Chapter 2 - PV Computations
Chapter 2 - PV Computations
Chapter 2 - PV Computations
Asset Pricing
Chapter 2
Present Value Computations
Reference:
Chapter 2, Section 1– Richard A. Brealey, Stewart C. Myers, and Franklin Allen.
2017 Principles of Corporate Finance, 13th Edition, McGraw-Hill
1
Learning Objectives
2
Time-value of Money Concept -
Valuation of Future Cash Flows
and computation of Present
Values
3
Evaluating Cashflows
Receiving $100,000
0 1 today
Cashflow A
$100,000 Or
Receiving $100,000
0 1 one year from today
Cashflow B
$100,000 $100,000 (1+ r%) A > B at
A Time 1
0 1
Deposit $100,000 in the bank and earn interest of r%
4
Outline
• FV = PV(1+r)
6
Future Value & Compounding
8
Simple Interest
I = PRT, where
I = interest earned
P = principle
R = rate of interest
T = time
11
Compound versus Simple
interest
12
Present Value & Discounting
Answer: = 0.91514165
16 16
Determining the Discount Rate
Solution:
PV(1+r)t = FV
(1.12) t = 50,000/25,000 = 2
t = ln2/ln1.12 = 6.12 years
18
Practice Q1
Solution:
19
Practice Q2
20
Practice Q3
21
Future Value with Multiple Cash
Flows
• To calculate future value of multiple cash
flows:
Calculate the FV of each cash flow and add
them at the ending period
• Example:
Suppose you deposit $100 today in an
account paying 8% p.a. In one year time,
you deposit another $100. How much will
you have in two years?
22
Present Value with Multiple Cash
Flows
• To calculate present value of multiple cash
flows:
Calculate the PV of each cash flow and add
them up
23
Cash Flow Timing
24
Opportunity Cost of Capital
25
Opportunity Cost of Capital
27
Making capital investment
decisions
28
Outline
29
Good Decision Criteria
31
Computing AAR For The Project
33
Payback Period
• Approach:
Compute the present value of each cash flow
Determine how long it takes to payback on a
discounted basis
Compare to a specified required period
37
Computing Discounted Payback
for the Project
Example: Discounted Payback Period
Assume required rate of return is 12%.
Year 0: CF = -165,000
Year 1: CF = 63,120/1.12 = 56,357
Year 2: CF = 70,800/1.122 = 56,441
Year 3: CF = 91,080/1.123 = 64,829
38
Advantages and Disadvantages
of Discounted Payback
Advantages Disadvantages
Includes time value Requires an arbitrary
of money cutoff point
Easy to understand Ignores cash flows
Adjusts for beyond the cutoff point
uncertainty of later Biased against long-term
cash flows; focus on projects, such as R&D
near term cash flows and new products
rather than later cash
flows
Biased towards
liquidity
39
Net Present Value
• Approach:
The first step is to estimate the expected
future cash flows.
The second step is to estimate the required
return for projects of this risk level.
The third step is to find the present value of
the cash flows and subtract the initial
investment.
40
NPV – Decision Rule
41
NPV – Decision Rule
42
NPV – Decision Rule
43
Relationship between
Risk and PV of Cashflows
• There is a positive relationship between risk &
return.
• A higher required rate of return is required to
compensate an investor for a riskier
investment.
• Higher required rates of return will lower
the PV of projected cash flows.
• Thus, the uncertainty of future projected
cashflow is adjusted for when a higher
discount rate is used.
44
Advantages of NPV
Advantages Disadvantages
Includes time value of Requires an estimate for
money required return/discount
Easy to understand rate
Directly measures the Does not differentiate
value created between projects of
different size; uses NPV
Factors the risk
measure as an absolute
inherent in the project
measure.
through the discount
rate
Adjusts for uncertainty
of later cash flows
(smaller PV) 45
NPV
NPV 86,739.66
PV (5th year) 583,623.76
46
NPV
NPV -1.255
48
Internal Rate of Return (IRR)
49
IRR – Definition and Decision Rule
51
Computing IRR for the Project
53
Computing IRR using
Algebraic Approach
Solving for IRR using algebraic approach
To solve for the IRR, basically we are looking for
the discount rate such that the present value of
future cash flows exactly equals the initial
investment. In other words:
54
Computing IRR using
Algebraic Approach
Example: IRR using Algebraic Approach
Consider the following cash flows:
Year 0: CF = -97.55;
Year 1: CF = 5;
Year 2: CF = 5;
Year 3: CF = 105;
55
Computing IRR using
Algebraic Approach
Example: IRR using Algebraic Approach
Solution using algebraic approach
Try y = 7%,
NPV = (1.07) (1.07) (1.07) - 97.55
=4.6729+4.3672+85.7113- 97.55
=-2.7986
Try y = 5%,
NPV = (1.05) (1.05) (1.05) - 97.55
=4.7619+4.535147+90.7029 – 97.55
=2.4499
56
Computing IRR using
Algebraic Approach
Example: IRR using Algebraic Approach
Solution using algebraic approach
2.4499
5% 7%
-2.7986
2.4499 (2%)
IRR = 5% +
(2.4499 + 2.7986 )
= 5.93%
57
Advantages of IRR
58
Problems with IRR
• Exceptions
Non-conventional cash flows – cash flow
signs change more than once or cash inflow
comes first before cash outflows
• When you solve for IRR you are solving for the
root of an equation and when you cross the x-
axis more than once, there will be more than
one return that solves the equation.
• If you have more than one IRR, which one do
you use to make your decision?
60
IRR and Non-conventional
Cash Flows
• Suppose an investment will cost $90,000
initially and will generate the following cash
flows:
Year 1: 132,000
Year 2: 100,000
Year 3: -150,000
• The required return is 15%.
• What is the NPV and IRR?
• Should we accept or reject the project?
61
IRR and Non-conventional
Cash Flows
Year 0 1 2 3
Cash flows -90,000 132,000 100,000 (150,000)
IRR 10.11%
• NPV=1,769.54
• If you compute the IRR on MS Excel, you get
10.11% because it is the first one that you come
to.
2 325 240
65
Example With Mutually
Exclusive Projects
Project A: NPV = $64.05, IRR = 19.43%
66
NPV Profiles
60.0000
Project B
If the required 40.0000
return is
20.0000
greater than
the crossover 0.0000
0% 2% 4% 6% 8% 10% 12% 14% 16% 18% 20% 22% 24%
point of 13.33, -20.0000
then you
should Crossover rate
-40.0000
choose B. https://www.youtube.com/watch?v=t_Bv5R_wSvY
67
Conflicts Between NPV and IRR
69
Practice Question