg 22.2000
Pasir Pasang M3 0.1020
Tenaga Kerja Pekerja OH 0.6000
Tukang Batu OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0300
Jumlah Harga per Satuan Pekerjaan
Analisa D.5 Memasang 1 m 2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata,campuran spesi 1 PC : 6 PP
Bahan Bata Merah Buah 140.0000
Semen Portland Kg 18.5000
Pasir Pasang M3 0.1220
Tenaga Kerja Pekerja OH 0.6000
Tukang Batu OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0300
Jumlah Harga per Satuan Pekerjaan
Analisa D.6 Memasang 1 m 2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata,campuran spesi 1 PC : 3 KP : 10 PP
Bahan Bata Merah Buah 140.0000
Semen Portland Kg 10.0800
Pasir Pasang M3 0.0925
Kapur padam M3 0.0275
Tenaga Kerja Pekerja OH 0.6000
Tukang Batu OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0300
Jumlah Harga per Satuan Pekerjaan
Analisa D.7 Memasang 1 m 2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata,campuran spesi 1 PC : 2 PP
Bahan Bata Merah Buah 70.0000
Semen Portland Kg 18.9500
Pasir Pasang M3 0.0380
Tenaga Kerja Pekerja OH 0.3000
Tukang Batu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0150
Jumlah Harga per Satuan Pekerjaan
Analisa D.8 Memasang 1 m 2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata,campuran spesi 1 PC : 3 PP
Bahan Bata Merah Buah 70.0000
Semen Portland Kg 14.3700
Pasir Pasang M3 0.0400
Tenaga Kerja Pekerja OH 0.3000
Tukang Batu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0150
Jumlah Harga per Satuan Pekerjaan
Analisa D.9 Memasang 1 m 2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata,campuran spesi 1 PC : 4 PP
Bahan Bata Merah Buah 70.0000
Semen Portland Kg 11.5000
Pasir Pasang M3 0.0430
Tenaga Kerja Pekerja OH 0.3000
Tukang Batu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0150
Jumlah Harga per Satuan Pekerjaan
Analisa D.10 Memasang 1 m 2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata,campuran spesi 1 PC : 5 PP
Bahan Bata Merah Buah 70.0000
Semen Portland Kg 9.6800
Pasir Pasang M3 0.0450
Tenaga Kerja Pekerja OH 0.3000
Tukang Batu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0150
Jumlah Harga per Satuan Pekerjaan
Analisa D.11 Memasang 1 m 2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata,campuran spesi 1 PC : 6 PP
Bahan Bata Merah Buah 70.0000
Semen Portland Kg 8.3200
Pasir Pasang M3 0.0490
Tenaga Kerja Pekerja OH 0.3000
Tukang Batu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0150
Jumlah Harga per Satuan Pekerjaan
Analisa D.12 Memasang 1 m 2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata,campuran spesi 1 PC : 8 PP
Bahan Bata Merah Buah 70.0000
Semen Portland Kg 6.5000
Pasir Pasang M3 0.0500
Tenaga Kerja Pekerja OH 0.3000
Tukang Batu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0150
Jumlah Harga per Satuan Pekerjaan
Analisa D.13 Memasang 1 m 2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata,campuran spesi 1 PC : 3 KP : 10 PP
Bahan Bata Merah Buah 70.0000
Semen Portland Kg 4.5000
Pasir Pasang M3 0.0500
Kapur padam M3 0.0150
Tenaga Kerja Pekerja OH 0.3000
Tukang Batu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0150
Jumlah Harga per Satuan Pekerjaan
Analisa D.14 Memasang 1 m 2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata,campuran spesi 1 KP : 1 SM : 1 PP
Bahan Bata Merah Buah 70.0000
Semen Merah M3 0.0180
Pasir Pasang M3 0.0180
Kapur padam M3 0.0180
Tenaga Kerja Pekerja OH 0.3000
Tukang Batu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0150
Jumlah Harga per Satuan Pekerjaan
Analisa D.15 Memasang 1 m 2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata,campuran spesi 1 KP : 1 SM : 2 PP
Bahan Bata Merah Buah 70.0000
Semen Merah M3 0.0140
Pasir Pasang M3 0.0280
Kapur padam M3 0.0140
Tenaga Kerja Pekerja OH 0.3000
Tukang Batu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0150
Jumlah Harga per Satuan Pekerjaan
Analisa D.16 Memasang 1 m 2 dinding HB/CB 20 , campuran spesi 1 PC : 3 PP
Bahan Hollow Block 20 Buah 12.5000
Semen Portland Kg 30.3200
Pasir Pasang M3 0.7280
Besi angkur diameter 8 mm Kg 0.2800
Tenaga Kerja Pekerja OH 0.3500
Tukang Batu OH 0.1500
Kepala Tukang OH 0.0150
Mandor OH 0.0180
Jumlah Harga per Satuan Pekerjaan
Analisa D.17 Memasang 1 m 2 dinding HB/CB 20 , campuran spesi 1 PC : 4 PP
Bahan Hollow Block 20 Buah 12.5000
Semen Portland Kg 24.2600
Pasir Pasang M3 0.7720
Besi angkur diameter 8 mm Kg 0.2800
Tenaga Kerja Pekerja OH 0.3500
Tukang Batu OH 0.1500
Kepala Tukang OH 0.0150
Mandor OH 0.0180
Jumlah Harga per Satuan Pekerjaan
Analisa D.18 Memasang 1 m 2 dinding HB/CB 15, campuran spesi 1 PC : 3 PP
Bahan Hollow Block 15 Buah 12.5000
Semen Portland Kg 22.7400
Pasir Pasang M3 0.5500
Besi angkur diameter 8 mm Kg 0.2800
Tenaga Kerja Pekerja OH 0.3200
Tukang Batu OH 0.1200
Kepala Tukang OH 0.0120
Mandor OH 0.0160
Jumlah Harga per Satuan Pekerjaan
Analisa D.19 Memasang 1 m 2 dinding HB/CB 15, campuran spesi 1 PC : 4 PP
Bahan Hollow Block 15 Buah 12.5000
Semen Portland Kg 18.2000
Pasir Pasang M3 0.5820
Besi angkur diameter 8 mm Kg 0.2800
Tenaga Kerja Pekerja OH 0.3200
Tukang Batu OH 0.1200
Kepala Tukang OH 0.0120
Mandor OH 0.0160
Jumlah Harga per Satuan Pekerjaan
Analisa D.20 Memasang 1 m 2 dinding HB/CB 10, campuran spesi 1 PC : 3 PP
Bahan Hollow Block 10 Buah 12.5000
Semen Portland Kg 15.1600
Pasir Pasang M3 0.3640
Besi angkur diameter 8 mm Kg 0.2800
Tenaga Kerja Pekerja OH 0.3000
Tukang Batu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0150
Jumlah Harga per Satuan Pekerjaan
Analisa D.21 Memasang 1 m 2 dinding HB/CB 10, campuran spesi 1 PC : 4 PP
Bahan Hollow Block 10 Buah 12.5000
Semen Portland Kg 12.1300
Pasir Pasang M3 0.3880
Besi angkur diameter 8 mm Kg 0.2800
Tenaga Kerja Pekerja OH 0.3000
Tukang Batu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0150
Jumlah Harga per Satuan Pekerjaan
Analisa D.22 Memasang 1 m 2 dinding terawang (roster) ukuran (12 x 11 x 24) cm, campuran spesi 1 PC : 3 PP
Bahan Terawang (Roster) Buah 30.0000
Semen Portland Kg 14.0000
Pasir Pasang M3 0.0320
Tenaga Kerja Pekerja OH 0.3000
Tukang Batu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0150
Jumlah Harga per Satuan Pekerjaan
Analisa D.23 Memasang 1 m 2 dinding terawang (roster) ukuran (12 x 11 x 24) cm, campuran spesi 1 PC : 4 PP
Bahan Terawang (Roster) Buah 30.0000
Semen Portland Kg 11.0000
Pasir Pasang M3 0.0350
Tenaga Kerja Pekerja OH 0.3000
Tukang Batu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0150
Jumlah Harga per Satuan Pekerjaan
E. PEKERJAAN PLESTERAN
Analisa E.1 1 m2 Plesteran Dinding 1Pc : 3Ps
Bahan Semen Portland Kg 6.4800
Pasir pasang M3 0.0190
Tenaga Kerja Pekerja OH 0.2000
Tukang Batu OH 0.1500
Kepala Tukang OH 0.0150
Mandor OH 0.0100
Jumlah Harga per Satuan Pekerjaan
Analisa E.2 1 m2 Plesteran Dinding 1Pc : 5Ps
Bahan Semen Portland Kg 4.3200
Pasir pasang M3 0.0220
Tenaga Kerja Pekerja OH 0.2000
Tukang Batu OH 0.1500
Kepala Tukang OH 0.0150
Mandor OH 0.0100
Jumlah Harga per Satuan Pekerjaan
Analisa E.3 1 m2 Plesteran Dinding 1Pc : 0. 5Kp : 3 Ps, tebal 15 mm
Bahan Semen Portland Kg 4.3200
Kapur Padam M3 0.0030
Pasir pasang M3 0.0130
Tenaga Kerja Pekerja OH 0.2000
Tukang Batu OH 0.1500
Kepala Tukang OH 0.0150
Mandor OH 0.0100
Jumlah Harga per Satuan Pekerjaan
Analisa E.4 1 m2 Plesteran Dinding 1Pc : 3Kp : 10Ps, tebal 15 mm
Bahan Semen Portland Kg 1.8400
Kapur Padam M3 0.0060
Pasir pasang M3 0.0140
Tenaga Kerja Pekerja OH 0.2000
Tukang Batu OH 0.1500
Kepala Tukang OH 0.0150
Mandor OH 0.0100
Jumlah Harga per Satuan Pekerjaan
Analisa E.5 1 m2 Plesteran 0.5 Pc : 1Kp : 4Ps, tebal 15 mm
Bahan Semen Portland Kg 3.0000
Kapur Padam M3 0.0050
Pasir pasang M3 0.0190
Tenaga Kerja Pekerja OH 0.2000
Tukang Batu OH 0.1500
Kepala Tukang OH 0.0150
Mandor OH 0.0100
Jumlah Harga per Satuan Pekerjaan
Analisa E.6 1 m2 Plesteran 1Kp : 1 Sm : 1 Ps, tebal 15 mm
Bahan Semen Merah Kg 0.0090
Kapur Padam M3 0.0090
Pasir pasang M3 0.0090
Tenaga Kerja Pekerja OH 0.2000
Tukang Batu OH 0.1500
Kepala Tukang OH 0.0150
Mandor OH 0.0100
Jumlah Harga per Satuan Pekerjaan
Analisa E.7 1 m2 Plesteran 1Pc : 2 Ps, tebal 20 mm
Bahan Semen Portland Kg 13.6320
Pasir pasang M3 0.0270
Tenaga Kerja Pekerja OH 0.4000
Tukang Batu OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0220
Jumlah Harga per Satuan Pekerjaan
Analisa E.8 1 m2 Plesteran 1Pc : 3 Ps, tebal 20 mm
Bahan Semen Portland Kg 10.3680
Pasir pasang M3 0.0310
Tenaga Kerja Pekerja OH 0.2600
Tukang Batu OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0130
Jumlah Harga per Satuan Pekerjaan
Analisa E.9 1 m2 Plesteran 1Pc : 4Ps, tebal 20 mm
Bahan Semen Portland Kg 8.3200
Pasir pasang M3 0.0320
Tenaga Kerja Pekerja OH 0.4000
Tukang Batu OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0220
Jumlah Harga per Satuan Pekerjaan
Analisa E.10 1 m2 Plesteran 1Pc : 5Ps, tebal 20 mm
Bahan Semen Portland Kg 6.9120
Pasir pasang M3 0.0350
Tenaga Kerja Pekerja OH 0.4000
Tukang Batu OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0220
Jumlah Harga per Satuan Pekerjaan
Analisa E.11 1 m2 Plesteran 1Pc : 6Ps, tebal 20 mm
Bahan Semen Portland Kg 5.8880
Pasir pasang M3 0.0360
Tenaga Kerja Pekerja OH 0.4000
Tukang Batu OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0220
Jumlah Harga per Satuan Pekerjaan
Analisa E.12 1 m2 Plesteran 1Kp : 1 Sm : 2Ps, tebal 15 mm
Bahan Semen Merah Kg 0.0090
Kapur Padam M3 0.0090
Pasir pasang M3 0.0180
Tenaga Kerja Pekerja OH 0.2500
Tukang Batu OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0125
Jumlah Harga per Satuan Pekerjaan
Analisa E.13 1 m2 Plesteran 1Pc : 2Ps, tebal 25 mm
Bahan Semen Portland Kg 15.5000
Pasir pasang M3 0.0130
Tenaga Kerja Pekerja OH 0.3000
Tukang Batu OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0130
Jumlah Harga per Satuan Pekerjaan
Analisa E.14 1 m2 Plesteran 1Pc : 3 Ps, tebal 25 mm
Bahan Semen Portland Kg 11.7500
Pasir pasang M3 0.0350
Tenaga Kerja Pekerja OH 0.3000
Tukang Batu OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0130
Jumlah Harga per Satuan Pekerjaan
Analisa E.15 1 m2 Plesteran 1Pc : 4 Ps, tebal 25 mm
Bahan Semen Portland Kg 9.4800
Pasir pasang M3 0.0380
Tenaga Kerja Pekerja OH 0.3000
Tukang Batu OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0130
Jumlah Harga per Satuan Pekerjaan
Analisa E.16 1 m2 Plesteran 1Pc : 5 Ps, tebal 25 mm
Bahan Semen Portland Kg 7.9400
Pasir pasang M3 0.0390
Tenaga Kerja Pekerja OH 0.3000
Tukang Batu OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0130
Jumlah Harga per Satuan Pekerjaan
Analisa E.17 1 m2 Plesteran 1Pc : 2 Ps, tebal 30 mm
Bahan Semen Portland Kg 18.6500
Pasir pasang M3 0.0350
Tenaga Kerja Pekerja OH 0.3200
Tukang Batu OH 0.2500
Kepala Tukang OH 0.0250
Mandor OH 0.0150
Jumlah Harga per Satuan Pekerjaan
Analisa E.18 1 m2 Plesteran 1Pc : 3 Ps, tebal 30 mm
Bahan Semen Portland Kg 14.1500
Pasir pasang M3 0.0390
Tenaga Kerja Pekerja OH 0.3200
Tukang Batu OH 0.2500
Kepala Tukang OH 0.0250
Mandor OH 0.0150
Jumlah Harga per Satuan Pekerjaan
Analisa E.19 1 m2 Plesteran 1Pc : 5 Ps, tebal 30 mm
Bahan Semen Portland Kg 8.1900
Pasir pasang M3 0.0450
Tenaga Kerja Pekerja OH 0.3200
Tukang Batu OH 0.2500
Kepala Tukang OH 0.0250
Mandor OH 0.0150
Jumlah Harga per Satuan Pekerjaan
Analisa E.20 1 m2 Berapen 1Pc : 3 Ps, tebal 30 mm
Bahan Semen Portland Kg 7.0700
Pasir pasang M3 0.0210
Tenaga Kerja Pekerja OH 0.1500
Tukang Batu OH 0.0700
Kepala Tukang OH 0.0070
Mandor OH 0.0080
Jumlah Harga per Satuan Pekerjaan
Analisa E.21 1 m2 Berapen 1Pc : 5 Ps, tebal 15 mm
Bahan Semen Portland Kg 5.6700
Pasir pasang M3 0.0230
Tenaga Kerja Pekerja OH 0.1500
Tukang Batu OH 0.0700
Kepala Tukang OH 0.0070
Mandor OH 0.0080
Jumlah Harga per Satuan Pekerjaan
Analisa E.22 1 m2 Pelesteran Beton 1Pc : 2Ps, tebal 15 mm
Bahan Semen Portland Kg 9.3000
Pasir pasang M3 0.0180
Tenaga Kerja Pekerja OH 0.2600
Tukang Batu OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0130
Jumlah Harga per Satuan Pekerjaan
Analisa E.23 1 m2 Pelesteran Beton 1Pc : 3Ps, tebal 15 mm
Bahan Semen Portland Kg 7.0700
Pasir pasang M3 0.0210
Tenaga Kerja Pekerja OH 0.2600
Tukang Batu OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0130
Jumlah Harga per Satuan Pekerjaan
Analisa E.24 1 m2 Pelesteran Skoring 1Pc : 2Ps
Bahan Semen Portland Kg 0.5000
Pasir pasang M3 0.0020
Tenaga Kerja Pekerja OH 0.0570
Tukang Batu OH 0.0380
Kepala Tukang OH 0.0380
Mandor OH 0.0020
Jumlah Harga per Satuan Pekerjaan
Analisa E.25 1 m2 Pelesteran Ciprat 1 Pc : 2 Ps
Bahan Semen Portland Kg 4.3200
Pasir pasang M3 0.0160
Tenaga Kerja Pekerja OH 0.2500
Tukang Batu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0150
Jumlah Harga per Satuan Pekerjaan
Analisa E.26 1 m2 Plesteran Dinding 1 : 3 + Acian
Bahan Semen Portland Kg 8.0000
Pasir pasang M3 0.0260
Tenaga Kerja Pekerja OH 0.2250
Tukang Batu OH 0.1525
Kepala Tukang OH 0.0100
Mandor OH 0.0080
Jumlah Harga per Satuan Pekerjaan
Analisa E.27 1 m2 Plesteran Dinding 1 : 5 + Acian
Bahan Semen Portland Kg 5.4000
Pasir pasang M3 0.0280
Tenaga Kerja Pekerja OH 0.2250
Tukang Batu OH 0.1525
Kepala Tukang OH 0.0100
Mandor OH 0.0080
Jumlah Harga per Satuan Pekerjaan
Analisa E.28 1 m2 Floor lantai kramik 1Pc : 5Ps, tebal 5 mm
Bahan Semen Portland Kg 15.8800
Pasir pasang M3 0.0780
Tenaga Kerja Pekerja OH 0.6000
Tukang Batu OH 0.4000
Kepala Tukang OH 0.0400
Mandor OH 0.0260
Jumlah Harga per Satuan Pekerjaan
Analisa E.29 200 M' Pekerjaan Profil Semen
Bahan Semen Portland Kg 1,350.0000
Pasir pasang M3 2.3200
Tenaga Kerja Pekerja OH 120.0000
Tukang Batu OH 12.0000
Kepala Tukang OH 320.0000
Mandor OH 16.0000
200 Meter Jumlah Harga per Satuan Pekerjaan
1 Meter Jumlah Harga per Satuan Pekerjaan
Analisa E.30 1 M2 Plesteran Halus 1 PC : 4 Ps Tebal 1,50 cm
Bahan Semen Portland Kg 5.7250
Pasir pasang M3 0.0170
Tenaga Kerja Pekerja OH 0.2000
Tukang Batu OH 0.1500
Kepala Tukang OH 0.0150
Mandor OH 0.0100
Jumlah Harga per Satuan Pekerjaan
F. PEKERJAAN KAYU
Analisa F.1 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu kelas I
Bahan Kayu Kelas I (Balok) M3 1.1000
Paku 5 cm - 12 cm Kg 1.2500
Lem kayu Kg 1.0000
Tenaga Kerja Pekerja OH 7.0000
Tukang Kayu OH 21.0000
Kepala Tukang OH 2.1000
Mandor OH 0.3500
Jumlah Harga per Satuan Pekerjaan
Analisa F.2 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu kelas II
Bahan Kayu Kelas II (Balok) M3 1.2000
Paku 5 cm - 12 cm Kg 1.2500
Lem kayu Kg 1.0000
Tenaga Kerja Pekerja OH 6.0000
Tukang Kayu OH 18.0000
Kepala Tukang OH 1.8000
Mandor OH 0.3000
Jumlah Harga per Satuan Pekerjaan
Analisa F.3 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, Kayu Kelasd III
Bahan Kayu Kelas III (Balok) M3 1.2000
Paku 5 cm - 12 cm Kg 1.2500
Lem kayu Kg 1.0000
Tenaga Kerja Pekerja OH 6.0000
Tukang Kayu OH 18.0000
Kepala Tukang OH 1.8000
Mandor OH 0.3000
Jumlah Harga per Satuan Pekerjaan
Analisa F.4 Membuat dan memasang 1 m2 pintu klamp standar, kayu kelas II
Bahan Kayu Kelas II (Balok) M3 0.0400
Paku 5 cm - 12 cm Kg 0.0500
Tenaga Kerja Pekerja OH 0.3500
Tukang Kayu OH 1.0500
Kepala Tukang OH 0.1050
Mandor OH 0.0180
Jumlah Harga per Satuan Pekerjaan
Analisa F.5 Membuat dan memasang 1 m2 pintu klamp sederhana, kayu kelas III untuk Gudang Sementara
Bahan Kayu kelas III (papan) M3 0.0400
Paku 5 cm - 12 cm Kg 0.0500
Tenaga Kerja Pekerja OH 0.3500
Tukang Kayu OH 1.0500
Kepala Tukang OH 0.1050
Mandor OH 0.0180
Jumlah Harga per Satuan Pekerjaan
Analisa F.6 Membuat dan memasang 1 m2 daun pintu panel, kayu kelas I
Bahan Kayu Kelas I (Papan) M3 0.0400
Lem kayu Kg 0.5000
Tenaga Kerja Pekerja OH 1.0000
Tukang Kayu OH 3.0000
Kepala Tukang OH 0.3000
Mandor OH 0.0500
Jumlah Harga per Satuan Pekerjaan
Analisa F.7 Membuat dan memasang 1 m2 daun pintu panel, kayu kelas II
Bahan Kayu Kelas II (Papan) M3 0.0400
Lem kayu Kg 0.5000
Tenaga Kerja Pekerja OH 1.0000
Tukang Kayu OH 3.0000
Kepala Tukang OH 0.3000
Mandor OH 0.0500
Jumlah Harga per Satuan Pekerjaan
Analisa F.8 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu kelas I
Bahan Kayu Kelas I (Papan) M3 0.0240
Lem kayu Kg 0.3000
Tenaga Kerja Pekerja OH 0.8000
Tukang Kayu OH 2.4000
Kepala Tukang OH 0.2400
Mandor OH 0.0400
Jumlah Harga per Satuan Pekerjaan
Analisa F.9 Membuat dan memasang 1 m2 pintu dan jendela jalusi kayu kelas I
Bahan Kayu Kelas I (Papan) M3 0.0640
Lem kayu Kg 0.5000
Tenaga Kerja Pekerja OH 1.0000
Tukang Kayu OH 3.0000
Kepala Tukang OH 0.3000
Mandor OH 0.0500
Jumlah Harga per Satuan Pekerjaan
Analisa F.10 Membuat dan memasang 1 m2 pintu dan jendela jalusi kayu kelas II
Bahan Kayu Kelas II (Papan) M3 0.0640
Lem kayu Kg 0.5000
Tenaga Kerja Pekerja OH 1.0000
Tukang Kayu OH 3.0000
Kepala Tukang OH 0.3000
Mandor OH 0.0500
Jumlah Harga per Satuan Pekerjaan
Analisa F.11 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu kelas II
Bahan Kayu Kelas II (Papan) M3 0.0240
Lem kayu Kg 0.3000
Tenaga Kerja Pekerja OH 0.8000
Tukang Kayu OH 2.4000
Kepala Tukang OH 0.2400
Mandor OH 0.0400
Jumlah Harga per Satuan Pekerjaan
Analisa F.12 Membuat 1 m2 daun pintu kayu lapis (plywood) rangkap, rangka tertutup kayu Kelas II (Lebar sampai 90 cm)
Bahan Kayu Kelas II (Papan) M3 0.0250
Paku 1 cm - 2,5 cm Kg 0.0300
Lem kayu Kg 0.5000
Plywood tebal 4 mm Uk. (90 x 220) cm Lembar 1.0000
Tenaga Kerja Pekerja OH 0.7000
Tukang Kayu OH 2.1000
Kepala Tukang OH 0.2100
Mandor OH 0.0350
Jumlah Harga per Satuan Pekerjaan
Analisa F.13 Membuat 1 m2 pintu plywood rangkap, rangka expose kayu kelas I
Bahan Kayu Kelas I (Papan) M3 0.0256
Paku 1 cm - 2,5 cm Kg 0.0300
Lem kayu Kg 0.5000
Plywood tebal 4 mm Uk. (90 x 220) cm Lembar 1.0000
Tenaga Kerja Pekerja OH 0.8000
Tukang Kayu OH 2.4000
Kepala Tukang OH 0.2400
Mandor OH 0.0400
Jumlah Harga per Satuan Pekerjaan
Analisa F.14 Membuat 1 m2 pintu plywood rangkap, rangka expose kayu kelas II
Bahan Kayu Kelas II (Papan) M3 0.0256
Paku 1 cm - 2,5 cm Kg 0.0300
Lem kayu Kg 0.5000
Plywood tebal 4 mm Uk. (90 x 220) cm Lembar 1.0000
Tenaga Kerja Pekerja OH 0.8000
Tukang Kayu OH 2.4000
Kepala Tukang OH 0.2400
Mandor OH 0.0400
Jumlah Harga per Satuan Pekerjaan
Analisa F.15 Memasang 1 m2 jalusi kusen, kayu kelas I
Bahan Kayu Kelas I (Papan) M3 0.0600
Paku 1 cm - 2,5 cm Kg 0.1500
Tenaga Kerja Pekerja OH 0.6700
Tukang Kayu OH 2.0000
Kepala Tukang OH 0.2000
Mandor OH 0.3350
Jumlah Harga per Satuan Pekerjaan
Analisa F.16 Memasang 1 m2 jalusi kusen, kayu kelas II
Bahan Kayu Kelas II (Papan) M3 0.0600
Paku 1 cm - 2,5 cm Kg 0.1500
Tenaga Kerja Pekerja OH 0.6700
Tukang Kayu OH 2.0000
Kepala Tukang OH 0.2000
Mandor OH 0.3350
Jumlah Harga per Satuan Pekerjaan
Analisa F.17 Memasang 1 m2 teakwood rangkap, rangka expose kayu kelas I
Bahan Kayu Kelas I (Papan) M3 0.0250
Paku 1 cm - 2,5 cm Kg 0.0300
Lem kayu Kg 0.3000
Teakwood tebal 4 mm, Uk. 90 cm x 220 cm Lembar 1.0000
Tenaga Kerja Pekerja OH 0.8000
Tukang Kayu OH 2.4000
Kepala Tukang OH 0.2400
Mandor OH 0.0400
Jumlah Harga per Satuan Pekerjaan
Analisa F.18 Memasang 1 m2 teakwood rangkap lapis formika, rangka expose kayu kelas II
Bahan Kayu Kelas II (Papan) M3 0.0250
Paku 1 cm - 2,5 cm Kg 0.0300
Lem kayu Kg 0.8000
Teakwood tebal 4 mm, Uk. 90 cm x 220 cm Lembar 1.0000
Formika Lembar 0.5000
Tenaga Kerja Pekerja OH 0.8500
Tukang Kayu OH 2.5500
Kepala Tukang OH 0.2550
Mandor OH 0.0430
Jumlah Harga per Satuan Pekerjaan
Analisa F.19 Memasang 1 m3 konstruksi kuda-kuda konvensional, kayu kelas I bentang 6 Meter
Bahan Kayu Kelas I (Balok) M3 1.1000
Besi strip tebal 5 mm Kg 15.0000
Paku 5 cm - 12 cm Kg 5.6000
Tenaga Kerja Pekerja OH 4.0000
Tukang Kayu OH 12.0000
Kepala Tukang OH 1.2000
Mandor OH 0.2000
Jumlah Harga per Satuan Pekerjaan
Analisa F.20 Memasang 1 m3 konstruksi kuda-kuda konvensional, kayu kelas II bentang 6 Meter
Bahan Kayu Kelas II (Balok) M3 1.1000
Besi strip tebal 5 mm Kg 15.0000
Paku 5 cm - 12 cm Kg 5.6000
Tenaga Kerja Pekerja OH 4.0000
Tukang Kayu OH 12.0000
Kepala Tukang OH 1.2000
Mandor OH 0.2000
Jumlah Harga per Satuan Pekerjaan
Analisa F.21 Memasang 1 m3 konstruksi kuda-kuda konvensional, kayu kelas III bentang 6 Meter
Bahan Kayu Kelas III (Balok) M3 1.1000
Besi strip tebal 5 mm Kg 15.0000
Paku 5 cm - 12 cm Kg 5.6000
Tenaga Kerja Pekerja OH 4.0000
Tukang Kayu OH 12.0000
Kepala Tukang OH 1.2000
Mandor OH 0.2000
Jumlah Harga per Satuan Pekerjaan
Analisa F.22 Memasang 1 m3 konstruksi kuda-kuda expose, kayu kelas I
Bahan Kayu Kelas I (Balok) M3 1.2000
Besi strip tebal 5 mm Kg 15.0000
Paku 5 cm - 12 cm Kg 5.6000
Tenaga Kerja Pekerja OH 6.7000
Tukang Kayu OH 20.1000
Kepala Tukang OH 2.0100
Mandor OH 0.3350
Jumlah Harga per Satuan Pekerjaan
Analisa F.23 Memasang 1 m3 konstruksi Gordeng, kayu kelas II
Bahan Kayu Kelas II (Balok) M3 1.1000
Besi strip tebal 5 mm Kg 15.0000
Paku 5 cm - 12 cm Kg 3.0000
Tenaga Kerja Pekerja OH 2.4000
Tukang Kayu OH 7.2000
Kepala Tukang OH 0.7200
Mandor OH 0.1200
Jumlah Harga per Satuan Pekerjaan
Analisa F.24 Pemasang 1 m2 rangka atap genteng keramik, kayu kelas II
Bahan Kayu Kelas II ( 5 x 7 cm) M3 0.0140
Kayu Kelas II ( 2 x 3 Cm) M3 0.0036
Paku 5 cm - 12 cm Kg 0.2500
Tenaga Kerja Pekerja OH 0.1000
Tukang Kayu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0050
Jumlah Harga per Satuan Pekerjaan
Analisa F.25 Memasang 1 m2 rangka atap genteng beton, kayu kelas II
Bahan Kayu Kelas II ( 5 x 7 cm) M3 0.0140
Kayu Kelas II ( 3 x 4 Cm) M3 0.0072
Paku 5 cm - 12 cm Kg 0.2500
Tenaga Kerja Pekerja OH 0.1000
Tukang Kayu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0050
Jumlah Harga per Satuan Pekerjaan
Analisa F.26 Memasang 1 m2 rangka atap sirap, kayu kelas II
Bahan Kayu Kelas II (Balok) M3 0.1650
Paku 5 cm - 12 cm Kg 0.2000
Tenaga Kerja Pekerja OH 0.1200
Tukang Kayu OH 0.1200
Kepala Tukang OH 0.0120
Mandor OH 0.0060
Jumlah Harga per Satuan Pekerjaan
Analisa F.27 Memasang 1 m2 rangka langit-langit (50 x 100) cm, kayu kelas II
Bahan Kayu Kelas II ( 5 x 7 cm) M3 0.0154
Paku 5 cm - 12 cm Kg 0.2000
Tenaga Kerja Pekerja OH 0.1500
Tukang Kayu OH 0.3000
Kepala Tukang OH 0.0300
Mandor OH 0.0750
Jumlah Harga per Satuan Pekerjaan
Analisa F.28 Memasang 1 m2 rangka langit-langit (50 x 100) cm, kayu kelas III
Bahan Kayu Kelas III ( 5 x 7 cm) M3 0.0154
Paku 5 cm - 12 cm Kg 0.2000
Tenaga Kerja Pekerja OH 0.1500
Tukang Kayu OH 0.3000
Kepala Tukang OH 0.0300
Mandor OH 0.0750
Jumlah Harga per Satuan Pekerjaan
Analisa F.29 Pasang 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas II
Bahan Kayu Kelas II ( 5 x 7 cm) M3 0.0163
Paku 5 cm - 12 cm Kg 0.2500
Tenaga Kerja Pekerja OH 0.2000
Tukang Kayu OH 0.3000
Kepala Tukang OH 0.0300
Mandor OH 0.0100
Jumlah Harga per Satuan Pekerjaan
Analisa F.30 Pasang 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas III
Bahan Kayu Kelas III ( 5 x 7 cm) M3 0.0163
Paku 5 cm - 12 cm Kg 0.2500
Tenaga Kerja Pekerja OH 0.2000
Tukang Kayu OH 0.3000
Kepala Tukang OH 0.0300
Mandor OH 0.0100
Jumlah Harga per Satuan Pekerjaan
Analisa F.31 Memasang 1 m1 lisplank ukuran (3 x 20) cm, kayu kelas I
Bahan Kayu Kelas I (Papan) M3 0.0108
Paku 5 cm - 12 cm Kg 0.1000
Tenaga Kerja Pekerja OH 0.1000
Tukang Kayu OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0050
Jumlah Harga per Satuan Pekerjaan
Analisa F.32 Memasang 1 m1 lisplank ukuran (3 x 20) cm, kayu kelas II
Bahan Kayu Kelas II (Papan) M3 0.0108
Paku 5 cm - 7 cm Kg 0.1000
Tenaga Kerja Pekerja OH 0.1000
Tukang Kayu OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0050
Jumlah Harga per Satuan Pekerjaan
Analisa F.33 Memasang 1 m1 lisplank ukuran (3 x 30) cm, kayu kelas I
Bahan Kayu Kelas I (Papan) M3 0.0110
Paku 5 cm - 12 cm Kg 0.0500
Tenaga Kerja Pekerja OH 0.1000
Tukang Kayu OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0050
Jumlah Harga per Satuan Pekerjaan
Analisa F.34 Memasang 1 m1 lisplank ukuran (3 x 30) cm, kayu kelas II
Bahan Kayu Kelas II (Papan) M3 0.0110
Paku 5 cm - 12 cm Kg 0.0500
Tenaga Kerja Pekerja OH 0.1000
Tukang Kayu OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0050
Jumlah Harga per Satuan Pekerjaan
Analisa F.35 Memasang 1 m2 rangka dinding pemisah (60 x 120) cm kayu kelas II
Bahan Kayu Kelas II (Balok) M3 0.0280
Paku 5 cm - 12 cm Kg 0.1500
Tenaga Kerja Pekerja OH 0.1500
Tukang Kayu OH 0.4500
Kepala Tukang OH 0.0450
Mandor OH 0.0080
Jumlah Harga per Satuan Pekerjaan
Analisa F.36 Memasang 1 m2 rangka dinding pemisah (60 x 120) cm kayu kelas III
Bahan Kayu Kelas III (Balok) M3 0.0280
Paku 5 cm - 12 cm Kg 0.1500
Tenaga Kerja Pekerja OH 0.1500
Tukang Kayu OH 0.4500
Kepala Tukang OH 0.0450
Mandor OH 0.0080
Jumlah Harga per Satuan Pekerjaan
Analisa F.37 Memasang 1 m2 dinding pemisah teakwood rangkap, rangka kayu kelas II (Kayu 6 x 12 cm)
Bahan Kayu Kelas II (Balok) M3 0.0280
Paku 5 cm - 12 cm Kg 0.1500
Teakwood tebal 4 mm, Uk. 120 cm x 240 cm Lembar 0.8600
Lem kayu Kg 0.5600
Tenaga Kerja Pekerja OH 0.1500
Tukang Kayu OH 0.4500
Kepala Tukang OH 0.0450
Mandor OH 0.0080
Jumlah Harga per Satuan Pekerjaan
Analisa F.38 Memasang 1 m2 dinding pemisah plywood rangkap, rangka kayu kelas II (Kayu Balok 6 x 12 Cm)
Bahan Kayu Kelas II (Balok) M3 0.0280
Paku 5 cm - 12 cm Kg 0.1500
Plywood tebal 4 mm Uk. (120 x 240) cm Lembar 0.8600
Lem kayu Kg 0.5600
Tenaga Kerja Pekerja OH 0.2000
Tukang Kayu OH 0.6000
Kepala Tukang OH 0.0600
Mandor OH 0.0100
Jumlah Harga per Satuan Pekerjaan
Analisa F.39 Memasang 1 m2 dinding lambriziring dari papan kayu kelas I
Bahan Kayu Kelas I (Papan) M3 0.0070
Paku 5 cm - 12 cm Kg 0.1000
Paku skrup 10 cm Kg 0.1500
Tenaga Kerja Pekerja OH 0.6000
Tukang Kayu OH 1.8000
Kepala Tukang OH 0.1800
Mandor OH 0.0300
Jumlah Harga per Satuan Pekerjaan
Analisa F.40 Memasang 1 m2 dinding lambriziring dari plywood ukuran (120 x 240) cm
Bahan Plywood tebal 4 mm Uk. (120 x 240) cm Lembar 0.4000
Paku 1 cm - 2,5 cm Kg 0.0500
Tenaga Kerja Pekerja OH 0.0250
Tukang Kayu OH 0.0750
Kepala Tukang OH 0.0080
Mandor OH 0.0010
Jumlah Harga per Satuan Pekerjaan
Analisa F.41 Memasang 1 m2 dinding bilik, rangka kayu kelas III atau Kelas IV
Bahan Bilik bambu M2 1.5000
Kayu Kelas III ( 5 x 7 cm) M3 0.0140
Paku 5 cm - 12 cm Kg 0.0120
Lis Kayu Profil Uk. 2 x 4 cm M3 0.0030
Tenaga Kerja Pekerja OH 0.1000
Tukang Kayu OH 0.0500
Kepala Tukang OH 0.0050
Mandor OH 0.0050
Jumlah Harga per Satuan Pekerjaan
G. PEKERJAAN BETON
Analisa G.1 Membuat 1 m 3 beton mutu f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87
Bahan Semen Portland Kg 247.0000
Pasir Beton M3 0.8690
Koral beton M3 0.9990
Air Liter 215.0000
Tenaga Kerja Pekerja OH 1.6500
Tukang Batu OH 0.2750
Kepala Tukang OH 0.0280
Mandor OH 0.0830
Jumlah Harga per Satuan Pekerjaan
Analisa G.2 Membuat 1 m 3 beton mutu f’c = 9,8 MPa (K 125), slump (12 ± 2) cm, w/c = 0,78
Bahan Semen Portland Kg 276.0000
Pasir Beton M3 0.8280
Koral Beton M3 1.0120
Air Liter 215.0000
Tenaga Kerja Pekerja OH 1.6500
Tukang Batu OH 0.2750
Kepala Tukang OH 0.0280
Mandor OH 0.0830
Jumlah Harga per Satuan Pekerjaan
Analisa G.3 Membuat 1 m 3 beton mutu f’c = 12,2 MPa (K 150), slump (12 ± 2) cm, w/c = 0,72
Bahan Semen Portland Kg 299.0000
Pasir Beton M3 0.7990
Koral beton M3 1.0170
Air Liter 215.0000
Tenaga Kerja Pekerja OH 1.6500
Tukang Batu OH 0.2750
Kepala Tukang OH 0.0280
Mandor OH 0.0830
Jumlah Harga per Satuan Pekerjaan
Analisa G.4 Membuat 1 m 3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (3-6) cm,w/c = 0,87
Bahan Semen Portland Kg 230.0000
Pasir Beton M3 0.8930
Koral beton M3 1.0270
Air Liter 200.0000
Tenaga Kerja Pekerja OH 1.2000
Tukang Batu OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0600
Jumlah Harga per Satuan Pekerjaan
Analisa G.5 Membuat 1 m 3 beton mutu f’c = 14,5 MPa (K 175), slump (12 ± 2) cm, w/c = 0,66
Bahan Semen Portland Kg 326.0000
Pasir Beton M3 0.7600
Koral beton M3 1.0290
Air Liter 215.0000
Tenaga Kerja Pekerja OH 1.6500
Tukang Batu OH 0.2750
Kepala Tukang OH 0.0280
Mandor OH 0.0083
Jumlah Harga per Satuan Pekerjaan
Analisa G.6 Membuat 1 m 3 beton mutu f’c = 16,9 MPa (K 200), slump (12 ± 2) cm, w/c = 0,61
Bahan Semen Portland Kg 352.0000
Pasir Beton M3 0.7310
Koral beton M3 1.0310
Air Liter 215.0000
Tenaga Kerja Pekerja OH 1.6500
Tukang Batu OH 0.2750
Kepala Tukang OH 0.0280
Mandor OH 0.0830
Jumlah Harga per Satuan Pekerjaan
Analisa G.7 Membuat 1 m 3 beton mutu f’c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,58
Bahan Semen Portland Kg 371.0000
Pasir Beton M3 0.6980
Koral beton M3 1.0470
Air Liter 215.0000
Tenaga Kerja Pekerja OH 1.6500
Tukang Batu OH 0.2750
Kepala Tukang OH 0.0280
Mandor OH 0.0830
Jumlah Harga per Satuan Pekerjaan
Analisa G.8 Membuat 1 m 3 beton mutu f’c = 21,7 MPa (K 250), slump (12 ± 2) cm, w/c = 0,56
Bahan Semen Portland Kg 384.0000
Pasir Beton M3 0.6920
Koral beton M3 1.0390
Air Liter 215.0000
Tenaga Kerja Pekerja OH 1.6500
Tukang Batu OH 0.2750
Kepala Tukang OH 0.0280
Mandor OH 0.0830
Jumlah Harga per Satuan Pekerjaan
Analisa G.9 Membuat 1 m 3 beton mutu f’c = 24,0 MPa (K 275), slump (12 ± 2) cm, w/c = 0,53
Bahan Semen Portland Kg 406.0000
Pasir Beton M3 0.6840
Koral beton M3 1.0260
Air Liter 215.0000
Tenaga Kerja Pekerja OH 1.6500
Tukang Batu OH 0.2750
Kepala Tukang OH 0.0280
Mandor OH 0.0830
Jumlah Harga per Satuan Pekerjaan
Analisa G.10 Membuat 1 m 3 beton mutu f’c = 26,4 MPa (K 300), slump (12 ± 2) cm, w/c = 0,52
Bahan Semen Portland Kg 413.0000
Pasir Beton M3 0.6810
Koral beton M3 1.0210
Air Liter 215.0000
Tenaga Kerja Pekerja OH 1.6500
Tukang Batu OH 0.2750
Kepala Tukang OH 0.0280
Mandor OH 0.0830
Jumlah Harga per Satuan Pekerjaan
Analisa G.11 Membuat 1 m 3 beton mutu f’c = 28,8 MPa (K 325), slump (12 ± 2) cm, w/c = 0,49
Bahan Semen Portland Kg 439.0000
Pasir Beton M3 0.6700
Koral Beton M3 1.0060
Air Liter 215.0000
Tenaga Kerja Pekerja OH 2.1000
Tukang Batu OH 0.3500
Kepala Tukang OH 0.0350
Mandor OH 0.1050
Jumlah Harga per Satuan Pekerjaan
Analisa G.12 Membuat 1 m 3 beton mutu f’c = 31,2 MPa (K 350), slump (12 ± 2) cm, w/c = 0,48
Bahan Semen Portland Kg 448.0000
Pasir Beton M3 0.6670
Koral beton M3 1.0000
Air Liter 215.0000
Tenaga Kerja Pekerja OH 2.1000
Tukang Batu OH 0.3500
Kepala Tukang OH 0.0350
Mandor OH 0.1050
Jumlah Harga per Satuan Pekerjaan
Analisa G.13 Membuat 1 m 3 beton kedap air dengan strorox – 100
Bahan Semen Portland Kg 400.0000
Pasir Beton M3 0.4800
Strorox - 100 Kg 1.2000
Koral beton M3 0.8000
Air Liter 210.0000
Tenaga Kerja Pekerja OH 2.1000
Tukang Batu OH 0.3500
Kepala Tukang OH 0.0350
Mandor OH 0.1050
Jumlah Harga per Satuan Pekerjaan
Analisa G.14 Pembesian 10 kg dengan besi polos atau besi ulir
Bahan Besi Beton Kg 10.5000
Kawat Beton Kg 0.1500
Tenaga Kerja Pekerja OH 0.0700
Tukang Besi OH 0.0700
Kepala Tukang OH 0.0070
Mandor OH 0.0040
Jumlah Harga per Satuan Pekerjaan
Jumlah Harga per Satuan Pekerjaan
Analisa G.15 Memasang 10 kg kabel presstressed polos/strands
Bahan Besi Beton Kg 10.5000
Kawat Beton Kg 0.1000
Tenaga Kerja Pekerja OH 0.0500
Tukang Besi OH 0.0500
Kepala Tukang OH 0.0050
Mandor OH 0.0030
10 Kg Jumlah Harga per Satuan Pekerjaan
1 Kg Jumlah Harga per Satuan Pekerjaan
Analisa G.16 Memasang 1 Kg jaring kawat baja/wire mesh
Bahan Besi Beton Kg 1.0200
Kawat Beton Kg 0.0500
Tenaga Kerja Pekerja OH 0.0250
Tukang Besi OH 0.0250
Kepala Tukang OH 0.0020
Mandor OH 0.0010
Jumlah Harga per Satuan Pekerjaan
Analisa G.17 Memasang 1 m 2 bekisting untuk pondasi
Bahan Kayu kelas III (papan) M3 0.0400
Paku 5 cm - 10 cm Kg 0.3000
Minyak Bekisting Liter 0.1000
Tenaga Kerja Pekerja OH 0.5200
Tukang Kayu OH 0.2600
Kepala Tukang OH 0.0260
Mandor OH 0.0260
Jumlah Harga per Satuan Pekerjaan
Analisa G.18 Memasang 1 m 2 bekisting untuk sloof
Bahan Kayu kelas III (papan) M3 0.0450
Paku 5 cm - 10 cm Kg 0.3000
Minyak Bekisting Liter 0.1000
Tenaga Kerja Pekerja OH 0.5200
Tukang Kayu OH 0.2600
Kepala Tukang OH 0.0260
Mandor OH 0.0260
Jumlah Harga per Satuan Pekerjaan
Analisa G.19 Memasang 1 m 2 bekisting untuk kolom
Bahan Kayu kelas III (papan) M3 0.0400
Paku 5 cm - 10 cm Kg 0.4000
Minyak Bekisting Liter 0.2000
Kayu Kelas II (Balok) M3 0.0150
Plywood tebal 9 mm Lembar 0.3500
Dolken Kayu Kelas III Ø 8 - 10/400 cm Batang 2.0000
Tenaga Kerja Pekerja OH 0.6600
Tukang Kayu OH 0.3300
Kepala Tukang OH 0.0330
Mandor OH 0.0330
Jumlah Harga per Satuan Pekerjaan
Analisa G.20 Memasang 1 m 2 bekisting untuk balok
Bahan Kayu kelas III (papan) M3 0.0400
Paku 5 cm - 10 cm Kg 0.4000
Minyak Bekisting Liter 0.2000
Kayu Kelas II (Balok) M3 0.0180
Plywood tebal 9 mm Lembar 0.3500
Dolken Kayu Kelas III Ø 8 - 10/400 cm Batang 2.0000
Tenaga Kerja Pekerja OH 0.6600
Tukang Kayu OH 0.3300
Kepala Tukang OH 0.0330
Mandor OH 0.0330
Jumlah Harga per Satuan Pekerjaan
Analisa G.21 Memasang 1 m 2 bekisting untuk plat lantai
Bahan Kayu kelas III (papan) M3 0.0400
Paku 5 cm - 12 cm Kg 0.4000
Minyak Bekisting Liter 0.2000
Kayu Kelas II (Balok) M3 0.0150
Plywood tebal 9 mm Lembar 0.3500
Dolken Kayu Kelas III Ø 8 - 10/400 cm Batang 6.0000
Tenaga Kerja Pekerja OH 0.6600
Tukang Kayu OH 0.3300
Kepala Tukang OH 0.0330
Mandor OH 0.0330
Jumlah Harga per Satuan Pekerjaan
Analisa G.22 Memasang 1 m 2 bekisting untuk dinding
Bahan Kayu kelas III (papan) M3 0.0300
Paku 5 cm - 12 cm Kg 0.4000
Minyak Bekisting Liter 0.2000
Kayu Kelas II (Balok) M3 0.0200
Plywood tebal 9 mm Lembar 0.3500
Dolken Kayu Kelas III Ø 8 - 10/400 cm Batang 3.0000
Formite/penjaga jarak begisting Buah 4.0000
Tenaga Kerja Pekerja OH 0.6600
Tukang Kayu OH 0.3300
Kepala Tukang OH 0.0330
Mandor OH 0.0330
Jumlah Harga per Satuan Pekerjaan
Analisa G.23 Memasang 1 m 2 bekisting untuk tangga
Bahan Kayu kelas III (papan) M3 0.0300
Paku 5 cm - 12 cm Kg 0.4000
Minyak Bekisting Liter 0.1500
Kayu Kelas II (Balok) M3 0.0150
Plywood tebal 9 mm Lembar 0.3500
Dolken Kayu Kelas III Ø 8 - 10/400 cm Batang 2.0000
Tenaga Kerja Pekerja OH 0.6600
Tukang Kayu OH 0.3300
Kepala Tukang OH 0.0330
Mandor OH 0.0330
Jumlah Harga per Satuan Pekerjaan
Analisa G.24 Memasang 1 m 2 bekisting Jembatan untuk pengecoran beton
Bahan Kayu kelas III (papan) M3 0.0264
Paku 5 cm - 12 cm Kg 0.6000
Dolken Kayu Kelas III Ø 8 - 10/400 cm Batang 0.5000
Tenaga Kerja Pekerja OH 0.1500
Tukang Kayu OH 0.0500
Kepala Tukang OH 0.0050
Mandor OH 0.0080
Jumlah Harga per Satuan Pekerjaan
Analisa G.25 Membuat 1 m 3 pondasi beton bertulang (150 kg besi + bekisting)
Bahan Kayu kelas III (papan) M3 0.2000
Paku 5 cm - 12 cm Kg 1.5000
Minyak Bekisting Liter 0.4000
Besi Beton Kg 157.5000
Kawat Beton Kg 2.2500
Semen Portland Kg 336.0000
Pasir Beton M3 0.5400
Koral beton M3 0.8100
Tenaga Kerja Pekerja OH 5.3000
Tukang Batu OH 0.2750
Tukang Kayu OH 1.3000
Tukang Besi OH 1.0500
Kepala Tukang OH 0.2620
Mandor OH 0.2650
Jumlah Harga per Satuan Pekerjaan
Analisa G.26 Membuat 1 m 3 sloof beton bertulang (200 kg besi + bekisting)
Bahan Kayu kelas III (papan) M3 0.2700
Paku 5 cm - 12 cm Kg 2.0000
Minyak Bekisting Liter 0.6000
Besi Beton Kg 210.0000
Kawat Beton Kg 3.0000
Semen Portland Kg 336.0000
Pasir Beton M3 0.5400
Koral beton M3 0.8100
Tenaga Kerja Pekerja OH 5.6500
Tukang Batu OH 0.2750
Tukang Kayu OH 1.5600
Tukang Besi OH 1.4000
Kepala Tukang OH 0.3230
Mandor OH 0.2830
Jumlah Harga per Satuan Pekerjaan
Analisa G.27 Membuat 1 m 3 kolom beton bertulang (300 kg besi + bekisting)
Bahan Kayu kelas III (papan) M3 0.4000
Paku 5 cm - 12 cm Kg 4.0000
Minyak Bekisting Liter 2.0000
Besi Beton Kg 315.0000
Kawat Beton Kg 4.5000
Semen Portland Kg 336.0000
Pasir Beton M3 0.5400
Koral Beton M3 0.8100
Kayu kelas II (balok) M3 0.1500
Plywood tebal 9 mm Lembar 3.5000
Dolken Kayu Kelas III Ø 8 - 10/400 cm Batang 20.0000
Tenaga Kerja Pekerja OH 7.0500
Tukang Batu OH 0.2750
Tukang Kayu OH 1.6500
Tukang Besi OH 2.1000
Kepala Tukang OH 0.4030
Mandor OH 0.3530
Jumlah Harga per Satuan Pekerjaan
Analisa G.28 Membuat 1 m 3 balok beton bertulang (200 kg besi + bekisting)
Bahan Kayu kelas III (papan) M3 0.3200
Paku 5 cm - 12 cm Kg 3.2000
Minyak Bekisting Liter 1.6000
Besi Beton Kg 210.0000
Kawat Beton Kg 3.0000
Semen Portland Kg 336.0000
Pasir Beton M3 0.5400
Koral Beton M3 0.8100
Kayu kelas II (balok) M3 0.1400
Plywood tebal 9 mm Lembar 2.8000
Dolken Kayu Kelas III Ø 8 - 10/400 cm Batang 16.0000
Tenaga Kerja Pekerja OH 6.3500
Tukang Batu OH 0.2750
Tukang Kayu OH 1.6500
Tukang Besi OH 1.4000
Kepala Tukang OH 0.3300
Mandor OH 0.3180
Jumlah Harga per Satuan Pekerjaan
Analisa G.29 Membuat 1 m3 plat beton bertulang (150 kg besi + bekisting)
Bahan Kayu kelas III (papan) M3 0.3200
Paku 5 cm - 12 cm Kg 3.2000
Minyak Bekisting Liter 1.6000
Besi Beton Kg 157.5000
Kawat Beton Kg 2.2500
Semen Portland Kg 336.0000
Pasir Beton M3 0.5400
Koral Beton M3 0.8100
Kayu kelas II (balok) M3 0.1200
Plywood tebal 9 mm Lembar 2.8000
Dolken Kayu Kelas III Ø 8 - 10/400 cm Batang 32.0000
Tenaga Kerja Pekerja OH 5.3000
Tukang Batu OH 0.2750
Tukang Kayu OH 1.3000
Tukang Besi OH 1.0500
Kepala Tukang OH 0.2650
Mandor OH 0.2650
Jumlah Harga per Satuan Pekerjaan
Analisa G.30 Membuat 1 m3dinding beton bertulang (150 kg besi + bekisting)
Bahan Kayu kelas III (papan) M3 0.2400
Paku 5 cm - 12 cm Kg 3.2000
Minyak Bekisting Liter 1.6000
Besi Beton Kg 157.5000
Kawat Beton Kg 2.2500
Semen Portland Kg 336.0000
Pasir Beton M3 0.5400
Koral Beton M3 0.8100
Kayu kelas II (balok) M3 0.1600
Plywood tebal 9 mm Lembar 2.8000
Dolken Kayu Kelas III Ø 8 - 10/400 cm Batang 24.0000
Tenaga Kerja Pekerja OH 5.3000
Tukang Batu OH 0.2750
Tukang Kayu OH 1.3000
Tukang Besi OH 1.0500
Kepala Tukang OH 0.2620
Mandor OH 0.2650
Jumlah Harga per Satuan Pekerjaan
Analisa G.31 Membuat 1 m3 dinding beton bertulang (200 kg besi + bekisting)
Bahan Kayu kelas III (papan) M3 0.2500
Paku 5 cm - 12 cm Kg 3.0000
Minyak Bekisting Liter 1.2000
Besi Beton Kg 210.0000
Kawat Beton Kg 3.0000
Semen Portland Kg 336.0000
Pasir Beton M3 0.5400
Koral Beton M3 0.8100
Kayu kelas II (balok) M3 0.1050
Plywood tebal 9 mm Lembar 2.5000
Dolken Kayu Kelas III Ø 8 - 10/400 cm Batang 14.0000
Tenaga Kerja Pekerja OH 5.6500
Tukang Batu OH 0.2750
Tukang Kayu OH 1.5600
Tukang Besi OH 1.4000
Kepala Tukang OH 0.3230
Mandor OH 0.2830
Jumlah Harga per Satuan Pekerjaan
Analisa G.32 Membuat 1 m' kolom praktis beton bertulang (11 x 11) cm
Bahan Kayu kelas III (papan) M3 0.0020
Paku 5 cm - 12 cm Kg 0.0100
Besi Beton Kg 3.0000
Kawat Beton Kg 0.0450
Semen Portland Kg 4.0000
Pasir Beton M3 0.0060
Koral Beton M3 0.0090
Tenaga Kerja Pekerja OH 0.1800
Tukang Batu OH 0.0200
Tukang Kayu OH 0.0200
Tukang Besi OH 0.0200
Kepala Tukang OH 0.0060
Mandor OH 0.0090
Jumlah Harga per Satuan Pekerjaan
Analisa G.33 Membuat 1 m' ring balok beton bertulang (10 x 15) cm
Bahan Kayu kelas III (papan) M3 0.0030
Paku 5 cm - 12 cm Kg 0.0200
Besi Beton Kg 3.6000
Kawat Beton Kg 0.0500
Semen Portland Kg 5.5000
Pasir Beton M3 0.0090
Koral Beton M3 0.0150
Tenaga Kerja Pekerja OH 0.2970
Tukang Batu OH 0.0330
Tukang Kayu OH 0.0330
Tukang Besi OH 0.0330
Kepala Tukang OH 0.0100
Mandor OH 0.0150
Jumlah Harga per Satuan Pekerjaan
Analisa G.34 1 m3 Membuat Lantai Kerja Beton Tumbuk 1 Pc : 3 Ps : 5 Kr
Bahan Semen Portland Kg 211.8200
Pasir Beton M3 0.5000
Koral Beton M3 1.0000
Tenaga Kerja Pekerja OH 6.0000
Tukang Batu OH 0.5000
Kepala Tukang OH 0.0500
Mandor OH 0.3000
Jumlah Harga per Satuan Pekerjaan
H. PEKERJAAN PENUTUP ATAP
Analisa H.1 1m² Pasang Atap Genteng Palentong Kecil
Bahan Genteng Palentong Buah 25.0000
Tenaga Kerja Pekerja OH 0.1500
Tukang Kayu OH 0.0750
Kepala Tukang OH 0.0080
Mandor OH 0.0080
Jumlah Harga per Satuan Pekerjaan
Analisa H.2 1m² Pasang Atap Genteng Kodok / Glazzur
Bahan Genteng Kodok Buah 25.0000
Tenaga Kerja Pekerja OH 0.1500
Tukang Kayu OH 0.0750
Kepala Tukang OH 0.0080
Mandor OH 0.0080
Jumlah Harga per Satuan Pekerjaan
Analisa H.3 1m² Pasang Atap Genteng Palentong Super / Besar
Bahan Genteng Palentong Super Buah 12.0000
Tenaga Kerja Pekerja OH 0.1500
Tukang Kayu OH 0.0600
Kepala Tukang OH 0.0060
Mandor OH 0.0080
Jumlah Harga per Satuan Pekerjaan
Analisa H.4 1m' Pasang Genteng Bubung Palentong
Bahan Genteng Bubung Palentong Buah 5.0000
Semen Portland Kg 8.0000
Pasir Pasang M3 0.0320
Tenaga Kerja Pekerja OH 0.4000
Tukang Kayu OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0020
Jumlah Harga per Satuan Pekerjaan
Analisa H.5 1m' Pasang Genteng Bubung Kodok Glazzur
Bahan Genteng Bubung Kodok Buah 5.0000
Semen Portland Kg 8.0000
Pasir Pasang M3 0.0320
Tenaga Kerja Pekerja OH 0.4000
Tukang Kayu OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0020
Jumlah Harga per Satuan Pekerjaan
Analisa H.6 1m' Pasang Genteng Bubung Palentong Besar
Bahan Genteng Bubung Palentong Buah 4.0000
Semen Portland Kg 8.0000
Pasir Pasang M3 0.0320
Tenaga Kerja Pekerja OH 0.4000
Tukang Kayu OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0020
Jumlah Harga per Satuan Pekerjaan
Analisa H.7 1m' Pasang Rooflight Fiberglass ( 180 x 90 ) cm
Bahan Roof Light Fiberglass Lembar 0.6000
Paku 1 cm - 2,5 cm Kg 0.0500
Tenaga Kerja Pekerja OH 0.1400
Tukang Kayu OH 0.0670
Kepala Tukang OH 0.0070
Mandor OH 0.0070
Jumlah Harga per Satuan Pekerjaan
Analisa H.8 1m' Pasang Atap Asbes Gelombang 2,25 x 0,92 m x 5 mm
Bahan Asbes Gelombang 2,25 x 0,92 m x 5 mm Lembar 0.5000
Paku Pancing 60 x 230 Kg 0.1200
Tenaga Kerja Pekerja OH 0.1400
Tukang Kayu OH 0.0750
Kepala Tukang OH 0.0080
Mandor OH 0.0080
Jumlah Harga per Satuan Pekerjaan
Analisa H.9 1m' Pasang Atap Asbes Gelombang 2,25 x 0.92 m x 5 mm
Bahan Asbes Gelombang 2,25 x 0.92 m x 5 mm Lembar 0.6000
Paku Pancing 60 x 230 Kg 0.1200
Tenaga Kerja Pekerja OH 0.1400
Tukang Kayu OH 0.0750
Kepala Tukang OH 0.0080
Mandor OH 0.0080
Jumlah Harga per Satuan Pekerjaan
Analisa H.10 1m' Pasang Atap Asbes Gelombang ( 2.00 x 0.92 m ) X 5mm
Bahan Asbes Gelombang 2.00 x 0.92 m x 5 mm Lembar 0.6000
Paku Pancing 60 x 230 Kg 0.1200
Tenaga Kerja Pekerja OH 0.1400
Tukang Kayu OH 0.0700
Kepala Tukang OH 0.0070
Mandor OH 0.0070
Jumlah Harga per Satuan Pekerjaan
Analisa H.11 1m' Pasang Atap Asbes Gelombang ( 1.80 x 0.92 m ) X 5 mm
Bahan Asbes Gelombang 1.80 x 0.92 m x 5 mm Lembar 0.7500
Paku Pancing 60 x 230 Kg 0.1200
Tenaga Kerja Pekerja OH 0.1400
Tukang Kayu OH 0.0700
Kepala Tukang OH 0.0070
Mandor OH 0.0070
Jumlah Harga per Satuan Pekerjaan
Analisa H.12 1m² Pasang Atap Asbes Gelombang ( 3.00 x 1.05 m ) X 4mm
Bahan Asbes Gelombang 3.00 x 1.05 m x 4 mm Lembar 0.3500
Paku Pancing 60 x 230 Kg 0.1200
Tenaga Kerja Pekerja OH 0.1400
Tukang Kayu OH 0.0700
Kepala Tukang OH 0.0070
Mandor OH 0.0070
Jumlah Harga per Satuan Pekerjaan
Analisa H.13 1m² Pasang Atap Asbes Gelombang 2.70 x 1.085 m x 4 mm
Bahan Asbes Gelombang 2.70 x 1.05 m x 4 mm Lembar 0.3800
Paku Pancing 60 x 230 Kg 0.1200
Tenaga Kerja Pekerja OH 0.1400
Tukang Kayu OH 0.0700
Kepala Tukang OH 0.0070
Mandor OH 0.0070
Jumlah Harga per Satuan Pekerjaan
Analisa H.14 1m² Pasang Atap Asbes Gelombang ( 2.40 x 1.05 m ) X 4 mm
Bahan Asbes Gelombang 2.40 x 1.05 m x 4 mm Lembar 0.4400
Paku Pancing 60 x 230 Kg 0.1200
Tenaga Kerja Pekerja OH 0.1400
Tukang Kayu OH 0.0670
Kepala Tukang OH 0.0070
Mandor OH 0.0070
Jumlah Harga per Satuan Pekerjaan
Analisa H.15 1m² Pasang Atap Asbes Gelombang 2.10 x 1.05 m x 4 mm
Bahan Asbes Gelombang 2.10 x 1.05 m x 4 mm Lembar 0.6000
Paku Pancing 60 x 230 Kg 0.1200
Tenaga Kerja Pekerja OH 0.1400
Tukang Kayu OH 0.0670
Kepala Tukang OH 0.0070
Mandor OH 0.0070
Jumlah Harga per Satuan Pekerjaan
Analisa H.16 1m² Pasang Atap Asbes Gelombang ( 1.50 x 1.05 m ) X 4mm
Bahan Asbes Gelombang 1.50 x 1.05 m x 4 mm Lembar 0.8000
Paku Pancing 60 x 230 Kg 0.1200
Tenaga Kerja Pekerja OH 0.1400
Tukang Kayu OH 0.0670
Kepala Tukang OH 0.0070
Mandor OH 0.0070
Jumlah Harga per Satuan Pekerjaan
Analisa H.17 1m² Pasang Atap Asbes Gelombang ( 3.00 x 1.08 m ) X 6 mm
Bahan Asbes Gelombang 3.00 x 1.08 m x 6 mm Lembar 0.3700
Paku Pancing 60 x 230 Kg 0.1200
Tenaga Kerja Pekerja OH 0.1400
Tukang Kayu OH 0.0670
Kepala Tukang OH 0.0070
Mandor OH 0.0070
Jumlah Harga per Satuan Pekerjaan
Analisa H.18 1m² Pasang Atap Asbes Gelombang ( 2.7 x 1.08 m ) X 6mm
Bahan Asbes Gelombang 2.70 x 1.08 m x 6 mm Lembar 0.3800
Paku Pancing 60 x 230 Kg 0.1200
Tenaga Kerja Pekerja OH 0.1400
Tukang Kayu OH 0.0670
Kepala Tukang OH 0.0070
Mandor OH 0.0070
Jumlah Harga per Satuan Pekerjaan
Analisa H.19 1m² Pasang Atap Asbes Gelombang ( 2.40 x 1.08 m ) X 6 mm
Bahan Asbes Gelombang 2.40 x 1.08 m x 6 mm Lembar 0.4600
Paku Pancing 60 x 230 Kg 0.1200
Tenaga Kerja Pekerja OH 0.1400
Tukang Kayu OH 0.0670
Kepala Tukang OH 0.0070
Mandor OH 0.0070
Jumlah Harga per Satuan Pekerjaan
Analisa H.20 1m' Pasang Bubung Stel Gelombang 0.92 m
Bahan Bubung Stel Gelombang 0.92 m Lembar 2.4000
Paku Pancing 60 x 230 Kg 6.0000
Tenaga Kerja Pekerja OH 0.0840
Tukang Kayu OH 0.1250
Kepala Tukang OH 0.0130
Mandor OH 0.0040
Jumlah Harga per Satuan Pekerjaan
Analisa H.21 1m' Pasang Nok Stel Gelombang 1.08 m
Bahan Nok Stel Gelombang 1,08 m Lembar 2.0500
Paku Skrup 3.5" Buah 6.0000
Tenaga Kerja Pekerja OH 0.0840
Tukang Kayu OH 0.1250
Kepala Tukang OH 0.0130
Mandor OH 0.0040
Jumlah Harga per Satuan Pekerjaan
Analisa H.22 1m' Pasang Nok Paten 0.92m
Bahan Nok Asbes Paten 0,92 m Lembar 1.2000
Paku Skrup 3.5" Buah 6.0000
Tenaga Kerja Pekerja OH 0.0840
Tukang Kayu OH 0.1250
Kepala Tukang OH 0.0130
Mandor OH 0.0040
Jumlah Harga per Satuan Pekerjaan
Analisa H.23 1m' Pasang Nok Stel rata 0.92 m
Bahan Nok Asbes Rata 0,92 m Lembar 1.1000
Paku Skrup 3.5" Buah 6.0000
Tenaga Kerja Pekerja OH 0.1000
Tukang Kayu OH 0.1500
Kepala Tukang OH 0.0130
Mandor OH 0.0040
Jumlah Harga per Satuan Pekerjaan
Analisa H.24 1m' Pasang Nok Stel rata 1.05 m
Bahan Nok Asbes Rata 1,05 m Lembar 1.1000
Paku Skrup 3.5" Buah 6.0000
Tenaga Kerja Pekerja OH 0.0840
Tukang Kayu OH 0.1250
Kepala Tukang OH 0.0130
Mandor OH 0.0040
Jumlah Harga per Satuan Pekerjaan
Analisa H.25 1m² Pasang Atap Genteng Beton
Bahan Genteng Beton Buah 11.0000
Paku 5 cm - 12 cm Kg 0.0300
Tenaga Kerja Pekerja OH 0.2000
Tukang Kayu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0100
Jumlah Harga per Satuan Pekerjaan
Analisa H.26 1m² Pasang Atap Genteng Metal polos
Bahan Genteng Metal polos Buah 2.5000
Paku 5 cm - 12 cm Kg 0.2000
Tenaga Kerja Pekerja OH 0.2000
Tukang Kayu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0010
Jumlah Harga per Satuan Pekerjaan
Analisa H.27 1m' Pasang Nok Genteng Beton
Bahan Nok Genteng Beton Buah 3.5000
Paku 1 cm - 2,5 cm Kg 0.0500
Semen abu -abu Kg 10.8000
Pasir Pasang M3 0.0320
Semen Warna Kg 1.0000
Tenaga Kerja Pekerja OH 0.4000
Tukang Kayu OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0200
Jumlah Harga per Satuan Pekerjaan
Analisa H.28 1m² Pasang Atap Seng Gelombang
Bahan Seng Gelombang 3" x 6" BJLS 28 Lembar 0.7000
Paku 1 cm - 2,5 cm Kg 0.0200
Tenaga Kerja Pekerja OH 0.1200
Tukang Kayu OH 0.0600
Kepala Tukang OH 0.0060
Mandor OH 0.0060
Jumlah Harga per Satuan Pekerjaan
Analisa H.29 1m² Pasang Atap Nok Seng
Bahan Seng Plat 3" x 6" BJLS 28 Lembar 0.3000
Paku 1 cm - 2,5 cm Kg 0.0400
Tenaga Kerja Pekerja OH 0.0150
Tukang Kayu OH 0.0700
Kepala Tukang OH 0.0080
Mandor OH 0.0060
Jumlah Harga per Satuan Pekerjaan
Analisa H.30 1m² Pasang Alluminium Foil / Sisalation
Bahan Sisalation / Alluminium Foil M2 1.0500
Tenaga Kerja Pekerja OH 0.1500
Tukang Kayu OH 0.0500
Kepala Tukang OH 0.0050
Mandor OH 0.0080
Jumlah Harga per Satuan Pekerjaan
Analisa H.31 1m' Pasang Nok Genteng Metal
Bahan Genteng Decra Bond M2 1.0500
Paku Biasa ½" - 1" OH 0.0700
Tenaga Kerja Pekerja OH 0.2500
Tukang Kayu OH 0.1500
Kepala Tukang OH 0.0150
Mandor OH 0.0130
Jumlah Harga per Satuan Pekerjaan
Analisa H.32 1m² Pasang Atap Genteng Metal berpasir
Bahan Genteng Metal berpasir Buah 2.6000
Paku 5 cm - 12 cm Kg 0.2000
Tenaga Kerja Pekerja OH 0.2000
Tukang Kayu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0010
Jumlah Harga per Satuan Pekerjaan
I. PEKERJAAN LANGIT - LANGIT
Analisa I.1 Memasang 1 m2 langit-langit asbes semen, tebal 4 mm
Bahan Asbes semen Tebal 4 mm M2 1.1000
Paku tripleks Kg 0.0100
Tenaga Kerja Pekerja OH 0.0300
Tukang kayu OH 0.0700
Kepala tukang OH 0.0070
Mandor OH 0.0040
Jumlah Harga per Satuan Pekerjaan
Analisa I.2 Memasang 1 m2 langit-langit asbes semen, tebal 5 mm
Bahan Asbes semen Tebal 5 mm M2 1.1000
Paku tripleks Kg 0.0100
Tenaga Kerja Pekerja OH 0.0300
Tukang kayu OH 0.0700
Kepala tukang OH 0.0070
Mandor OH 0.0040
Jumlah Harga per Satuan Pekerjaan
Analisa I.3 Memasang 1 m2 langit-langit asbes semen, tebal 6 mm
Bahan Asbes semen Tebal 6 mm M2 1.1000
Paku tripleks Kg 0.0100
Tenaga Kerja Pekerja OH 0.0300
Tukang kayu OH 0.0700
Kepala tukang OH 0.0070
Mandor OH 0.0040
Jumlah Harga per Satuan Pekerjaan
Analisa I.4 Memasang 1 m2 langit-langit akustik ukuran (30 x 30) cm
Bahan Akustik 30 x 30 cm Lembar 12.0000
Paku tripleks Kg 0.0500
Tenaga Kerja Pekerja OH 0.1200
Tukang kayu OH 0.1200
Kepala tukang OH 0.0120
Mandor OH 0.0060
Jumlah Harga per Satuan Pekerjaan
Analisa I.5 Memasang 1 m2 langit-langit akustik ukuran (30 x 60) cm
Bahan Akustik 30 x 60 cm Lembar 5.8000
Paku tripleks Kg 0.0500
Tenaga Kerja Pekerja OH 0.1000
Tukang kayu OH 0.1000
Kepala tukang OH 0.0100
Mandor OH 0.0050
Jumlah Harga per Satuan Pekerjaan
Analisa I.6 Memasang 1 m2 langit-langit akustik ukuran (60 x 120) cm
Bahan Akustik 60 x 120 cm Lembar 1.5000
Paku tripleks Kg 0.0500
Tenaga Kerja Pekerja OH 0.1000
Tukang kayu OH 0.1000
Kepala tukang OH 0.0100
Mandor OH 0.0050
Jumlah Harga per Satuan Pekerjaan
Analisa I.7 Memasang 1 m2 langit-langit tripleks ukuran (120 x 240) cm, tebal 3 mm
Bahan Tripleks tebal 3 mm Lembar 0.3750
Paku tripleks Kg 0.0300
Tenaga Kerja Pekerja OH 0.1000
Tukang kayu OH 0.1000
Kepala tukang OH 0.0100
Mandor OH 0.0050
Jumlah Harga per Satuan Pekerjaan
Analisa I.8 Memasang 1 m2 langit-langit tripleks ukuran (120 x 240) cm, tebal 4 mm
Bahan Tripleks tebal 4 mm Lembar 0.3750
Paku tripleks Kg 0.0300
Tenaga Kerja Pekerja OH 0.1000
Tukang kayu OH 0.1000
Kepala tukang OH 0.0100
Mandor OH 0.0050
Jumlah Harga per Satuan Pekerjaan
Analisa I.9 Memasang 1 m2 langit-langit tripleks ukuran (120 x 240) cm, tebal 6 mm
Bahan Tripleks tebal 6 mm Lembar 0.3750
Paku tripleks Kg 0.0300
Tenaga Kerja Pekerja OH 0.1000
Tukang kayu OH 0.1000
Kepala tukang OH 0.0100
Mandor OH 0.0050
Jumlah Harga per Satuan Pekerjaan
Analisa I.10 Memasang 1 m2 langit-langit lambriziring kayu, tebal 9 mm
Bahan Kayu Kelas II (Papan) M3 0.0150
Paku tripleks Kg 0.0100
Tenaga Kerja Pekerja OH 0.8000
Tukang kayu OH 0.8000
Kepala tukang OH 0.0800
Mandor OH 0.0400
Jumlah Harga per Satuan Pekerjaan
Analisa I.11 Memasang 1 m2 langit-langit gypsum board ukuran (1200 x 2400 x 9) mm,
Bahan Gypsum board Lembar 0.3640
Paku skrup 1 cm - 2,5 cm Kg 0.1100
Tenaga Kerja Pekerja OH 0.1000
Tukang kayu OH 0.0500
Kepala tukang OH 0.0050
Mandor OH 0.0050
Jumlah Harga per Satuan Pekerjaan
Analisa I.12 Memasang 1 m' list plafond gysum profil
Bahan List gypsum profil M' 1.0500
Tepung gypsum Kg 0.1500
Tenaga Kerja Pekerja OH 0.0600
Tukang kayu OH 0.0600
Kepala tukang OH 0.0060
Mandor OH 0.0030
Jumlah Harga per Satuan Pekerjaan
Analisa I.13 Memasang 1 m2 langit-langit akustik ukuran (60 x 120) cm + rangka alluminium
Bahan Profil Alluminium " T " M' 3.6000
Kawat diameter 4 mm Kg 0.1500
Ramset Buah 1.0500
Akustik 60 x 120 cm Lembar 1.5000
Tenaga Kerja Pekerja OH 0.5000
Tukang kayu OH 0.5000
Kepala tukang OH 0.0500
Mandor OH 0.0250
Jumlah Harga per Satuan Pekerjaan
Analisa I.14 Memasang 1 m' list langit-langit kayu profil
Bahan Lis Kayu Profil Uk. 2 x 3 cm M' 1.0500
Paku 1 cm - 2,5 cm Lembar 0.0100
Tenaga Kerja Pekerja OH 0.0500
Tukang kayu OH 0.0500
Kepala tukang OH 0.0050
Mandor OH 0.0030
Jumlah Harga per Satuan Pekerjaan
J. PEKERJAAN SANITASI
Analisa J.1 Memasang 1 buah Kloset Duduk / Monoblok
Bahan Kloset Duduk / Monoblok Buah 1.0000
Perlengkapan (6% x Kloset) Set 0.0600
Tenaga Kerja Pekerja OH 3.3000
Tukang Batu OH 1.1000
Kepala Tukang OH 0.0010
Mandor OH 0.1600
Jumlah Harga per Satuan Pekerjaan
Analisa J.2 Memasang 1 buah Kloset Duduk / Monoblok
Bahan Kloset Jongkok Porselen Buah 1.0000
Semen Portland Kg 6.0000
Pasir pasang M3 0.0100
Tenaga Kerja Pekerja OH 1.0000
Tukang Batu OH 1.5000
Kepala Tukang OH 1.5000
Mandor OH 0.1600
Jumlah Harga per Satuan Pekerjaan
Analisa J.3 Memasang 1 buah Kloset Jongkok Teraso
Bahan Kloset Jongkok Teraso Buah 1.0000
Bata merah Buah 7.0000
Semen Portland Kg 6.0000
Pasir Pasang M3 0.0100
Tenaga Kerja Pekerja OH 1.0000
Tukang Batu OH 1.5000
Kepala Tukang OH 0.3000
Mandor OH 0.1100
Jumlah Harga per Satuan Pekerjaan
Analisa J.4 Memasang 1 buah Urinoir
Bahan Urinoir Buah 1.0000
Perlengkapan (30% dari bahan) Set 0.3000
Semen Portland Kg 6.0000
Pasir Pasang M3 0.0100
Tenaga Kerja Pekerja OH 1.0000
Tukang Batu OH 1.0000
Kepala Tukang OH 0.1000
Mandor OH 0.1000
Jumlah Harga per Satuan Pekerjaan
Analisa J.5 Memasang 1 buah Wastafel
Bahan Wastafel Buah 1.0000
Perlengkapan (12% dari bahan) Set 0.1200
Semen Portland Kg 6.0000
Pasir Pasang M3 0.0100
Tenaga Kerja Pekerja OH 1.0000
Tukang Batu OH 1.4500
Kepala Tukang OH 0.1500
Mandor OH 0.1000
Jumlah Harga per Satuan Pekerjaan
Analisa J.6 Memasang 1 buah Bak Mandi Fiberglass, volume 0.30 m³
Bahan Bak Mandi Fiberglass Volume 0,30 M3 Buah 1.0000
Perlengkapan (18% dari bahan) Unit 0.1800
Tenaga Kerja Pekerja OH 1.8000
Tukang Batu OH 2.7000
Kepala Tukang OH 0.5400
Mandor OH 0.1100
Jumlah Harga per Satuan Pekerjaan
Analisa J.7 Memasang 1 buah Bak Mandi Batu bata, volume 0.30 m³ Porselin putih
Bahan Bata merah Buah 0.4000
Semen Portland Kg 120.0000
Pasir Pasang M3 0.3000
Porselen 11 x 11 cm putih Buah 360.0000
Semen Nat Kg 6.0000
Tenaga Kerja Pekerja OH 6.0000
Tukang Batu OH 3.0000
Kepala Tukang OH 0.3000
Mandor OH 0.3000
Jumlah Harga per Satuan Pekerjaan
Analisa J.8 Memasang 1 buah Bak Mandi Batu bata, volume 0.30 m³ Porselin Warna
Bahan Bata merah Buah 0.4000
Semen Portland Kg 120.0000
Pasir Pasang M3 0.3000
Porselen 11 x 11 cm warna Buah 360.0000
Semen Nat Kg 6.0000
Tenaga Kerja Pekerja OH 6.0000
Tukang Batu OH 3.0000
Kepala Tukang OH 0.3000
Mandor OH 0.3000
Jumlah Harga per Satuan Pekerjaan
Analisa J.9 Memasang 1 buah Badkip Porselen
Bahan Badkip Buah 1.0000
Perlengkapan (20% dari bahan) Set 0.2000
Tenaga Kerja Tukang Batu OH 0.0750
Kepala Tukang OH 0.7500
Mandor OH 0.2500
Jumlah Harga per Satuan Pekerjaan
Analisa J.10 Memasang 1 buah Bak Fiberglass volume 1 m³ air
Bahan Bak Fiberglass Volume 1,00 M3 Buah 1.0000
Perlengkapan (12% dari bahan) Set 0.1200
Tenaga Kerja Pekerja OH 3.0000
Tukang Batu OH 4.5000
Kepala Tukang OH 0.9000
Mandor OH 0.9000
Jumlah Harga per Satuan Pekerjaan
Analisa J.11 Memasang 1 m' Pipa Penyalur Air limbah jenis Pipa Tanah Ø15 cm
Bahan Pipa Tanah Ø 15 cm Buah 1.6000
Semen Portland Kg 0.6800
Pasir Pasang M3 0.0130
Pasir Urug M3 0.0110
Tenaga Kerja Pekerja OH 0.0600
Tukang Batu OH 0.0300
Kepala Tukang OH 0.0030
Mandor OH 0.0025
Jumlah Harga per Satuan Pekerjaan
Analisa J.12 Memasang 1 m' Pipa Penyalur Air limbah jenis Pipa Tanah Ø 20 cm
Bahan Pipa Tanah Ø 20 cm Buah 1.6000
Semen Portland Kg 0.8700
Pasir Pasang M3 0.0140
Pasir Urug M3 0.0140
Tenaga Kerja Pekerja OH 0.0800
Tukang Batu OH 0.0400
Kepala Tukang OH 0.0040
Mandor OH 0.0070
Jumlah Harga per Satuan Pekerjaan
Analisa J.13 Memasang 1 m' Pipa Beton Ø 5 cm - 20 cm
Bahan Pipa Beton Ø 20 cm Buah 1.1000
Bata merah Buah 205.0000
Semen Portland Kg 3.9200
Pasir Pasang M3 0.0560
Pasir Urug M3 0.0240
Tenaga Kerja Pekerja OH 0.1400
Tukang Batu OH 0.0700
Kepala Tukang OH 0.0070
Mandor OH 0.0070
Jumlah Harga per Satuan Pekerjaan
Analisa J.14 Memasang 1 m' Pipa Beton Ø 30 cm - 100 cm
Bahan Pipa Beton Ø 100 cm Buah 1.1000
Bata merah Buah 417.0000
Semen Portland Kg 10.3000
Pasir Pasang M3 0.0610
Pasir Urug M3 0.0690
Tenaga Kerja Pekerja OH 0.3800
Tukang Batu OH 0.1900
Kepala Tukang OH 0.0190
Mandor OH 0.0190
Jumlah Harga per Satuan Pekerjaan
Analisa J.15 Memasang 1 m' buah Bak Kontrol pasangan Batu Bata ukuran (30 x 30 )cm, t = 35cm
Bahan Bata merah Buah 110.0000
Semen Portland Kg 44.0000
Pasir Pasang M3 0.0700
Koral Beton M3 0.0700
Besi Beton M3 1.6000
Pasir Beton M3 0.0600
Tenaga Kerja Pekerja OH 3.2000
Tukang Batu OH 1.0150
Kepala Tukang OH 0.0015
Mandor OH 0.0160
Jumlah Harga per Satuan Pekerjaan
Analisa J.16 Memasang 1 m' buah Bak Kontrol pasangan Batu Bata ukuran (45 x 45 )cm, t = 50cm
Bahan Bata merah Buah 190.0000
Semen Portland Kg 77.0000
Pasir Pasang M3 0.1300
Koral Beton M3 0.0200
Besi Beton M3 2.6000
Pasir Beton M3 0.0900
Tenaga Kerja Pekerja OH 1.4200
Tukang Batu OH 0.4730
Kepala Tukang OH 0.0470
Mandor OH 0.0710
Jumlah Harga per Satuan Pekerjaan
Analisa J.17 Memasang 1 m' buah Bak Kontrol pasangan Batu Bata ukuran (60 x 60 )cm, t = 65cm
Bahan Bata merah Buah 281.0000
Semen Portland Kg 114.0000
Pasir Pasang M3 0.1840
Koral Beton M3 0.0330
Besi Beton M3 4.8500
Pasir Beton M3 0.1200
Tenaga Kerja Pekerja OH 2.1600
Tukang Batu OH 0.7200
Kepala Tukang OH 0.0720
Mandor OH 0.1080
Tukang Gali OH 0.1000
Jumlah Harga per Satuan Pekerjaan
Analisa J.18 Memasang 1 m' Pipa Galvanis Ø ½"
Bahan Pipa Galvanis Ø ½" M' 1.2000
Perlengkapan dihitung 35% dari bahan Set 0.3500
Tenaga Kerja Pekerja OH 0.0540
Tukang Pipa OH 0.0900
Kepala Tukang OH 0.0090
Mandor OH 0.0270
Jumlah Harga per Satuan Pekerjaan
Analisa J.19 Memasang 1 m' Pipa Galvanis Ø ¾"
Bahan Pipa Galvanis Ø ¾" M' 1.2000
Perlengkapan dihitung 35% dari bahan Set 0.3500
Tenaga Kerja Pekerja OH 0.0540
Tukang Pipa OH 0.0900
Kepala Tukang OH 0.0090
Mandor OH 0.0270
Jumlah Harga per Satuan Pekerjaan
Analisa J.20 Memasang 1 m' Pipa Galvanis Ø 1"
Bahan Pipa Galvanis Ø 1" M' 1.2000
Perlengkapan dihitung 35% dari bahan Set 0.3500
Tenaga Kerja Pekerja OH 0.0540
Tukang Pipa OH 0.0900
Kepala Tukang OH 0.0090
Mandor OH 0.0270
Jumlah Harga per Satuan Pekerjaan
Analisa J.21 Memasang 1 m' Pipa Galvanis Ø 1½"
Bahan Pipa Galvanis Ø 1½" M' 1.2000
Perlengkapan dihitung 35% dari bahan Set 0.3500
Tenaga Kerja Pekerja OH 0.1080
Tukang Pipa OH 0.1800
Kepala Tukang OH 0.0180
Mandor OH 0.0054
Jumlah Harga per Satuan Pekerjaan
Analisa J.22 Memasang 1 m' Pipa Galvanis Ø 3"
Bahan Pipa Galvanis Ø 3" M' 1.2000
Perlengkapan dihitung 35% dari bahan Set 0.3500
Tenaga Kerja Pekerja OH 0.1080
Tukang Pipa OH 0.1800
Kepala Tukang OH 0.0180
Mandor OH 0.0054
Jumlah Harga per Satuan Pekerjaan
Analisa J.23 Memasang 1 m' Pipa Galvanis Ø 4"
Bahan Pipa Galvanis Ø 4" M' 1.2000
Perlengkapan dihitung 35% dari bahan Set 0.3500
Tenaga Kerja Pekerja OH 0.1350
Tukang Pipa OH 0.2250
Kepala Tukang OH 0.0225
Mandor OH 0.0068
Jumlah Harga per Satuan Pekerjaan
Analisa J.24 Memasang 1 m' Pipa PVC tipe AW Ø ½"
Bahan Pipa PVC tipe AW Ø ½" M' 1.2000
Perlengkapan dihitung 35% dari bahan Set 0.3500
Tenaga Kerja Pekerja OH 0.0360
Tukang Pipa OH 0.0600
Kepala Tukang OH 0.0060
Mandor OH 0.0018
Jumlah Harga per Satuan Pekerjaan
Analisa J.25 Memasang 1 m' Pipa PVC tipe AW Ø ¾"
Bahan Pipa PVC tipe AW Ø ¾" M' 1.2000
Perlengkapan dihitung 35% dari bahan Set 0.3500
Tenaga Kerja Pekerja OH 0.0360
Tukang Pipa OH 0.0600
Kepala Tukang OH 0.0060
Mandor OH 0.0018
Jumlah Harga per Satuan Pekerjaan
Analisa J.26 Memasang 1 m' Pipa PVC tipe AW Ø 1"
Bahan Pipa PVC tipe AW Ø 1" M' 1.2000
Perlengkapan dihitung 35% dari bahan Set 0.3500
Tenaga Kerja Pekerja OH 0.0360
Tukang Pipa OH 0.0600
Kepala Tukang OH 0.0060
Mandor OH 0.0018
Jumlah Harga per Satuan Pekerjaan
Analisa J.27 Memasang 1 m' Pipa PVC tipe AW Ø 3"
Bahan Pipa PVC tipe AW Ø 3" M' 1.2000
Perlengkapan dihitung 35% dari bahan Set 0.3500
Tenaga Kerja Pekerja OH 0.0360
Tukang Pipa OH 0.0600
Kepala Tukang OH 0.0060
Mandor OH 0.0018
Jumlah Harga per Satuan Pekerjaan
Analisa J.28 Memasang 1 m' Pipa PVC tipe AW Ø 1½"
Bahan Pipa PVC tipe AW Ø 1½" M' 1.2000
Perlengkapan dihitung 35% dari bahan Set 0.3500
Tenaga Kerja Pekerja OH 0.0810
Tukang Pipa OH 0.1350
Kepala Tukang OH 0.0135
Mandor OH 0.0041
Jumlah Harga per Satuan Pekerjaan
Analisa J.29 Memasang 1 m' Pipa PVC tipe AW Ø 2"
Bahan Pipa PVC tipe AW Ø 2" M' 1.2000
Perlengkapan dihitung 35% dari bahan Set 0.3500
Tenaga Kerja Pekerja OH 0.0540
Tukang Pipa OH 0.0900
Kepala Tukang OH 0.0090
Mandor OH 0.0027
Jumlah Harga per Satuan Pekerjaan
Analisa J.30 Memasang 1 m' Pipa PVC tipe AW Ø 2½"
Bahan Pipa PVC tipe AW Ø 2½" M' 1.2000
Perlengkapan dihitung 35% dari bahan Set 0.3500
Tenaga Kerja Pekerja OH 0.0360
Tukang Pipa OH 0.0600
Kepala Tukang OH 0.0060
Mandor OH 0.0018
Jumlah Harga per Satuan Pekerjaan
K. PEKERJAAN BESI DAN ALLUMINIUM
Analisa K.1 Memasang 1 kg besi profil
Bahan Besi Profil Kg 1.1500
Tenaga Kerja Pekerja OH 0.0600
Tukang Las Konstruksi OH 0.0600
Kepala tukang OH 0.0060
Mandor OH 0.0030
Jumlah Harga per Satuan Pekerjaan
Analisa K.2 Memasang 1 kg rangka kuda-kuda baja IWF
Bahan Besi Profil WF Kg 1.1500
Tenaga Kerja Pekerja OH 0.0600
Tukang Las Konstruksi OH 0.0600
Kepala tukang OH 0.0060
Mandor OH 0.0030
Jumlah Harga per Satuan Pekerjaan
Analisa K.3 Mengerjakan 100 kg pekerjaan perakitan
Bahan Minyak Solar Industri Liter 1.0000
Minyak pelumas Liter 0.1000
Tenaga Kerja Pekerja OH 0.1000
Tukang Besi Konstruksi OH 0.1000
Kepala tukang OH 0.0010
Mandor OH 0.0050
Alat Sewa Alat Perakitan besi Jam 0.8000
100 Kg Jumlah Harga per Satuan Pekerjaan
1 Kg Jumlah Harga per Satuan Pekerjaan
Analisa K.4 Membuat 1 m2 pintu besi plat baja tebal 2 mm rangkap, rangka baja siku
Bahan Besi siku L 30.30.3 Kg 15.0000
Besi plat baja Kg 32.8000
Kawat las listrik Kg 0.0500
Tenaga Kerja Pekerja OH 1.0500
Tukang Las Biasa OH 1.0500
Kepala tukang OH 0.1050
Mandor OH 0.0520
Jumlah Harga per Satuan Pekerjaan
Analisa K.5 Mengerjakan 10 cm pengelasan dengan las listrik
Bahan Kawat las listrik Kg 0.4000
Minyak Solar Industri Liter 0.3000
Minyak pelumas Liter 0.0400
Tenaga Kerja Pekerja OH 0.0400
Tukang Besi Konstruksi OH 0.0200
Kepala tukang OH 0.0020
Mandor OH 0.0020
Alat Sewa Alat Las Listrik Jam 0.1700
10 Cm Jumlah Harga per Satuan Pekerjaan
1 Cm Jumlah Harga per Satuan Pekerjaan
Analisa K.6 Memasang 1 m2 pintu rolling door besi
Bahan Pintu gulung besi M2 1.0000
Tenaga Kerja Pekerja OH 1.2000
Tukang Las Biasa OH 1.2000
Kepala tukang OH 0.1200
Mandor OH 0.0060
Jumlah Harga per Satuan Pekerjaan
Analisa K.7 Memasang 1 m2 pintu lipat (Folding door) bahan plastik/PVC
Bahan Pintu lipat bahan PVC M2 1.0000
Tenaga Kerja Pekerja OH 0.4400
Tukang Kayu OH 0.4400
Kepala tukang OH 0.0440
Mandor OH 0.0220
Jumlah Harga per Satuan Pekerjaan
Analisa K.8 Memasang 1 m2 rolling door alluminium
Bahan Rolling door alluminium M2 1.0000
Tenaga Kerja Pekerja OH 1.0000
Tukang Khusus Aluminium OH 1.0000
Kepala tukang OH 0.1000
Mandor OH 0.0500
Jumlah Harga per Satuan Pekerjaan
Analisa K.9 Memasang 1 m kusen pintu alluminium
Bahan Profil alluminium M' 1.1000
Skrup fixer Buah 2.0000
Sealant Tube 0.0600
Tenaga Kerja Pekerja OH 0.0430
Tukang Khusus Aluminium OH 0.0430
Kepala tukang OH 0.0043
Mandor OH 0.0021
Jumlah Harga per Satuan Pekerjaan
Analisa K.10 Memasang 1 m2 pintu alluminium strip lebar 8 cm
Bahan Profil alluminium M' 4.4000
Alluminium strip M' 14.6000
Tenaga Kerja Pekerja OH 0.0850
Tukang Khusus Aluminium OH 0.0850
Kepala tukang OH 0.0085
Mandor OH 0.0042
Jumlah Harga per Satuan Pekerjaan
Analisa K.11 Memasang 1 m2 pintu kaca rangka alluminium
Bahan Pintu Allumunium M' 4.4000
Profil kaca M' 4.5000
Sealant Tube 0.2700
Tenaga Kerja Pekerja OH 0.0850
Tukang Khusus Aluminium OH 0.0850
Kepala tukang OH 0.0090
Mandor OH 0.0050
Jumlah Harga per Satuan Pekerjaan
Analisa K.12 Memasang 1 m2 terali besi strip (2 x 3) mm
Bahan Besi strip tebal 5 mm Kg 6.1770
Pengelasan Cm 27.0800
Tenaga Kerja Pekerja OH 1.6700
Tukang Las biasa OH 1.6700
Kepala tukang OH 0.1670
Mandor OH 0.0830
Jumlah Harga per Satuan Pekerjaan
Analisa K.13 Memasang 1 m2 kawat nyamuk
Bahan Kawat nyamuk M2 1.1000
Pengelasan Cm 11.1100
Besi strip tebal 2 mm Kg 1.7160
Tenaga Kerja Pekerja OH 0.1000
Tukang Khusus Aluminium OH 0.1000
Kepala tukang OH 0.0100
Mandor OH 0.0050
Jumlah Harga per Satuan Pekerjaan
Analisa K.14 Memasang 1 m2 jendela nako & trails
Bahan Jendela nako (rangka + kaca 5 mm) M2 1.1000
Paku skrup 1 cm - 2,5 cm Buah 10.0000
Besi strip tebal 5 mm M' 7.0000
Tenaga Kerja Pekerja OH 0.2000
Tukang Kayu OH 0.2000
Kepala tukang OH 0.0200
Mandor OH 0.0010
Jumlah Harga per Satuan Pekerjaan
Analisa K.15 Memasang 1 m' talang datar/ jurai seng bjls 28 lebar 90 cm
Bahan Seng Plat 3" x 6" BJLS 28 M' 1.0500
Paku 1 cm - 2,5 cm Kg 0.0150
Kayu Kelas II (Papan) M3 0.0190
Tenaga Kerja Pekerja OH 0.2000
Tukang Kayu OH 0.4000
Kepala tukang OH 0.0250
Mandor OH 0.0100
Jumlah Harga per Satuan Pekerjaan
Analisa K.16 Memasang 1 m' talang 1/2 lingkaran D-15 cm, Seng Plat 3" x 6" BJLS 30
Bahan Seng Plat 3" x 6" BJLS 30 M' 1.0500
Paku 1 cm - 2,5 cm Kg 0.0100
Besi strip tebal 5 mm Kg 0.5000
Tenaga Kerja Pekerja OH 0.1500
Tukang Kayu OH 0.3000
Kepala tukang OH 0.0300
Mandor OH 0.0080
Jumlah Harga per Satuan Pekerjaan
Analisa K.17 1 M2 Mengerjakan Rangka Atap Baja Ringan Zincalume
Bahan Profil U.85-06 Btg 0.4440
Profil reng RT.15 Btg 0.7110
Plat perletakan Bh 0.1780
Plat sudut Bh 0.0800
Tenaga Kerja Tukang Besi OH 0.7500
Kepala Tukang OH 0.0750
Pekerja OH 0.2500
Mandor OH 0.0100
Jumlah Harga per Satuan Pekerjaan
Analisa K.18 1 M' Talang Zincalume Untuk Patahan Atap
Bahan Talang Zincalume M' 0.4440
Profil reng RT.15 Btg 0.7110
Paku anti karat Bh 0.1780
Tenaga Kerja Tukang Besi OH 0.7500
Kepala Tukang OH 0.0750
Pekerja OH 0.2500
Mandor OH 0.0100
Jumlah Harga per Satuan Pekerjaan
Analisa K.19 1 M' Listplank Zincalume Dengan Lebar 24 Cm
Bahan Lisplank Zincalume M' 1.1000
Profil CT 6407-07 Btg 1.1000
Paku anti karat Bh 4.0000
Tenaga Kerja Tukang Besi OH 0.1000
Kepala Tukang OH 0.0800
Pekerja OH 0.2500
Mandor OH 0.0250
Jumlah Harga per Satuan Pekerjaan
L. PEKERJAAN KUNCI DAN KACA
Analisa L.1 1 Buah Pasang Kunsi Tanam Antik
Bahan Kunci Tanam Antik Buah 1.0000
Tenaga Kerja Pekerja OH 0.0600
Tukang Kayu OH 0.6000
Kepala Tukang OH 0.0600
Mandor OH 0.0030
Jumlah Harga per Satuan Pekerjaan
Analisa L.2 1 Buah Pasang Kunsi Tanam Biasa
Bahan Kunci Tanam Biasa Buah 1.0000
Tenaga Kerja Pekerja OH 0.0100
Tukang Kayu OH 0.5000
Kepala Tukang OH 0.0100
Mandor OH 0.0050
Jumlah Harga per Satuan Pekerjaan
Analisa L.3 1 Buah Pasang Kunsi Tanam Kamar Mandi
Bahan Kunci Tanam Kamar Mandi Buah 1.0000
Tenaga Kerja Pekerja OH 0.0050
Tukang Kayu OH 0.5000
Kepala Tukang OH 0.0050
Mandor OH 0.0025
Jumlah Harga per Satuan Pekerjaan
Analisa L.4 1 Buah Pasang Kunsi Silinder
Bahan Kunci Silinder Buah 1.0000
Tenaga Kerja Pekerja OH 0.0050
Tukang Kayu OH 0.5000
Kepala Tukang OH 0.0050
Mandor OH 0.0025
Jumlah Harga per Satuan Pekerjaan
Analisa L.5 1 Buah Pasang Engsel Pintu
Bahan Engsel Pintu Buah 1.0000
Tenaga Kerja Pekerja OH 0.0150
Tukang Kayu OH 0.1500
Kepala Tukang OH 0.0150
Mandor OH 0.0008
Jumlah Harga per Satuan Pekerjaan
Analisa L.6 1 Buah Pasang Engsel Jendela Kupu - kupu
Bahan Engsel Jendela Buah 1.0000
Tenaga Kerja Pekerja OH 0.0100
Tukang Kayu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0005
Jumlah Harga per Satuan Pekerjaan
Analisa L.7 1 Buah Pasang Engsel Angin
Bahan Engsel Angin Buah 1.0000
Tenaga Kerja Pekerja OH 0.0200
Tukang Kayu OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0100
Jumlah Harga per Satuan Pekerjaan
Analisa L.8 1 Buah Pasang Kait angin
Bahan Kait Angin Buah 1.0000
Tenaga Kerja Pekerja OH 0.0150
Tukang Kayu OH 0.1500
Kepala Tukang OH 0.0150
Mandor OH 0.0008
Jumlah Harga per Satuan Pekerjaan
Analisa L.9 1 Buah Pasang Door Closer
Bahan Door Closer Buah 1.0000
Tenaga Kerja Pekerja OH 0.0500
Tukang Kayu OH 0.5000
Kepala Tukang OH 0.0500
Mandor OH 0.0025
Jumlah Harga per Satuan Pekerjaan
Analisa L.10 1 Buah Pasang Kunci Selot
Bahan Kunci Selot Buah 1.0000
Tenaga Kerja Pekerja OH 0.0200
Tukang Kayu OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0010
Jumlah Harga per Satuan Pekerjaan
Analisa L.11 1 Buah Pasang Pegangan Pintu / Door Holder
Bahan Door Holder Buah 1.0000
Tenaga Kerja Pekerja OH 0.0500
Tukang Kayu OH 0.5000
Kepala Tukang OH 0.0500
Mandor OH 0.0025
Jumlah Harga per Satuan Pekerjaan
Analisa L.12 1 Buah Pasang Door Stop
Bahan Door Stop Buah 1.0000
Tenaga Kerja Pekerja OH 0.0100
Tukang Kayu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0005
Jumlah Harga per Satuan Pekerjaan
Analisa L.13 1 Buah Pasang Rel Pintu Dorong
Bahan Rel Pintu Dorong Buah 1.0000
Tenaga Kerja Pekerja OH 0.0600
Tukang Kayu OH 0.6000
Kepala Tukang OH 0.0600
Mandor OH 0.0030
Jumlah Harga per Satuan Pekerjaan
Analisa L.14 1 Buah Pasang Kunci Lemari
Bahan Kunci Lemari Buah 1.0000
Tenaga Kerja Pekerja OH 0.0250
Tukang Kayu OH 0.2500
Kepala Tukang OH 0.0250
Mandor OH 0.0013
Jumlah Harga per Satuan Pekerjaan
Analisa L.15 1 Buah Pasang Kaca tebal 3 mm
Bahan Kaca Polos tebal 3 mm M2 1.1000
Tenaga Kerja Pekerja OH 0.0150
Tukang Kayu OH 0.1500
Kepala Tukang OH 0.0150
Mandor OH 0.0008
Jumlah Harga per Satuan Pekerjaan
Analisa L.16 1 Buah Pasang Kaca tebal 5 mm
Bahan Kaca Polos tebal 5 mm M2 1.1000
Tenaga Kerja Pekerja OH 0.0150
Tukang Kayu OH 0.1500
Kepala Tukang OH 0.0150
Mandor OH 0.0008
Jumlah Harga per Satuan Pekerjaan
Analisa L.17 1 Buah Pasang Kaca tebal 8 mm
Bahan Kaca Polos tebal 8 mm M2 1.1000
Tenaga Kerja Pekerja OH 0.0165
Tukang Kayu OH 0.1650
Kepala Tukang OH 0.0165
Mandor OH 0.0008
Jumlah Harga per Satuan Pekerjaan
Analisa L.18 1 Buah Pasang Kaca tebal 12 mm
Bahan Kaca Polos tebal 12 mm M2 1.1000
Tenaga Kerja Pekerja OH 0.0250
Tukang Kayu OH 0.2500
Kepala Tukang OH 0.0250
Mandor OH 0.0013
Jumlah Harga per Satuan Pekerjaan
Analisa L.19 1 Buah Pasang Kaca Cermin tebal 5 mm
Bahan Kaca Cermin Tebal 5 mm M2 1.1000
Tenaga Kerja Pekerja OH 0.0150
Tukang Kayu OH 0.1500
Kepala Tukang OH 0.0150
Mandor OH 0.0008
Jumlah Harga per Satuan Pekerjaan
Analisa L.20 1 Buah Pasang Kaca Cermin tebal 6 mm
Bahan Kaca Cermin Tebal 6 mm M2 1.1000
Tenaga Kerja Pekerja OH 0.0150
Tukang Kayu OH 0.1500
Kepala Tukang OH 0.0150
Mandor OH 0.0008
Jumlah Harga per Satuan Pekerjaan
Analisa L.21 1 Buah Pasang Kaca Cermin tebal 8 mm
Bahan Kaca Cermin Tebal 8 mm M2 1.1000
Tenaga Kerja Pekerja OH 0.0165
Tukang Kayu OH 0.1650
Kepala Tukang OH 0.0165
Mandor OH 0.0008
Jumlah Harga per Satuan Pekerjaan
Analisa L.22 1 Buah Pasang Kaca Wireglass tebal 5 mm
Bahan Kaca Wireglass Tebal 5 mm M2 1.1000
Tenaga Kerja Pekerja OH 0.0150
Tukang Kayu OH 0.1500
Kepala Tukang OH 0.0150
Mandor OH 0.0008
Jumlah Harga per Satuan Pekerjaan
Analisa L.23 1 Buah Pasang Kaca Patri tebal 5 mm
Bahan Kaca Patri Tebal 5 mm M2 1.1000
Tenaga Kerja Pekerja OH 0.0150
Tukang Kayu OH 0.1500
Kepala Tukang OH 0.0150
Mandor OH 0.0008
Jumlah Harga per Satuan Pekerjaan
M. PEKERJAAN PENUTUP LANTAI DAN DINDING
Analisa M.1 Memasang 1 m2 Iantai ubin PC abu-abu ukuran (40 x 40) cm
Bahan Ubin Abu -abu 40 x40 cm Buah 6.6300
Semen Portland Kg 9.8000
Pasir Pasang M3 0.0450
Tenaga Kerja Pekerja OH 0.2500
Tukang Batu OH 0.1250
Kepala Tukang OH 0.0130
Mandor OH 0.0130
Jumlah Harga per Satuan Pekerjaan
Analisa M.2 Memasang 1 m2 Iantai ubin PC abu-abu ukuran (30 x 30) cm
Bahan Ubin Abu -abu 30 x 30 cm Buah 11.8700
Semen Portland Kg 10.0000
Pasir Pasang M3 0.0450
Tenaga Kerja Pekerja OH 0.2600
Tukang Batu OH 0.1300
Kepala Tukang OH 0.0130
Mandor OH 0.0130
Jumlah Harga per Satuan Pekerjaan
Analisa M.3 Memasang 1 m2 Iantai ubin PC abu-abu ukuran (20 x 20) cm
Bahan Ubin Abu -abu 20 x 20 cm Buah 26.5000
Semen Portland Kg 10.4000
Pasir Pasang M3 0.0450
Tenaga Kerja Pekerja OH 0.2700
Tukang Batu OH 0.1350
Kepala Tukang OH 0.0140
Mandor OH 0.0140
Jumlah Harga per Satuan Pekerjaan
Analisa M.4 Memasang 1 m2 Iantai ubin warna ukuran (40 x 40) cm
Bahan Ubin Warna 40 x 40 cm Buah 6.6300
Semen Portland Kg 9.8000
Pasir Pasang M3 0.0450
Semen Warna Kg 1.3000
Tenaga Kerja Pekerja OH 0.2500
Tukang Batu OH 0.1250
Kepala Tukang OH 0.0130
Mandor OH 0.0130
Jumlah Harga per Satuan Pekerjaan
Analisa M.5 Memasang 1 m2 Iantai ubin warna ukuran (30 x 30) cm
Bahan Ubin Warna 30 x 30 cm Buah 11.8700
Semen Portland Kg 10.0000
Pasir Pasang M3 0.0450
Semen Warna Kg 1.5000
Tenaga Kerja Pekerja OH 0.2600
Tukang Batu OH 0.1300
Kepala Tukang OH 0.0130
Mandor OH 0.0130
Jumlah Harga per Satuan Pekerjaan
Analisa M.6 Memasang 1 m2 Iantai ubin warna ukuran (20 x 20) cm
Bahan Ubin Warna 20 x 20 cm Buah 26.5000
Semen Portland Kg 10.4000
Pasir Pasang M3 0.0450
Semen Warna Kg 1.6200
Tenaga Kerja Pekerja OH 0.2700
Tukang Batu OH 0.1350
Kepala Tukang OH 0.0140
Mandor OH 0.0140
Jumlah Harga per Satuan Pekerjaan
Analisa M.7 Memasang 1 m2 Iantai ubin teraso ukuran (40 x 40) cm
Bahan Ubin Teraso 40 x 40 cm Buah 6.6300
Semen Portland Kg 9.8000
Pasir Pasang M3 0.0450
Semen Warna Kg 1.3000
Tenaga Kerja Pekerja OH 0.2500
Tukang Batu OH 0.1250
Kepala Tukang OH 0.0130
Mandor OH 0.0130
Jumlah Harga per Satuan Pekerjaan
Analisa M.8 Memasang 1 m2 Iantai ubin teraso ukuran (30 x 30) cm
Bahan Ubin Teraso 30 x 30 cm Buah 11.8700
Semen Portland Kg 10.0000
Pasir Pasang M3 0.0450
Semen Warna Kg 1.5000
Tenaga Kerja Pekerja OH 0.2600
Tukang Batu OH 0.0130
Kepala Tukang OH 0.0130
Mandor OH 0.0130
Jumlah Harga per Satuan Pekerjaan
Analisa M.9 Memasang 1 m2 Iantai ubin granit ukuran (40 x 40) cm
Bahan Ubin Granito 40 x 40 cm Buah 6.6300
Semen Portland Kg 9.8000
Pasir Pasang M3 0.0450
Semen Warna Kg 1.3000
Tenaga Kerja Pekerja OH 0.2500
Tukang Batu OH 0.1250
Kepala Tukang OH 0.0130
Mandor OH 0.0130
Jumlah Harga per Satuan Pekerjaan
Analisa M.10 Memasang 1 m2 Iantai ubin granit ukuran (30 x 30) cm
Bahan Ubin Granito 30 x 30 cm Buah 11.8700
Semen Portland Kg 10.0000
Pasir Pasang M3 0.0450
Semen Warna Kg 1.5000
Tenaga Kerja Pekerja OH 0.2600
Tukang Batu OH 0.1300
Kepala Tukang OH 0.0130
Mandor OH 0.0130
Jumlah Harga per Satuan Pekerjaan
Analisa M.11 Memasang 1 m plint ubin PC abu-abu ukuran (15 x 20) cm
Bahan Plint Ubin PC Abu - abu 15 x 20 cm Buah 5.3000
Semen Portland Kg 1.6500
Pasir Pasang M3 0.0040
Tenaga Kerja Pekerja OH 0.0900
Tukang Batu OH 0.0900
Kepala Tukang OH 0.0090
Mandor OH 0.0050
Jumlah Harga per Satuan Pekerjaan
Analisa M.12 Memasang 1 m plint ubin PC abu-abu ukuran (10 x 30) cm
Bahan Plint Ubin PC Abu-abu 10 x 30 cm Buah 3.5300
Semen Portland Kg 1.2400
Pasir Pasang M3 0.0030
Tenaga Kerja Pekerja OH 0.0900
Tukang Batu OH 0.0900
Kepala Tukang OH 0.0090
Mandor OH 0.0050
Jumlah Harga per Satuan Pekerjaan
Analisa M.13 Memasang 1 m plint ubin PC abu-abu ukuran (10 x 40) cm
Bahan Plint Ubin PC Abu-abu 10 x 40 cm Buah 2.6500
Semen Portland Kg 1.2400
Pasir Pasang M3 0.0030
Tenaga Kerja Pekerja OH 0.0900
Tukang Batu OH 0.0900
Kepala Tukang OH 0.0090
Mandor OH 0.0050
Jumlah Harga per Satuan Pekerjaan
Analisa M.14 Memasang 1 m plint ubin PC warna ukuran (10 x 20) cm
Bahan Plint Ubin PC Warna 10 x 20 cm Buah 5.3000
Semen Portland Kg 1.1400
Pasir Pasang M3 0.0030
Semen Warna Kg 0.1000
Tenaga Kerja Pekerja OH 0.0900
Tukang Batu OH 0.0900
Kepala Tukang OH 0.0090
Mandor OH 0.0050
Jumlah Harga per Satuan Pekerjaan
Analisa M.15 Memasang 1 m plint ubin PC warna ukuran (10 x 30) cm
Bahan Plint Ubin PC Warna 10 x 30 cm Buah 3.5300
Semen Portland Kg 1.1400
Pasir Pasang M3 0.0030
Semen Warna Kg 0.1000
Tenaga Kerja Pekerja OH 0.0900
Tukang Batu OH 0.0900
Kepala Tukang OH 0.0090
Mandor OH 0.0050
Jumlah Harga per Satuan Pekerjaan
Analisa M.16 Memasang 1 m plint ubin PC warna ukuran (10 x 40) cm
Bahan Plint Ubin PC Warna 10 x 40 cm Buah 2.6500
Semen Portland Kg 1.1400
Pasir Pasang M3 0.0030
Semen Warna Kg 0.1000
Tenaga Kerja Pekerja OH 0.0900
Tukang Batu OH 0.0900
Kepala Tukang OH 0.0090
Mandor OH 0.0050
Jumlah Harga per Satuan Pekerjaan
Analisa M.17 Memasang 1 m plint ubin teraso ukuran (10 x 30) cm
Bahan Plint Ubin Teraso 10 x 30 cm Buah 3.5300
Semen Portland Kg 1.1400
Pasir Pasang M3 0.0030
Semen Warna Kg 0.1000
Tenaga Kerja Pekerja OH 0.0900
Tukang Batu OH 0.0900
Kepala Tukang OH 0.0090
Mandor OH 0.0050
Jumlah Harga per Satuan Pekerjaan
Analisa M.18 Memasang 1 m plint ubin teraso ukuran (10 x 40) cm
Bahan Plint Ubin Teraso 10 x 40 cm Buah 2.6500
Semen Portland Kg 1.1400
Pasir Pasang M3 0.0030
Semen Warna Kg 0.1000
Tenaga Kerja Pekerja OH 0.0900
Tukang Batu OH 0.0900
Kepala Tukang OH 0.0090
Mandor OH 0.0050
Jumlah Harga per Satuan Pekerjaan
Analisa M.19 Memasang 1 m plint ubin granit ukuran (10 x 40) cm
Bahan Plint Ubin Granito 10 x 40 cm Buah 2.6500
Semen Portland Kg 1.1400
Pasir Pasang M3 0.0030
Semen Warna Kg 0.1000
Tenaga Kerja Pekerja OH 0.0900
Tukang Batu OH 0.0900
Kepala Tukang OH 0.0090
Mandor OH 0.0050
Jumlah Harga per Satuan Pekerjaan
Analisa M.20 Memasang 1 m plint ubin granit ukuran (10 x 30) cm
Bahan Plint Ubin Granito 10 x 30 cm Buah 3.5300
Semen Portland Kg 1.1400
Pasir Pasang M3 0.0030
Semen Warna Kg 0.1000
Tenaga Kerja Pekerja OH 0.0900
Tukang Batu OH 0.0900
Kepala Tukang OH 0.0090
Mandor OH 0.0050
Jumlah Harga per Satuan Pekerjaan
Analisa M.21 Memasang 1 m2 Iantai keramik artistik ukuran (10 x 20) cm
Bahan Ubin Keramik Artistik 10 x 20 cm Buah 53.0000
Semen Portland Kg 8.1900
Pasir Pasang M3 0.0450
Semen Warna Kg 2.7500
Tenaga Kerja Pekerja OH 0.7000
Tukang Batu OH 0.3500
Kepala Tukang OH 0.0350
Mandor OH 0.0350
Jumlah Harga per Satuan Pekerjaan
Analisa M.22 Memasang 1 m2 Iantai keramik artistik ukuran (10 x 10) cm
Bahan Plint Keramik Artistik 10 x 10 cm Buah 106.0000
Semen Portland Kg 8.1900
Pasir Pasang M3 0.0450
Semen Warna Kg 3.2000
Tenaga Kerja Pekerja OH 0.7000
Tukang Batu OH 0.3500
Kepala Tukang OH 0.0350
Mandor OH 0.0350
Jumlah Harga per Satuan Pekerjaan
Analisa M.23 Memasang 1 m2 Iantai keramik artistik ukuran (5 x 20) cm
Bahan Plint Keramik Artistik 5 x 20 cm Buah 106.0000
Semen Portland Kg 8.1900
Pasir Pasang M3 0.0450
Semen Warna Kg 3.2000
Tenaga Kerja Pekerja OH 0.7000
Tukang Batu OH 0.3500
Kepala Tukang OH 0.0350
Mandor OH 0.0350
Jumlah Harga per Satuan Pekerjaan
Analisa M.24 Memasang 1 m2 Iantai keramik ukuran (33 x 33) cm
Bahan Ubin Keramik 33 x 33 cm Buah 10.0000
Semen Portland Kg 8.1900
Pasir Pasang M3 0.0450
Semen Warna Kg 1.6200
Tenaga Kerja Pekerja OH 0.7000
Tukang Batu OH 0.3500
Kepala Tukang OH 0.0350
Mandor OH 0.0350
Jumlah Harga per Satuan Pekerjaan
Analisa M.25 Memasang 1 m2 Iantai keramik ukuran (30 x 30) cm
Bahan Ubin Keramik 30 X 30 cm Buah 11.8700
Semen Portland Kg 10.0000
Pasir Pasang M3 0.0450
Semen Warna Kg 1.5000
Tenaga Kerja Pekerja OH 0.7000
Tukang Batu OH 0.3500
Kepala Tukang OH 0.0350
Mandor OH 0.0350
Jumlah Harga per Satuan Pekerjaan
Analisa M.26 Memasang 1 m2 Iantai keramik ukuran (20 x 20) cm
Bahan Ubin Keramik 20 x 20 cm Buah 26.5000
Semen Portland Kg 10.4000
Pasir Pasang M3 0.0450
Semen Warna Kg 1.6200
Tenaga Kerja Pekerja OH 0.7000
Tukang Batu OH 0.3500
Kepala Tukang OH 0.0350
Mandor OH 0.0350
Jumlah Harga per Satuan Pekerjaan
Analisa M.27 Memasang 1 m2 Iantai keramik ukuran (10 x 33) cm, variasi/border
Bahan Ubin Keramik 10 x 33 cm Variasi Buah 33.0000
Semen Portland Kg 9.8000
Pasir Pasang M3 0.0450
Semen Warna Kg 4.3700
Tenaga Kerja Pekerja OH 1.0500
Tukang Batu OH 0.5250
Kepala Tukang OH 0.0530
Mandor OH 0.0530
Jumlah Harga per Satuan Pekerjaan
Analisa M.28 Memasang 1 m2 lantai mosaik ukuran (30 x 30) cm, campuran spesi 1 PC : 3 PP
Bahan Mozaik 30 x 30 cm Buah 11.8700
Semen Portland Kg 14.1500
Pasir Pasang M3 0.0390
Semen Warna Kg 2.0000
Tenaga Kerja Pekerja OH 0.7000
Tukang Batu OH 0.3500
Kepala Tukang OH 0.0350
Mandor OH 0.0350
Jumlah Harga per Satuan Pekerjaan
Analisa M.29 Memasang 1 m plint keramik ukuran (10 x 20) cm
Bahan Plint Keramik Artistik 10 x 20 cm Buah 5.3000
Semen Portland Kg 1.1400
Pasir Pasang M3 0.0030
Semen Warna Kg 0.0250
Tenaga Kerja Pekerja OH 0.0900
Tukang Batu OH 0.0900
Kepala Tukang OH 0.0090
Mandor OH 0.0050
Jumlah Harga per Satuan Pekerjaan
Analisa M.30 Memasang 1 m' plint keramik ukuran (10 x 10) cm
Bahan Plint Keramik Artistik 10 x 10 cm Buah 10.6000
Semen Portland Kg 1.1400
Pasir Pasang M3 0.0030
Semen Warna Kg 0.0500
Tenaga Kerja Pekerja OH 0.0900
Tukang Batu OH 0.0900
Kepala Tukang OH 0.0090
Mandor OH 0.0050
Jumlah Harga per Satuan Pekerjaan
Analisa M.31 Memasang 1 m' plint keramik ukuran (5 x 20) cm
Bahan Plint Keramik Artistik 5 x 20 cm Buah 5.3000
Semen Portland Kg 0.5700
Pasir Pasang M3 0.0015
Semen Warna Kg 0.0130
Tenaga Kerja Pekerja OH 0.0900
Tukang Batu OH 0.0900
Kepala Tukang OH 0.0090
Mandor OH 0.0050
Jumlah Harga per Satuan Pekerjaan
Analisa M.32 Memasang 1 m2 Iantai marmer ukuran (100 x 100) cm
Bahan Marmer 100 x 100 cm Buah 1.0600
Semen Portland Kg 8.1900
Pasir Pasang M3 0.0450
Semen Warna Kg 0.6500
Tenaga Kerja Pekerja OH 0.7000
Tukang Batu OH 0.3500
Kepala Tukang OH 0.0350
Mandor OH 0.0350
Jumlah Harga per Satuan Pekerjaan
Analisa M.33 Memasang 1 m2 Iantai karpet
Bahan Karpet M2 1.0500
Lem kayu Kg 0.3500
Tenaga Kerja Pekerja OH 0.1700
Tukang Batu OH 0.1700
Kepala Tukang OH 0.0170
Mandor OH 0.0090
Jumlah Harga per Satuan Pekerjaan
Analisa M.34 Memasang 1 m2 Iantai kayu (gymfloor)
Bahan Gymfloor M2 1.0500
Lem kayu Kg 0.6000
Tenaga Kerja Pekerja OH 0.7000
Tukang Batu OH 0.3500
Kepala Tukang OH 0.0350
Mandor OH 0.0350
Jumlah Harga per Satuan Pekerjaan
Analisa M.35 Memasang 1 m2 dinding porselen ukuran (11 x 11) cm putih
Bahan Porselen 11 x 11 cm putih Buah 86.0000
Semen Portland Kg 9.3000
Pasir Pasang M3 0.0180
Semen warna Kg 1.5000
Tenaga Kerja Pekerja OH 1.0000
Tukang Batu OH 0.5000
Kepala Tukang OH 0.0500
Mandor OH 0.0500
Jumlah Harga per Satuan Pekerjaan
Analisa M.36 Memasang 1 m2 dinding porselen ukuran (11 x 11) cm Warna
Bahan Porselen 11 x 11 cm warna Buah 86.0000
Semen Portland Kg 9.3000
Pasir Pasang M3 0.0180
Semen warna Kg 1.5000
Tenaga Kerja Pekerja OH 1.0000
Tukang Batu OH 0.5000
Kepala Tukang OH 0.0500
Mandor OH 0.0500
Jumlah Harga per Satuan Pekerjaan
Analisa M.37 Memasang 1 m2 dinding porselin ukuran (10 x 20) cm putih
Bahan Porselen 10 x 20 cm putih Buah 53.0000
Semen Portland Kg 9.3000
Pasir Pasang M3 0.0180
Semen warna Kg 2.7500
Tenaga Kerja Pekerja OH 0.9000
Tukang Batu OH 0.4500
Kepala Tukang OH 0.0450
Mandor OH 0.0450
Jumlah Harga per Satuan Pekerjaan
Analisa M.38 Memasang 1 m2 dinding porselin ukuran (10 x 20) cm Warna
Bahan Porselen 10 x 20 cm warna Buah 53.0000
Semen Portland Kg 9.3000
Pasir Pasang M3 0.0180
Semen warna Kg 2.7500
Tenaga Kerja Pekerja OH 0.9000
Tukang Batu OH 0.4500
Kepala Tukang OH 0.0450
Mandor OH 0.0450
Jumlah Harga per Satuan Pekerjaan
Analisa M.39 Memasang 1 m2 dinding porselin ukuran (20 x 20) cm Warna
Bahan Porselen 20 x 20 cm warna Buah 26.5000
Semen Portland Kg 9.3000
Pasir Pasang M3 0.0180
Semen warna Kg 1.9400
Tenaga Kerja Pekerja OH 0.9000
Tukang Batu OH 0.4500
Kepala Tukang OH 0.0450
Mandor OH 0.0450
Jumlah Harga per Satuan Pekerjaan
Analisa M.40 Memasang 1 m2 dinding keramik artistik ukuran (10 x 20) cm
Bahan Keramik Artistik 10 x 20 cm Buah 53.0000
Semen Portland Kg 9.3000
Pasir Pasang M3 0.0180
Semen warna Kg 2.7500
Tenaga Kerja Pekerja OH 0.9000
Tukang Batu OH 0.4500
Kepala Tukang OH 0.0450
Mandor OH 0.0450
Jumlah Harga per Satuan Pekerjaan
Analisa M.41 Memasang 1 m2 dinding keramik artistik ukuran (5 x 20) cm
Bahan Keramik Artistik 5 x 20 cm Buah 106.0000
Semen Portland Kg 9.3000
Pasir Pasang M3 0.0180
Semen warna Kg 2.9000
Tenaga Kerja Pekerja OH 0.9000
Tukang Batu OH 0.4500
Kepala Tukang OH 0.0450
Mandor OH 0.0450
Jumlah Harga per Satuan Pekerjaan
Analisa M.42 Memasang 1 m2 dinding keramik ukuran (10 x 20) cm
Bahan Keramik Artistik 10 x 20 cm Buah 53.0000
Semen Portland Kg 9.3000
Pasir Pasang M3 0.0180
Semen warna Kg 2.7500
Tenaga Kerja Pekerja OH 0.9000
Tukang Batu OH 0.4500
Kepala Tukang OH 0.0450
Mandor OH 0.0450
Jumlah Harga per Satuan Pekerjaan
Analisa M.43 Memasang 1 m2 dinding keramik ukuran (20 x 20) cm
Bahan Keramik 20 x 20 cm Buah 26.5000
Semen Portland Kg 9.3000
Pasir Pasang M3 0.0180
Semen warna Kg 1.9400
Tenaga Kerja Pekerja OH 0.9000
Tukang Batu OH 0.4500
Kepala Tukang OH 0.0450
Mandor OH 0.0450
Jumlah Harga per Satuan Pekerjaan
Analisa M.44 Memasang 1 m2 dinding marmer ukuran (100 x 100) cm
Bahan Marmer 100 x 100 cm Buah 1.0600
Paku 12 cm Kg 3.0030
Semen Portland Kg 12.4400
Pasir Pasang M3 0.0250
Semen warna Kg 0.6500
Tenaga Kerja Pekerja OH 1.3000
Tukang Batu OH 0.6500
Kepala Tukang OH 0.0650
Mandor OH 0.0650
Jumlah Harga per Satuan Pekerjaan
Analisa M.45 Memasang 1 m2 dinding bata pelapis ukuran (3 x 7 x 24) cm
Bahan Bata pelapis dinding Buah 63.0000
Semen Portland Kg 12.4400
Pasir Pasang M3 0.0250
Semen warna Kg 2.7500
Tenaga Kerja Pekerja OH 1.0000
Tukang Batu OH 0.5000
Kepala Tukang OH 0.0500
Mandor OH 0.0500
Jumlah Harga per Satuan Pekerjaan
Analisa M.46 Memasang 1 m2 dinding batu paras
Bahan Batu Paras M2 1.1000
Semen Portland Kg 11.7500
Pasir Pasang M3 0.0350
Tenaga Kerja Pekerja OH 0.7000
Tukang Batu OH 0.3500
Kepala Tukang OH 0.0350
Mandor OH 0.0350
Jumlah Harga per Satuan Pekerjaan
Analisa M.47 Memasang 1 m2 dinding batu tempel hitam
Bahan Batu tempel hitam Buah 1.1000
Semen Portland Kg 11.7500
Pasir Pasang M3 0.0350
Tenaga Kerja Pekerja OH 0.7000
Tukang Batu OH 0.3500
Kepala Tukang OH 0.0350
Mandor OH 0.0350
Jumlah Harga per Satuan Pekerjaan
Analisa M.48 Memasang 1 m lantai Vinyl ukuran (30 x 30) cm KL. I
Bahan Vinyl Buah 11.8700
Lem vinyl Kg 0.3500
Tenaga Kerja Pekerja OH 0.1500
Tukang Batu OH 0.1500
Kepala Tukang OH 0.0150
Mandor OH 0.0080
Jumlah Harga per Satuan Pekerjaan
Analisa M.49 Memasang 1 m2 wall paper, lebar 50 cm
Bahan Wall paper M' 2.2000
Lem Kayu Kg 0.2500
Tenaga Kerja Pekerja OH 0.3500
Tukang Batu OH 0.1750
Kepala Tukang OH 0.0170
Mandor OH 0.0020
Jumlah Harga per Satuan Pekerjaan
Analisa M.50 Memasang 1 m2 floor hardener
Bahan Floor hardener Kg 5.0000
Tenaga Kerja Pekerja OH 0.1200
Tukang Batu OH 0.1200
Kepala Tukang OH 0.0120
Mandor OH 0.0060
Jumlah Harga per Satuan Pekerjaan
Analisa M.51 Memasang 1 m' plint Vinyl karet ukuran (15 x 30) cm dengan perekat
Bahan Vinyl karet Buah 1.7600
Lem vinyl Kg 0.0800
Tenaga Kerja Pekerja OH 0.0800
Tukang Batu OH 0.0800
Kepala Tukang OH 0.0080
Mandor OH 0.0040
Jumlah Harga per Satuan Pekerjaan
Analisa M.52 Memasang 1 m' plint kayu kelas II tebal 2Cm, Lebar 10 Cm
Bahan Kayu Kelas II (Balok) M3 0.0030
Paku/skrup 5 cm Kg 0.0500
Tenaga Kerja Pekerja OH 0.1200
Tukang Batu OH 0.1200
Kepala Tukang OH 0.0120
Mandor OH 0.0060
Jumlah Harga per Satuan Pekerjaan
Analisa M.53 1 M2 Pemasangan Paving Block Tebal 8 cm
Bahan Paving Block Tebal 8 cm Buah 40.5000
Pasir Urug M3 0.1000
Tenaga Kerja Tukang Batu OH 0.1000
Kepala Tukang OH 0.0100
Pekerja OH 0.4000
Mandor OH 0.0400
Jumlah Harga per Satuan Pekerjaan
Analisa M.54 1 M2 Pemasangan Paving Block Tebal 6 cm
Bahan Paving Block Tebal 6 cm Buah 40.5000
Pasir Urug M3 0.1000
Tenaga Kerja Tukang Batu OH 0.1000
Kepala Tukang OH 0.0100
Pekerja OH 0.4000
Mandor OH 0.0400
Jumlah Harga per Satuan Pekerjaan

Analisa M.55 1 M' Pasang Kanstin dari beton tumbuk 1 Pc : 3 Ps : 5 Kr


Bahan Beton Tumbuk 1 Pc : 3 Ps : 5 Kr M3 0.0200
Begisting Pondasi M3 0.1200
Jumlah Harga per Satuan Pekerjaan
Analisa M.56 1 M2 Pemasangan Paving Block Tebal 8 cm Type Segienam
Bahan Paving Block Tebal 8 cm Type Segienam Buah 36.6000
Pasir Urug M3 0.1000
Tenaga Kerja Tukang Batu OH 0.1000
Kepala Tukang OH 0.0100
Pekerja OH 0.4000
Mandor OH 0.0400
Jumlah Harga per Satuan Pekerjaan
Analisa M.57 1 M2 Pemasangan Paving Block Tebal 6 cm Type Segienam
Bahan Paving Block Tebal 6 cm Type Segienam Buah 36.6000
Pasir Urug M3 0.1000
Tenaga Kerja Tukang Batu OH 0.1000
Kepala Tukang OH 0.0100
Pekerja OH 0.4000
Mandor OH 0.0400
Jumlah Harga per Satuan Pekerjaan
N. PEKERJAAN PENGECATAN
Analisa N.1 1 m² Mengikis / Mengerok Permukaan Cat Tembok Lama
Bahan Soda Api Kg 0.0500
Tenaga Kerja Pekerja OH 0.1500
Mandor OH 0.0025
Jumlah Harga per Satuan Pekerjaan
Analisa N.2 1 m² Mencuci Bidang Permukaan Tembok yang Pernah dicat
Bahan Sabun Kg 0.0500
Tenaga Kerja Pekerja OH 0.1500
Mandor OH 0.0025
Jumlah Harga per Satuan Pekerjaan
Analisa N.3 1 m² Mengerok Karat Cat Lama Permukaan Baja dengan Cara Manual
Bahan Sabun Kg 0.0500
Tenaga Kerja Pekerja OH 0.1500
Mandor OH 0.0025
Jumlah Harga per Satuan Pekerjaan
Analisa N.4 1 m² Menyabun Permukaan Tembok Lama
Bahan Sabun Kg 0.0500
Tenaga Kerja Pekerja OH 0.1500
Mandor OH 0.0025
Jumlah Harga per Satuan Pekerjaan
Analisa N.5 1 m² Mengerok Karat atau Cat Lama Permukaan Baja dgn Pancar Pasir ( Sanblasting ) dgn Tingkat Kebersihan Sa 2½.
Bahan Pasir Silika Kg 40.0000
Bahan Bakar Minyak Liter 10.0000
Peralatan Kompresor, Blasting Pot , Selang Dan Nozzle Hari 1.0000
Tenaga Kerja Pekerja OH 1.6000
Tukang Cat OH 1.6000
Kepala Tukang OH 0.8000
Mandor OH 0.5000
Jumlah Harga per Satuan Pekerjaan
Analisa N.6 1 m² Mendempul dan Menggosok Kayu
Bahan Dempul Jadi Kg 0.0800
Minyak Cat Liter 0.0200
Batu Apung Kg 0.0100
Tenaga Kerja Pekerja OH 0.0400
Tukang Cat OH 0.0400
Kepala Tukang OH 0.0040
Mandor OH 0.0025
Jumlah Harga per Satuan Pekerjaan
Analisa N.7 1 m² Mengecatan Bidang Kayu Lama
Bahan Plamir Kg 0.1500
Cat Dasar Kg 0.1700
Cat Penutup Kg 0.1700
Tenaga Kerja Pekerja OH 0.0700
Tukang Cat OH 0.0750
Kepala Tukang OH 0.0075
Mandor OH 0.0025
Jumlah Harga per Satuan Pekerjaan
Analisa N.8 1 m² Mengecatan Bidang Kayu Baru ( 1 Lapis Plamir ), 1 Lapis Cat Dasar, 2 Lapis Cat Penutup
Bahan Cat Meni Kg 0.2000
Plamir Kg 0.1500
Cat Dasar Kg 0.1700
Cat Kayu Kg 0.2600
Tenaga Kerja Pekerja OH 0.0700
Tukang Cat OH 0.0090
Kepala Tukang OH 0.0060
Mandor OH 0.0025
Jumlah Harga per Satuan Pekerjaan
Analisa N.9 1 m² Pelaburan Bidang Kayu dengan Teak Oil
Bahan Teak Oil Liter 0.3600
Tenaga Kerja Pekerja OH 0.0400
Tukang Cat OH 0.0630
Kepala Tukang OH 0.0630
Mandor OH 0.0025
Jumlah Harga per Satuan Pekerjaan
Analisa N.10 1 m² Pelaburan Bidang Kayu dengan Vernis
Bahan Vernis Kg 0.1500
Dempul Kg 0.0500
Ampelas Lembar 0.1000
Kuas Buah 0.0100
Tenaga Kerja Pekerja OH 0.1600
Tukang Cat OH 0.1600
Kepala Tukang OH 0.0160
Mandor OH 0.0025
Jumlah Harga per Satuan Pekerjaan
Analisa N.11 1 m² Mengecat Tembok baru ( 1 Plamir, 1 lapis cat dasar, 2 Lapis Cat penutup)
Bahan Plamir Kg 0.1000
Cat Dasar Kg 0.1000
Cat Tembok Kg 0.2600
Tenaga Kerja Pekerja OH 0.0200
Tukang Cat OH 0.0630
Kepala Tukang OH 0.0063
Mandor OH 0.0025
Jumlah Harga per Satuan Pekerjaan
Analisa N.12 1 m² Melabur Tembok dengan Kapur Sirih
Bahan Ampelas Lembar 0.1000
Alang - alang Ikat 0.2500
Perancah Kayu M3 0.0020
Kapur Sirih Kg 0.1500
Tenaga Kerja Pekerja OH 0.1500
Tukang Cat OH 0.0010
Kepala Tukang OH 0.0001
Mandor OH 0.0025
Jumlah Harga per Satuan Pekerjaan
Analisa N.13 1 m² Melabur Tembok Lama dengan Kapur Sirih ( untuk pemeliharaan )
Bahan Perancah Kayu M3 0.0020
Kapur Sirih Kg 0.3000
Tenaga Kerja Pekerja OH 0.0400
Tukang Cat OH 0.0050
Kepala Tukang OH 0.0005
Mandor OH 0.0025
Jumlah Harga per Satuan Pekerjaan
Analisa N.14 1 m² Pemasangan Wall Paper
Bahan Wall Paper M2 1.2000
Perekat Kg 0.2000
Tenaga Kerja Pekerja OH 0.0200
Tukang Cat OH 0.2000
Kepala Tukang OH 0.0020
Mandor OH 0.0025
Jumlah Harga per Satuan Pekerjaan
Analisa N.15 1 m² Pengecatan Permukaan Baja dengan Meni Besi
Bahan Cat Meni Besi Kg 0.1000
Kuas Buah 0.0100
Tenaga Kerja Pekerja OH 0.0200
Tukang Cat OH 0.2000
Kepala Tukang OH 0.0200
Mandor OH 0.0100
Jumlah Harga per Satuan Pekerjaan
Analisa N.16 1 m² Pengecatan Permukaan Baja dengan Meni Besi dan Perancah
Bahan Cat Meni Besi Kg 0.1000
Kuas Buah 0.0100
Perancah Kayu M3 0.0020
Tenaga Kerja Pekerja OH 0.2500
Tukang Cat OH 0.2250
Kepala Tukang OH 0.0225
Mandor OH 0.0075
Jumlah Harga per Satuan Pekerjaan
Analisa N.17 1 m² Pengecatan Permukaan Baja Lapis Seng ( Galbani ) secara Manual Sistem 4 Lapis Cat Konvensional, tebal 200 um
Bahan Meni ( Read Lead ) A Kg 0.1000
Meni ( Read Lead ) B Kg 0.1000
Alluminium C Kg 0.0400
Alluminium B Kg 0.0400
Pengencer Liter 0.0100
Perancah Kayu M3 0.0020
Tenaga Kerja Pekerja OH 0.0060
Tukang Cat OH 0.0060
Kepala Tukang OH 0.0225
Mandor OH 0.0075
Jumlah Harga per Satuan Pekerjaan
Analisa N.18 1 m² Pengecatan Permukaan Baja Lapis Seng ( Galbani ) secara Manual Sistem 1 Lapis Cat Mutakhir, tebal 200 um
Bahan Cat Meni Besi Kg 0.3000
Tenaga Kerja Pekerja OH 0.0060
Tukang Cat OH 0.0600
Kepala Tukang OH 0.0120
Mandor OH 0.0060
Jumlah Harga per Satuan Pekerjaan
Analisa N.19 1 m² Pengecatan Permukaan Baja Lapis Seng ( Galbani ) secara Manual Sistem 3 Lapis Cat Konvensional, tebal 200 um
Bahan Cat Dasar Kg 0.1100
Cat Antara Kg 0.1700
Cat Penutup Kg 0.0800
Tenaga Kerja Pekerja OH 0.5000
Tukang Cat OH 0.8000
Kepala Tukang OH 0.3000
Mandor OH 0.2000
Jumlah Harga per Satuan Pekerjaan
Analisa N.20 1 m² Pengecatan Permukaan Baja Lapis Seng ( Galbani ) secara Semprot ( Airless Spray ) dgn Sistem 1 Lapis Cat Mutakhir, te
Bahan Cat Dasar Kg 0.3000
Tenaga Kerja Pekerja OH 0.4000
Tukang Cat OH 0.7000
Kepala Tukang OH 0.2000
Mandor OH 0.2000
Jumlah Harga per Satuan Pekerjaan
Analisa N.21 1 M2 Meresidu/Ter kayu
Bahan Residu Liter 0.3500
Tenaga Kerja Pekerja OH 0.1000
Mandor OH 0.0060
Jumlah Harga per Satuan Pekerjaan
Analisa N.22 100 M2 Mengecat Genteng
Bahan Cat Genteng Kg 25.0000
Ampelas Lembar 15.0000
Tenaga Kerja Tukang Cat OH 1.0000
Kepala Tukang OH 0.1000
Mandor OH 6.0000
100 M2 Jumlah Harga per Satuan Pekerjaan
1 M2 Jumlah Harga per Satuan Pekerjaan
Analisa N.23 100 M2 Mengecat dengan Cat tembok (2 x Cat untuk Pemeliharaan)
Bahan Cat Tembok Kg 20.0000
Ampelas Lembar 5.0000
Tenaga Kerja Tukang Cat OH 0.5000
Kepala Tukang OH 0.0500
Pekerja OH 4.0000
100 M2 Jumlah Harga per Satuan Pekerjaan
1 M2 Jumlah Harga per Satuan Pekerjaan
Analisa N.24 100 M2 Mengecat besi dengan Cat Mengkilat
Bahan Cat Meni besi Kg 14.2000
Cat Besi Kg 28.4000
Ampelas Lembar 5.0000
Tenaga Kerja Tukang Cat OH 2.2500
Kepala Tukang OH 0.2250
Pekerja OH 15.0000
Mandor OH 0.7500
100 M2 Jumlah Harga per Satuan Pekerjaan
1 M2 Jumlah Harga per Satuan Pekerjaan
Analisa N.25 Pengecatan 100 M' Marka Jalan
Bahan Cat Marka Jalan Kg 155.73790
Thinner Liter 98.65750
Alat Bantu ( set @ 3 alat) Set 0.01080
Peralatan Compressor Jam 7.04720
Dump Truck Jam 7.04720
Tenaga Kerja Tukang Cat OH 2.01350
Pekerja OH 8.05407
Mandor OH 1.00670
100 M2 Jumlah Harga per Satuan Pekerjaan
1 M2 Jumlah Harga per Satuan Pekerjaan
O. PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
Analisa O.1 1 Buah Pasang saklar Triple
Bahan Saklar triple kualitas baik Buah 1.0000
Tenaga Kerja Instalatur Listrik OH 0.3200
Asisten Instalatur Listrik OH 0.1600
Jumlah Harga per Satuan Pekerjaan
Analisa O.2 1 Buah Pasang saklar Double
Bahan Saklar Double kualitas baik Buah 1.0000
Tenaga Kerja Instalatur Listrik OH 0.3200
Asisten Instalatur Listrik OH 0.1600
Jumlah Harga per Satuan Pekerjaan
Analisa O.3 1 Buah Pasang saklar Single
Bahan Saklar Single kualitas baik Buah 1.0000
Tenaga Kerja Instalatur Listrik OH 0.3200
Asisten Instalatur Listrik OH 0.1600
Jumlah Harga per Satuan Pekerjaan
Analisa O.4 1 Buah Pasang Stopkontak
Bahan Stop Kontak Buah 1.0000
Tenaga Kerja Instalatur Listrik OH 0.3200
Asisten Instalatur Listrik OH 0.1600
Jumlah Harga per Satuan Pekerjaan
Analisa O.5 1 Titik Instalasi Listrik
Bahan Kabel NYY 2,5 mm ( 3 x 2,5 ) M' 15.0000
Assecories dihitung 30% dari Bahan Titik 1.0000
Tenaga Kerja Instalatur Listrik OH 0.3200
Asisten Instalatur Listrik OH 0.1600
Jumlah Harga per Satuan Pekerjaan
Add. SNI O6 1 Buah Pasang Grendel Pintu Tanam
Bahan Grendel pintu Tanam Buah 1.0000
Tenaga Kerja Pekerja OH 0.0100
Tukang Kayu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0005
Jumlah Harga per Satuan Pekerjaan
Add. SNI O7 1 Buah Pasang Grendel Jendela
Bahan Grendel Jendela Buah 1.0000
Tenaga Kerja Pekerja OH 0.0100
Tukang Kayu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0005
Jumlah Harga per Satuan Pekerjaan
Add. SNI O8 1 Buah Pasang Tarikan Jendela
Bahan Tarikan Jendela Buah 1.0000
Tenaga Kerja Pekerja OH 0.0100
Tukang Kayu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0005
Jumlah Harga per Satuan Pekerjaan

Spl. A.4.4.3.4 Pemasangan 1 M2 Conblock


Bahan Conblock M2 1.1000
Pasir Pasang M3 0.1000
Tenaga Kerja Pekerja OH 0.4000
Tukang Batu OH 0.1000
Kepala Tukang OH 0.0100
Mandor OH 0.0400
Jumlah Harga per Satuan Pekerjaan

Add. SNI O9 Pemasangan 1 M' Pagar Panel Pracetak


Bahan Panel Beton Pracetak 5 x 40 x 240 cm Lbr 0.9860
Kolom Beton Pracetak 17 x 17 x 300 cm Btng 0.5250
Pasir Beton M3 0.0740
Koral 2/3 M3 0.1460
Semen Portland Kg 45.0000
Tenaga Kerja Pekerja OH 0.3750
Tukang Batu OH 0.1250
Kepala Tukang OH 0.0120
Mandor OH 0.0190
Jumlah Harga per Satuan Pekerjaan

Add. SNI O10 1 M3 Pasangan bronjong kawat Q 3mm diisi batu belah:
Bahan kawat galvanis Q 3mm Kg 2.5000
batu belah M3 1.3000
Tenaga Kerja Pekerja Anyam OH 2.6000
Pekerja Pengisi Batu OH 2.5000
Tukang Anyam OH 2.0000
Mandor OH 0.0750
Jumlah Harga per Satuan Pekerjaan

Add. SNI O11 1 M3 Pasangan bronjong kawat Q 3mm diisi batu belah:
Bahan kawat galvanis Q 3mm Kg 2.5000
batu belah M3 1.3000
Tenaga Kerja Pekerja Anyam OH 2.6000
Pekerja Pengisi Batu OH 2.5000
Tukang Anyam OH 2.0000
Mandor OH 0.0750
Jumlah Harga per Satuan Pekerjaan
UNG DAN PERUMAHAN

Harga Satuan
Bahan/Upah Jumlah
(Rp)

-
-
-
-
-
-
-
95,000.00 19,000.00
75,000.00 30,000.00
100,000.00 2,000.00
110,000.00 2,200.00
per Satuan Pekerjaan 53,200.00

37,950.00 47,437.50
1,300.00 3,250.00
264,500.00 317,400.00
326,212.00 2,935.91
4,140,000.00 298,080.00
18,000.00 1,080.00
65,000.00 29,250.00
95,000.00 19,000.00
75,000.00 30,000.00
100,000.00 2,000.00
110,000.00 2,200.00
per Satuan Pekerjaan 752,633.41

-
-
-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

4,140,000.00 49,680.00
18,000.00 360.00
4,255,000.00 29,785.00
95,000.00 9,500.00
75,000.00 7,500.00
100,000.00 1,000.00
110,000.00 550.00
per Satuan Pekerjaan 98,375.00

37,950.00 47,437.50
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
per Satuan Pekerjaan 47,437.50

-
-
-
-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

75,000.00 7,500.00
110,000.00 5,500.00
per Satuan Pekerjaan 13,000.00

-
-
-
-
-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

2,012,500.00 374,325.00
18,000.00 5,400.00
4,140,000.00 57,960.00
95,000.00 190,000.00
110,000.00 5,500.00
per Satuan Pekerjaan 633,185.00

8,400.00 8,400.00
10,000.00 2,500.00
95,000.00 190,000.00
75,000.00 75,000.00
100,000.00 20,000.00
110,000.00 5,500.00
per Satuan Pekerjaan 301,400.00

-
-
-
-
-
per Satuan Pekerjaan -

75,000.00 600,000.00
110,000.00 44,000.00
per Satuan Pekerjaan 644,000.00

75,000.00 15,000.00
110,000.00 1,100.00
per Satuan Pekerjaan 16,100.00

75,000.00 3,750.00
110,000.00 1,100.00
per Satuan Pekerjaan 4,850.00

75,000.00 7,500.00
110,000.00 1,100.00
per Satuan Pekerjaan 8,600.00

95,000.00 23,750.00
100,000.00 2,500.00
75,000.00 75,000.00
110,000.00 5,500.00
per Satuan Pekerjaan 106,750.00
per Satuan Pekerjaan 10,675.00

95,000.00 57,000.00
100,000.00 6,000.00
75,000.00 150,000.00
110,000.00 11,000.00
per Satuan Pekerjaan 224,000.00
per Satuan Pekerjaan 22,400.00

95,000.00 570,000.00
100,000.00 60,000.00
75,000.00 300,000.00
110,000.00 22,000.00
per Satuan Pekerjaan 952,000.00
per Satuan Pekerjaan 95,200.00

-
-
-
-
per Satuan Pekerjaan -

-
-
-
per Satuan Pekerjaan -

-
-
per Satuan Pekerjaan -

75,000.00 67,500.00
110,000.00 4,950.00
per Satuan Pekerjaan 72,450.00

75,000.00 78,750.00
110,000.00 7,370.00
per Satuan Pekerjaan 86,120.00

-
-
per Satuan Pekerjaan -

-
-
per Satuan Pekerjaan -

-
-
per Satuan Pekerjaan -

-
-
per Satuan Pekerjaan -

-
-
per Satuan Pekerjaan -

75,000.00 18,750.00
110,000.00 880.00
per Satuan Pekerjaan 19,630.00

75,000.00 37,500.00
110,000.00 5,500.00
per Satuan Pekerjaan 43,000.00

180,550.00 216,660.00
75,000.00 22,500.00
110,000.00 1,100.00
per Satuan Pekerjaan 240,260.00

-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
per Satuan Pekerjaan -

-
-
-
per Satuan Pekerjaan -
268,000.00 321,600.00
1,300.00 262,600.00
190,000.00 92,150.00
75,000.00 112,500.00
95,000.00 71,250.00
100,000.00 7,500.00
110,000.00 8,250.00
per Satuan Pekerjaan 875,850.00

268,000.00 321,600.00
1,300.00 211,900.00
190,000.00 98,800.00
75,000.00 112,500.00
95,000.00 71,250.00
100,000.00 7,500.00
110,000.00 8,250.00
per Satuan Pekerjaan 831,800.00

268,000.00 321,600.00
1,300.00 176,800.00
190,000.00 103,360.00
75,000.00 112,500.00
95,000.00 71,250.00
100,000.00 7,500.00
110,000.00 8,250.00
per Satuan Pekerjaan 801,260.00

268,000.00 321,600.00
1,300.00 152,100.00
190,000.00 106,590.00
75,000.00 112,500.00
95,000.00 71,250.00
100,000.00 7,500.00
110,000.00 8,250.00
per Satuan Pekerjaan 779,790.00

268,000.00 321,600.00
1,300.00 118,300.00
190,000.00 110,960.00
75,000.00 112,500.00
95,000.00 71,250.00
100,000.00 7,500.00
110,000.00 8,250.00
per Satuan Pekerjaan 750,360.00

215,000.00 258,000.00
180,550.00 77,997.60
75,000.00 58,500.00
95,000.00 37,050.00
100,000.00 3,900.00
110,000.00 4,290.00
per Satuan Pekerjaan 439,737.60
268,000.00 128,640.00
1,300.00 252,200.00
-
-
-
-
-
-
-
-
per Satuan Pekerjaan 380,840.00

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -
an spesi 1 PC : 2 PP
-
-
-
-
-
-
-
per Satuan Pekerjaan -
an spesi 1 PC : 3 PP
-
-
-
-
-
-
-
per Satuan Pekerjaan -
an spesi 1 PC : 4 PP
-
-
-
-
-
-
-
per Satuan Pekerjaan -
an spesi 1 PC : 5 PP
-
-
-
-
-
-
-
per Satuan Pekerjaan -
an spesi 1 PC : 6 PP
-
-
-
-
-
-
-
per Satuan Pekerjaan -
an spesi 1 PC : 3 KP : 10 PP
-
-
-
-
-
-
-
-
per Satuan Pekerjaan -
uran spesi 1 PC : 2 PP
-
-
-
-
-
-
-
per Satuan Pekerjaan -
uran spesi 1 PC : 3 PP
-
-
-
-
-
-
-
per Satuan Pekerjaan -
uran spesi 1 PC : 4 PP
400.00 28,000.00
1,300.00 14,950.00
190,000.00 8,170.00
75,000.00 22,500.00
95,000.00 9,500.00
100,000.00 1,000.00
110,000.00 1,650.00
per Satuan Pekerjaan 85,770.00
uran spesi 1 PC : 5 PP
400.00 28,000.00
1,300.00 12,584.00
190,000.00 8,550.00
75,000.00 22,500.00
95,000.00 9,500.00
100,000.00 1,000.00
110,000.00 1,650.00
per Satuan Pekerjaan 83,784.00
uran spesi 1 PC : 6 PP
400.00 28,000.00
1,300.00 10,816.00
190,000.00 9,310.00
75,000.00 22,500.00
95,000.00 9,500.00
100,000.00 1,000.00
110,000.00 1,650.00
per Satuan Pekerjaan 82,776.00
uran spesi 1 PC : 8 PP
-
-
-
-
-
-
-
per Satuan Pekerjaan -
uran spesi 1 PC : 3 KP : 10 PP
-
-
-
-
-
-
-
-
per Satuan Pekerjaan -
uran spesi 1 KP : 1 SM : 1 PP
-
-
-
-
-
-
-
-
per Satuan Pekerjaan -
uran spesi 1 KP : 1 SM : 2 PP
-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

4,000.00 50,000.00
1,300.00 39,416.00
190,000.00 138,320.00
15,000.00 4,200.00
75,000.00 26,250.00
95,000.00 14,250.00
100,000.00 1,500.00
110,000.00 1,980.00
per Satuan Pekerjaan 275,916.00

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -
-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -
esi 1 PC : 3 PP
-
-
-
-
-
-
-
per Satuan Pekerjaan -
esi 1 PC : 4 PP
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

1,300.00 10,816.00
190,000.00 6,080.00
75,000.00 30,000.00
95,000.00 19,000.00
100,000.00 2,000.00
110,000.00 2,420.00
per Satuan Pekerjaan 70,316.00

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -
s II (Lebar sampai 90 cm)
-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -

4,370,000.00 4,807,000.00
14,000.00 210,000.00
18,000.00 100,800.00
75,000.00 300,000.00
95,000.00 1,140,000.00
100,000.00 120,000.00
110,000.00 22,000.00
per Satuan Pekerjaan 6,699,800.00

-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -

4,370,000.00 4,807,000.00
14,000.00 210,000.00
18,000.00 54,000.00
75,000.00 180,000.00
95,000.00 684,000.00
100,000.00 72,000.00
110,000.00 13,200.00
per Satuan Pekerjaan 6,020,200.00

4,140,000.00 57,960.00
4,140,000.00 14,904.00
18,000.00 4,500.00
75,000.00 7,500.00
95,000.00 9,500.00
100,000.00 1,000.00
110,000.00 550.00
per Satuan Pekerjaan 95,914.00

-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

10,350,000.00 111,780.00
18,000.00 1,800.00
75,000.00 7,500.00
95,000.00 19,000.00
100,000.00 2,000.00
110,000.00 550.00
per Satuan Pekerjaan 142,630.00

4,370,000.00 47,196.00
18,000.00 1,800.00
75,000.00 7,500.00
95,000.00 19,000.00
100,000.00 2,000.00
110,000.00 550.00
per Satuan Pekerjaan 78,046.00
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -
lok 6 x 12 Cm)
-
-
-
-
-
-
-
-
per Satuan Pekerjaan -
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

1,300.00 321,100.00
264,500.00 229,850.50
326,212.00 325,885.79
50.00 10,750.00
75,000.00 123,750.00
95,000.00 26,125.00
100,000.00 2,800.00
110,000.00 9,130.00
per Satuan Pekerjaan 1,049,391.29

1,300.00 358,800.00
264,500.00 219,006.00
326,212.00 330,126.54
50.00 10,750.00
75,000.00 123,750.00
95,000.00 26,125.00
100,000.00 2,800.00
110,000.00 9,130.00
per Satuan Pekerjaan 1,080,487.54

1,300.00 388,700.00
264,500.00 211,335.50
326,212.00 331,757.60
50.00 10,750.00
75,000.00 123,750.00
95,000.00 26,125.00
100,000.00 2,800.00
110,000.00 9,130.00
per Satuan Pekerjaan 1,104,348.10

1,300.00 299,000.00
264,500.00 236,198.50
326,212.00 335,019.72
50.00 10,000.00
75,000.00 90,000.00
95,000.00 19,000.00
100,000.00 2,000.00
110,000.00 6,600.00
per Satuan Pekerjaan 997,818.22

1,300.00 423,800.00
264,500.00 201,020.00
326,212.00 335,672.15
50.00 10,750.00
75,000.00 123,750.00
95,000.00 26,125.00
100,000.00 2,800.00
110,000.00 913.00
per Satuan Pekerjaan 1,124,830.15

1,300.00 457,600.00
264,500.00 193,349.50
326,212.00 336,324.57
50.00 10,750.00
75,000.00 123,750.00
95,000.00 26,125.00
100,000.00 2,800.00
110,000.00 9,130.00
per Satuan Pekerjaan 1,159,829.07

1,300.00 482,300.00
264,500.00 184,621.00
326,212.00 341,543.96
50.00 10,750.00
75,000.00 123,750.00
95,000.00 26,125.00
100,000.00 2,800.00
110,000.00 9,130.00
per Satuan Pekerjaan 1,181,019.96

1,300.00 499,200.00
264,500.00 183,034.00
326,212.00 338,934.27
50.00 10,750.00
75,000.00 123,750.00
95,000.00 26,125.00
100,000.00 2,800.00
110,000.00 9,130.00
per Satuan Pekerjaan 1,193,723.27

1,300.00 527,800.00
264,500.00 180,918.00
326,212.00 334,693.51
50.00 10,750.00
75,000.00 123,750.00
95,000.00 26,125.00
100,000.00 2,800.00
110,000.00 9,130.00
per Satuan Pekerjaan 1,215,966.51

1,300.00 536,900.00
264,500.00 180,124.50
326,212.00 333,062.45
50.00 10,750.00
75,000.00 123,750.00
95,000.00 26,125.00
100,000.00 2,800.00
110,000.00 9,130.00
per Satuan Pekerjaan 1,222,641.95

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
-
per Satuan Pekerjaan -
16,000.00 168,000.00
18,500.00 2,775.00
75,000.00 5,250.00
95,000.00 6,650.00
100,000.00 700.00
110,000.00 440.00
per Satuan Pekerjaan 183,815.00
per Satuan Pekerjaan 18,381.50

-
-
-
-
-
-
per Satuan Pekerjaan -
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

4,255,000.00 170,200.00
18,000.00 5,400.00
34,500.00 3,450.00
75,000.00 39,000.00
95,000.00 24,700.00
100,000.00 2,600.00
110,000.00 2,860.00
per Satuan Pekerjaan 248,210.00

4,255,000.00 191,475.00
18,000.00 5,400.00
34,500.00 3,450.00
75,000.00 39,000.00
95,000.00 24,700.00
100,000.00 2,600.00
110,000.00 2,860.00
per Satuan Pekerjaan 269,485.00

4,255,000.00 170,200.00
18,000.00 7,200.00
34,500.00 6,900.00
4,140,000.00 62,100.00
161,000.00 56,350.00
37,950.00 75,900.00
75,000.00 49,500.00
95,000.00 31,350.00
100,000.00 3,300.00
110,000.00 3,630.00
per Satuan Pekerjaan 466,430.00

4,255,000.00 170,200.00
18,000.00 7,200.00
34,500.00 6,900.00
4,140,000.00 74,520.00
161,000.00 56,350.00
37,950.00 75,900.00
75,000.00 49,500.00
95,000.00 31,350.00
100,000.00 3,300.00
110,000.00 3,630.00
per Satuan Pekerjaan 478,850.00

-
-
-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -

4,255,000.00 851,000.00
18,000.00 27,000.00
34,500.00 13,800.00
16,000.00 2,520,000.00
18,500.00 41,625.00
1,300.00 436,800.00
264,500.00 142,830.00
326,212.00 264,231.72
75,000.00 397,500.00
95,000.00 26,125.00
95,000.00 123,500.00
95,000.00 99,750.00
100,000.00 26,200.00
110,000.00 29,150.00
per Satuan Pekerjaan 4,999,511.72

4,255,000.00 1,148,850.00
18,000.00 36,000.00
34,500.00 20,700.00
16,000.00 3,360,000.00
18,500.00 55,500.00
1,300.00 436,800.00
264,500.00 142,830.00
326,212.00 264,231.72
75,000.00 423,750.00
95,000.00 26,125.00
95,000.00 148,200.00
95,000.00 133,000.00
100,000.00 32,300.00
110,000.00 31,130.00
per Satuan Pekerjaan 6,259,416.72

4,255,000.00 1,702,000.00
18,000.00 72,000.00
34,500.00 69,000.00
16,000.00 5,040,000.00
18,500.00 83,250.00
1,300.00 436,800.00
264,500.00 142,830.00
326,212.00 264,231.72
4,255,000.00 638,250.00
161,000.00 563,500.00
37,950.00 759,000.00
75,000.00 528,750.00
95,000.00 26,125.00
95,000.00 156,750.00
95,000.00 199,500.00
100,000.00 40,300.00
110,000.00 38,830.00
per Satuan Pekerjaan 10,761,116.72

4,255,000.00 1,361,600.00
18,000.00 57,600.00
34,500.00 55,200.00
16,000.00 3,360,000.00
18,500.00 55,500.00
1,300.00 436,800.00
264,500.00 142,830.00
326,212.00 264,231.72
4,255,000.00 595,700.00
161,000.00 450,800.00
37,950.00 607,200.00
75,000.00 476,250.00
95,000.00 26,125.00
95,000.00 156,750.00
95,000.00 133,000.00
100,000.00 33,000.00
110,000.00 34,980.00
per Satuan Pekerjaan 8,247,566.72

4,255,000.00 1,361,600.00
18,000.00 57,600.00
34,500.00 55,200.00
16,000.00 2,520,000.00
18,500.00 41,625.00
1,300.00 436,800.00
264,500.00 142,830.00
326,212.00 264,231.72
4,255,000.00 510,600.00
161,000.00 450,800.00
37,950.00 1,214,400.00
75,000.00 397,500.00
95,000.00 26,125.00
95,000.00 123,500.00
95,000.00 99,750.00
100,000.00 26,500.00
110,000.00 29,150.00
per Satuan Pekerjaan 7,758,211.72

4,255,000.00 1,021,200.00
18,000.00 57,600.00
34,500.00 55,200.00
16,000.00 2,520,000.00
18,500.00 41,625.00
1,300.00 436,800.00
264,500.00 142,830.00
326,212.00 264,231.72
4,255,000.00 680,800.00
161,000.00 450,800.00
37,950.00 910,800.00
75,000.00 397,500.00
95,000.00 26,125.00
95,000.00 123,500.00
95,000.00 99,750.00
100,000.00 26,200.00
110,000.00 29,150.00
per Satuan Pekerjaan 7,284,111.72

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

4,255,000.00 8,510.00
18,000.00 180.00
16,000.00 48,000.00
18,500.00 832.50
1,300.00 5,200.00
264,500.00 1,587.00
326,212.00 2,935.91
75,000.00 13,500.00
95,000.00 1,900.00
95,000.00 1,900.00
95,000.00 1,900.00
100,000.00 600.00
110,000.00 990.00
per Satuan Pekerjaan 88,035.41

4,255,000.00 12,765.00
18,000.00 360.00
16,000.00 57,600.00
18,500.00 925.00
1,300.00 7,150.00
264,500.00 2,380.50
326,212.00 4,893.18
75,000.00 22,275.00
95,000.00 3,135.00
95,000.00 3,135.00
95,000.00 3,135.00
100,000.00 1,000.00
110,000.00 1,650.00
per Satuan Pekerjaan 120,403.68

-
-
-
-
-
-
-
per Satuan Pekerjaan -

2,400.00 60,000.00
75,000.00 11,250.00
95,000.00 7,125.00
100,000.00 800.00
110,000.00 880.00
per Satuan Pekerjaan 80,055.00

-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

6,500.00 71,500.00
18,000.00 540.00
75,000.00 15,000.00
95,000.00 9,500.00
100,000.00 1,000.00
110,000.00 1,100.00
per Satuan Pekerjaan 98,640.00

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -
-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
75,000.00 4,050.00
95,000.00 8,550.00
100,000.00 900.00
110,000.00 2,970.00
per Satuan Pekerjaan 16,470.00

-
-
75,000.00 4,050.00
95,000.00 8,550.00
100,000.00 900.00
110,000.00 2,970.00
per Satuan Pekerjaan 16,470.00

-
-
75,000.00 4,050.00
95,000.00 8,550.00
100,000.00 900.00
110,000.00 2,970.00
per Satuan Pekerjaan 16,470.00

-
-
75,000.00 8,100.00
95,000.00 17,100.00
100,000.00 1,800.00
110,000.00 594.00
per Satuan Pekerjaan 27,594.00

-
-
75,000.00 8,100.00
95,000.00 17,100.00
100,000.00 1,800.00
110,000.00 594.00
per Satuan Pekerjaan 27,594.00

-
-
75,000.00 10,125.00
95,000.00 21,375.00
100,000.00 2,250.00
110,000.00 748.00
per Satuan Pekerjaan 34,498.00

-
-
75,000.00 2,700.00
95,000.00 5,700.00
100,000.00 600.00
110,000.00 198.00
per Satuan Pekerjaan 9,198.00

-
-
75,000.00 2,700.00
95,000.00 5,700.00
100,000.00 600.00
110,000.00 198.00
per Satuan Pekerjaan 9,198.00

-
-
75,000.00 2,700.00
95,000.00 5,700.00
100,000.00 600.00
110,000.00 198.00
per Satuan Pekerjaan 9,198.00

151,525.00 181,830.00
53,033.75 18,561.81
75,000.00 2,700.00
95,000.00 5,700.00
100,000.00 600.00
110,000.00 198.00
per Satuan Pekerjaan 209,589.81

-
-
75,000.00 6,075.00
95,000.00 12,825.00
100,000.00 1,350.00
110,000.00 451.00
per Satuan Pekerjaan 20,701.00

-
-
75,000.00 4,050.00
95,000.00 8,550.00
100,000.00 900.00
110,000.00 297.00
per Satuan Pekerjaan 13,797.00

- -
- -
75,000.00 2,700.00
95,000.00 5,700.00
100,000.00 600.00
110,000.00 198.00
per Satuan Pekerjaan 9,198.00

-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -
per Satuan Pekerjaan -
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -
per Satuan Pekerjaan -

-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -
-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

2,300.00 93,150.00
180,550.00 18,055.00
95,000.00 9,500.00
100,000.00 1,000.00
75,000.00 30,000.00
110,000.00 4,400.00
per Satuan Pekerjaan 156,105.00

-
-
-
-
-
-
per Satuan Pekerjaan -
-

-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
per Satuan Pekerjaan -

-
-
-
per Satuan Pekerjaan -
-
-
-
per Satuan Pekerjaan -

-
-
-
per Satuan Pekerjaan -
ng ) dgn Tingkat Kebersihan Sa 2½.
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -
Lapis Cat Konvensional, tebal 200 um
-
-
-
-
-
-
-
-
-
-
per Satuan Pekerjaan -
Lapis Cat Mutakhir, tebal 200 um
-
-
-
-
-
per Satuan Pekerjaan -
Lapis Cat Konvensional, tebal 200 um
-
-
-
-
-
-
-
per Satuan Pekerjaan -
Spray ) dgn Sistem 1 Lapis Cat Mutakhir, tebal 200 um
-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
per Satuan Pekerjaan -
per Satuan Pekerjaan -

-
-
-
-
-
per Satuan Pekerjaan -
per Satuan Pekerjaan -

-
-
-
-
-
-
-
per Satuan Pekerjaan -
per Satuan Pekerjaan -

-
-
-
-
-
-
-
-
per Satuan Pekerjaan -
per Satuan Pekerjaan -

-
-
-
per Satuan Pekerjaan -

-
-
-
per Satuan Pekerjaan -

-
-
-
per Satuan Pekerjaan -

-
-
-
per Satuan Pekerjaan -

-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
per Satuan Pekerjaan -

-
-
-
-
-
per Satuan Pekerjaan -

300,000.00 330,000.00
190,000.00 19,000.00
75,000.00 30,000.00
95,000.00 9,500.00
100,000.00 1,000.00
110,000.00 4,400.00
per Satuan Pekerjaan 393,900.00

288,840.00 284,796.24
382,800.00 200,970.00
264,500.00 19,573.00
326,212.00 47,626.95
1,300.00 58,500.00
75,000.00 28,125.00
95,000.00 11,875.00
100,000.00 1,200.00
110,000.00 2,090.00
per Satuan Pekerjaan 654,756.19

18,000.00 45,000.00
268,000.00 348,400.00
75,000.00 195,000.00
95,000.00 237,500.00
100,000.00 200,000.00
110,000.00 8,250.00
per Satuan Pekerjaan 1,034,150.00

18,000.00 45,000.00
268,000.00 348,400.00
75,000.00 195,000.00
95,000.00 237,500.00
100,000.00 200,000.00
110,000.00 8,250.00
per Satuan Pekerjaan 1,034,150.00
RENCANA ANGGARAN BIAYA INFRASTRUKTUR

PROYEK : RUMAH SAKIT MECCA NUSANTARA


LOKASI : WAY TENONG - LAMPUNG BARAT

No URAIAN PEKERJAAN Analisa Volume

1 2 3 4

I. PEKERJAAN DINDING PENAHAN TANAH


1 Pasangan Batu Kali Analisa C.2 33903.6
2 Bronjong Add. SNI O10 2226.0

3 Kolom Pengikat 20 x 35
Pembesian Analisa G.14 24157.8
Bekisting Analisa G.17 936.3
Pengecoran Kolom Beton K - 250 Analisa G.10 187.3

4 Balok Pengikat 20 x 35
Pembesian Analisa G.14 34305.6
Bekisting Analisa G.17 1128.5
Pengecoran Balok Beton K - 250 Analisa G.10 225.7

5 Sloof Pengikat 20 x 35
Pembesian Analisa G.14 8137.1
Bekisting Analisa G.17 330.8
Pengecoran Sloof Beton K - 250 Analisa G.10 66.2

5 Pipa PVC 3" + Aksesoris Analisa J.27 469.4

SUB TOTAL BIAYA

II. PEKERJAAN PERKERASAN JALAN BETON (RIGID PAVEMENT)


1 Pek. Pondasi Bawah (Base) Analisa EI-421 826.3
2 Pek. Pelat Beton
Pembesian Analisa G.14 26303.9
Bekisting Analisa G.17 288.3
Pengecoran Pelat Beton K - 300 Analisa G.10 727.1

SUB TOTAL BIAYA


II. PEKERJAAN PERKERASAN JALAN ASPAL (FLEXIBEL PAVEMENT)
1 Pek. Pondasi Bawah (Sub Base) Analisa EI-422a 1471.7
2 Pek. Pondasi Bawah (Base) Analisa EI-421 735.8
3 Agregat Penutup (Burtu) Analisa EI-621 73.6
4 Lapisan Resap Pengikat Analisa EI-611a 3679.2
5 Lapisan Perekat Analisa EI-612a 1839.6
6 Laston Lapis Aus (AC -WC) Analisa EI-635a 184.0
SUB TOTAL BIAYA

III. Pekerjaan Pasangan Paving


1 Pekerjaan Pasir Urug Paving Analisa B.11 1178.7
2 Pekerjaan Paving Analisa M.53 23574.2
3 Pekerjaan Pasangan Dinding Panel Add. SNI O9 433.4

SUB TOTAL BIAYA

IV. Pekerjaan Pasangan Paving


1 Pekerjaan Lantai Kerja Kastin Adk 1 : 4 11.6
2 Pekerjaan Pasangan Kanstin 2585.7

SUB TOTAL BIAYA


Harga
Jumlah
Satuan Satuan
Rp
Rp

5 8 9

m3 831,800 28,201,041,306
m3 1,034,150 2,302,059,266

kg 18,382 444,057,034
m2 466,430 436,741,614
m3 1,193,723 223,548,497

kg 18,382 630,588,283
m2 478,850 540,369,535
m3 1,193,723 269,417,015

kg 18,382 149,571,234
m2 269,485 89,138,766
m3 1,193,723 78,970,644

m' 209,590 98,386,697

33,463,889,891

m3 854,153 705,745,958

kg 18,382 483,505,405
m2 248,210 71,549,015
m3 1,222,642 889,007,415

2,149,807,793
m3 696,711 1,025,336,133
m3 854,153 628,519,860
m3 23,673 1,741,945
ltr 15,250 56,106,044
ltr 15,033 27,655,571
Ton 1,804,269 331,913,405
2,071,272,958

m3 240,260 283,197,321
m2 156,105 3,680,056,423
m' 654,756 283,745,143

4,246,998,887

m3 - -
m' - -

-
Analisa Harga Satuan Pekerjaan Sipil

Harga Satuan
Kode Analisaa Kebutuhan Sat Indeks Bahan/Upah Jumlah
(Rp)

Analisa C.2 Memasang 1 m 3 pondasi batu belah, campuran 1 PC : 4 PP


Bahan Batu belah 15 cm/20 cm M3 1.2000 268,000.00 321,600.00
Semen Portland Kg 163.0000 1,300.00 211,900.00
Pasir Pasang M3 0.5200 190,000.00 98,800.00
Tenaga Kerja Pekerja OH 1.5000 75,000.00 112,500.00
Tukang Batu OH 0.7500 95,000.00 71,250.00
Kepala Tukang OH 0.0750 100,000.00 7,500.00
Mandor OH 0.0750 110,000.00 8,250.00
Jumlah Harga per Satuan Pekerjaan 831,800.00

Add. SNI 1 M3 Pasangan bronjong kawat Q 3mm diisi batu belah:


Bahan kawat galvanis Q 3mm Kg 2.5000 18,000.00 45,000.00
batu belah M3 1.3000 268,000.00 348,400.00
Tenaga Kerja Pekerja Anyam OH 2.6000 75,000.00 195,000.00
Pekerja Pengisi Batu OH 2.5000 95,000.00 237,500.00
Tukang Anyam OH 2.0000 100,000.00 200,000.00
Mandor OH 0.0750 110,000.00 8,250.00
Jumlah Harga per Satuan Pekerjaan 1,034,150.00

Analisa G.14 Pembesian 10 kg dengan besi polos atau besi ulir


Bahan Besi Beton Kg 10.5000 16,000.00 168,000.00
Kawat Beton Kg 0.1500 18,500.00 2,775.00
Tenaga Kerja Pekerja OH 0.0700 75,000.00 5,250.00
Tukang Besi OH 0.0700 95,000.00 6,650.00
Kepala Tukang OH 0.0070 100,000.00 700.00
Mandor OH 0.0040 110,000.00 440.00
Jumlah Harga per Satuan Pekerjaan 183,815.00
Jumlah Harga per Satuan Pekerjaan 18,381.50

Analisa G.17 Memasang 1 m 2 bekisting untuk pondasi


Bahan Kayu kelas III (papan) M3 0.0400 4,255,000.00 170,200.00
Paku 5 cm - 10 cm Kg 0.3000 18,000.00 5,400.00
Minyak Bekisting Liter 0.1000 34,500.00 3,450.00
Tenaga Kerja Pekerja OH 0.5200 75,000.00 39,000.00
Tukang Kayu OH 0.2600 95,000.00 24,700.00
Kepala Tukang OH 0.0260 100,000.00 2,600.00
Mandor OH 0.0260 110,000.00 2,860.00
Jumlah Harga per Satuan Pekerjaan 248,210.00
Analisa G.10 Membuat 1 m 3 beton mutu f’c = 26,4 MPa (K 300), slump (12 ± 2) cm, w/c = 0,52
Bahan Semen Portland Kg 413.0000 1,300.00 536,900.00
Pasir Beton M3 0.6810 264,500.00 180,124.50
Koral beton M3 1.0210 326,212.00 333,062.45
Air Liter 215.0000 50.00 10,750.00
Tenaga Kerja Pekerja OH 1.6500 75,000.00 123,750.00
Tukang Batu OH 0.2750 95,000.00 26,125.00
Kepala Tukang OH 0.0280 100,000.00 2,800.00
Mandor OH 0.0830 110,000.00 9,130.00
Jumlah Harga per Satuan Pekerjaan 1,222,641.95

Analisa J.27 Memasang 1 m' Pipa PVC tipe AW Ø 3"


Bahan Pipa PVC tipe AW Ø 3" M' 1.2000 151,525.00 181,830.00
Perlengkapan 35% dari bahan Set 0.3500 53,033.75 18,561.81
Tenaga Kerja Pekerja OH 0.0360 75,000.00 2,700.00
Tukang Pipa OH 0.0600 95,000.00 5,700.00
Kepala Tukang OH 0.0060 100,000.00 600.00
Mandor OH 0.0018 110,000.00 198.00
Jumlah Harga per Satuan Pekerjaan 209,589.81
Analisa Harga Satuan Jalan

Analisa EI-421 Pek. Pondasi Bawah (Base)

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.0595 10,714.29 637.14


2. Mandor (L03) Jam 0.0085 15,714.29 133.50

JUMLAH HARGA TENAGA 770.64

B. BAHAN

1. Agregat A (M26) M3 1.2586 349,029.42 439,291.66

JUMLAH HARGA BAHAN 439,291.66

C. PERALATAN

1 Wheel Loader E15 Jam 0.0085 728,611.25 6,189.71


2 Dump Truck E08 Jam 0.7884 405,264.64 319,528.09
3 Motor Grader E13 Jam 0.0035 874,403.36 3,072.70
4 Tandem Roller E17 Jam 0.0044 549,730.01 2,443.24
5 Water Tanker E23 Jam 0.0141 370,410.52 5,206.57
6 Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 336,440.32

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 776,502.62


E. OVERHEAD & PROFIT 10.0 % x D 77,650.26
F. HARGA SATUAN PEKERJAAN ( D + E ) 854,152.89
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

Analisa EI-422a Pek. Pondasi Bawah (Sub Base)

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.0595 10,714.29 637.14


2. Mandor (L03) Jam 0.0085 15,714.29 133.50

JUMLAH HARGA TENAGA 770.64

B. BAHAN

1. Agregat B (M27) M3 1.2586 212,218.62 267,100.32

JUMLAH HARGA BAHAN 267,100.32

C. PERALATAN

1 Wheel Loader E15 Jam 0.0085 728,611.25 6,189.71


2 Dump Truck E08 Jam 0.7884 405,264.64 319,528.09
3 Motor Grader E13 Jam 0.0047 874,403.36 4,096.94
4 Tandem Roller E17 Jam 0.0054 549,730.01 2,943.67
5 Water Tanker E23 Jam 0.0141 370,410.52 5,206.57
6 Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 337,964.98


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 605,835.94
E. OVERHEAD & PROFIT 15.0 % x D 90,875.39
F. HARGA SATUAN PEKERJAAN ( D + E ) 696,711.33
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

Analisa EI-621 Agregat Penutup (Burtu)

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.2126 10,714.29 2,278.02


2. Mandor (L02) Jam 0.0106 15,714.29 167.05

JUMLAH HARGA TENAGA 2,445.08

B. BAHAN

1. Chipping (M41) Kg 23.0000 0.00 0.00

JUMLAH HARGA BAHAN 0.00

C. PERALATAN

1. Wheel Loader E15 Jam 0.0106 728,611.25 7,745.69


2. Dump Truck E08 Jam 0.0248 405,264.64 10,063.17
3. P. Tyre Roller E18 Jam 0.0005 596,448.26 321.17
4. Alat Bantu Ls 1.0000 10.00 10.00

JUMLAH HARGA PERALATAN 18,140.03

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 20,585.11


E. OVERHEAD & PROFIT 15.0 % x D 3,087.77
F. HARGA SATUAN PEKERJAAN ( D + E ) 23,672.87
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

Analisa EI-611a Lapisan Resap Pengikat

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.0021 10,714.29 22.32


2. Mandor (L03) Jam 0.0004 15,714.29 6.55

JUMLAH HARGA TENAGA 28.87

B. BAHAN

1. Aspal (M10) Kg 0.6790 12,000.00 8,147.71


2. Kerosene (M11) liter 0.3708 13,500.00 5,005.80

JUMLAH HARGA BAHAN 13,153.51


C. PERALATAN

1. Asp. Distributor E41 Jam 0.0002 157,420.11 32.80


2. Compressor E05 Jam 0.0002 217,332.15 45.28

JUMLAH HARGA PERALATAN 78.07

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 13,260.45


E. OVERHEAD & PROFIT 15.0 % x D 1,989.07
F. HARGA SATUAN PEKERJAAN ( D + E ) 15,249.52
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

Analisa EI-612a Lapisan Perekat

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.0021 10,714.29 22.32


2. Mandor (L03) Jam 0.0004 15,714.29 6.55

JUMLAH HARGA TENAGA 28.87

B. BAHAN

1. Aspal (M10) Kg 0.8487 12,000.00 10,184.64


2. Kerosene (M11) liter 0.2060 13,500.00 2,781.00
JUMLAH HARGA BAHAN 12,965.64

C. PERALATAN

1. Asp. Distributor E41 Jam 0.0002 157,420.11 32.80


2. Compressor E05 Jam 0.0002 217,332.15 45.28

JUMLAH HARGA PERALATAN 78.07

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 13,072.58


E. OVERHEAD & PROFIT 15.0 % x D 1,960.89
F. HARGA SATUAN PEKERJAAN ( D + E ) 15,033.47
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

Analisa EI-635a Laston Lapis Aus (AC -WC)

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.2008 10,714.29 2,151.46


2. Mandor (L03) Jam 0.0201 15,714.29 315.55

JUMLAH HARGA TENAGA 2,467.01

B. BAHAN
1. Lolos screen2 ukuran ( 9.5 - 19, M3 0.2978 375,900.00 111,959.96
2. Lolos screen2 ukuran ( 0 - 5) M3 0.3523 320,700.00 112,988.53
3 Semen (M05) Kg 9.8700 12,000.00 118,440.00
4 Aspal (M10) Kg 62.8300 12,000.00 753,960.00

JUMLAH HARGA BAHAN 1,097,348.50

C. PERALATAN
1. Wheel Loader E15 Jam 0.0096 728,611.25 6,973.82
2. AMP E01 Jam 0.0201 10,528,961.22 211,424.92
3. Genset E12 Jam 0.0201 572,124.14 11,488.44
4. Dump Truck E08 Jam 0.5268 405,264.64 213,487.62
5. Asp. Finisher E02 Jam 0.0110 1,548,862.26 17,023.35
6. Tandem Roller E17 Jam 0.0108 549,730.01 5,947.61
7 P. Tyre Roller E18 Jam 0.0046 596,448.26 2,768.69
8 Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 469,114.44

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1,568,929.94


E. OVERHEAD & PROFIT 15.0 % x D 235,339.49
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,804,269.43
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

You might also like